California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.

10
California’s Proposed DR Cost-Effectiveness Framework January 30, 2008

Transcript of California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.

Page 1: California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.

California’s Proposed DR Cost-Effectiveness Framework

January 30, 2008

Page 2: California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.

© 2008 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution2

Background

January 2007 – DR proceeding opened at the CPUC– Phase 1: DR load impact protocols & cost-effectiveness

IOUs, DR providers, and others submitted straw proposals on cost-effectiveness methodologies

– Proposals focused on CA’s EE Standard Practice Manual as starting point for DR evaluation

– Straw proposals intended to focus on methodology – not inputs – since avoided costs were to be addressed in a different proceeding/forum

– Several areas of disagreement among parties with regard to C-E methodologies proposed

Settlement-style discussions to develop proposed evaluation “framework”

All signing parties reserved the right to contest details if framework approved and applied

– Data sources– Assumptions– Modifications to approach

Final decision from CPUC on framework expected Spring 2008

Page 3: California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.

© 2008 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution3

Purpose of DR Evaluation Framework

As an ex ante evaluation both event (e.g. dispatchable) and non-event (e.g. tariff pricing) based DR programs

To be used to evaluate the CA Utilities 2009 – 2011 DR program portfolios to be filed by June 1, 2008

To be used to evaluate 3rd party DR providers and other programs outside of the utilities’ portfolios

To represent the most up-to-date and accurate measurement of DR program costs and benefits

To establish a flexible framework for future evaluation of DR programs to accurately reflect their attributes

Page 4: California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.

© 2008 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution4

Analytical Approach

DR resources to be evaluated to the extent they can reduce the need for supply-side resources

– Reduce peak system loads

– Meet resource adequacy/reserve requirements

– Other benefits

Evaluate DR from four perspectives

– Total Resource Cost (TRC): Utilities’ primary screening test

– Program Administrator (PAC): Potential supplemental screening test

– Ratepayer Impact Measure (RIM)

– Participant (PCT)

Incentive costs offset customer costs for voluntary programs

– Assumption required because participating customers’ costs difficult to accurately determine

Lifecycle analysis comparing the net present values of benefits and costs

Page 5: California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.

© 2008 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution5

Avoided Generation Capacity Costs

Annual market price ($/kW) of the capacity of a new combustion turbine

– Increased by: return, income taxes, depreciation, O&M, taxes, insurance and other incremental costs

– Reduced by: gross margins earned by selling energy by employing option pricing methodology or production cost modeling analysis

– Will account for service-area-specific CT construction and fixed environmental costs and inter-regional differences in wholesale electricity prices

DR programs with no usage or availability constraints, avoided capacity cost value = full annualized and adjusted CT cost

For DR programs with availability constraints, value is determined by allocating CT costs across the highest-valued periods when program is available

CT costs account for DR’s preference in CA’s loading order such that no adjustment is made when reserve margins are expected to be exceeded (within reasonable limits)

Page 6: California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.

© 2008 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution6

Avoided Energy Costs

Value of avoided energy costs may be determined by:

– Wholesale energy prices averaged over the forecast’s highest-priced hours

– Stochastic method reflecting the correlation between electricity prices and the periods when DR events expected to occur and be available

Avoided energy costs will take into account:

– Avoided line losses

– Incremental costs of any additional demand resulting from load-shifting programs

– Avoided congestion costs after CA’s MRTU provides sufficient locational marginal pricing data (future input expected 2012 – 2014 program funding cycle)

Page 7: California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.

© 2008 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution7

Avoided T&D Costs

Interim method for valuing avoided T&D until more experience is gained with DR programs

Default avoided T&D costs will be calculated using the marginal transmission and distribution costs for non-ISO T&D resources

DR programs must meet “right place” and “right certainty” criteria:

1. Are located in areas where load growth would result in need for additional delivery infrastructure

2. Are located in areas where the specific DR program is capable of addressing local delivery capacity needs

3. Have sufficient certainty of providing long-term reductions

4. Can be relied upon for local T&D equipment loading relief

Case-specific study of avoided T&D costs may be performed in place of default values

Page 8: California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.

© 2008 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution8

Other Benefits

Higher generation capacity value may be applied when a shortfall in planning reserves is anticipated

Cost of meeting environmental emission standards not already accounted for in the CT costs (e.g. greenhouse gases)

Avoided ancillary services procurement

– Will not be applied immediately but value to be determined after CA’s new market design is operational and able to supply data (Future input)

Page 9: California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.

© 2008 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution9

DR Costs & Data Sources

DR Costs

Costs of incentives to participants

All other incremental costs associated with program– Program management, software development, etc.

Payments to third-party DR providers– Utility and 3rd party provider programs may not be comparable using this

framework – Incentives payments made by DR providers to customers are not

incremental so they are included as a cost in the TRC analysis.

Data Sources

Utilities will use the most recent, up-to-date estimates for each value and cost stream. This data may come from:

– Published/litigated sources– General rate case data– Modeling studies

Page 10: California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.

© 2008 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution10

EnerNOC, Inc.24 W. 40th Street, 16th Floor

New York, NY 10018

EnerNOC, Inc.594 Howard Street, Suite 400

San Francisco, CA 94105

EnerNOC, Inc.75 Federal St. Suite

300Boston, MA 02110

Carmen HenriksonSenior Manager Market [email protected](415) 343-9502

Questions?