Cap budget [autosaved]

29
10-1 The Basics of Capital Budgeting

Transcript of Cap budget [autosaved]

Page 1: Cap budget [autosaved]

10-1

The Basics of Capital Budgeting

Page 2: Cap budget [autosaved]

10-2

What is capital budgeting? Analysis of potential additions to

fixed assets. Long-term decisions; involve

large expenditures. Very important to firm’s future.

Page 3: Cap budget [autosaved]

10-3

Examples:

Expansion Replacement Buy or lease Choice of equipment Capital expenditure

Page 4: Cap budget [autosaved]

10-4

Problems:

Demand for capital-how much money needed for expenditure

Supply of capital – internal and external

Capital rationing – selection of the projects

Page 5: Cap budget [autosaved]

10-5

Types of capital

Debt Preference share Equity capital Retained earningsWACC: weighted average cost of

capital

Page 6: Cap budget [autosaved]

10-6

methods

Pay back method Accounting rate of return Internal rate of return Net present value

Page 7: Cap budget [autosaved]

10-7

Steps to capital budgeting

1. Estimate CFs (inflows & outflows).2. Assess riskiness of CFs.3. Determine the appropriate cost of

capital.4. Find NPV and/or IRR.5. Accept if NPV > 0 and/or IRR > WACC.

Page 8: Cap budget [autosaved]

10-8

What is the difference between independent and mutually exclusive projects?

Independent projects – if the cash flows of one are unaffected by the acceptance of the other.

Mutually exclusive projects – if the cash flows of one can be adversely impacted by the acceptance of the other.

Page 9: Cap budget [autosaved]

10-9

What is the difference between normal and nonnormal cash flow streams?

Normal cash flow stream – Cost (negative CF) followed by a series of positive cash inflows. One change of signs.

Nonnormal cash flow stream – Two or more changes of signs. Most common: Cost (negative CF), then string of positive CFs, then cost to close project. Nuclear power plant, strip mine, etc.

Page 10: Cap budget [autosaved]

10-10

What is the payback period?

The number of years required to recover a project’s cost, or “How long does it take to get our money back?”

Calculated by adding project’s cash inflows to its cost until the cumulative cash flow for the project turns positive.

Page 11: Cap budget [autosaved]

10-11

Calculating payback

PaybackL = 2 + / = 2.375 years

CFt -100 10 60 100Cumulative -100 -90 0 50

0 1 2 3

=

2.4

30 80

80

-30

Project L

PaybackS = 1 + / = 1.6 years

CFt -100 70 100 20Cumulative -100 0 20 40

0 1 2 3

=

1.6

30 50

50-30

Project S

Page 12: Cap budget [autosaved]

10-12

Strengths and weaknesses of payback

Strengths Provides an indication of a project’s

risk and liquidity. Easy to calculate and understand.

Weaknesses Ignores the time value of money. Ignores CFs occurring after the

payback period.

Page 13: Cap budget [autosaved]

10-13

Discounted payback period

Uses discounted cash flows rather than raw CFs.

Disc PaybackL = 2 + / = 2.7 years

CFt -100 10 60 80

Cumulative -100 -90.91 18.79

0 1 2 3

=

2.7

60.11

-41.32

PV of CFt -100 9.09 49.59

41.32 60.11

10%

Page 14: Cap budget [autosaved]

10-14

Accounting rate of return

= estimated net profits/ capital employed . 100

Average investment =( initial investment + scrap value) / 2

Limitation : does not look at time value of money

Page 15: Cap budget [autosaved]

10-15

Net Present Value (NPV) Sum of the PVs of all cash inflows and

outflows of a project:

n

0tt

t

) k 1 (CF

NPV

Page 16: Cap budget [autosaved]

10-16

What is Project L’s NPV?

Year CFt PV of CFt

0 -100 -$100 1 10 9.09 2 60 49.59 3 80 60.11

NPVL = $18.79

NPVS = $19.98

Page 17: Cap budget [autosaved]

10-17

Rationale for the NPV methodNPV = PV of inflows – Cost

= Net gain in wealth If projects are independent, accept if

the project NPV > 0. If projects are mutually exclusive,

accept projects with the highest positive NPV, those that add the most value.

In this example, would accept S if mutually exclusive (NPVs > NPVL), and would accept both if independent.

Page 18: Cap budget [autosaved]

10-18

Internal Rate of Return (IRR) IRR is the discount rate that forces PV of

inflows equal to cost, and the NPV = 0:

Normally NPV METHOD and IRR method gives the same result

n

0tt

t

) IRR 1 (CF

0

Page 19: Cap budget [autosaved]

10-19

How is a project’s IRR similar to a bond’s YTM?

They are the same thing. Think of a bond as a project.

The YTM on the bond would be the IRR of the “bond” project.

EXAMPLE: Suppose a 10-year bond with a 9% annual coupon sells for $1,134.20. Solve for IRR = YTM = 7.08%, the

annual return for this project/bond.

Page 20: Cap budget [autosaved]

10-20

Rationale for the IRR method

If IRR > WACC, the project’s rate of return is greater than its costs. There is some return left over to boost stockholders’ returns.

Page 21: Cap budget [autosaved]

10-21

IRR Acceptance Criteria If IRR > k, accept project. If IRR < k, reject project.

If projects are independent, accept both projects, as both IRR > k = 10%.

If projects are mutually exclusive, accept S, because IRRs > IRRL.

Page 22: Cap budget [autosaved]

10-22

NPV Profiles A graphical representation of project

NPVs at various different costs of capital.

k NPVL NPVS

0 $50 $40 5 33 2910 19 2015 7 1220 (4) 5

Page 23: Cap budget [autosaved]

10-23

Comparing the NPV and IRR methods

If projects are independent, the two methods always lead to the same accept/reject decisions.

If projects are mutually exclusive … If k > crossover point, the two

methods lead to the same decision and there is no conflict.

If k < crossover point, the two methods lead to different accept/reject decisions.

Page 24: Cap budget [autosaved]

10-24

Comparisons :proposals Initial inv Annual cash

flowLife in years

1 60,000 12000 15

2 88,000 22,500 22

3 2150 1,500 3

4 20,500 4500 10

5 4,25,000 2,25000 20

Page 25: Cap budget [autosaved]

10-25

Pay back methodPay back period =

Initial investment/annual cash flow

1 60,000/12,000 5

2 88,00/22500 3.9

3 21,50/1500 1.4

4 2,5000/4500 4.6

5 4,25000/2,25000 1.9

Page 26: Cap budget [autosaved]

10-26

Accounting rate proposal

Initial investment

Annual cash flow

Life in years

Annual depreciation

Net profits

Rate of return

1 60,000 12000 15 4000 8000 26.67

2 88,000 22,500 22 4000 18,500 42

3 2150 1500 3 717 783 72.84

4 20,500 4500 10 2050 2450 23.9

5 4,25000

2,25000

20 21,250 203750 95.88

Page 27: Cap budget [autosaved]

10-27

NPV

proposal

Initial inv

Annual cash low

life Pv(10%)

Pv npvi

1 60,000

12,000 15 7.7688 93225.6

1.55

2 88,000

22,500 22 8.8919 200,067.75

2.27

3 2150 1500 3 2.5918 3887.7 1.81

4 20,500

4500 10 6.3213 28445.8

1.39

5 425,000

2,25000

20 8.6466 1945485

4.56

Page 28: Cap budget [autosaved]

10-28

DCF

Discounted cash flows or internal rate of return may sometimes give different results

Page 29: Cap budget [autosaved]

10-29

All methods do not give the same interpretation

methods

payback

accounting

DCF NPV

Proposal rank ranks ranks ranks

1 5 4 4 4

2 3 3 3 2

3 1 2 2 3

4 4 5 5 5

5 2 1 1 1