Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences...
Transcript of Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences...
![Page 1: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/1.jpg)
Cardiff Strategic Flood Consequences Assessment
Phase 2 Part 1 Update Extend Development
Lifetime to 2110
Areas A, G, H and I
Final Report
Revised November 2011
![Page 2: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/2.jpg)
![Page 3: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/3.jpg)
/5097656-70-DG017-3.docx
Cardiff Strategic Flood Consequences Assessment
Notice
This report was produced by Atkins Limited for Cardiff Council for the specific purpose of undertaking a Strategic Flood Consequence Assessment for Cardiff.
Atkins accepts no liability for any costs, liabilities or losses arising as a result of the use of or reliance upon the contents of this report by any person other than Cardiff Council.
Atkins Limited
Document History
JOB NUMBER: 5097656 DOCUMENT REF: 5097656-DG-017
1 Final Issue to Client DMH KIO HR HR 16-08-11
2 Section 4 amended to be consistent with Nov 2009 SFCA report
DMH KIO KIO HR 18-08-11
3 Section 6 revised to reflect increased risk through the docks. Area G assessment added as Section 4.
DMH KIO/HDW HR HR 01-12-11
4 Client comments incorporated. Issue to Environment Agency.
DMH KIO HR HR 15-12-11
Revision Purpose Description Originated Checked Reviewed Authorised Date
![Page 4: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/4.jpg)
![Page 5: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/5.jpg)
5097656-70-DG017-3.docx i
Contents
Section Page
Glossary of Terms vi
1. Introduction 1
1.1 Background 1
1.2 Purpose of the SFCA 1
1.3 Approach to the SFCA 2
1.3.1 Phase 1 3
1.3.2 Phase 2 3
2. The Study Area & Assessment Methodologies 5
2.1 TAN15 Constraints 5
2.2 Development Sites 5
2.2.1 Site Areas 6
2.2.2 Lifetime of Development 6
2.2.3 Climate Change 7
2.3 General Climate and Hydrology 7
2.3.1 Hydrological Situation 7
2.3.2 Extreme Sea Levels 8
2.4 Sources of Flooding 8
2.5 Assessment Methodologies 9
2.5.1 Flood Risk from Tidal Sources 9
2.5.2 Flood Risk from Main Rivers 10
2.5.3 Flood Risk from Ordinary Watercourses 10
2.5.4 Flood Risk from Sewers 11
2.5.5 Flood Risk from Culverted Watercourses 11
2.5.6 Flood Risk from Groundwater 11
2.5.7 Flood Risk from Surface Water 12
3. Area A – Wentloog Levels 13
3.1 Site Description and Flood Risks other than by Tidal Inundation 13
3.1.1 General Site Description 13
3.1.2 Proposed Development 13
3.2 Flood Risk from Tidal Sources 15
3.3 Summary of Flood Risk Management 17
3.3.0 Key Access Routes across the Wentloog Levels 17
3.3.1 Study Site 76LGW 21
3.3.2 Study Site 22LGRM 22
3.3.3 Study Site 21LGR 24
3.3.4 Study Site 23LGR 25
3.3.5 Study Site 24LGRM 25
3.3.6 Study Site 74LGEMW 26
3.3.7 Study Site 2LGRM (formerly Site 77) 27
![Page 6: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/6.jpg)
5097656-70-DG017-3.docx ii
3.3.8 Study Site 1LGRM 28
3.3.9 Study Site 106LGEM 29
3.3.10 Study Site GTechPk 30
3.3.11 Study Site Wentloo_ii 31
3.3.12 Study Site Wentloo_iii 33
3.3.13 Study Site 3SBR 34
3.3.14 Study Site 55LGR 35
3.3.15 Study Site 56LBR 36
4. Area G – Junction 33 of M4 37
4.1 Site Description 37
4.1.1 General Site Description 37
4.1.2 Proposed Development 37
4.1.3 Hydrological Situation 39
4.2 Data Review and Analysis 39
4.2.1 Information Available 39
4.2.2 Analysis Approach 39
4.3 Flood Risk from Main Rivers and Ordinary Watercourses 39
4.3.1 Flood Risk from Ordinary Watercourses 39
4.4 Flood Risk from Sewers, Culverted Watercourses and Groundwater 40
4.4.1 Flood Risk from Sewers 40
4.4.2 Flood Risk from Culverted Watercourses 40
4.4.3 Flood Risk from Groundwater 41
4.5 Flood Risk from Surface Water Runoff 41
4.6 Summary of Flood Risk and Management 43
4.6.1 Study Site 102LGR 43
4.6.2 Study Sites 46LGRM 43
5. Area H – Cardiff West Central, Taff & Ely 45
5.1 Site Description 45
5.1.1 General Site Description 45
5.1.2 Proposed Development 45
5.1.3 Hydrological Situation 48
5.2 Data Review and Analysis 48
5.2.1 Information Available 48
5.2.2 Analysis Approach 48
5.3 Flood Risk from Main Rivers and Ordinary Watercourses 49
5.3.1 Flood Risk from Rivers Taff and Ely 49
5.3.2 Estimation of the Variation in Cardiff Bay levels during flood events 50
5.3.3 Final Flood Estimation on Taff and Ely based on the Variation in Cardiff Bay levels 51
5.3.4 Flood Risk from Ordinary Watercourses 53
5.4 Flood Risk from Sewers, Culverted Watercourses and Groundwater 53
5.4.1 Flood Risk from Sewers 53
5.4.2 Flood Risk from Culverted Watercourses 54
5.4.3 Flood Risk from Groundwater 54
5.5 Flood Risk from Surface Water Runoff 54
![Page 7: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/7.jpg)
5097656-70-DG017-3.docx iii
5.6 Summary of Flood Risk and Management 56
5.6.1 Site 8LGR, Site 75SBR and Site 111LGR 56
5.6.2 Site 32LGR 56
5.6.3 Site 16LBR 57
5.6.4 Site 52LBR 58
5.6.5 Site 36LBR 58
5.6.6 Sites 31LBEM, 62LBR, 77LBR, 78LBRM and 83LBRM. 59
5.6.7 Site 70LBEM 60
5.6.8 Site 61LBRM 61
5.6.9 Site 96LGED 61
5.6.10 Site 101LBEM 61
5.6.11 Site 17LGR 62
6. Area I – Cardiff Bay to Pengam Green 63
6.1 Site Description and Flood Risks other than by Tidal Inundation 63
6.1.1 General Site Description 63
6.1.2 Proposed Development 63
6.2 Flood Risk from Tidal Sources 66
6.2.1 Overtopping and breach from River Rhymney and the Coastal Frontage 67
6.2.2 Direct Inundation from Cardiff Bay and Cardiff Docks 69
6.3 Summary of Flood Risk and Management 73
6.3.1 Site 71LBC 73
6.3.2 Site 58SBR 74
6.3.3 Site 20LBU 74
6.3.4 Site 19LBU 75
6.3.5 Site 18LBM 77
6.3.6 Site 60LBRM 78
6.3.7 Site 57LBR 80
6.3.8 Site 73LBRM 81
6.3.9 Site 101LBEM 83
6.3.10 Site 94LBR 83
7. Conclusions 86
7.1 Site Summaries 86
8. Appendices 90
![Page 8: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/8.jpg)
5097656-70-DG017-3.docx iv
List of Tables
Table 1-1 - Flood Risk for Sub areas of Cardiff 3
Table 3-1 - Area A Summary of Study Sites 15
Table 3-2 - Locations of Breaches for different time horizons and by event probabilities 16
Table 3-3 - Replication of Table 4 Hazard to People Classification using Hazard Rating 19 Table 4-1 - Area G Candidate Sites Summary 37
Table 5-1 - Area H – Summary of Study Sites 47
Table 5-2 - Flood event scenarios modelled to derive variations in Cardiff Bay levels 51
Table 6-1 - Area I – Summary of Study Sites 66 Table 6-2 – Extreme Tide Levels Severn Estuary at Cardiff Docks 67
Table 6-3 – fluvial flows assessed to occur coincident with extreme tidal flood events – Area I 67
Table 6-4 5 Levels resulting in Cardiff Bay for current and future extreme tidal events 72
Table 7-1 - Summary of Sub Area A – Wentloog Tidal Development Sites 86 Table 7-2 Summary of Area G – Junction 33, M4 87
Table 7-3 - Summary of Sub Area H – West Central Taff/Ely, Development Sites 87
Table 7-4 - Summary of Sub Area I - Bay Area to Pengam Green, Development Sites 89
Table 8-1 Scenarios modelled in 1D-2D ISIS TUFLOW model of Cardiff Bay and Roath Basin - current and
future extreme tidal events cxxii
Table 8-2 Levels resulting in Cardiff Bay for current and future extreme tidal events cxxiii
List of Figures
Figure 1-1 - Reports comprising the Cardiff SFCA* 2 Figure 3-1 – Area A Study Site Locations 14
Figure 3-2 – Hazard Score for 0.5% (1 in 200) annual chance event 2085 for access routes and study sites.20
Figure 3-3 - Site 3SBR location relative to other candidate sites and railway line 34
Figure 4-1 – Area G Study Site Locations 38 Figure 5-1 – Area H Study Site Locations 46
Figure 5-2 - ISIS Bay Model - 30 October 2000 flood event 51
Figure 5-3 - Area H Map of Surface Water Runoff Potential Screening Score 55 Figure 6-1 - Area I - Study Site Locations 64
Figure 6-2 - Extent of 2D tidal inundation model - Area I 68
Figure 6-3 Potential overland flow from Roath Basin into Cardiff Bay during extreme tide events 70
Appendices
Appendix A - SFCA Area Overview Map
A.1 Cardiff SFCA Area Overview Map – Drawing Number 5097656/RCF/002
Appendix B – Area Specific Maps
B.1 Drawing Numbers
Appendix C - Flood Depth and Area Tables
Appendix D – 2D Tidal Inundation Modelling.
D.1 Modelling approaches common to both Areas A & I
D.2 Limitations of the modelling results
D.3 Use of model results for sites not included in the SFCA Reports
Appendix E – Area A – 2D Tidal Inundation Modelling Assumptions and Results.
E.1 Model Set-up
E.2 Key Hydraulic Assumptions
![Page 9: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/9.jpg)
5097656-70-DG017-3.docx v
E.3 Modelling Scenarios and Results
E.4 Future Improvements
Appendix F – Area I (Pengam Green to Cardiff Bay) 2D Tidal inundation modelling
F.1 Model Set-Up
F.2 Key Hydraulic Assumptions
F.3 Modelling Scenarios and Results
F.4 Future modeI refinements for site specific studies
Appendix G – Assessment of risk of tidal inundation via Cardiff Docks to Cardiff Bay.
G.1 Model Set-Up
G.2 Key Hydraulic Assumptions
G.3 Modelling Scenarios and Results
![Page 10: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/10.jpg)
5097656-70-DG017-3.docx vi
Glossary of Terms
Term Meaning / Definition
AStSWF Map of Areas Susceptibly to Surface Water Flooding produced by the Environment Agency Wales
CFMP Catchment Flood Management Plans prepared by the Environment Agency Wales
DAMs Development Advice Maps (published by Welsh Assembly Government within TAN15)
DEFRA Department for Environment, Food and Rural Affairs (UK Government)
EAW Environment Agency Wales
EWL Extreme Water Level (tide level)
FCA Flood Consequence Assessment
FEH Flood Estimation Handbook method (for hydrological assessment)
FMSW Flood Map of Surface Water
HEC-RAS Hydrologic Engineering Center - River Analysis System (modelling software developed by US Army Corps of Engineers)
LDP Local Development Plan
LiDAR Light Detection and Ranging data (ground level information)
LPA Local Planning Authority
NFCDD National Flood and Coastal Defence Database
NGR National Grid Reference
PPW Planning Policy Wales (Welsh Assembly Government‟s Planning Policy)
QMED Medium Annual Flood
STAM Solutions for Total Asset Management database (Dwr Cymru Welsh Water records of reported sewer flood incidents)
SuDS Sustainable Drainage Systems
SWL Still Water Level (Tide level without Wave – effectively interchangeable with the EWL term)
TAN Technical Advice Note
TAN15 PPW Technical Advice Note 15: Development and Flood Risk
UKCIP United Kingdom Climate Impacts Programme
WAG Welsh Assembly Government
Zones A, B & C Flood Zones defined on Welsh Assembly Government DAMs
![Page 11: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/11.jpg)
5097656-70-DG017-3.docx 1
1. Introduction This report represents an update of sections of the Cardiff Phase 2 SFCA of 2009, considering
an extended lifetime of development to 2110, compared to the period to 2060 previously
considered. As described in Section 1.3.1, Cardiff has been divided into Sub Areas for the
purpose of the SFCA.
The fluvially dominated flood risk to Area H and the tidally dominated risks to Area A and Area I
have been re-assessed. The assessments of all other sources of flood risk remain largely
unchanged and are as described in the SFCA Phase 2 Report (2009). The previous assessment
of surface water flood risk have been cross checked against the Environment Agency‟s Flood
Map for Surface Water and the Areas Susceptible to Surface Water Flooding map, which have
become available for planning purposes since completion of the 2009 SFCA Report. This
current report, therefore, represents an addendum to the SFCA Phase 2 (2009). The relevant
sections of that report are repeated below. The main section numbers are consistent with the
earlier report for ease of cross reference, if required.
1.1 Background
As part of the planning process, under the Compulsory Purchase Act 2004, planning authorities
in Wales are required to produce a Local Development Plan (LDP).
The Welsh Assembly Government‟s Planning Policy Wales (PPW) provides the planning policy
framework under which the Local Planning Authorities (LPAs) must prepare their Local
Development Plans (LDPs). The LDP has to show that it is encouraging patterns of development
that are economically, socially and environmentally sustainable. As part of this, PPW highlights
the need to reduce flood risk by avoidance of development within high risk areas, as opposed to
the previous approach of flood defence and mitigation of the consequences of flooding. The
guidance requires LPAs to consider the catchment as a whole and take a strategic approach to
flood risk.
PPW is supplemented by a number of Technical Advice Notes (TANs). Of key interest is TAN15:
Development and Flood Risk which provides guidance to LPAs regarding the assessment of
flood risk when they are preparing their LDPs. The advice note seeks to guide planning decisions
so that new development is directed away from areas that are considered to be at high risk of
flooding. Where development has to be considered within a high risk area, TAN15 outlines
justification tests in order to guide decisions regarding whether a specific development may
proceed.
Atkins Limited (Atkins) was appointed by Cardiff Council in January 2009 to undertake a
Strategic Flood Consequence Assessment (SFCA) for the City. The SFCA will form part of the
evidence base for the LDP and facilitates a risk based approach to development control in
Cardiff with respect to flood risk. This will provide clarity to both the Council and to potential
developers.
1.2 Purpose of the SFCA
The SFCA will provide an assessment of the flood risk for the study sites that are being
considered for development and provide guidance regarding the management of this risk. It
encompasses a broad level assessment and does not remove the requirement for more detailed
site-specific assessments which will follow the adoption of the LDP. Site-specific FCAs will need
to be undertaken by developers at the planning application stage, as required under TAN15.
The overarching aim of the SFCA is to provide sufficient data and information to enable the LPA
to apply a sequential approach to the allocating of sites, promoting flood Zones A and B before
Zone C (of the Welsh Assembly Government‟s Development Advice Maps – DAMs).
![Page 12: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/12.jpg)
5097656-70-DG017-3.docx 2
The SFCA will assist Cardiff Council to:
Prepare appropriate policies for the management of flood risk within the LDP;
Ensure that flood risk is taken into account when considering options and in preparation of
strategic land-use policies;
Identify the level of detail required for site-specific FCAs in particular locations, and enable
the Council to determine the acceptability of flood risk in relation to emergency planning
capability;
Identify potential for producing local standing advice; and
Identify issues relating to managing surface water and use for sustainable drainage.
1.3 Approach to the SFCA
The SFCA considers both fluvial and tidal influences on flood risk within areas of the City.
Consideration is also given to other sources of flood risk; there are a number of ordinary
watercourses in the vicinity as well as public sewer networks.
Since the extent and suitability of the information available to inform the SFCA was not fully
known at the commencement of the study, the SFCA has been undertaken in two phases.
A number of reports comprise the overall Cardiff SFCA. How each of these reports relates to the
overall process is shown in Figure 1-1. The phasing of the SFCA and the definition of sub areas
A to I are described in the sections below.
Figure 1-1 - Reports comprising the Cardiff SFCA*
* PHASE 2 Part 1 Update revised November 2011 to include consideration of a flood path through Cardiff Docks to
Cardiff Bay following a query raised by the Environment Agency.
![Page 13: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/13.jpg)
5097656-70-DG017-3.docx 3
1.3.1 Phase 1
The first phase of this project involved scoping out the requirements to be considered within the
SFCA. This included defining the areas within Cardiff where the flood consequences needed to
be determined and the extent and nature of the analytical assessments required to define the
risks.
It was felt that the recommendations indicated in the Environment Agency Wales‟ guidance note
to local authorities for SFCAs were too detailed for a city-wide assessment, and to assess all the
sites in detail against the TAN15 guidance would be prohibitively expensive.
A broad-level assessment using existing information was proposed for the study. The City was
divided into nine areas, existing information was gathered and reviewed, and an initial
assessment of the flood risk for each area was made, as described in the Phase 1 Report. The
initial Phase 1 flood risk by area is summarised as shown in the table below. The geographical
location of each area within Cardiff authority boundary is shown on Drawing 5097656/RCF/002,
Appendix A.
Table 1-1 - Flood Risk for Sub areas of Cardiff
SUB AREA TYPICAL RISK SCORE
Area A - Wentloog Tidal High
Area B - Rhymney North Pontprennau Varies Low to High
Area C - NE Cardiff - Roath Brook & Nant Glandulais High
Area D - Briwnant & Tongwynlais Low
Area E - Taff at Morganstown High
Area F - Cardiff West Low
Area G - Area of Junction 33, M4 Motorway Medium
Area H – Taff/Ely 2d modelled area High
Area I - Bay Area to Pengam Green High
Tasks required to fully define the risks for each area were identified and the cost of analysis
determined. The core activities undertaken in the SFCA assessment, which are dependent on
the initial risk score, are detailed in the Phase 1 report1.
1.3.2 Phase 2
In order to achieve best value from the budget available, the Phase 2 assessment was first
targeted on four sub-areas then considered to be of greatest strategic importance to Cardiff‟s
future development. Areas A, G, H and I were progressed first as they included a significant
number of proposed LDP allocations for housing and employment uses. The report on this first
Phase 2 assessment was delivered in November 2009 and is referred to hereafter as Phase 2
Part 1. In order to address areas of uncertainty in the level of flood risk to some areas identified
by the Phase 2 study, Cardiff Council commissioned a further 2D tidal inundation modelling
studies of Area A and Area I. This was reported in an Addendum Report to the SFCA, delivered
in March 2010. These reports considered a development lifetime of 50years to 2060.
This current report documents work undertaken to update the development lifetime to consider
the period up to 2110 for Areas A, H & I in accordance with the current Environment Agency
1 Report on Phase 1 (Scoping Study) and Proposed Methodology for Offer of Services for Phase 2 - the Assessment, Atkins Report
Ref.: 5076243.56.DG.032, April 2009.
![Page 14: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/14.jpg)
5097656-70-DG017-3.docx 4
recommendation. It represents an update of Section 5 of the SFCA Phase 2 Part 1(2009) Report
and of the 2D Modelling Addendum of March 2010 (see Figure 1-1). The effects of new extreme
sea level estimates (see Section 2.3) have also been incorporated into the assessment.
Section 4, covering Area G – Area at Junction 33 of the M4 Motorway, has been updated to
include the sites submitted for the 2010 list of Candidate Sites.
The main section numbers of the SFCA Phase 2 Part 1 (2009) have been retained for this
current report for ease of cross reference.
Section 2 details the study areas and methodologies used in the assessment.
Each of Sections 3 through to Section 6 is specific to a certain area covering the main tasks
undertaken and the relevant findings.
It is worth noting, at this stage, that post-submission of the Phase 1 report, Cardiff Council
requested that some existing Allocations and Policy Areas be included in the SFCA in addition to
the Candidate Sites listed in Phase 1. For the purposes of analysis the site areas were treated
the same, and within the Phase 2 Part 1 (2009) and 2D Modelling Addendum reports (2010)
were referred to as “study sites”.
![Page 15: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/15.jpg)
5097656-70-DG017-3.docx 5
2. The Study Area & Assessment
Methodologies
2.1 TAN15 Constraints
TAN15 has different requirements for sites depending on the type of development proposed and
the zones into which they fall. Zones are defined as follows:
Zone A – Little or no risk of fluvial or tidal flooding;
Zone B – Areas known to have been flooded in the past evidenced by sedimentary deposits;
Zone C1 – Areas at risk of flooding from fluvial or tidal sources (based on EAW extreme
flood outline for 0.1% annual chance event), but currently developed and served by
significant infrastructure, including flood defences; and
Zone C2 – Areas at risk of flooding from fluvial or tidal sources (based on EAW extreme
flood outline for 0.1% annual chance event) and without flood defence infrastructure.
Section 6 of TAN15 states that “new development should be directed away from Zone C and
towards suitable land in Zone A”. Where development is proposed within Zone C it must meet
the justification tests outlined within the Section. Where consideration of a development site can
be justified, the development must then meet the acceptability criteria detailed in TAN15 Section
7 and Appendix 1.
Development within Zone C1 or C2 must be flood free during a 1% (1 in 100) annual chance
fluvial event (including climate change) and the 0.5% (1 in 200) chance tidal event and have
acceptable consequences of flooding in the extreme 0.1% (1 in 1000) annual chance event as
defined by TAN15 A1.15. A development must not increase flooding elsewhere. In addition,
flood defences must be shown to be structurally adequate under extreme overtopping conditions,
and an emergency flood plan, including flood warning system and identified evacuation routes,
must be in place.
Emergency services and highly vulnerable development (as defined by TAN15 Section 5 and
including residential development) should not be considered within Zone C2.
All development, including that within Zone A (which has few constraints to development), must
give due consideration to the management of surface water; guidance is provided in TAN15
Section 8. Any development will result in changes to the natural hydrology of the catchment as a
result of increased runoff from impermeable ground and built-up areas. TAN15 states that
Sustainable Drainage Systems (SuDS) should be employed to manage surface water runoff
wherever possible, and if the use of conventional drainage systems is proposed, developers
must give good reasons why SuDS cannot be implemented. This approach is further reinforced
through recent legislation, the Flood and Water Management Act, 2010.
2.2 Development Sites
This current report considers the flood risk to candidate sites submitted to the Council for the
Draft LDP in 2010. Much of the analysis and assessment work for the SFCA had already been
completed based on the previous 2008 list of candidate sites. However, many of the sites in the
2010 list are the same or similar to those in the 2008 list.
The flood risks associated with development of each site are described in the site summaries in
Sections 3.3, 5.6 and 6.3. The assessments of the risks from sources which have not been
updated from the 2009 report are italicised in these site summaries. This indicates the text is
repeated from the earlier SFCA 2009 report.
![Page 16: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/16.jpg)
5097656-70-DG017-3.docx 6
2.2.1 Site Areas
A review of the majority of the various sites identified for development was undertaken within the
Phase 1 assessment. This was undertaken for candidate site list as at 2008. The initial risk
categorisation of the individual sites led to the sub area risk categorisations shown within Table
1-1 above.
The three areas considered in this report as shown on Drawing Number 5076243/RCF/001 in
Appendix A, are as follows:
Area A – Wentloog Tidal
Area H – Taff/Ely 2d modelled area
Area I – Bay Area to Pengam Green
A detailed description of each area, and the development proposed there, is included in the area-
specific sections later in this report.
There is some overlap between Area I and Area H due to the potential for parts of each area to
be affected by overland flow paths from the other. Flooding mechanisms have been considered
for the overlap and study sites discussed within the most appropriate report chapter. Area
boundaries do not wholly correspond to those initially proposed within Phase 1 of the SFCA.
2.2.2 Lifetime of Development
TAN15 states that “the Assembly has a duty, under Section 121 of the Government of Wales Act,
to promote sustainable development in the exercise of its functions”, and part of this includes
“making provision for future changes in flood risk.” The guidance comments on the mounting
evidence that climate change will result in increased flood risk. Hence, flood risk must be
considered over the anticipated lifetime of each development.
Current Environment Agency Wales (EAW) policy is to accept a development lifetime of 75 years
for industrial/ commercial developments and 100 years for residential development. It previously
accepted a 50 year development lifetime, which was the basis of the analysis underlying the
Phase 2 Part 1 SFCA (2009).
The period of the development lifetime considered is important in areas where tidal influences
have an effect on the flood risk. This is because sea level is predicted to rise over time. The
longer the development lifetime considered, the greater will be the sea level rise. The allowance
made for future changes in fluvial flows is not, in practice, dependant on the period considered.
The latest Defra guidance adopted by the Welsh Assembly Government in 20072 for fluvial
flooding is to apply a 20% increase to peak river flows in order to evaluate the effects of climate
change. This is the same whether a 50 year or a 100year lifetime is considered. So for areas
affected by fluvial flooding only, the period of the development lifetime is less important than for
tidally affected areas.
In this SFCA, the peaks at the 1% (1 in 100) annual chance event in all watercourses have been
increased by 20% to account for the effect of climate change over the lifetime of the
development. No allowance for climate change was applied to a 0.1% (1 in 1000) annual chance
event, recognising the high uncertainty already inherent in estimating the flows for such extreme
events.
2 Welsh Assembly Government, July 2007, Flood and Coastal Defence Appraisal Guidance, FCDPAG3 Economic Appraisal,
Supplementary Note to Operating Authorities – Climate Change Impacts.
![Page 17: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/17.jpg)
5097656-70-DG017-3.docx 7
2.2.3 Climate Change
The Environment Agency‟s guidance3 advises that allowances for climate change should be
included when assessing compliance with the threshold frequencies identified in the table within
A1.14 of TAN15. However, it does not expect an allowance to be included, when considering the
indicative values set out in the table within A1.15 of TAN15.
Unless development for emergency services is to be considered, which must be flood free over
the lifetime of the development, then consideration of climate change to a 0.1% (1 in 1000)
annual chance flood event is not required. Since no sites proposed for emergency services have
been assessed as part of this SFCA, forecast sea level rise has only been applied to 0.5% (1 in
200) annual chance extreme tide levels.
2.3 General Climate and Hydrology
2.3.1 Hydrological Situation
Cardiff falls within the Ely, Taff and Rhymney River Catchments. Two Catchment Flood
Management Plans (CFMP) cover the Cardiff area, the Taff and Ely CFMP and the Eastern
Valleys CFMP, which includes the River Rhymney.
The Taff Ely CFMP states that the catchment covers an area of approximately 696km² and
includes the catchments of the River Taff, River Ely, River Rhondda, River Cynon and the River
Clun. The Rhondda and Cynon are tributaries of the Taff, while the Clun is a tributary of the Ely.
The catchment generally drains in a southerly direction with both the Rivers Taff and Ely
discharging into Cardiff Bay, and subsequently into the Severn Estuary.
The headwaters of the Taff are located in the north of the catchment in the Brecon Beacons.
Moving southwards the land elevations fall. Whilst the river has a steep gradient in the upper
reaches (1:60 on the Taff Fechan upstream of Merthyr Tydfil) this gradient flattens (to
approximately 1:500) as it flows through Cardiff.
The Ely valley, running in a south easterly direction adjacent to the Taff catchment, is generally
less varied than the Taff. The steep upper reaches are characterised by deep narrow valleys
that open out into meandering lowland topography on the approach to Cardiff.
Current tidal influence on flood risk from the Rivers Taff and Ely is limited by the Cardiff Barrage.
However, future flood risk from the Taff and Ely will be affected by predicted increases in sea
level and the resulting effect on levels in Cardiff Bay during fluvial flood events (see section
5.3.2)
The River Rhymney drains to the Severn Estuary in the east of the city. A confluence of a
tributary, the Roath Brook, with the main Rhymney river channel is located at some 980m
upstream from the coast. The Rhymney has a catchment area of 223km² to downstream of this
confluence, with the Roath Brook contributing 20km² of this area. Tidal influence on river levels
is high in the lower reaches of the Rhymney and the Roath Brook. The tidal limit (the maximum
upstream location where the tide influences the river flows) is considered to extend to
Llanrumney.
The average annual rainfall for the Taff Ely CFMP catchment is 1,850mm and for the Rhymney
catchment is 1,380mm, compared to the average for Wales of 1,310mm. The steep upper slopes
of the catchments and above average annual rainfall result in rapid responses to rainfall events.
Downstream through Cardiff the rivers are relatively less responsive.
Further detail regarding the hydrological situation within each sub area is included in the relevant
report chapter.
1. 3 Environment Agency Operational Instruction 229_10, Flood Risk Management: TAN15 related Planning Applications
(Wales only), Oct 2010.
![Page 18: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/18.jpg)
5097656-70-DG017-3.docx 8
2.3.2 Extreme Sea Levels
The results of a research project providing new extreme tide levels estimates were published by
Environment Agency/ Defra on the 21st February 20114. The research project provided an up-
to-date scientifically robust national evidence base and practical guidance on appropriate design
sea levels and uncertainty data around England, Wales and Scotland.
The estimated extreme tide levels and associated confidence intervals have been adopted by
Environment Agency Wales for assessment of flood risk for development control purposes, the
estimates provided being within the 95% confidence limit.
Updated tidal inundation modelling has therefore been undertaken for Areas A & I for the SFCA.
The results of the modelling and the amended assessments of tidal flood risks to the Wentloog
Levels and Cardiff Bay to Pengam Green areas are reported in section 3 and 6 below.
The extreme tidal events tested in the models are those with annual chance of exceedance of
0.5% (1 in 200) and 0.1% (1 in 1000). These are used for assessment of the study sites against
the guidance described in TAN15.
2.4 Sources of Flooding
The main risks of flooding to the study areas are:
the Rivers Ely and Taff,
from direct tidal inundation along the coast,
tidal flooding via the lower reach of the River Rhymney in the east of the City.
River Taff
The Taff catchment has experienced widespread flooding on a number of occasions over the last
60 years. These include the floods of 1946/47 (due to snowmelt), December 1960, December
1979, December 1992 and October 1998, all of which were from heavy rainfall. The most
notable flooding to Cardiff occurred in 1960 and 1979, where thousands of properties were
affected. This resulted in the Government spending a considerable sum of money on flood
defences.
River Ely
In contrast, the Ely catchment has only suffered from two significant events in the last few
decades. These were a result of heavy rainfall falling on a wet catchment in March 1998 and in
October 2000. The 1998 event only affected a small number of properties in the Ely Bridge area
of Cardiff, St Fagans, Peterston Super Ely, Brynsadler and Talbot Green. In October 2000 few
reports of flooding were reported and these were in St Fagans only.
Cardiff Bay Tidal
Tidal flood risk is considerably lower in Cardiff since the construction of the Cardiff Bay Barrage
in 1999. The barrage significantly reduces the risk of tidal flooding. However, the risk of flooding
in extreme events remains and is considered within Section 5.3.2 and Section 6.2.2 of this
SFCA.
The effects of extreme tidal events to flooding to the Cardiff Docks and the associated potential
flow routes into Cardiff Bay have been considered in Section 6.2.2
The defences to the east of the barrage are potentially susceptible to tidal overtopping. The
Environment Agency flood map indicates that the areas of Pengam Moors and Tremorfa are at
risk. Tidal flooding into these areas via the River Rhymney is discussed in Section 6.
4 Environment Agency, February 2011, Joint Defra & Environment Agency Research Project: SC060064. Coastal flood boundary
conditions for UK mainland and islands
![Page 19: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/19.jpg)
5097656-70-DG017-3.docx 9
Tidal Severn Estuary
The Wentloog Levels are partially protected by flood defence embankments along the coast.
Improvements have been made to the defences over the years but floodplain remains
susceptible to flooding due to wave and tidal sources. Storm surge levels, tidal currents and the
wind wave climate along the Severn Estuary shoreline are significant. The existing salt marsh
has previously provided extra protection to the shoreline but is generally eroding. Overtopping or
breach of defences could result in significant flooding to the low lying area behind. Further
discussion of this risk is included in Section 3.2 and Appendix E.
Other flood risks
Other flood risks have been identified within the area, including:
Ordinary watercourses;
Culverted watercourses;
Sewers; and
Surface water runoff.
Groundwater flooding is not considered a strategically significant source of flooding in the study
areas, as evidenced in the CFMPs covering the Cardiff authority area. This source has not been
the subject of analysis for this SFCA. However, there will still be a need for future site specific
FCAs to consider the local conditions, including potential groundwater issues and any control
measures necessary.
The risks associated with each source of flooding are discussed on an area-specific basis.
2.5 Assessment Methodologies
Following review of available data for each area (see area-specific chapters), assessment of the
various flood risks for each area were made, as detailed below.
2.5.1 Flood Risk from Tidal Sources
As a coastal city, the risk of flooding to Cardiff from the sea has always been significant and the
effects of climate change are expected to make the situation worse. The 2007 report on climate
change published by the IPCC emphasises the certainty of accelerated climate change, and the
previously accepted guidance for sea-level rise of 5mm/ year for Wales has now been revised.
Current DEFRA guidance states that anticipated annual sea level rises are:
3.5mm/ year until 2025,
8.0mm/ year between 2025 and 2055,
11.5mm/ year between 2055 and 2085,
14.5mm/ year beyond 2085.
These values have been used within this SFCA. The allowances for future sea level rise,
provided by Defra and adopted by WAG, used information from the UKCIP scenarios, published
in 2002. Revised estimates from UKCIP were produced in 2009, although the Defra guidance
has not been revised.
As noted in Section 2.3 above, construction of the Cardiff Bay Barrage has considerably reduced
the flood risk to the city centre and areas in the Taff and Ely catchment. However, the risk to the
Wentloog Levels (Area A) and areas to the South and East of Cardiff (Area I) from direct tidal
flooding remains high. The flooding mechanisms for these two areas are entirely different and
hence have been analysed separately.
![Page 20: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/20.jpg)
5097656-70-DG017-3.docx 10
Section 3 and Appendix E detail analysis undertaken in the determination of flood risk to the
Wentloog Levels. The assessment of potential tidal inundation was based on the Severn Estuary
Flood Risk Management Strategy (SEFRMS) previously undertaken for the Environment Agency
by Atkins. Two dimensional (2D) inundation modelling has been undertaken, incorporating the
risk of overtopping and breach of the defences to the area from the River Rhymney around the
Severn Estuary frontage to the River Ebbw. The methodology is described in more detail in
Appendix E.
For Area I, the SEFRMS analysis was extended to include an assessment of overtopping of tidal
waters that may propagate up the lower reach of the River Rhymney. This approach is
described in Appendix F.
The impact of tide level and future sea level rise on Cardiff Bay, and the resulting flood
predictions on the River Taff and River Ely is discussed in detail in Section 5.3.1. Although the
flood risk from these rivers is defined as fluvially dominated (with the 1% (100) and 0.1% (1 in
1000) annual chance events being considered), the risk arises from combinations of fluvial and
tidal effects.
Testing as part of this study has confirmed that in the river channels affecting study sites in Area
H, extreme fluvial events result in higher water levels in the Rivers Taff and Ely compared to
extreme tidal events of comparable probability.
By contrast extreme tidal effects in the Cardiff Bay area are dominant over extreme fluvial
events, i.e. result in higher flood levels. The tidal risk to study sites around Cardiff Bay is
discussed in Section 6. This includes the risk of tidal inundation into the Bay area via the Cardiff
Docks.
2.5.2 Flood Risk from Main Rivers
Fluvial flooding has been considered for the Rivers Taff and Ely (see Section 5.3.1). Tidal
influence is considered to be dominant over the fluvial effects on the River Rhymney at its
downstream end. The risks associated with this river are discussed within the tidal inundation
modelling for Area I and Area A described respectively in Appendix E and Appendix F.
Consideration of the potential impacts of climate change when assessing the consequences of
flooding have been made in line with the current DEFRA guidance and for fluvial flooding a 20%
increase to peak river flows has been included in order to reflect the influence of climate change.
Due to the high uncertainty inherent in estimating the peaks for the 0.1% (1 in 1000) annual
chance event, an allowance for climate change is not generally added to such extreme events.
2.5.3 Flood Risk from Ordinary Watercourses
No hydraulic models exist for the ordinary watercourses in the study areas and it was determined
within Phase 1 of this study that undertaking detailed modelling work as part of this study would
not be a cost effective use of resources given the anticipated level of risk. Therefore, a simple
assessment of the flood risk areas for the watercourses identified has been undertaken, with the
exception of the reen system in Area A.
The Wentloog levels are drained by a system of drainage channels, known as reens. The reens
system‟s main purpose is to move water from the fields to discharge in the sea during wet
seasons, but they also store water during dry periods for irrigation purposes. Water levels are
controlled by a system of sluices and the complexity of the system makes it difficult to assess
accurately. Since risk of flooding from the reens is potentially significant, a broad screening
assessment of the system was undertaken. This approach is described in Section 3.4.1 of the
Phase 2 SFCA (2009). The results are referenced for the relevant sites in the site summaries in
Section 3 of this current report.
For Areas H and I, reference was made to the LiDAR contour data in order to determine potential
flood extents and flow paths.
![Page 21: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/21.jpg)
5097656-70-DG017-3.docx 11
The Dock Feeder in Area I is a potential source of flooding. This watercourse runs from an off-
take from the River Taff at Blackweir to Bute Dock through sections of open canalised channels
and culverts. A full discussion of its route is included in Section 6.4 of SFCA Phase 2 Part1
(November 2009). Since no existing flood studies exist for the watercourse an assessment of
potential risks was based on review of LiDAR data. However, it is recommended that a detailed
study of the hydrology and hydraulic modelling of the Dock Feeder channel is undertaken as
part, or prior to, any FCA for sites potentially affected in order to provide a better understanding
of the risks.
2.5.4 Flood Risk from Sewers
Cardiff has both separate and combined foul and surface water drainage systems. As a result of
historic development, unknown connections, and the existence of additional private sewer
systems within developed areas, there is significant uncertainty as to the local drainage
catchments in some areas. Although not all incidents are reported, the best information available
for determining flood risk from the sewerage system is the Dwr Cymru Welsh Water (DCWW)
Solutions for Total Asset Management (STAM) database. The database provides details of
reported flooding, pollution and odour incidents and, where appropriate, details of consequent
action taken.
With DCWW‟s permission, interrogation of the STAM incident database has been made for all
areas. DG5 sewer flood incidents, reported Severe External Flooding (SEF) and Other Flooding
(OF) incidents were all considered. It was noted in Phase 1 or this study that caution must be
exercised in interpretation of the database, since the nature of the incidents will depend on a
combination of local conditions at the time of individual storm events (blocked drains, local
maintenance protocols) and not all indicate a longer-term flood risk. In order to give indication of
areas of potential longer term risk, database incidents were screened to include incidents relating
to hydraulic overload only; known blockage incidents were excluded. The location of hydraulic
overload incidents have been considered in relation to the study sites taking account of local
ground profile in order to determine those which might be at risk from sewer flooding in the
future. Discussion of conclusions drawn from the analysis is included in the area-specific
chapters.
2.5.5 Flood Risk from Culverted Watercourses
The majority of watercourses within the study area remain in open channel for much of their
length; no risk from long culverted watercourses has been identified. However, there will be risks
associated with short culvert sections under roadways. Potential blockage within culverts could
result in waters backing up and watercourses overtopping and flooding land upstream of
culverts.
Flood risk has also been noted for two culverts within Area H and I; see Sections 5.4.2 and 6.4.2
respectively.
A large number of culverts within Area A are associated with the Reen System. Inspection and
assessment of each of these is beyond the scope of this strategic level study. It is anticipated
that these will be subject of site specific FCAs and are likely to be manageable through local
mitigation measures on the study sites. A limited amount of information was made available by
Network Rail, supplemented by site visit to inform the hydraulic inundation model of Area A (see
Appendix E) No separate assessment has been undertaken for flood risk linked to individual
culverts within this area.
2.5.6 Flood Risk from Groundwater
The brief for this SFCA did not include the requirement to consider risk of flooding from
groundwater sources. It is anticipated that the risk of groundwater flooding is low, and this is
confirmed by the Taff and Ely CFMP which states that groundwater flooding is not considered to
be a significant issue within the catchment. However, this does not negate that fact that risks
![Page 22: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/22.jpg)
5097656-70-DG017-3.docx 12
associated with groundwater ought to be investigated as part of any site-specific FCAs carried
out in the future.
2.5.7 Flood Risk from Surface Water
Surface water risk was considered as part of the earlier reports forming the Parts of the Cardiff
SFCA (see Figure 1-1). These were completed prior to the Environment Agency‟s release of a
new Flood Map for Surface Water (FMSW) in late 2010. The FMSW represents the mechanisms
that cause surface water flooding. The map is available for 30- and 200-year storms.
Guidance issued by the Environment Agency states that the map is not intended to be definitive.
The maps should be used to support local flood risk management where better data are lacking.
The methods used to assess risk from surface water are described in section 2.5.7 of SFCA
Phase Report, November 2009.
In preparing this current report, the FMSW has been referred to. Where these maps indicate a
risk of surface water flooding which is different to that previously identified, this is noted. The
methods used previously and thus supplemented by the information in the FMSW are considered
to provide a level of assessment appropriate for this strategic level study.
![Page 23: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/23.jpg)
5097656-70-DG017-3.docx 13
3. Area A – Wentloog Levels This section updates the assessment of flood risk for sites in the Wentloog Levels. It is based on
updated 2D tidal inundation modelling and supersedes the 2D Modelling Addendum Report of
March 2010 (see Figure 1-1 and section 1.3). The updated modelling takes account of new
estimates of extreme sea levels, released by the Environment Agency in February 2011 and
considers development lifetime up to 2110.
The assessments of all sources of flood risk, other than tidal, remain unchanged from those
reported in the SFCA Phase 2 Part1, November 2009. These assessments are, for
completeness and ease of reference, repeated under the summary of flood risk in Section 3.3,
together with the updated assessment of tidal flood risk. The text repeated from the earlier
Phase 2 report is italicised.
3.1 Site Description and Flood Risks other than by Tidal Inundation
Full details of the extent and description of Area A and the assessment methodologies used for
sources of flood risk other than tidal are given in the SFCA Phase 2 Part1 Report (2009).
As described in Section 1.3, the earlier SFCA 2D Model Addendum Report (March 2010)
considered the candidate sites to the Draft LDP which was withdrawn in 2010. The Candidate
Sites Submitted in 2010 for the current Draft LDP have been considered for this update.
3.1.1 General Site Description
Area A covers the area of the Wentloog levels that lie within the Cardiff Council Local Authority
Boundary. This extends from the Rhymney River in the West to St Mellons Business Park in the
East. The Wentloog Levels comprise an area of historically reclaimed land. As part of the
reclamation and subsequent management, an extensive network of ditches (reens) exists to
drain water out to sea. Land use in the area includes wide swathes of agricultural land, with a
large number of smaller conurbations to the North. Strategic infrastructure includes the main
London to south Wales railway line.
3.1.2 Proposed Development
A wide range of development types have been proposed for the Wentloog levels comprising
developments for employment, business, industry, housing and mixed use. The majority of the
sites in this area fall within the Environment Agency‟s extreme flood outline (0.1% (1 in 1000)
annual chance flood event) and Zone C1 of the TAN15 DAM. Although the area is defended
from tidal inundation, the sites were categorised as High Risk within Phase 1 of this SFCA due to
the potential for the defences to be either overtopped or breached.
The geographical extent of the study sites are shown on Figure 3-1 and site details are
summarised in Table 3-1 below.
![Page 24: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/24.jpg)
5097656-70-DG017-3.docx 14
Figure 3-1 – Area A Study Site Locations
© Crown Copyright. Cardiff County Council, 100023376 (2011)
![Page 25: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/25.jpg)
5097656-70-DG017-3.docx 15
Table 3-1 - Area A Summary of Study Sites
Site ID Name/ Location Existing Land Use
Development Category Area (ha)
76LGW South of Wentloog Avenue Previously Undeveloped Land
Waste Management Facility
60.0
22LGRM Trowbridge Mawr Previously Undeveloped Land
Residential/Industrial and Ancillary Community
35.0
21LGR Areas 9 - 12 St. Mellons Previously Undeveloped Land
Residential and Ancillary Community
18.8
23LGR Land bet. Crickhowell Rd and Willowbrook Rd
Previously Undeveloped Land
Residential and Ancillary Community
5.6
24LGRM Land East of Cypress Drive, St. Mellons
Previously Undeveloped Land
Mixed Use 9.5
74LGEMW Wentloog South of the Railway Line Previously Undeveloped Land
Employment and Waste 8.3
2LGRM Land at St. Mellons Business Park Previously Undeveloped Land
Mixed Use 3.9
1LGRM Land at Wentloog Levels Previously Undeveloped Land
Mixed Use 28.0
106LGEM Land at St Mellons/ Wentloog Previously Undeveloped Land
Mixed Use 71.0
GTchPk Action Area Previously Undeveloped Land
Green Tech Park 14.70
Wentloo_ii Action Area Previously Undeveloped Land
Business, Industry and Warehousing
15.60
Wentloo_iii Action Area Previously Undeveloped Land
Business, Industry and Warehousing
15.40
3SBR Pill Du Farm, Hendre Lane, Trowbridge, Cardiff
Yard and Scrubland
Residential 0.5
55LGR Trowbridge Road, Cardiff Greenfield Residential 2.6
56LBR St John‟s College Site, Greenway Road, Trowbridge, Cardiff
Brownfield Residential 2.51
3.2 Flood Risk from Tidal Sources
The Wentloog Levels floodplain is considered to be susceptible to flooding due to wave and tidal
effects. The defences are generally higher than extreme still water sea levels (SWL). The wave
climate, however, is such that during extreme storms, the quantity of water overtopping the
defences may be sufficient to cause damage to sections of the defences and potentially cause
breaches. The chances of extreme sea levels and high waves occurring together have been
considered. For each of the combinations, the resulting likelihood of breach of the coastal
defences has been assessed.
The risk of breaches has been assessed based on methodologies underlying the Environment
Agency‟s Severn Estuary Flood Risk Management Strategy (SEFRMS). The approach to the
modelling is described in Appendix E. Essentially the approach considers the joint probability of
wave and extreme tide levels, the probability of breach of the coastal defences and the
consequences of such breach events.
![Page 26: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/26.jpg)
5097656-70-DG017-3.docx 16
Different combinations of extreme tide level and wave height, each with the same overall
probability were tested for scenarios at each time horizon. The modelling results indicate that
various combinations could result in breach at a number of locations along the defences over a
one hundred year development lifetime. These locations are referenced5 as listed below and are
marked on drawings 5097656/RCF-120 to RCF-122 in Appendix B.
Table 3-2 - Locations of Breaches for different time horizons and by event probabilities
Year Event chance Location References
2010 0.5% (1 in 200) SR1-RREB & SR1-2
0.1% (1 in 1000) As above plus SR1-0
2085 0.5% (1 in 200) As above plus SR1-3 & SR1-6
2110 0.5% (1 in 200) As above plus SR1-1 & SR1-REWB
SR1-RREB River Rhymney East Bank (downstream of rail bridge)
SR1-0 Little Wharf
SR1-1 Rhymney Great Wharf
SR1-2 Sluice Farm
SR1-3 Peterstone Great Wharf
SR1-6 Lighthouse Park
SR1-REWB River Ebbw West Bank
Currently two locations are considered susceptible to breach with a 0.5% (1 in 200) annual
chance in any year. For 0.1% (1 in 1000) annual chance events the number of sections of
defence currently considered susceptible to breach increases to three.
The weak points in the defences at Sluice Farm and on the east bank of the River Rhymney are
predicted to be damaged, but not breach, by events of a current 2% (1 in 50) annual chance of
exceedance. The Rhymney defence is predicted to be breached by tidal event with a 1% (1 in
100) annual chance, whilst the Sluice Farm defence will be breached by 0.5% (1 in 200) chance
events.
The numbers of susceptible sections of defence are predicted to increase into the future due to
the effect of sea level rise. The locations considered to be susceptible to breach over different
time horizon are summarised in the following table. It is considered likely that by 2085, four
locations will be susceptible to breach during 0.5% (1 in 200) chance events.
The results of the modelling are presented as flood boundaries on Drawings numbered
50976565/RCF/120 to 122 in Appendix B.
The consequences for the study sites indicated by the results of the modelling are described in
the following section.
5 Note that the referencing of the breach locations has been changed since the March 2010 SFCA 2D modelling addendum to be
consistent with the referencing used in the Environment Agency‟s SEFRMS project.
![Page 27: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/27.jpg)
5097656-70-DG017-3.docx 17
3.3 Summary of Flood Risk Management
The flood risks to each study site in this area are described in the site summaries below. The
drawings in Appendix B which show the results of the 2D tidal inundation modelling for Area A
should be referred to in reading these site summaries.
Area wide impacts
By the year 2085, as a result of climate change, it is predicted that the majority of the Wentloog
levels within the Cardiff Authority area, especially south of the main rail line, are likely to be
inundated by 0.5% (1 in 200) tidal events as a result of breach of the coastal defences. All this
land therefore fails TAN15 criteria for the threshold of flooding (A1.14 of TAN15). Site specific
measures alone are unlikely to reduce the risk to acceptable levels for new development in line
with TAN15.
A strategic approach to flood alleviation to the Wentloog Levels as a whole is required if future
development is to proceed in this area.
Consideration is being given to improvements in flood risk management measures in the
Wentloog levels as part of the Environment Agency‟s Severn Estuary Flood Risk Management
Strategy (SEFRMS).
The SEFRMS consultation document for South East Wales6 contains a number of proposals to
manage flood risk in the Wentloog Levels. However, these aspirations cannot be guaranteed.
Funding and a commitment to progress the proposals would be required to mitigate the area
wide risk from 0.5% (1 in 200) chance events.
The proposed measures include:
improvements within 5 years to the weak point in the defences at Sluice Farm to bring the
general standard of defence to the Wentloog levels up to 0.5% (1 in 200) chance of
exceedance in any year.
In order to counteract the effects of climate change and keep the overall level of flood risk at
current day levels, further measures are proposed :
“Between 2060 and 2100” it is “proposed” to undertake “strengthening of the defences by
increasing the height of the embankments to keep pace with climate change”.
The objective is to “ensure that the chance of tidal flooding remains at 1 in 200 or less in any
year”.
However, as there is no guarantee that the costs of providing improvements to the defences can
be secured, for the purpose of the SFCA, it is assumed that the current defences will be
maintained at existing levels, and that the probability of overtopping and breach will increase into
the future due the effects of predicted sea level rise.
As part of the suite of mitigation options to be considered for each site, it is recommended that
flood management protocols should be developed for all study sites identified as being at risk of
flooding. This would need to take account of the risk to the site and the access and egress
routes.
3.3.0 Key Access Routes across the Wentloog Levels
For those sites situated south of the railway line, maintenance of access during extreme tidal
flood events poses a significant problem. This is less of an issue for those sites north of the
railway. The modelling indicates that key access routes across the Wentloog levels will be
affected by flooding within a 75 year development lifetime to 2085.
6 Managing Flood Risk on the Severn Estuary, South East Wales, Consultation Document, Environment Agency January 2011
![Page 28: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/28.jpg)
5097656-70-DG017-3.docx 18
If development of any given site is to proceed in line with TAN15, it will need to be demonstrated
that escape/ evacuation routes remain operational under all conditions, as stated in A1.12
TAN15. This is a matter requiring expert assessment from the emergency services and local
authority emergency planners.
It is likely that this would include a more detailed assessment of the flood risk, considering the
actual site use as well as the depths and velocities of flood water.
An indication of the likelihood that access will remain operational can be gained by calculating a
hazard rating for locations based on the 2D tidal modelling of 0.5% annual chance events for
2085. This method is based on DEFRA research FD2320/TR2 and is recognised in England in
PPS25, (Planning Policy Statement 25: Development and Flood Risk: England). PPS25 adopts
a risk based approach. The hazard rating combines velocity, depths and a debris factor to
assess the combined hazard against conditions which are tolerable for emergency services to
function.
The PPS25 document references separate research7 which provides the guidance
recommended for development control and planning purposes. Although, this method has no
official endorsement through planning guidance in Wales, it can be considered to provide
evidence as to whether or not access will be operational for emergency services in the event of a
flood event.
The resulting hazard matrix from Defra Research Paper produced in PPS25, Table 4 is
replicated below as Table 3-3.
Figure 3-2 presents the hazard scores across the Cardiff Wentloog Levels area based on depths
and velocities which the modelling indicates can be expected during 0.5% (1 in 200) chance
events in 2085. This corresponds to the 75year development lifetime which is relevant to non
residential developments.
Based on this information and referencing the hazard matrix (Table 3-3) the following is
concluded with respect to the risk to access routes:
By 2085, along the majority of the flooded sections of main access roads, notably Wentloog
Avenue, the hazard score is classified at the highest rating of “Danger for All”. This indicates that
these sections of road would not be safe for emergency services to operate. Some lengths of
Wentloog Avenue are indicated to have a “Very low hazard” score, where the road is flood free
due to its elevation above the surrounding land. However, without mitigation, it cannot be
considered that access to sites which rely on this route (notably Site 76LGW) will remain
operational, and so fail to comply with TAN15 A1.12.
It is noted that the hazard rating is sensitive to the debris factor (DF) assumed (it is taken as 1.0
for all depths above 0.2m in the current analysis). Further more detailed assessment based on
local factors are required, This would include more detailed survey and consideration of the
actual likelihood of debris being a significant factor.
The potential to mitigate the risk to the main access routes may be achieved through raising key
sections – i.e. reduce the hazard score to at least “Danger for most” or below. Although subject
to confirmation, such measures might include raising of sections of low lying road. These would
need to be achieved without diverting flows and so increasing flood risk elsewhere.
A strategic approach to managing flood risk to the Wentloog levels in line with the proposals
included in the Environment Agency‟s Severn Estuary Flood Risk Management Strategy, would
reduce the risk to access across the area to all sites to acceptable levels.
7 Supplementary note on flood hazard ratings and thresholds for development planning and control purpose: Suresh Surendran and
Geoff Gibbs (Environment Agency),Steven Wade and Helen Udale-Clarke (HR Wallingford): May 2008:
![Page 29: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/29.jpg)
5097656-70-DG017-3.docx 19
Table 3-3 - Replication of Table 4 Hazard to People Classification using Hazard Rating
![Page 30: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/30.jpg)
5097656-70-DG017-3.docx 20
Figure 3-2 – Hazard Score for 0.5% (1 in 200) annual chance event 2085 for access routes and study sites.
© Crown Copyright. Cardiff County Council, 100023376 (2011)
![Page 31: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/31.jpg)
/5097656-70-DG017-3.docx 21
3.3.1 Study Site 76LGW
This study site covers an area of some 60 ha. The proposed use is solely waste management.
If this includes waste disposal, this is classified under TAN15 as highly vulnerable development.
The site lies in TAN15 Zone C1. If waste disposal is proposed for the site, such highly vulnerable
development will need to be justified in line with Section 7 of TAN15.
The majority of the area of this previously undeveloped land lies south of Wentloog Avenue. The
site abuts or lies in close proximity to the coastal frontage over a length of some 2km. The south
west extremity of the site lies within 360m of one of the sections of the coastal defence assessed
to be at risk of breaching.
Tidal inundation
The results of the 2D tidal inundation modelling are summarised below.
Current situation 2010
The model results indicate that the site is flood free for a current 0.5% (1 in 200) annual
chance tidal event.
Large areas of the site would be inundated during a current 0.1% (1 in 1000) annual chance
event. Those areas remaining flood free would become islands surrounded by inundated
areas.
Depths of flooding would exceed 0.6m over some areas during this event, particularly in the
northern and south western parts of the site. Some localised areas around the existing
drainage channels could be expected to flood to depths exceeding 1.0m.
The corresponding velocities during a 0.1% (1 in 1000) chance event would be below
0.3m/s over the majority of the site. However, velocities would exceed 0.45m/s in the
southern part of the site and along existing drainage channels.
Considering climate change and sea level rise allowances to 2085:
The majority of the site area is within the 0.5% (1 in 200) annual chance tidal inundation
flood boundary. Islands of flood free ground would be isolated from existing access/egress
routes to Wentloog Avenue by the surrounding flooded areas.
Newton Road which runs from Wentloog Avenue through the site towards the coast is
predicted to be flooded in a 0.5% (1 in 200) annual chance event. Access along Newton
Road from the east would not meet TAN15 indicative acceptance criteria.
A potential access/ egress route to the site from the north over the rail line via Wentloog
Avenue is flooded along most of its length in a 0.5% (1 in 200) annual chance event.
Considering climate change and sea level rise allowances to 2110
The proposed development use of this site is for non residential development. Climate change
to 2110 would need to be considered if residential use were to be proposed.
Mitigation of the risk
It is possible that mitigation of the flood risks for at least part of the site over a 75 year period to
2085 could be achievable for non residential uses. The mitigation measures will need to be
explored as part as a site specific FCA. Options which may be considered include:
Options to manage the risk of flooding should consider a flood management plan within the
site operation plan, which would include a flood warning system and emergency evacuation
procedures.
Within the site it may be possible to raise ground levels to connect the flood-free portions of
the site. A site specific FCA would need to demonstrate that changes in ground and
highway levels would not adversely impact on flood risk elsewhere.
![Page 32: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/32.jpg)
/5097656-70-DG017-3.docx 22
Ground raising to connect flood free area and provide flood free access across the site
(during a 0.5% chance event). Compensatory ground lowering would be required in other
appropriate areas, ensuring a level for level compensation;
Reducing the probability of breach through reinforcement of the coastal defences;
It is possible that raising some lengths of Wentloog Avenue to maintain safe access during a
0.5% (1 in 200) chance event could be explored for the benefit of the western Wentloog
area as a whole.
It is reiterated that TAN15 requires that mitigation measures must not adversely impact on flood
risk elsewhere.
Fluvial and other sources of flood risk
The flooding risk considered for sources other than tidal inundation are based on the broad scale
assessments as described in the Cardiff SFCA, November 2009.
Fluvial flood risk for the site is not considered to be significant, and no sewer or groundwater
issues have been identified for the site. Assessment of surface water indicates that there no
significant sources of runoff or flow paths in the area so risk from this source is also low.
Reference has been made to the Environment Agency surface water flood map (FMWS) does
not suggest any significant surface water management problem.
Site summary
By 2085, large areas of the site fail A1.14 of TAN15 as they are inundated by a 0.5% (1 in 200)
annual chance tidal event.
The safe access and egress routes to and from the site during this event would not be available
by 2085 if the Severn Estuary defences were to remain at their existing heights and conditions.
Without a strategic approach to future flood risk management, in line with the proposals included
in the Environment Agency‟s Severn Estuary Flood Risk Management Strategy, justification of
the site under TAN15 would be problematical.
Mitigation of the risk of breach through reinforcement of the sea defences may reduce the risk of
tidal flooding to an acceptable level to achieve TAN15 compliance for development of this site. A
site specific FCA would be required to fully define the risk and the extent of any possible
mitigation measures.
Waste disposal is categorised as “highly vulnerable” within TAN15 and the planning authority
would need to justify such a use in the flood plain as described in section 7 of TAN15. Without
further details of the proposed site use under the general waste management description, the
proposed site use is assumed to be highly vulnerable. It is recommended that the site use will
need further discussion with the Environment Agency to determine if the proposed use is treated
as highly or less vulnerable development under the terms defined in TAN15.
3.3.2 Study Site 22LGRM
This previously undeveloped land is known as Trowbridge Mawr. The proposed land use has
been changed since the original SFCA to include industrial uses as well as residential.
Tidal inundation
For the 2D tidal inundation modelling, the rail line is assumed to provide some protection from
tidal inundation waters for those areas to its north. This assumption would need to be confirmed
through structural assessments and ground investigation as part of any development proposals
at this site. The 2D tidal inundation modelling results, which assume that the railway provides an
effective barrier to tidal inundation, are described below.
![Page 33: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/33.jpg)
/5097656-70-DG017-3.docx 23
Current situation
Undeveloped land at Trowbridge Mawr is estimated to be flood free for a current 0.5% (1 in
200) annual chance tidal event
Currently the site is indicated to be almost entirely flood free for 0.1% (1 in 1000) annual
chance flood events. A small area at the southern extent of the site would be inundated to
depths and velocities less than 0.6m and 0.15m/s, respectively.
Considering climate change and sea level rise allowances to 2110:
The topography of the site is such that flood extents during 0.5% (1 in 200) annual chance
events for 2085 and 2110 are not significantly different in relation to the overall site area.
Approximately two-thirds of the site would be flooded by a 0.5% (1 in 200) annual chance
event and so fails A1.14 of TAN15. The north eastern part of the site would remain flood
free.
Flood free access/ egress would be possible from the north.
Fluvial flood risk
For a fluvial event, based on volumetric filling of the flood plain, analysis indicates there is
adequate storage capacity to ensure that a 0.1% (1 in 1000) annual chance rainfall event would
not impact the site. Local conditions will need to be assessed to determine measures required to
ensure drainage to the reen system remains sufficient to convey any flood flows. A number of
culverts under the rail line to the south will need to be assessed for condition, conveyance
capacity and risk of blockage.
Other sources of flood risk
As noted in Section 3.5.3 of the SFCA, the site has a history of high groundwater levels causing
ponding on the fields to depths of up to 0.3m. This source will need to be investigated further as
part of any site specific FCA. It is considered likely that the risk from this source could be
managed. Use of filter drains and other ground water management methods, along with options
to raise the elevation of developed areas of the site and make a feature of ponds, should be
considered within the site specific FCA.
Site summary
For the reasons described in Appendix D, the 2D modelling takes account of the characteristics
of the overland flow paths from the coastal defences to the study sites. The results provide a
representation of the distribution of flood flows and depths through the Wentloog Levels.
Our analysis indicates that water is conveyed overland from the coast to the study site via the
culverts under the railway embankment. By 2085, a 0.5% (1 in 200) tidal event would flood the
majority of the site. This area of the site fails to comply with A1.14 of TAN15 for all development
types, based on the frequency of flooding.
Although the majority of the site has been assigned a medium surface water risk score, it is
considered likely that surface water runoff can be accommodated in the existing drainage
system. The use of SuDS in the design of any development should be adopted to ensure that
runoff from the site does not adversely affect flood risk elsewhere.
Without mitigation of the tidal flood risk, the majority of the site fails to comply with TAN15
guidance. Access routes to the site which remain operational under all conditions should be
achievable.
Mitigation of the flood risks for at least part of the site over a 100 year period to 2110 should be
achievable and will need to be addressed by any site specific FCA. It is unlikely that the whole
site area will meet TAN5 acceptability criteria. The following options could be considered to
mitigate the flood risk to parts of the site and so increase the proportion of the site that meets the
TAN15 acceptability criteria:
![Page 34: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/34.jpg)
/5097656-70-DG017-3.docx 24
Ground raising to reduce flooding to site areas. This would require compensatory ground
lowering in other appropriate areas, ensuring a level for level compensation;
Reducing the probability of breach through reinforcement of the coastal defences (likely to
require a multi agency strategic approach);
Provision of groundwater drainage measures; and
Provision of detailed flood management plan including flood warning system and emergency
evacuation procedures.
It is reiterated that TAN15 requires that mitigation measures must not adversely impact on flood
risk elsewhere.
Without a strategic approach to future flood risk management of the Wentloog Levels, in line with
the proposals included in the Environment Agency‟s Severn Estuary Flood Risk Management
Strategy, it is likely that approximately one third of the site area will comply with the indicative
acceptance criteria in TAN15.
3.3.3 Study Site 21LGR
This study site is known as Areas 9-12, St Mellons and is situated north of the rail line. The site
is proposed for housing and ancillary services.
Tidal inundation
Current Situation 2010
Currently flood free for current 0.1% (1 in 1000) annual chance events.
Considering climate change to 2110
2D tidal inundation modelling results indicates that the site is flood free for all events tested
including the future 0.5% (1 in 200) annual chance events through to 2110.
Other sources of flood risk
The flood risk from surface water and fluvial flooding is not anticipated to be significant. The
sites are situated at the bottom of sloping land which may contribute some runoff from the
surrounding developed areas although surface water runoff is likely to be managed in these
areas already.
The potential risk from groundwater should be clarified through a site specific FCA. As described
in Section 3.3.2, the adjacent Site 22 has a history of groundwater flooding. However, it is
considered likely that the risk from this source can be mitigated.
Site summary
No significant problems are anticipated for the development of this site with respect to TAN15
indicative guidance.
![Page 35: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/35.jpg)
/5097656-70-DG017-3.docx 25
3.3.4 Study Site 23LGR
This site is understood to have extant planning permission. Any future issuing or renewal of
planning consent will need to reflect the management of the consequences of flooding in line
with current planning policy guidance.
This land between Crickhowell Road and Willowbrook Drive is proposed for residential and
ancillary services. Although the southern extent of the site lies within TAN15 Zone C1, our
assessment based on 2D modelling indicates that this land is situated outside the current 0.1%
(1 in 1000) annual chance tidal event flood extent. It is also predicted to remain flood free during
0.5% (1 in 200) annual chance events over a development lifetime of 100 years.
The site slopes from some 13mAOD in the north to 7.5mAOD in the south. The local topography
does not suggest any significant residual risk from the stream running through the site.
It is anticipated that housing development may be directed away from low end of the site where
runoff from the steep slope may cause local transient ponding. It may be possible to mitigate this
risk through the drainage design for any proposed development. Mitigation of any residual flood
risks for the site as a whole should be achievable. The site has a medium risk score for surface
water runoff.
Site summary
It is considered unlikely that there would be any problems with developing the site in line with
TAN15 indicative acceptability criteria, providing a site specific FCA gives adequate
consideration to the management of surface water runoff.
3.3.5 Study Site 24LGRM
This site, at the East of Cypress Drive, lies in of TAN15 Zone C1.
Current situation 2010
The 2D tidal inundation modelling results indicate that site would be flood free for the current
0.1% (1 in 1000) annual chance tidal inundation event.
Considering climate change to 2085
The modelling indicates that it is likely that the site would remain flood free during 0.5% (1 in
200) annual chance tidal to 2085.
Considering climate change to 2110
During a 0.5% (1 in 200) annual chance event in 2110, a significant proportion of the site would
be subject to flooding in low lying areas in the east and the south of the site.
Mitigation
It is anticipated that the risk to parts of the flooded areas could potentially be mitigated by raising
ground levels and so increase the proportion of the site which might be developable in line with
TAN15. Some land would need to be used to provide compensatory flood storage for any areas
raised out of the flood plain. Therefore, even with mitigation, it is unlikely that all the site will
comply with the TAN15 indicative acceptance criteria.
A site specific FCA would be necessary to confirm that the mitigation would not create adverse
flooding impacts elsewhere.
Flood free access/ egress would be possible via Cypress Drive from the north.
Other sources
A reen runs around the eastern boundary of the site. An hydraulic assessment of this channel
during fluvial flood events will need to be undertaken as part of any site specific FCA. Similarly,
the site’s low elevation compared with the land to the west might make it susceptible to surface
![Page 36: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/36.jpg)
/5097656-70-DG017-3.docx 26
runoff issues from existing residential areas and highways and this risk should be investigated
further within the FCA.
There are a number of flooding incidents to the north of this site recorded on DCWW’s STAM
database over a number of years (see SFCA Section 3.5.1). Whilst the potential risk to the site is
considered low, it is unclear if reported incidents indicate any under capacity in the sewerage
network which may need addressing. A site specific FCA should confirm the level of the risk and
impacts on the development of the site.
Site summary
It is likely that considering a 100 year period to 2110, mitigation of flood risk to the majority of the
site area should be achievable in line with the TAN15 indicative guidance for residential
development of this site.
3.3.6 Study Site 74LGEMW
Land at Wentloog south of the rail line has been identified for employment and waste
management, the latter of these being classed as “highly vulnerable development” within TAN15.
The site lies in TAN15 Zone C1.
Tidal inundation
The following is a summary of the 2D tidal inundation modelling results.
Current situation
The site would remain flood free during a 0.5% (1 in 200) annual chance tidal event.
The majority of the site would be flooded during a 0.1% (1 in 1000) annual chance tidal
event. Flood depths would generally be below 0.6m although some localised areas around
existing drainage channels would subjected to depths up to 1.0m. Flow velocities would be
less than 0.15m/s over much of the flooded area with velocities up to 0.3m/s in the south
eastern corner of the site.
An access/ egress route could be established to the west via Wentloog Avenue.
Considering climate change and sea level rise allowances to 2085:
The site would be completely inundated during a 0.5% (1 in 200) annual chance tidal event
and without mitigation would fail A1.14 of TAN15.
Access/ egress routes to the west of the site via Wentloog Avenue would be completely
inundated by 0.5% (1 in 200) event by 2085.
Other sources of flooding
No other significant flood risks have been identified for the site.
Site summary
Mitigation of the risk of tidal breach through reinforcement of the coastal defences would likely
achieve TAN15 compliance at this site. As stated previously, this would most likely be
undertaken as part of a broader effort to facilitate development of the Wentloog Levels,
consistent with the proposals described in the Environment Agency„s Severn Estuary Flood Risk
Management Strategy.
Without mitigation the site fails TAN15 for all development types.
It is possible that without strategic reinforcement of the coastal defences that TAN15 criteria may
be met for some small areas of the site through raising of ground levels. This would require
lowering of levels elsewhere to compensate for loss of flood storage. However, the inundation of
access routes would remain a problem (as described in section 3.3.0). Further site specific
assessment would be required to consider the viability of managing the risk to the access route
![Page 37: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/37.jpg)
/5097656-70-DG017-3.docx 27
through a flood management plan, including flooding warning and emergency evacuation
procedures.
3.3.7 Study Site 2LGRM (formerly Site 77)
Site 2 runs approximately north to south around the eastern extent of the existing St Mellons
Business Park. The entire site lies within TAN15 Zone C1. The southern end of the site is low
lying (below 4.8mAOD) compared with the general ground elevation in the Wentloog Levels.
Ground elevations in the northern area of the site are above 6.5mAOD.
Tidal inundation
The rail line has been assumed to provide an effective defence against tidal inundation for areas
to its north. This would need to be confirmed by site specific FCA.
The following is a summary of the 2D tidal modelling results.
Current situation
The site is predicted to be flood free during a current 0.1% (1 in 1000) annual chance tidal
event.
Considering climate change and sea level rise allowances to 2085:
Approximately 25% of the site would be flooded during a 0.5% (1 in 200) annual chance
tidal event. The northern part of the site would remain flood free.
In the event of a flood, the existing access via Heol Las would be cut off. A new access/
egress route to the flood free portion of the site would need to be provided from the north or
west.
Considering climate change and sea level rise allowances to 2110:
Approximately 50% of the site would be flooded during a 0.5% (1 in 200) annual chance
tidal event.
A new access/ egress route to the flood free portion of the site would need to be established
from the north or west.
Fluvial flood risk
A drainage channel to the reen system forms the eastern boundary of the site. The broad scale
assessment of rainfall volumes in this study suggests the potential for runoff during a 0.1% (1 in
1000) annual chance event will exceed the storage capacity of the reens. Flooding of low lying
areas of the site can be expected. Existing information is insufficient to confirm compliance or
otherwise with TAN15, although it is anticipated that the reens could be managed to facilitate
development within the northern part of the site. Detailed hydrological and hydraulic assessment
of the drainage in this area will be required as part of a site specific FCA.
Other sources of flood risk
A high groundwater table, identified as a potential residual risk in Study Site 22 at Trowbridge
Mawr may also affect this low lying site. This will also need to be addressed as part of any site
specific FCA. There are no significant sources of runoff adjacent to the site.
The risk associated with recorded incidents of sewer flooding, including Pascal Close, as
described in Section 3.5.1 (of the SFCA), will also need to be addressed by any site specific
FCA.
Site summary
The risk posed by the existing drainage channel through the area will need to be understood in
more detail. Options for mitigation of this risk will need to be explored as part of a site specific
FCA. However, it is considered likely that this risk can be mitigated.
![Page 38: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/38.jpg)
/5097656-70-DG017-3.docx 28
The tidal modelling indicates that approximately 60% of the site would meet TAN15 indicative
acceptability criteria for commercial development. A smaller proportion, approximately 50%, of
the site would meet the criteria for residential development which must consider a 100 year
development lifetime.
Access and egress routes are likely to be available via the flood free northern part of the site.
It is likely that if a strategic approach to future flood risk management of the Wentloog Levels, in
line with the proposals included in the Environment Agency‟s Severn Estuary Flood Risk
Management Strategy, then the majority of the site would comply with the indicative acceptance
criteria in TAN15 for all development types.
3.3.8 Study Site 1LGRM
This site is being considered for residential, commercial and industrial development.
The entire extent of the site lies within TAN15 Zone C1. The land is low lying compared with the
rest of the Wentloog Levels, and is bounded in the north by the railway line.
Tidal inundation
The following is a summary of the 2D tidal inundation modelling results.
Current situation
The majority of the site is predicted to remain flood free during a current 0.5% (1 in 200)
annual chance event.
During a 0.1% (1 in 1000) annual chance event, the entire site would be flooded entirely.
Flood depths over the majority of the site would remain below 0.6m with depths reaching up
to 1.0m along the south eastern boundary of the site. Flow velocities over the south eastern
half of the site would exceed 0.15m/s but would remain below 0.3m/s.
Considering climate change and sea level rise allowances to 2085:
The modelling predicts flooding of the entire site during a 0.5% (1 in 200) annual chance
event in 2085, which fails TAN15 A1.14 for all development types based on existing
Environment Agency guidance.
It would be difficult to provide flood free access/ egress to the site as modelling results show
inundation of Heol Las along routes from the north and south.
Considering climate change and sea level rise allowances to 2110:
As for 2085, the model results show complete inundation of the site and access/ egress
routes via Heol Las.
Fluvial flood risk
The site is likely to be flood free during a 1% (1 in 100) chance fluvial event (for a 24 hr storm)
based on simple volumetric filling of the floodplain.
However, the hydraulic capacity and risk associated with the Green Lane Reen which runs
parallel to Heol Las at the eastern boundary of the site will need to be assessed by any site
specific FCA.
Other sources of flood risk
A high groundwater table, identified as a potential residual risk for Study Site 22 at Trowbridge
Mawr, may also affect these low lying sites. This will also need to be addressed as part of any
site specific FCA.
The risk associated with the recorded incidents of sewer flooding as described in Section 3.5.1
(of the SFCA) will also need to be addressed by any site specific FCA.
![Page 39: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/39.jpg)
/5097656-70-DG017-3.docx 29
Site summary
The site is predicted to be completely inundated by a 0.5% (1 in 200) annual chance tidal event
considering both 75 and 100 year periods.
Without a strategic option to maintain the current standard of service of the Severn Estuary
defences into the future, it is unlikely that this risk could be mitigated to provide compliance with
TAN15 indicative acceptability criteria for any of the development types proposed.
It is likely that a strategic approach to future flood risk management of the Wentloog Levels, in
line with the proposals included in the Environment Agency‟s Severn Estuary Flood Risk
Management Strategy, would result in the majority of the site complying with the indicative
acceptance criteria in TAN15 for all development types.
3.3.9 Study Site 106LGEM
Industrial and retail uses have been proposed for this site.
Site 106 lies within TAN15 Zone C1. The site is composed of two parts, one north and one south
of the railway embankment. Both parts of the site are low lying compared with the rest of the
Wentloog Levels.
Tidal inundation
It should be noted that the rail line has been assumed to provide an effective defence against
tidal inundation for areas to its north. This would need to be confirmed by a site specific FCA.
The following is a summary of the 2D tidal inundation modelling results.
Current Situation
The great majority of the site is currently flood free for the 0.5% (1 in 200) annual chance
tidal event. Some limited localised flooding is indicated for around drainage channels in the
very south of the site.
During a 0.1% (1 in 1000) annual chance event, the majority of the site south of the rail line
would be flooded. Approximately 10% of the part of the site north of the rail line would be
inundated. Flood depths remain below 0.6m, and flow velocities would be less than 0.15m/s
over the majority of the flooded areas.
Considering climate change and sea level rise allowances to 2085:
The site south of the rail line would be completely inundated during a 0.5% (1 in 200) annual
chance tidal event.
During the same event, approximately two-thirds of the site area north of the rail line would
be flooded.
In the event of a flood, an access/ egress route to the northern part of the site that meets the
indicative acceptance criteria detailed in TAN15 would be available via Fortran Road. .
Fluvial flood risk
The entire area of this site area is likely to be flood free during a 1% (1 in 100) chance fluvial
event (for a 24 hr storm) based on simple volumetric filling of the floodplain.
However, the hydraulic capacity and risk associated with the reen running along the western
boundary of the northern part of the site will need to be assessed by any site specific FCA.
Other sources of flood risk
A high groundwater table, identified as a potential residual risk in Study Site 22 at Trowbridge
Mawr may also affect this low lying site. This will also need to be addressed as part of any site
specific FCA.
The risk associated with the recorded incidents of sewer flooding as described in Section 3.5.1
(of the SFCA) will also need to be addressed by any site specific FCA.
![Page 40: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/40.jpg)
/5097656-70-DG017-3.docx 30
Site summary
A large portion of the site north of the rail line and all of the site area south of the rail line are
predicted to be inundated by a 0.5% (1 in 200) annual chance tidal event by 2085. Without
mitigation, these areas fail A1.14 of TAN15.
The remaining portion of the site will be flood free during an event of this probability and comply
with TAN15 acceptability criteria and Environment Agency guidance for non residential
development.
It may be possible that mitigation measures could result in more of the site being flood free over
the development lifetime. A site specific FCA will be necessary to investigate the flood risk
posed by the reen draining along the western boundary of the site and to suggest measures for
mitigating this risk.
It is recommended that site specific FCAs consider the viability of the following mitigation
options:
Ground raising to reduce flooding to site areas with compensatory ground lowering in other
areas;
Reducing the probability of breach through reinforcement of the coastal defences;
Culvert replacement/improvement;
Provision of groundwater drainage measures; and
Provision of detailed flood management plan including flood warning system and emergency
evacuation procedures.
To achieve any significant increase in the area complying with TAN15, a strategic scheme to
reinforce the Severn Estuary defences is likely to be required consistent with proposals
contained in the Environment Agency‟s Severn Estuary Flood Risk Management Strategy.
3.3.10 Study Site GTechPk
The Green Technology Park site is bounded to the north by the main London to Swansea rail line
and to the south by Wentloog Avenue. It lies within TAN15 Zone C1 and is almost 1km from the
coastal frontage.
The proposed use for this site is employment.
Tidal inundation
The 2D tidal inundation modelling results are described below.
Current situation
The site is flood free for a 0.5% (1 in 200) annual chance tidal flood event.
Modelling indicates that a 0.1% (1 in 1000) annual chance event would flood 70% of the
site‟s area, with maximum depths of flooding being less than 0.6m over most of this area.
Some deeper flooding is associated with existing drainage channels. Flood flow velocities
would generally remain below 0.15m/s.
An existing access route from Trowbridge Road over the rail line could provide access to the
northern, flood free portion of the site.
The main access/ egress route via Wentloog Avenue is flood free for the great majority of its
length during a 0.1% (1 in 1000) annual chance event. However, high velocities and depths
exceeding TAN15 indicative criteria affect parts of this route. It is considered likely that
mitigation of this risk on these short sections of road could be achievable through the raising
of road levels and alterations to culvert arrangements under the road. The feasibility of
such measures would need to be explored as part of any site specific FCA.
![Page 41: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/41.jpg)
/5097656-70-DG017-3.docx 31
Considering climate change and sea level rise allowances to 2085:
The majority of the site area is flooded by a 0.5% (1 in 200) annual chance tidal event. Only
a small area at the northern edge of the site would remain flood free.
By 2085, as indicated in Section 3.3.0, the main off site access/egress route via Wenloog
Avenue will not be passable during 0.5%(1 in 200) events. Reliance on this route alone
would fail TAN15 A1.12.
An access/ egress route for this site could be possible north via the existing rail line
overpass to Trowbridge Road. This would allow access to the site under all flood conditions
and so comply with TAN15 A1.12. The viability of this route would need to be confirmed as
part of a site specific FCA.
Fluvial flood risk
The site is not considered to be at risk from fluvial flooding.
Other sources
A site specific FCA will need to give adequate consideration to the management of surface water
runoff, although the risk from this source is considered to be low.
Site summary
Our analysis indicates that the site is impacted by the combined effects of overland flows from
the breach locations southwest and east of the site (Referenced SR1-0 and SR1-2 on Drawing
5097656/ RCF/ 120), Appendix B.
The site can be broadly divided into northern and southern areas based on compliance with or
failure to meet TAN15 indicative acceptability criteria.
The small area towards the northern edge of the site lies outside the 0.5% (1 in 200) tidal flood
extent over the 75 year period to 2085. Development of this part of the site should be achievable
in compliance with TAN15. This assumes that safe access and egress route can be
demonstrated to be maintained in the event of a flood.
However, the great majority of the site will be within the 0.5% (1 in 200) annual chance tidal flood
boundary by 2085 and so without mitigation would fail A1.14 of TAN15. It may be possible to
achieve compliance for at least part of this area through ground raising and compensatory
lowering in other parts. This would need to be achieved without affecting local overland flow
paths to avoid increasing flood risk elsewhere.
The strategic reinforcement of the Severn Estuary defences proposed as part of the Environment
Agency‟s Severn Estuary Flood Risk Management Strategy would provide mitigation of the tidal
risk and would increase developable area. This would require a strategic option to defend the
existing properties in the Wentloog Levels in general.
3.3.11 Study Site Wentloo_ii
This study site has been identified for potential commercial and industrial development and lies
south of the rail line and east of the proposed Green Technology Park to the west of study site
Wentloo_iii. The site is located within TAN15 Zone C2. The site boundary is 800m from its
closest point to the location of the coastal frontage assessed as at risk from breach.
Tidal inundation
The results of the 2D tidal inundation modelling are summarised below.
Current situation
The site is predicted to be flood free during a 0.5% (1 in 200) annual chance tidal event.
A small localised area of the site would be flooded during a 0.1% (1 in 1000) annual chance
event. Depths and velocities would remain within TAN15 indicative acceptance criteria
![Page 42: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/42.jpg)
/5097656-70-DG017-3.docx 32
The main access/ egress route via Wentloog Avenue is flood free for the great majority of its
length during a 0.1% (1 in 1000) annual chance event. However, high velocities and depths
exceeding TAN15 indicative criteria affect short sections of this route. It is considered likely
that mitigation of this risk on these short sections of road could be achievable through the
raising of road levels and alterations to culvert arrangements under the road. The feasibility
of such measures would need to be explored as part of any site specific FCA.
Considering climate change and sea level rise allowances to 2085:
Approximately two-thirds of the site would be flooded during a 0.5% (1 in 200) annual
chance tidal event. The flood free areas would occur as isolated islands scattered across
the site.
As described for Site 74, existing access/ egress route to the west of the site via Wentloog
Avenue will be completely inundated by a 0.5% (1 in 200).
A potential emergency access/ egress route to flood free land may be available via an
existing rail overpass to Trowbridge Road, located north of the Site GTchPk.. This may
require crossing third party land.
Other sources of flooding
Flood risk to the site from other sources is considered to be low.
Parts of the site are indicated to have a high risk score from as a result of the surface water
runoff screening. Although the area is fairly flat, it is heavily developed for industrial use and has
large areas of hard-standing which can generate significant runoff. However, it is considered
that the management of surface runoff through SuDS should be achievable for any new
development.
Site summary
The majority of the site fails to comply with TAN15 guidance. The main access and egress
routes to those parts of the site which remain flood free for 0.5% (1 in 200) chance events to
2085 would be flooded. It is possible that alternative access may be possible via an existing rail
overpass to Trowbridge Road (Figure 3-2). The viability of this route will need confirming. It is
likely that without mitigation the route to this overpass would not remain operational under all
flood conditions and so fail A1.12 of TAN15. Access and egress in line with TAN15 may prove
problematic.
If the access problems can be overcome TAN15 criteria may be met for parts of the site
considering the following measures to mitigate the risk.
Ground level raising with lowering of levels elsewhere to compensate for loss of flood
storage , may achieve some increase in site areas flood for a 0.5%(1 in 200) event by 2085.
All options to manage the risk of flooding should consider a flood management plan within
the site operation plan, which would include a flood warning system and emergency
evacuation procedures.
A new crossing of the rail line could be considered or formalised access to the location of
the existing rail overpass to Trowbridge Road. This would provide emergency access and
egress in the event of a flood event.
A strategic approach to future flood risk management of the Wentloog Levels, in line with the
proposals included in the Environment Agency‟s Severn Estuary Flood Risk Management
Strategy, would result in the majority of the site complying with the indicative acceptance criteria
in TAN15 for all development types.
![Page 43: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/43.jpg)
/5097656-70-DG017-3.docx 33
3.3.12 Study Site Wentloo_iii
This study site is identified for potential commercial and industrial development. It lies south of
the rail line and east of the Wentloo_ii study site and is within TAN15 Zone C1.
Tidal inundation
The results of the 2D tidal inundation modelling are summarised below.
Current situation
The site is predicted to be flood free during a 0.5% (1 in 200) annual chance tidal event.
Approximately 20% of the site would be flooded during a 0.1% (1 in 1000) annual chance
event. Flood depths and velocities would remain below 0.6m and 0.15m/s.
The main access/ egress route via Wentloog Avenue is flood free for the great majority of its
length during a 0.1% (1 in 1000) annual chance event. However, high velocities and depths
exceeding TAN15 indicative criteria affect short sections of this route. It is considered likely
that mitigation of this risk on these short sections of road could be achievable through the
raising of road levels and alterations to culvert arrangements under the road. The feasibility
of such measures would need to be explored as part of any site specific FCA.
Considering climate change and sea level rise allowances to 2085:
The majority of the site would be flooded during a 0.5% (1 in 200) annual chance tidal event.
Without mitigation this fails TAN15 A1.14.
As described in 3.3.0, it is unlikely that off site access and egress via the main routes via
Wentloog Avenue would remain operation under all flood conditions as required
under A1.12 of TAN15.
Other sources of flooding
Flood risk to the site from other sources is considered to be low.
Parts of the site are indicated to have a high risk score from as a result of the surface water
runoff screening. Although the area is fairly flat, it is heavily developed for industrial use and has
large areas of hard-standing which can generate significant runoff. However, it is considered
that the management of surface runoff through SuDS should be achievable for any new
development.
Site summary
With the exception of small islands of flood free areas, the great majority of the site is flooded by
a 0.5% (1 in 200) annual chance event by 2085 and so fails A1.14 of TAN15.
The remaining proportion of the site area which may be developable in line with TAN15 may be
increased through mitigation works. Such works may include raising parts of the site with
compensatory lowering of others. This viability of such measures would need further site specific
assessment. It is likely that the majority of the site would not meet TAN15 indicative acceptability
criteria following mitigation. Access in line with TAN15 A1.12, which requires access and egress
routes for a site remain operational under all conditions, will prove problematic.
Offsite access and egress cannot be demonstrated to be operational under all flood conditions
by 2085. The use of Wentloog Avenue for access/ egress during a flood would be very unlikely,
even for emergency services based on the hazard rating as described in 3.3.0. Alternative
access may be possible via the existing rail overpass to Trowbridge Road, west of the site. This
will require mitigation of the access over approximate 160m between Site Wentloo_ii and Site
GtchPk. This mitigation would most likely require a raised flood free path parallel to the rail line.
Overall, development of even parts of this site in line with TAN15 is likely to be problematic due
to the tidal flood risk.
![Page 44: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/44.jpg)
/5097656-70-DG017-3.docx 34
A strategic approach to future flood risk management of the Wentloog Levels, in line with the
proposals included in the Environment Agency‟s Severn Estuary Flood Risk Management
Strategy, would result in the majority of the site complying with the indicative acceptance criteria
in TAN15 for all development types.
3.3.13 Study Site 3SBR
This study site at Pill Du Farm, Hendre Lane, which is identified for potential residential
development, has not previously been assessed as part of any earlier SFCA.
It lies between the Pill Du Reen to the north and the main railway line to the south in the central
part of the Area A. This site is within TAN15 Zone C1.
Figure 3-3 - Site 3SBR location relative to other candidate sites and railway line
Tidal inundation
The results of the 2D tidal inundation modelling are summarised below.
Current situation
The site is flood free for 0.1% (1 in 1000) annual chance tidal breach events.
Considering climate change and sea level rise allowances to 2085:
The site is flood free for 0.5% (1 in 200) annual chance tidal breach events and is within TAN15
indicative acceptability criteria and Environment Agency guidance for non residential
developments.
Considering climate change and sea level rise allowances to 2110:
By 2110, the modelling indicates that tidal breach events of 0.5% (1 in 200) annual chance would
result in inundation of almost the entire site area and the access routes. The site therefore fails
to meet TAN15 A1.14 for residential development.
Depths of flooding are likely to exceed 0.6m on the access road to the site during a 0.5% (1 in
200) annual chance event.
![Page 45: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/45.jpg)
/5097656-70-DG017-3.docx 35
Mitigation of the tidal risk is likely to require works off site. Raising parts of the site may be
possible. However, without further site specific assessment, it is unclear if compensatory
storage could be achieved within the site boundary.
Other Sources
The site‟s location at the bottom of gentle south sloping land may suggest some susceptibility to
surface runoff from surrounding areas. The surface water flood maps for the area also indicate
this potential for the area surrounding the site. However, the majority of the lies above the area
indicated on the Environment Agency Map of Area Susceptible to Surface Water Flooding
(AStSWF). It is likely that surface water runoff from the north is managed in that developed
areas. The location of the reen immediately north of the site would also serve to intercept runoff
from the north. Management of surface water runoff onto the site will need to be considered as
part of any site specific study, but it is considered likely that this risk could be mitigated. The
flood risk from surface water and fluvial flooding is not anticipated to be significant.
The potential risk from groundwater should be clarified through a site specific FCA. As described
in Section 3.3.2, the adjacent Site 22 has a history of groundwater flooding. However, it is
considered likely that the risk from this source can be mitigated
Site summary
Whilst it is likely that development of the site for non-residential purposes could be achieved, the
proposed development of the site for residential development would require mitigation of the tidal
flood risk over a development lifetime to 2110.
It is likely that mitigation of the risk to the site could be achieved through raising parts of the site.
However, it is unclear if there is sufficient area available on the site to provide sufficient
compensate for the resulting loss of flood storage. Access to the site may
If a strategic approach to future flood risk management of the Wentloog Levels were to be
promoted, in line with the proposals included in the Environment Agency‟s Severn Estuary Flood
Risk Management Strategy, it is likely that the majority of the site would comply with the
indicative acceptance criteria in TAN15 for all development types.
3.3.14 Study Site 55LGR
Trowbridge Road Cardiff, proposed for residential use, lies in TAN15 zone C1. It is located
between Site 21LGR to its east (shown on Figure 3.4, above) and Site 22LGRM to its west.
Trowbridge Road forms the western boundary of the site.
Tidal inundation
Current situation
The modelling indicates that the site lies outside the current 0.1% (1 in 1000) annual chance
flood outline.
Considering climate change and sea level rise allowances to 2110:
The site is not indicated to be affected by tidal breach events of 0.5%(1 in 200) annual chance by
2110.
Other Sources
The site is low lying relative to surrounding areas to its north and northwest. Approximately 30%
of the site is indicated to be potentially at risk of surface water flooding on the Environment
Agency Map of Areas Susceptible to Surface Water Flooding (AStSWF). The ground contours in
the area suggest potential overland flow paths from the developed areas via open space to the
north of the site. It is likely that surface water on Trowbridge Road on the west boundary of the
site will bypass the site.
Mitigation of the risk is likely through the site layout and vertical alignments of the distributor
roads to ensure that overland flows do no impact on existing or new development.
![Page 46: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/46.jpg)
/5097656-70-DG017-3.docx 36
Based on available information, we consider that it is likely that this risk can be managed within
the design of the development layout.
Surface runoff from the development site will need to be managed using appropriate sustainable
drainage systems (SuDS) to restrict runoff as required by section 8.5 of TAN15. If this is not
possible due to existing hydrological regime then attenuation systems will be required to reduce
the surface water discharge to at least Greenfield runoff.
Consideration will need to be given to any existing flow paths onto or away from the site
Site summary
The risk of tidal flooding to the site is considered very low.
Further site specific study will be required to define the risk of surface water flooding. It is
considered likely that the risk to this site can be managed in line with TAN15.
3.3.15 Study Site 56LBR
This site at St John‟s College, Greenway Road, proposed for residential use, lies in TAN15 zone
A, defined as little or no risk of flooding.
Site summary
It is considered likely that this site can be developed in compliance with TAN15. It is unlikely that
a site specific FCA would be required by the Environment Agency.
![Page 47: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/47.jpg)
/5097656-70-DG017-3.docx 37
4. Area G – Junction 33 of M4 The sites in this area were assessed under the previous Phase 2 Report (November 2009). The
assessments presented in this chapter are based substantially on analysis undertaken at that
time. However, the Environment Agency has since released a new Flood Map for Surface
Water (FMSW). The FMSW represents the mechanisms that cause surface water flooding.
Where these maps indicate a risk of surface water flooding which is different to that previously
identified, this is noted. The site references have been changed to those in the 2010 list of
Candidate Sites for the LDP. Where the text previously reported in the 2009 report is repeated
here, it is italicised for clarity.
4.1 Site Description
4.1.1 General Site Description
Area G is mostly located to the North of the M4, at the north western edge of Cardiff, and to the
south of the village of Creigiau. The area is largely rural with a few main roads.
The area is fairly hilly, but the majority of slopes are not steep. There are two disused railway
lines in the area. The area is bounded to the west by the Nant Coslech River and the A4119
Llantrisant Road approximately bisects the area.
4.1.2 Proposed Development
There are two candidate sites identified in the area. They cover areas of 37ha and 89ha
respectively and are on currently undeveloped land.
Site 102LGR borders the south of the existing settlement of Creigiau . Site 46LGRM lies
between the A4119 and the M4 and is the larger of the two sites. The south east of this site
borders the existing development of the services area at the M4, Junction 33. Both of the
candidate sites are located in rural areas away from any significant existing development.
The sites are shown on Figure 4.1 and site details summarised in Table 4-1 below.
Table 4-1 - Area G Candidate Sites Summary
Site ID Name/ Location Existing Land
Use Development Category/ Policy Type
Area(ha)
102 LGR Land South of Creigiau Agricultural Residential and Ancillary Community
37.64
46LGRM Junction 33 Agricultural Mixed Used Development
82.96
![Page 48: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/48.jpg)
/5097656-70-DG017-3.docx 38
Figure 4-1 – Area G Study Site Locations
NANT GLASWG NANT HENSTAFF
NANT COSLECH
![Page 49: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/49.jpg)
/5097656-70-DG017-3.docx 39
4.1.3 Hydrological Situation
Rainfall from the upland hillsides enter a number of ordinary watercourses which have formed
around the village of Creigiau.
The most significant of these are the Nant Glaswg in the east, Nant Coslech in the west and the
Nant Henstaff which runs through Site 102GLR and skirts the western boundary of site 46LGRM.
The latter two watercourses combine before joining the River Ely. Nant y Glaswg joins the Nant
Dowlais before joining the River Ely further downstream.
All of these watercourses are culverted beneath roads and paths in the area, including the M4
motorway, at several locations.
The Environment Agency Flood Risk map shows that the area around the confluence of the Nant
Dowlais and Nant y Glaswg is at risk of flooding. This is not directly within any of the proposed
development sites.
The TAN15 Development Advice Map shows part of the Nant y Glaswg as being in TAN15 Zone
C2 and part of the Nant Henstaff is in TAN15 Zone B.
4.2 Data Review and Analysis
4.2.1 Information Available
A review of the available data has included the following:
TAN15 Development Advice Map;
EA Extreme Flood Outline Map;
DCWW STAM (Solution for Total Asset Management) Database; and
Light Detection and Ranging (LiDAR) data.
Environment Agency Flood Map of Surface Water (FMSW)
4.2.2 Analysis Approach
In Phase 1 of the SFCA all the sites in Area G were categorised as Medium risk due to potential
issues with culverted watercourses and known history of sewer flooding.
The sites fall outside of EA Flood Zone 1, and are in TAN15 Flood Zone A, so a strategic
assessment is considered appropriate at this stage to provide insight into the risks associated
with a development and guidance for the management of these risks.
The strategic assessment included the following:
Check for recorded sewer flooding.
Review of likely overland flow paths using LiDAR data.
Assessment of surface water runoff risk.
Site visit.
The site visit confirmed the initial assessment of medium risk for some parts of the sites, but also
showed that some parts of the sites could be re-assessed to Low risk. No sites were deemed to
be High risk.
4.3 Flood Risk from Main Rivers and Ordinary Watercourses
4.3.1 Flood Risk from Ordinary Watercourses
The EA flood maps do not show flooding for ordinary watercourses. However, some partial
modelling of the Nant Henstaff and the Nant y Glaswg has been carried out by the Waterman
![Page 50: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/50.jpg)
/5097656-70-DG017-3.docx 40
Group for the International Business Park Environmental Statement. This shows the depths of
flooding that could occur in some parts of these watercourses.
Undertaking detailed modelling work to include the remaining sections of watercourse as part of
this study was not considered cost effective given the anticipated level of risk. Therefore, a
simple assessment of the flood risk areas was made with reference to the LiDAR contour data
and an assumed maximum rise in water levels within the watercourses of 3m. This was
considered a conservative estimate and such a rise would not be expected except in extreme
rainfall events concentrated on the watercourse’s catchment.
The combined analysis of existing data and estimated water level rises in the three watercourses
showed the following:
A rise of levels in the Nant Henstaff would affect small parts of the western end of Site 46LGRM.
Also the low central part of site 102LGR could become flooded.
Likewise, a rise in levels in the Nant y Glaswg could result in flooding to the eastern parts of site
46LGRM .
The areas affected are shown on Drawing Number 5097656/RCF/020/B, Appendix B.
4.4 Flood Risk from Sewers, Culverted Watercourses and
Groundwater
4.4.1 Flood Risk from Sewers
Candidate Site 102LGR gives cause for concern in this area.
The STAM database records that the wet well of the Ffordd Dinefwr Sewage Pumping Station
(SPS) regularly becomes surcharged during storm events, spilling via an outfall pipe to the
watercourse nearby. This indicates that the pumping station would be unable to accommodate
additional flows from the proposed development in the area, so alternative drainage
arrangements should be explored.
Near to this pumping station, are three surface water outfalls into the local watercourse which
serve the existing housing development. The head of the watercourse is within Candidate Site
102LGR and it was observed to be in poor condition at the points of discharge, with water
backing up, ponding and causing very wet ground conditions.
Flood reports are limited in this area, with only three isolated incidents reported. A repeat of one
of these, at Cardiff Road, could present a risk to Site 102LGR, as the topography would cause
overland flooding from Cardiff Road into the eastern end of the site.
4.4.2 Flood Risk from Culverted Watercourses
There are 11 culverts that have been indentified within the area the blockage or undercapacity of
which could potentially result in flood risk to proposed development sites. Key culverts and
references used below are shown on Drawing Number 5097656/RCF/020/B.
A full investigation into the hydraulic capacity of the culverts and any regular maintenance
operations has not been undertaken. However, for the majority of the culverts identified it is not
unreasonable to except that due to their limited size blockage may occur during severe rainfall
events and a delay in clearing the blockage may result due to inaccessibility.
The Nant Henstaff is culverted at 4 locations in Area G: at Cardiff Road (H1), beneath the old
railway within Site 102LGR (H2), at the southern edge of Site 102LGR under the A4119 (H3) and
under the M4 at the edge of site 46LGRM (H4).
If culvert H2 beneath the old railway line becomes blocked, water in the Nant Henstaff could
back up and flood part of the eastern end of Site 102LGR, running alongside the railway
embankment. If culvert H3 beneath the A4119 became blocked, rather than flow across the
![Page 51: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/51.jpg)
/5097656-70-DG017-3.docx 41
road, water could flow to the low point at the centre of Site 102LGR potentially resulting in
flooding to part of the site.
There is a risk of flooding to a small part of sites 46LGRM if culvert H4 becomes blocked causing
water to back up upstream.
The Nant y Glaswg is culverted at 3 locations potentially affecting site 46LGRM:
G2 - under the A4119 at the north eastern end of site 46LGRM,
G3 - under Heol Saint y Nyll
G4 under the M4 just to the east of Cardiff West motorway services.
Culvert G2 beneath the A4119 is fairly small. If it culvert blocks, floodwaters flowing across the
road from this location could affect a small area of 46LGRM before rejoining the watercourse.
Access to the culvert under Heol Saint y Nyll (G3) was not achieved during a site visit and its
size is not known. If it were to block a small strip of site46LGRM may become flooded. Water
overtopping the culvert would flow onto the road and rejoin the watercourse upstream of culvert
G4.
The M4 culvert (G4) is very large and unlikely to block. It is contained within a well defined
valley, so water would not flow far from the current route and no flood risk to study sites has
been identified from this culvert.
4.4.3 Flood Risk from Groundwater
Susceptibility to groundwater flooding was not included as a part of this assessment. Risks
associated with groundwater should be investigated as part of site-specific FCAs.
4.5 Flood Risk from Surface Water Runoff
Surface water runoff was analysed using a number of different methods which sought to
complement each other and give a comprehensive overview of the flood risks. Following the
overview assessment of surface water runoff potential, included in Figure 4.2 below, LiDAR and
OS Mastermap data was reviewed to determine other potential flood risks and likely overland
flow directions resulting from any surface water runoff in the area. A site visit was undertaken to
confirm conclusions of the desk study.
In updating the assessments of these sites for 2010 list of candidate sites, for this current report,
the FMSW has been referred to. Where these maps indicate a risk of surface water flooding
which is different to that previously identified, this is noted in the site summaries below.
A significant number of sites are adjacent to already built-up residential areas and it is
anticipated that runoff from surrounding areas is already controlled by local surface water and
highway drainage systems. However the site areas are mainly rural undeveloped land and
without mitigation any development will result in increase runoff from the site itself. The flood risk
may be considered minimal providing an assessment of increased runoff rates from proposed
development is made and managed to avoid adverse impacts to both the new development and
existing properties in the area.
![Page 52: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/52.jpg)
/5097656-70-DG017-3.docx 42
Figure 4-2 – Area G Surface Water Runoff Potential
![Page 53: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/53.jpg)
5097656-70-DG017-3.docx 43
4.6 Summary of Flood Risk and Management
4.6.1 Study Site 102LGR
The land located to the South of the village of Creigiau lies adjacent to the Ffordd Dinefwr estate.
The site is currently rolling grassland with some minor water courses crossing it.
There is a risk of flooding from surface water runoff from the north, particularly around the centre
of the site as most flows would gravitate to this area, although the local watercourses are likely to
convey any surface flow away from the site. The western half of the site slopes away to higher
ground from its centre and therefore is not at risk from surface water flooding. The eastern tip of
the site has a small risk of some flooding from surface water runoff from the road.
A risk of flooding to the site from sewers has been identified. There are reports of the Ffordd
Dinefwr sewage pumping station surcharging regularly and spilling to the watercourse at the
centre of the site; this could affect the proposed development. A manhole in the road at the
eastern end of the site has also previously been surcharged. If this was repeated flow would be
likely to gravitate on to the site.
Three culverts have been identified on the site (H2, H3, and U2); there is a risk of some localised
flooding to small areas of the site if any of these were to become blocked. Due to the
topography it is likely the worst affected area would be the centre of the site as flows would
gravitate here and along the edge of the railway embankment as this would enable flows to pond
there. This correlates with the area indicated to be at risk on the FMSW.
The site specific FCAs will need to give adequate consideration to the management of sewer
overflows and flooding adjacent to the watercourses. Options to mitigate flood risk should also be
investigated within the site specific FCA, including:
Avoiding development within the central part of the site;
Designating areas deemed to be at risk of surface water flooding as storage/ attenuation
ponds; and
Improving the drainage channels and culverts on the site to be able to convey flows and
reduce the risk of blockage.
Overall, a moderate level of flood risk has been identified for this site. However successful risk
mitigation is anticipated to be possible and no significant difficulties are expected in the
development of these sites with respect to flood risk.
4.6.2 Study Sites 46LGRM
The area of Site 46LGRM is currently rolling grassland and woodland.
Throughout the majority of the area the risk of surface water flooding is considered low as there
are no significant areas where water would runoff onto the site without being intercepted by
watercourses. Parts of the sites are located at a lower elevation than the adjacent motorway
embankments. If the motorway drainage infrastructure was poorly maintained then runoff onto
these sites could result. However, the risk of this being the case is considered low.
Analysis indicates there is a significant risk of some areas of the site flooding from watercourses.
In the northwest of the site, an area upstream of a pond on a tributary stream of the Nant
Henstaff could flood. If the culverts on the Nant y Glaswg (G2, G3) became blocked, areas of
the site in the shallow valleys of the watercourse would flood, affecting small parts of the north
east and east of the site. A site-specific FCA will be required in order to identify options to
confirm and manage the risk of flooding from these watercourses.
However, the areas at risk of flooding from watercourses make up a very small proportion of the
total site and it is thought that the primary means of mitigating against flood risk is to avoid
development in those areas affected. In addition other measures such as flood defences, culvert
improvements and site landscaping could be investigated to reduce the risk.
![Page 54: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/54.jpg)
5097656-70-DG017-3.docx 44
It is likely that as indicated on the FMSW that surface water flood risk is likely to be limited to the
areas immediately adjacent to the streams and watercourses which currently drain the site
Development of the site is anticipated to be possible within TAN15 guidance.
![Page 55: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/55.jpg)
5097656-70-DG017-3.docx 45
5. Area H – Cardiff West Central, Taff &
Ely
5.1 Site Description
5.1.1 General Site Description
Area H has been defined by the extents of the flood plains of the River Taff and the River Ely
which reach upstream from Cardiff Bay to Llandaff Weir (NGR ST 153784) and the A4232 bridge
crossing (NGR ST 111762), respectively. The area covers significant residential areas of Cardiff
including Grangetown, Riverside, Canton and Ely. The town centre is located to the east of the
River Taff, and to the southwest are the industrial areas of Leckwith and Penarth Moors.
Land between the two rivers is mostly flat and lies at a level of less than 10m AOD. South and
west of the River Ely the ground rises and is less developed with significant areas of open fields
and woodland.
The rivers both flow southeast into Cardiff Bay. The freshwater bay was created by the
construction of Cardiff Bay Barrage, which was completed in 2001. The tidal effects on the rivers
are restricted by the water levels in the bay. The Bay level is controlled by sluice gates in the
barrage and typically the level is maintained at 4.5mAOD.
5.1.2 Proposed Development
A significant number of development sites originally considered for the SFCA within the Taff/Ely
area are no longer candidate sites for the current Draft LDP. However, the current candidate
sites include some extensive new residential areas proposed on undeveloped land in Ely to the
west of the area. These sites are on land south of the river and border existing residential
developments. Another cluster of sites proposed for mixed uses are located in the Ely Bridge
area, a notable example is the large site of the former Arjo Wiggins Paper Mill.
Several large sites have been identified for development in the existing industrial/ commercial
areas of Leckwith and Grangetown north of the River Ely and generally south of the railway
which runs southeast to Penarth.
The proposed development sites are shown on Figure 5-1 and details of the sites are
summarised in Table 5-1 below.
![Page 56: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/56.jpg)
5097656-70-DG017-3.docx 46
Figure 5-1 – Area H Study Site Locations
(EAW 0.1% or 1 in 1000 annual chance flood outline also shown in blue)
© Crown Copyright. Cardiff County Council, 100023376 (2011)
![Page 57: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/57.jpg)
5097656-70-DG017-3.docx 47
Table 5-1 - Area H – Summary of Study Sites
(Details extracted from the Candidate Sites Register, 2010. Cardiff Council)
Site ID Name/ Location Existing Land Use
Development Category
Area (ha)
8LGR West of Clos y Cwarra, Michaelston-super-Ely, Cardiff
Grazing for horses Residential 1.6
16LBR Ely Bridge, Western Business Centre, Cowbridge Road East
Unused Residential/
commercial/ retail/ community uses
22.3
17LGR Ely Bridge Farm, Dyfrig Road, Ely.
Unused Previously used agriculturally
Residential 0.7
31LBEM Land at Brindley Road, Leckwith, Cardiff
Nil use Employment uses 8.0
32LGR Land at Michaelston Road, Cardiff
Combination of pasture and partly wooded. Former quarrying and tipping site
Residential & Strategic Open
Space 9.8
36LBR Former Lansdowne Hospital Site, Sanatorium Road, Canton, Cardiff, CF11 8PL
Redundant hospital buildings and ancillary offices
Residential 1.5
52LBR Paper Mill Road, Cardiff , CF11 8PH
Vacant warehouse premises
Residential 0.8
61LBRM Penarth Road Car Park Site (adjacent to Cardiff Central Railway Station) of which includes Riverside Sidings/Semaphore House
S.A. Brain & Co Ltd land: Brewery
Railway land and station car park
3.0
62LBR Land adjacent to Clive Lane Operational railway land
Railway land 2.9
70LBEM Central Square Bus station / highway
Commercial/ Public Transport
Interchange 1.5
75SBR Land East of Great House Farm, Michaelston Road
Curtilage of Great House Farm House
Residential 0.2
77LBR Ferry Road, Grangetown, Cardiff
Part of site in operational use for Wales and West Utilities, due to cease.
Residential 11.7
78LBRM Wholesale Fruit Centre Cardiff
Former Wholesale Fruit Centre, Retail Warehouse and small industrial estate.
Residential/ commercial/ employment
7.0
![Page 58: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/58.jpg)
5097656-70-DG017-3.docx 48
Site ID Name/ Location Existing Land Use
Development Category
Area (ha)
83LBRM Former J R Freeman Factory, Penarth Road, Cardiff
Commercial unit – former J R Freeman cigar factory
Mixed use – Employment/
Retail/ Residential 3.8
96LGED Land adjacent to Llandaff Campus to river bank and rear of campus
Greenfield Educational 0.72
111LGR Land north west of Great House Farm, Michaelston Road
Nil Residential 0.5
5.1.3 Hydrological Situation
The Taff and Ely area is relatively flat and is drained by the two main rivers. The River Taff has a
catchment area of 510 km2 upstream of Cardiff Bay, and the River Ely has a catchment area of
163 km2. A number of ordinary watercourses are present in the area, many of which are partly
culverted under the densely developed areas of the city.
Environment Agency Flood Risk and TAN15 Development Advice Maps show that a significant
area is at risk of flooding. However, a number of flood defences have been constructed along the
River Ely to provide protection from fluvial events, and the Cardiff Bay Barrage has provided
significant enhanced protection from tidal flooding. As a result the majority of the city centre area
is classified as TAN15 Zone C1 (see definition in Section 2.1).
5.2 Data Review and Analysis
5.2.1 Information Available
A review of the available data has included the following:
TAN15 Development Advice Map;
EA Extreme Flood Outline Map;
DCWW STAM (Solutions for Total Asset Management) database;
DCWW Cardiff West and Cardiff Central InfoWorks sewer model;
Environment Agency 2-dimensional Ely/ Taff model (developed post-Phase 1 as part of the
Ely TUFLOW model update, July 2009);
Light Detection and Ranging (LiDAR) data.
5.2.2 Analysis Approach
The majority of the candidate sites identified within Area H fall within the low-lying areas adjacent
to the main rivers.
Of the sites assessed in Phase 1 of the SFCA (see Section 2.2 and Section 1.3.1), 56 fell within
EA Flood Zone 2 and were categorised as High Risk. A more detailed level of assessment was
proposed to determine the flood risks for these sites compared to those identified as low or
medium risk during Phase 1.
2D hydraulic model of the combined lower Ely & Taff Rivers
The detailed assessment made use of the 1S-2D ISIS-TUFLOW Ely/ Taff model which had
previously been completed by Atkins for the Environment Agency, as detailed in Section 5.3.1.
The existing EA model deals largely with current-day flood scenarios; therefore, additional model
![Page 59: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/59.jpg)
5097656-70-DG017-3.docx 49
runs were required to map future flood event scenarios to reflect the effects of climate change
and sea level rises.
The model has been further developed for the SFCA to improve the representation of the
variation in levels in the impounded Cardiff Bay and the effect of this on flood risk upstream on
the two rivers.
Sites to the west, in the Ely area, were considered to have a lower risk of flooding. Only one of
the four sites considered within Phase 1, Site 111 (Site Ref. No.72 in SFCA Phase 1 Report),
was specified as Medium Risk due to its proximity to the River Ely and uncertainty with respect to
watercourses and culverts in the area. The other three sites were defined as Low Risk. A
strategic high level assessment was considered sufficient to understand the risks associated with
development in this area and provide initial guidance for the management of the identified risks.
The strategic assessment overlapped with the detailed TUFLOW model and assessment
techniques were applied to all the sites on the perimeter of the area shown to be at risk of
flooding from the Rivers Taff and Ely.
The strategic high level assessment included the following:
Check for recorded sewer flooding;
Review of likely overland flow paths using LiDAR data;
Assessment of Surface Water Runoff Risk; and
Site visit.
5.3 Flood Risk from Main Rivers and Ordinary Watercourses
5.3.1 Flood Risk from Rivers Taff and Ely
Existing Information
Atkins Limited has previously completed on behalf of the Environment Agency8, a combined one
and two dimensional (1D/2D) model of the rivers Taff and Ely using TUFLOW9 modelling
software. The extents of the Lower Ely ISIS-TUFLOW model correspond closely with the
upstream limits of Area H for both the River Taff and the River Ely. Downstream, the model
terminates at the confluences of the rivers with Cardiff Bay. The operation of the barrage was
not included in the model.
Hydrological assessment of the 1% (1 in 100) annual chance event including climate change,
and the current 0.1% (1 in 1000) annual chance event for both the rivers was made as part of the
TUFLOW modelling project. Given the proximity of the two river catchments the simultaneous
occurrence of the extreme events on the catchments is not considered overly conservative.
At the downstream end of both watercourses, the Cardiff Bay Barrage maintains water levels at a
typical level of 4.5m AOD. However, the level within the Bay fluctuates at every tide due to
periods when flows from the Rivers Taff and Ely cannot discharge into the sea, i.e. when tides in
the Bristol Channel exceed a level of 4.5m AOD. Extreme tidal events result in longer tide-
locked periods and when combined with greater flows in the rivers, this can mean that water
levels in the Bay significantly exceed the typical control level.
Although analysis undertaken by HR Wallingford determined that there is no direct correlation
between the occurrence of extreme fluvial events and extreme tidal events10
, various
combinations of tide levels and river flows will result in increased bay levels. Data from this joint
8 River Ely and Tributaries Model Update and Hazard Mapping, Atkins Job Number 5075684, final report reference:
5075684/71/DG/004, July 2009. 9 Area H Update used TUFLOW version 2009-07-AF-iSP, BMT WBM Hydraulics, Australia
10
A new joint probability appraisal of flood risk, P.G. Samuels and N. Burt, published in the Proceedings of the Institution of Civil Engineers Water & Maritime Engineering Journal 154 Issue 2, June 2002.
![Page 60: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/60.jpg)
5097656-70-DG017-3.docx 50
probability report was used to provide the downstream boundary levels (i.e. the levels
representing the levels in Cardiff Bay) for the events previously tested in the Environment
Agency TUFLOW model.
The downstream boundary within the Environment Agency ISIS-TUFLOW model was a fixed
water level derived from this joint probability analysis.
5.3.2 Estimation of the Variation in Cardiff Bay levels during flood events
The effects of future sea level rises on level in Cardiff Bay were considered within the HR
Wallingford analysis.
However, in consultation with the Environment Agency, it was determined that extrapolation of
some of the key assumptions in the paper, without access to the underlying analysis, may lead to
overly conservative estimates of future levels in Cardiff Bay. This would have the knock on effect
of potentially significant over estimation of future flood levels in the lower reaches of the rivers
Ely and Taff.
In addition, the use of a fixed level in the ISIS-TUFLOW hydraulic model may also lead to over
estimation of flood levels, since it effectively assumes a permanent tide lock over the period of
the flood in the rivers. Whilst this conservative approach may be appropriate for flood mapping
areas currently at risk of flooding, it is considered overly conservative in estimating future flood
risk over the 100 year development lifetime.
Model of Cardiff Bay and Sluice Gates
To estimate the variation in the level in Cardiff Bay for design flows in the rivers and coincident
tide levels in the Severn Estuary, a 1D hydraulic model of Cardiff Bay was built using ISIS v3.3
software. This model incorporates the Bay and the operation of the 5 sluice gates in the
Barrage. Fluvial inflows to the model where derived from the outflows at the bottom of the EA
ISIS-TUFLOW model referred to above.
These flood flows were run against a tide curve representing the Mean High Water Spring
(MHWS) tide level downstream of the barrage.
Design event data which had been used to calibrate a previous model of the Bay prepared to
develop the control logic of the gate operation was supplied by the Cardiff Barrage Manager,
together with recorded flood event data from 30 October 2000.
The model was adjusted and considered to give good agreement with this verification and
calibration data. The model under predicts the peak Bay level recorded during the October 2000
event by 120mm.
Figure 5-2 shows the change in Bay level predicted by the model with the actual recorded Bay
levels recorded during the October 2000 event. As well as the difference at the peak, the two
Bay levels lines on the graph demonstrate the characteristic rise and fall in the Bay level with
fluvial inflows and coincident tide levels in the Severn Estuary.
![Page 61: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/61.jpg)
5097656-70-DG017-3.docx 51
Figure 5-2 - ISIS Bay Model - 30 October 2000 flood event
Modelled Bay level compared to recorded Bay level. for recorded fluvial inflows and tide level data
5.9
6.23
0
50
100
150
200
250
300
350
400
450
500
3.25
3.5
3.75
4
4.25
4.5
4.75
5
5.25
5.5
5.75
6
6.25
6.5
6.75
Flo
w/ c
um
ec
Wa
te
r le
ve
l/ m
AO
D
Time hrs
Recorded Sea Level
Recorded Bay Level (enraf)
Model Bay Level Result
Ely flow
Taff flow
The variation in Bay level was tested in the model for the scenarios as summarised in the
following table.
Table 5-2 - Flood event scenarios modelled to derive variations in Cardiff Bay levels
Fluvial Event
(Annual
chance)
Year Peak River
Taff Inflow
(cumec.)
Peak River Ely
Inflow
(cumec.)
MHWS Tide
level
(mAOD)
Resulting
Model Output
Peak Bay
Level (mAOD)
1% (1 in 100) 2010 463 271 6.1 6.550
0.1% (1 in 1000) 2010 1023 262 6.1 6.79
1% (1 in 100) 2085 831 310 6.74 7.25
1% (1 in 100) 2110 808 330 7.1 7.62
5.3.3 Final Flood Estimation on Taff and Ely based on the Variation in Cardiff Bay levels
The Iterative approach to running the two hydraulic models
The two models (the ISIS Bay Model and the Ely Taff TUFLWOW model) could theoretically be
combined. However, to minimise model development time the two models have been
maintained as separate entities.
However, the outflows from the TUFLOW model, which provide the inflows to the Bay model, will
be affected by the downstream boundary applied. The flat downstream boundary in the
TUFLOW model may result in the flows into the Bay being underestimated. To overcome this
problem the following strategy was adopted, based around iterative runs of the two models.
![Page 62: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/62.jpg)
5097656-70-DG017-3.docx 52
Two iterations of the model runs were carried out for each scenario listed in Table 5-2:
1st Run of ISIS Bay model - The inflows to the Bay model for each scenario were derived
from the Ely Taff ISIS-TUFLOW model which had been run with a flat downstream boundary
(i.e. representing a constant water level in the Bay). These inflows were run against a
MHWS spring tide cycle (with climate change applied for the future scenarios).
1st iteration – runs of the TUFLOW model were undertaken using the varying downstream
boundaries derived from the 1st runs of the scenarios in the Bay model.
2nd
Run of ISIS Bay model - The outflows from the TUFLOW model each scenario were then
used as inflows to the Bay model for a second set of runs of each scenario.
2nd
iteration – run of the Ely –Taff Model. The resulting variations in the Bay level from the
1st iterations were smoothed and used as the varying downstream boundary for the final runs
of each scenario in the Ely Taff ISIS TUFLOW Model.
Results
It is the results of this second iteration of the Ely Taff ISIS-TUFLOW model using time varying
downstream boundaries in the Bay that are presented in Drawing No. 5097656/RCF/320 to 322,
Appendix B., which show the flood risk to the candidate sites.
The model results provide a good understanding of the flood depths and velocities likely to be
encountered and enable full assessment of the sites in line with TAN15 guidelines.
Drawing Number 5076243/RCF/320 shows the maximum flood extents for the1% (1 in 100)
annual chance event currently and including climate change allowances to 2085 and 2110.
Appendix 1.14 of TAN15 requires that development sites remain flood free for the 1% event over
the lifetime of the development.
For the 0.1% (1 in 1000) annual chance event indicative limits on the maximum depth and
velocity of flooding are given in Appendix A1.15 of TAN15 (see Section 2.1). Drawing numbers
5076243/RCF/321 and 322 show, respectively, the maximum flood depths and corresponding
velocities predicted by the Ely/ Taff ISIS-TUFLOW model for the this event for the current day as
required by current Environment Agency guidance.
Please note that the results from this model should not be used to assess flood risk to areas
other than the candidate sites listed in Table 5.1. Checks have been undertaken and
amendments made to the digital terrain model in the area of the sites to reflect physical features
which impact on overland flow paths. Similar assessments would need to be undertaken before
the model for the detailed assessment of the other sites.
Main Flood Mechanisms indicated by the modelling relative to the candidate sites.
The results indicate:
1% (1 in 100) annual chance event - current day
Flooding occurs initially from overtopping from the River Taff at Blackweir into Pontcanna Fields
and into Bute Park on the Left Bank. Flooding from the River Ely occurs at Ely Bridge flowing
down Lansdowne Road into the Victoria Park area.
1% (1 in 100) annual chance event - 2085
Simulations indicate that by 2085 a 1% (1 in 100) annual chance event would extend south from
Pontcanna via Llandaff and into the roads of Canton. Bute Park on the left Bank of the Taff
would be completely inundated. Direct overtopping of the right bank of the Taff into the Riverside
area would occur upstream of the Castle Street Bridge. Direct overtopping from the River Ely
would extend over the southern half of Site 16LBR.
The overland flows from the two rivers would not meet under this scenario.
![Page 63: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/63.jpg)
5097656-70-DG017-3.docx 53
1% (1 in 100) annual chance event - 2110
By 2110 the increased levels in Cardiff Bay due to sea level rise in the Severn Estuary would
result in flooding extending further across some areas of Cardiff. Notable areas are Riverside on
the right bank of the Taff and increased extents around Victoria Park. Flooding from the Ely
would extend onto Site 36LBR. Some overtopping of the left bank of the Taff south of the rail
station is also indicated for this scenario, although the nearest candidate site (Site 61LBRM)
would not be inundated.
0.1% (1 in 1000) annual chance event – current day
This event results in the most extensive flooding of the scenarios tested with overland flows from
the Taff and Ely meeting and interacting.
Simulations suggest that the flood extents include the whole of Pontcanna and Riverside, with
overland flows extending below the main railway line into Grangetown and parts of Leckwith
Moors.
Table C2 in Appendix C details the depths and areas of flooding for each study site during this
event.
Discussion of the individual sites is included in Section 5.7 below.
5.3.4 Flood Risk from Ordinary Watercourses
A number of ordinary watercourses flow into the main rivers. Of particular note is the Nant y Plac
on the western edge of Site 111LGR. This is a relatively minor watercourse and no hydraulic
model exists to accurately determine flood extents. However, the watercourse is located within a
narrow valley and the adjacent site area slopes steeply up away from both the Nant y Plac and
the River Ely to the northwest. If the Nant y Plac was to overtop its banks flow is predicted to be
contained within the narrow valley and quickly enter the main river; flooding would only affect the
very edge of the site, if at all.
At a strategic level, no other proposed development sites have been identified as at risk from
ordinary watercourses, although this will need to be confirmed within site-specific FCAs.
5.4 Flood Risk from Sewers, Culverted Watercourses and
Groundwater
5.4.1 Flood Risk from Sewers
The DCWW STAM database records one hundred and twelve DG5 sewer flooding incidents in
Area H.
Approximately 50% of these incidents occurred on 4th July 2001. The storm was assessed to
have an annual exceedance probability of 1.6% (1 in 60).
The majority of the reported incidents occurred in St Mary Street, Royal Arcade, Morgan Arcade
and Wyndham Arcade. No further developments are proposed in the vicinity of the retail
premises affected, but flooding was also reported at isolated properties at the southern end of
Clive Street. The nearest candidate sites are the proposed residential developments at Clive
Street and Ferry Road (sites 62 and 77). The potential adverse impact of these developments
on existing sewer flood risk should be investigated further as part of site specific assessments.
Flood incidents were reported on consecutive days at six properties on Station Terrace and six
properties in Redcliff Avenue. These are close to the extensive housing developments proposed
at the former Arjo Wiggins Paper Mill and adjacent sites (16, 52 and 36). Further investigations
are recommended when considering development in this area. Other reported incidents are
mostly located along the southwest border of Area H in Ely, and along the railway line heading
northwest.
![Page 64: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/64.jpg)
5097656-70-DG017-3.docx 54
A number of isolated incidents are recorded, but these are either very old or not near proposed
development sites and are not considered to pose significant risks to the proposed
developments.
5.4.2 Flood Risk from Culverted Watercourses
The Rivers Taff and Ely remain in open channel along their entire reach. A number of minor
watercourses flow into them at various points along their length and some of these are culverted
under existing residential and commercial properties, and under roadways. Of particular note are
the culverts under the A4232 which link drainage channels from Study Site 31LBEM to the River
Ely. The potential for flooding due to culvert blockage should be considered if development at the
site is to proceed.
No other culverted watercourses have been identified affecting proposed development sites.
However, should culverts be discovered, it is important to note that Environment Agency policy
generally does not allow development over existing culverts because inaccessibility can
exacerbate problems should they develop in the future.
5.4.3 Flood Risk from Groundwater
Susceptibility to groundwater flooding was not included as part of this assessment. The Taff and
Ely CFMP states that groundwater flooding is not considered to be a significant issue within the
catchment.
It is noted that a large groundwater control scheme was introduced as part of the Cardiff Barrage
scheme. There is a groundwater control system built into the Millennium Stadium. There are
other similar schemes dotted throughout the low lying areas, designed to keep the groundwater
levels low.
It is not perceived that groundwater flooding would be a significant issue for the study sites.
However, risks associated with groundwater should be investigated as part of site-specific FCAs.
It is recommended that assessments should be made of additional control measures which may
be required for specific sites.
5.5 Flood Risk from Surface Water Runoff
Surface water runoff was analysed using a number of different methods which sought to
complement each other and give a comprehensive overview of the flood risks.
Initially a broad overview of risks was provided using a GIS technique; explanation of the
technique is included in Section 2.5.7. Figure 5-3 below shows the results of the surface water
risk screening analysis.
In addition to the above screening assessment a qualitative assessment of the likely flow paths
of surface water runoff was undertaken. This was based on a review of the contours derived
from LiDAR and using OS Mastermap to assess ground features which might serve to confirm
conclusions of the desk study; particular attention was given to those sites to the West of Area H
and those that were not considered at risk from flooding from the River Taff or River Ely.
![Page 65: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/65.jpg)
5097656-70-DG017-3.docx 55
Figure 5-3 - Area H Map of Surface Water Runoff Potential Screening Score
110011LLBBEEMM
![Page 66: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/66.jpg)
5097656-70-DG017-3.docx 56
A significant number of sites fall within built-up residential areas and it would normally be
anticipated that runoff within such areas is already controlled by local surface water and highway
drainage systems. Unfortunately, a comprehensive database of surface water flood incident does
not yet exist and, due to the historic piece-meal development of the drainage system in parts of
the city, there is a lack of understanding of the operation of surface water drainage systems and
the associated risk of flooding. In the absence of a more detailed investigation into the
management of surface water, assessment of the risk has been made on the basis of site
observations and standard assumptions.
Walkover surveys of the sites in Michaelston-super-Ely confirm the GIS assessment that minimal
risk of flooding from surface water runoff is anticipated for the majority of these sites providing
that surface water drainage facilities in existing upslope developed areas are of sufficient
capacity. The one exception to this is Site 32LGR, a full discussion of this site is included in
Section 5.6 below.
5.6 Summary of Flood Risk and Management
5.6.1 Site 8LGR, Site 75SBR and Site 111LGR
These sites at Great House Farm lie outside the defined TAN15 DAM Zone C2 and hydraulic
modelling indicates the sites are beyond the 0.1% event boundary. An ordinary watercourse
follows the boundary of Site 8 but is generally down slope from the site. Although the risk from
this source will need to be confirmed as part of a site specific study, it is considered likely that it
could be mitigated.
Flood risk from fluvial sources is considered to be low for these sites and would meet TAN15
guidelines for development.
The three proposed sites border an existing housing development situated on higher ground.
The drainage provision for the existing housing will need further investigation and any new
development in the area will need to consider the risk of surface water runoff and potential
mitigation measures.
Additionally, the runoff from the site itself will need to be managed to ensure no increased risk of
flooding elsewhere. TAN15, Section 8, requires that sustainable drainage systems (SuDS) are
considered for all new development. “Developers need to give good reason why SuDS could not
be implemented. If a conventional drainage system does not improve the status quo, then this
can be a valid reason for refusal of planning”.
Development of the site for housing in line with TAN15 requirements is likely. A site specific
assessment of the management of surface water for any development is recommended.
5.6.2 Site 32LGR
This site is located to the east of Michaelston Road, opposite sites 75 and 111. Although initially
no flood risk was identified from the main watercourses, sewers or surface water runoff , the site
visit brought to light a number of issues requiring further investigation prior to development of the
site.
A spring and small stream within the site will need managing in order to facilitate site
development. Within the southern end of the site a densely overgrown area was fenced off and
carried a sign warning of the risk of Weils‟ Disease. From remote visual inspection it appeared
that the structure was probably an abandoned sewage filter or similar. Further investigation will
be required as part of a site-specific FCA for this site in order to determine the exact purpose of
the structure and the level of flood risk posed by any connected underground pipe network.
Developers will need to satisfy themselves and the planning authority that there are no flood
risks from abandoned pipe work in the area.
Confirmation that ground contamination issues can be adequately addressed will also be
required prior to development of this site; however, since this is not a TAN15 issue it would not
need to be directly addressed in the site-specific FCA.
![Page 67: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/67.jpg)
5097656-70-DG017-3.docx 57
Development of the majority of the site in line with TAN15 requirements is likely to be possible
subject to confirmation by a site specific assessment.
5.6.3 Site 16LBR
The site is understood to have planning permission, subject to the completion of a legal
agreement. Any change in the extant permission will need to reflect the management of the
consequences of flooding in line with current planning policy guidance.
The TUFLOW modelling results show that the northern end of the site is predicted to be flooded
by a current 1% (1 in 100) annual chance event (without climate change). The flood-free area
reduces significantly by 2085, with the majority of the site being inundated by a 1% (1 in 100)
chance fluvial event (approximately 60% by area inundated). The extent of inundation is
indicated to be marginally greater by 2110 as shown on Drawing Number 5076243/RCF/320.
Approximately 30% of the 22ha site is considered to remain flood free over the development
lifetime under current conditions. The majority of the site, therefore, would fail A1.14 of TAN15
without mitigation of the risk.
Modelling of the 0.1% (1 in 1000) annual chance event indicates that depths over the majority of
the site will be below 0.6m. However, over approximately 1.0 ha at the north and 1.8ha at the
south eastern end of the site flood depths will be over 1.0m. Flood depths will also exceed 1.0m
on the land to the south of the site and on land to the north east towards Victoria Park. The
potential access/ egress routes for any proposed development would need to take account of
this flood risk to the surrounding areas.
Over the majority of the site water velocities during a 0.1% chance event would be within the
indicative acceptance criteria given in A1.15 of TAN15. However, velocities would exceed those
acceptable limits at the northern tip of the site and over the entire portion of the site area on the
right (west) bank of the River Ely.
A number of flood risk mitigation options may exist for this site that could facilitate more
extensive development. A detailed FCA would be required to confirm the viability of options, but
the following potential solutions could be considered:
1) Provision of detailed flood management plan including flood warning system and emergency
evacuation procedures;
2) Ground raising within the central section of the site with lowered „pond‟ sections provided so
overall flood water storage volumes are not altered, and impacts on adjacent land is
minimised;
3) Ground raising for the whole site and construction of drainage channels to divert floodwater
flow volumes towards currently undeveloped land to the south of the site;
4) Provision of flood defences along the banks of the River Ely.
From initial consideration of the options it is anticipated that a flood management plan would be
unlikely to be sufficient to mitigate the risks as a stand-alone option but would need to be
combined with civil engineering works. Ground raising is likely to be most viable, although
compensatory storage volume would need to be provided (most likely within the site). TAN15
requires that development proposals should not cause flooding elsewhere.
The option to provide improved flood defences to the River Ely may be difficult to achieve without
increasing flood risk elsewhere. It is also worth noting that flooding to the south east of the site
results from overland flows from the River Taff merging with flooding from the River Ely. The
provision of a defence barrier along the River Ely may result in the restriction of River Taff flood
flow paths and increase flood risk to other sites.
Detailed two-dimensional modelling would be required to assess the impacts on adjacent land of
any of the proposed mitigation options that involve physical changes.
![Page 68: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/68.jpg)
5097656-70-DG017-3.docx 58
Should development of any part of the site be proposed, the detailed FCA would also be required
to demonstrate acceptable access/ egress routes are available for emergency services during a
flood event. Accident and Emergency facilities in Cardiff are located to the North of the River
Taff in the Heath area, access to which would potentially require crossing flooded areas.
The FCA should also address the potential flood risk from sewers, as identified in Section 5.4.1
above. The cause of reported flood incidents should be determined and if necessary, measures
to manage the future risk identified before development in the vicinity proceeds.
5.6.4 Site 52LBR
This site lies immediately to the east of Site 16LBR, Papermill Road being located between two
railway lines.
The site is currently considered to be flood free for a 1% (1 in 100) annual chance event. Taking
climate change to 2085 into account, an event of this probability will result in inundation over
approximately 30% of the 7ha site area. The extent of this event by 2110 will be little changed.
The whole site will be flooded by a 0.1% chance event. Depths of flooding will be less than 0.6m
over approximately 55% of the total site area. Depths will exceed 0.6m but less than 1.0m over
35% of the area. Depths exceed 1.0m over 10% of the site area. Corresponding velocities will
be less than 0.15m/s over the majority of the site.
Access south along Papermill Road via the rail underpass to Sanatorium Road will also be
flooded during a 1% chance event by 2085. During a current 0.1% (1 in 1000) annual chance
fluvial event, the maximum depths on the road would be less than 0.6m on the road immediately
adjacent to the site, but would exceed 0.6m at the rail underpass onto Sanatorium Road. The
velocities during this event are indicated to be very high on the approach to the rail underpass, in
excess of 0.45m/s. There are currently no alternative access routes. The site‟s location between
two railway means that options are very limited.
Under existing conditions, without mitigation, safe access to the site cannot be demonstrated to
be maintained in the event of flooding over the 75 year development lifetime recommended by
the Environment Agency for commercial developments. The flood risk to the site itself complies
with the TAN15 indicative criteria for retail and commercial development over approximately 55%
of its area.
Since flooding of the site and access routes originates from both the south east and northwest of
the site, hard engineering solutions are likely to be challenging and costly. These might include
improved defences to the River Ely, but for the reasons given above in relation to Site 16LBR,
the feasibility of this option will need extensive further appraisal. Options within the site layout
itself would not mitigate the flood risk associated with the access.
Any options to mitigate the risk would include a flood management plan.
Future development of the site would need to demonstrate that the consequences of flooding to
the site would not be exacerbated compared to the existing site use. Based on the existing flood
risk and mitigation options, significant re-development of this site in line with TAN15 would be
extremely challenging.
5.6.5 Site 36LBR
The site is considered to be flood free during a 1% (1 in 100) annual chance event including
climate change allowance up to and including 2085. By 2110 a 1% (1 in 100) chance event
would inundate part of the west end of the site.
The entire site would be inundated by a current 0.1% (1 in 1000) chance fluvial event, with
depths exceeding 0.6m over approximately 50% of the site which fails TanAN15 A1.15 for
residential development. Depths exceed 1.0m over approximately 30% of the total site area,
which fails TAN15 for all development types. The corresponding velocities would be less than
0.15m/s over the whole site.
![Page 69: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/69.jpg)
5097656-70-DG017-3.docx 59
The existing road access to the east of the site will be flooded by a 1% (1 in 100) chance event
by 2085. Flood free access will not be maintained to the site and so fails TAN15. In addition, a
current 0.1% (1 in 1000) chance event would result in velocities exceeding 0.45m/s on the main
access routes east, crossing the railway lines via Sanatorium Road and Leckwith Road and
south via Lawrenny Avenue. These fail TAN15 criteria for safe access and egress.
Although the area of existing housing immediately to the south would remain flood free during a
1% (1 in 100) chance event to 2110, access to the wider area east of the rail lines would be
inundated by the 1% chance event by 2085.
The site, therefore, fails TAN15 criteria. If development is to proceed, measures to mitigate the
risk will be required to comply with TAN15 guidance. Such mitigation measures could include
engineering works to improve the flood defence to the River Ely. However, such mitigation is
unlikely to be straight forward and may prove problematic. Mitigation of the risk through a flood
management plan for non residential development may be less problematic than mitigation to
standards required for residential development.
Any FCA for this site will also need to address the potential flood risk from sewers, as identified
in Section 5.4.1 above. The cause of reported flood incidents should be determined and if
necessary, measures to manage the future risk identified before development in the vicinity
proceeds.
5.6.6 Sites 31LBEM, 62LBR, 77LBR, 78LBRM and 83LBRM.
Three of these sites; Site 31LBEM, Site 78LBRM and Site 83LBRM are understood to have
planning permission subject to completion of legal agreements. Any future issuing or renewal of
planning consents will need to reflect the management of the consequences of flooding in line
with current planning policy guidance
The five sites within the Leckwith Industrial Estate and Penarth Moors areas are shown to remain
flood free for a 1% (1 in 100) annual chance event over a development lifetime to 2110.
However, during a more extreme 0.1% (1 in 1000) annual chance event flooding is expected to
affect either parts of the sites themselves or the potential access/ egress routes for the sites.
The velocity of flow would be expected to remain below 0.15m/s over all five sites during a 0.1%
chance flood event.
Site 31LBEM - This site is flood free for 0.1% chance event and flood free access for this site via
Brindley Road and Hadfield Road is considered to be maintained during this event. A risk of
flooding to part of this site from culverts under the A4232 has been identified as noted in Section
5.4.2. Culverts under this road link drainage channels from the site to the River Ely. Although
the extent of flooding from culvert blockage may be considered to be low, the potential frequency
of flooding means that this risk should be addressed by potential developers.
It is considered likely that development of this site can be achieved in line with TAN15.
Site 77LBR – Approximately 50% of the total area of this site located east of the railway line at
Ferry Road will be inundated by a 0.1% (1 in 1000) chance fluvial flood event. Maximum depths
and corresponding velocities over the flooded area would remain within TAN15 criteria for all
development types. The existing access to the site to its northeast, the Ferry Road roundabout,
will be flooded to depths over 1.0m during this extreme event. Works to the roundabout or to
establish alternative routes to mitigate the flood risk to the access route may be feasible. These
would need to be developed as part of a flood management plan for any proposed development.
Few difficulties would be anticipated should a developer propose development of the southern
end of the site providing it is demonstrated within the FCA that the risk of sewer flooding (raised
by incidents reported in nearby Clive Street for the 4th July 2001 event) can be adequately
managed. Suitable access/ egress routes will also need to be identified.
Site 62LBR – The model results indicate that this site to the west and parallel with Clive Street
would remain flood-free during a 0.1% (1 in 1000) chance flood event. However, the potential
![Page 70: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/70.jpg)
5097656-70-DG017-3.docx 60
access routes to east and south will be flooded to depths exceeding 1.0m. Depths of flooding
exceed 1.0m on the roundabout to Ferry Road at the south end of this site. Land to the west will
be flooded to depths varying from in excess of 0.6m to greater than 1.0m. Access to the north
via Penarth Road may be viable, although this route is flooded to a depth of greater than 0.6m.
Management of access/ egress for emergency services will, therefore, also need addressing.
The flood risk to the site itself is low. However, measures to mitigate the risk to access routes
and provide safe access during a 0.1% (1 in 1000) chance event may prove challenging. A flood
management plan as part of any site specific FCA for any proposed development of this site
would be advisable.
Site 78LBRM - A mixed use development is proposed at site 78 on Hadfield/ Penarth Road. With
the current ground profile of the site, approximately 60% of its area would be flood free for all
events modelled. The majority of the eastern part of the site is flooded to depths greater than
0.6m, but less than 1.0m. Flood depths would exceed 1.0m on only 3% of the overall site area.
Without mitigation, the inundated part of the site would be suitable only for industrial uses.
Access from all parts of the site to Hadfield Road would meet TAN15 criteria for depths and
velocity of flooding under current conditions.
Mitigation of the risk to at least part of the affected area of the site could be achieved through
raising part of the site, with compensatory lowering of other parts. This would allow other
development types to be considered i.e. commercial & retail uses, in compliance with TAN15
guidance.
A site-specific FCA would be required and careful consideration of changes to overland flows
and any potential adverse impacts on flooding elsewhere. It is likely that at least part of this site
can developed in line with TAN15 guidance.
Site 83LBRM –under existing conditions, the entire site would be inundated during a 0.1% (1 in
1000) chance fluvial event. However, for a little over 60% of the site area depths would not
exceed 0.6m during such an extreme event. Development of this part of the site for all
development types is likely to be achieved in line with TAN15 guidance. The depths over the
remaining 36% of the site area would be below 1.0m. Under existing conditions this part of the
site is likely to be suitable only for industrial uses, based on TAN15 acceptability criteria. Ground
re-profiling may increase the area available for uses other than industrial. Care will be required to
ensure any resulting changes to overland flow paths do not adversely affect flooding elsewhere.
On the main access/egress route for the site, via Penarth Road, maximum flood depths are
mostly below 0.6m. There are some localised areas of depths in excess of 0.6m but below 1.0m
on this road. It is considered likely that with careful planning and design of any proposed
development, that the risk to safe access can be managed safely.
There are no reported incidents indicating a problem with sewer flooding in the area of this site.
5.6.7 Site 70LBEM
The site is expected to remain flood free during a 1% (1 in 100) chance fluvial event over a
development lifetime to 2110.
A cluster of reported sewer flooding incidents is located to the east of this site. Further liaison
with Dwr Cymru Welsh Water is recommended. This should ensure that the source of these
incidents is understood and that any potential overland flow paths towards the site are identified
to allow mitigation. It is considered likely that the risk from this source can be mitigated. The
magnitude of any works required would need to be determined from the further investigation.
Overall the flood risk to this site is considered to be low (noting the recommended further
investigation of the sewer flood risk) and it is likely that the risk can be managed in line with
TAN15.
![Page 71: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/71.jpg)
5097656-70-DG017-3.docx 61
5.6.8 Site 61LBRM
Site 61LBRM is defined as within TAN15 DAM Zone C1 (protected).
Modelling shows that this site is not at risk from the 1% (1 in 100) annual chance event flood
within the next 100 years.
Although areas to the south and west of the site, towards the Taff, are estimated to flood in a 1%
chance event by 2110, alternative flood free access and egress routes would be available.
The site is also considered flood free for a current 0.1% (1 in 1000) annual chance fluvial event.
From consideration of the fluvial flooding on the Rivers Taff and Ely, it is concluded that the
development of this site is likely to meet TAN15 requirements.
The town centre, north of the rail line has already been identified as being at risk from sewer
flooding. Further investigation of the underlying reasons and any implications being for
development of the site should be undertaken as part of the design of the development.
Overall, the flood risk to the site is considered to be low and development within TAN15
guidance is considered to be likely.
The EAW‟s Flood Map of Surface Water (FMSW) indicates that Dumballs Road may be at risk
from surface water flooding. This risk would need to be considered in more detail as part of a
site specific assessment. It is considered that management of this risk is likely to be achievable.
The detailed site specific assessment for the site would need to demonstrate that the developer
has considered all flood risk issues associated with developing the site, including the provision of
acceptable access/ egress routes for emergency services, and the use of SuDS.
5.6.9 Site 96LGED
This site in Llandaff lies between an existing college campus and the right bank of the River Taff.
It lies in TAN15 DAM Zone C1 (protected) and benefits from defences from the River Taff..
The 2D model results indicate that the site would remain flood free for a 1% (1 in 100) chance
flood event over the lifetime to 2110. During a 0.1% (1 in 1000) chance event, currently, the
model results indicate that there would be some overtopping from the river defences at the
upstream (west) end of the site. However, maximum flood depths and corresponding velocities
would be well within TAN15 A1.15 criteria.
Surface water management will need to be given careful consideration. The EA Flood Map of
Surface Water (FMSW) indicates flooding only for the more severe of the rainfall events tested (1
in 200 annual chance) and this is indicated to be “deep” over a very localised area.
The nearest reported sewer flooding incidents are remote from the existing college or the
proposed development site. The capacity of the sewer system to accommodate any new
development would need to be explored with the sewerage undertaker as part of the
development design.
It is considered likely that, subject to a more detailed site specific FCA being undertaken, the
flood risk associated with development of this site can be managed in line with TAN15 guidance.
5.6.10 Site 101LBEM
Site 101LBEM lies partially within the TAN15 DAM Zone C1 (protected) and partially in Zone B.
Modelling shows that this site is not at risk from the 1% (1 in 100) annual chance event flood
within the next 100 years.
The site is also considered flood free for a current 0.1% (1 in 1000) annual chance fluvial event.
From consideration of the fluvial flooding on the Rivers Taff and Ely, it is concluded that the sites
will meet TAN15 requirements and development of the area may be possible.
![Page 72: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/72.jpg)
5097656-70-DG017-3.docx 62
A detailed site specific assessment for the site would need to demonstrate that the developer
has considered all flood risk issues associated with developing the site, including the provision of
acceptable access/ egress routes for emergency services, and the use of SuDS.
5.6.11 Site 17LGR
Site 17 lies adjacent to the defended right bank of the River Ely. The site is flood free over the
majority of its area during a 1% (1 in 100) annual chance flood event over the development
lifetime to 2110.
However, by 2085 the access route to the site via Dyfrig Road would be completely inundated by
a 1% (1 in 100) chance event as a result of overland flow from the River Ely upstream of the site.
The site itself will be completely inundated by a current 0.1% (1 in 100) annual chance flood
event as a result overland flow from the Ely via Dyfrig Road.
Although depths of flooding would be within TAN15 criteria over almost the entire site area, the
velocities over parts of the site would exceed TAN15 acceptability criteria. The velocities on the
site near the current site access to Dyfrig Road would be particularly high.
Velocities on Dyfrig Road, the main access/ egress route to the site would exceed 0.45m/s over
approximately 200m from the entrance to Site 17.
The site, therefore, fails TAN15 criteria. If development is to proceed, measures to mitigate the
risk will be required to comply with TAN15 guidance. Such mitigation measures could include
engineering works to improve the flood defence to the River Ely. However, such mitigation is
unlikely to be straight forward and may prove problematic.
![Page 73: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/73.jpg)
5097656-70-DG017-3.docx 63
6. Area I – Cardiff Bay to Pengam Green This section updates the assessment of flood risk for sites in the Pengam Green to Cardiff Bay
Area. It is based on updated 2D tidal inundation modelling and supersedes the 2D Modelling
Addendum Report of March 2010 (see Figure 1-1 and section 1.3). The updated modelling takes
account of new estimates of extreme sea levels, released by the Environment Agency in
February 2011 and considers development lifetime up to 2110. Following comments from the
Environment Agency, the potential for tidal flood water to enter Cardiff Bay via the Docks has
been investigated and assessed. This is described in Section 6.2.2.
As described in Section 2.5.7, surface water flood maps have been released by the Environment
Agency since completion of assessments of surface water flooding reported in the SFCA Phase
2 Part 1, November 2009. As part of the current assessment reference has been made to the
surface water flood maps to check the previous assessments for those candidate sites which
were the subjects of the November 2009 report. Otherwise, the assessments of all sources of
flood risk, other than tidal, remain unchanged for those sites which were previously assessed.
For completeness and ease of reference, these earlier assessments are repeated under the
summary of flood risk in Section 6.3, together with the updated assessment of tidal flood risk.
The text repeated from the earlier Phase 2 report is italicised.
Four of the current list of candidate sites (site references: 20LBR, 71LBC, 73LBRM and 58SBR)
have not been previously assessed; Phase two assessments in line with the methodologies
described in the SFCA November 2009 and the 2D tidal modelling update has been undertaken
for these sites.
6.1 Site Description and Flood Risks other than by Tidal Inundation
Full details of the extent and description of Area I and the assessment methodologies used for
sources of flood risk other than tidal are given in the SFCA Phase 2 Part 1 Report (2009).
As described in Section 1.3, the earlier SFCA 2D Model Addendum Report (March 2010)
considered the candidate sites to the Draft LDP which was withdrawn in 2010. The Candidate
Sites Submitted in 2010 for the current Draft LDP have been considered for this update.
6.1.1 General Site Description
Area I is bounded to the east by the River Rhymney, to the southeast by the coast and to the
west by the flood plain of the River Taff and Cardiff Bay. The centre of the City of Cardiff lies to
the northwest of Area I. The area is approximately bisected into east and west portions by the
spur rail line to Cardiff Docks. To the east are the areas of Tremorfa and Pengam Green. To the
west of the rail line are the areas of Splott and Butetown. Along the coast the Cardiff Flats
comprise an area of historically reclaimed land. The Cardiff Barrage lies in the south of the area
with the lock gate entrance to the Docks, being to the east of the barrage. The existing land use
in the area includes industrial, residential and dock developments.
The topographical elevations in the area vary between 6mAOD to over 10mAOD.
6.1.2 Proposed Development
The proposed development types comprise residential, mixed use and employment. The
individual sites cover areas of between 0.03ha to 24ha. The largest site at Pengam Green is
proposed for Employment and Industry and covers some 24ha.
The geographical extent of the study area is shown together with the individual site locations on
Figure 6-1 and site details are summarised in Table 6-1, below.
![Page 74: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/74.jpg)
5097656-70-DG017-3.docx 64
Figure 6-1 - Area I - Study Site Locations
(EAW 0.1% or 1 in 1000 annual chance flood outline also shown in blue)
QQuueeeenn AAlleexxaannddrraa DDoocckk
RRooaatthh DDoocckk
RRooaatthh BBaassiinn
CCaarrddiiffff BBaarrrraaggee
EEnnttrraannccee ttoo DDoocckkss
![Page 75: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/75.jpg)
5097656-70-DG017-3.docx 65
This page is intentionally blank
![Page 76: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/76.jpg)
5097656-70-DG017-3.docx 66
Table 6-1 - Area I – Summary of Study Sites
Site ID Name/ Location Existing Land Use Development Category
Site Area (ha)
71LBC Wales Millennium Centre 'Phase 3' Land
Occasional outdoor events
Arts related activities
0.1
58SBR Moorland Road, Cardiff
Vacant buildings and adjacent yard
Residential 0.03
20LBU Queens Gate Car Park Vacant Unknown 1.6
19LBU Pengam Green Vacant Employment 24.1
18LBM Queen Alexandra Head Vacant
Mixed use including leisure
4.7
60LBR Porth Teigr (formerly known as Roath Basin South), Cardiff Bay, Cardiff
Part – land under construction;
Part – vacant awaiting development;
Part – Cardiff Bay
Mixed use residential, retail, commercial and leisure
16.6
57LBR Hannah Street, Bute Town, Cardiff
Vacant, cleared site Residential 0.1
73LBRM Cardiff Graving Docks / Landsea Gardens / Landsea Square / Havannah Street Car Park, Cardiff Bay
Surface car park, small vessel moorings, public waterside access, restaurant, public space
Mixed use 2.1
101LBEM Land off Dumballs Road, Cardiff
Mixed industrial use (B1, B2 & B8) and temporary car park
Mixed use 3.7
94LBR Colchester Avenue, Cardiff
Education Residential 2.0
6.2 Flood Risk from Tidal Sources
The most significant flood risk in the east of the area is due to extreme tide levels in the Severn
Estuary, the River Rhymney and the Roath Brook. Tidal events in the lower reaches of the River
Rhymney and Roath Brook have been confirmed to result in higher flood levels than comparable
fluvial events (tested using EAW 1D HEC RAS model11
).
In the west of the area the main sources of flood risk arise from potential increases in water
levels in Cardiff Bay due to combined fluvial and tidal influences in concert with the impoundment
of the Cardiff Bay Barrage. There is also a potential for tidal inundation through Cardiff Docks.
The level in Cardiff Bay has been tested for tidal and extreme fluvial events using the 1D ISIS
Bay model described in Section 5.3.2. For extreme tidal events this model has been developed
further to test the effect of flooding into the Bay from the Docks via the Roath Basin (see Section
6.2.2).
11
Environment Agency Wales, 2007, Lower Rhymney and Roath Brook model, v2, HEC-RAS
![Page 77: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/77.jpg)
5097656-70-DG017-3.docx 67
Extreme Tide Levels and coincident fluvial flows into Cardiff Bay
It is noted that events described as tidal will have coincident fluvial component and vice versa.
For this current assessment the following combinations of events have been assumed in the
modelling:
Tidal events:
0.5% (1 in 200) annual chance tide level – coincides with QMED in Rivers
0.1% (1 in 1000) annual chance tidal level – coincides with QMED in Rivers
Fluvial events:
0.5% (1 in 200) annual chance fluvial flow – coincides with a Mean High Water Spring level
in Severn Estuary
0.1% (1 in 1000) annual chance fluvial flow – coincides with a Mean High Water Spring level
in Severn Estuary
The maximum extreme still water tide levels considered for this assessment are presented in the
table below.
Table 6-2 – Extreme Tide Levels Severn Estuary at Cardiff Docks
(source Environment Agency Wales, 2011)
Annual chance of exceedance
2010 2085 2110
0.5% (1 in 200) 8.4mAOD 9.1mAOD 9.4mAOD
0.1% (1 in 1000) 9.0mAOD *- *-
*Not assessed for the SFCA
The peak fluvial flows assumed to coincide with these extreme tides are presented in Table 6-3
below. These are referenced in the descriptions of the modelled flood levels in the following
sections.
Table 6-3 – fluvial flows assessed to occur coincident with extreme tidal flood events – Area I
QMED
(50% or 1 in 2 annual chance)
20%
(1 in 5 annual chance)
QMED inc climate change allowance
River Taff 356 m3/s 443 m
3/s 430 m
3/s
River Ely N/A12
78 m3/s 78 m
3/s
River Rhymney N/A12
112 m3/s 112 m
3/s
Roath Brook N/A12
12 m3/s 12 m
3/s
6.2.1 Overtopping and breach from River Rhymney and the Coastal Frontage
The Cardiff Flats floodplain is considered to be susceptible from flooding due to wave and tidal
sources. Storm surge levels, tidal currents and the wind wave climate along the shoreline are
significant.
12
In the absence of existing estimates of the QMED flows, we consider that use of the Q5 or 20% (1 in 5) annual chance flow represents a conservative approach. We have confirmed, based on analysis of ratios of ReFH flow estimates that the Q5 is greater than a QMED+20%. The Q5 has therefore also been used for the climate change scenarios and current day estimates.
![Page 78: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/78.jpg)
5097656-70-DG017-3.docx 68
The flooding due to overtopping and breach has been assessed using the 2D inundation model
(see Appendix D and Appendix F for further details). The extent of the model is shown in the
following Figure.
The right bank of the River Rhymney in the lower reaches comprises a mixture of infrastructure
which would not all have been designed formally for a flood and coastal risk management
function. They are not all Environment Agency maintained assets and there may be private ad-
hoc maintenance.
The tidal risk is considered dominant over the fluvial influences for the lower reaches of the
Rhymney and Roath Brook.
The main source of flood risk to the eastern side of Area I is overtopping of the right bank of the
River Rhymney. Extreme tide levels are propagated up the channel of the Roath Brook. The
effects of sea level rise also increase the risk of breach to the coastal frontage due to the
combined effect of wave and still water tide levels (SWL).
Figure 6-2 - Extent of 2D tidal inundation model - Area I
Green line indicates the extent of the tidal boundaries assessed
Reproduced from Figure F.1, Appendix F
The risk of breach has been assessed based on methodologies underlying the Environment
Agency Severn Estuary Flood Risk Management Strategy (SEFRMS). The approach to the
modelling is described in Appendix F. The increase in level up the Roath Brook during extreme
![Page 79: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/79.jpg)
5097656-70-DG017-3.docx 69
tide events has been tested by routing a fluvial flood event against a fixed tide level through an
Environment Agency 1D HEC RAS model of the Roath Brook and Lower Rhymney.13
The breach assessment essentially comprises consideration of the joint probability of wave and
extreme still water tide levels (SWL), the probability of breach and the consequences of breach
events.
Different combinations of SWL and wave height, corresponding to a series of joint probabilities
were tested for scenarios at each time horizon.
Results
The results of the 2D modelling of overtopping and breach from the coastal frontage, and the
River Rhymney and Roath Brook, are presented on Drawing Numbers 509765/RCF/420 to 422,
Appendix B.
Current situation
There is no breach indicated for a current 0.5% (1 in 200) event. The flooding indicated on
Drawing No. 5097656/RCF/420 results from overtopping from the River Rhymney and the Roath
Brook.
A single location at Tremorfa - labelled SR1-RRWB on Drawing No. 5097656/RCF/420 is
indicated to breach during a current 0.1% (1 in 1000) annual chance event.
Considering Climate Change to 2110
A single breach in the same location is indicated for a 0.5% (1 in 200) annual chance event in
2085 and 2110.
6.2.2 Direct Inundation from Cardiff Bay and Cardiff Docks
The sites in the west of the area will potentially be affected by elevated levels in the impounded
Cardiff Bay. The flood levels in the Bay are affected by a combination of fluvial and tidal
influences. A comparison has been made between the estimated flood levels in Cardiff Bay and
ground levels for the study sites.
The existing ground and defence levels are presented here for comparison with the results of the
modelling of flood levels in Cardiff Bay (presented below in this section). The LIDAR ground
levels around the Bay generally exceed 8.2mAOD. There are flood defence walls at two
locations of lower ground, at Windsor Esplanade and around the Graving Docks. The top of
defence level at Windsor Esplanade is 8.3mAOD. It is understood that a spot level survey
indicates that the top of the defences around the Graving Dock are approximately 8.0 to
8.1mAOD, although this requires further verification. It had previously been understood that this
defence was at least 8.2mAOD (as reported in the August 2010 issue of SFCA). Prior to
construction of the Graving Dock defence the hinterland area to the north, including Stuart
Street, Adelaide Street and the site of the Techniquest building, had been subject to flooding.
This area lies in a low lying corridor of land which stretches north towards central Cardiff. Any
water overtopping the Graving Docks defences will tend to flow north into this area.
Flow Path Through Cardiff Docks (Roath Basin)
Sites around Cardiff Docks, most notably Sites 20LBU, 60LBRM and 18 LBM, are potentially at
risk from elevated water levels in the docks. It is understood from the operators of the Docks,
Associated British Ports (ABP) that the current operating procedure requires opening the lock
gates to the Queen Alexandra Dock on tides in excess of 7.3mAOD. This effectively allows the
water in the docks to equal the level of the tide. Therefore, areas around the dock are at risk of
13
Environment Agency Wales, 2007, Lower Rhymney and Roath Brook model, v2, HEC-RAS
![Page 80: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/80.jpg)
5097656-70-DG017-3.docx 70
flooding for the extreme tides assessed for the SFCA (the tide level of 7.3mOAD is exceeded for
all events tested).
Inspection of LIDAR ground levels between the Roath Basin and the impounded Bay indicate
that potential overland flow routes exist by which water overtopping the dockside can weir into
the impounded Cardiff Bay. Under normal operating conditions, sea water from the dock is
prevented from passing into the impounded Bay by a bund structure in the disused lock adjacent
to the Norwegian Church. LiDAR data indicates a top of bund elevation of 7.6mAOD. The land
either side of this bund rises up to 9.0mAOD. The potential flow paths into the Bay via the Docks
are indicated on Figure 6-3.
Figure 6-3 Potential overland flow from Roath Basin into Cardiff Bay during extreme tide events
The Area I 2D tidal inundation model was used to test the volume of tide water entering the
docks during extreme tidal events under two scenarios:
Assuming the lock gates to the Queen Alexandra Dock to be open allowing the full area of
the lock to convey tide water into the dock, i.e. approximating to the actual situation.
Assuming the lock gates to remain closed. Sea water can only enter the dock by weiring
over the lock gates and any low lying land either side of the lock. i.e. limiting (i) the
conveyance area for flow and (ii) the time of overtopping to a relatively short period either
side of high water.
The gate open scenario is considered to approximate more closely to the current operating
procedure for tide levels exceeding 7.3mAOD. However, the second scenario has been tested
to inform the potential flood mitigation benefits of closing off the flow path through the open lock.
The extent of flooding around the Docks and the overland flow paths into Cardiff Bay has been
assessed as described in Appendix G. Essentially, the 1D ISIS hydraulic model of the Bay
described in Section 5.3.2 has been developed further to include a link to a 2D model of the area
Location of bund separating Cardiff Bay from the Docks
![Page 81: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/81.jpg)
5097656-70-DG017-3.docx 71
between the Roath Basin and the Bay14
. This models the overland flow which will develop from
the Roath Basin during extreme tidal events and the resultant effect on levels in Cardiff Bay.
In order to test compliance with TAN15 A1.14, a comparison was made between the 1% (1 in
100) annual chance fluvial events and 0.5% (1 in 200) annual chance tidal events to determine
whether fluvial or tidal events result in the higher levels. For assessment of TAN15 A1.15, the
0.1% (1 in 1000) annual chance fluvial and tidal events were compared.
It is industry practice to compare the 1% (1 in 100) annual chance fluvial events and 0.5% (1 in
200) annual chance tidal events when determining fluvial – tidal dominance for flood levels. i.e.
do extreme fluvial or tidal events result in the higher levels.
The effect of climate change on Bay levels due to increased fluvial flows and predicted sea level
rise has been considered in the assessment of the study sites.
The increase in the level in the Bay during extreme tidal events is predominantly due to the tide
locking of the incoming fluvial flows. To test the relative significance of the flow path into the Bay
from the Docks, sensitivity tests were undertaken using the model based on assumption of no
flow in via this route. i.e. assuming only fluvial flows into the Bay. These are presented in Table
6-4 5.
A separate sensitivity test of the Area I 2D only model (not linked to the 1D Cardiff Bay model)
was also run to estimate the levels likely to develop in the Docks if the gates were re-engineered
to allow their closure during extreme tidal events. This was tested for the most extreme level
only, the 0.5% (1 in 200) chance tidal event in 2110, a tide level of 9.4mAOD. The result is
presented in Table 6-4 5.
Tide Levels
The extreme tide levels in the Severn Estuary (on the seaward side of the Cardiff Barrage) used
in the assessments are presented in Table 6-2.
Results
The levels in Cardiff Bay for extreme tidal events predicted from the modelling are presented in
Table 6-4 5, the extent and depths of flooding are indicated in Drawings 5097656/RCF/420 and
421, Appendix B. The levels presented in the table include both the existing conditions and
assuming a mitigation scenario. This latter situation assumes the tidal inundation of the Docks is
mitigated through re-engineering of the lock gates to enable their closure during extreme tides.
The economic viability of such an option has not been assessed.
14
This is separate to the larger Area I 2D model used to assess direct coastal breach and inundation via the River Rhymney.
![Page 82: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/82.jpg)
5097656-70-DG017-3.docx 72
Table 6-4 5 Levels resulting in Cardiff Bay for current and future extreme tidal events
Assumes coincident QMED flows in the River Taff and River Ely
Scenario Tide level (mAOD)
Water Levels (mAOD)
TIDAL EVENT YEAR Key model assumption *
Roath Basin Impounded Bay
0.1%
(1 in 1000) annual chance
2010 Existing condition - Dock Lock Gates
open
9.0 9.0 7.66
No flow from Roath Basin
9.0 N/A 7.58
0.5% (1 in 200) annual chance
2085 Existing condition - Dock Lock Gates
open
9.1 9.1 8.08
No flow from Roath Basin
9.1 N/A 7.96
0.5% (1 in 200) annual chance
2110 Existing Condition Dock Lock Gates
open
9.4 9.4 8.29
No flow from Roath Basin
9.4 N/A 8.11
Lock Gates to Docks assumed to be retained closed
(overtopped only) **
9.4 8.2 N/A
* Open Lock Gates is current situation
** 2D only model
Current situation
During extreme 0.1% (1 in 1000) annual chance fluvial events in both the Taff and Ely Rivers, the
Bay level is predicted to rise to a peak level of 6.79mAOD (see Table 5-2 under Area H). All
sites in Area I would be flood free from this source during such an event.
During the comparable 0.1% (1 in 1000) annual chance tidal event, the tide level in the Severn
Estuary is predicted to be 9.0mAOD. The model results indicate that the Bay level would rise to
a peak of 7.66mAOD, if this event were to coincide with a QMED (50% or 1 in 2 annual chance)
fluvial flood event.
This level would be contained within the impounded Bay by the defences around the Graving
Docks, at Windsor Esplanade and by the general ground levels around the eastern sides of the
Bay. Some localised flooding to the low lying area in front of the Millennium Centre building
would occur during the peak level in the Bay.
Localised areas in the eastern Bay and Roath Basin area would be flooded due to tidal
inundation via the docks. This will result in overtopping from the Roath Basin into Cardiff Bay
and flooding to land at the dock side. (see Drawing 5097656/RCF/421C, Appendix B)
![Page 83: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/83.jpg)
5097656-70-DG017-3.docx 73
If the flow path from the Docks into the Bay were to be mitigated against, then the Bay level
would peak at less than 7.60mAOD as a result of the reduction in the volume of water entering
the Bay.
Considering Climate Change to 2085
The peak Bay level is predicted to increase to 8.08mAOD considering a 0.5% (1 in 200) annual
chance tide of 9.1mAOD. This assumes a greater flow into the Bay as a result of climate
change.
Considering Climate Change to 2110
A 1% (1 in 100) chance fluvial event would result in a peak water level of 7.62mAOD in the Bay
(see Table 5-2 under Area H), assuming a coincident Mean High Water Spring level (including
climate change) in the Severn Estuary of 7.1mAOD.
The 0.5% (1 in 200) annual chance tidal event level in the Severn Estuary is expected to rise to
9.4mAOD, based on current sea level rise predictions.
The modelling indicates that the Bay water level would rise to a peak of 8.3mAOD, assuming the
peak of the tide coincides with a QMED (including +20% climate change allowance) flood in the
Rivers Taff and Ely and with the lock gates to the docks open. Flooding to the area around the
docks and the area between the Roath Basin and the impounded Bay would result as indicated
on 5097656/RCF/421, Appendix B.
If the dock gates were re-engineered to ensure that they can be kept closed during extreme tide
events, then the reduced conveyance of sea water into the docks would result in reduced
flooding around the docks and less overtopping into the Bay. The model indicates that a peak
Bay level of 8.1mAOD would result.
The potential impacts of the predicted water levels on candidate sites are discussed in the
following section.
6.3 Summary of Flood Risk and Management
The results of the modelling of 0.5% (1 in 200) annual chance events showing the predicted
extent of flooding over the development lifetime are presented on Drawing 5097656/RCF/420 in
Appendix B. The depth and velocities estimated by the modelling for a current 0.1% (1 in 1000)
annual chance tidal event are shown on Drawings 5097656/RCF/421 to 422. These should be
referred to in reading the following site summaries.
Note: For the Docks area, only the Roath Basin has been modelled in 2D. Flow velocities are
available only for this part of the Docks. For the other areas of the Docks, the depths of flooding
have been estimated by contouring the extreme tide levels over the existing LIDAR ground
levels.
For all sites, surface runoff from developments will need to be managed using appropriate
sustainable drainage systems (SuDS) to restrict runoff as required by section 8.5 of TAN15.
6.3.1 Site 71LBC
Ground levels on this site are above 9.0mAOD, and generally over 9.5mAOD over most of the
site.
Fluvial and tidal sources of flooding
Current situation and considering climate change to 2110:
The site is not considered to be at risk from fluvial or tidal sources over a 100 year development
lifetime.
![Page 84: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/84.jpg)
5097656-70-DG017-3.docx 74
Other sources of flooding
Surface Water Flood Maps indicate some limited localised risk to part of the site for a 0.5% (1 in
200) rainfall event.
Site summary
It is considered likely that this site can be developed in line with TAN15. The management of
surface water within the site will be required. It is likely that the surface water risk to the site can
be managed within the design of the site layout and vertical alignments of any footpaths or roads
to ensure flow paths do not impact on any proposed or existing developments.
6.3.2 Site 58SBR
Fluvial and tidal sources of flooding
Current situation
The modelling indicates that this site is flood free for the fluvial and tidal events.
Considering climate change and sea level rise allowances to 2110:
The modelling indicates that this site is flood free for the fluvial and tidal events assessed over
the development lifetime to 2110.
Although flood free to 2085, the access road to the north and areas west of the site lie within the
0.5% (1 in 200) annual chance flood outline by 2110 as indicated on Drawing 5097656/RCF/420.
Other sources of flooding
The areas immediately north and west of the site are also indicated to be potentially at risk of
surface water flooding based on the EAW FMSW. The management of surface water within the
site will require consideration within the development design. It is considered likely that surface
water risk to the site can also be managed.
Consideration will need to be given to maintenance of access to the site under all conditions in
line with A1.12 of TAN15. The land south of the site is indicated to be flood free and there is the
potential to design emergency access via this route.
Site summary
It is considered likely that development of the site in line with TAN15 acceptability criteria can be
achieved, subject to confirmation through a site specific FCA.
6.3.3 Site 20LBU
This site lies partially in TAN15 Zone B, but with the majority within Zone A. The proposed use
for this site is unknown but assumed to include residential development.
The general site LIDAR levels are indicated to be at or above 9.0mAOD. Ground levels in the
southern half of the site are generally higher, reaching 9.6mAOD. There is a shallow depression
in the ground levels in the northern half of the site. The levels, bordering the Dockside at the
southern boundary are more typically 8.7mAOD.
Fluvial and tidal sources of flooding
Current situation
The site is flood free for tidally or fluvially dominated 0.1% (1 in 1000) annual chance flood
events.
Considering climate change and sea level rise allowances to 2085
The site is elevated above both the tidally dominated 0.5% (1 in 200) annual chance flood
levels and so is considered flood free.
![Page 85: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/85.jpg)
5097656-70-DG017-3.docx 75
The site is therefore complies with TAN15 within a 75year development lifetime and is
considered suitable for industrial/ commercial developments.
Considering climate change and sea level rise allowances to 2110
The majority of the site lies below the 9.4mAOD tide level for a 0.5% (1 in 200) annual
chance event level by 2110.
However, the flood depths during this event would be less than 0.4m over the majority of the
site.
Without mitigation, large parts of the site fail to comply with TAN15 over the 100year
development lifetime required for assessment of residential developments.
Mitigation of the risk may be achievable for example, through the construction of raised defences
to the dockside of the site. The modelling indicates that if the lock gates to Queen Alexandra
docks are re-engineered to allow them to remain closed during extreme tide levels, then dock
water levels would remain below the site levels.
The risk to any proposed development could be also managed by limiting the use of the ground
floor to non residential uses with residential units restricted to above ground flood level. The
duration of any tidal flooding would be limited to a period of a few hours around high water. Flood
free refuge could be sought above ground level during this time.
The access to the site from the north is likely to remain flood free over a 100year development
lifetime.
Other sources of flooding
The EAW Surface Water Flood maps indicate that the depression in the northern part of the site
is susceptible to surface water flooding. It is considered likely that this risk can be mitigated
through consideration of surface water in the design of the vertical alignments of roads and paths
as part of any future development.
The site is flood free and access routes to the site are likely to remain operational under all
conditions.
Site summary
The current risk to the site from fluvial or tidal sources is considered to be low. However, within
the 100year lifetime the site is at risk from a 0.5% (1 in 200) annual chance tidal flood event.
It is likely that site specific mitigation measures, such as defences to the dockside could allow
development to proceed in compliance with TAN15. The risk to any proposed development
could also include limiting any residential elements to above ground floor levels.
Changes to the lock gates to Cardiff Docks to allow closure during extreme tide events would
mitigate the risk to this site and improve flood risk to the docks and wider Roath Basin area.
The site design will need to take account of potential surface water risk and management of
surface water within the site.
It is considered likely that development of this site can be achieved in compliance with TAN15
guidance, subject to appropriate mitigation being demonstrated as part of a site specific FCA.
6.3.4 Site 19LBU
The Study Site at Pengam Green is proposed for employment and lies in TAN15 Zone C2.
Tidal Inundation
Current situation
The area around the site is affected by overland flow routes from the north and east due to
overtopping of the right bank of the River Rhymney.
![Page 86: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/86.jpg)
5097656-70-DG017-3.docx 76
The majority of the site is flood free for a current 0.5% (1 in 200) annual chance event with
small localised areas being inundated in the narrow strip of land adjacent to the River
Rhymney. The inundated area approximates to less than 10% of the site area.
The model results indicate that during a 0.1% (1 in 1000) annual chance flood event, a
number of small localised areas comprising approximately 20% of the site will be flood free.
50% of the site will flood to depths greater than 1.0m. Flood depths would remain below
0.6m over approximately 40% of the site.
The velocities of flood water are not indicated to exceed 0.15m/s over the majority of the
site. Velocities exceeding 0.45m/s are indicated in parts of the thin strip of land which lies
adjacent to Rover Way near the River Rhymney at the north east boundary of the site.
The site therefore fails to meet TAN15 A1.15 acceptability criteria for commercial
development over approximately 60% of the site‟s area. Approximately 50% of the site
would comply with A1.15 for Industrial development, due to the slightly greater depths of
flooding considered acceptable for such development types.
Consider climate change and sea level rise allowances to 2085
Approximately 80% of the site‟s area would be inundated by a 0.5% (1 in 200) annual
chance tidal event. Without mitigation of this risk, these areas of the site would fail the
TAN15 criteria for threshold of flooding, A1.14 of TAN15.
It is considered likely that routes for off-site access and egress would be available to the
south and west of the site via Rover Way and Seawall Road during this event and so would
comply with the requirement of A1.12 of TAN15 that access remain operational under all
conditions. It is noted that existing access to the east via Rover Way would be completely
flooded during this event and it is unlikely that this route would remain operational.
Consider climate change and sea level rise allowances to 2110
The proposed site use is for employment which requires consideration of a 75 year development
lifetime. The longer 100 year lifetime is considered for residential developments. The modelling
indicates that the entire site would be inundated by a 0.5% (1 in 200) tidal event by 2110. If use
of any part of the site were to be considered for residential use, this would fail A1.14 of TAN15.
Other sources of flooding
It is considered that the risk of flooding from other sources is unlikely to be significant compared
to the tidal flood risk, although they are not negligible.
Within the screening assessment the surrounding areas are indicated to have a high surface
runoff risk score. The site is generally at lower ground levels than the surrounding land. Runoff
risk from the surrounding areas would also need to be considered as part of the design for the
development of any part of this site. Although it is anticipated that surface water management
measures incorporated in the overall site design should be able to address the risk.
Two sewer flooding incidents at Greenbay Road and another at the Pengam Green Tesco are
close to the proposed sites. The causes are unknown. The area sewer provision should be
investigated as part of any proposed development to determine if any significant risk of sewer
flooding exists e.g. possibly related to under capacity issues or blockage.
Site summary
The results of the 2D modelling are considered to provide a good representation of the
distribution of flood flows and depths through Area I for a strategic broad scale assessment. (The
2D modelling is described in Appendix F).
During a current 0.5% (1 in 200) tidal event, the majority of the water flooding the area results
from overtopping of the right bank of the River Rhymney. During a current 0.1% (1 in 1000)
chance event and a future 0.5% (1 in 200) chance tidal event, breach of the coastal frontage is
predicted.
![Page 87: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/87.jpg)
5097656-70-DG017-3.docx 77
Without mitigation, the site fails to comply with TAN15 over the majority of its area.
Access and egress routes are likely to remain available during a 0.5% (1 in 200) annual chance
tidal event to 2085.
Mitigation of the tidal risk to the site to meet TAN15 acceptability criteria may be problematic.
Increasing defence levels on the River Rhymney could be considered. This may be considered
as part of a flood alleviation strategy for the existing properties at risk from this source. This
would require a multi agency approach involving the Environment Agency and the local authority.
Such a scheme may reduce risk to the site sufficiently to meet the TAN15 acceptability criteria
and so facilitate development. However, the extent of such works is likely to be considerable.
The design of flood resilient buildings should also be considered. In addition, it should be noted
that the Environment Agency are not normally supportive of proposals which rely on flooding of
voids under buildings being used in mitigation of loss of flood plain storage.
Ground raising with compensatory lowering of other appropriate areas within the site may reduce
flooding to meet TAN15 criteria for at least part of the site area which is predicted to be
inundated. This measure alone would not allow development of the entire site, due to the need
to provide equivalent compensation for loss of flood plain storage. The increase in the proportion
of the site which may meet TAN15 would be subject to further more detailed assessment.
Interception of the overland flow from the north could also be considered to reduce flood risk to
the site. This would have the added benefit of potentially protecting existing properties which are
currently lie in the overland flow paths. However, consideration would have to be given to any
adverse impacts on flood risk elsewhere arising from changes in the overland flow routes.
Without mitigation, it is likely that only a small proportion of the site could be developed in line
with TAN15 guidance.
6.3.5 Site 18LBM
This site is proposed for mixed use development including leisure. It is almost entirely within
TAN15 Zone B or ZONE A. Site levels are generally above 9.0mAOD with a significant
proportion of the area above 10mAOD.
Current Situation
The site is elevated above a 0.1% (1 in 1000) annual chance tidal flood level. The current risk of
flooding is considered to be low.
Considering climate change to 2085
The inundation modelling indicates that the site is elevated above potential flooding from the
Docks. A low lying strip of land crosses the site, including a ditch on land north of the existing
Harbour Authority and ABP Offices. The ground elevations in these areas are as low as
approximately 8.8mAOD. Inundation of these areas and north into the site would occur from the
lock entrance to the Queen Alexandra Dock, during the 0.5% (1 in 200) annual chance tide level
of 9.1mAOD. Some overtopping into the Bay is possible via this route. The period of
overtopping into these areas is likely to be short, limited to a few hours either side of high water.
The volumes entering the Bay via overland flow paths across the site would not be expected to
significantly affect the water level in Cardiff Bay.
Considering climate change to 2110
The area of inundation of the site during a 0.5% (1 in 200) annual chance tide level of 9.4mAOD
will be slightly more extensive than the situation for 2085. The overland flow paths developing
across parts of the site are likely to be of short duration, of approximately 1 hour, around the
peak of the tide.
![Page 88: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/88.jpg)
5097656-70-DG017-3.docx 78
It is considered that mitigation of the risk through the design of the site layout and ground levels
should be achievable without causing adverse impact elsewhere, with the potential to direct
water back to the open coast.
Access
LIDAR levels indicate that access bridges across the docks north of the site are likely to be
flooded for a 0.5% (1 in 200) chance tidal event by 2085. However, the depths of flooding are
likely to be less than 0.6m and will be of short duration. Similarly the new bridge access via Site
60LBRM from the Norwegian Church area would be flooded, albeit to predicted depths less than
0.6m and for a relatively short duration.
If development of any given site is to proceed in line with TAN15, it will need to be demonstrated
that escape/ evacuation routes remain operational under all conditions, as stated in A1.12
TAN15. This is a matter requiring expert assessment from the emergency services and local
authority emergency planners.
Flood free refuge would be available over a large area of the site itself during any periods when
of site access could not be maintained.
Other sources
There is no indication of a significant surface water risk to the site.
Site summary
Some areas of the site are at risk from extreme tidal events as indicated by the flood extents
indicated on Drawings RCF/420 to RCF421, Appendix B. It is likely that mitigation of the direct
inundation from the coast and lock gate area could be achieved by ground raising or raised
defences without adverse impacts elsewhere.
The access routes to the north via the Roath Basin and eastern Bay area are likely to flood,
albeit to depths less than 0.6m and for short duration.
More involved mitigation based around re-engineering of the lock gates to the Queen Alexandra
Dock such that the gates remain closed during extreme tidal events could restrict the flood
outline to the cross hatched area indicated on Drawing 5097656/RCF/420. This would mitigate
the risk to the site itself and the off-site access routes to the north.
It is considered likely that the site can be developed in compliance with TAN15. The scale of
mitigation options necessary will need further investigation and development.
6.3.6 Site 60LBRM
This majority of the site lies within TAN15 Zone B. Some parts of the site lie in Zone C1, but
these are a small proportion of the overall 16.6 hectare site.
This site is understood to have extant planning permission. Any future issuing or renewal of
planning consents will need to reflect the management of the consequences of flooding in line
with current planning policy guidance.
Current Situation
Whilst the majority of the site area is elevated above a 0.1% (1 in 1000) annual chance flood
level, flooding to some parts of the site can be expected during such an event. The flooding of
this site derives from two directions during this extreme tidal event;
i) due to the increase in the level in Cardiff Bay during tide lock,
ii) inundation of tide water from the Roath Basin dock.
![Page 89: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/89.jpg)
5097656-70-DG017-3.docx 79
A small area of the lower lying part of the site bordering an old dock on Cardiff Bay will flood
during a 0.5% (1 in 200) tidal event. The flood depths in this low lying area will be less than 0.6m
during a 0.1% (1 in 1000) chance event (excluding the dock area itself).
Overtopping is also predicted from the Roath Basin onto the lower lying areas in the north central
part of the site during a 0.5% (1 in 200) chance tidal event. During a 0.1% (1 in 1000) chance
tidal event, the flood depths over the majority of the affected areas are likely to remain below
0.6m. Some localised areas will be affected by flooding over 0.6m. Flood depths greater than
1.0m will be restricted to the areas of the actual docks. The flow velocities across the site are
likely to be benign, the flooding being due to steady filling of both the Bay and the Docks. High
velocities can be expected near a new access bridge north of the site by the Norwegian Church.
This is adjacent to the main flow path for water overtopping the bund separating the Roath Basin
dock from Cardiff Bay (described in section 6.2.2 and indicated on Figure 6-3).
The flooding from Roath Basin reflects the flow path through Cardiff Docks under the existing
conditions whereby the lock gates must be opened during extreme tide levels (See Section 6.2.2
and Appendix G).
Although the current risk of flooding to the majority of the site is considered to be low, the lower
lying areas of the site which lie in the 0.5% (1 in 200) flood outline fail to comply with TAN15
guidance.
Considering climate change to 2085
Although the modelling of levels in Cardiff Bay suggests that the majority of the site area is
above the 0.5% (1 in 200) annual chance level estimated in the Cardiff Bay (8.01mAOD)
overland flows will develop from Roath Basin dock around peak of high tide. Approximately 50%
of the site area will be affected during this event. The flooding will be of relatively short duration
of a few hours and the depths of flooding over the majority of the area will remain below 0.6m.
The velocities across the site are likely to be largely benign as the flooding derives from steady
filling of the docks and eventual overtopping of the dock sides.
Consider climate change to 2110
The flooding across the site during a 0.5% (1 in 200) chance tidal event will be slightly more
extensive than the case for 2085, as indicated on Drawing 5097656/RCF/420/B, Appendix B.
Access
If development of any given site is to proceed in line with TAN15, it will need to be demonstrated
that escape/ evacuation routes remain operational under all conditions, as stated in A1.12
TAN15. This is a matter requiring expert assessment from the emergency services and local
authority emergency planners.
LIDAR levels indicate that the approaches to the access bridges across the docks north of the
site are likely to be flooded for a 0.5% (1 in 200) chance tidal event by 2085. However, the
depths of flooding are likely to be less than 0.6m and will be of short duration. It is considered
likely that the access routes north of the site will remain operational for all but few hours near the
peak of the tide for the extreme flood events assessed. This would need to be confirmed by a
site specific study as part of any FCA for the site. It is noted that the new bridge access to Site
60LBRM from the Norwegian Church area would be flooded, albeit to predicted depths less than
0.6m and for a relatively short duration. However, the velocities at this bridge are likely to be
high, due to its proximity to the flow path over the bund which separates the Roath Basin dock
from the Bay. It is likely that during the period around the peak of the extreme tides, this access
route would not be operational.
Flood free refuge would be available over a large area of site 60LBRM during any periods when
off site access is not operational.
![Page 90: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/90.jpg)
5097656-70-DG017-3.docx 80
Other sources
There is no indication of a significant surface water risk to the site. Evidence does not suggest a
risk of sewer flooding.
Site summary
All but the very lowest areas of the site, bordering the old dock on Cardiff Bay are elevated
above the highest flood levels predicted for Cardiff Bay during current day extreme tidal events.
The main source of flood risk to the site results from the tidal filling of the Roath Basin dock
during extreme tide events. The small proportion of the site will be affected by a current 0.1% (1
in 1000) annual chance event. The resulting flood depths will be below 0.6m over much of the
affected areas with some localised flooding above 0.6m. Depths greater than a 1.0m will be
restricted to the old docks within the site.
The current flood risk to the majority of the site area is considered to be low.
By 2085, relatively short duration shallow flooding is predicted for approximately 50% of the site‟s
area during a 0.5% (1 in 200) chance tidal event. Flood depths will be greater in those areas
bordering the docks.
By 2110, the depths of flooding will increase during the 0.5% (1 in 200) chance event. Flood
depths are predicted to exceed 1.0m around the dock sides. These depths will affect areas up to
60m from the dock side.
Flood free refuge will be available within the site for the duration of the flooding which is likely to
be of short duration of a few hours around the peak of the tide.
It is considered likely that the majority of the site can be developed in line with TAN15 guidance
for residential and mixed use development. The low lying areas of the site may be suitable for
boating, boatyards, marinas or other water related uses as recognised in TAN15.
Mitigation options to increase the area suitable for all development types might include raised
defences to the Roath Basin dock to reduce tidal flooding. Mitigation based around re-
engineering of the lock gates to the Queen Alexandra Dock to allow their closure during extreme
tidal events could restrict the flood outline to the cross hatched area indicated on Drawing
5097656/RCF/420. This would mitigate the risk to the site itself, the wider Roath Basin and
Cardiff Docks area including the off-site access routes to the north.
The level of the access bridges to the site will need to be confirmed to inform any assessment to
determine if escape/ evacuation routes remain operational under all conditions, as required by
A1.12 TAN15. This is a matter requiring expert assessment from the emergency services and
local authority emergency planners.
Flood free refuge would be available over a large area of the site itself during any periods when
such access/egress were not operational.
It is considered likely that the site can be developed in compliance with TAN15, The scale of
mitigation options will need further investigation and development.
6.3.7 Site 57LBR
This site at Hannah Street Church, Hannah Street, is proposed for residential development and
lies in TAN15 Zone C1. The surrounding area comprises a low lying corridor west of the Central
Cardiff to Cardiff Bay Rail line. Typical ground levels are between 7.4mAOD and 7.8mAOD.
The site benefits from defences to Cardiff Bay to the south and the River Taff to the west.
Tidal inundation
The 2D tidal inundation modelling results indicate that this site is not affected by extreme tidal
inundation events over the assessed 100 year period to 2110.
![Page 91: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/91.jpg)
5097656-70-DG017-3.docx 81
Based on the 1D modelling, the peak water level in Cardiff Bay during a 0.5% (1 in 200) event is
estimated to reach a peak of 8.1mAOD by 2110. Defences to the Bay area prevent water
overtopping and flowing north and towards this site.
The site is considered to be flood free for a 100 year development lifetime.
The flood risks from other sources as assessed in the SFCA are repeated below.
Fluvial flood risk
River modelling of the River Taff described for Area H in Section 5.3 indicates that this site is
flood free during a current 0.1% (1 in 1000) annual chance fluvial event.
The site is also flood free for a 1% (1 in 100) annual chance event over a 100 year period to
2100. This takes account of the effect of 20% increase in river flow and the effect of sea level
rise on tide locking of flows into Cardiff Bay.
Other sources
The Surface Water Flood risk screening score indicates a potential risk between medium and
high. Inspection of the LiDAR levels indicates that ground levels in the area are generally low
lying compared to surrounding areas. However, Site 57LBR is elevated above its immediate
area. Overland flow paths developing as a result of highway and surface runoff are likely to
divert away from the site. The EA Map of Surface Water (FMSW) indicated that the access
roads north and south of the site may be susceptible to surface water flooding.
The risk of surface water flooding will need to be taken into account in the design of the
development. The areas further north of the site are indicated on the FMSW to be at risk from
widespread surface water flooding. The FMSW map indicates that access and egress for Site 57
should be maintained in the event of extreme rainfall events via routes to the south and east of
the site.
The study site is in close proximity to a large number of recorded sewer flooding incidents. The
site‟s elevation above its immediate area should prevent overland flows impacting the site. It is
recommended that the risk from this source is investigated further as part of the site
development.
The risk will need to be determined and any mitigation measures such as surface water
management plan will need to be developed as part of the development design.
Site summary
It is considered likely that the site will remain flood free for the flood events assessed over the
development lifetime to 2110. A site specific assessment will need to give adequate
consideration to the management of surface water runoff, although the risk from this source is
considered to be low. Subject to investigation and confirmation of the sewer flooding risk and
suitable mitigation measures, it is likely that the site could be developed in line with TAN15
guidance.
6.3.8 Site 73LBRM
This site is proposed for mixed use including residential development and lies in TAN15 Zone
C1.
The site is discussed in terms of eastern and western parcels of land, in relation to Havannah
Street which lies northwest of the St David‟s Hotel site. Ground levels on the westernmost parcel
are above 8.0mAOD over approximately 80% of its 0.7ha area. The parts of the site east of
Havannah Street comprise the Graving Docks area.
Anecdotal reports from the Manager of the Cardiff Barrage indicate that this area and the
Techniquest building were subject to flooding prior to impoundment of the Bay. In the current
post impoundment situation, the area between the Graving Docks is reported to contribute to the
![Page 92: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/92.jpg)
5097656-70-DG017-3.docx 82
flood storage during elevated levels in Cardiff Bay. The hinterland to this site, Stuart Street and
north into Cardiff is protected by hard defences. It is understood that a spot level survey
indicates that the top of the defences around the Graving Dock are 8.1mAOD although this
requires further verification.
Tidal inundation
Current Situation
The current 0.1% (1 in 1000) annual chance tide level in the Severn Estuary is 9.0mAOD. If this
were to occur coincident with QMED (1 in 2 annual chance) flows in the Taff and Ely Rivers, the
model results indicate that levels in the Bay would rise to 7.66mAOD (compared to 6.79mAOD
for a fluvial dominated 0.1% (1 in 1000) chance event – see Table 5-2).
The areas of the site on the Bay side of the defences around the Graving Docks would flood.
The areas on the landward side of the defences would remain flood free. All of the site west of
Havannah Street would be flood free during a 0.1% (1 in 1000) annual chance tidal event.
Climate Change to 2085
By 2085, the peak level in Cardiff Bay during a 0.5% (1 in200) tidal event is predicted to rise to
just over 8.0mAOD. The defended areas of the site would be expected to remain flood free
during an event of this chance.
A small area of the site west of Havannah Street lies below 8mAOD. Taking a precautionary
approach, this area is highlighted as within the 0.5% (1 in 200) chance outline for 2085 on
Drawing 5097656/RCF/420. The flooding to this area is likely to be shallow and of short
duration. Verification of the level of the defence along Windsor Esplanade may show this area to
be defended.
Climate Change to 2110
Modelling results indicate that a 0.5% (1 in 200) annual chance event coincident with a QMED (1
in 2) flow in the rivers would result in the Bay level rising to 8.3mAOD. (This compares to an
estimated Bay level of 7.62mAOD during level fluvially dominated 1% (1 in 100) annual chance
event in the Rivers Taff and Ely - as shown in Table 5-2). This would result in overtopping of the
defences around the Graving Docks. The water would flood the areas of the Candidate Site
behind the defences and overland flows would develop into the low lying areas north of this site
as indicated by the arrows on drawing 5097656/RCF/420, Appendix B.
The majority of the site west of Havannah Street would remain flood free with some minor
overtopping in to the small lower lying area in the north part of this western portion of the site.
Although slightly deeper than this event in 2085, the flooding to this area is likely to be shallow
and of short duration. Verification of the level of the defence along Windsor Esplanade may
show this area to be defended.
Other sources
The Environment Agency Surface Water Flood Map does not indicate any significant risk from
this source.
Site summary
Those parts of the site on the landward side of the existing flood defences will remain flood free
during a current 0.1% (1 in 1000) chance tidal event. The site would remain flood free for all
fluvially dominated events over the development lifetime to 2110.
The lower lying areas of the Graving Docks, on the undefended side of the defences serve as
designated flood storage and would flood during a current 0.5% (1 in200) annual chance tidal
event. Further details of the proposed development uses included in the “mixed use” description
may allow certain development in this area for boating, boatyards, marinas or other water related
uses as recognised in TAN15. Further detailed assessment would be required to ensure the risk
can be managed and will be dependent on the specific land use proposed.
![Page 93: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/93.jpg)
5097656-70-DG017-3.docx 83
The defence levels around the Graving Docks require verification, currently understood to be
between 8.0 and 8.1mAOD. By 2085 a 0.5% (1 in 200) chance tidal event could result in the
peak Bay level of 8.08mAOD just overtopping or coming within 0.02m of the top of the defence.
Subject to verification of the defence levels, the defended parts of the site would either suffer
flooding at the peak of the tide or just remain flood free to 2085.
By 2110, a 0.5% (1 in 200) chance event would overtop the defences resulting in flooding to the
site and the development of overland flow paths north into Stuart Street and Adelaide Street and
the low lying hinterland to the north as indicated by the arrows on Drawing Number
5097656/RCF/420/C, Appendix B . The period of overtopping would be of the order of ¾ hour.
Options to mitigate the future risk could include raising the levels of the existing defences to the
Graving Docks.
The section of the site west of Havannah Street lies on higher ground and all but a small part of
this area of the site would remain flood free over a development lifetime to 2110.
Up to 2085, it is considered likely that access would remain operational under all conditions to
the defended parts of the site and the high ground of the site area west of Havannah Street.
By 2110, it is likely that mitigation measures will be required to manage the risk to the site itself
and to the off-site access routes. Flood free refuge would be available in the higher ground in
the west of the site, west of Havannah Street.
Considering Site 73LBRM overall, it is considered likely that a large proportion of this site can be
developed in compliance with TAN15, subject to a more detailed site specific FCA being
undertaken.
6.3.9 Site 101LBEM
This site is not considered to be at risk from tidal inundation. The assessment of the flood risks
to the site are described in Section 5.6.10.
6.3.10 Site 94LBR
This site at Colchester Avenue lies within TAN15 Zone C2 (not benefitting from defence). It is
noted that the road at Colchester Avenue over which overland flows would need to pass to affect
the site is designated as being in TAN15 Zone C1 (benefitting from defence infrastructure).
The site is proposed for residential use which is considered highly vulnerable development as
defined in TAN15.
This site is understood to have extant planning permission. Any future issuing or renewal of
planning consents will need to reflect the management of the consequences of flooding in line
with current planning policy guidance
Tidal inundation
The site lies on the left (northern) west bank of the Roath Brook. This is outside the area for
which the 2D model was designed to assess the flood risk. The defence levels to the left bank of
the Roath Brook are based on the LIDAR levels within the 2d domain, rather than surveyed
levels. This will tend to underestimate the actual defence levels. A comparison has been made
between the LIDAR levels representing defences in the 2D model and surveyed levels used in
the EAW 1D ISIS model of the Roath Brook and Lower Rhymney15
. It is considered that the
LIDAR levels provide a reasonable estimate of the defences and do not result in overly
pessimistic estimates of flooding to the area which includes Site 94LBR.
The results of the 2D tidal inundation modelling for this site can be considered as indicative and
are likely to provide conservative estimates. Incorporating surveyed levels into the model may
15
Lower Rhymney and Roath Brook Flood Risk Mapping Study, ISIS v3, Environment Agency Wales, 2008
![Page 94: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/94.jpg)
5097656-70-DG017-3.docx 84
reduce the risk slightly for the current situation. It is considered unlikely that the future scenarios
will be materially affected due to the extensive overtopping of the left bank.
The modelling indicates that the site is affected by water overtopping the left bank of the Roath
Brook during extreme tidal events.
At the time of writing, it is understood that the Environment Agency is developing a combined 1D
2D inundation model of the Roath Brook and its flood plain, including the area at Colchester
Avenue. It is likely that the results of the EAW modelling will represent an improvement in the
level of detail in this area compared to the inundation model developed for this SFCA.
Nevertheless, the current model is considered to provide a level of detail appropriate to the
strategic broad scale nature of the SFCA. Further detailed modelling will be required, to confirm
the viability of mitigation measures to mitigate the flood risk.
The results of the 2D modelling in relation to Site 94LBR are described below.
Current situation 2010
The model results indicate that the site is inundated by a current 0.5% (1 in 200) annual
chance tidal event over approximately 75% of the site area. Depths of flooding would be
shallow, estimated to be generally less than 0.1m.
The modelling indicates that the majority of the site would be flooded to depths of at least
1.0m during a current 0.1% (1 in 1000) annual chance event. A small portion in the east of
the site would remain flood free.
The corresponding velocities during a 0.1% (1 in 1000) chance event would be below
0.3m/s over the majority of the site and the access to Colchester Avenue.
Based on the modelling results, the site fails to comply with TAN15 A1.14 and A1.15
Considering climate change and sea level rise allowances to 2085
The extent of flooding to the site would not increase significantly for a 0.5% (1 in 200)
annual chance tidal inundation event, but depth would increase dramatically to over 1.0m.
The flooding would extend north of the site to properties on Sinclair Drive.
Recognising the limitations of the modelling, the hazard score (see Section 3.3.0 above for
definition) during 0.5% (1 in 200) annual chance event indicates that access via Colchester
Avenue would remain passable to emergency services only.
Considering climate change and sea level rise allowances to 2110
Depths of flooding to the site would increase further by 2110 during a 0.5% (1 in 200)
annual chance event.
The eastern portion of the site would remain flood free for this event.
Without mitigation, it is unlikely that an off-site access and egress route for the flood free
area could be maintained via Colchester Avenue under all conditions. Alternative
emergency access could potentially be available via land to the east of the site.
Based on the modelling results, the site fails to comply with TAN15 A1.14 and A1.15.
Mitigation of the risk
Any mitigation of the risk to the site would need to be achieved without increasing the flood risk
elsewhere.
The installation of a structure on the culvert outfall of the Roath Brook to the Rhymney could be
considered and may provide benefit in preventing tide levels backing up the Brook channel.
However, it is questionable if there is sufficient storage in the Roath Brook channel to contain the
fluvial volumes which would accumulate during tide lock periods.
![Page 95: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/95.jpg)
5097656-70-DG017-3.docx 85
Localised raising of ground levels on the site may mitigate the flood risk to some parts. However,
the displaced volumes are likely to be significant, given that the depths of water on the site are
indicated by the modelling to exceed 1.0m for a current 0.1% chance event and the future 0.5%
( 1 in 200) chance event. Compensatory storage may be available on the site, but this would
reduce the available development area.
The site lies in an area which is already heavily urbanised. Raising defences to the Roath Brook
would have benefits alleviating flood risk to the existing properties. It is possible that such
mitigation may reduce the risk sufficiently to facilitate development of Site 94LBR.
Strategic solutions for the area as a whole would need to be explored in partnership with the
Environment Agency. These may provide benefits to reducing risk to the site 94LBR sufficient
for TAN15 criteria to be met. Further detailed work would be required to confirm this.
Fluvial Flood Risk
The flood levels in the Roath Brook during extreme fluvial flood events have been checked
against the relevant tidal events (i.e. those required for assessment of A1.14 and A1.15 of
TAN15) with reference to an Environment Agency 1D HEC RAS model of the Roath Brook16
.
Fluvial flood levels are less than those for the corresponding tidal events. The flood risk in the
lower reach of the Roath Brook is therefore considered to be tidally dominated. It is likely that
mitigation of the tidal flood risk to Site 94LBR will also mitigate the fluvial flood risk.
Other sources of Flood Risk
Reference to the EAW‟s FMSW map indicates that shallow flooding may affect some small areas
of the site during a 1 in 30 year rainfall event. More extensive flooding across approximately
60% of the site is indicated for a 1 in 200 year rainfall event. These maps are indicative only.
The management of surface water risk to the site and the runoff from any proposed development
would need to be managed as part of the overall design of the site. It is likely that these risks
can be mitigated.
Site summary
Under existing conditions, the majority of the site fails TAN15 for all development types. A small
parcel of land (approximately 0.24ha) in the east of the site remains flood free over development
lifetime to 2110. Providing that an emergency access and egress route can be established,
development of this part of the site for residential use may be achievable in line with TAN15
guidance.
Any more significant development of this site will require further more detailed assessment of the
existing flood risk. This is likely to require more detailed modelling. This could be informed by a
2D inundation model of the area which we understand is under development by the Environment
Agency.
Mitigation of the risk to the site is likely to be problematic. A strategic solution to alleviate
flooding to the Colchester Avenue and Newport Road areas may reduce flood risk to the site
sufficiently to facilitate development in line with TAN15 guidance. Such a strategic solution is
likely to require a multi agency approach involving the Environment Agency, Cardiff Council and
Welsh Government.
16
Environment Agency Wales, 2007, Lower Rhymney and Roath Brook model, v2, HEC-RAS
![Page 96: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/96.jpg)
5097656-70-DG017-3.docx 86
7. Conclusions
7.1 Site Summaries
The following tables summarise the situation assessed for each study site, based on the existing
information. The main flood risk for each site is highlighted together with its current planning
status and a cross reference to the relevant section above which describes the likelihood of any
new planning application achieving compliance with the current planning policy guidance in
TAN15. Each of the four sub areas are summarised in Table 7-1 to Table 7-4.
Table 7-1 - Summary of Sub Area A – Wentloog Tidal Development Sites
Site ID Name/ Location Main Flood Risk Reference
76LGW South of Wentloog Avenue Tidal S.3.3.1
p.21
22LGRM Trowbridge Mawr Tidal S.3.3.2
p.22
21LGR Areas 9 - 12 St. Mellons Surface Water S.3.3.3
P.24
23LGR Land between Crickhowell Rd and Willowbrook Rd
Surface Water S.
p.25
24LGRM Land East of Cypress Drive, St. Mellons
Tidal S.3.3.5
p.25
74LGEMW Wentloog South of the Railway Line Tidal S.3.3.6
p.26
2LGRM Land at St. Mellons Business Park Tidal S.3.3.7
p.27
1LGRM Land at Wentloog Levels Tidal S.3.3.8
p.28
106LGEM Land at St Mellons/ Wentloog Tidal S.3.3.9
p.29
GTchPk Action Area Tidal S.3.3.10
p. 30
Wentloo_ii Action Area Tidal S.3.3.11
p.31
Wentloo_iii Action Area Tidal S.3.3.12
p. 33
3SBR Pill Du Farm, Hendre Lane, Trowbridge
Tidal
Surface Water
S.3.3.13
p.34
55LGR Land at Trowbridge Road Surface Water S.3.3.14
p.35
56LBR Land at Former St John‟s College Negligible S.3.3.15
p.36
![Page 97: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/97.jpg)
5097656-70-DG017-3.docx 87
Table 7-2 Summary of Area G – Junction 33, M4
Site ID Name/ Location Main Flood Risk
Reference
102 LGR Land South of Creigiau
Sewers including (SPS) Fluvial (minor watercourses/ culvert blockage)
S.4.6.1
p.43
46LGRM Junction 33
Fluvial (minor watercourses/ culvert blockage)
S.4.6.2
p. 43
Table 7-3 - Summary of Sub Area H – West Central Taff/Ely, Development Sites
Site ID Name/ Location Main Flood Risk
Reference
8LGR West of Clos y Cwarra, Michaelston-super-Ely, Cardiff
Surface water Potential risk to part of site from ordinary watercourse
S.5.6.1
p. 56
16LBR Ely Bridge, Western Business Centre, Cowbridge Road East Fluvial
S.5.6.3
p.57
17LGR Ely Bridge Farm, Dyfrig Road, Ely. Fluvial
S.5.6.11
p.62
31LBEM Land at Brindley Road, Leckwith, Cardiff
Limited
Consider culvert blockage
S.5.6.6
p.59
32LGR Land at Michaelston Road, Cardiff Low risk
Possible Sewer
S.5.6.2
p.56
36LBR Former Lansdowne Hospital Site, Sanatorium Road, Canton, Cardiff, CF11 8PL
Fluvial S.5.6.5
p.58
52LBR Paper Mill Road, Cardiff , CF11 8PH Fluvial
S.5.6.4
p.58
61LBRM Penarth Road Car Park Site (adjacent to Cardiff Central Railway Station) - includes Riverside Sidings/ Semaphore House
Low Risk S.5.6.8
p.61
62LBR Land adjacent to Clive Lane Fluvial risk to access routes
S.5.6.6
p.59
70LBEM Central Square Low risk
Possible sewer
S.5.6.7
p.60
75SBR Land East of Great House Farm, Michaelston Road
Low risk
SW management
S.5.6.1
p.56
![Page 98: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/98.jpg)
5097656-70-DG017-3.docx 88
Site ID Name/ Location Main Flood Risk
Reference
77LBR Ferry Road, Grangetown, Cardiff Fluvial
Access during 0.1% chance event
S.5.6.6
p.59
78LBRM Wholesale Fruit Centre Cardiff Fluvial
0.1% chance only
S.5.6.6
p.59
83LBRM Former J R Freeman Factory, Penarth Road, Cardiff
Fluvial
0.1% chance only
S.5.6.6
p.59
96LGED Land adjacent to Llandaff Campus to river bank and rear of campus
Low Risk
Possible SW runoff
S.5.6.9
p.61
101LBEM Land off Dumballs Road, Cardiff Negligible S.5.6.10
p.61
111LGR Land north west of Great House Farm, Michaelston Road
Low Risk
Management of on site drainage channels.
S.5.6.1
p.56
![Page 99: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/99.jpg)
5097656-70-DG017-3.docx 89
Table 7-4 - Summary of Sub Area I - Bay Area to Pengam Green, Development Sites
Site ID Name/ Location Main Flood Risk Reference
71LBC Wales Millennium Centre 'Phase 3' Land
Surface Water S.6.3.1
p.73
58SBR Moorland Road, Cardiff Low risk
Tidal & Surface Water impacts to access routes
S.6.3.2
p.74
20LBU Queens Gate Car Park Surface Water S.6.3.3
p.74
19LBU Pengam Green Tidal S.6.3.4
p.75
18LBM Queen Alexandra Head Tidal S.6.3.5
p.77
60LBRM Porth Teigr (formerly known as Roath Basin South), Cardiff Bay, Cardiff
Tidal S.6.3.6
p. 78
57LBR Hannah Street, Bute Town, Cardiff Surface Water impacts to access routes
S.6.3.7
p.80
73LBRM Cardiff Graving Docks / Landsea Gardens / Landsea Square / Havannah Street car park, Cardiff Bay
Tidal S.6.3.8
p.81
101LBEM Land off Dumballs Road, Cardiff Negligible
See Area H
S.6.3.9
p.83
94LBR Colchester Avenue, Cardiff Tidal S.6.3.10
p.83
![Page 100: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/100.jpg)
![Page 101: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/101.jpg)
8. Appendices Appendix A - SFCA Area Overview Map
Appendix B – Area Specific Maps
Appendix C - Flood Depth and Area Tables
Appendix D – 2D Tidal Inundation Modelling.
Appendix E – Area A – 2D Tidal Inundation Modelling Assumptions and Results.
Appendix F – Area I (Pengam Green to Cardiff Bay) 2D Tidal inundation modelling
Appendix G – Assessment of risk of tidal inundation via Cardiff Docks to Cardiff Bay.
![Page 102: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/102.jpg)
![Page 103: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/103.jpg)
5097656-70-DG017-3.docx
Appendix A - SFCA Area Overview Map
A.1 Cardiff SFCA Area Overview Map – Drawing Number
5097656/RCF/002
![Page 104: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/104.jpg)
![Page 105: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/105.jpg)
5097656-70-DG017-4.docx
Appendix B – Area Specific Maps B.1 Drawing Numbers
5076243/RCF/120 – Area A - Wentloog Tidal. Flood Extents for 0.5% (1 in 200) Annual Chance Events – Current and with Climate Change to 2085 and 2110.
5076243/RCF/121 – Area A – Wentloog Tidal. 0.1% (1 in 1000) Annual Chance Flood event - 2010 Current Day. Predicted Maximum Flood Depths Contours
5076243/RCF/122 – Area A – Wentloog Tidal. 0.1% (1 in 1000) Annual Chance Flood event – 2010 Current Day. Predicted Velocity Contours
5076243/RCF/020/B – Area H – Cardiff West Central Taff & Ely. Flood Extents for 1% (1 in 100) Annual Chance Events – Current and with Climate Change to 2085 and 2110.
5076243/RCF/320 – Area H – Cardiff West Central Taff & Ely. Flood Extents for 1% (1 in 100) Annual Chance Events – Current and with Climate Change to 2085 and 2110.
5076243/RCF/321 – Area H - Cardiff West Central Taff & Ely. 0.1% (1 in 1000) Annual Chance Flood event – 2010 Current Day. Predicted Maximum Flood Depths Contours
5076243/RCF/322 – Area H - Cardiff West Central Taff & Ely. 0.1% (1 in 1000) Annual Chance Flood event – 2010 Current Day. Predicted Velocity Contours
5076243/RCF/420/B – Area I – Cardiff Bay to Pengam Green Flood Extents for 0.5% (1 in 200) Annual Chance Tidal Events – Current and with Climate Change to 2085 and 2110.
5076243/RCF/421/C – Area I – Cardiff Bay to Pengam Green. 0.1% (1 in 1000) Annual Chance Flood event - 2010 Current Day. Predicted Maximum Flood Depths Contours
5076243/RCF/422/B – Area I – Cardiff Bay to Pengam Green. 0.1% (1 in 1000) Annual Chance Flood event - 2010 Current Day. Predicted Velocity Contours.
![Page 106: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/106.jpg)
![Page 107: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/107.jpg)
Appendix C - Flood Depth and Area Tables
Areas A & H
![Page 108: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/108.jpg)
![Page 109: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/109.jpg)
5097656-70-DG017-3.docx
Table C.1 Proportion of Study Sites in Area A affected by Indicative Depths of flooding for 0.1% annual chance tidal flood event 2010
Site ID Name/ Location Existing Land Use Development Category Site
Area (ha)
Flood free or
<0.6m
>0.6m, <1.0m
>1.0m
76LGW South of Wentloog Avenue Previously Undeveloped Land
Waste Management Facility 60.0 36.6 12.5 9.2
22LGRM Trowbridge Mawr Previously Undeveloped Land
Residential/Industrial and Ancillary Community
35.0 35.0 0.0 0.0
21LGR Areas 9 - 12 St. Mellons Previously Undeveloped Land
Residential and Ancillary Community 18.8 20.4 0.0 0.0
23LGR Land bet. Crickhowell Rd and Willowbrook Rd Previously Undeveloped Land
Residential and Ancillary Community 5.6 5.6 0.0 0.0
24LGRM Land East of Cypress Drive, St. Mellons Previously Undeveloped Land
Mixed Use 9.5 9.2 0.0 0.0
74LGEMW Wentloog South of the Railway Line Previously Undeveloped Land
Employment and Waste 8.3 7.7 0.5 0.1
2LGRM Land at St. Mellons Business Park Previously Undeveloped Land
Mixed Use 3.9 4.0 0.0 0.0
1LGRM Land at Wentloog Levels Previously Undeveloped Land
Mixed Use 28.0 25.6 2.6 0.0
106LGEM Land at St Mellons/ Wentloog Previously Undeveloped Land
Mixed Use 71.0 72.6 0.4 0.0
GTchPk Action Area Previously Undeveloped Land
Green Tech Park 14.7 12.6 1.4 0.6
Wentloo_ii Action Area Previously Undeveloped Land
Business, Industry and Warehousing 15.6 15.6 0.0 0.0
Wentloo_iii Action Area Previously Undeveloped Land
Business, Industry and Warehousing 15.4 15.3 0.1 0.0
3SBR Pill Du Farm, Hendre Lane, Trowbridge, Cardiff Yard and Scrubland Residential 0.5 0.5 0.0 0.0
55LGR Trowbridge Road, Cardiff Greenfield Residential 2.6 1.5 0.0 0.0
56LBR St John‟s College Site, Greenway Road, Trowbridge, Cardiff
Brownfield Residential 2.5 2.5 0.0 0.0
![Page 110: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/110.jpg)
5097656-70-DG017-3.docx
Table C.2 Proportion of Study Sites in Area H affected by Indicative Maximum Depths of flooding for 0.1% annual chance fluvial flood event – 2010
Site ID Name/ Location Development Type
Total Site Area (ha)
Area of Site affected (ha)
Flood free or <0.6m
>0.6m, <1.0m >1.0m
8LGR West of Clos y Cwarra, Michaelston-super-Ely, Cardiff Residential 1.60 1.0 0.0 0.0
16LBR Ely Bridge, Western Business Centre, Cowbridge Road East
Residential/ Commercial/ Retail/ Community uses
22.30 0.8 2.1 2.6
17LGR Ely Bridge Farm, Dyfrig Road, Ely. Education & Mixed Use 0.70 1.0 0.0 0.0
31LBEM Land at Brindley Road, Leckwith, Cardiff Employment uses 8.00 1.0 0.1 0.1
32LGR Land at Michaelston Road, Cardiff Residential & Strategic Open Space.
9.80 1.0 0.0 0.0
36LBR Former Lansdowne Hospital Site, Sanatorium Road, Canton, Cardiff, CF11 8PL
Residential 1.60 0.4 0.5 0.5
52LBR Paper Mill Road , Cardiff , CF11 8PH Residential 0.80 0.6 0.3 0.1
61LBRM Penarth Road Car Park Site (adjacent Cardiff Central Railway Station) Riverside Sidings/ Semaphore House
Residential & Mixed-use 3.00 1.0 0.0 0.0
62LBR Land adjacent to Clive Lane Residential 2.50 1.0 0.0 0.0
70LBEM Central Square Commercial/ Public Transport Interchange
1.58 1.0 0.0 0.0
75SBR Land East of Great House Farm, Michaelston Road Residential 0.24 1.0 0.0 0.0
77LBR Ferry Road, Grangetown, Cardiff Residential 11.73 1.0 0.3 0.0
78LBRM Wholesale Fruit Centre Cardiff Residential/ Commercial/ Employment
7.00 0.7 2.1 0.2
83LBRM Former J R Freeman Factory, Penarth Road Mixed use – Employment/ Retail/ Residential
3.62 0.6 1.3 0.0
111LGR Land northwest of Great House Farm, Michaelston Road Residential 0.74 1.0 0.0 0.0
![Page 111: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/111.jpg)
5097656-70-DG017-3.docx
Appendix D – 2D Tidal Inundation Modelling.
D.1 Modelling approaches common to both Areas A & I
The 1D-2D hydraulic models have been constructed using ESTRY TUFLOW, which is an
industry standard hydraulic modelling software package. The models‟ outputs provide estimates
of both flood depths and flow velocities over the modelled extents.
The modelling of tidal overtopping and breach of the defences to the Severn Estuary is based on
a development of the approach and information gathered by the Environment Agency for the
Severn Estuary Flood Risk Management Strategy (SEFRMS).
Digital Elevation Model (DEM)
The Digital Elevation Models (DEM) of the study areas form a basis of the 2D hydraulic models.
The DEMs of the study areas have been generated using a combination of filtered LiDAR data
and NEXTMap data. The NEXTMap data has been used at places where the LiDAR data was
not available or the resolution was poor. The DEMs for both areas, A & I, were created by
extracting ground elevations on a computational grid having a cell size of 10m x 10m. The
chosen grid size of 10m provided a reasonable balance between level of topographic details
required to achieve accuracy appropriate for the nature of study, and reasonable model
runtimes.
The DEM is based on LiDAR available at November 2009.
D.2 Limitations of the modelling results
The 2D modelling provides a significant improvement in the level of confidence in the estimated
flood depths and velocities during extreme flood events and so informs the assessment of flood
consequences to the study sites. However, further detailed modelling will be required for site
specific studies, incorporating surveyed levels on the study sites themselves and key overland
flow routes. No testing of any proposed site layouts has been included as part of this strategic
modelling study.
D.3 Use of model results for sites not included in the SFCA Reports
The modelling for Area A and Area I has been developed specifically for the study sites listed in
the list of Study Sites in Section 3 and Section 4, respectively.
The results of the flood modelling should not be extrapolated to sites other than those specifically
listed in this report without due consideration being given to the assumptions inherent in the
model development. The confidence in the model results away from these sites will vary, being
affected by the assumptions made in developing the model.
![Page 112: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/112.jpg)
![Page 113: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/113.jpg)
5097656-70-DG017-3.docx
Appendix E – Area A – 2D Tidal Inundation
Modelling Assumptions and
Results.
E.1 Model Set-up
The model simulates the spreading out of tidal floodwaters onto and over the flood plain during
extreme tides which overtop and in places may breach the existing flood defences. It will also
estimate flood levels and velocities across the proposed development sites. It should be noted
that the model is not intended to predict flood levels upstream on the River Rhymney or River
Ebbw.
The Wentloog Levels area is considered at risk of tidal flooding resulting from overtopping from
rivers and overtopping and breach of the Severn Estuary defences. The methodology adopted to
predict tidal flood risks to the area and the key assumptions are set out below.
E.1.1 Spatial Extent of the Model
The Area A model covers the Wentloog Levels area. The western extent of the model is located
along the River Rhymney and the eastern extent is located along the River Ebbw. The Severn
Estuary shoreline forms the southern extent of the model.
E.1.2 Key Topographic Details
A site visit was undertaken prior to building the hydraulic model to assess key topographic
features which are likely to influence local flooding mechanisms and therefore need incorporating
into the model. Features such as the flood defences to the estuary, along the River Rhymney
and River Ebbw; the railway embankment and the culverts underneath it, are likely to affect
overland flow paths. The methods adopted to incorporate these features into the model and
modelling assumptions made are set out below.
Left Bank / Defence Levels on the Lower Rhymney
The levels along the left (eastern) bank of the River Rhymney would govern the volume of
floodwater overtopping from the river and potentially developing into overland flow paths towards
the study sites. These levels were extracted from the 1D HEC-RAS model of the River Rhymney
provided by the Environment Agency (EA Wales, Lower Rhymney and Roath Brook, v2 2007).
The bank levels were stamped onto the existing DEM, interpolating the levels between the
locations of the HEC RAS cross sections.
Since issue of the March 2010 SFCA 2D modelling addendum, an additional weakness in the left
bank defences was highlighted to the Severn Estuary Flood Risk Management Study
(SEFRMS17
) team by the Environment Agency‟s Area Flood Risk Manager. This improvement in
the available information has been incorporated into the SFCA hydraulic model for Area A. The
modelling of this newly identified location of potential breach in the defences is described in
section E.2.3, below.
Right Bank / Defence Levels on the River Ebbw
Limited topographic information on the bank levels along the River Ebbw is available and
therefore bank levels are based on the LiDAR data. These were compared with top of bank level
in an Environment Agency ISIS model of the lower River Ebbw. Retention of the LiDAR levels
17
Severn Estuary FRM Strategy, Baseline Flood Consequences Assessment, Working Draft Report, Environment Agency June 2009.
![Page 114: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/114.jpg)
5097656-70-DG017-3.docx
are considered a conservative assumption as LiDAR will tend to underestimate levels on the top
of defence structures.
Coastal Defence Levels along the Shoreline
These levels are based on detailed topographic survey18
which was undertaken for the
Environment Agency‟s SEFRMS19
.
Railway Embankment and Culverts Underneath
The Railway embankment which runs across the Wentloog Levels area serves as an informal
defence to prevent tidal flooding spreading overland north of the railway line. Levels along the
railway embankment are based on the LiDAR data.
Several culverts through the railway embankment exist which could allow conveyance of
floodwaters to the north of railway line. A site visit was undertaken to assess the significance of
these culverts to convey flows across the railway line. Culverts which are likely to affect flood
risks to the proposed development sites are incorporated into the model. No detailed topographic
survey data is available for these culverts. The sizes of some of the culverts were available from
the Network Rail. For the culverts where no data is available, sizes have been assumed based
on on-site observations and the channel width derived from maps of the area. Inverts for all the
culverts are based on the LiDAR data. These culverts are modelled as one-dimensional (1D)
elements in the model.
E.2 Key Hydraulic Assumptions
The Wentloog Levels area is considered at risk of tidal flooding due to a combination of
overtopping and breach of the coastal defences. The volumes entering the flood plain as a result
of breach of a defence far exceed those resulting from overtopping.
E.2.1 Modelling Breach of Defences
The coastal defences along the Wentloog levels have been assessed for susceptibility to breach
as part of the SEFRMS.
The formation of a breach in the defences is dependent on the flow of water down the back of
the defence structure as a result of overtopping. Once the tolerable flow of water is exceeded,
erosion of the structure will commence leading to failure and potentially breach of the defence.
The susceptibility of a defence will depend on a number of interrelated factors including the
defence height, type of defences, slope etc.
It is assumed that the defences will be maintained in their current condition and will be
maintained into the future. No raising of defences in the future is assumed. This results in an
increased probability of overtopping and breach of the defences if sea levels rise as predicted.
E.2.2 Joint Probability Still Water Tide Level and Deep Water Wave Height
The water overtopping a defence will result from a combination of the tide level (still water level
or SWL) and the coincident wave heights. As part of the SEFRMS the joint probability of a series
of tide levels and wave heights were assessed. For events of a given probability only a limited
number of combinations of tide level and wave will result in breach of the defence. As the tide
level (SWL) increases the coincident wave height decreases.
The joint probability assessment has been updated for the SFCA to reflect the new extreme tide
level estimates released by the Environment Agency in February 2011 (see Section 2.3.2).
18
Topographic Survey of flood defences (Infomap Ltd, May 2009) for SEFRMS 19
Severn Estuary FRM Strategy, Baseline Flood Consequences Assessment, Working Draft Report, Environment Agency June 2009.
![Page 115: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/115.jpg)
5097656-70-DG017-3.docx
E.2.3 Breach Locations and related model assumptions
Based on the detailed breach analysis methodology undertaken as a part of the SEFRMS study,
seven locations in the Wentloog levels are considered to be at risk of breach over the 100 year
period to 2110.
These locations are referenced20
as listed below and are marked on drawings 5097656/RCF-120
to RCF-122 in Appendix B.
SR1-RREB River Rhymney East Bank (downstream of rail bridge)
SR1-0 Little Wharf
SR1-1 Rhymney Great Wharf
SR1-2 Sluice Farm
SR1-3 Peterstone Great Wharf
SR1-6 Lighthouse Park
SR1-REWB River Ebbw West Bank
The numbers of locations considered susceptible to breach increases over the time horizons
considered, due to the effect of predicted sea level rise, as follows:
Table E.1 - Locations of Breaches for different time horizons and by event probabilities
Year Event chance Location References
2010 0.5% (1 in 200) SR1-RREB & SR1-2
0.1% (1 in 1000) As above plus SR1-0
2085 0.5% (1 in 200) As above plus SR1-3 & SR1-6
2110 0.5% (1 in 200) As above plus SR1-1 & SR1-REWB
The boundary conditions adopted to represent the breaches in the 2D model are those
developed for the SEFRMS. The main parameters defining the breach in the model are:
A period of 1 hour was set to represent the time for the full breach to form from the time of
its commencement.
All the these breaches are assumed to develop to 50m in width once initiated.
The toe levels to which the defences reduce at each breach location are:
SR1-RREB - 7.5mAOD
SR1-0 - 6.0mAOD
SR1-1, - 5.7mAOD
SR1-2 - 7.0mAOD
SR1-3 - 7.0mAOD
SR1-6 - 7.0mAOD
SR1-REWB 7.3mAOD
20
Note that the referencing of the breach locations has been changed since the March 2010 SFCA 2D modelling addendum to be consistent with the referencing used in the Environment Agency‟s SEFRMS project.
![Page 116: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/116.jpg)
5097656-70-DG017-3.docx
These levels are based on the higher of the average toe levels (base of the defence
embankment) on the landward or seaward side of the defences (or the river side in case of the
river defences).
Table E.1 includes combinations of Still Water tide Levels (SWL) and Deep Water Wave Height
(HO) which have been assessed to cause breach at each of the locations. The Table also
includes trigger levels (level at which breach is initiated) for different modelling scenarios. The
trigger level reflects the minimum SWL that is assessed to cause breach in combination with a
given HO.
E.2.4 Boundary Conditions
A spatially varying tidal boundary condition (tide levels versus time) along the shoreline has been
used to model overtopping and breach of the Severn Estuary defences during extreme tidal
events. The boundary condition has also been extended up the channels of the River Rhymney
and the River Ebbw to model overtopping of river banks.
River Ebbw
Along the River Ebbw, the tidal boundary condition extends up to A4042 roundabout (Docks
Way). Only limited topographic levels are available along the River Ebbw upstream of this
location. Inspection of the LiDAR data indicates that upstream of the A4042 roundabout area,
defences exist to the east of residential development at Beech Grove and Lighthouse Road.
Levels along these defences are higher than the tide levels. It should be noted that LiDAR data is
likely to underestimate the defence height and therefore in absence of accurate defence levels,
tidal boundary conditions were not extended upstream of A4042 roundabout.
It should be noted that the model is not designed to give detailed accurate results in the area of
the River Ebbw upstream of the A4042 roundabout. Any additional flood risk to the study sites
from this potential source is considered unlikely to be significant, given that the nearest site is
over 5½ km from the Ebbw. Caution should be exercised in interpreting the model results to
assess sites further east than the study sites listed in Table 3-1.
River Rhymney
Along the River Rhymney, the tidal boundary condition is extended to a point approximately 0.75
km north of the A48 roundabout. The defence levels upstream of this location are high enough
to prevent overtopping during the extreme tidal events tested and therefore, the tidal boundary
conditions are not extended beyond this location.
During extreme tidal events, the levels along the River Rhymney channel are likely to be higher
than the tide levels at its mouth due to the contribution of fluvial flows in the river channel. An
Environment Agency one-dimensional (1D) HEC-RAS model has been used to estimate
increases in level up the river channel during extreme tidal events. A 20% (1 in 5) annual
chance fluvial flow was routed against the extreme tide levels. 21
The resulting increase in water level up to the Newport Road bridge is less than 150mm for all
tide levels tested. The impact on flooding to the Wentloog levels is not significant. The elevated
water levels in the river channels are nonetheless incorporated into the model for completeness.
This is achieved by means of three level change points along the route of the Rhymney, the tide
levels being linearly interpolated along the model boundary.
These elevated water levels in the river channels have been used to simulate overtopping of the
defences.
21
In the absence of existing estimates of the QMED flow on the Rhymney or Roath Brook, we consider that use of the Q5 or 20% (1 in 5) annual chance flow represents a conservative approach. We have confirmed, based on analysis of ratios of ReFH flow estimates that the Q5 is greater than a QMED+20%. The Q5 has therefore also been used for the climate change scenario in 2060.
![Page 117: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/117.jpg)
5097656-70-DG017-3.docx
Change in Tide level along the Severn Estuary
The predicted tide level (SWLs) for an extreme event of a given annual chance will increase
along the Severn Estuary from the mouth of the Rhymney to the River Ebbw. This is
incorporated into the hydraulic model by interpolation of the tide levels.
Table E.2 shows tide levels used for different modelling scenarios and the variation in tide levels
between the River Rhymney and the River Ebbw.
E.3 Modelling Scenarios and Results
The latest development of the 2D inundation model has been run for different scenarios as listed
in Table E.2. The spread of floodwater as represented by the model have been analysed. The
predicted maximum flood depths and corresponding velocities for each scenario are plotted in
the drawings presented in Appendix B.
The consequences for each of the study sites are described in Section 3.3 of the main report.
An overview of the tidal flood risk to the Wentloog Levels, specifically that part within the Cardiff
Authority area, is given below.
0.5% (1 in 200) annual chance events, 2010
For the existing situation, base year 2010, flooding during 0.5% (1 in 200) chance tidal events
results from some overtopping from the Severn Estuary at Sluice Farm and the left (east) bank of
the River Rhymney. Currently the most significant source of tidal flooding is the predicted breach
of the Severn Estuary flood defence at Sluice Farm (SR1-2). (This section of the defence
currently has a 2% (1 in 50) annual chance of breach in any year based on the SEFRM
analysis). The flooding extends immediately northwest of the breach site, but does not extend
quite as far as the nearest study site (Site 74GEMW). The overland flow path does, however,
extend sufficiently north to cover the south eastern boundary of Site 1LGRM. The breach of the
defence on the River Rhymney downstream of the rail bridge is less significant.
The main access routes into the general Wenloog area would remain flood free for this event
currently.
0.1% (1 in 1000) annual chance events, 2010
The two events modelled, each with a 0.1% (1 in 1000) annual chance of exceedance, represent
the highest tide level and the lowest tide level at which breach will occur. The lower tide (SWL)
is coincident with a higher deep water wave height. The results of the modelling for these events
are presented on Drawing 5097656/RCF/121, Appendix B.
The breaches at Little Wharf and Sluice Farm result in wide spread flooding across the area;
although, within the Cardiff Authority area this is largely restricted to the seaward side of the
main rail line. The higher tide level of 9.2mAOD results in fewer breaches of the Severn Estuary
defences, but causes increased overtopping from the River Rhymney. As a result more water
spreads east along the route of the rail line and Lamby Way, but is not significant for the study
sites assessed.
Depths of flooding remain below 0.6m over the majority of the Cardiff Authority area. However,
depths do exceed 1.0m in a number of locations. This occurs in areas generally local to the
routes of the drainage channels or reens.
Of particular note is the roundabout on Lamby Way in the east of the area where depths are
predicted to exceed 1.0m with corresponding velocities greater than 0.45m/s. This is the main
access route west to the Rhymney crossing into Cardiff.
Depths and velocities are also indicated to be high at two locations of overland flows crossing
Mardy Road. This affects the main crossing north out of the Wentloog levels over the rail line.
![Page 118: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/118.jpg)
5097656-70-DG017-3.docx
Depths and velocities are predictably high local to the breach locations at Little Wharf (SR1-0)
and Sluice Farm (SR1-2). Site 76LGW is affected most. The impacts on all study sites are
described in relation to TAN15 A1.15 acceptability criteria in Section 3.3 of the main report.
It is also noted that flow velocities are high, in excess of 0.45m/s, at a localised area along the
rail line in the far west of the area. This does not affect the study sites directly, but may be worthy
of further investigation given this rail line‟s strategic importance to south Wales.
0.5% (1 in 200) annual chance events, 2085
This scenario, the shorter of the two development lifetimes considered, is used to assess
commercial sites against A1.14 of TAN15, i.e. the threshold of flooding.
By 2085 the Severn Estuary Defence at Peterstone Great Wharf is indicated to be susceptible to
breach during tidal events of 0.5% (1 in 200) annual chance, in addition to the locations at Sluice
Farm, Little Wharf and the left bank of the River Rhymney. The result is widespread flooding
extending over the Wentloog Levels area including the majority of study sites and the access
egress routes.
0.5% (1 in 200) annual chance events, 2110
The extent of the flooding during events of this annual chance is not significantly greater than for
2085, although sites at the edge of the area flooded in 2085 will be completely inundated, Site
3SBr, Site 24LGRM and 105LGEM.
There are two additional locations subject to breach during such events, but these are located a
considerable distance to the east in the Newport Authority area. Any impact on the study sites is
masked by the effects of the breaches more local to the study sites, indicated on the Drawings in
Appendix B.
![Page 119: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/119.jpg)
5097656-70-DG017-3.docx
Table E.2 - Sea level scenarios tested for Area A – considering the joint probability of surge tide level and wave height
YEAR
Tidal Events - Annual
Probability
Tide level variation
River Rhymney to River Ebbw
(mAOD)
Tide Level at which Breach starts at each location – mAOD to one decimal place
(coincident wave height required to cause breach)
Scenario Reference
SR1-RREB SR1-0 SR1-1 SR1-2 SR1-3 SR1-6 SR1-REWB
River Rhymney east bank
(No significant
wave climate)
Little Wharf Rumney Great Wharf
Sluice Farm Peterstone Great Wharf
Lighthouse Park
River Ebbw West Bank
2010
0.5% 8.6 to 8.9 8.2 No Breach No Breach No Breach No Breach No Breach No Breach SFCA_Scenario1_2011
8.2 to 8.5 8.2 No Breach No Breach 8.3
(0.81m wave)
No Breach No Breach No Breach SFCA_Scenario2_2011
0.1% 9.2 to 9.4 8.2 a
No Breach 8.8
(zero wave)
No Breach No Breach No Breach SFCA_Scenario3_2011
8.7 to 9.0 8.2 8.6
(0.7m wave)
No Breach 8.2
(0.9m wave)
No Breach No Breach No Breach SFCA_Scenario4_2011
2085
0.5% 9.2 to 9.5 8.2 9.1
(0.5m wave)
No Breach 9.1
(zero wave)
No Breach No Breach No Breach SFCA_Scenario5_2011
8.9 to 9.2 8.2 9.0
(0.9m wave)
No Breach 8.3
(0.9m wave)
8.8
(0.9m wave) No Breach No Breach SFCA_Scenario6_2011
2110
0.5% 9.6 to 9.9 8.2 9.6
(zero wave)
No Breach 9.1
(zero wave)
No Breach No Breach 9.8
(zero wave)
SFCA_Scenario7_2011
8.8 to 9.1 8.2 8.1
(1.3m wave)
8.5
(1.3m wave)
7.8
(1.3m wave)
8.4
(1.3m wave)
8.9
(1.3m wave)
No Breach SFCA_Scenario9_2011
![Page 120: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/120.jpg)
5097656-70-DG017-3.docx
E.4 Future Improvements
Two-dimensional hydrodynamic modelling has been undertaken to assess the risk of
tidal flooding to the proposed development site in the Wentloog Levels. The modelling
assumptions and the level of topographic and hydraulic details incorporated within the
model are based on the current available information.
We recommend that further improvements in the understanding of some of the
information and data used in the modelling should be investigated. It is possible that
further refinement of the hydraulic model may be appropriate for further analysis as
part of site specific FCAs.
Some areas to be investigated further are identified below:
Topographic survey of defence levels along the left bank of the lower Rhymney
would be required to confirm the levels used in the current modelling.
No assessment of the structural integrity of defences along the left bank of the
River Rhymney has been undertaken.
A location considered susceptible to breach on the left bank of the Rhymney
immediately downstream of the railway bridge has been incorporated. The level
of detail applied in this study should be improved upon if site specific
assessments are required of sites located nearer the potential breach location in
the west of the area.
The current study used flow sets which were supplied with the model by the
Environment Agency, and which are considered reasonable in assessing the
“order of magnitude” of increase in levels up the river channel. Given the small
increase in river levels relative to the magnitude of overtopping of the defence
levels used in the current study, we would not anticipate that revision of the
hydrology will significantly affect the flood risk to the Study Sites.
Culverts present underneath the railway embankment are based on data
supplied by the Network Rail. For culverts where data was not available, sizes
have been assumed based on on-site observations and channel width. It is
considered likely that more accurate information will confirm culvert dimensions
are narrower than those assumed in the model. We consider that the approach
adopted for the current study is conservative and will tend to overestimate
conveyance of tidal flood flow north of the rail line through the Wentloog levels.
Modelling of proposed site layouts would be required to identify any potential
impacts on flood risk elsewhere and to inform the development of potential
mitigation measures.
![Page 121: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/121.jpg)
5097656-70-DG017-3.docx
Appendix F – Area I (Pengam Green to
Cardiff Bay) 2D Tidal
inundation modelling
F.1 Model Set-Up
The study area of Pengam Green to Cardiff Bay is considered to be at risk of tidal
flooding resulting from overtopping both from the River Rhymney and over the
defences to the Severn Estuary. Breach of the Severn Estuary Defence is also a
potential source of flooding. The methodology of the 2D tidal inundation modelling
adopted to predict tidal flood risks to the study area and the key assumptions made
are set out below.
F.1.1 Spatial Extent of the Model
The Area I 2D model covers Pengam Green to Cardiff Bay area (excluding the
impounded Bay itself). The spatial extent of the model extends from the Cardiff Bay
area in the west to the River Rhymney in the east.
Figure F.1 - Extent of Area I Inundation Model
![Page 122: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/122.jpg)
5097656-70-DG017-3.docx
The Severn Estuary shoreline forms the south eastern extent of the model. The Roath
Brook runs across the north of the study area in a west-easterly direction.
F.1.2 Key Topographic Details
Key topographic and hydraulic features specific to the study area include flood
defences along the Roath Brook and River Rhymney, the culvert at the confluence of
the Roath Brook and River Rhymney, the railway embankment and culverts/openings
across railway embankment which may affect propagation of overland flow paths. Site
visits were undertaken prior to building the hydraulic model to assess key topographic
features which are likely to influence local flooding mechanisms and therefore, need
incorporating into the model. The methods adopted to incorporate these features into
the model and modelling assumptions made are set out below.
Roath Brook - Old Course and New Cut
The Roath Brook bifurcates into two routes at the Sainsbury‟s store site off Colchester
Avenue (see Figure F.1).
Figure F.1 - Location of the Old Course and New Cut of the Roath Brook and confluence
with the River Rhymney
The first route to the confluence of the Roath Brook with the River Rhymney is
referred to as the New Cut. This follows a north easterly direction to the confluence
just north of the A4232 roundabout with the Newport Road. The second route, which
is referred to as the Old Course, follows a general easterly direction to discharge to
the River Rhymney just north of the Lamby Way/Rover Way roundabout. This old cut
off channel is understood to only receive highway and surface water drainage from a
housing development to the south of Newport Road.
![Page 123: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/123.jpg)
5097656-70-DG017-3.docx
It is considered that overland flow paths from the Roath Brook could potentially affect
the proposed development sites and therefore, this watercourse is included in the
model.
Earlier versions of the model assumed that tide levels in the Rhymney would
propagate up both channels of the Roath Brook. However, information from the
Environment Agency suggests that the Old Course from Sainsbury‟s serves only as a
surface water drain. Any back flow up the Old Course is prevented by a flap vale on
the end of the culvert through which it discharges to the River Rhymney. By contrast,
since no such structure is present on the end of the culvert at the downstream end of
the New Cut, water is able to back flow up the New Cut of the Roath Brook when
flood levels are elevated in the River Rhymney.
For the tidal inundation model, tide level boundary has been incorporated into the
New Cut of the Roath Brook.
Right Bank / Defence Levels on the Roath Brook
The defence levels along the right bank of the Roath Brook would govern the volume
of floodwater overtopping the brook and subsequent development of overland flow
paths towards the study sites. These levels were extracted from the 1D ISIS22
model
of the Roath Brook provided by the Environment Agency. The bank / defence levels
were stamped onto the existing DEM.
Right Bank / Defence Levels on the River Rhymney
The defence levels along the right bank of the River Rhymney were provided by the
Environment Agency. These levels are based on topographic survey undertaken in
January 2009 by Total Surveys Limited for the Environment Agency Wales‟ Lower
Rhymney Embankments Standard of Service Assessment.
Defence Levels to the Severn Estuary
The frontage to the Severn Estuary from the mouth of the River Rhymney south to a
Travellers‟ Site on Rover Way (OSNGR 321781, 178578) is based on survey provided
by the Environment Agency. The levels south along the coast to the Cardiff Barrage
are based on LiDAR data.
Railway Embankment and Culverts Underneath
Levels along the railway embankment which runs across the study area are based on
LiDAR data. The Roath Brook Old Course is understood to be culverted under the rail
line. Inspection of the OS MasterMap data did not reveal any other culverts under the
railway embankment which could affect/influence the overland flow paths.
F.2 Key Hydraulic Assumptions
A review of the Environment Agency existing hydraulic models23
of the Lower
Rhymney and Roath Brook indicates that fluvial flood levels are lower than tidal flood
events of same chance of occurrence. i.e. over the lower reaches of the Rhymney
and Roath Brook tidal flood risk is considered to be dominant over fluvial.
Modelling Breach of Defences
The principles underlying the breach assessment for Area I are essentially the same
as those described for Area A in Appendix E.
22
Environment Agency Wales, ISIS model, Lower Rhymney and Roath Brook v3, 2008 23
Environment Agency Wales, HEC-RAS model, Lower Rhymney & Roath Brook, v2, 2007
![Page 124: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/124.jpg)
5097656-70-DG017-3.docx
A joint probability assessment of extreme tide levels (EWL) and coincident waves
heights along the coastal defences to Area I has been updated for the SFCA to reflect
the new extreme tide level estimates released by the Environment Agency in
February 2011 (see Section 2.3.2).
The susceptibility of the defences to breach along the Severn Estuary and the lower
reach of the River Rhymney bordering Area I was assessed by Atkins Limited as part
of the Environment Agency‟s Severn Estuary Flood Risk management Strategy
(SEFRMS).
Since it is assumed that the defences will be maintained in their current condition into
the future the probability of overtopping and breach of the defences increases into the
future, if the sea levels rise as predicted.
The formation of a breach in the defences is dependent on the flow of water down the
back of the defence structure as a result of overtopping. Once the tolerable flow of
water is exceeded, erosion of the structure will commence leading to failure and
potentially breach of the defence. The susceptibility of a defence will depend on a
number of inter-related factors including the defence height, type of defences and
slope.
The water overtopping a defence will result from a combination of the tide level (SWL)
and the coincident wave heights. As part of the SEFRMS the joint probability of a
series of tide levels and wave heights were assessed. For events of a given
probability only a limited number of combinations of tide level and wave will result in
breach of the defence. As the tide level (SWL) increases the coincident wave height
decreases. It is assumed that the defences will be maintained in their current
condition and will be maintained into the future. No raising or reinforcement of
defences in the future is assumed. This assumption results in an increased
probability of overtopping and breach of the defences if sea levels rise as predicted.
Based on the detailed breach analysis methodology, a single location on the Severn
Estuary defences to Area I is considered to be at risk of breach over the 100 year
period to 2110.
This is located on the coastal frontage to the Severn Estuary at Rover Way, Pengam
Green, shown labelled as SR1_RRWB on Figure F.1 above and Drawings
5097656/RCF/420 to 422, Appendix B.
The breach assessment of a range of EWL and wave height combinations indicates
that this location has a current standard of service in excess of a 0.5% (1 in 200)
annual chance event. This location is currently at risk of breach during a more
extreme 0.1% (1 in 1000) annual chance event. The probability of breach will
increase into the future.
The boundary conditions adopted to represent the breach in the Area I 2D model are
those developed for the SEFRMS. The main parameters defining the breach in the
model are:
A period of 1 hour for the full breach to form following its commencement.
The breach is assumed to develop to 50m in width once initiated.
The defence reduces to a toe level of 7.65mAOD following breach.
![Page 125: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/125.jpg)
5097656-70-DG017-3.docx
Boundary Conditions
A tidal boundary condition (tide levels versus time) along the Severn Estuary
shoreline has been used to model overtopping of tidal defences. The tidal boundary
condition has also been used along the Roath Brook and the River Rhymney to model
overtopping of defence and subsequent development of overland flow paths. Only
the New Cut course of the Roath Brook, downstream of the Sainsbury‟s store has
been incorporated into the model. The tidal boundary condition along the Roath Brook
extends to Roath Mill garden area, approximately 1.6 km from its confluence with the
River Rhymney. Upstream of this location, banks levels are such as to prevent any
overtopping during extreme tidal events.
Along the River Rhymney, tidal boundary condition extends up to A48 roundabout,
beyond which flood levels are unlikely to affect the proposed development sites.
During extreme tidal events, the levels along the River Rhymney and the Roath Brook
are likely to be higher than the tide levels in the Severn Estuary due to a contribution
of fluvial flows in the river channel.
The Environment Agency Wales‟ one-dimensional (1D) HEC-RAS model (Lower
Rhymney & Roath Brook, v2, HEC-RAS, 2007) has been used to estimate the
increase in water levels up the river channel by routing a 20% (1 in 5) annual chance
fluvial flows against extreme tides such as 0.1% (1 in 1000) and 0.5% (1 in 200)
annual chance events. In the absence of an estimate of QMED or 50% (1 in 2)24
annual chance flow, we consider that the use of 20% (1 in 5) annual chance flow
represents a conservative approach. The increase in water levels up the river
channels of the Roath Brook and River Rhymney are presented in Table F.1 - . These
elevated water levels in the river channels have been used to simulate overtopping of
the defences.
To incorporate the increases in water levels up the river channels in the event of tidal
events coincident with Q5 or 20% (1 in 5) annual chance fluvial flood flows, a number
of level change points have been used along the River Rhymney and the Roath
Brook. In total 2 change points have been used for the River Rhymney and 3 change
points for the Roath Brook. Tides were then linearly interpolated between these points
and input into the hydraulic model.
Table F.1 - shows tide levels which were used for the different modelling scenarios
and the increases in flood levels up the river channels due to coincident fluvial flows in
the River Rhymney and the Roath Brook
24
In the absence of existing estimates of the QMED flow on the Rhymney or Roath Brook, we consider that use of the Q5 or 20% (1 in 5) annual chance flow represents a conservative approach. We have confirmed, based on analysis of ratios of ReFH flow estimates that the Q5 is greater than a QMED+20%. The Q5 has therefore also been used for the climate change scenario in 2060.
![Page 126: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/126.jpg)
5097656-70-DG017-3.docx
Table F.1 - Tide Levels and increases up the Channels of the River Rhymney and Roath
Brook for the tidal scenarios modelled
Year Tidal Event
Probability
Tide levels
at Coast
Water levels at Change Points (mAOD)
Model Run Case Ref. ID
(mAOD)
Down-stream
extent of the
Roath Brook
Just north of Newport
Road Round-about
Approx. 0.35km north of
Sainsbury’s
Near Waterloo Gardens
Near Roath
Mill Gardens
(Change Point 1)
(Change Point 2)
(Change Point 3)
(Change Point 4)
(Change Point 5)
RHYMNEY XS 1116
RHYMNEY XS2554
ROATH XS 569.40
ROATH XS
1181.40
ROATH XS
1637.50
2010
0.50%
8.6 8.65 8.72 8.67 8.78 8.82 AREA"I"_CASE10 (1 in 200)
0.10%
9.2 9.2 9.26 9.22 9.3 9.33 AREA"I"_CASE 11 Sensitivity 2 (1 in 1000)
2085
0.50%
9.2 9.3 9.35 9.31 9.39 9.42 AREA"I"_CASE 12 Sensitivity (1 in 200)
0.50% 8.9 8.95 9 8.96 9.04 9.07 AREA"I"_CASE13
(1 in 200)
2110 0.50%
9.6 9.66 9.71 9.67 9.75 9.78 AREA"I"_CASE14 (1 in 200)
1 – Note: levels were applied in the model to the nearest one decimal point.
In addition to testing the overtopping from the rivers and the coastal frontage, the
probability of breach at the coastal frontage has been incorporated into the modelling.
The tide levels at which breach is initiated for the scenarios tested are given in the
following table.
Table F.2 – Breaches Assumed in Scenarios Area I Tidal inundation
Year Tidal Event Probability
Model Run
Case Ref. ID
BREACH @ SR1-RRWB (Coastal Frontage Pengam
Green)
2010 0.5%
(1 in 200) AREA"I"_CASE10 No Breach
0.1%
(1 in 1000) AREA"I"_CASE 11 Sensitivity 2
Breach commences at 9.0mAOD tide
2085 0.5%
(1 in 200) AREA"I"_CASE 12 Sensitivity No Breach
0.5%
(1 in 200) AREA"I"_CASE13
Breach commence at 8.9mAOD tide
2110 0.5%
(1 in 200) AREA"I"_CASE14
Breach commence at 8.7mAOD tide
![Page 127: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/127.jpg)
5097656-70-DG017-3.docx
F.3 Modelling Scenarios and Results
The model has been run for different scenarios as listed in Table F.1 - , above.
Predicted maximum flood depths and corresponding velocities for each scenario were
analysed to estimate worst case flood depths and corresponding velocities. The
results are presented on Drawings 5097656/RCF/420 to 422, Appendix.B.
Current Situation 2010
0.5% (1 in 200) Annual chance event 2010
Flooding during this event derives from overtopping from the River Rhymney and
Roath Brook.
The 2D model allows estimation of the overland flow paths from the locations of tidal
overtopping of right (west) bank of the River Rhymney, notably into the area of
allotment gardens upstream of the A4232 crossing of the Rhymney. Water from this
source flows west over Rover Way into Tremorfa and south, reaching the boundary of
Site 19LBU.
Overland flows from overtopping of the River Rhymney upstream of the main railway
line d combine with those overtopping the right bank of the Roath Brook to inundate
the Newport Road area. Flooding to this area extends up Colchester Avenue to
inundate across Site 94LBR. Flooding from both banks of the Roath Brook at the
Waterloo Gardens Area does not affect any of the study sites.
Flood water is also indicated to spread along the main railway line, extending
approximately 750m west of the Rover Way crossing over this rail line.
0.1% (1 in 1000) Annual chance event 2010
As well as overtopping, the breach of the coastal defence at SR1-RRWB (see Figure
F.1) close to the Study Site 19LBU contributes to extensive flooding across the
Tremorfa and Pengam Green area.
Greater overtopping volumes from the right bank of the River Rhymney and the Roath
Brook enter the flood plain by the same mechanisms as described above for the 0.5%
chance event. In addition direct overtopping from the River Rhymney occurs
immediately east of Site 19LBU.
The flood water from north of the main rail line flows south and merges with the
overland flows overtopping south of the railway line.
Flood water also derives from the breach of the coastal defence south of Site 19LBU,
merging with the flow paths from the north on this site.
Floodwater would also extend approximately 800m further west along the main
railway line compared to the 0.5% (1 in 200) annual chance event.
0.5% (1 in 200) Annual chance events, 2085
As a result of the higher tide levels, a greater volume of floodwater enters the
floodplain and the overland flow paths extend further south and west across the
Tremorfa area and Study Site 19LBU particularly. North of the Roath Brook, the flood
extents are greater than the 2010 base year, with significantly greater depths of water
on Study Site 94LBR and the surrounding area, including the access/egress routes for
the site. In addition to the overtopping from the Roath Brook and River Rhymney,
overtopping and breach of the coastal defences contributes significantly to the
volumes of flood water, causing extensive flooding across site 19LBU.
![Page 128: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/128.jpg)
5097656-70-DG017-3.docx
The overland flow along the main rail line extends further west, with some flooding to
roads away from the immediate locality of the rail line, although this flow path does
not impact any of the Study Sites over this time horizon.
0.5% (1 in 200) Annual chance events, 2110
The greater volumes entering the flood plain from the River Rhymney, the Roath
Brook and the coastal frontage result in more extensive flooding than the situation in
2085. Overland flows from the Tremorfa area, east of the Dock rail line merge with
flows which develop south from the main Swansea London rail line. The modelling
indicates that large areas of Splott and Tremorfa will be flooded during a 0.5% (1 in
200) tidal event by 2110. It is noted that Study Site 58SBR in the Splott area would
remain flood free.
In the west of the area, the modelling indicates that the 0.5% (1 in 200) annual chance
tide level of 9.4mAOD would overtop the dock gates and the local area. The high
ground levels bordering this area serve to contain the extent of flooding. The limited
time of the overtopping and the limited flow conveyance area, results in the flood level
in the Roath Basin Docks being very much less than the tide level in the open coast of
the Severn Estuary. The flood level which develops in the Roath Basin Docks will
depend on the exiting dock water level prior to the extreme tide. A relatively small
area of Study Site 60LBRM would be affected by 2110.
In summary, the 2D model provides improved estimates of the local distribution of
flood water through the area assessed.
F.4 Future modeI refinements for site specific studies
We suggest that further investigation into some of the information used in the
modelling should be undertaken. It is possible that further refinement of the hydraulic
model may be appropriate for further analysis as part of site specific FCAs.
Some areas to be investigated further are identified below:
The Environment Agency are currently undertaking 2D modelling of the lower
Roath Brook which may provide a source of improved information.
Improved topographic survey of the defence levels along the left bank of the
Roath Brook would improve the level of confidence in the model results,
particularly for sites north of the Roath Brook. It is unlikely that this will change
the baseline condition for the future scenarios. It will be required to inform
mitigation options.
Investigation should be undertaken to confirm the arrangements of any structures
(such as flap valves) on the outfalls of the two routes of the Roath Brook at their
respective confluences with the River Rhymney. The current model assumes a
functioning flap valve on the Old Course.
No detailed assessment of the structural integrity of defences along the River
Rhymney has been undertaken. The current model assumes that defences
would not fail during extreme events. Site specific detailed study would need to
consider the possibilities of defence breach, building on the “Standard of Service
Assessment” undertaken in 2005 by Atkins on behalf of the Environment Agency.
The results of such a detailed assessment of the probability of breach of the
River Rhymney defences could have an impact not only for potential
development at Study Sites but also for the risk to existing properties in Area I.
More detailed hydrological assessment of the River Rhymney and Roath Brook
could be undertaken to confirm the increases in water levels up the river
![Page 129: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/129.jpg)
5097656-70-DG017-3.docx
channels due to fluvial flows coincident with extreme tidal events. However, we
consider that in this current study, the use of the flow sets supplied by the
Environment Agency with the HEC RAS model, are likely to be reasonable in
assessing the “order of magnitude” of increase in levels up the river channel. We
would not expect this to have a significant impact on the volumes of water
entering the flood plain and the resulting overland flows to the Study Sites.
Modelling of proposed site layouts would be required to identify any potential
impacts on flood risk elsewhere and to inform the development of potential
mitigation measures.
Before undertaking on any further modelling as part of site specific studies, the
Environment Agency should be consulted for the results and limitations of the 1D - 2D
inundation model of the Roath Brook which is currently under development.
![Page 130: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/130.jpg)
![Page 131: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/131.jpg)
Appendix G – Assessment of risk of
tidal inundation via Cardiff
Docks to Cardiff Bay.
G.1 Model Set-Up
The potential for extreme tide levels to enter Cardiff Bay from the Docks via Roath
Basin Dock were tested by developing a 1D-2D ISIS TUFLOW hydraulic model.
The methodology of the 1D-2D tidal inundation modelling adopted to predict tidally
dominated flood risks to Cardiff Bay and the key assumptions made are set out below.
G.1.1 Spatial Extent of the Model
The 1D element of the model comprises the Bay model described in outline in Section
5.3.2 of the main report.
Overland flow from Roath Basin to Cardiff Bay
The 1D ISIS model of the Bay described in Section 5.5.5 of the SFCA was developed
and combined with a new section of 2D domain covering the Roath Basin and the
land bordering the eastern Bay. This 1D-2D ISIS TUFLOW model was used to test
the extent of overland flow from the Roath Basin into the Bay and the effect on peak
water levels in the Bay.
Channel and bund separating Roath Basin Dock from Cardiff Bay
Under normal operating conditions the water in Cardiff Docks is prevented from
entering Cardiff Bay by a bund located in an old lock channel adjacent to the
Norwegian Church (structure shown in Figure G.1 - and location shown on Figure
G.3 ).
This channel and bund were represented by adding a 1D link section of channel to the
1D ISIS model of Cardiff Bay (described in section 5.3.2). The bund itself is
represented as a spill unit. The dimensions of the link sections were estimated from
OS Mastermap25
data. The widths of the channel sections of the link are set at 25m
and the invert level is an assumed level of -1.7mAOD. The error in estimating the
depth of the channel and so the velocity losses calculated in the model are likely to be
small and are considered appropriate for a strategic level assessment. Overall each
section is 95m wide to include the flow in the out of channel area of the dockside
bordering the lock. The spill level is set at 7.6mAOD based on the LIDAR levels to the
top of the bund.
The resulting 1D ISIS model was linked to a 2D TUFLOW domain to represent the
area of overland flow around the Roath Basin and into Cardiff Bay. The 2D domain
was created based on LIDAR levels.
The 1D ISIS geometry is presented schematically on Figure G.2, below.
The extent of the 2D domain is indicated by the black & magenta outline on Figure
G.3.
25 © Crown Copyright. Cardiff County Council, 100023376 (2011)
![Page 132: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/132.jpg)
Figure G.1 - Bund separating Roath Basin Dock from Cardiff Bay. View from Roath Basin
Figure G.2 - 1D ISIS Geometry
![Page 133: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/133.jpg)
The overland flows spilling into the Bay (i.e. not via the 1D link channel) were
estimated by allowing the water reaching the edge of the 2D domain to spill into
infinity. The volumes spilling were estimated using “po lines” within the TUFLOW
model along the boundary of the 2D domain with the edge of the Bay. These are
shown as green lines on the Figure below.
Figure G.3 - Extent of area of 2D domain to test overland flow paths into Cardiff Bay.
Green lines are po lines in the TUFLOW model
The area of the Bay in the model is 1.64km2. Dividing the volume of water crossing
the po lines within the model by this area provides an estimate of the order of
increase in the Bay level. This additional level is added to the peak modelled water
level calculated within the 1D ISIS model to derive an estimated peak level in Cardiff
Bay.
Note that the flow over the bund separating the Roath Basin from the Bay is
accounted for directly in the 1D ISIS link (sections Dock_Sect to CH0002 shown in
schematic Figure G.1)
![Page 134: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/134.jpg)
G.2 Key Hydraulic Assumptions
G.2.1 Operation of the lock gates to Queen Alexandra Dock
The operation of the lock gates to Cardiff Docks is based on information obtained
from the port operators, ABP Limited.
The lock to Queen Alexandra (QA) Dock connects Cardiff Docks to the Severn
Estuary. However, these lock gates cannot restrain tides higher than the level in the
QA Dock. To remain in the closed position a positive head is required, i.e. a higher
level in the QA Dock relative to the tide level in the Severn Estuary.
The normal water level in the dock is 6.71mAOD i.e. 13.01m above Admiralty Chart
Datum (mACD).
The level to the top of the lock gates is 7.7mAOD and the sill level to the lock
entrance is understood to be -6.7mAOD.
The impounded dock level can be increased up to a maximum of 7.3mAOD
(13.6mACD). Therefore, a positive head of water can be maintained inside the dock
for any height of tide up to 7.3mAOD and the lock gates can be retained in the closed
position.
However, for tide elevations above 7.3mAOD, the lock gates are opened and the level
in the dock equalises with that of the tide at the lock entrance. The gates can be
closed once the tide has dropped below 7.3mAOD.
This level compares with the range of 8.4mAOD to 9.4mAOD extreme tide levels
tested for the SFCA.
G.2.2 Boundary Conditions
The Area I 2D inundation model, described in Appendix F, was extended to the
eastern end of the Cardiff Barrage to include the entrance to the QA Dock.
This 2D model was run to test the effect of the lock gates being open during extreme
tide events. This confirmed that the order of magnitude of the conveyance available
through the locks is sufficient for the extreme tide levels to be achieved throughout the
docks to the Roath Basin (the dock immediately east of the impounded Cardiff Bay).
It was established that the level in the Roath Basin will vary, to a close approximation,
with the tide level in the Severn Estuary for tide levels above 7.3mAOD.
As a result, a head-time (HT) boundary of the extreme tide cycles was applied within
the Roath Basin in the 2D domain in the 1D-2D ISIS TUFLOW model.
A separate HT tidal boundary is also applied in the 1D ISIS model, the downstream
boundary (TF_DS_001) on the Severn Estuary side of the sluice gates representing
the Cardiff Bay Barrage.
The fluvial flows into the Bay from the rivers Taff and Ely are applied as flow-time
(QT) boundaries at the top of the respective reaches in the 1D model.
A QMED flow estimate for the Taff and a Q5 estimate for the Ely were assumed to
occur with each tide event tested.
Flow estimates derived from existing Environment Agency models were used. The
combined Ely-Taff 1D-2D ISIS TUFLOW model does not contain a QMED estimate.
A QMED estimate was taken from an earlier model developed for the Environment
Agency, the Lower Taff 1D ISIS Flood Risk Mapping update, November 2007. No
QMED estimate was available for the River Ely. As a surrogate, a 20% (1 in 5) annual
![Page 135: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/135.jpg)
chance estimate (Q5) was taken from the Environment Agency, River Ely 1D ISIS
model, CFMP, 2008. For the future scenarios a 20% increase in fluvial flow was
applied to the QMED on the Taff. No increase in flow was applied to the River Ely Q5
estimate as this is considered to approximate the QMED +20%.
The model flows for the Ely represent an over estimate of a QMED flow. This was
considered reasonable given the Ely‟s relatively small contribution to overall flow into
the Bay at the peak of the tide. The Taff flow is assumed to occur at the same time as
the peak of the tide. The Ely peaks some 5hours after the peak on the Taff.
G.3 Modelling Scenarios and Results
This combined 1D-2D ISIS TUFLOW model was used to:
a) Determine the extent of flooding during extreme tide events
b) The depths and velocities in the overland flow paths from the Roath Basin to
Cardiff Bay.
c) Calculate the volumes of overland flow entering the Bay
Note: For areas of the Docks outside the 2D domain of the model, the tide levels were
contoured over the LIDAR and a depth grid calculated within a proprietary GIS
software package. No velocity profiles were therefore available for areas outside the
limits of the 2D domain representing the western Roath Basin.
G.3.1 Scenarios Modelled
The boundary conditions were applied for each of the scenarios as listed in Table 8.1.
Two sets of model runs were:
1. The existing situation with respect to the lock gates to Cardiff Queen Alexandra
Dock being open during extreme high tides.
2. Mitigation situation – assumes that water is prevented from entering Cardiff Bay
from the Roath Basin Dock.
Table 8-1 Scenarios modelled in 1D-2D ISIS TUFLOW model of Cardiff Bay and Roath
Basin - current and future extreme tidal events
Assumes coincident QMED flows in the River Taff and River Ely**
Scenario Tide level (mAOD)
Peak Fluvial flows
TIDAL EVENT
Annual Chance
YEAR River Taff
River Ely**
0.1% (1 in 1000) 2010 9.0 360 78
0.5% (1 in 200) 2085 9.1 429 78
0.5% (1 in 200) 2110 9.4 429 78
* Open Lock Gates is current situation
** Ely Q5 Flow used as existing QMED estimate not available
![Page 136: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/136.jpg)
G.3.2 Results
Table 8-2 Levels resulting in Cardiff Bay for current and future extreme tidal events
Assumes coincident QMED flows in the River Taff and River Ely
Scenario Tide level
(mAOD)
TIDAL EVENT
(Annual Chance)
YEAR Assumption regarding flow path
from Roath Basin into
Cardiff Bay
Peak Model Bay
Level - excludes overland
flow
(mAOD)
Volume Spilling into Bay
via overland flows.***
(m3)
Derived increase in Bay level
(m)
Final Estimated Bay Level
m(AOD)
0.1%
(1 in 1000)
annual chance
2010
9.0 Existing condition - Dock Lock Gates open
7.66 3,123 0.002 7.66
9.0 No flow from Roath
Basin
7.58 N/A N/A 7.58
0.5% (1 in 200) annual chance
2085
9.1 Existing condition - Dock Lock Gates open
8.06 32,108 0.02 8.08
9.1 No flow from Roath
Basin
7.96 N/A N/A 7.96
0.5% (1 in 200) annual chance
2110
9.4 Existing condition - Dock Lock Gates open
8.22 111,069 0.07 8.29
9.4 No flow from Roath
Basin
8.11 N/A N/A 8.11
*** Flows extracted from po lines in TUFLOW 2D domain
The resulting extents and depths of flooding are presented in the Drawings in
Appendix B and the consequences for the Candidate Sites discussed in Section 6 of
the main Report.
![Page 137: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/137.jpg)
![Page 138: Cardiff Strategic Flood Consequences Assessment Phase … · Cardiff Strategic Flood Consequences Assessment Phase 2 Part 1 Update Extend Development Lifetime to 2110 Areas A, G,](https://reader030.fdocuments.us/reader030/viewer/2022021707/5b9ea53e09d3f2fc778c46eb/html5/thumbnails/138.jpg)
Atkins Limited West Glamorgan House 12 Orchard Street Swansea SA1 5AD Telephone: +44(0)1792 641172 Fax: +44(0)1792 472019
Atkins Limited West Glamorgan House 12 Orchard Street Swansea SA1 5AD Telephone: +44(0)1792 641172 Fax: +44(0)1792 472019