CAPACITY MANAGEMENT Nyoman Pujawan. MRP is capacity intensive. Validation of MPS is important to...
-
Upload
earl-warner -
Category
Documents
-
view
218 -
download
0
Transcript of CAPACITY MANAGEMENT Nyoman Pujawan. MRP is capacity intensive. Validation of MPS is important to...
CAPACITY MANAGEMENT
Nyoman Pujawan
• MRP is capacity intensive.
• Validation of MPS is important to establish a feasible schedule.
• Checking capacity sufficiency is done at MPS level and termed as Rough Cut Capacity Planning (RCCP)
Sales & OperationsPlanning
ResourcePlanning
Demand Management
Master ProductionScheduling
Detailed MaterialPlanning
Detailed CapacityPlanning
Material & CapacityPlans
Supplier SystemsShop-floorSystems
Ent
erpr
ise
Res
ourc
e P
lann
ingFront End
Engine
Back End
Sales & OperationsPlanning
ResourcePlanning
Demand Management
Master ProductionScheduling
Material Requirements
Planning
Rough Cut CapacityPlanning
Supplier Systems
Capacity requirementsPlanning
Ent
erpr
ise
Res
ourc
e P
lann
ingFront End
Engine
Back EndShop scheduling
RCCP Techniques
• Capacity Planning using Overall Factors (CPOF)
• Bill of Labor Approach
• Resource Profile Approach
Capacity Planning using Overall Factors (CPOF)
• Three inputs are needed:– MPS– The time the total plant requires to produce one “typical” part– Historical proportion of total plant time required by each of the
key resources
• CPOF multiplies the “typical” time by the MPS quantity to obtain total time required in the entire plant to meet the MPS.
• This time is then prorated among the key resources by multiplying total plant time by the historical proportion of time used at a given work center.
• The company only produces one product family, i.e., lamps
• A typical lamp requires 0.22 standard hours of labor / machine time.
• Bill of Labor for Lamp LAXX– Lamp assembly 0.1 hr– Oven 0.01 hr– Base forming 0.05 hr– Plastic molding 0.02 hr– Socket assembly 0.04 hrTOTAL 0.22 hr
Month Total Prod.
x 0.22 Lamp Assy
Oven Base Forming Plastic Moldi
ng
Socket Assy
Historical Proportion
0.455 0.045 0.227 0.091 0.182
J 15000 3300 1501.5 148.5 749.1 300.3 600.6
F 15000 3300 1501.5 148.5 749.1 300.3 600.6
M 15000 3300 1501.5 148.5 749.1 300.3 600.6
A 15000 3300 1501.5 148.5 749.1 300.3 600.6
M 15000 3300 1501.5 148.5 749.1 300.3 600.6
J 15000 3300 1501.5 148.5 749.1 300.3 600.6
J 15000 3300 1501.5 148.5 749.1 300.3 600.6
A 16000 3520 1601.6 158.4 799.04 320.32 640.64
S 19000 4180 1901.9 188.1 948.86 380.38 760.76
O 19000 4180 1901.9 188.1 948.86 380.38 760.76
N 19000 4180 1901.9 188.1 948.86 380.38 760.76
D 19000 4180 1901.9 188.1 948.86 380.38 760.76
197000 Total Hours 19717.7 1950.3 9838.18 3943.94 7887.88
RCCP using the CPOF Approach
Bill of Labor Approach• Also known as Bill of Resources or Bill of Capacity• Is a listing by item number the amount of labor required
by a major labor category to produce that item or group of part numbers. It is not intended to be a routing, but merely a means of estimating the capacity requirements for a particular item. The BOL may be compiled for each distinct item or for group of similar items, and extended by the scheduled quantities to determine capacity requirements.
• In each department, calculate the time required by multiplying the time required in each department to produce a lamp by the number of lamps to produce in a month
Month Total Prod.
x 0.22 Lamp Assy
Oven Base Forming Plastic Molding
Socket Assy
BOL X 0.1 hr X 0.01 hr X 0.05 hr X 0.02 hr X 0.04 hr
J 15000 3300 1500 150 750 300 600
F 15000 3300 1500 150 750 300 600
M 15000 3300 1500 150 750 300 600
A 15000 3300 1500 150 750 300 600
M 15000 3300 1500 150 750 300 600
J 15000 3300 1500 150 750 300 600
J 15000 3300 1500 150 750 300 600
A 16000 3520 1600 160 800 320 640
S 19000 4180 1900 190 950 380 760
O 19000 4180 1900 190 950 380 760
N 19000 4180 1900 190 950 380 760
D 19000 4180 1900 190 950 380 760
197000 Total Hours 19700 1970 9850 3940 7880
RCCP using the BOL Approach
Resource Profile Approach
• Both of the previous techniques ignore lead-time offsets
• Here, we will consider it. Each BOL must be time phased in the resource profile approach.
Resource Profile for Lamp LAXX
Department Month before due date
2 1 0
Lamp assembly 0.1
Oven 0.01
Base forming 0.05
Plastic molding 0.02
Socket assembly 0.04
Month Total Prod.
x 0.22 Lamp Assy
Oven Base Forming Plastic Molding
Socket Assy
BOL X 0.1 hr X 0.01 hr X 0.05 hr X 0.02 hr X 0.04 hr
J 15000 3300 1500 150 750 300 600
F 15000 3300 1500 150 750 300 600
M 15000 3300 1500 150 750 300 600
A 15000 3300 1500 150 750 300 600
M 15000 3300 1500 150 750 300 600
J 15000 3300 1500 150 800 300 600
J 15000 3300 1500 160 950 320 640
A 16000 3520 1600 190 950 380 760
S 19000 4180 1900 190 950 380 760
O 19000 4180 1900 190 950 380 760
N 19000 4180 1900 190 0 380 760
D 19000 4180 1900 0 0 0 0
197000 Total Hours 19700 1820 8350 3640 7280
RCCP using the BOL Approach
Choosing an RCCP Technique
• Resource profile requires more computational time than the bill of labor approach, but for the case where lead times are long, the results are more accurate.
Example
• A product, W, has two operations, performed in WCs 1 and 2. The BOL and resource profile are as follows:
BOL
WC1 20WC2 30
Resource Profile
Work until due 1 0
WC1 20WC2 30
MPS Week1 2 3 4100 200 250 100
Develop Capacity Requirement using BOL and Resource Profile Approach
Determining Capacity Available
Factors affecting available capacity:• Time available• Utilization 1 minus the proportion of
time typically lost due to machine, worker, tool, or material unavailability
• Efficiency time standard / time actually needed to perform an operation
Capacity available = Time available x Utilization x Efficiency
Capacity Requirements Planning (CRP)
• Te function of establishing, measuring, and adjusting limits or levels of capacity …. The process of determining how much labor and machine resources are required to accomplish the task of production.
Closed-Loop MRP
MPS
CapacityOK?
MRP
CapacityOK?
Vendor control Detail Schedule
Input / Output Control
CRP
RCCP
CRP Logic
• MPS is exploded via MRP system
• Planned order release are taken from MRP system and used to perform a deterministic simulation of the time each order passes through each work station
• A machine load report is produced
Example of CRP
Level Part Qty/
Parent
Description
0 100 1 Finished product
1 110 2 Subassembly
2 121 6 Component A
2 122 10 Component B
Bill of Material
Item Master RecordItem Order
Quantity
On Hand On Order Due Date
Lead Time
Allocated
100 LFL 0 250 7/3 1 week 0
110 400 500 400 7/10 2 weeks 0
121 2400 1500 2400 7/10 3 weeks 0
122 6000 2500 6000 7/10 4 weeks 0
Work Center
Available Utilization Efficiency Planned Queue
1 2400 minutes 100% 100% 4 days
2 2400 minutes 100% 100% 4 days
3 2400 minutes 100% 100% 4 days
Work Center Master File
Part Work Center Setup Time / Lot Run Time / Piece
100 1 30 2.5
110 2 10 0.75
1 15 0.5
121 3 15 0.3
1 25 0.25
2 15 0.25
122 2 25 0.75
3 30 0.15
1 75 0.5
3 30 0.75
Routing Files
MPS for Part 100
1 2 3 4 5 6 7 8 9 10 11 12
QTY 250 200 250 150 200 300 150 250 200 200 250 200
WC 1 2 3 4 5 6 7 Average
1 2604 2083 2604 1562 2083 3125 1562 2232
2 2657 2125 2657 1594 2125 3188 1594 2277
3 2734 2187 2734 1640 2187 3281 1640 2343
RCCP
Item 100, LT = 1
0 1 2 3 4 5 6 7
Gross Req 250 200 250 150 200 300 150
Sched receipts 250
Projected OH 0 0 0 0 0 0 0 0
Planned release 200 250 150 200 300 150 250
Item 110, LT = 2
0 1 2 3 4 5 6 7
Gross Req 400 500 300 400 600 300 500
Sched receipts 400
Projected OH 500 100 0 100 100 0 100 0
Planned release 400 400 500 400 400 400 400
Fixed period, period to order = 1
Fixed quantity, MOQ = 400, Incremental = 100
Item 121, LT = 3
0 1 2 3 4 5 6 7
Gross Req 1200 1200 1200 1200 1200 1200 1200
Sched receipts 2400
Projected OH 1500 300 1500 0 1200 0 1200 0
Planned release 2400 0 2400 0 2400 2400 0
Item 122, LT = 4
0 1 2 3 4 5 6 7
Gross Req 2000 2000 2000 2000 2000 2000 2000
Sched receipts 6000
Projected OH 2500 500 4500 2000 0 4000 2000 0
Planned release 6000 0 0 6000 0 0 0
Fixed quantity, quantity to order = 2400
Fixed quantity, Quantity to order = 6000
1 2 3 4 5 6 7
100 200 250 150 200 300 150 250
110 400 400 500 400 400 400 400
121 2400 0 2400 0 2400 2400 0
122 6000 0 0 6000 0 0 0
Planned Order Release
• POR is lumpy for items 121 and 122.• This could cause problems with the shop floor uneven flow of work.• CRP is needed even when RCCP has been properly developed, to determine whether batching orders for components has created an uneven flow of work.
CRP Computation
• A separate calculation for setup time and run time
• Each operation has one week lead time• Setup matrix is created directly from
Planned Order Release in MRP system and Routing Files
• Example: Part 122 (6000 is to be released in wek 1). From routing file, 122 is routed to WC2, WC3, WC1, and back to WC3.
1 2 3 4 5 6 7
WC1 100 30 30 30 30 30 30 30
110 0 15 15 15 15 15 15
121 0 25 0 25 0 25 25
122 0 0 75 0 0 75 0
Total 30 70 120 70 45 145 70
WC2 100 0 0 0 0 0 0 0
110 10 10 10 10 10 10 10
121 0 0 15 0 15 0 15
122 25 0 0 25 0 0 0
Total 35 10 25 35 25 10 25
WC3 100 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0
121 15 0 15 0 15 15 0
122 0 30 0 30 30 0 30
Total 15 30 15 30 45 15 30
Setup Time Matrices
1 2 3 4 5 6 7
WC1 100 500 625 375 500 750 375 625
110 0 200 200 250 200 200 200
121 0 600 0 600 0 600 600
122 0 0 3000 0 0 3000 0
Total 500 1425 3575 1350 950 4175 1425
WC2 100 0 0 0 0 0 0 0
110 300 300 375 300 300 300 300
121 0 0 600 0 600 0 600
122 4500 0 0 4500 0 0 0
Total 4800 300 975 4800 900 300 900
WC3 100 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0
121 600 0 600 0 600 600 0
122 0 900 0 2100 900 0 2100
Total 600 900 600 2100 1500 600 2100
Run Time Matrices = Quantity x Run Time / Unit
1 2 3 4 5 6 7
WC1 530 1495 3695 1420 995 4320 1495
WC2 4835 310 1000 4835 925 310 925
WC3 615 930 615 2130 1545 615 2130
Capacity requirements of Planned Release (Setup + Run Times)
Part WC Week Setup Time
Run Time Calculation
Run Time Total Time
100 1 1 30 250 x 2.5 625 655
110 2 1 10 400 x 0.75 300 310
110 1 2 15 400 x 0.5 200 215
121 1 1 25 2400 x 0.25 600 625
121 2 2 15 2400 x 0.25 600 615
122 1 1 75 6000 x 0.5 3000 3075
122 3 2 30 6000 x 0.75 4500 4530
Capacity required by Released Orders
WC Week 1 Week 2
1 4355 215
2 310 615
3 0 4530
1 2 3 4 5 6 7
WC1 4885 1710 3695 1420 995 4320 1495
WC2 5145 925 1000 4835 925 310 925
WC3 615 5460 615 2130 1545 615 2130
Summary of Released Order Capacity Requirements
Capacity Requirements Plan (Overall)
Available Vs Required Capacity
0
1000
2000
3000
4000
5000
6000
1 2 3 4 5 6 7
WC1
WC2
WC3
Available capacity