capitalBudgetingChp9

download capitalBudgetingChp9

of 37

Transcript of capitalBudgetingChp9

  • 8/8/2019 capitalBudgetingChp9

    1/37

    Chapter

    McGraw-Hill/Irwin Copyright 2006 by The McGraw-Hill Companies, Inc. All rights reserved.

    9

    Net Present Value and

    Other Investment Criteria

    Net Present Value and

    Other Investment Criteria

    Revised by DBH, January 2006

  • 8/8/2019 capitalBudgetingChp9

    2/37

  • 8/8/2019 capitalBudgetingChp9

    3/37

    9-2

    Project Example Information

    You are looking at a new project and youhave estimated the following cash flows:

    Year 0: CF = -165,000

    Year 1: CF = 63,120; NI = 13,620

    Year 2: CF = 70,800; NI = 3,300

    Year 3: CF = 91,080; NI = 29,100

    Average Book Value = 72,000

    Your required return for assets of this riskis 12%.

  • 8/8/2019 capitalBudgetingChp9

    4/37

    9-3

    Payback Period

    How long does it take to get the initial costback in a nominal sense?

    Computation

    Estimate the cash flows

    Subtract the future cash flows from the initialcost until the initial investment has been

    recovered Decision Rule Accept if the payback

    period is less than some preset limit

  • 8/8/2019 capitalBudgetingChp9

    5/37

    9-4

    Computing Payback For TheProject

    Assume we will accept the project if it paysback within two years.

    Year 1: 165,000 63,120 = 101,880 still torecover

    Year 2: 101,880 70,800 = 31,080 still torecover

    Year 3: 31,080 91,080 = -60,000projectpays back in year 3

    Do we accept or reject the project?

  • 8/8/2019 capitalBudgetingChp9

    6/37

    9-5

    Decision Criteria Test - Payback

    Does the payback rule account for the timevalue of money? (No)

    Does the payback rule account for the riskof the cash flows? (No)

    Does the payback rule provide anindication about the increase in value?

    (No)

    Should we consider the payback rule forour primary decision rule? (No)

  • 8/8/2019 capitalBudgetingChp9

    7/37

    9-6

    Advantages and DisadvantagesofPayback

    Advantages

    Easy to understand

    Adjusts for uncertainty

    of later cash flows Biased towards

    liquidity

    Disadvantages

    Ignores the time valueof money

    Requires an arbitrarycutoff point

    Ignores cash flowsbeyond the cutoff date

    Biased against long-term projects, such asresearch anddevelopment, and newprojects

  • 8/8/2019 capitalBudgetingChp9

    8/37

    9-7

    AAR and Discounted Payback

    Discounted paybackis a variation on thepayback rule that does allow for the time value ofmoney, but still requires an arbitrary cutoff.

    Average Accounting Return (AAR) doesnt evenmeasure cash flows, but only whether averageaccounting income from the project = a setpercentage of return

    Neither effectively measures whether a long-terminvestment has added value to the firm. Forsake of time, we will ignore these methods.

  • 8/8/2019 capitalBudgetingChp9

    9/37

    9-8

    Net Present Value

    The difference between the market valueof a project and its cost

    How much value is created from

    undertaking an investment? The first step is to estimate the expected

    future cash flows.

    The second step is to estimate the requiredreturn for projects of this risk level.

    The third step is to find the present value ofthe cash flows and subtract the initialinvestment.

  • 8/8/2019 capitalBudgetingChp9

    10/37

    9-9

    NPV Decision Rule

    If the NPV is positive, accept the project

    A positive NPV means that the project isexpected to add value to the firm and willtherefore increase the wealth of theowners.

    Since our goal is to increase ownerwealth,

    NPV is a direct measure of howwell thisproject will meet our goal.

  • 8/8/2019 capitalBudgetingChp9

    11/37

    9-10

    Computing NPV for the Project

    Using the formulas:

    NPV = 63,120/(1.12) + 70,800/(1.12)2 +91,080/(1.12)3 165,000 = 12,627.42

    Many financial calculators also havetemplates for calculating NPV

    Easiest to calculate using a computerized

    spreadsheet (See Excel, next slide): Do we accept or reject the project?

  • 8/8/2019 capitalBudgetingChp9

    12/37

    9-11

    NPV using Excel

    e s low

    ' N P V

    O ig in l n es enN e P res en V lue

    Since NPV is posi i e we s ould ccep e in es en

  • 8/8/2019 capitalBudgetingChp9

    13/37

    9-12

    Decision Criteria Test - NPV

    Does the NPV rule account for the timevalue of money? (Yes)

    Does the NPV rule account for the risk ofthe cash flows? (Yes)

    Does the NPV rule provide an indicationabout the increase in value? (Yes)

    Should we consider the NPV rule forourprimary decision rule? (Yes)

  • 8/8/2019 capitalBudgetingChp9

    14/37

    9-13

    Internal Rate of Return

    This is the most important alternative toNPV

    It is often used in practice and is intuitivelyappealing

    It is based entirely on the estimated cashflows and is independent of interest rates

    found elsewhere

  • 8/8/2019 capitalBudgetingChp9

    15/37

    9-14

    IRR Definition and DecisionRule

    Definition: IRR is the return that makes theNPV = 0

    Decision Rule:Accept the project if theIRR is greater than the required return

  • 8/8/2019 capitalBudgetingChp9

    16/37

    9-15

    Computing IRR For The Project

    If you do not have a financial calculator,then this becomes a trial and error process

    Again many financial calculators havetemplates for estimating IRR

    But IRR is most easily estimated using aspreadsheet (See Excel, next slide)

    Do we accept or reject the project?

  • 8/8/2019 capitalBudgetingChp9

    17/37

  • 8/8/2019 capitalBudgetingChp9

    18/37

    9-17

    Decision Criteria Test - IRR

    Does the IRR rule account for the timevalue of money? (Yes)

    Does the IRR rule account for the risk ofthe cash flows? (Yes)

    Does the IRR rule provide an indicationabout the increase in value? (Yes, by %)

    Should we consider the IRR rule forourprimary decision criteria? (Not primary,see following slides)

  • 8/8/2019 capitalBudgetingChp9

    19/37

    9-18

    Advantages of IRR

    Knowing a return is intuitively appealing

    It is a simple way to communicate thevalue of a project to someone who doesntknow all the estimation details

    If the IRR is high enough, you may notneed to estimate a required return, which is

    often a difficult task

  • 8/8/2019 capitalBudgetingChp9

    20/37

    9-19

    Summary of Decisions For TheProject

    Summary

    Net Present Value Accept

    Payback Period Reject

    Discounted Payback Period Reject

    Average Accounting Return Reject

    Internal Rate of Return Accept

  • 8/8/2019 capitalBudgetingChp9

    21/37

    9-20

    NPV Vs. IRR

    NPV and IRR will generally give us thesame decision

    Exceptions

    Non-conventional cash flows cash flow signschange more than once

    Mutually exclusive projects

    Initial investments are substantially different Timing of cash flows is substantially different

  • 8/8/2019 capitalBudgetingChp9

    22/37

    9-21

    IRR and Non-conventional CashFlows

    When the cash flows change sign morethan once, there is more than one IRR

    When you solve for IRR you are solving forthe root of an equation and when you crossthe x-axis more than once, there will bemore than one return that solves the

    equation If multiple IRRs are calculated, none are

    then reliable.

  • 8/8/2019 capitalBudgetingChp9

    23/37

    9-22

    Another Example Non-conventional Cash Flows

    Suppose an investment will cost 90,000initially and will generate the following cashflows:

    Year 1: 132,000

    Year 2: 100,000

    Year 3: -150,000

    The required return is 15%. Should we accept or reject the project?

  • 8/8/2019 capitalBudgetingChp9

    24/37

    9-23

    Excel utputExample #2

    ea

    ea 2

    ea 2

    ea

    e ec t

    P x

    e

    P a t ac c ep t

    a t e ec t u t P a t

    ac c ep t G t P

  • 8/8/2019 capitalBudgetingChp9

    25/37

    9-24

    Summary of Decision Rules

    The NPV is positive at a required return of15%, so you shouldAccept

    If you use the financial calculatororspreadsheet, you would get an IRR of10.11% which would tell you toReject

    You need to recognize when there are

    non-conventional cash flows and look atthe NPV profile

  • 8/8/2019 capitalBudgetingChp9

    26/37

    9-25

    IRR and Mutually ExclusiveProjects

    Mutually exclusive projects

    If you choose one, you cant choose the other

    Example: You can choose to attend graduate

    school at either Harvard or Stanford, but notboth

    Intuitively you would use the following

    decision rules: NPV choose the project with the higher NPV

    IRR choose the project with the higher IRR

  • 8/8/2019 capitalBudgetingChp9

    27/37

    9-26

    Example With Mutually ExclusiveProjects

    Period ProjectA

    ProjectB

    0 -500 -400

    1 325 325

    2 325 200

    IRR 19.43% 22.17%

    NPV 64.05 60.74

    The required return

    for both projects is

    10%.

    Which project

    should you accept

    and why?

    Project A has a smaller IRRbut it is a larger project,thus generating greatervalue to the firm

    IRR cant measure that, but

    NP

    V can.

  • 8/8/2019 capitalBudgetingChp9

    28/37

    9-27

    Conflicts Between NPV and IRR

    NPV directly measures the increase invalue to the firm

    Whenever there is a conflict between NPVand another decision rule, you shouldalways use NPV

    IRR is unreliable in the following situations

    Non-conventional cash flows

    Mutually exclusive projects

  • 8/8/2019 capitalBudgetingChp9

    29/37

    9-28

    Profitability Index

    Measures the benefit per unit cost, basedon the time value of money

    A profitability index of 1.1 implies that forevery 1 of investment, we create anadditional 0.10 in value

    This measure can be very useful in

    situations in which we have limited capital

  • 8/8/2019 capitalBudgetingChp9

    30/37

    9-29

    Advantages and DisadvantagesofProfitability Index

    Advantages

    Closely related toNPV, generally leadingto identical decisions

    Easy to understandand communicate

    May be useful whenavailable investment

    funds are limited

    Disadvantages

    May lead to incorrectdecisions incomparisons ofmutually exclusiveinvestments

  • 8/8/2019 capitalBudgetingChp9

    31/37

    9-30

    Capital Budgeting In Practice

    We should consider several investmentcriteria when making decisions

    NPV and IRR are the most commonly usedprimary investment criteria

    Payback is a commonly used secondaryinvestment criteria

  • 8/8/2019 capitalBudgetingChp9

    32/37

    9-31

    Summary Discounted Cash FlowCriteria

    Net present value Difference between market value and cost Take the project if the NPV is positive Has no serious problems Preferred decision criterion

    Internal rate of return Discount rate that makes NPV = 0 Take the project if the IRR is greater than the required return Same decision as NPV with conventional cash flows IRR is unreliable with non-conventional cash flows or mutually exclusive

    projects

    Profitability Index Benefit-cost ratio Take investment ifPI > 1 Cannot be used to rank mutually exclusive projects May be used to rank projects in the presence of capital rationing

  • 8/8/2019 capitalBudgetingChp9

    33/37

    9-32

    Summary Payback Criteria

    Payback period

    ength of time until initial investment is recovered

    Take the project if it pays back in some specified

    period Doesnt account for time value of money and there is

    an arbitrary cutoff period

    Discounted payback period

    ength of time until initial investment is recovered on adiscounted basis

    Take the project if it pays back in some specifiedperiod

    There is an arbitrary cutoff period

  • 8/8/2019 capitalBudgetingChp9

    34/37

    9-33

    Quick Quiz

    Consider an investment that costs 100,000 andhas a cash inflowof 25,000 every year for 5years. The required return is 9% and requiredpayback is 4 years. What is the payback period? (4 yrs)

    What is the NPV? (-2,758.72)

    What is the IRR? ( 7.93%)

    Should we accept the project? (No)

    What decision rule should be the primarydecision method?

    When is the IRR rule unreliable?

  • 8/8/2019 capitalBudgetingChp9

    35/37

    9-34

    Quiz using Excel

    Year 0 - 100,000

    Year 1 25,000

    Year 2 25,000

    Year 3 25,000

    Year 4 25,000

    Year 5 25,000

    IRR 7.93%

    NPV at 9% 97,241.28

    - riginal Inv. - 100,000

    NPV ( 2,758.72)

    Reject project!

  • 8/8/2019 capitalBudgetingChp9

    36/37

    9-35

    Class Case

    Pause here towork in-class NPV / IRR casefor Wallys Widget Works:

  • 8/8/2019 capitalBudgetingChp9

    37/37

    Chapter

    McGraw-Hill/Irwin Copyright 2006 by The McGraw-Hill Companies, Inc. All rights reserved.

    9

    End of ChapterEnd of Chapter