capitalBudgetingChp9
-
Upload
patelhiteshkumarbahe -
Category
Documents
-
view
219 -
download
0
Transcript of capitalBudgetingChp9
-
8/8/2019 capitalBudgetingChp9
1/37
Chapter
McGraw-Hill/Irwin Copyright 2006 by The McGraw-Hill Companies, Inc. All rights reserved.
9
Net Present Value and
Other Investment Criteria
Net Present Value and
Other Investment Criteria
Revised by DBH, January 2006
-
8/8/2019 capitalBudgetingChp9
2/37
-
8/8/2019 capitalBudgetingChp9
3/37
9-2
Project Example Information
You are looking at a new project and youhave estimated the following cash flows:
Year 0: CF = -165,000
Year 1: CF = 63,120; NI = 13,620
Year 2: CF = 70,800; NI = 3,300
Year 3: CF = 91,080; NI = 29,100
Average Book Value = 72,000
Your required return for assets of this riskis 12%.
-
8/8/2019 capitalBudgetingChp9
4/37
9-3
Payback Period
How long does it take to get the initial costback in a nominal sense?
Computation
Estimate the cash flows
Subtract the future cash flows from the initialcost until the initial investment has been
recovered Decision Rule Accept if the payback
period is less than some preset limit
-
8/8/2019 capitalBudgetingChp9
5/37
9-4
Computing Payback For TheProject
Assume we will accept the project if it paysback within two years.
Year 1: 165,000 63,120 = 101,880 still torecover
Year 2: 101,880 70,800 = 31,080 still torecover
Year 3: 31,080 91,080 = -60,000projectpays back in year 3
Do we accept or reject the project?
-
8/8/2019 capitalBudgetingChp9
6/37
9-5
Decision Criteria Test - Payback
Does the payback rule account for the timevalue of money? (No)
Does the payback rule account for the riskof the cash flows? (No)
Does the payback rule provide anindication about the increase in value?
(No)
Should we consider the payback rule forour primary decision rule? (No)
-
8/8/2019 capitalBudgetingChp9
7/37
9-6
Advantages and DisadvantagesofPayback
Advantages
Easy to understand
Adjusts for uncertainty
of later cash flows Biased towards
liquidity
Disadvantages
Ignores the time valueof money
Requires an arbitrarycutoff point
Ignores cash flowsbeyond the cutoff date
Biased against long-term projects, such asresearch anddevelopment, and newprojects
-
8/8/2019 capitalBudgetingChp9
8/37
9-7
AAR and Discounted Payback
Discounted paybackis a variation on thepayback rule that does allow for the time value ofmoney, but still requires an arbitrary cutoff.
Average Accounting Return (AAR) doesnt evenmeasure cash flows, but only whether averageaccounting income from the project = a setpercentage of return
Neither effectively measures whether a long-terminvestment has added value to the firm. Forsake of time, we will ignore these methods.
-
8/8/2019 capitalBudgetingChp9
9/37
9-8
Net Present Value
The difference between the market valueof a project and its cost
How much value is created from
undertaking an investment? The first step is to estimate the expected
future cash flows.
The second step is to estimate the requiredreturn for projects of this risk level.
The third step is to find the present value ofthe cash flows and subtract the initialinvestment.
-
8/8/2019 capitalBudgetingChp9
10/37
9-9
NPV Decision Rule
If the NPV is positive, accept the project
A positive NPV means that the project isexpected to add value to the firm and willtherefore increase the wealth of theowners.
Since our goal is to increase ownerwealth,
NPV is a direct measure of howwell thisproject will meet our goal.
-
8/8/2019 capitalBudgetingChp9
11/37
9-10
Computing NPV for the Project
Using the formulas:
NPV = 63,120/(1.12) + 70,800/(1.12)2 +91,080/(1.12)3 165,000 = 12,627.42
Many financial calculators also havetemplates for calculating NPV
Easiest to calculate using a computerized
spreadsheet (See Excel, next slide): Do we accept or reject the project?
-
8/8/2019 capitalBudgetingChp9
12/37
9-11
NPV using Excel
e s low
' N P V
O ig in l n es enN e P res en V lue
Since NPV is posi i e we s ould ccep e in es en
-
8/8/2019 capitalBudgetingChp9
13/37
9-12
Decision Criteria Test - NPV
Does the NPV rule account for the timevalue of money? (Yes)
Does the NPV rule account for the risk ofthe cash flows? (Yes)
Does the NPV rule provide an indicationabout the increase in value? (Yes)
Should we consider the NPV rule forourprimary decision rule? (Yes)
-
8/8/2019 capitalBudgetingChp9
14/37
9-13
Internal Rate of Return
This is the most important alternative toNPV
It is often used in practice and is intuitivelyappealing
It is based entirely on the estimated cashflows and is independent of interest rates
found elsewhere
-
8/8/2019 capitalBudgetingChp9
15/37
9-14
IRR Definition and DecisionRule
Definition: IRR is the return that makes theNPV = 0
Decision Rule:Accept the project if theIRR is greater than the required return
-
8/8/2019 capitalBudgetingChp9
16/37
9-15
Computing IRR For The Project
If you do not have a financial calculator,then this becomes a trial and error process
Again many financial calculators havetemplates for estimating IRR
But IRR is most easily estimated using aspreadsheet (See Excel, next slide)
Do we accept or reject the project?
-
8/8/2019 capitalBudgetingChp9
17/37
-
8/8/2019 capitalBudgetingChp9
18/37
9-17
Decision Criteria Test - IRR
Does the IRR rule account for the timevalue of money? (Yes)
Does the IRR rule account for the risk ofthe cash flows? (Yes)
Does the IRR rule provide an indicationabout the increase in value? (Yes, by %)
Should we consider the IRR rule forourprimary decision criteria? (Not primary,see following slides)
-
8/8/2019 capitalBudgetingChp9
19/37
9-18
Advantages of IRR
Knowing a return is intuitively appealing
It is a simple way to communicate thevalue of a project to someone who doesntknow all the estimation details
If the IRR is high enough, you may notneed to estimate a required return, which is
often a difficult task
-
8/8/2019 capitalBudgetingChp9
20/37
9-19
Summary of Decisions For TheProject
Summary
Net Present Value Accept
Payback Period Reject
Discounted Payback Period Reject
Average Accounting Return Reject
Internal Rate of Return Accept
-
8/8/2019 capitalBudgetingChp9
21/37
9-20
NPV Vs. IRR
NPV and IRR will generally give us thesame decision
Exceptions
Non-conventional cash flows cash flow signschange more than once
Mutually exclusive projects
Initial investments are substantially different Timing of cash flows is substantially different
-
8/8/2019 capitalBudgetingChp9
22/37
9-21
IRR and Non-conventional CashFlows
When the cash flows change sign morethan once, there is more than one IRR
When you solve for IRR you are solving forthe root of an equation and when you crossthe x-axis more than once, there will bemore than one return that solves the
equation If multiple IRRs are calculated, none are
then reliable.
-
8/8/2019 capitalBudgetingChp9
23/37
9-22
Another Example Non-conventional Cash Flows
Suppose an investment will cost 90,000initially and will generate the following cashflows:
Year 1: 132,000
Year 2: 100,000
Year 3: -150,000
The required return is 15%. Should we accept or reject the project?
-
8/8/2019 capitalBudgetingChp9
24/37
9-23
Excel utputExample #2
ea
ea 2
ea 2
ea
e ec t
P x
e
P a t ac c ep t
a t e ec t u t P a t
ac c ep t G t P
-
8/8/2019 capitalBudgetingChp9
25/37
9-24
Summary of Decision Rules
The NPV is positive at a required return of15%, so you shouldAccept
If you use the financial calculatororspreadsheet, you would get an IRR of10.11% which would tell you toReject
You need to recognize when there are
non-conventional cash flows and look atthe NPV profile
-
8/8/2019 capitalBudgetingChp9
26/37
9-25
IRR and Mutually ExclusiveProjects
Mutually exclusive projects
If you choose one, you cant choose the other
Example: You can choose to attend graduate
school at either Harvard or Stanford, but notboth
Intuitively you would use the following
decision rules: NPV choose the project with the higher NPV
IRR choose the project with the higher IRR
-
8/8/2019 capitalBudgetingChp9
27/37
9-26
Example With Mutually ExclusiveProjects
Period ProjectA
ProjectB
0 -500 -400
1 325 325
2 325 200
IRR 19.43% 22.17%
NPV 64.05 60.74
The required return
for both projects is
10%.
Which project
should you accept
and why?
Project A has a smaller IRRbut it is a larger project,thus generating greatervalue to the firm
IRR cant measure that, but
NP
V can.
-
8/8/2019 capitalBudgetingChp9
28/37
9-27
Conflicts Between NPV and IRR
NPV directly measures the increase invalue to the firm
Whenever there is a conflict between NPVand another decision rule, you shouldalways use NPV
IRR is unreliable in the following situations
Non-conventional cash flows
Mutually exclusive projects
-
8/8/2019 capitalBudgetingChp9
29/37
9-28
Profitability Index
Measures the benefit per unit cost, basedon the time value of money
A profitability index of 1.1 implies that forevery 1 of investment, we create anadditional 0.10 in value
This measure can be very useful in
situations in which we have limited capital
-
8/8/2019 capitalBudgetingChp9
30/37
9-29
Advantages and DisadvantagesofProfitability Index
Advantages
Closely related toNPV, generally leadingto identical decisions
Easy to understandand communicate
May be useful whenavailable investment
funds are limited
Disadvantages
May lead to incorrectdecisions incomparisons ofmutually exclusiveinvestments
-
8/8/2019 capitalBudgetingChp9
31/37
9-30
Capital Budgeting In Practice
We should consider several investmentcriteria when making decisions
NPV and IRR are the most commonly usedprimary investment criteria
Payback is a commonly used secondaryinvestment criteria
-
8/8/2019 capitalBudgetingChp9
32/37
9-31
Summary Discounted Cash FlowCriteria
Net present value Difference between market value and cost Take the project if the NPV is positive Has no serious problems Preferred decision criterion
Internal rate of return Discount rate that makes NPV = 0 Take the project if the IRR is greater than the required return Same decision as NPV with conventional cash flows IRR is unreliable with non-conventional cash flows or mutually exclusive
projects
Profitability Index Benefit-cost ratio Take investment ifPI > 1 Cannot be used to rank mutually exclusive projects May be used to rank projects in the presence of capital rationing
-
8/8/2019 capitalBudgetingChp9
33/37
9-32
Summary Payback Criteria
Payback period
ength of time until initial investment is recovered
Take the project if it pays back in some specified
period Doesnt account for time value of money and there is
an arbitrary cutoff period
Discounted payback period
ength of time until initial investment is recovered on adiscounted basis
Take the project if it pays back in some specifiedperiod
There is an arbitrary cutoff period
-
8/8/2019 capitalBudgetingChp9
34/37
9-33
Quick Quiz
Consider an investment that costs 100,000 andhas a cash inflowof 25,000 every year for 5years. The required return is 9% and requiredpayback is 4 years. What is the payback period? (4 yrs)
What is the NPV? (-2,758.72)
What is the IRR? ( 7.93%)
Should we accept the project? (No)
What decision rule should be the primarydecision method?
When is the IRR rule unreliable?
-
8/8/2019 capitalBudgetingChp9
35/37
9-34
Quiz using Excel
Year 0 - 100,000
Year 1 25,000
Year 2 25,000
Year 3 25,000
Year 4 25,000
Year 5 25,000
IRR 7.93%
NPV at 9% 97,241.28
- riginal Inv. - 100,000
NPV ( 2,758.72)
Reject project!
-
8/8/2019 capitalBudgetingChp9
36/37
9-35
Class Case
Pause here towork in-class NPV / IRR casefor Wallys Widget Works:
-
8/8/2019 capitalBudgetingChp9
37/37
Chapter
McGraw-Hill/Irwin Copyright 2006 by The McGraw-Hill Companies, Inc. All rights reserved.
9
End of ChapterEnd of Chapter