CALIFORNIA STATE UNIVERSITY, NORTHRIDGE RELIABILITY OF ...
Transcript of CALIFORNIA STATE UNIVERSITY, NORTHRIDGE RELIABILITY OF ...
i
CALIFORNIA STATE UNIVERSITY, NORTHRIDGE
RELIABILITY OF DISTRIBUTION SYSTEMS
USING MARKOV PROCESS AND ETAP
A graduate project submitted in partial fulfillment of the requirements
For the degree of Master of Science in Electrical Engineering
By Kunal Raut
December 2018
ii
The graduate project of Kunal Raut is approved:
_______________________________ _____________
Xiyi Hang, Ph.D. Date
_______________________________ _____________
John Valdovinos, Ph.D. Date
_______________________________ _____________
Ignacio B. Osorno, Chair Date
California State University, Northridge
iii
ACKNOWLEDGEMENT
I would love to grab this opportunity to impart appreciation to my mentor for this
project, my project chair, Prof. Bruno Osorno. I got to learn a lot about power system
reliability through my project βReliability of distribution systems using Markov process
and ETAPβ which would have not been possible without the guidance of my advisor.
I also convey my acknowledgement to Dr. Valdovinos, John and Dr. Hang, Xiyi.
Their expertise related to the subject has been helpful in resolving many issues during the
project.
Also, Iβm much obliged to my kinfolks for having my back through the entire
process of my education.
iv
TABLE OF CONTENTS
Signature Page ii
Acknowledgement iii
List of Figures v
List of Tables vii
Abstract viii
Section 1 β Introduction 1
1.1 Reliability concepts 1
1.2 Reliability assessment techniques 2
1.3 Continuous Markov process 2
Section 2 β Reliability assessment module in ETAP 3
2.1 Single Contingency 10
2.2 Double Contingency 11
Section 3 β Roy Billinton Test System (RBTS) 13
Section 4 β Evaluation of reliability indices 16
Section 5 β Reliability Analysis using RBTS model 19
Section 6 β Results and discussion 20
6.1 Reliability assessment without any DG connected 20
6.2 Reliability assessment with penetration of one DG 25
6.3 Reliability assessment with penetration of multiple DGs 28
6.4 Reliability assessment vs Distance 31
Section 7 β Conclusion 33
References 34
v
LIST OF FIGURES
Figure 1.1 β System subdivisionβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦...β¦2
Figure 1.2 β Two state modelβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦.β¦..3
Figure 1.3 β Stages of a componentβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦.β¦.3
Figure 2.1 β Radial distribution systemβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦4
Figure 2.2 β Reliability parameters for busesβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦5
Figure 2.3 β Data for cableβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦5
Figure 2.4 β Reliability parameter for Cableβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦5
Figure 2.5 β System Annual Outage Duration in (hour/year) and (hour)β¦β¦β¦β¦β¦β¦β¦6
Figure 2.6 β Parallel systemβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦.7
Figure 2.7 β Parallel system annual outage duration (hr)β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦8
Figure 2.8 β Parallel system annual outage duration (hr/yr)β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦8
Figure 2.9 β Single and double contingencyβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦9
Figure 2.10 β Single contingency, System annual outage duration (hr)β¦β¦β¦β¦.β¦β¦β¦11
Figure 2.11 β Double contingency, System annual outage duration (hr/yr)β¦β¦β¦..β¦β¦11
Figure 2.12 β System annual outage duration (hr)β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦.β¦.β¦β¦11
Figure 2.13 β System annual outage duration (hr/yr)β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦.β¦β¦β¦11
Figure 3.1 β Complete SLD of RBTSβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦13
Figure 3.2 β System dataβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦15
Figure 3.3 β System for RBTS Bus 2β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦..β¦β¦15
Figure 4.1 β Analytical technique for reliability calculationβ¦β¦β¦β¦β¦β¦β¦β¦β¦..β¦β¦18
Figure 5.1 β Modified bus 2 of RBTSβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦19
Figure 6.1 β Reliability assessment results for modified bus 2 of RBTS without DG
connectedβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦..β¦β¦20
Figure 6.2 β Summary (left) and output load point report (right)β¦β¦β¦β¦β¦β¦..β¦β¦β¦21
Figure 6.3 β Example elements contribution towards ECOST and EENSβ¦β¦..β¦β¦β¦β¦22
Figure 6.4 β Sensitivity analysis for ECOST at load point βCommercial 1ββ¦β¦..β¦β¦β¦23
vi
Figure 6.5 β Sensitivity analysis for EENS at load point βCommercial 1ββ¦β¦β¦β¦.β¦β¦24
Figure 6.6 β DG insertion at load point βG&I 4ββ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦.β¦β¦25
Figure 6.7 β RA after DG insertion at load point βG&I 4ββ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦..β¦β¦26
Figure 6.8 β Sensitivity analysis for EENS after DG insertion at load point
βCommercial 1ββ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦..β¦β¦β¦26
Figure 6.9 β Sensitivity analysis for ECOST after DG insertion at load point
βCommercial 1ββ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦..β¦β¦27
Figure 6.10 β Summary after insertion of DG at load point βG&I 4ββ¦β¦β¦β¦β¦β¦β¦β¦27
Figure 6.11 β Multiple DG penetration at load point βG&I 4ββ¦β¦β¦β¦β¦β¦β¦β¦β¦..β¦.28
Figure 6.12 β RA for multiple DG penetration at load point βG&I 4ββ¦β¦β¦β¦β¦β¦β¦β¦29
Figure 6.13 β Summary for multiple DG penetration at load point βG&I 4ββ¦β¦β¦.β¦β¦30
Figure 6.14 β Location of DG insertion at various load pointsβ¦β¦β¦β¦β¦β¦β¦β¦..β¦β¦31
vii
LIST OF TABLES
Table 3.1 β Peak load contributionβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦.14
Table 3.2 β Feeder lengthsβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦..β¦β¦14
Table 6.1 β Comparison of DG insertion in case of single DG and multiple DG
Insertionβ¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦.β¦.29
Table 6.2 β Comparison of reliability indices for DG insertion at various locationsβ¦β¦32
viii
ABSTRACT
RELIABILITY OF DISTRIBUTION SYSTEMS
USING MARKOV PROCESS AND ETAP
By
Kunal Raut
Master of Science in Electrical Engineering
Studies carried out by the US Department of Energy [10] states that out of the total
generating capacity 20% is derived from distributed generation. Power systems utilities
predict that in near future, the number of βDistributed Energy Generatorsβ installed will
increase due to its reliability, flexibility, efficiency, upgradability and diversity. Electricity
could not be stored readily and thus is generated and consumed instantaneously, thereby
making it mandatory to maintain a tradeoff between the generated and consumed power.
On the other hand, the ever increasing demand for electricity makes system planning and
operations an important task. This can be achieved and done precisely with the aid of
system reliability.
This project pinpoints assessment of a system designed by Roy Billinton [3]. The
intention is to examine the consequences of DEG on the network. The analysis being
carried out on HLIII and the improvement in system reliability is studied using various
indices. Additionally, system response in terms of overall reliability is observed and
ix
analyzed after penetration of single DG and multiple DG near the load point. Later, the
relation between system reliability and the distance of the installed DEG is analyzed.
Recollecting the importance of system reliability for distribution companies from
an investment point of view is also one of the objective. Studies and analysis are supported
and are verified using ETAP software [9].
1
SECTION 1: INTRODUCTION
Electrical power system being the most vital system is also the most complex
system designed by mankind. Since its invention, electrical power system has been
constantly developing and expanding to meet the increasing demands. The prime function
of such a system is to provide uninterrupted electricity to its consumers, and this has always
been the priority of the utility companies.
A grid comprises of generating stations, transmission line and distribution network.
Initially, reliability study was carried out on the generating and transmission level rather
than on distribution system since generating and transmission system outages are costly
and the latter being comparatively cheap and localized. However, recent studies have
shown that distribution system accounts for up to 80% - 85% of all the reliability problems.
Thus, reliability improvement at the distribution level is of utmost importance as it goes
hand in hand with the cost of electricity and consumer satisfaction. Failure in doing so can
lead to a series of problems which include system overloading, power outages and transient
behavior of the system.
This research work is aimed at assessment of reliability of the RBTS β 2 bus test
system [3] using the Reliability assessment tool of the Electrical Transient Analyzer
Program (ETAP) [9] and analytical techniques. This research will have 9 sections in total.
Section 1 gives a quick introduction, followed by network reliability in section 2. Section
3 explains the basics of reliability using Markov process and 2 state models, the reliability
assessment module of ETAP is being explained in the succeeding section, whereas the
reliability parameters and its calculation is presented in the subsequent section. Simulation
of a RBTS test model and its analysis for different scenario are explained in section 6 and
section 7 respectively. Finally, the results and conclusion are explained in section 8 and
section 9 respectively.
1.1 Reliability concepts
Reliability has a very broad definition, but a universally accepted definition would
be: βReliability is the probability of a device performing its purpose adequately for the
period of time intended under the operating conditions encountered.β [10]
Based on this on can say that reliability can be broken down into:
a) Probability
b) Performance
c) Time
d) Operating conditions
Probability is the input for reliability assessment and is a numerical value. The rest
being engineering parameters, does not follow probabilistic methods.
2
System reliability is governed by two parameters as shown in below figure :
Figure 1.1 β System sub-division
Adequacy is ability of the system to meet customer load demands continuously with
the help of facilities available within the system. Whereas, security is systemβs potential to
tolerate certain disruptions.
1.2 Reliability assessment techniques
No specific formula for reliability calculation exist, the approach used by engineers
to deduce reliability is either by understanding the problem or by making assumptions. The
guidelines followed by engineers to deduce reliability in a power system are as follows
a. Know how the system operates
b. Point out ways it could fail
c. Identify how the failure will affect the system
d. Perform reliability survey
Reliability can be estimated by analytical or simulation methods. Mathematical
models serve as a base for reliability calculations using analytical methods, where system
indices are calculated and compared. Simulation methods like Monte Carlo have a
relatively high computing time and simulate random nature of the system. A standard
procedure would be to divide and simplify the entire system into small components and
estimate the reliability of those components. Once the individual component reliability is
known the reliability of the entire network can be calculated after combining the
component reliability with the aid of available analytical techniques.
1.3 Continuous Markov process
In a continuous Markov process the probability of a component to be either in a failed
state or healthy state is constant for a fixed time interval. Components in power system
thereby can be represented by these two states. As seen in Figure 1.2, βState 0β indicates
healthy state and is operational, whereas βState 1β indicates a failed state and its inability
to perform the task. The change in state occurs with a rate of "π" (failure rate) and from
βState 1β to βState 0β with a rate of "π" (repair rate). Here the failure rate depends upon the
active and passive failure rate of the component.
Reliability
Adequacy Security
3
Figure 1.2 β Two state model
The stages of a component are described in Figure 1.3.
Figure 1.3 β Stages of a component
(Source:https://www.researchgate.net)
The addition of MTTD, MTTR and MTTF is MTBF. The equations below depict
the relations between the transition rates.
ππππΉ = 1/π
ππππ = 1/π
πππ΅πΉ = ππππ· + ππππ + πππ΅πΉ = 1/πππππ’ππππ¦
State 0
UP
State 1
DOWN
π = ππ΄ + ππ
π
4
SECTION 2 : RELIABILITY ASSESSMENT MODULE IN ETAP
The reliability assessment module in ETAP serves as a tool for engineers for
estimating the reliability of a system. Reliability can be calculated for radial as well as
looped systems. Calculating network reliability, its indices and ability to use single
contingency or double contingency method are some of the key features of this tool. This
tool also allows user to plot the energy (cost) indices for the entire system or specific
components graphically.
Consider a simple radial distribution system as mentioned below. The utility has a
short circuit rating of 100 MVAsc and both the buses are rated at 10kV. A 3C x 50 mm2
Copper cable with XLPE insulation, measuring 1 km in length connects Bus 1 and Bus 2.
Failure and repair rates for various components are shown below.
Figure 2.1 β Radial distribution system
Here the average failure rate is,
π = (ππ. ππ ππ’π ππ Γ πππππ’ππ πππ‘ππ ) + (ππ. ππ ππππππ Γ πππππ’ππ πππ‘π )
π = [3 (π1, π΅π’π 1 πππ π΅π’π 2) Γ 0.001 (πΉ π¦πβ )] + 0.05 (πΉ π¦πβ )
π = 0.053 πΉππππ’ππ/π¦πππ β¦...(1)
5
Figure 2.2 β Reliability parameters for buses Figure 2.3 β Data for cable
Also, the unavailability of the
system can be calculated from the
formula mentioned below,
π = (ππ. ππ ππ’π ππ Γ πππππ’ππ πππ‘π
Γ ππππ )
+ (ππ. ππ ππππππ
Γ πππππ’ππ πππ‘π
Γ ππππ )
π = [3 Γ 0.001 (πΉ π¦πβ ) Γ 2 (βπ)]
+ [1 Γ 0.05 (πΉ/π¦π)Γ 30 (βπ)]
π = 1.506 π»ππ’π π¦πππβ ...β¦(2)
Figure 2.4 β Reliability parameter for Cable
6
From eq. 1 and eq. 2, load side reliability is formulated and the same can be compared with
the result obtained in ETAP as depicted in figure 2.5
πΏπππ πππππ‘ ππππππππππ‘π¦ πππππ₯ =ππππ£πππππππππ‘π¦
π΄π£πππππ πΉππππ’ππ πππ‘π=
1.506 βπ/π¦π
0.053 π/π¦π
πΏπππ πππππ‘ πππππππππππ‘π¦ πππππ₯ = 28.42 βπ/πππππ’ππ
Figure 2.5 β System Annual Outage Duration in (hour/year) and (hour)
7
Now, consider a parallel structure as depicted in figure 2.6. Here the reliability of
the system is regulated by the two 10MVA transformers (T1 and T2) and the two lines
supplying power to the motors (Mtr1 and Mtr2). Data for various components in the system
is as follows:
Utility and buses:
Active failure rate (Ξ»a) = 0.001 failure/year
MTTR = 2 hours
MTTF = 1000 years
Switching time = 2 hours
Breakers:
Active failure rate (Ξ»a) = 0.003 failure/year
Passive failure rate (Ξ»p) = 0.002failure/year
MTTR = 30 hour
MTTF = 200 years
Switching time = 50 hours Figure 2.6 β Parallel structure
Transformers:
Active failure rate (Ξ»a) = 0.025 failure/year
MTTR = 200 hours
MTTF = 40 years
Switching time = 200 hours
Here, reliability indices at the main bus are to be calculated. As seen from figure
2.6, main bus would de-energize in one of the below mentioned cases
1. Breaker 1 fails actively or passively
2. Breaker 2 or breaker 3 fails actively
3. Utility grid fails
4. Main bus fails itself
Based on these cases the failure rate for the main bus can be calculated.
πππππ = (ππ + ππ)πΆπ΅1 + (ππ)πΆπ΅2 + (ππ)πΆπ΅3 + ππ1 + πππππ
= (0.003 + 0.002) + 0.003 + 0.003 + 0.001 + 0.001
πππππ = 0.013 πππππ’ππ π¦πππβ β¦...(3)
8
Similarly, the unavailability of the main bus can be formulated as,
πππππ = [ππππ πΆπ΅1 Γ (ππ + ππ)πΆπ΅1
] + [ππππ πΆπ΅2 Γ (ππ)πΆπ΅2]
+ [ππππ πΆπ΅3 Γ (ππ)πΆπ΅3] + [ππππ π1 Γ ππ1] + [ππππ ππππ Γ πππππ]
= [30 Γ (0.003 + 0.002)] + [30 Γ 0.003] + [30 Γ 0.003] + [2 Γ 0.001]
+ [2 Γ 0.001]
πππππ = 0.334 βππ’π π¦πππβ β¦...(4)
The time to replace the main bus can be calculated using equation 3 and equation 4,
π ππππ =πππππ
πππππ=
0.334 βππ’π π¦πππβ
0.013 πππππ’ππ π¦πππβ
π ππππ = 25.692 βππ’ππ
Figure 2.7 : System annual outage duration Figure 2.8 : System annual outage duration (hr/yr) (hr)
9
ETAP provides an added advantage of selecting the method of analysis, one can
choose either single contingency or double contingency. To understand this concept let us
consider a system with two parallel branches as shown in Figure 2.9. In case of single
contingency analysis, ETAP considers that only one of the two branches have failed
whereas in double contingency simultaneous failure of both the branches is considered
along with failure of either one of the branch.
Figure 2.9 β Single and double contingency
In the case of single contingency, failure of either transformer 1 or transformer 2 is
considered at a time. Whereas in case of double contingency simultaneous failure of
transformer 1 and transformer 2 is considered in addition.
The data for various components in the system are as follows:
Breakers (CB1 and CB9):
Active failure rate (Ξ»a) = 0.003 failure/year
Passive failure rate (Ξ»p) = 0.002failure/year
MTTR = 30 hour
MTTF = 200 years
Switching time = 50 hours
Buses (Bus 1 and Bus 2) and Utlity (U-1):
Active failure rate (Ξ»a) = 0.001 failure/year
MTTR = 2 hours
MTTF = 1000 years
10
Switching time = 2 hours
Transformers:
Active failure rate (Ξ»a) = 1 failure/year
MTTR = 200 hours
MTTF = 1 year
Switching time = 200 hours
For simplicity of analytical calculations, the failure rates of the breakers connecting the
transformers to the buses are considered to be zero.
2.1 Single contingency
ππ πππππ = ππ1 + (ππ + ππ)πΆπ΅1 + πππππ + (ππ)πΆπ΅2 + (ππ)πΆπ΅6
= 0.001 + (0.003 + 0.002) + 0.001 + 0.001 + 0.003
ππ πππππ = 0.011 πππππ’ππ π¦πππβ β¦...(5)
The unavailability of the main bus can be formulated as,
ππ πππππ = [ππππ π1 Γ ππ1] + [ππππ πΆπ΅1 Γ (ππ + ππ)πΆπ΅1
] + [ππππ ππππ Γ πππππ]
+ [ππππ πΆπ΅2 Γ (ππ)πΆπ΅2] + [ππππ πΆπ΅6 Γ (ππ)πΆπ΅6]
= [2 Γ 0.001] + [30 Γ (0.003 + 0.002)] + [2 Γ 0.001] + [2 Γ 0.001]
+ [30 Γ 0.003]
ππ πππππ = 0.246 βππ’π π¦πππβ β¦...(6)
The time to replace the main bus can be calculated using equation 3 and equation 4,
π π πππππ =ππ πππππ
ππ πππππ=
0.246 βππ’π π¦πππβ
0.011 πππππ’ππ π¦πππβ
π π πππππ = 22.36 βππ’ππ
11
Figure 2.10 β System annual outage duration Figure 2.11 β System annual outage duration
(hr) (hr/yr)
2.2 Double contingency
Figure 2.12 β System annual outage duration Figure 2.13 β System annual outage duration
(hr) (hr/yr)
12
In case of double contingency analysis, the indices at Bus 1 are the same whereas
the same are a lot higher at Bus 2. This is due to the consideration that both the transformers
(Tr 1 and Tr 2) fail at the same time. As mentioned earlier, for simplicity the failure rates
of both the transformers is considered 1 and Ξ» for the breakers connecting both the
transformers to the buses are assumed to be 0.
Failure rate at Bus 2:
ππππ’πππ =
π1π2(π1 + π2)8760
1 +π1π1 + π2π2
8760
=
1 Γ 1 Γ (200 + 200)8760
1 +(1 Γ 200) + (1 Γ 200)
8760
ππππ’πππ = 0.0437 πππππ’ππ π¦πππβ
The total failure rate (Ξ»total) would be,
ππ‘ππ‘ππ = ππ πππππ + ππππ’πππ
= 0.011 πππππ’ππ π¦πππβ + 0.0437 πππππ’ππ/π¦πππ
ππ‘ππ‘ππ = 0.0547 πππππ’ππ/π¦πππ
13
SECTION 3 : ROY BILLINTON TEST SYSTEM (RBTS)
A test system was presented to estimate the overall indices and predict system
reliability from a customer point of view. This test system, also called as RBTS, consists
of three level of hierarchy:
1. Level one, HLI β Reliability evaluation of generation system
2. Level two, HLII β Reliability evaluation of generation and transmission system
3. Level three, HLIII β Overall system reliability
Figure 3.1 β Complete SLD of RBTS [3]
14
This research work focuses on the HLIII and helps in assessing customer side
reliability. The primary system reliability indices at HLIII are βΞ»β, βrβ and annual
unavailability (U). HLIII reliability indices at the load are called as customer oriented
indices and are:
a) Average Service Availability Index (ASAI)
b) System Avg. Interruption Duration Index (SAIDI)
c) Average Service Unavailability Index (ASUI)
d) System Avg. Interruption Freq. Index (SAIFI)
e) Customer Avg. Interruption Duration Index (CAIDI)
As seen in Figure 3.1, the 6-bus test system has voltage levels of 230kV, 138kV,
33kV, 11kV and 220V. It consists of 11 generators, 9 transmission lines and five load
buses. This research is dedicated to the distribution system located at bus 2 which
represents a typical urban system with household loads, institutional loads, commercial
load and industrial load which adds up to a total of 1256 customers and has a peak load of
20MW. The contribution of various customers towards the peak load is as follows:
Sr. No. Customer Type Peak load (MW)
1 Residential 7.25
2 Industrial 3.50
3 Government/Institution 5.55
4 Commercial 3.70
Total 20 Table 3.1 β Peak load contribution
The 11kV feeders and laterals are considered to be cables and their lengths are
mentioned in Table 3.2, whereas the diagram for RBTS bus-2 and its network data is shown
in Fig. 3.3 and Fig. 3.2 respectively.
Sr. No. Length (km) Feeder numbers (as per Figure 3.3)
1 0.60 2, 6, 10, 14, 17, 21, 25, 28, 30, 34
2 0.75 1, 4, 7, 9, 12, 16, 19, 22, 24, 27, 29, 32, 35
3 0.80 3, 5, 8, 11, 13, 15, 18, 20, 23, 26, 31, 33, 36 Table 3.2 β Feeder lengths
The RBTS bus 2 system consists of 17 transformers in total which includes 2 x
16MVA 33kV/11kV HT transformers and 15 x 2MVA 11kV/220V LT transformers. The
system data in Figure 3.2 provides the user important data like the permanent and active
failure rates (Ξ»a and Ξ»p), repair time (r), switching time (s), outage rate during maintenance
(Ξ»ββ) and outage time during maintenance (rββ) for various components.
16
SECTION 4 : EVALUATION OF RELIABILITY INDICES
In a distribution system consisting of components, loads and customers the
reliability can be calculated using the parameters mentioned below. These reliability
indices help us determine the reliability of the entire system. As per IEEE standards any
interruption which is longer than 5 mins is termed as βsustained interruptionβ. The primary
system reliability indices are:
1. Failure rate @ βjβ (Ξ»j)
ππ(πππππ’ππ/π¦πππ) = β ππ,π(ππ£π. πππππ’ππ πππ‘π ππ πππππππ‘ π)
ππ.ππ πππππππ‘π (π)
2. Annual Outage Duration @ βjβ (Ui)
ππ(βπ π¦πππβ ) = β ππ,π(ππ£π. πππππ’ππ πππ‘π ππ πππππππ‘ π)
ππ.ππ πππππππ‘π (π)
Γ πππ(πππππ’ππ ππ’πππ‘πππ @ π )
3. Avg. Outage duration @ βjβ
ππ(βππ . ) =ππ(π΄πππ’ππ ππ’π‘πππ ππ’πππ‘πππ @ π)
ππ(π΄π£π. πππππ’ππ πππ‘π @ π)
Similarly, the sustained interruption indices:
1. SAIFI
ππ΄πΌπΉπΌ =πππ‘ππ ππ. ππ ππ’π π‘. πππ‘ππππ’ππ‘ππππ
πππ‘ππ ππ. ππ ππ’π π‘. π πππ£ππ
ππ΄πΌπΉπΌ (πππππ’ππ/ππ’π π‘ππππ. π¦πππ) =β ππ Γ ππ(ππ. ππ ππ’π π‘. @ β²πβ²)
β ππ
2. SAIDI
ππ΄πΌπ·πΌ =ππ’π ππ ππ’π π‘ππππ πππ‘ππππ’ππ‘ππππ ππ’πππ‘πππ
πππ‘ππ ππ. ππ ππ’π π‘πππππ π πππ£ππ
ππ΄πΌπ·πΌ (βππ’π/ππ’π π‘ππππ. π¦πππ) =β ππ Γ ππ(ππ. ππ ππ’π π‘. @ β²πβ²)
β ππ
17
3. CAIDI
πΆπ΄πΌπ·πΌ =ππ’π ππ ππ’π π‘. πππ‘ππππ’ππ‘ππππ ππ’πππ‘πππ
πππ‘ππ ππ. ππ ππ’π π‘. πππ‘ππππ’ππ‘ππππ
πΆπ΄πΌπ·πΌ (βπ/ππ’π π‘ππππ πππ‘ππππ’ππ‘πππ) =β ππ Γ ππ(ππ. ππ ππ’π π‘πππππ @ β²πβ²)
β ππ Γ ππ(ππ. ππ ππ’π π‘πππππ @ β²πβ²)
4. ASAI
π΄ππ΄πΌ =ππππ£πππ ππ£πππππππ πππ ππ’π π‘πππππ (ππ βππ . )
ππππ£πππ ππππππππ ππ¦ ππ’π π‘πππππ (ππ βππ . )
π΄ππ΄πΌ (ππ’) =β ππ Γ 8760 (ππ. ππ βππ . ππ π ππππππππ π¦πππ) β β ππππ
β ππ Γ 8760 (ππ. ππ βππ . ππ π ππππππππ π¦πππ)
5. ASUI
π΄πππΌ (ππ’) = 1 β π΄ππ΄πΌ
6. EENS
πΈπΈππ = β πΈπΈπππ
πΈπΈπππ(ππ. βππ’π/π¦πππ) = ππ(π·πππππ ππ‘ ππππ πππππ‘ β²πβ²) Γ ππ
18
Analytical technique for reliability calculation of power system uses the flowchart
depicted in Figure 4.1.
Figure 4.1 β Analytical technique for reliability calculation
Start
Get system and customer data
X=1
Consider failure for a component βxβ
Identify the affected load points
Calculate Ξ»lp, rlp and Ulp for that affected load point
More
components.?
Accumulate load point indices to evaluate Ξ», r and U
Report
End
X=X+1
19
SECTION 5 : RELIABILITY ANALYSIS USING RBTS MODEL
In this research, modified RBTS bus 2 system is taken into consideration and
reliability assessment is carried out by using the ETAP software. The system data for the
bus 2 is as per RBTS and the failure rates for various components, feeder length and loads
are as per data mentioned in section 3.
.
Figure 5.1 β Modified bus 2 of RBTS
Analysis of this model is done using four different scenarios and the results for each
of the case is tabulated and compared to show the diverse effect of DG and its distance on
the overall reliability of the system. The different scenarios considered in this research are
as follows:
1. Reliability assessment without any DG connected
2. Reliability assessment with penetration of one DG
3. Reliability assessment with penetration of multiple DGs
4. Reliability assessment vs Distance
20
SECTION 6 : RESULTS AND DISCUSSION
6.1 Case 1: Reliability assessment without any DG connected
Reliability analysis for the RBTS system without any DG connected in the system
was carried out utilizing the RA tool in ETAP and the output attained are:
Figure 6.1 β Reliability assessment results for modified bus 2 of RBTS without DG connected
The customer oriented indicia are analytically evaluated using network, load point
and bus. ETAP provides a summary of all the various customer oriented indices along with
the results for sensitivity analysis which includes EENS and ECOST. ETAP also provides
graphical display of the reliability results and helps the user to understand the contribution
of various components towards the overall system reliability. The report generated by
ETAP contains all of the aforementioned data along with load point output report and
sensitivity analysis.
21
Figure 6.2 β Summary (left) and output load point report (right)
ππ΄πΌπ·πΌ (βππ’π/ππ’π π‘ππππ. π¦πππ) =β ππ Γ ππ(ππ. ππ ππ’π π‘πππππ ππ‘ ππππ πππππ‘ β²πβ²)
β ππ
=
(7.64) + (9.67) + (6.99 Γ 210) + (10.15 Γ 210) + (10.33 Γ 200) + (12.17) +(12.33) + (14.15 Γ 10) + (7.66 Γ 10) + (7.17 Γ 200) + (9.68 Γ 200)
+(10.33 Γ 200) + (12.82) + (14.66) + (14.82 Γ 10)
1 + 1 + 210 + 210 + 200 + 1 + 1 + 10 + 10 + 200 + 200 + 200 + 1 + 1 + 10
=11536.99
1256
ππ΄πΌπ·πΌ (βππ’π/ππ’π π‘ππππ. π¦πππ) = 9.1855 βππ’π/ππ’π π‘ππππ. π¦πππ
Similarly,
ππ΄πΌπΉπΌ (πππππ’ππ/ππ’π π‘ππππ. π¦πππ) =β ππ Γ ππ(ππ. ππ ππ’π π‘πππππ ππ‘ ππππ πππππ‘ β²πβ²)
β ππ
=
(1.7285) + (2.1375) + (1.5985 Γ 210) + (2.2350 Γ 210) + (2.2720 Γ 200) +(2.6440) + (2.6765) + (3.0410 Γ 10) + (1.7345 Γ 10) + (1.6370 Γ 200) +(2.1435 Γ 200) + (2.2735 Γ 200) + (2.7740) + (3.1445) + (3.1770 Γ 10)
1 + 1 + 210 + 210 + 200 + 1 + 1 + 10 + 10 + 200 + 200 + 200 + 1 + 1 + 10
22
=2564.865
1256
ππ΄πΌπΉπΌ (πππππ’ππ/ππ’π π‘ππππ. π¦πππ) = 2.042 πππππ’ππ/ππ’π π‘ππππ. π¦πππ
Also,
πΆπ΄πΌπ·πΌ (βπ/ππ’π π‘ππππ πππ‘ππππ’ππ‘πππ) =β ππ Γ ππ(ππ. ππ ππ’π π‘. ππ‘ πππππ‘ β²πβ²)
β ππ Γ ππ(ππ. ππ ππ’π π‘. ππ‘ πππππ‘ β²πβ²)
=2564.865
2.042
πΆπ΄πΌπ·πΌ (βπ/ππ’π π‘ππππ πππ‘ππππ’ππ‘πππ) = 4.498 βπ/ππ’π π‘ππππ πππ‘ππππ’ππ‘πππ
Figure 6.3 β Example of elements contribution towards ECOST and EENS
For Average Service Availability Index (ASAI),
π΄ππ΄πΌ (ππ’) =β ππ Γ 8760 (ππ. ππ βππ . ππ π ππππππππ π¦πππ) β β ππππ
β ππ Γ 8760 (ππ. ππ βππ . ππ π ππππππππ π¦πππ)
=(1256 Γ 8760) β (11536.99)
(1256 Γ 8760)
23
π΄ππ΄πΌ (ππ’) = 0.9989 ππ’
Thus,
Average Service Unavailability Index, π΄πππΌ (ππ’) = 1 β π΄ππ΄πΌ
π΄πππΌ (ππ’) = 0.001048 ππ’
And for EENS,
πΈπΈππ = β πΈπΈπππ
= β
(7.64 Γ 0.961) + (9.67 Γ 1.105) + (6.99 Γ 0.455) + (10.15 Γ 0.455) +(10.33 Γ 0.382) + (12.17 Γ 0.481) + (12.33 Γ 0.481) + (14.15 Γ 0.386)
+(7.66 Γ 0.386) + (7.17 Γ 0.382) + (9.68 Γ 0.382) + (10.33 Γ 0.382)
+(12.82 Γ 0.481) + (14.66 Γ 0.481) + (14.82 Γ 0.386)
πΈπΈππ = 79.237 ππ. βππ’π/π¦πππ
Sensitivity analysis for ECOST and EENS was carried out near load point
βCommercial 1β which has a total of 10 customers and load of 0.454 MVA. As seen from
the graph the element that is closest to the load point contributes the maximum whereas
the elements which are farther away from the load point contribute minimum and the
same could be observed.
Figure 6.4 β Sensitivity analysis for ECOST at load point βCommercial 1β
25
6.2 Case 2: Reliability assessment with penetration of one DG
Consider a case where a Wind turbine is placed near load point βGovernment and
Institution 4β. The wind turbine is considered as a source of DG and its reliability data is
as follows:
Wind Turbine rating : 1 MW
Ξ» (F/yr) : 0.020
r (hours) : 50 hrs.
Switching time (hr) : 1 hr.
The reliability analysis results for this case is shown in figure 6.7 whereas the
sensitivity analysis for ECOST and EENS and the summary of customer oriented indices
and are shown in figure 6.8, 6.9 and 6.10 respectively.
Figure 6.6 β DG insertion at load point βG&I 4β
26
Figure 6.7 β RA after DG insertion at load point βG&I 4β
Figure 6.8 β Sensitivity analysis for EENS after DG insertion at load point βCommercial 1β
27
Figure 6.9 β Sensitivity analysis for ECOST after DG insertion at load point βCommercial 1β
Figure 6.10 β Summary after insertion of DG at load point βG&I 4β
When compared with the customer oriented indices obtained in case 1, the overall
reliability is improved drastically.
28
6.3 Case 3: Reliability assessment with penetration of multiple DGs
Figure 6.11 β Multiple DG penetration at load point βG&I 4β
As seen from figure 6.11, two DG sets are connected at load point βG&I 4β. The
rating and failure rates of both the DGs are the same and are similar to the one used in
case 2. Results from case 2 and case 3 are tabulated and compared in table 6.1 whereas
the reliability assessment results and the summary for the customer oriented indices are
shown in figure 6.12 and 6.13 respectively.
From table 6.1 injection of more than one DG units at one location had an adverse
effect on the system and its reliability by a measurable amount.
29
Table 6.1 β Comparison of DG insertion in case of single DG and multiple DG insertion
Figure 6.12 β RA for multiple DG penetration at load point βG&I 4β
Point of
injection
G&I 4
SAIFI
(f /
cust.
yr)
SAIDI
(hr/
cust.
yr)
CAIDI
(hr/
cust.
Intr.)
ASAI
(pu)
ASUI
(pu)
EENS
(MWH
/yr
ECOST
($/year)
Single DG 1.2008 6.9361 5.776 0.9992 0.00079 58.907 261792.9
Multiple
DG
1.2010 6.9449 5.783 0.9992 0.00079 59.774 268841.3
31
6.4 Case 4: Reliability vs Distance
After analyzing DG penetration on the system reliability, the effect of DG location
is evaluated. Six different load points marked as βA-Fβ are selected which include load
classes that include residential, industrial, government and institutional and commercial
loads. Customer oriented reliability indices are evaluated for these six points. The figure
shown below depicts the various location where the DG would be inserted.
Figure 6.14 β Location of DG insertion at various load points
The customer oriented reliability indices and the sensitivity indices are compared
with case 1 and are tabulated in table 6.2.
32
Table 6.2 β Comparison of reliability indices for DG insertion at various locations
As seen from the above table it can be concluded that the optimum location for DG
insertion would be near load point A. Also, one can conclude that the overall system
reliability is increased upon addition of a DG near the load points.
Case SAIFI
(f / cust.
yr)
SAIDI
(hr / cust.
yr)
CAIDI
(hr / cust.
Intr.)
ASAI
(pu)
ASUI
(pu)
EENS
(MWH/
yr)
ECOST
($/year)
W/O DG 2.0421 9.1853 4.498 0.9990 0.00105 79.306 335176.40
A 1.2008 6.9361 5.776 0.9992 0.00079 58.907 261792.90
B 1.2158 7.300 6.004 0.9992 0.00083 65.690 289815.70
C 1.3957 8.3441 5.978 0.9990 0.00095 72.106 312587.70
D 1.2101 6.9803 5.768 0.9992 0.00080 59.815 263797.40
E 1.2244 7.3488 6.002 0.9992 0.00084 65.992 291103.00
F 1.3944 7.8833 5.653 0.9991 0.00090 71.344 310861.90
33
SECTION 7 : CONCLUSION
Reliability analysis on modified bus 2 of the test system portrayed the effect of DG
insertion on overall system reliability. A total of four cases were considered and the system
behavior in each of these cases was observed and tabulated. The customer oriented indices
and the system reliability indices clearly indicate that system reliability is increased after
DG placement near to the load or far away from the feeder. We could also observe that
when multiple DG are placed near to the load, the system reliability decreases. This
concludes that system reliability is highly sensitive to the location of the DG.
Based on the results obtained, system designers and planners can identify the weak
points and take necessary actions to improve overall system reliability. Additionally, one
could also benchmark the system performance and compare it after system expansion. One
major advantage of this analysis is that supply interruption cost can be reduced drastically
by investing more on one of the load points during system planning.
34
REFERENCES
[1] Billinton Roy,, and R. Norman,. βReliability Evaluation of Engineering Systems:
Concepts and Techniquesβ, Second ed., Plenum Press, 1983.
[2] A Akhikpemelo,, N. Eyibo,, A. Adeyi,. βRELIABILITY ANALYSIS OF POWER
DISTRIBUTION NETWORKβ. Continental J. Engineering Sciences, 2016.
[3] R. Allan,, R. Billinton,, I. Sjarief,, L. Goel, and K. S., "A reliability test system for
educational purposes-basic distribution system data and results," in IEEE
Transactions on Power Systems, May 1991.
[4] R. Billinton and S. Jonnavithula, "A test system for teaching overall power system
reliability assessment," in IEEE Transactions on Power Systems, Nov 1996.
[5] Sanaullah, Ahmad, et al. βAnalyzing Distributed Generation Impact on the
Reliability of Electric Distribution Network.β, IJACSA 2016.
[6] βIEEE Recommended Practice for the Design of Reliable Industrial and
Commercial Power Systems," in IEEE, June 25 2007.
[7] βIEEE Guide for Electric Power Distribution Reliability Indices," in IEEE Std
1366-2012, May 31 2012.
[8] Sanaullah, Ahmad, et al. βImpact of Distributed Generation on the Reliability of
Local Distribution System.β IJACSA, 2017.
[9] βETAP | Electrical Power System Analysis Software | Power Management
Systemβ, http://www.etap.com/, accessed: 2018-03-14
[10] βDepartment of Energy.β, www.energy.gov/.