Canal Road Project Analysis Last Updated: July 2021 Overview Start End 6094360 Design 1/1/2017 Land 10/1/2018 Construction 1/1/2022 Project Status Project Manager Mike Sturm Departments Public Works 3/31/2021 12/31/2021 12/31/2024 District 2 Design and construct four (4) travel lanes between US 301 to north of 17th Street East. Include the realignment of Mendoza Road connecting 37th Street East to 39th Street East at Canal Road. To meet current design standards for thoroughfare roadways. Traffic analysis indicates an increase in traffic volume on Canal Road between US 301 and 17th Street East. Therefore, increasing the scope of work to design and construct four (4) lanes instead of two (2) will increase safety to the motoring public. Further, the realignment of Mendoza Road connecting the eastern segment, 37th Street E, to the western segment, 39th Street E, at one intersection on Canal Road will decrease conflicts at the intersection allowing for a safer traffic movement. (Project # 6094360)

Transcript of Canal Road Project Analysis

Page 1: Canal Road Project Analysis

Canal Road Project AnalysisLast Updated: July 2021

Overview

Start End6094360 Design 1/1/2017

Land 10/1/2018Construction 1/1/2022

Project Status

Project Manager Mike Sturm

Departments Public Works

3/31/202112/31/202112/31/2024

District 2

Design and construct four (4) travel lanes between US 301 to north of 17th Street East. Include the realignment of Mendoza Road connecting 37th Street East to 39th Street East at Canal Road.

To meet current design standards for thoroughfare roadways. Traffic analysis indicates an increase in traffic volume on Canal Road between US 301 and 17th Street East. Therefore, increasing the scope of work to design and construct four (4) lanes instead of two (2) will increase safety to the motoring public. Further, the realignment of Mendoza Road connecting the eastern segment, 37th Street E, to the western segment, 39th Street E, at one intersection on Canal Road will decrease conflicts at the intersection allowing for a safer traffic movement. (Project # 6094360)

Page 2: Canal Road Project Analysis

Canal Road Project Analysis

Summary of Finances

Budget Year to Date Remaining

Balance %

Received Revenues

AppropriatedLocal Option 4 Cent Capital Projects Gas Tax1,000,000 1,000,000 - 100%NW Transportation Impact Fees 2,000,000 2,000,000 - 100%Infrastructure Sales Tax 4,830,000 4,830,000 - 100%

7,830,000 7,830,000 - 100%Future Appropriation

Infrastructure Sales Tax 21,145,209 - 21,145,209 0%28,975,209 7,830,000 21,145,209 27%

Budget Encumb Project Total Remaining

Balance % Spent Expenses

AppropriatedCanal Rd - US 301 - US 41 7,830,000 1,480,822 1,692,789 4,656,389 22%

7,830,000 1,480,822 1,692,789 4,656,389 22%Future Appropriations

Canal Rd - US 301 - US 41 21,145,209 - - 21,145,209 0%28,975,209 1,480,822 1,692,789 25,801,598 6%

Manatee County Capital Projects - 1112 Manatee Ave W., Bradenton, FL 34205https://www.mymanatee.org/departments/financial_management/capital_improvement_program