Can Prolongation Costs Be Claimed When There is No Entitlement to an Extension of Time

download Can Prolongation Costs Be Claimed When There is No Entitlement to an Extension of Time

of 2

Transcript of Can Prolongation Costs Be Claimed When There is No Entitlement to an Extension of Time

  • 7/26/2019 Can Prolongation Costs Be Claimed When There is No Entitlement to an Extension of Time

    1/2

    This paper has been reproduced with permission from the author and included in the ICCP

    Knowledge Center to support and encourage the learning and professional development ofICCP members.

    The ICCP seeks to ensure that all content, information and downloadable articles published onthe ICCP website is current and accurate, but such information does not in any way constitute

    legal advice. The ICCP cannot be held liable for any losses incurred as a result of anycommunication from the ICCP, or from information found on the ICCP website or members

    Knowledge Centre.

    Title: Can Prolongation Costs be claimed when there is no Entitlement to anExtension of Time?

    Author: Andy Hewitt

    Date: 12 March 2016

    It is generally accepted that, in a situation where a contractor is entitled to an extension of time,

    he is also entitled to claim for time-related costs for site overheads and head office running

    costs for the additional time that he was obliged to remain on site. This is based upon a

    fundamental principle of law, that a party who has been prevented from performing his

    obligations by the other party, is entitled to compensation to put him back into the position that

    he would have been in, had the act of prevention not occurred. In construction terms, this

    usually means the reimbursement of the contractors costs for providing site management, site

    establishment, plant and equipment, insurances, additional financing costs and the like and

    head office costs, which are often referred to as prolongation costs for the extended time.

    Are there situations, however, that a contractor may legitimately claim for the payment of costs

    when an extension of time is not warranted? Well, yes there are. Consider the following

    example.

    The contractor is constructing a high-rise building and has a tower crane on site, which his

    programme shows is to be removed on a certain date. The contractor however receives a

    variation order to change the specification of the air-conditioning chiller, which is located on the

    roof of the building and needs to be hoisted into position by the tower crane. The change to the

  • 7/26/2019 Can Prolongation Costs Be Claimed When There is No Entitlement to an Extension of Time

    2/2

    chiller requires modifications to be made at the factory where the chiller is being manufactured

    and this will delay the delivery of the chiller to a date later than the date by which the contractor

    had planned to remove the crane.

    The contractor will therefore incur additional costs in hiring (or depreciation costs of) the tower

    crane, the crane operator and safety checks and maintenance, from the time that he should

    have been able to remove the crane, to the date that he was able to hoist the chiller into

    position.

    There is a direct linkage of the cause, i.e. the variation, to the effect, which is the additional

    time-related costs for the tower crane.

    The costs here could either be claimed with the variation for the chiller, or submitted as a

    discrete claim.