Calculation of Screw Conveyors 07-QFPC1
Transcript of Calculation of Screw Conveyors 07-QFPC1
-
7/30/2019 Calculation of Screw Conveyors 07-QFPC1
1/1
ITEM DESCRIPTION
Length
(m)
Future
length(m)
INCLINA
TION
Specific
Gravity
capacity
(ton/h)
Spiral Screw
Diameter(m)
Pitch
(m)
D-41 SC Nr.1 under Tricanter 18.10 18.10 3 0.75 54 0.60 0.45
D-42 SC Nr. 2 outgoing to Drying area 9.00 9.00 15 0.75 54 0.60 0.45
G-01 SC Nr. 3 to homogenizer Nr. 1 13.70 13.70 22 0.75 54 0.60 0.45
G-04 SC Nr. 4 after homogenizer Nr. 1 15.40 15.40 23 0.75 54 0.60 0.45
G-06 SC Nr. 5 to dryer Nr. 1 4.60 9.60 0 0.75 54 0.60 0.45
G-09 SC Nr. 6 from dryer Nr. 1 6.75 6.75 16 0.70 24 0.50 0.35
G-10 SC Nr. 7 from cyclones Nr. 1 6.00 10.45 14 0.70 10 0.30 0.25
G-11 SC Nr. 8 reciving stick water concentrate 25.20 25.20 11 0.75 45 0.50 0.35
G-14 SC. Nr 9 to dryer Nr. 2 29.73 29.73 11 0.75 45 0.50 0.35
G-15 SC Nr 10 horizontal feed to dryer Nr. 2 6.00 10.50 0 0.75 45 0.50 0.35
G-18 SC Nr. 11 discharge of dryer Nr. 2 6.96 10.60 0 0.70 19 0.50 0.35G-19 SC Nr. 12 discharge of cyclones Nr. 2 6.00 10.73 0 0.70 8 0.30 0.25
G-20 SC Nr. 13 to SC Nr 11 7.03 7.03 4 0.70 8 0.30 0.25
G-21 VERTICAL Screw conveyor Nr. 1 8.50 8.50 90 0.70 26
G-22 SC Nr. 15 to cooling area 23.50 23.50 0 0.70 26 0.50 0.35
K-01 FREE (eliminated)
K-09 FREE (eliminated)
K-11 FREE (eliminated)
K-12 FREE (eliminated)
K-13 SC Nr. 20 to feed air chiller 5.00 5.00 0 0.70 26 0.50 0.35
K-34 SC Nr. 21 discharge of air chiller 4.25 4.25 0 0.70 26 0.50 0.35
K-36 SC Nr. 22 to grinding system 26.35 26.35 18 0.70 26 0.50 0.35
L-02 SC Nr. 23 to Antioxidant mixer 15.50 15.50 19 0.70 26 0.50 0.35
L-04 SC Nr. 24 to bagging machines 18.90 18.90 22 0.70 26 0.50 0.35
L-07 SC Nr. 25 over bagging machines 6.80 6.80 0 0.70 26 0.50 0.35
NOTE:
Gear motors for Screw conveyors highligth in yellow, are already at the factory
Screw conveyors highlight in green, are already at the factory and will need only some modification
and shall not be quoted.
* : Because these motors are available in the factory
Central pipe is the pipe which spiral screws are welded to it (outer diameter and thickness is given in the table)
Shaft diameter is the diameter at end of shaft in connection to the electromotor (outer diameter is given in the table)
The required screws are: G09-G11-G14-G22-K34-K36-L02-L04
Relation of Screw Conveyors