Capstone Project FINAL

18
Master Bathroom Renovation By: Cindy Cabalo

Transcript of Capstone Project FINAL

Page 1: Capstone Project FINAL

Master Bathroom RenovationBy: Cindy Cabalo

Page 2: Capstone Project FINAL

Project Description

I have chosen a Master Bathroom Renovation as my capstone project. This is a real life project I have offered to help my sister with. She wanted to see it would look like with a different layout, as well as to see an estimated cost of renovation.

Page 3: Capstone Project FINAL

Scope of Work• Develop renovation plans• Site survey of existing floor plan • Preserve all existing interior and exterior

walls• Research materials• Fixtures, Flooring, Vanity, Paint

• Create new floor plan • AutoCAD • 3D Drawing• Rendering • Camera Views

• Cost Analysis

Page 4: Capstone Project FINAL

Weekly Progression Schedule• Week 1 & 2: Project proposal & Survey Current Bathroom• Week 3 & 4: Draft Floor Plan into AutoCAD • Week 5 & 6: AutoCAD – Create current layout of bathroom• Week 7 & 8: Research materials, colors, and styles.• Week 9: AutoCAD – Create new layout of renovated bathroom and add

materials• Week 10: Putting together cost analysis and materials• Week 11: Finalize and Completion of Project• Week 12: Final Presentation

Page 5: Capstone Project FINAL

Survey Notes

Master Bedroom & Master Bath Dimensions of Doorway & Windows

Page 6: Capstone Project FINAL

Existing Floor Plan

Page 7: Capstone Project FINAL

Existing Bathroom

Master Bathroom EntranceCamera View of Vanity, Tub, & Shower

Page 8: Capstone Project FINAL

Inspirations

Walk-In Shower Tile Work

Page 9: Capstone Project FINAL

Inspirations (cont.)

Barn Doors Vanity

Page 10: Capstone Project FINAL

New Floor Plan

Sectioned – Master BathroomMaster Bedroom & Bathroom

Page 11: Capstone Project FINAL

Materials of Choice

Page 12: Capstone Project FINAL

DEMOLTION COST TOTAL COMMENTS

Dumpster Rental $549 $549 15yd dumpster, up to 6000lbs. 10 Day rental includes delivery fee, pickup fee, and applicable taxes.

Plumbing $3000 n/a Average Cost to change plumbing

Cost Analysis

MATERIALS COST QTY TOTAL COMMENTS

Paint $124.98 1 $124.98 Sherwin-Williams Extra White Satin Interior Pain and Primer in One

Vanity, glass counter top & dual sinks

$1549 1 $1549Wyndham Collection Avara Espresso Vessel Double Sink Oak Bathroom Vanity with Tempered Glass and Glass Top, includes matching medicine cabinet mirrors and side shelves.

Sink Faucets $159 2 $318 Delta Nyla Stainless 1 Handle Vessel WaterSense Bathroom Faucet, Drain Included

Shower Fixtures $59.55 2 $119.10 DreamSpa Chrome Rain Showerhead

Page 13: Capstone Project FINAL

Cost Analysis (cont.)

MATERIALS COST QTY TOTAL COMMENTS

Tiles – Shower Walls $21.50 110 sq/ft $2365 Pental G&M Streamline Porcelain. Brown & Cream 12 x

24Tiles – Shower Floor $21.50 37 sq/ft $795.50 Pental G&M Streamline Porcelain. White 12 x 24

Glass Panels $288.40 2 $576.80Bath Authority Dreamline Linea Frameless Shower Door Panel (30 x 72) Brushed Nickel Finish Hardware

Barn Doors $1710 n/a $1710 Real Sliding Hardware. Includes 2 Doors, tracks, hardware

Bamboo Flooring – Main Bathroom Floor $3.99 107

sq/ft $426.93 Cali Bamboo 4.05in Prefinished Bamboo Hardwood Flooring (Java Click Fossilized)

Estimated Cost of Materials & Demolition (Pre-Tax) $11,534.31

Page 14: Capstone Project FINAL

Renovated Bathroom

New Barn DoorsEntrance to Bathroom

New Vanity and Hardwood Floors

Page 15: Capstone Project FINAL

Updated Bathroom

Walk-In Dual ShowerInside Walk-In Shower

Page 16: Capstone Project FINAL

References• (n.d.). Retrieved January 05, 2016, from

https://www.realslidinghardware.com/barn-door-hardware-photo-gallery-pg-5

• Bathroom Addition & Renovation Costs. (n.d.). Retrieved February, 2016, from http://www.homeadvisor.com/cost/bathrooms/#ashower

• DreamSpa 12-in 2.5-GPM (9.5-LPM) Chrome Rain Showerhead. (n.d.). Retrieved February 21, 2016, from http://www.lowes.com/ProductDisplay?partNumber=539720-741981489&catalogId=10051&storeId=10151&langId=-1&productId=50422686

• Wyndham Collection Avara Espresso Vessel Double Sink Oak Bathroom Vanity with Tempered Glass and Glass Top (Common: 72-in x 23-in; Actual: 72-in x 22.5-in). (n.d.). Retrieved February 21, 2016, from http://www.lowes.com/pd_154052-43095-WCS007SH72ESGRD28WH__?productId=50070763&pl=1&Ntt=wyndham collection

• Lowes: HomePaint Paint & Primer Interior Paint. (n.d.). Retrieved February, 2016, from http://www.lowes.com/pd_756340-678-OV0024001-20_1z0yye5__?productId=999918710&pl=1

• Modern Bathroom: Bath Authority DreamLine Linea Frameless Shower Door Panel (30" x 72"). (n.d.). Retrieved February, 2016, from http://www.modernbathroom.com/showers-tubs/bath-authority-dreamline-linea-frameless-shower-door-panel-30-x-72-__shdr-3230721.aspx

Page 17: Capstone Project FINAL

References (cont.)• (n.d.). Retrieved January 05, 2016, from

https://www.realslidinghardware.com/barn-door-hardware-photo-gallery-pg-5 • BudgetDumpster.com. (n.d.). Retrieved February, 2016, from

http://www.budgetdumpster.com/seattle-wa-dumpster-rental-washington.php • Lowes: HomeBathroom Bathroom Faucets & Handles Bathroom Faucets. (n.d.).

Retrieved February, 2016, from http://www.lowes.com/pd_356756-72981-17708LF_0__?productId=3518000&Ntt=

Page 18: Capstone Project FINAL

THANK YOU