Calculating Total Power Requirements Transcript

download Calculating Total Power Requirements Transcript

of 22

description

df

Transcript of Calculating Total Power Requirements Transcript

  • Calculating Total Power Requirements P a g e | 1

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Calculating Total Power Requirements

    Transcript

    Slide 1

    Welcome to the Data Center University course on Calculating Total Power Requirements.

    Slide 2: Welcome

    For best viewing results, we recommend that you maximize your browser window now. The screen controls

    allow you to navigate through the eLearning experience. Using your browser controls may disrupt the

    normal play of the course. Click the attachments link to download supplemental information for this course.

    Click the Notes tab to read a transcript of the narration.

    .

    Slide 3: Learning Objectives

    At the completion of this course, you will be able to:

    Calculate total power requirements for a data center.

    Understand the components of the data centers electrical capacity calculation:

    Critical and non-critical loads

    Electrical Service via the utility

    Generator Standby Power Systems

    Recognize the benefits to right sizing your power needs.

    Discuss the power evolution in the data center as well as the impact of multi-core processor

    technology and new dynamic loads.

    Slide 4: Introduction

    An essential part of data center planning and design is to align the power requirements of the IT equipment

    with the capacity of the supporting infrastructure.

  • Calculating Total Power Requirements P a g e | 2

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Over the years, the architecture of data center physical infrastructure which includes cooling, power,

    security, fire suppression, racks and cabling, has evolved from fixed, hard-wired, centralized components to

    mobile, modular components that employ standardized technologies.

    These innovations simplify the process of calculating power needs and allow for a much higher degree of

    flexibility in data center design. With the adoption of scalable pay as you grow UPS architectures, its

    becoming easier and less costly to install and grow these back-up systems.

    Slide 5: Introduction

    Despite these new technology innovations, data center designers still need an organized methodology for

    calculating future electrical needs of the data center or server room.

    Confronted with the challenge of determining both current and future power requirements, data center

    managers often over size their power requirements by as much as 70%.

    This leads to both the drastic under utilization of the infrastructure and the commitment of financial

    resources to fund unrealized investments. Accurately determining power requirements is one of the most

    important pieces of the overall data center project process.

    This course will provide you with the working knowledge needed to determine current, and future, total

    power requirements for your data center.

    Lets begin by identifying availability requirements.

    Slide 6: Identifying Availability Requirements

    Successful design initiatives begin with a needs assessment that includes the identification of availability

    requirements for the data center.

  • Calculating Total Power Requirements P a g e | 3

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    This assessment essentially establishes the availability needs of the business applications being processed

    by IT equipment.

    Some popular availability configurations, from a power and cooling perspective, include N, N+1, and 2N.

    Slide 7: Identifying Availability Requirements

    Its important to remember that the redundancy architecture deployed will impact the amount of power

    consumed in the data center.

    No matter what the actual physical infrastructure system design configuration is, the core issue will be to

    provide sufficient power to the critical load while keeping that critical load cool enough to operate without

    experiencing downtime. It is important to address this carefully, because underestimating the required

    capacity may result in future power disruptions. Over estimation can lead to excessive upfront installation

    costs and higher ongoing maintenance expenses.

    Once availability requirements have been identified, the next phase of the design process includes the

    identification of load components and their power requirements.

    Slide 8: Determining Load Requirements

    Determining the load requirements is critical because most data centers are part of a larger building.

    Data centers and network rooms draw a total load, which is the sum of the power consumed by the installed

    IT and physical infrastructure equipment.

    Before we explore each of the components which contribute to the total load requirements, lets establish

    our data center assumptions.

  • Calculating Total Power Requirements P a g e | 4

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Slide 9: Data Center Assumptions

    This pie chart illustrates a breakdown of how the electrical capacity is divided among the various loads in a

    data center.

    For purposes of this course, our breakdown assumes a 50 square foot, (4.64 square meters) data center

    with an initial steady state critical load of 50kW, plus a future steady state load of 50kW. The cooling system

    is assumed to be 50% direct expansion (DX) and 50% chilled water. The utility voltage is 480 volts AC.

    Now lets use this information to determine the load components for the data center.

    Slide 10: Critical Load Requirements

    Regardless of whether the data center consists of a single rack environment or a full scale data center, the

    first step in calculating total power requirements is to determine the size of the critical load that must be

    served and protected.

    The critical load includes all of the IT hardware components that make up the IT business architecture:

    servers, routers, computers, storage devices, telecommunications equipment, etc., as well as the security

    systems, fire and monitoring systems that protect them.

  • Calculating Total Power Requirements P a g e | 5

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Slide 11: Critical Load Requirements

    This process begins by compiling a list of all such devices, with their nameplate power rating, their voltage

    requirements, and whether they are single phase or three phase devices.

    It is important to note that the nameplate power requirements are the worst-case power consumption

    numbers required by Underwriters Laboratory (UL) and in almost all cases, the nameplate power

    requirements are well above the expected operating power level.

    Slide 12: Critical Load Requirements

    In fact, studies conducted by reputable consulting engineering firms and power supply manufacturers

    indicate that the nameplate rating of most IT devices is well in excess of the actual running load by a factor

    of at least 33%.

    The U.S. National Electrical Code (NEC) and similar worldwide regulatory bodies also recognize this fact

    and allow electrical system planners to add up nameplate data for anticipated loads and multiply by a

    diversity factor, anticipating that not all devices are running at full load 100% of the time.

    Therefore, the nameplate information should be adjusted to reflect the true anticipated load.

    Lets take a moment and practice manually calculating load requirements.

  • Calculating Total Power Requirements P a g e | 6

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Slide 13: Calculating Critical Loads

    We can use this table as a simple example of how to string together a workable calculation worksheet.

    For the purposes of this example, we are making the assumption that one rack of equipment will represent

    the entire critical load component in our imaginary data center. In reality, a typical 5,000 square foot (465

    square meter) data center could consist of 100 to 200 of these racks with various types of servers and other

    installed components.

  • Calculating Total Power Requirements P a g e | 7

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    In this example, Server #1, the first component in our rack, does have a nameplate that reveals a rating of

    300 watts.

    For simplicitys sake all of our component power readings should be converted to Kilowatts which is the

    easiest measurement to calculate power requirements. 1 Kilowatt is equivalent to 1000 Watts. Therefore,

    we have converted our 300 watt nameplate rating for Server #1 to .3 kilowatts.

  • Calculating Total Power Requirements P a g e | 8

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Slide 14: Calculating Critical Loads

    For Disk Array #1, the second component in our rack, we have a nameplate rating of 500 Watts. Again, we

    convert to Kilowatts and our conversion comes out to .5 kW.

    Both Server #2 and Disk Array #2 are a bit more problematic because, in our example, neither has a visible

    nameplate rating. Although this is unusual, it can happen. However, we can use a formula that will allow us

    to calculate a kW rating for these two devices.

    If the wattage is not listed on the device, it can be determined by multiplying the incoming current in amps

    by the voltage of the device, which is typically 120 or 208V in North America and 220V outside of North

    America, to get the VA or volt-amps.

    Slide 15: Calculating Critical Loads

    If you dont know the voltage information off hand, you will need to contact your electrician or facilities

    manager. If you dont have power consumption of the individual component in amps, consult either the

    product manual or the vendors website. Then, multiply the anticipated VA number by 0.67 to estimate the

  • Calculating Total Power Requirements P a g e | 9

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    actual power, in watts, that the critical load will represent. Finally, divide the number by 1000 to establish

    the Kilowatt (kW) load level of the anticipated critical load.

    In our example, we have determined the voltage for Server #2 to be 120 V and the amps coming in to be at

    5 amps. Therefore, 120V x 5 amps = 600 VA. To covert to watts we need to multiple the VA by .67. That

    gives us a total of approximately 400 Watts. We convert this figure to .4 Kilowatts.

    We follow the same procedure for determining our kilowatt rating for Disk Array #2. (310 watts / 1000 =.31

    kW)

    The sum of our four components is equal to 1.51 kW.

    Slide 16: Calculating Critical Loads

    This figure will represent the first line item in our worksheet which is the critical load (the power

    requirements of all our servers, storage, network equipment etc).

  • Calculating Total Power Requirements P a g e | 10

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Slide 17: Calculating Critical Loads

    Its critical to consider the future load requirements because data center loads are not static. Once built or

    established, the IT equipment will be under an almost constant state of change during the lifetime of the

    data center.

    IT refreshes will, at a minimum, have a 3 year cycle where new, more powerful and efficient devices will be

    installed. These new devices will replace the original devices that are the current basis for calculating the

    bulk of the power requirements.

    Slide 18: Calculating Critical Loads

    A realistic assessment of the scope and timing of future changes and upgrades should be developed by the

    IT organization to allow proper planning for the initial determination of power requirements.

    The downstream elements of the electrical power and distribution system can be scaled, or adjusted to

    known loads and future loading, but the utility input service supplying the NCPI (Network Critical Physical

    Infrastructure) components either has to be sufficiently sized to carry the known load at start-up and future

    loads, or a provision has to be made for installation of additional capacity without incurring excessive

    downtime that would adversely affect the availability expected by the IT end user.

    Once an estimate is made for the amount of future loading, it is added to the base loading information, to

    establish the electrical critical load number in kW.

  • Calculating Total Power Requirements P a g e | 11

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Slide 19: Calculating Peak Power Draw

    Our worksheet will also assist in calculating future loads. For purposes of this exercise, well list our best

    estimate of what the additional future critical load will be over the next three years.

    Lets assume that our server base in the data center will grow by 20% over the next 3 years to reflect an

    anticipated growth in business.

    (Although over the last five years, servers have consumed increasingly large amounts of power, this trend

    may be reversed in the near future as multi-core processors begin to replace the traditional CMOS chip. We

    will discuss more about multi-core processors later on in this course. For the purposes of this example, well

    assume that the power consumption will be the same.)

    Since our projected growth will be 20%, we will add 20% to our current critical load numbers to establish our

    future load.

    This equation illustrates the additional power requirement increase of our future load and shows how we

    have taken our existing critical load of 1.51 kW and multiplied by 20% to determine how much in extra kW

    we have to account for in our future critical load.

    Slide 20: Calculating Future Critical Loads

    In order to ensure that our electrical system is capable of supporting peak power draws (due to some

    variations that might exist in the critical load) we will also add the critical load and future load kW amounts

  • Calculating Total Power Requirements P a g e | 12

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    and multiply by a factor of 1.05. This will give us a total of 1.90 kW (1.51 + .3 x 1.05). This would be the

    peak power draw. In order to calculate the net amount of extra capacity needed to address this peak power

    draw consideration, we simply take this peak power draw number (1.90) and subtract the sum of the existing

    load. In this case, 1.90 -1.81 results in an extra .09 kW of power required.

    Slide 21: UPS Load Requirements

    Although the UPS will support the critical loads in the event of an outage or power anomaly, the UPS

    equipment itself will also consume a portion of the available power. While UPS models will vary in terms of

    their efficiency and some UPS architectures are less efficient at lower load levels than others, for purposes

    of this particular course, lets assume a UPS efficiency rating of 88%.

    UPS battery charging or external battery banks are a significant but intermittent power consumer. Under

    normal operation with a charged battery the battery charging load is negligible. However, when a battery

    has been partially or completely discharged the battery charging power can be on the order of 20% of the

    rated UPS load.

    Now lets take this information and calculate UPS loads.

    Slide 22: Calculating UPS Loads

    To derive the UPS load you need to know the existing load, future load and the inefficiency factor for the

    UPS & UPS battery charging.

    For purposes of this example, we assume the UPS inefficiency rating to be 12%, and the UPS battery

    charging factor to be 20%. Adding these 2 together will result in an inefficiency factor of 32%.

    Now, take the Existing Load of 1.51 kW and add it to the Future Load of .3 kW and multiply it by the UPS &

    battery inefficiency of .32. This will result in the UPS Load of .58 kW (for this example).

    (Image on next page)

  • Calculating Total Power Requirements P a g e | 13

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Now that weve calculated the UPS load, lets move on to lighting loads.

    Slide 23: Lighting Load Requirements

    Lighting loads account for all the lighting in the data center portion of the building. To perform this

    calculation, you will need to know:

    The square footage of the data center: in this example of an imaginary one rack data center, we are

    assuming the space to be 50 square feet (4.64 sq meters). A simple formula for average lighting

    consumption is 2 watts per square foot or 21.5 watts per square meter. Again, for the purpose of producing

    consistent numbers, we are converting watts to kilowatts. Therefore, 2 watts will be converted into .002

    kilowatts, or if calculating in meters, 21.5 watts will be converted to .0215 kilowatts.

    So, to calculate the lighting load:

    Take the square footage and multiply by the average consumption to get the Total Lighting Load, in this

    case: 50 x .002 = .1 kW or 4.64 x .0215 =.1kW for calculation in square meters

    Cooling will comprise the largest draw on the data center requirements, so lets estimate that next.

  • Calculating Total Power Requirements P a g e | 14

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Slide 24: Cooling Load Requirements

    All electrical equipment produces heat, which must be removed to prevent the equipment temperature from

    rising to an unacceptable level.

    Most IT equipment and other equipment found in a data center or network room is air cooled.

    As we learned previously, a significant portion of the power consumption in the data center is controlled by

    the cooling load. While this particular course does not significantly address the specifics of calculating

    cooling requirements, it is important to note that the size of a cooling system will have a direct impact on the

    data center load requirements.

    (For more information on calculating total cooling requirements, see the DCU course Calculating Total

    Cooling Requirements)

    Slide 25: Cooling Load Requirements

    Cooling systems vary widely in efficiency but can be broken down into chilled water systems and direct

    expansion systems.

    Chilled water systems are somewhat more efficient, and a general guide for power consumption is 70% of

    the total peak load being supported.

    Direct expansion systems require about 100% of the total peak load being supported.

    (Note that cooling loads have start-up peak loads that exceed the steady state values. We will account for

    these in this calculation.)

    Every kW of power must be compensated for with an equal amount in kW of cooling so that the heat

    generated by power consuming equipment can be removed, and a consistent temperature is maintained in

    the data center.

  • Calculating Total Power Requirements P a g e | 15

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Slide 26: Calculating Cooling Loads

    This chart illustrates the power requirements for cooling. The power load needs to be supported by an equal

    amount of cooling load, so take the total sum of all electrical loads that were calculated previously

    throughout this course; (existing critical load, future critical load, peak power draw, UPS/battery and lighting).

    This number is 2.58 kW.

    Lets assume that half of the installed air cooling equipment consists of chilled water system and the other

    half is a direct expansion architecture. So, dividing 2.58 in half give us 1.29 kWs for each of the two air

    cooling architectures.

    Finally, you will need to know the Cooling Efficiency Factor for these cooling architectures. DX is multiplied

    by 1 which results in a factor of 1.29 and chilled water is multiplied by .7, resulting in a factor of .90. By

    adding the DX load to the chilled water load, we can derive the total cooling load of 2.19 kW.

    Slide 27: Total Power Requirements Summary Calculation

    Now the total power requirements for the data center has been calculated. This chart is a summary of the 6

    steps we have taken to arrive at our total power requirements sample number.

    (Image on next page)

  • Calculating Total Power Requirements P a g e | 16

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Slide 28: Finalizing Electrical Capacity Computation

    Once the total electrical capacity (current, future, UPS, lighting and cooling) is estimated in Kilowatts, two

    critical determinations can be made: the first is an estimate of the electrical service, or utility power needed

    to supply the data center, and the second is the size of any standby power generator capacity that may be

    needed to achieve the desired availability.

    Slide 29: Finalizing Electrical Capacity Computation

    Although operators will look at the steady-state power consumption of the loads within a data center when

    determining electrical costs, designers should avoid sizing the power sources (Electrical Service and the

    Generator) that power the data center to the steady state values.

    (Image on next page)

  • Calculating Total Power Requirements P a g e | 17

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    These sources must be sized to the peak power consumption of the loads, plus any de-rating or oversizing

    margins required by code or standard engineering practice.

    Using the same percentage breakdown of the data center electrical requirements as discussed previously,

    this illustration emphasizes the important distinction between peak power and steady state power by

    comparing the electrical service requirements for both. (In practice, this difference between peak and steady

    state requirement causes the electrical service and generator sizing to be substantially larger than might be

    expected.)

    Observe that the electrical service required at peak is almost 4 times the steady state critical load value.

    (It also must be noted that this is only an estimate, and that the final determination of the service size is

    highly dependent on accurate site specific information.)

  • Calculating Total Power Requirements P a g e | 18

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Slide 30: Calculating Electrical Service

    The electrical service, (the power coming in from the utility) can be calculated as follows:

    Take the total electrical capacity required in Kilowatts (4.77) as well as the requirements of the National

    Electrical Code and similar regulatory bodies,(1.25) and multiply to get the estimate for the total utility (5.96

    kW).

    Next, determine the three phase AC voltage of the service entrance to be supplied by the utility company.

    Typically this is 480 Volts AC in the United States and 230 Volts AC in most other parts of the world.

    Use the following formula to determine the electrical service size to supply the data center, in Amps:

    Amps = (kW x 1000) / (Volts x 1.73)

    To use our example, take the Total Adjusted Power Requirement (5.96) and multiply it by 1000 to get 5960.

    Then take the Data Center AC voltage (480) and multiply it by 1.73 to get 830.4

    Now, all you have to do is take 5960 and divide it by 830.4 to get 7.18 amps.

    (This provides an estimate of the electrical service capacity required to support the critical load, cooling, and

    the building functions for a data center. It is strongly recommended that the services of a qualified

    professional consulting engineer be retained to verify the initial estimate and develop the final data center

    electrical supply design.)

    Slide 31: Generator Standby Power Systems

    Once the size of the electrical service has been determined, consideration can be given to sizing an

    appropriate standby power generator, which will provide power in the event of a utility failure and maintain

    the availability of the data center.

  • Calculating Total Power Requirements P a g e | 19

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    A typical generator installation is illustrated here.

    It is important to identify that the data center can be just one of many loads on the system, so this diagram

    can be interpreted as a subset of a much larger electrical system.

    Air conditioning loads, for example, require high starting currents and can impose harmonic currents on a

    generator that may impact its ability to supply the power needed. The UPS itself may contribute to this

    problem if it does not operate at a high input power factor, and may cause generator failure.

    It is sufficient to note that the UPS must be chosen carefully to achieve end-to-end reliability. A UPS system

    that exhibits poor efficiency characteristics under low load conditions is to be avoided.

  • Calculating Total Power Requirements P a g e | 20

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Certain UPS topologies, such as the delta conversion, are better suited for generator supplied systems.

    They can produce less harmonic distortion and manage various load levels more efficiently.

    When selecting a UPS, the choice between a typical double conversion UPS and a Delta Conversion UPS

    can influence the required generator size greatly, frequently by a factor of 3 (meaning: the generator would

    have to be 1.75 to 3 times larger for a typical double conversion UPS than a Delta Conversion UPS).

    When selecting a generator, base the choice on the kW rating of the generator, but be aware that

    generators are designed to operate loads at a lower power factor than 1.0, typically 0.8. This means that the

    current and voltage will be slightly out of phase and that the generator must withstand that difference. A

    1000 kW generator, designed to operate loads having a power factor of 0.8 will be rated at 1200 kVA.

    It is important not to confuse the kVA rating with the true power capacity of the generator, which is always in

    kW.

    Slide 32: Calculating Estimated Generator Size

    Now lets determine the generator size for the data center.

    To calculate the correct generator size, you will first need:

    The number of kilowatts of the existing power load requiring generator back-up. This is made up of

    the critical load, plus the future load, plus the peak power draw, plus the UPS and battery plus the

    light load. In our example, the number equates to 2.58 kW.

    Next, you need to assess the status of the UPS. For this example the UPS is assumed to be a

    fully power factor corrected UPS, so the existing load of 2.58 kW will be multiplied by 1.3, to result

    in 3.35 kW.

    (If your UPS consists of a traditional double conversion UPS with input from harmonic filters, the existing

    load of 2.58 kW will be multiplied by 3.0 which calculate to 7.74 kW.)

  • Calculating Total Power Requirements P a g e | 21

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Then, you need the number of kilowatts from the cooling load requiring generator back-up. This

    was figured previously, when we calculated the cooling load. In this particular case, we will be

    using the number 2.19 kW and multiplying it by a factor of 1.5 to get 3.28 kW.

    Finally, add the 3.35 and 3.28 to result in 6.63 kW for the estimated generator size.

    Slide 33: Planning for Future Changes

    Now that we have reviewed all the elements involved in data center power capacity planning, lets look

    ahead. New technologies will be introduced that will impact our power and cooling load calculations in

    different ways.

    Slide 34: Planning for Future Changes

    The basic building block of computer architecture has, for many years, been the CMOS chip. This chip,

    which is commonly found in todays servers, has dominated the desktop computer and server market since

    the early 1970s.

    Over the last three decades, the chip manufacturers have continually improved the CMOS chip, but are now

    quickly reaching the theoretical limits of the design. Any further enhancements to the

    CMOS chip are difficult to justify financially, because the cost of additional engineering is high and the

    increases in horsepower and throughput are negligible.

    Slide 35: Planning for Future Changes

    This illustration depicts the evolution of the CMOS chip and demonstrates the architectural wall that has

    been encountered.

    Now, chip manufacturers are introducing new multi-core processor chips. These new chips consume power

    in a different manner than the traditional CMOS chip. While CMOS generally consumed power at a steady

    rate, multi-core processors power consumption will go up and down depending upon the level of processing

    required.

  • Calculating Total Power Requirements P a g e | 22

    2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.

    Slide 36: Planning for Future Changes

    When power varies with time, many new challenges occur for the design and management of data centers

    and network rooms.

    Fluctuations in power consumption can lead to unplanned and undesirable consequences in the data center

    and network environment; including tripped circuit breakers, overheating, and loss of redundancy in

    redundant power systems.

    Because of this multi-core processor dynamic loading feature, power and cooling planning and monitoring

    methodologies in the data center will have to be redefined to manage these new multi-core environments.

    Slide 37: Summary

    To summarize, lets review some of the information that we have covered throughout the course.

    Assessing the electrical power required to support the critical loads within the data center is an essential

    step to help ensure that the data center meets the end users requirements. Once business requirements

    are defined, a proper availability needs assessment can help to better define the NCPI topologies required

    to meet the business need. Automated tools exist that can help data center staff quickly identify and size

    their data center loads. A power requirements worksheet should include proper measurement formulas for

    key components such as UPS, generators, cooling and utility power. New technologies, such as the multi-

    core processor chip will be introduced that will impact our power and cooling load calculations in different

    ways.

    By accurately calculating the total power requirements in a systematic and comprehensive manner, data

    center personnel will be able to employ all the economic advantages of scalable, modular, NCPI

    infrastructure components without sacrificing reliability or uptime.

    Slide 38: Thank You!

    Thank you for participating in this Data Center University course.