8/11/2019 Calibration Process IPC1
1/30
Systems and Technical Support Division
Canon
Standardized Calibration Process for theimagePRESS C1 Series with Server
Calibrations
-
8/11/2019 Calibration Process IPC1
2/30
Systems and Technical Support Division
Canon
Please read this disclosure before proceeding.
The printer should be stabilized before performing the followingadjustments. If the printer has not been operating for a period oftime, it is recommended that at least 50 sheets of 11x17 images beprinted before starting the adjustments. Determine if it is possiblefor your customer to manage jobs so that a non color cri tical jobcan be run before performing the following procedures. This shouldsuff iciently stabilize the printer and reduce any additional cost tothe Customer.
In the RIP calibration process, step 16-23, CUSA suggests using the21 sorted patches for the measurement page. Overall this should
provide satisfactory image quality. If your customer is still notsatisfied with the printer output using the 21 sorted, performing thecalibration procedure using the 34 sorted or either of therandomized measurement pages may provide more satisfactoryoutput.
-
8/11/2019 Calibration Process IPC1
3/30
Systems and Technical Support Division
Canon
Calibration Process
Steps Description
1-3 Stabilizing the printer prior to Calibration
4-9 Shading Correction
10-12 Preparing Printer for Auto Gradation
13-15 Auto Gradation Process
16-23 RIP Calibration
-
8/11/2019 Calibration Process IPC1
4/30
Systems and Technical Support Division
Canon
Calibration Process
Steps Description
1-3 Stabilizing the printer prior to Calibration
4-9 Shading Correction
10-12 Preparing Printer for Auto Gradation
13-15 Auto Gradation Process
16-23 RIP Calibration
-
8/11/2019 Calibration Process IPC1
5/30
Systems and Technical Support Division
Canon
1. Prepare a paper tray and place 11X17 paper in it. Paper type is not important in thisstep.
2. Enter Service Mode and go to Copier > Test.
A. Properly enter the tray in PG-PICK that was selected in Step 1 and select OK.
B. Select 2-Side and enter 1. Select OK.
C. Select PG-QTY, enter 25 on the key pad and Select OK.
A-B-
C-25
-
8/11/2019 Calibration Process IPC1
6/30
Systems and Technical Support Division
Canon
3. Select TYPE and from the key pad enter 16 and press OK and press the Start button. Let theprinter run the 50 prints to refresh the starter in the developer housings.
-
8/11/2019 Calibration Process IPC1
7/30
Systems and Technical Support Division
Canon
Calibration Process
Steps Description
1-3 Stabilizing the printer prior to Calibration
4-9 Shading Correction
10-12 Preparing Printer for Auto Gradation
13-15 Auto Gradation Process
16-23 RIP Calibration
-
8/11/2019 Calibration Process IPC1
8/30
Systems and Technical Support Division
Canon
4. From the Fiery Command WorkStation select Server then Manage Color.
-
8/11/2019 Calibration Process IPC1
9/30
Systems and Technical Support Division
Canon
5. Select Calibrator.
-
8/11/2019 Calibration Process IPC1
10/30
Systems and Technical Support Division
Canon
6. A. Select the Shading Correction tab.
B. Select Measurement tool, in this example we chose the EFI Spectrometer ES-1000.
C. Follow the procedure to Generate Measurement Page.( Procedure Performed at Printer UI)
D. Click Measure.
E. Message will appear.
and select OK.
-E
A
B
C
D
-
8/11/2019 Calibration Process IPC1
11/30
Systems and Technical Support Division
Canon
7. After clicking OK in previous step the dialogue box on the left will appear. If thePatches are scanned improperly the dialogue box on the right will appear. Whenscanning Test Page, scan from left to right, see picture below.
Be sure to place 20sheets of 28lbHammermill 98 or 100Brightness paper underyour test page before
scanning.
-
8/11/2019 Calibration Process IPC1
12/30
Systems and Technical Support Division
Canon
8. When the process is complete select OK, then Apply and Done. Complete Shading Correction at
the Printer UI.
-
8/11/2019 Calibration Process IPC1
13/30
Systems and Technical Support Division
Canon
9. The following screen will appear on the Printer UI. Select Store and Finish. TheShading Correction Process is complete.
-
8/11/2019 Calibration Process IPC1
14/30
Systems and Technical Support Division
Canon
Calibration Process
Steps Description
1-3 Stabilizing the printer prior to Calibration
4-9 Shading Correction
10-12 Preparing Printer for Auto Gradation
13-15 Auto Gradation Process
16-23 RIP Calibration
-
8/11/2019 Calibration Process IPC1
15/30
Systems and Technical Support Division
Canon
10. Select Additional Functions>Device Management Settings. Then select AutoGradation Adjustment.
-
8/11/2019 Calibration Process IPC1
16/30
Systems and Technical Support Division
Canon
11. Select Auto Gradation Adjust Method.
-
8/11/2019 Calibration Process IPC1
17/30
Systems and Technical Support Division
Canon
12. Select Printer Only.
-
8/11/2019 Calibration Process IPC1
18/30
Systems and Technical Support Division
Canon
Calibration Process
Steps Description
1-3 Stabilizing the printer prior to Calibration
4-9 Shading Correction
10-12 Preparing Printer for Auto Gradation
13-15 Auto Gradation Process
16-23 RIP Calibration
-
8/11/2019 Calibration Process IPC1
19/30
Systems and Technical Support Division
Canon
13. Set up a paper tray with Hammermill 28 lb and 98 or 100 Brightness. In AdditionalSettings go to Adjustment / Cleaning and select Auto Gradation Adjustment.
-
8/11/2019 Calibration Process IPC1
20/30
Systems and Technical Support Division
Canon
14. Select Full Adjust and follow the process.
-
8/11/2019 Calibration Process IPC1
21/30
Systems and Technical Support Division
Canon
15. Select the Tray loaded with 11x17 28 lb Hammermill (98 or 100)
Brightness then select OK. Let the Full Adjust run to completion.
-
8/11/2019 Calibration Process IPC1
22/30
Systems and Technical Support Division
Canon
Calibration Process
Steps Description
1-3 Stabilizing the printer prior to Calibration
4-9 Shading Correction
10-12 Preparing Printer for Auto Gradation
13-15 Auto Gradation Process
16-23 RIP Calibration
-
8/11/2019 Calibration Process IPC1
23/30
Systems and Technical Support Division
Canon
16. From the Fiery Command WorkStation select Server then Manage Color.
-
8/11/2019 Calibration Process IPC1
24/30
Systems and Technical Support Division
Canon
17. Select Calibrator.
-
8/11/2019 Calibration Process IPC1
25/30
Systems and Technical Support Division
Canon
18. A. Select Calibration.B. Select Expert.
C. Choose the type of Spectrometer that is being used. In this example we are
using the EFI Spectrometer ES-1000. Connect the device, the message will
appear when the connection is made.
D. Select Print.
B
D
A
C
-
8/11/2019 Calibration Process IPC1
26/30
Systems and Technical Support Division
Canon
19. For this demonstration we are using the 21 Sorted Patches Measurement Page(please see note) . This will generate a Measurement Page. Select 2 copies. Then SelectPrint.
Note: The 21Sorted Patches
Measurement pagegenerally providessatisfactory coloroutput. This may notbe acceptable to allCustomers.
Therefore if aCustomer isconcerned aboutcolor output it isadvisable to performcalibration choosinganotherMeasurement pageto determine if theoutput satisfies theCustomers
requirements.
-
8/11/2019 Calibration Process IPC1
27/30
Systems and Technical Support Division
Canon
20. Use the second test print from step 19. Slide the Spectrometer, from left toright, over the color gradation strips in the order shown on the screen shot on theleft.
Using the second test print from step 19, placeHammermill 28 lb (98 or 100) Brightness 11 X 17paper under the pattern to ensure a pure whitebackground when scanning.
Using the second print ensuresthat any residual image ordefects are eliminated.
-
8/11/2019 Calibration Process IPC1
28/30
Systems and Technical Support Division
Canon
21. If the Spectrometer is unable to read the correct number of patches on thecolor gradation strip the following red screen will appear. Just follow thedirections on the red screen to proceed.
-
8/11/2019 Calibration Process IPC1
29/30
Systems and Technical Support Division
Canon
22. Once successful, all of the colored rectangles will have check marks and the screenwill declare The measurement process was successful. Select OK.
-
8/11/2019 Calibration Process IPC1
30/30
Systems and Technical Support Division
Canon
23. Click Ok, then Apply and finally select Done. The Calibration Process is nowcompleted.