Cape Paterson North Proposed Drainage Strategy
Transcript of Cape Paterson North Proposed Drainage Strategy
Cape Paterson North
Proposed Drainage Strategy
REVISION F
1 February 2016
Report by: Valerie Mag BE Civil (Hons), M Eng Sci
Stormy Water Solutions
Ph 9511 5911, M 0412 436 021
Contents
1. INTRODUCTION AND BACKGROUND .................................................................................. 1
2. ASSUMED DRAINAGE SYSTEM REQUIREMENTS ............................................................ 4
2.1 HYDROLOGICAL REQUIREMENTS ............................................................................................. 4
2.2 WATER SENSITIVE URBAN DESIGN REQUIREMENTS ................................................................ 4
2.3 ECOLOGICAL CONSIDERATIONS ............................................................................................... 5
3. DRAINAGE STRATEGY DESCRIPTION ................................................................................ 6
4. HYDROLOGIC FLOOD FLOW MODELLING ....................................................................... 9
4.1 EXISTING CONDITIONS............................................................................................................. 9
4.2 POST DEVELOPMENT CONDITIONS ......................................................................................... 13
5. STORMWATER POLLUTANT MODELLING ...................................................................... 19
6. POTENTIAL ESTUARY IMPACTS......................................................................................... 23
6.1. FLOW FREQUENCY ANALYSIS ................................................................................................ 24
6.1.1 Analysis Methodology ....................................................................................................... 24
6.1.2 Scenarios Investigated ...................................................................................................... 24
6.1.3 Rainfall Data .................................................................................................................... 25
6.1.4 Catchment Delineation and Specification ........................................................................ 25
6.2 ANALYSIS RESULTS ............................................................................................................... 27
7. CONCLUSIONS AND FURTHER WORK REQUIRED ........................................................ 28
8. ABBREVIATIONS AND DEFINITIONS ................................................................................. 30
APPENDIX A – RETARDING BASIN CONCEPT DESIGNS ....................................................... 31
A.1 RETARDING BASIN RB1 ......................................................................................................... 32
A.2 RETARDING BASIN RB2 ......................................................................................................... 34
A.3 RETARDING BASIN RB3 ......................................................................................................... 36
A.4 RETARDING BASIN RB4 ......................................................................................................... 38
APPENDIX B – RETARDING BASIN MODELS ............................................................................ 40
APPENDIX C FLOOD FREQUENCY ANALYSIS RESULTS ................................................. 44
1
1. Introduction and Background
This report pertains to the drainage system which discharges to Seaward Drive, north of Cape
Paterson. In particular it considerers the implication of development of the subject site for
residential purposes as detailed in Figure 1 below.
Figure 1 Subject Site
Figure 1 shows:
• The subject site,
• The piped trunk drainage within the existing township (denoted by the bold red line),
• The indicative location of informal farm drainage systems as denoted by the bold blue
lines (in some cases these systems are made up of many very small paddock drains),
and
• The major outfall points from the subject site at Seaward Drive.
The drainage system configuration was formulated given,
• Site observations,
2
• Google map information, especially in relation to defining existing farm drain locations
and outfall points,
• One metre lidar contour information,
• 0.5 metre site survey information,
• 10 metre Vic Map contour information,
• Bass Coast Shire Council Drainage plans within Cape Paterson Township,
• Details of the existing drainage system within the proposed Eco Village located west
of the township (Bass coast Planning Scheme Amendments C53, C93 and C98 Panel
Report, April 2010, Figure 5.4)
• Detailed survey of Wilsons Road (including all culverts) and the Cape Paterson Road
culvert systems.
Actual detailed drainage configurations may differ slightly from those shown. However, it is
considered that enough analysis has been undertaken to give a reasonable indication of the
drainage system configuration and operation north of Cape Paterson.
Outfall Point 5 denotes the location of the major external catchment inflow north of the subject
site.
Point 6 is a formal site outfall point. Flow at this point is conveyed via a culvert under Cape
Paterson Road to a road drain at Point 7, where is joins a flow path conveying rural flow from
the catchment east of the road. As shown, this drainage system forms the major outfall to the
sea via a naturalistic drainage path east of the township. South of Cape Paterson Road, the
drain flows through Parks Victoria land (downstream of Point 8) and is relatively large and,
although overgrown, exhibits ecological and landscape attributes.
The only other “real” outfall to the sea is the outfall from the township drainage system as
shown in red. Council have indicated that the township drainage system only accounts for
drainage of the town, and makes no provision for external upstream catchments. However, it
appears that some minor input may occur at Points 2, 3 and 4 (possibly though small road
culverts into the township drainage system). Whatever the case, in relatively large storm
events, when flow does occur over Seaward Drive from the catchment to the north, nuisance
flooding in the township would be expected.
Outfall Point 1 denotes the location of the outfall from the subject site across Seaward Drive
and into the proposed Eco Village (located west of the existing Cape Paterson township).
Council have confirmed that discharge can occur from Point 1 into the future Eco Village
provided flow retardation to predevelopment flow rates occurs.
3
This report details a proposed a site drainage strategy developed by Stormy Water Solutions
and Beveridge Williams designed to mitigate stormwater impacts downstream of Point 7 and
to improve the flood impact within the Cape Peterson township.
The November 2015 (Revision E) of this report specifically addresses minor changes in
wetland/retarding basin location and extents given landowner consultation process which has
occurred throughout 2015.
4
2. Assumed Drainage System Requirements
Stormy Water Solutions and Beveridge Williams met with Bass Coast Shire Council (Council)
and The West Gippsland Catchment Management Authority (WGCMA) on 3 September 2013.
This meeting confirmed that:
• The had been no formal drainage strategy submitted to council for the proposed eco
village located south of Point1,
• Any future drainage strategy for the eco village should account for existing external
flows, including those entering the eco village at Point 1,
• There is no provision within the existing township piped drainage system to accept
ANY additional flows from north of Seaward Drive (i.e. flows from existing outfall
points 2, 3 and 4),
• The most obvious site outfall point was to Point 6, with site flows then being directed
to the drain downstream of Point 7 and into the Parks Victoria land, and
• The WGCMA confirmed an appropriate drainage strategy would have to show no
impact on the creek through the Parks Victoria Land.
If any flow were to be directed into the existing township, piped drainage system
augmentation would be required to ensure no increased flood effect, and if possible an
increased level of flood protection should be provided. Subsequent investigations indicated
that the cost of drainage system augmentations through the township would be prohibitive in
regard to the subject site drainage strategy implementation.
Given the above the following drainage strategy requirements are assumed. It should be
noted that these requirements are in line with existing best practice in Victoria for simular
developments.
2.1 Hydrological Requirements
It is assumed that:
• The 100 Year ARI flow directed into the eco village site should be retarded to below
existing flow rates at Point 1,
• No site drainage discharges into the township should occur, and
• Any flow directed to Point 6 must be retarded to ensure the 100 Year ARI post
development flow is not greater than the existing 100 Year flow at this point.
2.2 Water Sensitive Urban Design Requirements
It is assumed that all subject site runoff must be treated to at least best practice before
discharge from the subject site. As such the following requirements must be met
5
• 80 % retention of subject site Total Suspended Solids (TSS) on site,
• 45 % retention of subject site Total Phosphorus (TP) on site , and
• 45 % retention of subject site Total Nitrogen (TN) on site.
2.3 Ecological Considerations
The existing waterway downstream of Point 8, though the Parks Victoria land is relatively
degraded and exhibits many weed species etc. It is understood that this waterway was
originally constructed to provide a concentrated drainage outflow point for the land located to
the north. Prior to this there was no large outflow connection directly to the sea.
The developer has recently extended the site Flora and Fauna Report (Ecology and Heritage
Partners) to include the proposed drainage outfall for the development (to its estuary) and
provide an assessment as to whether or not there are any adverse effects from directing the
flows from another catchment through this outfall. It is understood by Stormy Water Solutions
that the main issue that was highlighted was that there are a mating pair of hooded plovers
that nest in the path of the existing outfall on the beach.
Advice from Ecology and Heritage Partners, on 27/03/2015 regarding this issue suggest that:
• The outfall is usually blocked but there is, on average, two storm events during the
hooded plover’s breeding period (September – March) that are large enough to blow
out the sand and wash away eggs or young chicks, and
• It takes the hooded plover two and a half months to raise a chick from when the eggs
are laid. If the sand is blown out and the outfall flows during this time, the eggs (or
chicks) are washed away. If there is not two and a half months between these events
the hooded plover does not reproduce for the year.
It is required to be shown that the frequency of the times in which a flow event occurs capable
of opening the estuary does not increase due to the drainage strategy proposals.
6
3. Drainage Strategy Description
Stormy Water Solutions has used the constraints and requirements detailed above to develop
a drainage strategy for the subject site. The strategy is presented as shown in Figure 2. The
strategy incorporates the following:
• Retarding Basin 1 ( RB1),
• Retarding Basin 2 ( RB2),
• Retarding Basin 3 ( RB3),
• Retarding Basin 4 ( RB4),
• A bypass pipe along Seaward Drive directing site outflow from retarding basins RB1,
RB2 and RB3 in an easterly direction,
• A grassed swale in parkland west of RB3, directing a flow from a localised low point
into the RB3 inlet pipeline as shown,
• Discharge of RB4 outflows south through the Cape Paterson Eco Village (this
assumes the Eco Village accounts for an inflow at the Seaward Drive low point at
predevelopment flow rates),
• A vegetated swale along the eastern boundary of the subject site designed to convey
external flows around the site from Point 5 to Point 6,
• 2000 litre tanks for toilet flushing on all new lots within the subdivision, and
• Increasing the size of the existing road culvert at Point 6 to ensure 100 year flow
conveyance across the road at this point and to ensure free outflow from RB1 in all
events up to and including the 100 Year ARI event.
All retarding basins incorporate a wetland within its base to ensure maximum flood storage
given the site area available and to provide stormwater treatment. It is assumed that each
retarding basin and wetland system treats and stores water from its local catchment only (as
defined in Figure 2), before discharge of flows.
All retarding basin and wetland concept design parameters are detailed in Appendix A. It
should be noted that the outflow from each system has been minimised (given site and
topography constraints), to minimise site discharge downstream. All concept designs have
been formulated given actual site outfall invert level constraints and topographical constraints
(e.g. 1 in 5 batters to cut lines etc).
The requirements of the proposed lot stormwater harvesting tanks for toilet flushing are
detailed in Section 5 of this report.
The strategy:
• Ensures NO discharge south into the existing township in all events up to the 100
Year event, thus reducing the current flood impact in the township considerably,
7
• Ensures no increase in the 100 Year flood flows downstream of Point 6, thus
addressing flood impact considerations in the waterway through the Parks Victoria
Land (see Section 4),
• Meets current best practice in regard to stormwater treatment (See Section 5), and
• Shows that the frequency of the times in which a flow event occurs capable of
opening the estuary does not increase, thus addressing the ecological requirement
detailed in Section 2.3.
The main issues in regard to implementation of the drainage strategy is the construction of
the bypass pipe along Seaward Drive which is required to be relatively deep to meet
upstream wetland discharge requirements and downstream invert level constraints,
All designs are to the concept design stage only at this stage. All proposals are subject to
change during the design process. However, enough analysis has been conducted to clearly
show that development of the subject site is achievable without adverse stormwater impact on
downstream properties or ecological habitats. In fact, by formally constructing an outfall for
the catchment north of Seaward Drive, flooding impacts though the existing township should
be reduced when the drainage strategy is implemented.
It should be noted that the strategy developed is a “worst case” scenario in terms of
downstream stormwater impact. There is some scope in the design to increase flood
storage/wetland provisions (if required due to site or subdivision design constraints) during
the design process.
The remainder of this report details the hydrological calculations relating to the formulation of
the above drainage strategy.
8
Figure 2 Proposed Drainage Strategy Note: 2000 litre tanks for Toilet Flushing are to be incorporated on each lot
9
4. Hydrologic Flood Flow Modelling
The analysis detailed below explains the RORB models and storage parameters used for this project.
4.1 Existing Conditions
The RORB model parameters are based on the regional parameter developed by Melbourne Water for the
South East region of Melbourne.
• Kc = 1.53A 0.55 = 2.57
• m = 0.8
• Initial loss = 10 mm
• Pervious area runoff coefficient (Cperv) 100 year ARI Cperv = 0.6
Figure 3 details the RORB model for the existing situation. Tables 1 and 2 detail the tabulation of the RORB
model setup (i.e. catchment areas, fraction imperviousness and reach lengths etc). Cape Paterson rainfall
intensities were utilised.
Reaches have been defined as either “natural” or “excavated unlined” to represent the farm and road
drainage network.
10
Table 1 Existing Situation RORB Model Setup - Subareas
Sub Area Area (ha) Area (km2) Fraction
Imperviousness
(Existing)
A 2.8 0.028 0.10
B 3.1 0.031 0.10
C 3.5 0.035 0.10
D 2.8 0.028 0.10
E 4 0.04 0.10
F 5.5 0.055 0.10
G 4.9 0.049 0.10
H 3.1 0.031 0.10
I 3.3 0.033 0.10
J 2.6 0.026 0.10
K 4.5 0.045 0.10
L 7.4 0.074 0.10
M 3.8 0.038 0.10
N 6 0.06 0.10
O 6.6 0.066 0.10
P 8.5 0.085 0.10
Q 3.7 0.037 0.10
R 4.8 0.048 0.10
S 3.3 0.033 0.10
T 10.5 0.105 0.10
U 12.2 0.122 0.10
V 9 0.09 0.10
W 5.3 0.053 0.10
X 8.7 0.087 0.10
Y 5.9 0.059 0.10
Z 5.5 0.055 0.10
AA 6.3 0.063 0.10
AB 6.6 0.066 0.10
AC 4.5 0.045 0.10
AD 5.4 0.054 0.10
AE 31.8 0.318 0.10
AF 30.8 0.308 0.10
AG 17.6 0.176 0.10
AH 12.7 0.127 0.10
257.0 2.57
11
Table 2 Existing Situation RORB Model Setup - Reaches
Reach Length (m) Length (km) Reach Type - Existing
100 Year
1 220 0.22 NATURAL
2 120 0.12 NATURAL
3 270 0.27 NATURAL
4 100 0.1 NATURAL
5 320 0.32 EXCAVATED UNLINED
6 200 0.2 NATURAL
7 170 0.17 NATURAL
8 20 0.02 NATURAL
9 190 0.19 NATURAL
10 130 0.13 NATURAL
11 100 0.1 NATURAL
12 250 0.25 NATURAL
13 120 0.12 EXCAVATED UNLINED
14 190 0.19 NATURAL
15 130 0.13 EXCAVATED UNLINED
16 110 0.11 EXCAVATED UNLINED
17 20 0.02 NATURAL
18 300 0.3 NATURAL
19 180 0.18 EXCAVATED UNLINED
20 140 0.14 NATURAL
21 270 0.27 NATURAL
22 80 0.08 NATURAL
23 130 0.13 EXCAVATED UNLINED
24 170 0.17 EXCAVATED UNLINED
25 130 0.13 EXCAVATED UNLINED
26 20 0.02 NATURAL
27 110 0.11 NATURAL
28 20 0.02 NATURAL
29 280 0.28 NATURAL
30 270 0.27 NATURAL
31 200 0.2 NATURAL
32 170 0.17 NATURAL
33 290 0.29 EXCAVATED UNLINED
34 180 0.18 EXCAVATED UNLINED
35 240 0.24 EXCAVATED UNLINED
36 120 0.12 EXCAVATED UNLINED
37 140 0.14 EXCAVATED UNLINED
38 180 0.18 EXCAVATED UNLINED
39 160 0.16 EXCAVATED UNLINED
40 300 0.3 EXCAVATED UNLINED
41 210 0.21 EXCAVATED UNLINED
42 160 0.16 EXCAVATED UNLINED
43 70 0.07 NATURAL
44 920 0.92 EXCAVATED UNLINED
45 320 0.32 NATURAL
46 680 0.68 EXCAVATED UNLINED
47 240 0.24 NATURAL
48 240 0.24 EXCAVATED UNLINED
49 460 0.46 EXCAVATED UNLINED
12
Figure 3 RORB Model - Existing Conditions
Note: Reaches and catchments may vary slightly from those detailed above. However the model is considered to give a reasonable representation of the existing conditions given the consideration detailed in Section 1 above.
The following 100 Year ARI flows were obtained for the existing conditions:
• Point 1 – 0.9 m3/s (critical duration = 2 hours)
• Point 2 – 1.2 m3/s (critical duration = 2 hours)
• Point 3 – 1.2 m3/s (critical duration = 2 hours)
• Point 4 – 0.2 m3/s (critical duration = 2 hours)
13
• Point 5 – 1.9 m3/s (critical duration = 2 hours)
• Point 6 – 2.7 m3/s (critical duration = 2 hours)
• External Catchment AE – AH – 2.9 m3/s (critical duration = 9 hours)
• Point 7 – 5.6 m3/s (critical duration = 9 hours)
• Dummy Combined outflow from all outfall points = 8.3 m3/s (critical duration = 9 hours)
The total dummy combined flow was compared with flows estimated using the rational method and the DSE
regional flow estimate graphs. This check was done to ensure the parameter set adopted was valid for its
application in this area. The rational method obtained a 100 Year flow estimate of 11.1 m3/s (C100 = 0.4 and
a tc = 30 mins). The DSE regional flow estimate graph (Q100 = 4.67×A 0.763) resulted in a flow estimate of
9.6m3/s. Given the sandy nature of the soils in this catchment, the dummy RORB estimated flow of 8.3 m3/s
is deemed comparable with flows obtained using the above two methods.
4.2 Post Development Conditions
As above, the RORB model parameters for the post development scenario were based on the regional
parameter developed by Melbourne Water for the South East region of Melbourne.
• Kc = 1.53A 0.55 = 2.6 (slightly increased catchment area)
• m = 0.8
• Initial loss = 10 mm
• Pervious area runoff coefficient (Cperv) 100 year ARI Cperv = 0.6
Figure 4 details the RORB model for the post development situation. Tables 3 and 4 detail the tabulation of
the RORB model setup. Cape Paterson rainfall intensities were utilised. Reaches have been defined as
either “piped” within the developed area and as per the “existing conditions” model otherwise.
Flood storage models for RB1 - RB4 were developed given:
• Site survey and topography constraints at all sites,
• 1 in 5 batters from cut lines to embankment crests to the wetland normal water levels,
• The approximate space allocated to each area at the present time by Beveridge Williams, and
• Estimated downstream culvert and pipe invert levels.
Appendix B details the Stage/Storage/Discharge relationship determination for each site.
14
Table 3 Post Development Situation RORB Model Setup - Subareas
Sub Area Area (ha) Area (km2) Fraction
Imperviousness
(Future)
A 2.8 0.028 0.10
B 5.2 0.052 0.10
C 2.3 0.023 0.60
D 3.5 0.035 0.10
E 2.8 0.028 0.50
F 6.8 0.068 0.60
G 8 0.08 0.10
H 3.1 0.031 0.50
I 2.5 0.025 0.60
J 4.9 0.049 0.60
K 4.4 0.044 0.50
L 5 0.05 0.60
M 6.9 0.069 0.50
N 6.3 0.063 0.60
O 5.4 0.054 0.30
P 7.8 0.078 0.60
Q 2.9 0.029 0.60
R 4.8 0.048 0.30
S 3.4 0.034 0.10
T 10.5 0.105 0.10
U 12.2 0.122 0.10
V 9 0.09 0.10
W 5.3 0.053 0.10
X 8.7 0.087 0.10
Y 5.9 0.059 0.10
Z 6.4 0.064 0.60
AA 7 0.07 0.60
AB 4.8 0.048 0.60
AC 4.5 0.045 0.60
AD 5.4 0.054 0.60
AE 31.8 0.318 0.10
AF 30.8 0.308 0.10
AG 17.6 0.176 0.10
AH 12.7 0.127 0.10
261.4 2.61
15
Table 4 Post Development Situation RORB Model Setup - Reaches
Reach Length (m) Length (km)
Reach Type -
developed
100 /5 Year
1 320 0.32 NATURAL
2 290 0.29 PIPED
3 140 0.14 PIPED
4 250 0.25 PIPED
5 420 0.42 PIPED
6 170 0.17 PIPED
7 270 0.27 PIPED
8 190 0.19 NATURAL
9 100 0.1 PIPED
10 220 0.22 PIPED
11 150 0.15 PIPED
12 100 0.1 PIPED
13 220 0.22 PIPED
14 170 0.17 PIPED
15 270 0.27 PIPED
16 250 0.25 PIPED
17 220 0.22 PIPED
18 90 0.09 PIPED
19 440 0.44 NATURAL IN PARK
20 100 0.1 PIPED
21 210 0.21 PIPED
22 270 0.27 PIPED
23 110 0.11 PIPED
24 110 0.11 PIPED
25 130 0.13 PIPED
26 90 0.09 PIPED
27 110 0.11 PIPED
28 250 0.25 PIPED
29 280 0.28 NATURAL
30 270 0.27 NATURAL
31 200 0.2 NATURAL
32 170 0.17 NATURAL
33 290 0.29 EXCAVATED UNLINED
34 180 0.18 NATURAL
35 240 0.24 EXCAVATED UNLINED
36 120 0.12 PIPED
37 140 0.14 PIPED
38 180 0.18 PIPED
39 160 0.16 PIPED
40 300 0.3 PIPED
41 210 0.21 PIPED
42 160 0.16 PIPED
43 70 0.07 PIPED
44 920 0.92 EXCAVATED UNLINED
45 320 0.32 NATURAL
46 680 0.68 EXCAVATED UNLINED
47 240 0.24 NATURAL
48 240 0.24 EXCAVATED UNLINED
49 460 0.46 EXCAVATED UNLINED
16
Figure 4 RORB Model - Post Development Conditions
Note: Reaches and catchments may vary slightly from those detailed above. However the model is considered to give a reasonable representation of the post development conditions given the consideration detailed in Section 1 above.
17
The following 100 Year ARI flows were obtained for the post development conditions:
Retarding Basin 4
• 100 Year Inflow = 3.3 m3/s (critical duration = 25 mins)
• 100 Year Outflow = 0.85 m3/s (critical duration = 9 hours)
• Maximum 100 Year flood storage = 3,720 m3
• Maximum 100 Year flood level = 28.45 m AHD
Reach 19 (assuming conveyed by swale in parkland) = 0.2 m3/s (100 yr.)
Retarding Basin 3
• 100 Year Inflow = 6.8 m3/s (critical duration = 15 mins)
• 100 Year Outflow = 0.36 m3/s (critical duration = 24 hours)
• Maximum 100 Year flood storage = 22,800 m3
• Maximum 100 Year flood level = 28.22 m AHD
Bypass pipe along Seaward Drive between RB3 outlet and RB2 outlet = 0.36 m3/s (100 yr.)
Retarding Basin 2
• 100 Year Inflow = 3.9 m3/s (critical duration = 15 mins)
• 100 Year Outflow = 0.10 m3/s (critical duration = 48 hours)
• Maximum 100 Year flood storage = 9,300 m3
• Maximum 100 Year flood level = 25.5 m AHD
Bypass pipe along Seaward Drive between RB2 outlet and RB1 outlet = 0.52 m3/s (100 yr.)
External Flow at Point 5 = 2.1 m3/s
(Note differs slightly from existing flow estimate due to different catchment setup)
Retarding Basin 1
• 100 Year Inflow = 4.4 m3/s (critical duration = 25 mins)
• 100 Year Outflow = 0.65 m3/s (critical duration = 9 hours)
• Maximum 100 Year flood storage = 6,790 m3
• Maximum 100 Year flood level = 20.15 m AHD
Site Outflow at Point 6 = 2.5 m3/s (9 hr.)
Note: Existing Q100 = 2.7 m3/s at Point 6.
18
External Catchment AE – AH – 3.2 m3/s (critical duration = 2 hours)
(Note differs slightly from existing flow estimate due to different catchment setup)
Flow downstream of site at Point 7 = 5.6 m3/s (9 hr.)
Note: Existing Q100 = 5.6 m3/s at Point 7.
As detailed above, the proposed drainage strategy results in the post development 100 Year flow estimates
at Points 6 and 7 being at or below the existing flow estimates.
19
5. Stormwater Pollutant Modelling
Retarding Basins RB1, RB2, RB3 and RB4 will incorporate wetlands within the base of each system. These
wetlands maximise flood storage given the area available. However, they also serve the dual function of
providing stormwater treatment for pollutant loads generated in the developed area. Wetland parameters
are:
RB1
• Wetland area (average area between Normal Water Level (NWL = 3,970 m2) and Top of Extended
Detention (TED = 4,350 m2 )) = 4,160 m2
• Extended Detention = 0.5 m
• Detention Time = 36 hours
• Sediment pond (to be located at upstream end of the system) = 1000 m3
RB2
• Wetland area (average area between NWL = 7,080 m2 and TED = 9,560 m2) = 8,300 m2
• Extended Detention = 0.5 m
• Detention Time = 36 hours
• Sediment pond (to be located at upstream end of the system) = 500 m3
RB3
• Wetland area (average area between NWL = 10,125 m2 and TED = 12,340 m2) = 11,230 m2
• Extended Detention = 0.5 m
• Detention Time = 36 hours
• Sediment pond (to be located at upstream end of the system) = 1,500 m3
RB4
• Wetland area (average area between NWL = 4,140 m2 and TED = 4,670 m2) = 4,400 m2
• Extended Detention = 0.25 m
• Detention Time = 36 hours
• Sediment pond (to be located at upstream end of the system) = 500 m3
It should be noted, that at 36 hours, the detention times in the wetland ED range (RB1 to RB3) are less than
usually specified. However, it is considered that this is enough time to facilitate adequate stormwater
pollutant update, while producing a downstream flow regime similar to the existing situation in low flow
events. This is required to meet the site ecological requirements (See Section 6).
20
On site stormwater harvesting for toilet flushing was modelled. This harvesting initiative was seen as easy to
implement if required via (say) a 173 agreement on the development.
Catchment, demand and storage size assumptions are as detailed below. Of course, these may be subject
to change given the final development form. However they are considered enough to give a reasonable
indication of the benefits of this initiative.
Cape Paterson North Development Catchment Breakdown
Area
(ha)
Approx
Dwellings*
Roof to
Toilet* Roof Fimp
Non Roof
Catchment
Non roof
Fimp
Catchment (ha) (ha) (ha) (ha)
C, E, F 11.9 178.5 1.8 1.0 10.1 0.5
H to O 38.5 577.5 5.8 1.0 32.7 0.5
P, Q, R 15.5 232.5 2.3 1.0 13.2 0.5
Z to AC 22.7 340.5 3.4 1.0 19.3 0.5
AD 5.4 81.0 0.8 1.0 4.6 0.5
.*Assumes 15 lots/ha = 600 m2 lots (say)
.** Assumes 100 m2 of roof to 2000 litre tank for toilet flushing
.*** Assumes overall catchment Fimp = 0.6
Toilet Demand and Tank size
Number of people per house = 2
Duel flush toilet demand = 22 l/person /day
(Coomes Consulting Group-Epping Project 2002)
storage - 2000 litre tanks for toilet flushing
Area
(ha)
Approx
Dwellings*
Approx
Population
Approx toilet
Demand
Approx
toilet
Demand
Tank
volume (m3)
Catchment litres/day ML/yr
C, E, F 11.9 179 357 7854 2867 357
H to O 38.5 578 1155 25410 9275 1155
P, Q, R 15.5 233 465 10230 3734 465
Z to AC 22.7 341 681 14982 5468 681
AD 5.4 81 162 3564 1301 162
The performance of the WSUD system detailed in Appendix A and Figure 2 was analysed using the Model
for Urban Stormwater Improvement Conceptualisation model (MUSIC – Version 6). Figure 5 details the
MUSIC model developed for the catchment.
21
Catchments are defined as per the catchment layout detailed in Section 4 above. The model utilised the
Melbourne Water reference year for Narre Warren North 1998 at 6 minute intervals. This rainfall and
evaporation data is considered valid for areas south east of Melbourne exhibiting annual rainfall between
850 – 1100 mm. As Cape Paterson receives about 950 mm/yr rainfall, it is considered that this gauge
information is valid for this application. The default base flow generation parameters have been used as they
represent reasonably sandy soils.
Figure 6 shows the MUSIC model developed. Table 5 details the performance of the strategy.
Figure 5 MUSIC Model Note external catchment T – Y not treated and conveyed in a vegetated swale along the eastern edge of the development. Wetlands treat subject site and external catchments A, B, D and G
22
Table 5 Music Results
Point 1 - RB4 outflow to Eco Village
Point 6 – Combined Eastern Site outfall
Table 5 shows that the load reduction objectives for Total Suspended Solids (80% retention of loads
produced on site), Total Phosphorus (45% retention) and Total Nitrogen (45% retention) will be met by the
proposed wetland and sediment ponds located within the RB1, RB2, RB3 and RB4.
It should be noted that the load pollutant reduction will still be met even without tanks for toilet flushing.
However, this initiative has been specified to meet the ecological requirements detained in Section 6 below.
In addition, although the stormwater pollutant reduction targets are exceeded, no reduction in wetland size is
proposed. The wetlands are required to also maximise the flood storage provisions detailed in Section 4
above.
23
6. Potential Estuary Impacts
The existing waterway downstream of Point 8, though the Parks Victoria land is relatively degraded and
exhibits many weed species etc. It is understood that this waterway was originally constructed to provide a
concentrated drainage outflow point for the land located to the north. Prior to this there was no large outflow
connection directly to the sea.
In 2015 the developer extended the site Flora and Fauna Report (Ecology and Heritage Partners) to include
the proposed drainage outfall for the development (to its estuary) and provide an assessment as to whether
or not there are any adverse effects from directing the flows from another catchment through this outfall. It is
understood by Stormy Water Solutions that the main issue that was highlighted was that there are a mating
pair of hooded plovers that nest in the path of the existing outfall on the beach.
Advice from Ecology and Heritage Partners, on 27/03/2015 regarding this issue suggest that:
• The outfall is usually blocked but there is, on average, two storm events during the hooded plover’s
breeding period (September – March) that are large enough to blow out the sand and wash away
eggs or young chicks, and
• It takes the hooded plover two and a half months to raise a chick from when the eggs are laid. If the
sand is blown out and the outfall flows during this time, the eggs (or chicks) are washed away. If
there is not two and a half months between these events the hooded plover does not reproduce for
the year.
It is required to be shown that the frequency of the times in which a flow event occurs capable of opening the
estuary does not increase due to the proposals.
Development of a catchment usually results in an increase in frequency of low and medium range flow
events at the estuary mouth. This may lead more storm events during the hooded plover’s breeding period
(September – March) that are large enough to blow out the sand and wash away eggs or young chicks.
The drainage strategy proposes to use the retarding basin/wetland systems to mitigate the effect of
increased flood frequency downstream at the estuary.
The wetlands within the base of each retarding basin provide a stormwater treatment function. However,
through storing water in their extended detention ranges they also act to retard and mitigate frequent flow
events.
The extent of these retardation/stormwater harvesting benefits during frequent rainfall events is investigated
below.
24
6.1. Flow Frequency Analysis
6.1.1 Analysis Methodology
The following methodology has been used to assess estuary impacts due to development.
1. Determine the flow magnitude (in m3/s) which is exceed, on average, twice per breeding season for
the existing catchment,
2. Assess the increase in flows exceeding the rate calculated in 1. due to the Cape Paterson North
development and diversion to the estuary without wetlands and tanks for toilet flushing in the
development , and
3. Assess the reduction in impact of 2. Given the drainage strategy wetland proposals (3 wetlands in
RB1, RB2 and RB3 (500 mm extended detention and 36 hours extended detention period) and tanks
for toilet flushing utilised in the development.
It should be noted that an extended detention of 36 hours was deliberately chosen to balance the stormwater
pollutant retention function of the wetlands with the low flow range retardation function. At a detention time of
36 hours, the low flow wetland outlet flow rate is measurable (i.e. typically 15 – 45 l/s) and the wetland TED
storage range can be modelled as flood storage. This allows control of minor flow events within the extended
detention range of the wetland, rather than bypass of these minor events due to the wetland being full. If the
wetland bypasses too much (which could happen with wetlands of long detention times), the mitigation of the
required number of low flow events may not occur.
The performance of the drainage strategy in relation to mitigation of frequent flow events was analysed using
the MUSIC model. The water balance component of the model was utilised to conduct the analysis as it is an
appropriate tool to examine the effect of low flow events.
6.1.2 Scenarios Investigated
The scenarios analysis were:
1. Existing situation. No development or diversion of Cape Paterson North Flows.
2. Development of Cape Paterson North and diversion of flows east. No wetlands, rainwater tanks or
retardation initiatives.
3. Development of Cape Paterson North and diversion of flows east. 2000 Litre Tanks for toilet flushing
on all lots. Wetlands and retarding basins as detailed including an extended detention range of 500
mm and an extended detention period of 36 hours.
25
6.1.3 Rainfall Data
The closest Bureau of Metrology (BoM) rain gauge to Cape Paterson is Wonthaggi. The BoM web site
information for this gauge suggests an average long term rainfall for this gauge of 938 mm/yr. Eight years of
Croydon rainfall and evaporation data (BoM site 86234) at 1 hour intervals was used to undertake a water
balance analysis of the catchment. This gauge, duration and time interval were used as:
• This is considered a long enough duration to give an indication of long term average effect,
• The 1980’s is a good period to look at long term averages in and around Melbourne as they
contained some dry years, some wet years and an average rainfall per year of around the expected
long term average,
• 1 hour is less than the time of concentration of the total catchment to the estuary,
• Gauge 86234 (Croydon) recorded 874 mm rainfall/yr. during this period which is within 7 % of the
expected rainfall in Wonthaggi,
• An extension of the information contained within the current Melbourne Water rainfall distribution
map for Melbourne and surrounds suggests that Croydon rainfall can be a reasonable indication of
the rainfall distribution in the Cape Paterson region, and
• The MUSIC rainfall data was assessed as adequate for use (i.e. no significant gaps in the rainfall
record) between 1980 and 1988.
6.1.4 Catchment Delineation and Specification
The MUSIC Model delineation is as detailed in Figures 6 and 7 below.
A fraction imperviousness of 0.1 was used for existing rural areas, and as per the RORB model for the Cape
Paterson North Development.
Wetland areas are as detailed in the 2014 Appendix A.
Catchment areas for the development are as per the RORB model in Section 4. Catchment areas for the
extensive existing rural catchment are as detailed in Figures 6 and 7.
Soil infiltration parameters are as per the default MUSIC parameter set as they are known to be
representative of relatively sandy soil profiles. Minor infiltration at the wetland sites of 10 mm/hr is assumed.
This is on the lower end of infiltration expected for sandy clay profiles, and a conservative assumption in
regard to the sandy profiles expected at each site.
26
Figure 6 Catchment Deliniation – Scenario 1 (588 ha)
Figure 7 Catchment Deliniation – Scenario 3 (677 ha)
27
6.2 Analysis Results
The flow output (in m3/s) can be extracted at 1 hour interval at the estuary for the above scenarios. This was
done, and the output cropped to just consider the month of September to March inclusive (i.e. the breeding
months). For Scenario 1, it was found that a flow rate of 1.2 m3/s occurred on average 2.0 times per breeding
season over the eight years. As such, this seems a reasonable flow rate to assess as the flow rate capable
resulting in sand being washed out of the estuary and estuary flows occurring directly to the sea. This flow
also matches the rule of thumb check for a 3 month ARI flow for a catchment of this size. Again this seems
reasonable as the flow rate to assess as the event which may be exceeded twice over a breeding season.
Appendix C details the detailed results of each scenario. Table 6 below summarises the results.
Table 6 Analysis Results
Scenario
Average number times during a
breeding season that the flow at
the estuary is greater than 1.2 m3/s
=
Number of breeding seasons
incorporating a flow of 1.2 m3/s
more than two times in that
season
1
Existing situation. No development
or diversion of Cape Paterson North
Flows
2.0 3 out of 8
2
Development of Cape Paterson
North. No wetlands or retardation
initiatives
6.9 8 out of 8
3
Development of Cape Paterson
North. 2000 Litre Tanks for toilet
flushing on all lots. Wetlands as
detailed - Extended detention range
= 500 mm, detention time = 36 hours
2.0 3 out of 8
As detailed above incorporating tanks for toilet flushing on all lots and the wetland provisions as per this
strategy should ensure replication of existing estuary flow frequencies in regard to opening of the estuary to
the sea after a storm event.
It should be noted that, if either tanks for toilet flushing cannot be applied, and/or the required wetland
extended detention provisions cannot be applied (possibly due to unforseen site or design constraints) there
is scope in the drainage strategy to still complement the low flow frequency reduction benefits of the scheme
via provision of an additional wetland/retardation basin at Point 5 (Figure 1).
As such it is concluded that mitigation of the impact of the development on the existing estuary dynamics can
occur going forward.
28
7. Conclusions and Further Work Required
The proposed rainwater harvesting tanks, retarding basin / wetland systems detailed in this report
represents:
• a best practice application of water sensitive urban design principles to the mitigation of stormwater
pollutant impacts given future development of the subject site,
• a strategy which will mitigate storm flows such that the 100 year ARI flow at the catchment outlet is
reduced below the predevelopment flow rate, and
• a strategy which can mitigate the impact of the development on the existing estuary dynamics in
relation to the ecological requirements.
The retarding basin/wetland concept designs have been considered to enough detail to set the following
given topography and outlet invert level constraints:
• Normal water level
• Top of extended detention level
• Normal water level areal extents
• Top of extended detention level areal extents, and
• Cut line extents given 1 in 5 batters (min) to NWL
Work required to develop these to a functional design includes (but is not limited to):
• Confirming the size (and depth to natural surface level) of the bypass pipe system along Seaward
Drive to convey the 100 Year ARI outflow from RB2 and RB3,
• Determining if any drain cleanout, revegetation or enlargement works are required downstream of
Point 7,
• Setting wetland bathymetry (i.e. shape and levels) below normal water level,
• Confirming the retarding basin outlet sizes and configurations,
• Designing the sediment pond areas in all retention basins giving due consideration for cleanout
access provision and storage of sediment for drying during cleanout maintenance activities,
• Sizing all retarding basin inlet pipes (outfall invert into retarding basins should be above the set
concept design normal water level),
• Finalising the subdivision layout around the retarding basins giving due consideration of:
o The assumed contributing catchments to each basin as described in this report,
o The assumed location of the inlet pipe system to each system,
o The social and landscape benefits of locating boulevard roads adjacent to the retarding
basin systems
o The road levels, if any roads are to form part of a retarding basin embankment,
• Obtaining detailed survey of each site to ensure all design levels detailed in this report are
reasonable,
29
• Undertaking full testing of the site to determine soil characteristics, and
• Completing the site landscape design including access track and (potentially) boardwalk locations.
It should be noted that the retarding basin concept designs have optimized each site in regard to the
retardation and wetland requirements. In particular, incorporating a wetland in the base of the retarding
basins has reduced the retarding basin site requirements, as the flood storage is provided within the vertical
airspace, rather than the areal expanse during flooding.
All designs are to the concept design stage only at this stage. However, enough analysis has been
conducted to clearly show that development of the subject site is achievable without adverse stormwater
impact on downstream properties. In fact, by formally constructing an outfall for the catchment north of
Seaward Drive, flooding impacts though the existing Cape Paterson township should be reduced if the
drainage strategy is implemented.
The strategy developed is a “worst case” scenario in terms of downstream stormwater impact. There is
scope in the drainage strategy to complement the scheme (if required) via provision of an additional
wetland/retardation basin at Point 5 (Figure 1).
30
8. Abbreviations and Definitions
The following table lists some common abbreviations and drainage system descriptions and their definitions
which are referred to in this report.
Abbreviation
Descriptions
Definition
AHD - Australian Height Datum
Common base for all survey levels in Australia. Height in metres above mean sea level.
ARI - Average Recurrence Interval.
The average length of time in years between two floods of a given size or larger
BoM Bureau of Meteorology
DoT Department of Transport
Evapotranspiration
The loss of water to the atmosphere by means of evaporation from free water surfaces (e.g. wetlands) or by transpiration by plants
Groundwater All water stored or flowing below the ground surface level
Groundwater Level The level of groundwater below the surface level at a particular point of interest (usually given in AHD or relative to surface level)
Inlet Pond See Sediment Pond
Hectare (ha) 10,000 square metres
Hec Ras A one dimensional, steady state hydraulic model which uses the Standard Step Method to calculate flood levels and flood extents
Kilometre (km) 1000 metres
m3/s -cubic metre/second
Unit of discharge usually referring to a design flood flow along a stormwater conveyance system
Megalitre (ML) (1000 cubic metres)
1,000,000 litres = 1000 cubic metres Often a unit of water body (e.g. pond) size
MUSIC Hydrologic computer program used to calculate stormwater pollutant generation in a catchment and the amount of treatment which can be attributed to the WSUD elements placed in that catchment. Can also be used to calculate water body turnover period and wetland draw downs etc
NWL Normal Water Level – invert level of lowest outflow control from a wetland or pond.
PET Potential Evapotranspiration – potential loss of water to the atmosphere by means of evaporation or transpiration from wetland or pond systems.
Retarding Basin Drainage element used to retard flood flows to limit flood impacts downstream of a development. Can include complementary WSUD and ecological site benefits if wetland incorporated within the site.
Sedimentation basin (Sediment pond)
A pond that is used to remove coarse sediments from inflowing water mainly by settlement processes.
Surface water All water stored or flowing above the ground surface level
TED Top of Extended Detention – Level to which stormwater is temporarily stored for treatment in a wetland or pond (above NWL).
TSS Total Suspended Solids – a term for a particular stormwater pollutant parameter
TP Total Phosphorus – a term for a particular stormwater pollutant parameter
TN Total Nitrogen – a term for a particular stormwater pollutant parameter
Wetland
WSUD elements which is used to collect TSS, TP and TN. Either permanently or periodically inundated with shallow water and either permanently or periodically supports the growth of aquatic macrophytes
WSUD Water Sensitive Urban Design.
31
Appendix A – Retarding Basin Concept Designs
All plans detailed should not be scaled. A set scale in this report has not been assigned.
The designs detailed below are concept designs only. They have been considered to enough detail to set the following
given topography and outlet invert level constraints:
• Normal water level
• Top of extended detention level
• Normal water level areal extents
• Top of extended detention level areal extents, and
• Cut line extents given 1 in 5 batters (min) to NWL
Work required to develop these to a functional design includes (but is not limited to) those aspects discussed in
Section 7 above.
It should be noted that 2000 litre tanks for toilet flushing on all lots is also proposed as part of this strategy.
32
A.1 Retarding Basin RB1
33
34
A.2 Retarding Basin RB2
35
36
A.3 Retarding Basin RB3
37
38
A.4 Retarding Basin RB4
39
40
Appendix B – Retarding Basin Models
RB1 Stage Storage Discharge Relationship
Normal Water Level 18.75 m AHD
Normal Water Level Area = 3971 m2
Extended Detention level = 19.25 m AHD
Top of Extended Detention Area = 4349 m2
Outflow relationshipsRetarding Basin Outflow below TED m AHD
Average wetland treatment storage area = 4160 m2
Extended Detention height = 0.50 m
Extended detention volume = 2080 m3
Detention time = 36 hours - maximise outflow in ED range while
still allowing adequate treatment time
Outflow at TED = 0.016 m3/s
Therefore orifice control at invert level = 18.75 m AHD to limit outflow to
0.016 m3/s in ED range
ORIFICE CALCULATION Q = 0.6× A×(2gH) 0.5
orifice dia = 0.13 m
Area = 0.01389471 m2
Elevation H (m) Q(m3/s)
19 0 0.0
19.25 0.2 0.016 130 mm orifice hole required at IL = 18.75 m AHD
Culvert acting under inlet control
ORIFICE CALCULATION Q = 0.6× A×(2gH) 0.5
pipe dia = 0.375 m
Area = 0.110460938 m2
Elevation H (m) Q(m3/s) Q(m3/s)
ONE 450 mm dia THREE 450 mm dia
18.75 0 0.000 0.000 wetland outflow at TED
19.25 0.3 0.02
20 1.1 0.303 0.91
20.5 1.6 0.367 1.10
nb IN THIS CASE INLET AND OUTLET CONTROL
Storage Relationship PRODUCE ESSENTIALLY THE SAME US WL
Level (m AHD) Area (m2) Average Area (m2) Height Diff (m) Volume (m3) Cumulative Volume (m3)
18.75 3971 0
19.25 4349 4160 0.5 2080 2080
20 5800 5075 0.75 3806 5886
20.5 6813 6307 0.5 3153 9039
Stage/Storage/Storage Relationship
Level (m AHD) Q(m3/s) Storage (m3)
18.75 0.000 0 Normal Water Level
19.25 0.016 2080 Top of Extended Detention
20 0.908 5886
20.5 1.101 9039
41
RB2 Stage Storage Discharge Relationship
Normal Water Level 24.5 m AHD
Normal Water Level Area = 7080 m2
Extended Detention level = 25 m AHD
Top of Extended Detention Area = 9560 m2
Outflow relationshipsRetarding Basin Outflow below TED m AHD
Average wetland treatment storage area = 8320 m2
Extended Detention height = 0.50 m
Extended detention volume = 4160 m3
Detention time = 36 hours - maximise outflow in ED range while
still allowing adequate treatment time
Outflow at TED = 0.032 m3/s
Therefore orifice control at invert level = 24.5 m AHD to limit outflow to
0.032 m3/s in ED range
ORIFICE CALCULATION Q = 0.6× A×(2gH) 0.5
orifice dia = 0.15 m
Area = 0.01767375 m2
Elevation H (m) Q(m3/s)
24.5 0 0.0
25 0.4 0.031 150 mm orifice hole required at IL = 23.5 m AHD
Culvert acting under inlet control
ORIFICE CALCULATION Q = 0.6× A×(2gH) 0.5
pipe dia = 0.225 m
Area = 0.039765938 m2
Elevation H (m) Q(m3/s)
25 0 0.031 wetland outflow at TED
25.05 0.4 0.070
25.5 0.9 0.100
26.5 1.9 0.145
Storage Relationship
Level (m AHD) Area (m2) Average Area (m2) Height Diff (m) Volume (m3) Cumulative Volume (m3)
24.5 7080 0
25 9560 8320 0.5 4160 4160
25.5 10800 10180 0.5 5090 9250
26.5 14000 12400 1 12400 21650
Stage/Storage/Storage Relationship
Level (m AHD) Q(m3/s) Storage (m3)
24.5 0 0 Normal Water Level
25 0.031 4160 Top of Extended Detention
25.05 0.070 4500
25.5 0.100 9250
26.5 0.145 21650 Cut line at lowest natural surface level
42
RB3 Stage Storage Discharge Relationship
Normal Water Level 26.5 m AHD
Normal Water Level Area = 10125 m2
Extended Detention level = 27 m AHD
Top of Extended Detention Area = 12340 m2
Outflow relationshipsRetarding Basin Outflow below TED m AHD
Average wetland treatment storage area = 11232.5 m2
Extended Detention height = 0.50 m
Extended detention volume = 5616.25 m3
Detention time = 36 hours - maximise outflow in ED range while
still allowing adequate treatment time
Outflow at TED = 0.043 m3/s
Therefore orifice control at invert level = 26.5 m AHD to limit outflow to
0.043 m3/s in ED range
ORIFICE CALCULATION Q = 0.6× A×(2gH) 0.5
orifice dia = 0.18 m
Area = 0.0254502 m2
Elevation H (m) Q(m3/s)
26.5 0 0.0
27 0.4 0.043 180 mm orifice hole required at IL = 26.5 m AHD
Culvert acting under inlet control
ORIFICE CALCULATION Q = 0.6× A×(2gH) 0.5
pipe dia = 0.375 m
Area = 0.110460938 m2
Elevation H (m) Q(m3/s)
27 0 0.043 wetland outflow at TED
27.05 0.4 0.177
27.5 0.8 0.265
28.5 1.8 0.395
Storage Relationship
Level (m AHD) Area (m2) Average Area (m2) Height Diff (m) Volume (m3) Cumulative Volume (m3)
26.5 10125 0
27 12340 11233 0.5 5616 5616
27.5 13593 12967 0.5 6483 12100
28.5 16100 14847 1 14847 26946
Stage/Storage/Storage Relationship
Level (m AHD) Q(m3/s) Storage (m3)
26.5 0 0 Normal Water Level
27 0.043 5616 Top of Extended Detention
27.05 0.177 6000
27.5 0.265 12100
28.5 0.395 26946 Cut line at lowest natural surface level
43
RB4 Stage Storage Discharge Relationship
Normal Water Level 27.75 m AHD
Normal Water Level Area = 4140 m2
Extended Detention level = 28 m AHD
Top of Extended Detention Area = 4666 m2
Outflow relationshipsRetarding Basin Outflow below TED m AHD
Average wetland treatment storage area = 4403 m2
Extended Detention height = 0.25 m
Extended detention volume = 1100.75 m3
Detention time = 36 hours - maximise outflow in ED range while
still allowing adequate treatment time
Outflow at TED = 0.008 m3/s
Therefore orifice control at invert level = 27.75 m AHD to limit outflow to
0.008 m3/s in ED range
ORIFICE CALCULATION Q = 0.6× A×(2gH) 0.5
orifice dia = 0.10 m
Area = 0.007089138 m2
Elevation H (m) Q(m3/s)
27.75 0 0.0
28 0.2 0.008 100 mm orifice hole required at IL = 27.75 m AHD
Culvert acting under inlet control
ORIFICE CALCULATION Q = 0.6× A×(2gH) 0.5
pipe dia = 0.45 m
Area = 0.15906375 m2
Elevation H (m) Q(m3/s)
27.75 0 0.000 wetland outflow at TED
28 0.0 0.008
28.5 0.5 0.919 TRIPLE outlet pipes under road
Storage Relationship
Level (m AHD) Area (m2) Average Area (m2) Height Diff (m) Volume (m3) Cumulative Volume (m3)
27.75 4140 0
28 4666 4403 0.25 1101 1101
28.5 6100 5383 0.5 2692 3792
Stage/Storage/Storage Relationship
Level (m AHD) Q(m3/s) Storage (m3)
27.75 0 0 Normal Water Level
28 0.008 1101 Top of Extended Detention
28.5 0.919 3792 Cut line at lowest natural surface level
44
Appendix C Flood Frequency Analysis Results
Scenario 1
• Existing situation
• No development or diversion of Cape Paterson North Flows
No times > 1.2 m3/s = 16 .= 2.0 per breeding season Looks OK - 1.2 m3/s is approx 3 month flow
No Breeding seasons incorporating a flow of 1.2 m3/s more than two times = 3 out of 8
0
200
400
600
800
1000
1200
1
10
81
21
61
32
41
43
21
54
01
64
81
75
61
86
41
97
21
10
80
1
11
88
1
12
96
1
14
04
1
15
12
1
16
20
1
17
28
1
18
36
1
19
44
1
20
52
1
21
60
1
22
68
1
23
76
1
24
84
1
25
92
1
27
00
1
28
08
1
29
16
1
30
24
1
31
32
1
32
40
1
33
48
1
34
56
1
35
64
1
36
72
1
37
80
1
38
88
1
39
96
1
41
04
1
42
12
1
43
20
1
44
28
1
45
36
1
46
44
1
47
52
1
48
60
1
49
68
1
50
76
1
51
84
1
52
92
1
54
00
1
55
08
1
56
16
1
57
24
1
58
32
1
59
40
1
60
48
1
61
56
1
62
64
1
63
72
1
64
80
1
65
88
1
66
96
1
68
04
1
69
12
1
45
Scenario 2
• Development of Cape Paterson North
• No wetlands or retardation initatives
No times > 1.2 m3/s = 55 .= 6.9 per breeding season
No Breeding seasons incorporating a flow of 1.2 m3/s more than two times = 8 out of 8
0
200
400
600
800
1000
1200
1
10
81
21
61
32
41
43
21
54
01
64
81
75
61
86
41
97
21
10
80
1
11
88
1
12
96
1
14
04
1
15
12
1
16
20
1
17
28
1
18
36
1
19
44
1
20
52
1
21
60
1
22
68
1
23
76
1
24
84
1
25
92
1
27
00
1
28
08
1
29
16
1
30
24
1
31
32
1
32
40
1
33
48
1
34
56
1
35
64
1
36
72
1
37
80
1
38
88
1
39
96
1
41
04
1
42
12
1
43
20
1
44
28
1
45
36
1
46
44
1
47
52
1
48
60
1
49
68
1
50
76
1
51
84
1
52
92
1
54
00
1
55
08
1
56
16
1
57
24
1
58
32
1
59
40
1
60
48
1
61
56
1
62
64
1
63
72
1
64
80
1
65
88
1
66
96
1
68
04
1
69
12
1
46
Scenario 3
• Development of Cape Paterson North
• 2000 Lite Tanks for toilet flushing on all lots
• Wetland extended detention range = 500 mm, extendeded detention period = 36 hours