Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date...
Transcript of Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date...
![Page 1: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/1.jpg)
Caltrain Electrification
UpdateSunnyvale Council Meeting
November 13, 2018
![Page 2: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/2.jpg)
Agenda
• Caltrain System Overview
• Project Overview
• Electric Train Design
• Sunnyvale Construction Activities
• Questions
![Page 3: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/3.jpg)
Caltrain System
• 32 Stations Gilroy to
San Francisco
• 92 Weekday Trains
• At-Grade Crossings,
viaducts, and bridges
• Intermodal Connections
• Bike Commuters
JPB owns
right-of-way
from SF to
San Jose
![Page 4: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/4.jpg)
Ridership
![Page 5: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/5.jpg)
At Capacity Today
Bi-directional commute with riders standing on
trains going southbound and northbound
![Page 6: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/6.jpg)
Aging Fleet
At Retirement Age: 20/29 loco; 73/134 cars
![Page 7: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/7.jpg)
Regional Transportation Needs
• US 101 and Interstate 280 Congested
• Corridor supports growing economy
• 75% Caltrain riders commute to work
• 60% are choice riders
![Page 8: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/8.jpg)
Project DescriptionArea Project Service
51 miles
San Francisco
to San Jose
(Tamien Station)
Electrification:
• Overhead Contact
System (OCS)
• Traction Power
Facilities
Electric Trains
• 75 percent of fleet
Up to 79 mph
Service Increase
• 6 trains / hour / direction
• More station stops / reduced travel
time
• Restore Atherton & Broadway
service
Mixed-fleet service (interim period)
Continue tenant service
• ACE, Capital Corridor, Amtrak,
Freight
![Page 9: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/9.jpg)
Service Benefits
Metric Today PCEP
Example Baby Bullet Train
Retain 5-6 stops 60 minutes 45 minutes
Retain SF to SJ
60 minutes
6 stops 13 stops
Example Redwood City Station
Train stops / peak
hour
3 5
Note: Prototypical Train and Schedule
![Page 10: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/10.jpg)
Key Regional Benefits (2040)
Note: 2013 BAC Report, generates $2.5B economic activity and 9,600 jobs
![Page 11: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/11.jpg)
Schedule
![Page 12: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/12.jpg)
Electric Train• 2016 Capacity Board Decision (bike to seat ratio,
onboard bathrooms, upper doors ‘not precluded’)
• 2017 Design Progressing w/ Additional Public Input
– Completed: Exterior design, Seat colors, Bike
Storage, ADA restroom
• 2019 Virtual Reality 360 Tour
![Page 13: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/13.jpg)
Construction Phasing
• 51 Miles Corridor
• 4 Work Segments
• 3,000 Poles
• 10 Traction Power
Facilities
![Page 14: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/14.jpg)
Sunnyvale – Work Segment 3
Sunnyvale Work Area 4 miles
![Page 15: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/15.jpg)
Field Work Status
Pre-Construction
Work Completed
• Utility Survey
• Geotechnical Investigations
• Disposal of Soil from Geotechnical Investigations
• Soil Resistivity Testing
• Site Surveys
• Signal Cable Inspections
Pre-Construction
Work In Progress
• Foundation Potholing
• Tree Pruning and Removal
Future Work • Foundation Installation
• Overhead Contact System Pole Installation
• Overhead Contact System Wire Installation
• Paralleling Station
![Page 16: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/16.jpg)
Future Construction Activities
Sunnyvale
Date Work ActivityExpected
Duration*
Summer/Fall 2018 Potholing 2-3 months
Fall 2018 Tree Pruning/Removal 2-3 months
Early 2019 Paralleling Station Construction 4-6 months
Summer/Fall 2019 Pole/Wire Installation 4-5 months
Summer/Fall 2019 Foundation Installation 2-4 months
*Expected duration indicates first and last day of activity.
Number of actual work days will be fewer.
![Page 17: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/17.jpg)
Potholing
Approx. 325 Potholes Sunnyvale
![Page 18: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/18.jpg)
Tree Pruning and Replacement
Vegetation cleared for Electrical Safety Zone
![Page 19: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/19.jpg)
City of Sunnyvale
Caltrain
Right of Way
Public
Property
Private
Property
Trees Removed 85 1 45
Trees Pruned
>25%133 2 38
Trees Pruned
<25%148 5 101
304 Trees will be replaced per the Sunnyvale Tree Replacement Plan
City of Sunnyvale: Tree Pruning and Replacement Plan
Note: Information may change as the design progresses
![Page 20: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/20.jpg)
Foundation Construction
• Excavation
• Rebar and Anchor Installation
• Electrical Grounding
• Concrete Fill
![Page 21: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/21.jpg)
Foundation Installation
On Track Equipment
![Page 22: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/22.jpg)
Pole Installation
• 3,000 Installed throughout Corridor
• Approx. 250 Poles in Sunnyvale
• Pole Height: 30-45.5’
• Pole Spacing: ~180’ apart
![Page 23: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/23.jpg)
Example Pole Types
PortalsSingle Track Cantilever Two Track Cantilever
![Page 24: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/24.jpg)
Pole Installation
Current Pole Installation
![Page 25: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/25.jpg)
Stringing Wire
On-track Equipment
![Page 26: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/26.jpg)
Traction Power Facilities
• 10 Traction Power Facilities Installed throughout
Corridor
• Facility Components
– Transformer
– Gantries (up to 50’)
– Control House
• Provides electrical power to trains through the
Overhead Contact System
• Unmanned secure station
![Page 27: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/27.jpg)
Paralleling Station 6
• Located at the Sunnyvale Caltrain Station Parking Lot
– Coordination with City on location during EIR
– Approx. 21 parking spots permanently taken
• Vegetation Screening will be implemented with review
and input from City Staff
• Additional parking spaces needed during construction
• Majority of work done during the day
![Page 28: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/28.jpg)
Paralleling Station 6
Location
Gantries
Transformer
Control House
Layout subject to change as design progresses
![Page 29: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/29.jpg)
Example Paralleling Station
Example from Amtrak Northeast Corridor
![Page 30: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/30.jpg)
Overall Construction Information
• Work will occur during day and night
• Some 24 hour weekend work
• Crews will utilize acoustical barrier blankets and
position lights away from homes
• Dedicated hotline for construction complaints
![Page 31: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/31.jpg)
SF Weekend Caltrain Closures
• Weekends - Oct 6, 2018 to Late Spring 2019
– Caltrain service north of the Bayshore Station
will be suspended on the weekends
– Bus service will be provided from Bayshore to 4th
and King and 22nd Street stations
• Weekday service will remain unchanged
• Caltrain service south of Bayshore will remain
unchanged
• Bus schedule available at caltrain.com
![Page 32: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/32.jpg)
Public Outreach
• Subscribe to Weekly Updates
– Visit www.calmod.org/get-involved
• Additional Community Meetings
– Pole and Wire Installation
– Paralleling Station Construction
• Social Media
• Construction Outreach Office
![Page 33: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/33.jpg)
Public Outreach
Physical Notices
![Page 34: Caltrain Electrification Update · 2019. 1. 2. · Future Construction Activities Sunnyvale Date Work Activity Expected Duration* Summer/Fall 2018 Potholing 2-3 months Fall 2018 Tree](https://reader034.fdocuments.us/reader034/viewer/2022051906/5ff8c0defcf8ab1c3e4e1b6f/html5/thumbnails/34.jpg)