NEW YORK CITY HOUSING AUTHORITY
SELECTED DEVELOPMENTS
CAPITAL PROJECTS
MODERNIZATION ACTIVITIES REPORT
FEBRUARY, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION SUMMARY ALL REPORT FOR SELECTED DEVELOPMENTS
STATUS BUDGET
COMPLETED - 11 YEARS $61,068,682
IN - PROGRESS $3,065,890
DESIGN / PROCUREMENT $800,000
$64,934,572TOTAL
YEAR BUDGET
5 - YEAR PLAN
FY - 2019 $1,100,000
$1,100,000TOTAL
STATUS BUDGET
DASNY MANAGED
COMPLETED $500,000
$500,000TOTAL
Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: 335 EAST 111TH STREET MANHATTAN
NY005010640 66DWELLING UNITS:HUD AMP#:203TDS: 1DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
6225 $9,501 2012INSTALL SMOKE, CARBON MONOXIDE DETECTORS & STROBE LIGHTSFEDERAL
6343 $194,999 2008FIRE ESCAPESFEDERAL
$204,500Total :
Project Type of WorkConst.
StartFund CodeBudget
IN PROGRESS
Ant.
End
9352 $400,000 CITY 11/15/18INSTALLATION OF SECURITY CAMERAS AND A NEW DOOR 03/08/20
$400,000Total :
5-YEAR PLAN
BudgetProject Fund Code Type of WorkFiscal
Year
$1,000,0009841 2019CITY ELEVATORS
$1,000,000Total :
An asterisk (*) in a date column denotes a projected date Page 1 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: 344 EAST 28TH STREET MANHATTAN
INITIATIVES :
NY005021850 225DWELLING UNITS:HUD AMP#:185TDS: 1DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
6234 $1,975,040 2012ELEVATOR REHAB (STAFFING & CONTINGENCY)MIXED FINANCE
7053 $5,145,969 2010SWARMPS (SAFE WITH A REPAIR AND MAINTENANCE PROGRAM)FEDERAL/MIXED FINANCE
7681 $261,333 2017EXTERIOR BRICK REPAIR WORKHAF
8966 $38,567 2017FACADES (LOCAL LAW 11) (CM AND A/E SERVICES)MF CITY
$7,420,909Total :
MF - Mayor's Action Plan: Facades
An asterisk (*) in a date column denotes a projected date Page 2 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: FORT WASHINGTON AVENUE REHAB MANHATTAN
NY005013090 226DWELLING UNITS:HUD AMP#:309TDS: 1DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
2770 $4,430,056 2010ROOF REPLACEMENTFEDERAL
5462 $2,754,719 2008COMMUNITY CENTER UPGRADE (GC,EL, PL AND HVAC WORK)FEDERAL
6165 $47,359 2008EMERGENCY ROOF REPAIRS AT FT WASHINGTON SENIOR CENTERFEDERAL
6197 $104,634 2008REPAIRS AND RENOVATIONS IN APARTMENT 5C AT 503 WEST 177TH STREETFEDERAL
6225 $8,373 2012INSTALL SMOKE, CARBON MONOXIDE DETECTORS & STROBE LIGHTSFEDERAL
6481 $1,318,239 2015FAÇADE RESTORATION AND SIDEWALK SHEDS (LOCAL LAW 11)FEDERAL
6956 $5,218,551 2019REPLACEMENT OF BOILERS AND RELATED EQUIPMENTFEDERAL
7781 $66,272 2014SECURITY ENHANCEMENTS(CM FEES)FEDERAL
8358 $268,241 2014SECURITY ENHANCEMENTS AT 99 FT WASHINGTON AVE.CITY
$14,216,443Total :
Project Type of WorkConst.
StartFund CodeBudget
IN PROGRESS
Ant.
End
7448 $1,244,721 CITY/FEDERAL 08/17/17SENIOR CENTER UPGRADE PHASE II 03/31/19
$1,244,721Total :
Project Type of WorkConst.
StartPhaseBudget
DASNY MANAGED
Const.
End
D104 $500,000 CLOSED 09/22/17LAC & CCTV 10/12/18
$500,000Total :
An asterisk (*) in a date column denotes a projected date Page 3 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: GRAMPION MANHATTAN
NY005010300 35DWELLING UNITS:HUD AMP#:281TDS: 1DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
6481 $417,255 2015FAÇADE RESTORATION AND INSTALL SHEDS (LOCAL LAW 11)FEDERAL
$417,255Total :
Project Type of WorkConst.
StartFund CodeBudget
IN PROGRESS
Ant.
End
8869 $82,334 FEDERAL 01/11/19FIRE ESCAPE & BALCONY METAL RAILING REPAIR 04/15/19
$82,334Total :
An asterisk (*) in a date column denotes a projected date Page 4 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: MANHATTANVILLE REHAB (GROUP 2) MANHATTAN
INITIATIVES :
NY005010810 46DWELLING UNITS:HUD AMP#:296TDS: 3DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
6009 $483,506 2009ROOF REPLACEMENT AND ASBESTOS ABATEMENT OF 8500 SQ FT AT THE CHILDREN'S CENTER.FEDERAL
6225 $15,397 2012INSTALL SMOKE, CARBON MONOXIDE DETECTORS & STROBE LIGHTSFEDERAL
6481 $5,108 2017EXTERIOR BRICKWORK REPAIRS (SIDEWALK SHEDS)FEDERAL
6505 $341,781 2010COMPLETE ELEVATOR REHAB (CHANGE ORDER)FEDERAL
8966 $441,168 2018EXTERIOR BRICK REPAIRS (LOCAL LAW 11)MF CITY
$1,286,961Total :
MF - Mayor's Action Plan: Facades
An asterisk (*) in a date column denotes a projected date Page 5 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: MANHATTANVILLE REHAB (GROUP 3) MANHATTAN
INITIATIVES :
NY005010810 51DWELLING UNITS:HUD AMP#:297TDS: 2DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
6225 $4,264 2012INSTALL SMOKE, CARBON MONOXIDE DETECTORS & STROBE LIGHTSFEDERAL
6499 $310,019 2010ELEVATORSFEDERAL
6851 $171,101 2010BRICKWORKFEDERAL
8966 $691,391 2018EXTERIOR BRICK REPAIRS (LOCAL LAW 11)MF CITY/FEDERAL
$1,176,775Total :
Project Type of WorkConst.
StartFund CodeBudget
IN PROGRESS
Ant.
End
6481 $925,397 FEDERAL 08/30/16EXTERIOR BRICKWORK REPAIRS (LOCAL LAW 11) 05/31/19
$925,397Total :
MF - Mayor's Action Plan: Facades
An asterisk (*) in a date column denotes a projected date Page 6 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: PARK AVENUE-EAST 122ND, 123RD STREETS MANHATTAN
NY005012410 90DWELLING UNITS:HUD AMP#:204TDS: 2DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
6225 $6,368 2012INSTALL SMOKE, CARBON MONOXIDE DETECTORS & STROBE LIGHTSFEDERAL
6481 $51,421 2015EXTERIOR BRICKWORK REPAIRS (LOCAL LAW 11)FEDERAL
6680 $677,459 2013COMPLETE ELEVATOR REHABFEDERAL
7492 $342,964 2012BRICK REPAIR PURSUANT TO LOCAL LAW 11/98FEDERAL
7589 $3,887,651 2017EXTERIOR BRICKWORK & ROOFING - WINDOW REPLACEMENTFEDERAL
7616 $8,244 2014REPLACEMENT OF UNDERGROUND STEAM DISTRIBUTION SYSTEMFEDERAL
$4,974,107Total :
5-YEAR PLAN
BudgetProject Fund Code Type of WorkFiscal
Year
$100,0009470 2019FEDERAL INTERIOR COMPACTORS
$100,000Total :
An asterisk (*) in a date column denotes a projected date Page 7 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: PUBLIC SCHOOL 139 (CONVERSION) MANHATTAN
NY005011110 125DWELLING UNITS:HUD AMP#:340TDS: 1DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
5940 $580,204 2010REPLACEMENT OF FREIGHT ELEVATORFEDERAL
$580,204Total :
An asterisk (*) in a date column denotes a projected date Page 8 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: SAMUEL (MHOP) I MANHATTAN
NY005013170 31DWELLING UNITS:HUD AMP#:389TDS: 5DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
6083 $1,250,099 2011REPLACEMENT OF ROOFS AT CHILD CARE AND COMMUNITY CENTERSFEDERAL
7781 $261,771 2015SECURITY ENHANCEMENTSFEDERAL
7988 $584,370 2015EXTERIOR BRICK REPAIRS (LOCAL LAW 11)FEDERAL
$2,096,241Total :
An asterisk (*) in a date column denotes a projected date Page 9 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: SAMUEL (MHOP) II MANHATTAN
INITIATIVES :
NY005013170 5DWELLING UNITS:HUD AMP#:398TDS: 1DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
9001 $379,110 2018APARTMENT RENOVATION - OFFLINE UNITSMA CITY/FEDERAL
$379,110Total :
MA - Mayor's Homeless Initiatives
An asterisk (*) in a date column denotes a projected date Page 10 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: SAMUEL (MHOP) III MANHATTAN
INITIATIVES :
NY005013170 2DWELLING UNITS:HUD AMP#:399TDS: 1DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
9001 $577,424 2018APARTMENT RENOVATION - OFFLINE UNITSMA CITY/FEDERAL
$577,424Total :
MA - Mayor's Homeless Initiatives
An asterisk (*) in a date column denotes a projected date Page 11 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: WASHINGTON HEIGHTS REHAB (GROUPS 1&2) MANHATTAN
INITIATIVES :
NY005013090 214DWELLING UNITS:HUD AMP#:293TDS: 5DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
5639 $9,700,785 2009BRICKWORKFEDERAL
6225 $5,358 2012INSTALL SMOKE, CARBON MONOXIDE DETECTORS & STROBE LIGHTSFEDERAL
6481 $123,336 2017EXTERIOR BRICKWORK REPAIRS (LOCAL LAW 11)(SIDEWALK SHEDS)FEDERAL
8032 $1,855,834 2015REPAIRING FIRE ESCAPESFEDERAL
8966 $185,883 2018FACADES (LOCAL LAW 11) (SIDEWALK SHEDS)MF CITY
$11,871,197Total :
Project Type of WorkConst.
StartFund CodeBudget
IN PROGRESS
Ant.
End
7989 $52,991 FEDERAL 07/25/17EXTERIOR BRICK REPAIRS (LOCAL LAW 11)(SIDEWALK SHEDS) 09/30/19
$52,991Total :
MF - Mayor's Action Plan: Facades
An asterisk (*) in a date column denotes a projected date Page 12 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: WASHINGTON HEIGHTS REHAB PHASE III (FORT WASHINGTON) MANHATTAN
NY005013090 102DWELLING UNITS:HUD AMP#:523TDS: 8DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
7480 $926,399 2015REPLACEMENT OF BOILERSFEDERAL
$926,399Total :
An asterisk (*) in a date column denotes a projected date Page 13 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: WASHINGTON HEIGHTS REHAB PHASE III (HARLEM RIVER) MANHATTAN
NY005010030 102DWELLING UNITS:HUD AMP#:329TDS: 8DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
6602 $148,400 2011REPLACEMENT AND REPAIR INTERIOR COMPACTORSFEDERAL
$148,400Total :
An asterisk (*) in a date column denotes a projected date Page 14 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: WASHINGTON HEIGHTS REHAB PHASE IV (C) MANHATTAN
NY005013090 32DWELLING UNITS:HUD AMP#:330TDS: 2DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
2876 $512,341 2011ROOF REPLACEMENT/BRICKWORKFEDERAL
$512,341Total :
An asterisk (*) in a date column denotes a projected date Page 15 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: WASHINGTON HEIGHTS REHAB PHASE IV (D) MANHATTAN
NY005013090 32DWELLING UNITS:HUD AMP#:331TDS: 2DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
2877 $520,229 2011ROOF REPLACEMENT/BRICKWORKFEDERAL
$520,229Total :
An asterisk (*) in a date column denotes a projected date Page 16 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: WISE TOWERS MANHATTAN
INITIATIVES :
NY005021270 398DWELLING UNITS:HUD AMP#:127TDS: 2DWELLING BUILDINGS
Project Type of WorkComp.
YearFund CodeBudget
COMPLETED - 11 YEARS
7066 $5,510,227 2011HEATING UPGRADEFEDERAL/MIXED FINANCE
7681 $1,319,148 2016EXTERIOR BRICK REPAIRS (LOCAL LAW 11)HAF
8253 $7,000 2012HURRICANE SANDY RELATED WORKIRSAND
8695 $121,444 2017PLAY AREACITY/HAF
8904 $2,847,164 2017LOCAL LAW 11 WORKHAF/OPER. RES.
9053 $3,955,202 2019ROOFING, RAILING REPLACEMENT AND ROOFTOP STRUCTURE REPAIRSMR CITY
$13,760,185Total :
Project Type of WorkConst.
StartFund CodeBudget
IN PROGRESS
Ant.
End
8657 $360,447 FEDERAL 06/04/19*FIRE ALARM AND FIRE SUPPRESSION UPGRADES 11/01/19
$360,447Total :
Project Type of WorkFund Code
DESIGN / PROCUREMENT
Budget PhaseAnt.
Start
Ant.
End
9872 $525,000 CITY 12/31/19PLAY AREA AND SPRINKLER 02/27/21DESIGN
9906 $275,000 CITY 04/12/21OUTDOOR PLAZA CAMERAS 03/07/22PLANNING
$800,000Total :
MR - Mayor's Action Plan: Roofs
An asterisk (*) in a date column denotes a projected date Page 17 of 17Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION SUMMARY REPORT FOR SELECTED DEVELOPMENTS
MANHATTAN
DEVELOPMENT: 335 EAST 111TH STREET
STATUS BUDGET
COMPLETED - 11 YEARS $204,500
IN - PROGRESS $400,000
$604,500TOTAL
YEAR BUDGET
5 - YEAR PLAN
FY - 2019 $1,000,000
$1,000,000TOTAL
DEVELOPMENT: 344 EAST 28TH STREET
STATUS BUDGET
COMPLETED - 11 YEARS $7,420,909
$7,420,909TOTAL
DEVELOPMENT: FORT WASHINGTON AVENUE REHAB
STATUS BUDGET
COMPLETED - 11 YEARS $14,216,443
IN - PROGRESS $1,244,721
$15,461,164TOTAL
STATUS BUDGET
DASNY MANAGED
COMPLETED $500,000
$500,000TOTAL
Page 1 of 5Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION SUMMARY REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: GRAMPION
STATUS BUDGET
COMPLETED - 11 YEARS $417,255
IN - PROGRESS $82,334
$499,590TOTAL
DEVELOPMENT: MANHATTANVILLE REHAB (GROUP 2)
STATUS BUDGET
COMPLETED - 11 YEARS $1,286,961
$1,286,961TOTAL
DEVELOPMENT: MANHATTANVILLE REHAB (GROUP 3)
STATUS BUDGET
COMPLETED - 11 YEARS $1,176,775
IN - PROGRESS $925,397
$2,102,172TOTAL
Page 2 of 5Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION SUMMARY REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: PARK AVENUE-EAST 122ND, 123RD STREETS
STATUS BUDGET
COMPLETED - 11 YEARS $4,974,107
$4,974,107TOTAL
YEAR BUDGET
5 - YEAR PLAN
FY - 2019 $100,000
$100,000TOTAL
DEVELOPMENT: PUBLIC SCHOOL 139 (CONVERSION)
STATUS BUDGET
COMPLETED - 11 YEARS $580,204
$580,204TOTAL
DEVELOPMENT: SAMUEL (MHOP) I
STATUS BUDGET
COMPLETED - 11 YEARS $2,096,241
$2,096,241TOTAL
DEVELOPMENT: SAMUEL (MHOP) II
STATUS BUDGET
COMPLETED - 11 YEARS $379,110
$379,110TOTAL
Page 3 of 5Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION SUMMARY REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: SAMUEL (MHOP) III
STATUS BUDGET
COMPLETED - 11 YEARS $577,424
$577,424TOTAL
DEVELOPMENT: WASHINGTON HEIGHTS REHAB (GROUPS 1&2)
STATUS BUDGET
COMPLETED - 11 YEARS $11,871,197
IN - PROGRESS $52,991
$11,924,188TOTAL
DEVELOPMENT: WASHINGTON HEIGHTS REHAB PHASE III (FORT WASHINGTON)
STATUS BUDGET
COMPLETED - 11 YEARS $926,399
$926,399TOTAL
DEVELOPMENT: WASHINGTON HEIGHTS REHAB PHASE III (HARLEM RIVER)
STATUS BUDGET
COMPLETED - 11 YEARS $148,400
$148,400TOTAL
Page 4 of 5Wednesday, February 27, 2019
NEW YORK CITY HOUSING AUTHORITY
CAPITAL PROJECTS
MODERNIZATION SUMMARY REPORT FOR SELECTED DEVELOPMENTS
DEVELOPMENT: WASHINGTON HEIGHTS REHAB PHASE IV (C)
STATUS BUDGET
COMPLETED - 11 YEARS $512,341
$512,341TOTAL
DEVELOPMENT: WASHINGTON HEIGHTS REHAB PHASE IV (D)
STATUS BUDGET
COMPLETED - 11 YEARS $520,229
$520,229TOTAL
DEVELOPMENT: WISE TOWERS
STATUS BUDGET
COMPLETED - 11 YEARS $13,760,185
IN - PROGRESS $360,447
DESIGN / PROCUREMENT $800,000
$14,920,632TOTAL
Page 5 of 5Wednesday, February 27, 2019