    Cape Canaveral Minuteman Launch Complex 31 and 32Department of Defense Historic Structures Documentation Project

    1961

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    2/16

    Cape Canaveral Minuteman Launch Complex 31 and 32Department of Defense Historic Structures Documentation Project

    2008

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    3/16

    Minuteman Missile Program

    1961 - 1991

    Critical component of the U.S. Cold War missile system

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    4/16

    Launch Complex 31 and 32 Beehive BlockhousesDepartment of Defense Historic Structures Documentation Project

    Cape Canaveral Launch Complex 31 and 32

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    5/16

    Minuteman Launch Complex

    Blockhouses for the Minuteman Missile were 55 ft. high, made of

    reinforced concrete shells covered with sandbags that give it an

    unusual beehive appearance.

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    6/16

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    7/16

    Task:

    Capture detailed data of blockhouse exteriors forarchitectural restoration and condition monitoring

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    8/16

    Challenge:

    Hazardous conditions and structural instability caused by organicdegradation precluded conventional architectural measurement

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    9/16

    Solutions:

    Terrestrial LiDAR documentation of structures exteriorfrom ground-based and elevated platforms

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    10/16

    Solutions:

    3D Laser Scan data used to create CAD drawings and 3D modelsfor engineering analysis and management planning

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    11/16

    Method:

    Field data acquisition: 2 days Post-processing data: 1 week

    3D point clouds of data collected consisting of millions of x, y, and z points

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    12/16

    Method:

    Field data acquisition: 2 days Post-processing data: 1 week

    3D point clouds of data collected consisting of millions of x, y, and z points

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    13/16

    Final Product:

    Measurable data for engineering studies

    Planar view of scan data acquired demonstrating measurement capabilities

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    14/16

    Final Product:

    Measurable data for engineering studies

    Planar view of scan data acquired demonstrating measurement capabilities

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    15/16

    Final Products:

    Determination of structural integrity and deformation analysis

    Note substantial structural deformation apparent in cross sections

    Cross section (red)

    Cross section (yellow)

  • 8/6/2019 Cape Canaveral Minuteman Launch Complex 31 and 32 Department of Defense Historic Structures Documentation Project

    16/16

    This project was conducted in collaboration with:

    Thomas E. Penders, RPA, Archaeologist, 45 CES/CEVP