CAPTIVE POWERPOLICY
Prepared by-Nitesh Gupta
-
7/28/2019 Captive policy.pptx
2/10
InceptionSection 44 of the Electricity(Supply) Act, 1948 gave birth toCaptive Generation.
Any person (other than central govt. gencos ) toestablish or to acquire a new generating station orto extend any major unit of plant has to takepermission from SEB
If capacity > 25MW then SEB required to consultCEA
-
7/28/2019 Captive policy.pptx
3/10
Definition given under IEA 2003
These restrictions & control on captive generation inSupply Act, 1948 is removed under Electricity Act2003, Section 2
(8) Captive generating plant means a power plantset up by any person to generate electricity primarilyfor his own use and includes a power plant set up by
any co-operative society or association of persons forgenerating electricity primarily for use of members ofsuch cooperative society or association.
Captive generation is generation primarily
-
7/28/2019 Captive policy.pptx
4/10
Section 9. (Captive generation):(1)A person may construct, maintain or operate a captive
generating plant and dedicated transmission lines primarily forhis own use, and he can sell the surplus power available to the
grid.
Owner can construct dedicated transmission line for carryingelectricity from captive plant to the destination.
No requirement of license for supplying power to a licensee andopen access consumer
-
7/28/2019 Captive policy.pptx
5/10
Section 9. (Captive generation):(2)Electricity generated from captive plant can be transmit throughthe grid to the destination.
He should have the right to open access in the interveningtransmission facilities, subject to availability of transmission capacity.
Availability of Transmission facility determined by the central/ stateTransmission Utility
Dispute if any on the issue shall be studied and settled upon by theAppropriate Commission.
-
7/28/2019 Captive policy.pptx
6/10
National electricity policyCaptive power plant facilitate the creation of employmentopportunities through speedy and efficient growth ofindustry.
Captive power plant help in meeting the demand forpower by harnessing the surplus capacity.
Grid inter-connections for captive generators shall befacilitated as per section 30 of the Act(Transmissionwithin a State).
-
7/28/2019 Captive policy.pptx
7/10
National Tariff PolicyDistribution licensees can buy power fromCaptive Plant using the guidelines issuedby the Central Government under section
63 of the Act.
Captive generators can be allowed toinject into the grid under the AvailabilityBased Tariff (ABT) mechanism.
-
7/28/2019 Captive policy.pptx
8/10
Electricity Rules 2005Not < than 26 % of the ownership should be
held by the captive user and
Not < than 51 % of the aggregate electricitygenerated in such plant, determined on anannual basis, should be consumed for the
captive use.
-
7/28/2019 Captive policy.pptx
9/10
Policy of Maharashtra on Captive
power PlantIndustrial unit using captive genration atleast 75%
of total installed capacity
Balance 25% should be sold to any 2 third partiesin any state through wheeling
Clearance may also be granted for setting up of acaptive power plant by a company on the condition
that the user company owns at least 51 per centshare of the generating company.
Such companies will be permitted for sale ofsurplus electricity
-