CADEMO Research and Demonstration Goals
Transcript of CADEMO Research and Demonstration Goals
C I E R CO
CADEMO Research and Demonstration Goals
Resolving California’s needs for an offshore wind pilot project
Prepared by CADEMO Corporation
June 2021
Now
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032
T r
Early 2025 Early 2028 Lale2020 Lale2030 Mid 2022 Early 2023 Late2026+ Submission of BOEM BOEM review & Completion of BOEMpenntt, Consbuction Earliest possible data
s approval approval of Site design envelope auction BOEM of dplatfonns for instalation of first & Assessment COPtoBOEM environmental & installation begins turbine
Plans technical reviews design
Bureau of
Ocean Energy
Management
(BOEM) proces
for Morro Bay
Ca li fornia
State Lands Commission
(SLC)
process for
CADEMO
December Late 2023 Early 2026 2020 SLC and other Installation at SLC publi~ agencies permit Vandenberg engagement approval site starts
October 25, ~~~~ary Mid 2026 2021 Early 2023 First export NOP approval EIR approval by Construction of power by SLC SLC of platforms and commissioners commissioners begins completion _ ________ ....;;.;.;;;:;.;.;;.;;.;;;;.i
4+ years time advantage
Allows time to conduct environmental research, test compatibility with military activities, build supply chain,
and develop ports capacity.
" ________________________________________ _
CADEMO Project (A2222) CADEMO Research and Demonstration Goals
1. PURPOSE OF THE CADEMO PROJECT
The overall aim of the CADEMO project is to "DEMONSTRATION PROJECTS" are
defined as “projects that put into
practice, test, evaluate and
disseminate actions, methodologies or
approaches that are new or unknown
in the specific context of the project,
such as the geographical, ecological,
socio-economic context, and that
could be applied elsewhere in similar
i circumstances” or “a project that is
innovative or new to the state”ii.
demonstrate new models of floating offshore wind
technology to the emerging Californian offshore
wind market. This demonstration project will be the
first of its kind through permitting, leasing approval
and the grid interconnection process in California.
CADEMO proposes to install four offshore wind
platforms, comprising two different floating
designs, with turbines of 12-15 MW each. The
deployment of floating platforms with turbines at
this scale has not been done anywhere else in the world to date.
CADEMO will demonstrate the technical, environmental, economic, and social aspects of
commercial offshore wind in California. The CADEMO project will not act as a silver bullet to
answer all technical, environmental, and social issues associated with commercial offshore wind
development in California - no one project can do PURPOSE of the CADEMO project - to be the
first:
to install floating wind turbines in the
12 – 15 MW range.
to fabricate, install and test 2 different
floating foundation designs.
floating wind project >4 years ahead
of federal plans.
to launch local industry for
competitive readiness and creation of
new jobs.
this, as each deployment environment is unique
and will have its own particular set of aspects to
consider. The CADEMO project will, however,
resolve the state’s need to prove floating platform
designs on the largest-scale turbines, study
environmental effects in real-world California
conditions, and develop an in-state supply chain
rather than relying on imports.
The research results and lessons learned from
CADEMO will significantly improve the chances of success for California’s offshore wind industry
overall. Key to delivering CADEMO as a demonstration project is its ability to be in the water at
least four years before any offshore wind project in federal waters.
Page | 2 June 2021
CADEMO Research and Demonstration Goals CADEMO Project (A2222)
CADEMO is being developed entirely within California state waters, so it will have no influence
on the timing, scale, or decisions to be made within the larger commercial-scale leasing process
in federal waters undertaken by the Bureau of Ocean Energy Management (BOEM).
2. VALUE OF A DEMONSTRATION PROJECT CADEMO advantages include:
• small enough to avoid significant
impacts on fisheries, birds, and marine
mammals.
• large enough to provide sufficient scale
for research credibility.
• situated close enough to shore to
provide accessibility.
• ideal to test and validate technologies
and processes needed for deep
waters.
The CADEMO site has been carefully chosen to
allow suitable access to evaluate both the
technology performance and its environmental
interactions. The smaller scale of the
demonstration project and its proximity to shore
means that it will be more feasible to access and
learn from this early installation, make
corrections, and prove concepts of environmental
avoidance and operation. Despite claims from
other sources, it is not true to state that projects closer to shore cannot provide learning for
developments further offshore. In fact, most demonstration projects for fixed offshore wind have
been near shore (e.g., ORE Catapult Methil, UK (0.1 miles from shore), Blyth, UK (0.5 miles),
Vindby Offshore Wind, DK (1 mile), Aberdeen, UK (1.8 miles), Middelgrunden, DK (2 miles),
Haliade X Rotterdam Harbor, NED (0 miles), Block Island, US (3.8 miles)).
The demonstration value of CADEMO can be summarized in four categories: Technical,
Environmental, Economic and Social. While we are providing examples of some of the
demonstration ambitions of the CADEMO project, we know that more opportunities will be
identified as we engage further with stakeholders and the local supply chain.
Technical
The U.S. West Coast is fundamentally different from the locations where most offshore wind
projects have been deployed to date. California’s waters are deeper, and the maritime physical,
environmental, and social aspects are completely TECHNICAL BENEFITS:
• Test a new generation of wind
turbines and floating platforms.
• Full scale of technologies deployed.
• Provides results before deployment
of 200-270 wind turbines in Morro
Bay.
• Validate advanced mooring
systems and cabling strategies and
DoD equipment, paving way for
future deployments.
• Test and validate projections of
Levelized Cost of Energy.
different. In addition, floating offshore wind
technology is relatively new. Only three floating
wind platform designs have been deployed at
scale to date and none of these in U.S. waters. The
mere fact of deploying new floating offshore wind
platforms in the Pacific is a demonstration action
in itself. It will enable technology learning in how
to fabricate, install and operate floating turbines
at this scale in Pacific sea conditions – including
how the turbines behave, their control systems
and testing installation and O&M strategies. The
project will also offer opportunities to test and demonstrate modular technologies that have the
June 2021 3 | Page
CADEMO Project (A2222) CADEMO Research and Demonstration Goals
potential to reduce the Levelized Cost of Energy (LCOE), applicable across floating platform
technologies and in deeper water, thus enabling offshore wind to be competitive in California
power markets. Cierco has already discussed opportunities with several technology developers
(including partnering on research opportunities) on unique anchoring and mooring systems
intended to be deployed on the CADEMO project.
Environmental
Some stakeholders have legitimate concerns that the projects proposed for development in
federal waters are at such large scale that they may pose a significant risk of unforeseen
environmental harm, the CADEMO project can address those issues at an appropriate scale
before they are installed. A demonstration project in state waters allows for carefully controlled
management of wildlife interaction, environmental risks, and the testing of effective mitigation
measures before large-scale build-out proceeds. Currently, little or no research has been
conducted of the interactions of West Coast fish, bird, and marine mammal species and wind
turbines and barge moorings. CADEMO will allow studies of the impacts of floating offshore wind
projects on a broad variety of relevant species, including birds, bats, cetaceans, fish, reptiles, and
ENVIRONMENTAL ADVANTAGES:
• The area provides a wide range of species,
where interactions and behavior around
the wind turbines can be documented
• Test and validate methodologies and
equipment to mitigate or eliminate impact.
• Valuable information can be documented
around 4 wind turbines instead of 200 - 250
units.
• Opportunities to deploy equipment to
undertake long term monitoring and
document species in the actual
environment.
invertebrates (corals and shellfish) – all on a
relatively small scale that poses minimal risk to
habitats and species.
For example, gray whales migrate generally
close to shore than three nautical miles and
are potentially present in the project area, so
evaluation of effects is likely to be more
accurate and representative than further
offshore. Impacts to gray whales are unlikely,
but the demonstration project can confirm
this and provide greater certainty for a major
industry going forward. More widely, the
project offers an outpost to examine the abundance and movement of listed cetaceans
(humpback, blue, fin, sei, sperm, and northern right whales) closer to shore and monitor their
interactions with offshore wind turbines at small scale with low risk.
The project also provides a unique opportunity to identify issues, and test mitigation and
monitoring strategies at a small scale prior to wider commercial roll out. For example, floating
barges may present unforeseen opportunities for pinniped haul out, the project offers the
prospect to monitor potential haul-out areas on the floating barges (which have never been
deployed in California) to understand the risk likelihood, and test haul out deterrent methods if
needed. There are numerous other opportunities to test technology offshore – for example night-
time radar surveillance for bats/birds, remote monitoring of moorings for derelict/ghost fishing
gear and techniques for removal, turtle interaction surveillance, etc. The project will be a good
Page | 4 June 2021
CADEMO Research and Demonstration Goals CADEMO Project (A2222)
opportunity to adopt a “survey, deploy and monitor” approach throughout the permitting
process, providing an opportunity to test the effectiveness of monitoring and mitigation systems,
procedures, and techniques prior to the wider commercial deployment.
Economic
Offshore wind is a global, competitive industry, and California project developers will face
considerable market pressure to source foreign-manufactured and constructed inputs rather
than locally made products. CADEMO will enable the development of a local supply chain, ports,
and workforce for the large-scale commercial opportunity.
ECONOMIC VALUES:
• The project is active part in a State High Road
Training Partnership with trade unions and
work force development groups to identify
opportunities for job creation and training.
• Early launch of industry is required to mature
industry for competitiveness to avoid
imported options.
• Local industry is required to reach the
targeted job creation numbers by state and
federal government.
• Work with fishing industry to document
impact on fishing and fishing methods as well
as access.
CADEMO provides an opportunity to set a
workforce development “high road”
standard for the industry. CADEMO has
partnered with the Tri-Counties Building and
Construction Trades Council, IBEW 1245, and
other groups in a High Road Training
Partnership (HRTP), funded by the California
Workforce Development Board. Our HRTP is
aimed at identifying options for CADEMO to
incorporate a high road California supply
chain and to ensure community benefits
such as pre-apprenticeship programs with
hiring targets for local disadvantaged communities. This is key to establishing the offshore wind
industry as a model for a “just transition” to clean energy with well-paying union jobs and social
equity.
The fishing sector is a key industry impacted by the deployment of commercial scale offshore
wind in California. The potential impacts range from loss of access to fishing grounds to risks of
radar interference and navigational safety. CADEMO is an ideal small-scale demonstration project
to identify key issues, test potential solutions and formulate good inter-industry working
practices prior to wider commercial implementation. Some examples are testing of radar
trials, and fishing technique interaction
SOCIAL BENEFITS:
• Identification and validation of key
stakeholder issues on the West Coast.
• Confirmation of the potential of
offshore wind to contribute to
attainment of SB 100 goals.
• Testing concept of security of
decentralized supply in a vulnerable
area
systems, Automatic Identification System (AIS)
requirements.
Social
As a new technology on the West Coast, a small-
scale demonstration will enable a deeper
understanding of the technology, social context
and stakeholder views in the region before large-
scale development in federal waters. Installing a
demonstration project by 2026 will prove that
California can host and deliver offshore wind,
June 2021 5 | Page
Provide a facility to demonstrate new model of
floating offshore wind at 12MW+ scale
Need to test Lack of floating platform designs at advanced stage Behavior & control on fullscale operations in California's Pacific conditions Test and demonstrate deployment to reduce LCOE (cost) Installation strategies Scale (e.g. cranage, turbine coupling with floater, etc) DoD interactions Operational strategies
Fabrication, installation and operation of two new floating platforms at >12MW scale. Provision of platform to test new modular technologies (e.g. HAGGIS anchors, DOC Load Reduction Device, etc). Test installation strategies using local supply chain and infrastructure.
ENVIRONMENTAL
Identify, monitor and address environmental floating wind issues of concern in California
_j_ Impact of noise and entanglement on marine mammals
Avian and bat interactions
Turtle interaction
Pinniped haul out
Benthic/seafloor impact
Noise / EMF
Permitting process -appropriate monitoring and mitigation measures
Entanglement (PNNL MoorSea proposal).
Develop technologies to detect bird/bat presence and avoid mortality at a small , manageable scale.
Survey, deploy and monitor mitigation measures with mooring and structures.
ECONOMIC
Evaluate and prepare the California economy for
commercial scale floating offshore wind
Contribute to SB 100 goals Grid stability and resiliency Supply chain preparedness and requirements Port and harbor infrastructure Fishing interactions
_J_
Delivery of 60MW by 2026 to contribute to stability and resiliency of state and local grid.
Engagement with local supply chain on the provision of materials, fabrication, installation and O&M services, components, etc in preparation for large-scale BOEM deployment.
Identification and development of port facilities for construction, assembly and O&M.
Test fishing interactions at small scale - e.g. radar risks, AIS coverage, navigation risk,
Lexclusionlencroachment, cable safety, etc. ~ l
Identify, understand and socialize the concept of
floating offshore
Workforce development
Social equity - ensuring offshore wind takes "high road" not "low road"
University research
High Road Training Partnership to prepare local workforce. Identify supply chain issues for public discussion: local production or imports? Create pre-apprenticeship programs with targeted hiring in disadvantaged communities. Early identification and resolution of stakeholder concerns about full-scale BOEM offshore wind development. Research agreement with Cal Poly and REACH on fisheries and economic impacts.
______________________________________________________________________________
CADEMO Project (A2222) CADEMO Research and Demonstration Goals
providing confidence that offshore wind can provide a significant contribution to the state’s SB
100 goal of carbon-free energy by 2045.
Finally, the project will provide a source of energy in an area vulnerable to unplanned power
outages. The concept of large-scale offshore wind energy supply to provide resiliency to
vulnerable grid areas can be monitored and evaluated. Understanding the technical interactions
of offshore wind with the local electrical grid will enable assessment of various modes of energy
management including hydrogen generation and battery storage to explore decentralized power
systems.
i https://www.euro-access.eu/calls/demonstration_projects_-_nature__biodiversity ii https://www.legis.iowa.gov/docs/aco/arc/2140c.pdf
Page | 6 June 2021
CIIERCO
-< / ::>
____ __ l___h_~--
CADEMO Project Siting Factors Report
Prepared by CADEMO Corporation
June 2021
CADEMO Project (A2222) CADEMO Siting Factors Report
Contents 1. I
2.
3.
4.
4.1.
4.2.
4.3.
4.4.
5.
5.1
5.2.
3.
4.
5.
5.
6.
7.
8.
Appe
Appe
ntroduction .......................................................................................................................................... 3
Siting Objectives.................................................................................................................................... 3
Regions of Consideration ...................................................................................................................... 4
Regional Suitability Analysis.................................................................................................................. 5
Oregon Border to Cape Mendocino.............................................................................................. 5
Cape Mendocino to Pt. Arena....................................................................................................... 5
Point Arena to Cambria (Central California) ................................................................................. 6
Cambria to Point Conception........................................................................................................ 6
Siting Suitability Analysis....................................................................................................................... 7
. Region 1 - Dragon Channel ........................................................................................................... 8
Region 2 - Mattole, Windy Point, Spanish Canyon, and Point Delgada........................................ 8
Region 3 – Point Arena, Gualala and Russian River ...................................................................... 9
Region 4 - Point Arguello ............................................................................................................10
Conclusion of the Siting Analysis ........................................................................................................11
Site Selection within the Point Arguello Region .................................................................................12
References Cited .................................................................................................................................14
ndix 1 – Site Selection Heatmap Detail ..............................................................................................17
ndix 2 – CADEMO Siting Factors Maps ...............................................................................................18
Page | 2 June 2021
CADEMO Siting Factors Report CADEMO Project (A2222)
1. INTRODUCTION
The selection of the Point Arguello site for the CADEMO floating offshore wind demonstration project
resulted from a detailed analysis of potential locations along the entire California coastline. This analysis
was centered on the special requirements of a demonstration-scale project, as described below.
The broader objectives of the project as a demonstration project are addressed in the “210604 CADEMO
Research and Demonstration Goals B1” document. This Siting Factors Report lists the project’s siting
objectives and major constraints, identifies six California siting regions, addresses each region in terms of
key siting criteria, identifies specific site locations with potential to host the project, and evaluates those
sites based on the siting criteria. The report concludes that the identification of the CADEMO project site
off Point Arguello is most consistent with the siting criteria and project objectives.
2. SITING OBJECTIVES
There are five key siting objectives (listed below) that are closely aligned with the overall project objectives
of CADEMO as a FLOW demonstration project in California, which are:
Objective 1: Consistent with the needs of a technology, environmental, and economic demonstration
project. The following are key aspects of siting the project to meet the special needs of a demonstration
project.
• A demonstration project must be sited close to shore and supporting infrastructure. A larger, utility-
scale project could be more optimally sited further offshore in higher wind speed areas despite the
longer subsea cable requirements because the project is supported by a large revenue stream. A key
requirement of a demonstration project is that it is easily accessible for modifications as the project
gathers data about project operation. This is more feasible at a more accessible site closer to shore
and can provide the same benefits in research and demonstration as a project sited further from
shore.
• Given the purpose of a demonstration project, it must be permitted and constructed quickly, relative
to larger utility-scale projects so that the latter can learn and benefit from experience with the
demonstration project. This means that the appropriate location is in state waters (within three
nautical miles (nm) from shore) because leasing and permitting through the State Lands Commission
(SLC) and cooperating agencies requires much less time than the equivalent process for sites on the
outer continental shelf that the Bureau of Ocean Energy Management (BOEM) manages, due to the
scale of development involved. The BOEM process includes several discrete steps that occur in
sequence (call for lease interest, competitive bidding for leaseholds, Site Assessment Plan and data
gathering, formal lease, Construction and Operations Plan) before construction. Moving through
these steps can take eight years or more. BOEM announced in May 2021 that it expects to open the
Morro Bay and Humboldt offshore wind lease areas for auction in summer 2022, with the first projects
operational in the early 2030s. In comparison, SLC’s permitting and leasing process for CADEMO is
well under way and operation is expected by 2026.
• In addition, the permitting process for a very large commercial project runs a proportionally greater
risk of encountering environmental issues, with subsequent delays to find solutions, which may
include further delays due to a need to modify the project and seek permits for those modifications.
A larger project will also take longer to fabricate and construct. A smaller project closer to shore has
June 2021 3 | Page
CADEMO Project (A2222) CADEMO Siting Factors Report
a good chance to be up and running relatively quickly while observing important environmental
protections.
Objective 2: A minimum average wind speed at 90 meters of 7.5 m/s and minimum depth of 50 meters.
A minimum average wind resource speed of 7.5 m/s at 90 meters height is needed to experience a broad
range of conditions for turbine and flotation system testing, particularly given the new generation large
(12-15 MW) turbines that CADEMO will be testing. The tension leg platform design requires a minimum
draft of 50m.
Objective 3: Located within feasible distance of a grid connection (major substation). The ability to
connect with and export power to the state electricity grid is a critical requirement for a project to
demonstrate capacity factor and overall contribution to grid reliability. Connection to the grid also
provides the required access to market to sell the power generated to offset the costs of construction and
operation. Construction of a long subsea transmission cable (>6 nm) or on-land generator tie-line (>10
miles) would be prohibitively expensive and not be economically feasible for a small-scale demonstration
project. For example, a BOEM-funded study by PG&E for the Schatz Energy Research Center in 2020
estimated the needed transmission upgrades for a 48 MW floating demonstration project in the Humboldt
Call Area would cost approximately $540 million. Where suitable connection points are identified, there
is an additional requirement to ensure that the sufficient spare voltage capacity exists to connect the
power generated.
Objective 4: Avoids sensitive biological resource areas to the extent practicable. The most sensitive
biological resources areas are relatively well known in coastal California, given the many years of research
that has been done by the California Cooperative Oceanic Fisheries Investigations program (CalCOFI), US
Fish and Wildlife Service, BOEM, research universities, and others. The project should avoid marine
protected areas, including marine reserves and areas known to be of special biological sensitivity.
Objective 5: Avoids conflicts with other land and sea uses to the extent practicable. These include scenic
viewsheds and major coastal recreational areas, major fishing grounds, shipping lanes, military areas,
aquaculture sites and other important land and sea uses.
3. REGIONS OF CONSIDERATION
Given the project siting objectives, which regions along the California Coastline can best meet these
objectives? The following are six major coastal California regions for offshore wind demonstrator siting
purposes (north to south, Figure 1 – CADEMO Site Regions of Consideration):
1) Region 1 - Oregon border to Cape Mendocino
2) Region 2 - Cape Mendocino to Point Arena
3) Region 3 - Point Arena to Cambria (Central California)
4) Region 4 - Cambria to Point Conception
5) Region 5 - Point Conception to the Mexican Border
6) Region 6 – The Channel Islands
Two of these regions are eliminated from consideration because they have no suitable areas for offshore
wind:
Page | 4 June 2021
CADEMO Siting Factors Report CADEMO Project (A2222)
a) Region 5 - From Point Conception to the Mexican border along the California coastline, average wind
speed at 90 m height does not exceed 7.5 m/s and so this region does not meet the minimum criteria
for wind speed under Objective 2.
b) Region 6 – The Channel Islands: San Miguel, Santa Rosa, Santa Cruz, Anacapa, and Santa Barbara
Islands constitute the Channel Islands National Park and are surrounded by the Channel Islands
National Marine Sanctuary to a distance of six nautical miles. For this reason, the siting of an offshore
wind demonstration project would not be consistent with Objective 4 and would be prohibited per
the National Oceanic and Atmospheric Administration’s National Marine Sanctuary Program regulations at 15 CFR 922.72(a){4)i.
San Nicolas Island is a United States Navy base whose waters are home to classified weapons tests,
war games, and live fire practices. This would be considered a major conflict with other uses and
would be inconsistent with Objective 5. In addition, this island lies more than 60 miles offshore and
any subsea transmission cable route to land would need to cross steep-sided canyons up to 5,000’
deep, thus not complying with Objective 3. San Clemente and Santa Catalina Islands have average
wind speeds under 7.5 m/s and thus do not meet Objective 2.
4. REGIONAL SUITABILITY ANALYSIS
The next level of siting factors analysis identifies sites meeting the project objectives within the remaining
three regions. The sites were explored using the NOAA’s Marine Cadastre National Viewer (NOAA 2021)ii,
the California Offshore Wind Energy Gateway data basiniii, the California Energy Commissioniv, and the
U.S. Geological Survey California State Waters Map Series Data Catalogv to show the locations of marine
protected areas and other important features, and other sources as noted.
4.1. Oregon Border to Cape Mendocino
In this region, average annual wind speed >7.5 m/s is available from the Oregon border south for about
25 miles to the Crescent City harbor area. Due to offshore rocks at the St. George Reef, state waters in
this area extend in a bulge for about 7 nautical miles offshore directly off Crescent City. However, water
depths of 50 m (and outside of a State Marine Reserve) are only available south of the Point St. George
Reef State Marine Conservation Area and Dragon Channel. Waters north of Crescent City are very shallow
and unsuitable per Siting Objective 2.
The only feasible site in this region is the following:
• Dragon Channel – For about 4 nautical miles south of the Pyramid Point State Marine Conservation
Area (SMCA). South of this towards Crescent City the water depth within State waters would be too
shallow for either the SATH barge (9.5m draft) or the tension leg platform (TLP) design (30 m draft).
This site is marginally useful, however, from an engineering perspective because of the relatively small
area that exceeds 50 m in depth.
4.2. Cape Mendocino to Pt. Arena
From just north of Cape Mendocino to Shelter Cove (33 miles), the average wind speed in State waters is
greater than 7.5 m/s and in fact is very strong, reaching up to levels over 10 m/s. The seafloor near Cape
Mendocino, however, includes large sections of rocky bottom that are classified as Essential Fish Habitat,
June 2021 5 | Page
CADEMO Project (A2222) CADEMO Siting Factors Report
excluding moorings and cabling. There are three State Marine Reserves (SMRs) in this section of coastline
(South Cape Mendocino, Mattole Canyon, Sea Lion Gulch), a State Marine Conservation Area (SMCA) (Big
Flat), and three Essential Fish Habitat Conservation Areas (EFH HCAs: Mendocino Ridge, Blunt’s Reef,
Delgada Canyon).
In addition, this area is very remote, and from the Mattole River (10 miles south of Cape Mendocino) to
Shelter Cove, there are no roads near the shoreline. Adjacent land is part of the King Range National
Conservation Area, a semi-wilderness area administered by the U.S. Bureau of Land Management.
Nearshore areas along this stretch of coastline are part of the King Range Area of Special Biological
Significance State Water Quality Protection Area. These factors would make it very difficult to site and
operate a demonstration project in this sub-region. Nevertheless, there are four sites that lie outside of
the marine reserves and EFH conservation areas, included for comparison with other prospective sites.
• Mattole – between South Cape Mendocino SMR and Mattole Canyon SMR
• Windy Point – between Mattole Canyon SMR and the Sea Lion Gulch SMR
• Spanish Canyon - between the Sea Lion Gulch SMR and Big Flat SMCA
• Point Delgada - between the Big Flat SMCA and the Delgado Canyon EFH HCA
4.3. Point Arena to Cambria (Central California)
The Central California area covers approximately 275 miles, with the vast majority covered by National
Marine Sanctuary designations that extend from shore for a long distance into the Pacific Ocean. Offshore
wind facilities and their cables are currently prohibited in these areas, and so most of this area does not
meet Objective 5.
In this region, average annual wind speed >7.5 m/s is available in State waters from Point Arena to Point
Reyes. There are three potential areas identified to the north of the region that technically could host a
demonstration project. Although this area is dependent on tourism, has a coastal road and a number of
coastal residential properties (which will create viewshed issues and interference with coastal vistas) and
is located next to (and in some cases intersects) with the Mendocino Country Pelagic Important Bird Area,
these three sites sit outside of marine reserves and are included for comparison with other prospective
sites.
• Point Arena – between Point Arena and Saunders Reef SMCA
• Gualala – between Saunders Reef SMCA and Stewarts Point SMR
• Russian River – between Stewarts Point SMR and Bodega Head SMR
4.4. Cambria to Point Conception
In this region, the coastline from Point Arguello to Point Conception (about 15 air miles) provides suitable
average annual wind speeds > 7.5 m/s. Possible sites for the demonstration project include the following:
• Point Arguello – Offshore of Vandenberg Space Force Base (VSFB) with a shore landing at Vandenberg
Dock and an alternative location further south (offshore Jalama beach, north of the Point Conception
SMR). The Point Conception SMR extends to the 3 nautical mile limit of state waters along a line due
west from the Point Conception area.
Page | 6 June 2021
CADEMO Siting Factors Report CADEMO Project (A2222)
These sites have an added benefit of the potential to provide renewable power to VSFB, helping the U.S.
Space Force to achieve its goal of energy security and resiliency.
5. SITING SUITABILITY ANALYSIS
The regional suitability analysis has identified nine possible sites, as follows:
a) Dragon Channel (Region 1)
b) Mattole (Region 2)
c) Windy Point (Region 2)
d) Spanish Canyon (Region 2)
e) Point Delgada (Region 2)
f) Point Arena (Region 3)
g) Gualala (Region 3)
h) Russian River (Region 3)
i) Point Arguello (Region 4)
An internal scoring heatmap exercise was undertaken to identify any prohibitive factors and understand
the relative strength and weakness of each location. The multi-attribute decision analysis (MADA) scoring
was moderated through the use of a comparative scoring guide (table 2). The scoring result is provided in
the table 1 below:
Objective Constraint
1 In CA State Lands Yes Yes Yes Yes Yes Yes Yes Yes Yes
Water Depth (> 50 m) Yes Yes Yes Yes Yes Yes Yes Yes Yes
2Wind Energy
Resource7.37 to 8.62 4 8.87 to 9.2 5 9.62 to 9.87 5 7.62 to 9.87 5 7.87 2 7.62 to 8.12 3 7.62 to 8.62 4 7.375 to 8.12 3 7.37 - 7.6 2
Distance to grid
(miles - straight line)13 30 30 26 20 1.5 1.5 2.5 10
Grid Capacity and
Availability (kV)66 66 66 66 66 60 60 60 115
4Sensitive Biological
Resource
DPS and
MAMU1
DPS, King
Range ASBS2
DPS, King
Range ASBS2
DPS, King
Range ASBS2
DPS, King
Range ASBS2
Farallones
National Marine
Sanctuary
1
Farallones
National Marine
Sanctuary
1
Farallones
National Marine
Sanctuary
1
Partial
Leatherback
Turtle critical
Habitat
3
Viewshed Cresent CityPetrolia and
Mattole Beach
Rocks and
Islands
Wilderness
Rocks and
Islands
Wilderness
Rocks and
Islands
Wilderness
Point Arena,
CA1 shoreline
highway
Gualala Point
Regional Park,
CA1 shoreline
highway
CA1 shoreline
highwayJalama Beach
Other UsersCritical
FisheriesWilderness Wilderness Wilderness Wilderness Tourism Tourism Tourism
DoD
Fisheries
1 3
5
1
Region 2 Region 4Region 3
Russian River
5
Region 3
Gualala
14Total
21 43
1314 12 17
5 1 1 1 1 1
3 3 1
14 14
5 5 5 5
Region 1
Dragon Channel
Region 2
Spanish Canyon Point Delgada Point Arguello
Region 2
Mattole
5
Region 2
Windy Point
5
3
14
Region 3
Point Arena
5
3
13
1 1
Table 1 - CADEMO Site Location Heatmap
1 2 3 4 5
2 Wind Energy Resource (m/s) < 7.5 7.5 - 8.0 8.0 - 8.5 8.5 - 9.0 >9.0
Distance to Grid (miles) > 20 15 - 20 10 - 15 5 - 10 < 5
Grid Capacity (kV) < 60 60 - 66 66 - 110 110 - 200 >200
4 Sensitive biological Resource Prohibitive Difficult Manageable Mild Constraint None
Viewshed Designated Scenic Area Residential
Recreational
Industrial None
Other Users Critical Fisheries
Wilderness
Tourism Dependent
High Tourist
Recreational
DoD
Fisheries
Light Fisheries No critical
Uses
Cri
teri
a
3
5
Table 2 - MADA Scoring Guidance Table
June 2021 7 | Page
CADEMO Project (A2222) CADEMO Siting Factors Report
Further detail of the screening level analysis to determine suitable sites for the CADEMO demonstration
project is provided below. For clarity, each site was required to meet objective 1 and 2 before taken
forward for consideration:
• Siting Objective 1 - all sites considered need to be at least 50m in depth and within state waters.
• Siting Objective 2 - areas failing to exceed an average annual wind speed 7.5 m/s were eliminated.
5.1. Region 1 - Dragon Channel
Objective 3: Location within feasible distance of a grid connection. A project at Dragon Channel would
most likely connect with PacificCorp’s transmission infrastructure at either the PacificCorp Belmont or Northcrest 66 kV substation. These are located within Crescent City. Coastal Del Norte County is a small
and isolated load pocket with limited connectivity and may require significant system upgrades to handle
CADEMO’s transmission load. In addition, the PacificCorp transmission system serves power north to Oregon, not south to California, and so would not help meet California’s renewable power goals.
Siting Objective 4: Secure a site that avoids sensitive biological resource areas to the extent practicable.
The site is in critical habitat for the Southern DPS of the green sturgeon. Regulatory agencies have
expressed concerns about the sensitivity of this species to electric and magnetic fields from subsea cables.
The site would be near the Audubon Society’s Pelican Bay MAMU Important Bird Area. This area which
encompasses pelagic open water habitat for the marbled murrelet (Brachyramphus marmoratus), a state-
endangered, federal-threatened species and extends through this species’ usual offshore foraging range,
about a nautical mile offshore (Audubon Society 2021vi).
Siting Objective 5: Secure a site that avoids conflicts with other land and sea uses to the extent
practicable. This site is located roughly five to six nautical miles from the entrance of the Crescent City
harbor. Crescent City is home to a substantial fishing fleet and portions of the area are relatively shallow
(50 to 100 m) soft bottom that is good habitat and fishing grounds for Dungeness crab (California
Department of Fish and Wildlifevii , CDFW 2021a). In 2019, commercial fish landings at Crescent City totaled
more than $22M and over 86 percent of this ($19M) was from Dungeness crab fishing (CDFW 2021b). This
represents one third of the $52M annual value of Dungeness crab landings in the California in 2019 (CDFW
2021c). A project proposed for this location would encounter strong and vocal opposition from
commercial fishers. A project this close to the Crescent City harbor entrance may also interfere with
general navigation to the port, given that access to the port is constrained by the St. George Reef.
Recreational users of the scenic Crescent City waterfront and Crescent Beach are likely to object to the
visual resources impacts of a demonstration project in this location, within 5 nautical miles of the
shoreline.
The project in this location would also be within 5 nautical miles of the Del Norte County Airport in
Crescent City and would likely conflict with flight operations and radars.
5.2. Region 2 - Mattole, Windy Point, Spanish Canyon, and Point Delgada
These prospective sites are treated together because of their geographic proximity.
Objective 3, Grid Connection Feasibility—This area is entirely lacking in grid connectivity. The nearest
PG&E transmission lines and substations are inland in the State Route 101 corridor (inland in this area
Page | 8 June 2021
CADEMO Siting Factors Report CADEMO Project (A2222)
partly due to mountainous terrain on the coast). From Point Delgada (southern end), the nearest
substation is at Garberville, a straight-line distance of 15 miles and a road distance of 25 miles over rough
terrain.
Siting Objective 4: Secure a site that avoids sensitive biological resource areas to the extent practicable.
The site is in critical habitat for the Southern DPS of the green sturgeon. In the past, regulatory agencies
have expressed concerns about the sensitivity of this species to electric and magnetic fields from subsea
cables.
Submerged areas within a short distance of the shore adjacent to all three sites are part of the King Range
Area of Special Biological Significance State Water Quality Protection Area/King Range State Marine
Reserve.
Siting Objective 5: Secure a site that avoids conflicts with other land and sea uses to the extent
practicable. Land adjacent to three of the sites (Windy Point, Spanish Canyon and Point Delgada) is part
of the King Range National Conservation Area, and is part of the “Lost Coast,” the state’s only remaining
significant roadless coastal area. The visual impact of an offshore wind project to a wilderness area would
be a significant issue with any of these sites. The same three sites are also within the Rocks and Islands
Wilderness, part of the National Wilderness Preservation System. The remaining site, Mattole, is
overlooked by the unincorporated community of Petrolia and the local scenic spot of Mattole Beach.
5.3. Region 3 – Point Arena, Gualala and Russian River
These prospective sites are treated together due to their geographic proximity.
Objective 3: Grid Connection Feasibility—This region has relatively close access to local grid, with a local
substation, operated by PG&E and rated between 33 to 92kV, available at each location of Point Arena,
Gualala or Russian River (Fort Ross). Connection should be relatively straightforward with distances being
between two to five miles at the nearest points. However, there are limited power offtake options in the
region.
Siting Objective 4: Secure a site that avoids sensitive biological resource areas to the extent practicable.
The site is in critical habitat for the Southern DPS of the green sturgeon. Regulatory agencies have
expressed concerns about the sensitivity of this species to electric and magnetic fields from subsea cables.
The Audubon Society’s Mendocino Coast Pelagic Important Bird Area (IBA)viii is located a few miles farther
out to sea from these three sites. The project would not directly affect either of these areas. The Point
Arena IBA is designated for the pink-footed shearwater (Ardenna creatopus), a species is on Audubon
WatchList and considered vulnerable, per the International Union for the Conservation of Nature (IUCN).
Shearwaters are the lowest-flying of all seabirds, typically flying within only 10m of the surface of the
water. Encounters with an offshore wind turbine rotor (25 m above water) are thus likely to be rare. While
these IBAs are important for the species, they represent only a small proportion of its overall foraging
range, which extends from southern Chile to Alaska and the pink shearwaters of the project area represent
a small part of the overall population. The Mendocino Coast Pelagic IBA is designated for the black-footed
albatross (Phoebastria nigripes). This species is considered near-threatened by the IUCN, mainly because
of the effects of long-line fishing.
June 2021 9 | Page
CADEMO Project (A2222) CADEMO Siting Factors Report
Siting Objective 5: Secure a site that avoids conflicts with other land and sea uses to the extent
practicable. These sites pose at least two compatible use conflicts. First, the entire area lies within the
Greater Farallones National Marine Sanctuaryix, within which an offshore wind project would not be
permitted.
Second, although the coastal strip is relatively sparsely populated, all three sites can be directly viewed
from the California State Route 1 Shoreline Highway, designated as an “All-American” roadx providing a
scenic route to numerous tourist attractions along the route. These include Manchester State Park, Point
Arena Lighthouse, Point Arena-Stornetta Public Lands, Pelican Bluffs, Schooner Gulch State Beach,
Glennen Beach, Gualala Point Regional Park, Shell Beach, Stillwater Cove Regional Park, Salt Point State
Park, Fort Ross State Historic Park, Russian Gulch State Beach, and Sonoma Coast State Park, among
others. In addition, residences along the coast would be considered highly sensitive to visual resources
impacts, as many are recreational homes that are specifically oriented for views of the coast and ocean.
5.4. Region 4 - Point Arguello
Objective 3, Grid Connection Feasibility—A facility at Point Arguello can interconnect with the
Vandenberg grid at Vandenberg Space Force Base Substation “N” or can interconnect with the wider PG&E grid at 115 kV at Surf Substation, approximately 10 miles north of a cable landing at Vandenberg Dock.
Routing a cable to shore at Jalama Beach would not be feasible because the land route to the nearest
substation would be prohibitively long (Manville Substation south of Lompoc) and would have to be
constructed over difficult terrain. A cable route to the Gaviota substation would not be feasible because
it would have to cross the Point Conception SMR.
Siting Objective 4: Secure a site that avoids sensitive biological resource areas to the extent practicable.
The site is in critical habitat for the leatherback turtle, but project operations would not be likely to harm
this species’ breeding habitat or food sources.
The Audubon Society’s Point Conception Important Bird Areaxixii is located approximately five nautical
miles further out to sea at its nearest point from the Point Arguello site, and the Point Sal Important Bird
Areaxiiixiv is approximately fourteen nautical miles north. The project would not directly affect either of
these areas.
Both Important Bird Areas (IBAs) are designated for the pink-footed shearwater (Ardenna creatopus), a
species on the Audubon WatchList and is considered vulnerable, per the International Union for the
Conservation of Nature. Shearwaters are the lowest-flying of all seabirds, typically flying within only 10m
of the surface of the water. Encounters with an offshore wind turbine rotor (25 m above water) are thus
likely to be rare. While these IBAs are important for the species, they represent only a small proportion
of its overall foraging range, which extends from southern Chile to Alaska and the pink shearwaters of the
project area represent a small part of the overall population.
The Point Conception IBA also identifies the ashy storm petrel (Oceanodroma homochroa) as a feature.
The ashy storm petrel breeds on rocky islands off California and Mexico and is an endangered species (c.
10,000 birds and declining). It’s range is relatively limited compared to other seabird species but still covers many thousands of square km. Most foraging is done around the edge of the continental shelf. This
group of birds (storm petrels) feed by skipping over the surface of the sea, very rarely flying at height. The
risk to this species, and consequently the IBA, is therefore very low.
Page | 10 June 2021
CADEMO Siting Factors Report CADEMO Project (A2222)
An additional Point Sal IBA feature is Brandt’s cormorant (Phalacrocorax penicillatus). This species is
numerous (population c. 230,000 individuals) and has a very large range. It feeds mostly in shallow waters
but also further out in deeper water. Flights over water tend to be low, beneath the rotor swept zone. It’s
very unlikely that significant numbers of birds will use the CADEMO area, and birds which might occur in
the area are likely to be on the water or flying low over it. The risk to the birds from the scheme is therefore
very low, and consequently to the integrity of the IBA.
The waters off Point Sal also provide feeding areas for the brown pelican (Pelecanus occidentalis) which
roosts on the shore near Point Sal (approximately 20 miles north of Point Arguello). The coastal region
around Point Sal supports large numbers of this species, which is identified as a secondary feature within
the IBA, but it is an inshore species, rarely venturing out to deeper waters. The risk to this species, and
consequently the IBA is extremely low.
Independent researchers (Calambokidis 2015) have identified a biologically important area (BIA) for the
endangered blue whale in the project area (extending from Point Conception north to Point Sal), with
moderately high blue whale density. The potential for vessel collisions this species would need to be
carefully managed at this site.
Siting Objective 5: Secure a site that avoids conflicts with other land and sea uses to the extent
practicable. One unique aspect of the Point Arguello site is that a significant portion of the adjacent
onshore land in the northern area of the region is owned and managed by the Vandenberg Space Force
Base (VSFB) for about 28 miles from the shoreline to the crest of adjacent mountains. This greatly reduces
conflicts based on visual resources impacts to recreational or residential uses, because of the lack of
private or other public land in the project viewshed. Public access to the coastline in this area is limited
to small areas at Surf and Jalama beaches, each more than 10 air miles from the nearest turbine site.
The site is relatively distant from the nearest fishing ports at Morro Bay (45 nautical miles), Port San Luis
(35 nautical miles), and Santa Barbara (60 nautical miles). While commercial fishing boats use the area,
based on the historical landings records from the Californian Department of Fish and Wildlife, the catch
in fishing blocks around this site is likely to be rated as lower in value than in areas closer to fishing ports.
An offshore wind project in region 4 presents potential conflict issues with flight operations and radars at
Vandenberg Space Force Base, however consultation with the U.S. Department of Defense through their
Site Clearinghouse process has identified appropriate mitigation to resolve this (see section 7).
The southern section of region 4 is located within one of the Californian Department of Fish and Wildlife
designated California halibut trawl areas and would therefore be likely to draw significant opposition from
commercial fishing interests (Conservation Biology Institute 2021).
6. CONCLUSION OF THE SITING ANALYSIS
Siting analysis concludes that only one of the nine sites assessed would be feasible for CADEMO:
Region 1 - Dragon Channel – Infeasible because of the major potential conflict with the crab fishing
industry, lack of a connection to the California grid, and proximity to the Crescent City waterfront and
Crescent Beach viewsheds.
Region 2 - Mattole, Windy Point, Spanish Canyon, and Point Delgada - Infeasible because of visual
resources conflicts with a wilderness area, biological resources sensitivity, and lack of grid connectivity.
June 2021 11 | Page
CADEMO Project (A2222) CADEMO Siting Factors Report
Region 3 - Point Arena, Gualala and Russian River – Infeasible because of conflict with the National
Marine Sanctuary, visual resource conflicts with State Parks, recreational viewers at scenic viewpoints
along the adjacent shoreline highway and conflict with residential users of coastal properties.
Region 4 - Pont Arguello – Feasible. The Point Arguello site is excellent for a demonstration project
because of the relative lack of conflicts with potentially competing uses or interests and because it meets
all the project siting objectives, as follows:
• Objective 1: Consistent with the needs of a technology, environmental, and economic
demonstration project. The site is near shore, easily accessible, located away from areas of
significant use conflict but relatively near support facilities.
• Objective 2: With a minimum average wind speed at 90 meters of 7.5 m/s and minimum depth
of 50 meters. The site exceeds these minimum criteria.
• Objective 3: Grid Connection Feasibility This site can easily connect with VSFB Substation N or
Surf Substation using a generator tie-line less than 10 miles long.
• Objective 4: Avoids sensitive biological resource areas to the extent practicable. The site avoids
marine reserves and important bird areas. Although located in critical habitat for the leatherback
turtle and in important cetacean feeding areas, the project would not conflict with or directly
affect these species.
• Objective 5: Avoids conflicts with other land and sea uses to the extent practicable. There would
be few or no conflicts with recreational and residential users over visual resources impact because
of the siting on federal government property at VSFB. The site is not near a commercial fishing
port or major fishing grounds.
7. SITE SELECTION WITHIN THE POINT ARGUELLO REGION
Following the initial process identifying the Arguello region as the preferential location as, number of
areas around Platform Irene and VSFB outside of designated protected areas, available offshore seabed
profile, proximity to an available grid connection at Surf Substation and significant available
environmental information gathered as part of the CalWave project were identified. The preferred
location being selected on the following basis:
• The most favorable location for wind resource and yield (i.e. highest wind).
• Few environmental constraints (it avoided activities within the Vandenberg State Marine
Reserve).
• Favorable geotechnical and seabed conditions for mooring design.
• Avoidance of areas of high coastal population and minimization of visual intrusion.
These assessments led to the selection of a lease area for the demonstration project which formed the
basis of the SLC lease and permit application.
Page | 12 June 2021
0
t;I
-
CADEMO Siting Factors Report CADEMO Project (A2222)
Figure 1 - Original CADEMO turbine locations
During the SLC application, a dialogue was opened with the Department of Defense Military Aviation and
Installation Assurance Siting Clearinghouse (The Clearinghouse) on the specific locations for the floating
offshore wind turbines. At a meeting on the 22 May 2020, the Clearinghouse provided feedback that their
analysis determined that any locality south of Point Arguello would be military incompatible. This led to
the identification of a revised configuration that is considered by the Clearinghouse as mission compatible
with mitigation. This configuration now forms the basis of the CADEMO seabed lease and permit
application to the State Lands Commission and is presented in figure 2:
Figure 2 - CADEMO Project Layout
June 2021 13 | Page
CADEMO Project (A2222) CADEMO Siting Factors Report
8. REFERENCES CITED
Audubon Society. 2021. California IBA Interactive Site Map.
https://ca.audubon.org/conservation/california-iba-interactive-site-map. Accessed April 24,
2021.
Beiter, Philipp, Walter Musial, Patrick Duffy, Aubryn Cooperman, Matt Shields, Donna Heimiller, and
Mike Optis. 2020. The Cost of Floating Offshore Wind Energy in California Between 2019 and 2032.
Golden, CO: National Renewable Energy Laboratory. NREL/TP-5000-77384.
https://www.nrel.gov/docs/fy21osti/77384.pdf
Calambokidis, J, GH Steiger, C Curtice, J Harrison, MC Ferguson, E Becker, M DeAngelis, and SM Van
Parijs. 2015. Biologically Important Areas for Selected Cetaceans Within U.S. Waters – West Coast
Region. Aquatic Mammals 41(1), 39-53. DOI 10.1578/AM.41.1.2015.39
California Department of Fish and Wildlife (CDFW). 2021a. Dungeness Crab Enhanced Status Report.
https://marinespecies.wildlife.ca.gov/dungeness-crab/. Accessed April 25, 2021.
California Department of Fish and Wildlife (CDFW). 2021b. Poundage and Value of Commercial Fish
Landings by Port, Eureka Area, 2019.
https://nrm.dfg.ca.gov/FileHandler.ashx?DocumentID=178025&inline. Accessed April 24, 2021.
California Department of Fish and Wildlife (CDFW). 2021c. Poundage and Value of Landings of
Commercial Fish into California, by Area, 2019.
https://nrm.dfg.ca.gov/FileHandler.ashx?DocumentID=178025&inline. Accessed April 25, 2021.
https://nrm.dfg.ca.gov/FileHandler.ashx?DocumentID=178022&inline
California Energy Commission (CEC). 2021. California Electric Infrastructure. https://cecgis-
caenergy.opendata.arcgis.com/app/ad8323410d9b47c1b1a9f751d62fe495. Accessed April 24,
2021.
Conservation Biology Institute. 2021. Databasin: California Offshore Wind Energy Gateway. California
Halibut Trawl Grounds. Accessed May 28,
2021.https://caoffshorewind.databasin.org/maps/new/#datasets=e6d974dfb5b34f5d9823252a
4f667cbc.
National Oceanic and Atmospheric Administration (NOAA). 2021. Marine Cadastre National Viewer.
https://marinecadastre.gov/nationalviewer/. Accessed April 24, 2021.
National Renewable Energy Laboratory (NREL). 2021. California Offshore 90-Meter Wind Map and Wind
Resource Potential. https://windexchange.energy.gov/maps-data/146. Accessed April 21, 2021.
i https://www.law.cornell.edu/cfr/text/15/922.72 ii https://marinecadastre.gov/nationalviewer/ iii https://caoffshorewind.databasin.org/ iv https://caenergy.maps.arcgis.com/home/index.html v https://pubs.usgs.gov/ds/781/ vi https://www.audubon.org/important-bird-areas/pelican-bay-ca-mamu vii https://marinespecies.wildlife.ca.gov/dungeness-crab/the-fishery/
Page | 14 June 2021
CADEMO Siting Factors Report CADEMO Project (A2222)
viii https://www.audubon.org/important-bird-areas/mendocino-coast-pelagic-ca ix https://farallones.noaa.gov/ x https://www.fhwa.dot.gov/byways/states/CA xi https://www.audubon.org/important-bird-areas/point-conception-121w34n xii https://www.audubon.org/important-bird-areas/point-conception-120w34n#:~:text=The%20Point%20Conception%20120W34N%20IBA,%2C%20ports%2C%20and%20oil%20extracti on xiii https://www.audubon.org/important-bird-areas/point-sal-121w35n xiv https://www.audubon.org/important-bird-areas/point-sal-120w35n
June 2021 15 | Page
CADEMO Siting Factors Report CADEMO Project (A2222)
APPENDIX 1 – SITE SELECTION HEATMAP DETAIL
Ob
jec
tiv
eC
on
str
ain
t
1In
CA
Sta
te L
an
ds
Ye
sY
es
Ye
sY
es
Ye
sY
es
Ye
sY
es
Ye
s
Wa
ter
De
pth
(>
50
m)
Ye
sY
es
Ye
sY
es
Ye
sY
es
Ye
sY
es
Ye
s
2W
ind
En
erg
y
Re
so
urc
e7
.37
to
8.6
24
8.8
7 to
9.2
59
.62
to
9.8
75
7.6
2 to
9.8
75
7.8
72
7.6
2 to
8.1
23
7.6
2 to
8.6
24
7.3
75
to
8.1
23
7.3
7 -
7.6
2
Dis
tan
ce
to
gri
d
(mile
s -
str
aig
ht
lin
e)
13
30
30
26
20
1.5
1.5
2.5
10
Gri
d C
ap
ac
ity
an
d
Av
aila
bilit
y (
kV
)6
66
66
66
66
66
06
06
01
15
4S
en
sit
ive
Bio
log
ica
l
Re
so
urc
e
DP
S a
nd
MA
MU
1D
PS
, K
ing
Ra
ng
e A
SB
S2
DP
S, K
ing
Ra
ng
e A
SB
S2
DP
S, K
ing
Ra
ng
e A
SB
S2
DP
S, K
ing
Ra
ng
e A
SB
S2
Fa
rallo
ne
s
Na
tio
na
l Ma
rine
Sa
nctu
ary
1
Fa
rallo
ne
s
Na
tio
na
l Ma
rine
Sa
nctu
ary
1
Fa
rallo
ne
s
Na
tio
na
l Ma
rine
Sa
nctu
ary
1
Pa
rtia
l
Le
ath
erb
ack
Turt
le c
ritica
l
Ha
bita
t
3
Vie
ws
he
dC
rese
nt C
ity
Pe
tro
lia a
nd
Ma
tto
le B
ea
ch
Ro
cks a
nd
Isla
nd
s
Wild
ern
ess
Ro
cks a
nd
Isla
nd
s
Wild
ern
ess
Ro
cks a
nd
Isla
nd
s
Wild
ern
ess
Po
int A
rena
,
CA
1 s
ho
relin
e
hig
hw
ay
Gua
lala
Po
int
Re
gio
na
l Pa
rk,
CA
1 s
ho
relin
e
hig
hw
ay
CA
1 s
ho
relin
e
hig
hw
ay
Ja
lam
a B
ea
ch
Oth
er
Us
ers
Cri
tica
l
Fis
he
rie
sW
ilde
rne
ss
Wild
ern
ess
Wild
ern
ess
Wild
ern
ess
To
uri
sm
To
uri
sm
To
uri
sm
Do
D
Fis
he
rie
s
13
5 1
Re
gio
n 2
Re
gio
n 4
Re
gio
n 3
Ru
ss
ian
Riv
er 5
Re
gio
n 3
Gu
ala
la
14To
tal
21
43
1314
1217
51
11
11
33
1
1414
55
55
Re
gio
n 1
Dra
go
n C
ha
nn
el
Re
gio
n 2
Sp
an
ish
Ca
ny
on
Po
int
De
lga
da
Po
int
Arg
ue
llo
Re
gio
n 2
Ma
tto
le
5
Re
gio
n 2
Win
dy
Po
int
5 3
14
Re
gio
n 3
Po
int
Are
na
5 3
13
11
12
34
5
2W
ind
Ener
gy R
esou
rce
(m/s
)<
7.5
7.5
- 8
.08.
0 -
8.5
8.5
- 9.
0>9
.0
Dis
tanc
e to
Gri
d (m
iles)
> 20
15 -
20
10 -
15
5 -
10<
5
Gri
d C
apac
ity
(kV
)<
6060
- 6
666
- 1
1011
0 -
200
>200
4Se
nsi
tive
bio
logi
cal R
esou
rce
Proh
ibit
ive
Dif
ficu
ltM
anag
eabl
eM
ild C
onst
rain
tN
one
Vie
wsh
edD
esig
nate
dSc
enic
Are
aR
esid
enti
al
Rec
reat
iona
l
Indu
stri
alN
one
Oth
er U
sers
Cri
tica
l Fis
heri
es
Wild
erne
ss
Tour
ism
Dep
ende
nt
Hig
h To
uris
t
Rec
reat
iona
l
DoD
Fish
erie
s
Ligh
t Fi
sher
ies
No
crit
ical
Use
s
Criteria
3 5
June 2021 17 | Page
CADEMO Project (A2222) CADEMO Siting Factors Report
APPENDIX 2 – CADEMO SITING FACTORS MAPS
Index:
Figure Title 1 Site Regions of Consideration 2 Region 1 - Oregon border to Cape Mendocino – Technical Constraints 3 Region 1 - Oregon border to Cape Mendocino – Protected and Sensitive Areas 4 Region 1 - Oregon border to Cape Mendocino – Sensitive Habitats 5 Region 2 - Cape Mendocino to Point Arena – Technical Constraints 6 Region 2 - Cape Mendocino to Point Arena – Protected and Sensitive Areas 7 Region 2 - Cape Mendocino to Point Arena – Sensitive Habitats 8 Region 3 - Point Arena to Cambria (Central California) – Technical Constraints 9 Region 3 - Point Arena to Cambria (Central California) – Protected and Sensitive Areas
10 Region 3 - Point Arena to Cambria (Central California) 11 Region 4 - Cambria to Point Conception – Technical Constraints 12 Region 4 - Cambria to Point Conception – Protected and Sensitive Areas 13 Region 4 - Cambria to Point Conception – Sensitive Habitats 14 Region 5 - Point Conception to the Mexican Border – Technical Constraints 15 Region 5 - Point Conception to the Mexican Border – Protected and Sensitive Areas 16 Region 5 - Point Conception to the Mexican Border – Sensitive Habitats 17 Region 6 – The Channel Islands – Technical Constraints 18 Region 6 – The Channel Islands – Protected and Sensitive Areas 19 Region 6 – The Channel Islands – Sensitive Habitats 20 Point Arguello – detailed constraints
Page | 18 June 2021
Nevada
Oregon
Cambria to Point Conception
Point Arena to Cambria
Cape Mendocino to Point Arena
Oregon Border to Cape Mendocino California
Point Conception to the Mexican Border
The Channel Islands
Gualala Russian River
Dragon Channel
Mattole
Point Arena
Spanish Canyon
Point Arguello
Point Delagada
Windy Point
Arizona California
Nevada Utah Legend
Technically Suitable Area (Depth + SLC)Region Area
Oregon Border to Cape Mendocino Cape Mendocino to Point Arena Point Arena to CambriaCambria to Point Conception Point Conception to the Mexican Border The Channel Islands State Boundary
0 30 60 Miles
Figure 1 Site Regions of Consideration
CiercoCADEMO Project
June 07, 2021 IUTM Zone 11 North
Datum: NAD 1983
Sources: Cierco, 2021
Pacific Ocean
12:J CZI IZJ 12:J CZI IZJ
PalntANllalDCamllda
c.nbllltDPolnla.-..pllan •
I I ■- ■
- --11 ■- .
!!
!!
!! !!
!! !!
!
! !!
!! !
!
!
! !!
!! !! !! !!
! !
!
!
! !
! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
!
!
!
!
!
!
!
!
!
! !
!
!
! !
! ! !
!
!
!
!
!
!
!!
!
! !!
!
!!
!
!
!! !
!
!
!!!
!! ! ! ! !
!
!
! !
! !
!
! ! ! !
! ! !
! !
! !
!! ! !
!!! ! !
!! !!
! ! !! !
! ! !
!
!
! !
!
! !
! !
!
! !
!
!
!
!
! !
!
!
! !
!
! !
! !
! !
! !
!
!
!
!
Figure 2Region 1 - Oregon Border to Cape Mendocino
Technical Constraints
Dragon Channel
Pacific Ocean
!
!!
!
Mattole Legend
Technically Suitable Area (Depth + S LC) Windspeed 8.625 Transmission Line (kV) Region Area D 7.375 8.875 ! 60 kV iz::::J Oregon Border to Cape Mendocino D 7.625 9.125 ! 69 kV□ Cape Mendocino to Point Arena D 7.875 9.375 ! 115 kV
Minimum Depth (-50) D 8.125 ----9.625 • State Boundary CJ 8.375 9.875
Sources: Cierco, NOAA, CEC, 2021 Nevada Utah
CiercoCalifornia CADEMO ProjectUTM Zone 1 1 North Datum: NAD 1983
June 07, 2021
ArizonaI 0 5 10 Miles
!
!
! ! !
!
!
!
!
!
!
!
!
!!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
!
!
!
!
! !
!
!
!
!
!
!
!
!
!
!
!
! ! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
! !
!
!
!
!
!
!
!
!
!
!
!
! !
!
!
!
! !
!
!
! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
!
!
!
!
!
!
!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
! !
!
!
#
#
#
#
#
#
Dragon Channel
Mattole
Arizona California
Nevada Utah Legend#Vista Point
Technically Suitable Area (Depth + SLC)Region Area
Oregon Border to Cape MendocinoCape Mendocino to Point ArenaFederal Protected AreaState Protected AreaCoastal Tribal LandsMinimum Depth (-50)
Transmission Line (kV) ! 60 kV ! 69 kV ! 115 kV
State Boundary
0 5 10 Miles
Figure 3Region 1 - Oregon Border to Cape Mendocino
Protected and Sensitive Areas
CiercoCADEMO Project
June 07, 2021 IUTM Zone 11 North
Datum: NAD 1983
Sources: Cierco, NOAA, CEC,State of Califronia, Offshore Wind Databasin,
2021
Pacific Ocean
-[Z)
IZJ
CII •
~· • .,.., _, I
t I .. • • ' J
' ' I I .,
' ;
/'
,. ,..,;
; .... __ .. ,,
#'
I I
I I I I I I I
' , I I • , ., , ,,
,' -l ,,
,,
' ~ ... .. C I,
• I
' I, I I, I,
' .. ... • • I,
• 1 I I
' .. • ' ' I ..
!!
-□ [ZJ
--CJ CJ
-·
•
I I
• ' I
' ~ ... .. II: I,
• I
' I, I I, I,
' .. ... • • I,
• 1 I I
' .. • ' ' I ..
!!
!!
!! !!
!! !!
!
! !!
!! !
!
!
!
!! !! !! !!
!!
! !
!
!
! !
! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
!
!
!
!
!
!
!
! !
! !
!
!
! !
! ! !
!
!
!
!
!
!
!!
!
! !!
!
!!
!
!
!! !
!
!
!!!
!! ! ! ! !
!
!
! !
! !
!
! ! ! !
! ! !
! !
! !
!! ! !
!!! ! !
!! ! !
! ! !! !
! ! ! ! !
!!
! !
!
!
!
! ! !
!
!
! !
!
! !
!
! !
!
!
!
!
! !
!
! ! !
!
! !
! !
!
!
! !
! !
! !
!
Dragon Channel
Pacific Ocean
!
!!
!
MattoleLegend
Techn Figure 4Transmission Line (kV) on 1 - Oregon Border to Cape Mendoc60 kV69 kV
ically Suitable Area (Depth + SLC)on Area Regi noRegi Sources: Cierco, NOAA, CEC,
Audobon, 2021 Utah Sensitive HabiNevada tats!
Oregon BorderCape Mendoci
tant Bird Areas
o Cape Mendocino no to Point Arena t !
115 kVSt Ci
CADEMO Pro ! erco
ject(IBA)mpor
GlobalSt
ate Boundary CaliforniaUTM Zone 11 NorthDat : NAD 1983 ArizonaIate umGreen S
StellMi i
urgeon Critical Habi er Sea Lion Cri mum Dep
0 5t t tical Habitat
-50)
ta
June 07, 2021h ( Milestn
i
I
10
\ ...
- -D -iz::::J D -r::::zl D -[ZJ D -D -D -
! !
! !
!
! !
! !
! !
!
!
!
!
!
! !
!
!
!
!
!
!
! !
!
!
!
!! ! !! !
!
!
! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
!
! !
!
! !
! !
!
!
!
!
!
!
!
!
!
!
!
!
! !
! !
! !
!
!
!
!
!
!
!
Mattole
Windy Point
!
Spanish Canyon
Point Delagada
Pacific Ocean
Point Arena Figure 5
iLegend
RegiTechnically Suitable Area (Depth + SLC) Windspeed 8.875 Transmission Line (kV)Region Area 7.375 9.125 ! 60 kV Nevada Utah
Oregon Border o Cape Mendocino 7.625 9.375 115 kV no to Point Arena
on 2 - Cape Mendoc no to PoTechnical Constrai
int ArenaSources: Cierco, NOAA, CEC, 2021 nts
t !
a CiCADEMO Pro
Cape MendociPoint Arena t
7.875 9.625 ercojecto Cambr
Minimum Depth (-50) ia 8.125 9.875
8.375 10.1258.625 10.375
CaliforniUTM Zone 11 NorthDat : NAD 1983 AriI zonaum 0 5
June 07, 2021 Miles
10
-iz::::J [21
[ZJ
~
m
!
!
Mattole
! ! !
! !
!
!
!
!
! !
!
!
!
Windy Point !
! !
!
!
!
Spanish Canyon !
!
!
!
! !
!
Point Delagada
!
!
!
!
! !! !
!
!
!
!
!
Pacific Ocean
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!! !
! !
! !
! !
! !
!
Point Arena !
!
LegendTechnically Suitable Area (Depth + SLC)
Region AreaOregon Border to Cape MendocinoCape Mendocino to Point ArenaPoint Arena to CambriaFederal Protected AreaState Protected AreaCoastal Tribal Lands
Minimum Depth (-50)Transmission Line (kV) ! 60 kV ! 115 kV
Sources: Cierco, NOAA, CEC,State of Califronia, Offshore Wind Databasin,
2021 UtahNevada
California Arizona
Figure 6Region 2 - Cape Mendocino to Point Arena
Protected and Sensitive Areas Ci
CADEMO ProercojectUTM Zone 11 North
Datum: NAD 1983 I 0 5 10 MilesJune 07, 2021
! !
! !
!
! !
! !
! !
!
!
!
!
!
! !
!
!
!
!
!
!
! !
!
!
!
!! ! !! !
!
!
! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
!
! !
!
! !
! !
!
!
!
!
!
!
!
!
!
!
!
!
! !
! !
! !
!
!
!
!
!
!
!
Mattole
Windy Point
!
Spanish Canyon
Point Delagada
Pacific Ocean
Point Arena Legend
Technically Suitable Area (Depth + SLC) Green Sturgeon Critical Habitat RegiRegion Area Leatherback Turtle Critical Habitat Audobon, 2021 Nevada
Oregon Border to Cape Mendocino S no to Point Arena Mi imum Dep h (-50)
Figure 7ion 2 - Cape Mendoc no to Po
Sensitive Habi int ArenaSources: Cierco, NOAA, CEC, Utah tats
teller Sea Lion Critical HabitatCape MendociPoint Arena t
tnTransm CiCalifornia CADEMO Pro
ercojecto Cambr
Important Bird Areas (IGlobal
iaBA
ission Li (kV)ne UTM Zone 11 NorthDat : NAD 1983
) 60 kV115 kV
AriI zona!
um 0 5!
State June 07, 2021 Miles
10
,., ~
- D D -iz::::J D -[21 D -[ZJ D -
., •' \ -.., __ ..,
... ,
... ~ •• t
11 ■- .
!
!
! !
!
!
!
!
!
!
! ! !
!
!
!
!
! !
!
!
!!
!!
!
!
!
! !
! !
! !
!
!!
!!
!
!!
!!
!
! ! !
! !
!
!
! !
!
!
! ! !
! ! ! ! ! !
! !
!!
! !
!
! ! !!
!
! ! !
!
!
!
!
! ! !
! !
!
! ! !
!
! ! !!! !
! !
! !
!! ! !!
! !
!
! !!
!!!
! !
!
!
!
!
!
!
! !
!! !
!
!
!
!
!
!
!
!
! !!
!
! !
!! !
! !! !!
!!
!
!
! !
!! !
!
! !
!!!!
!!!
!
!
! ! ! ! !
!! ! !
!
!
! ! !
!
!
! ! ! ! !
!
!
! !
! ! ! ! ! !
!!
!
!!!!
!
! !
!
!
! !
!
!!
!
! !
! ! !
! !!
!
!! !
!
! !
!
!! !
!
!
!
!
!
! !!!
!
! ! !
!
! !
!
! ! !
!
! !
!
!
! ! !
!
!
! !!
! ! ! !
!! !!!
! !
! !
!
!
!
! !
! ! !
!
!
!!
! !!
!
!! ! !! !
!
! !
!
! !!!
! !! !!
!! ! ! !
! ! !!
!
!
!
!
!!! ! ! !
!!
!
!
!!! !
! !!!
!
! ! !!!!
!
!
!
!
!
!
!
!!!
!!! !
! !
!! !!!
!! !! !
!
!
! ! !
!
!
! !!!
!!!!!
! ! ! !! !
!
! ! !
!!!
!
!
!
! ! !
!
!
! !
!
!
!!
!!! ! !
!
! ! !
!
!
!
!
! !
!!
!
!
!
!
! ! !
!
! !
! !
!
!! !
! !
!
! ! !!! ! !
! ! ! !
! !
! ! !
!
!!! ! ! !! !! !
!
!
!!
! !
! ! !
!
!
! ! !
!
! !!
!
! !
!
! ! ! !!!!
! !
!
!
!
!
!
! !
!!!
!
! !
! ! !!!!!!
! !! ! !
!
!!!! ! ! !
!!! !!!!!! ! !
!
!
! !
!!
!! !
!
!
!
!! !!
!
!
!
! ! ! !
! !
!
! !
!
!!
!
!
!!
!
!!
! !
!
!
! !
!!
!
! !
! !
! !
!
!
!
! !
!
! !!
!
!
! !
! ! ! !
!
!
!
! !
! !
!
! !
!
! !
!
! !
!
! !
!
!
!!
! !
! !
!
!
!
!
!
!! !
!
!
!!!!
!
! !
! !
!
! !
! ! ! !
!!
! !
! !!
!
!
! ! !
!
! !!
!
! ! ! !! !!!!
! ! !
!
!!!!
! !
!!
! ! !
!
!
!
! ! !
! !
!
!
! !
! !
! ! ! !
!
!
!! !! ! !!
! !
! !
! ! ! ! !
! !
!!! !
!
!! !
! !!
!
! !!
!
!
! !
!
!
! !
!
!
! !
!
! !
!
! !
!
!
! ! !
! !
! !!!
! !
!!
!! !
!
!
!
! !
!
!
! !
!
! ! !!
!
! !! ! !!
! !
! !
!
!
!!!
!
!
! !!
!
!!! !
!
!
!
!
! ! ! !
!
!
! !! !!!
!!!
!
!
! !! !!!!!!!!!
!
! !!!!!
! !! !
!
! !
!
! ! ! ! !
! !
!
!
!
!
!
! ! ! !!
!
! !! !
!
!
!
!
!
!! !
!
!
!
! ! !
!
!!!
!
!!
!
!
!
! ! ! !
! !
! !
! !
!
! !
!
!
! !
!
!
!!!
!
!
!
!
!
!
!
! !
!
!! !
!
!
!
!! !
!
! !
!
!
! !! !!!!!
!
! !
! !!
!
!!!
! ! !
! ! !!
! !
!! !
!! ! !
!
!
! !
!
! !
!!
! !
! ! !
!
! !
!
! !!
!
! !!!
! !
!
!
!
!
!
!!
!! !
! ! !
!
!!! !
! !
!
!
!!
!
!
! ! !!
!
!!!! !! !!
!
! !
! !! !!! ! !!
!
! !
!
!
! ! !
!
! !
!
!
!
!
! !
!
!! !
!
!
!!!! !!!
! !
!
!!
!
!
!
!
!
! !
! !
! !
!
! ! !
! ! !
!
!
!
!!!!
!
! !
! ! !
!
!
! !
!
!
!
!
! !
!
!!! !
!!
!
!!
! !
!!! !
!
!
!
!! ! !
!
! ! !! !!!
!
!
! ! !!
!
! !
!! !!!! !
! ! !
!
!
!
!
! !
!
! !
!
! ! !! !!
!
! !
!
! !!! !
! !
!
!
! ! !
! !
! ! !
!
! !
!
! !
!!
!!!
! !!!!!!! !
!
! !
!!
!
!
! !
! !
!
!! ! !
!
!!
!
!
!!!
!
!
! !
! !
! !
! !
! !!
! !
!
!!
!
!
!
! ! ! !
!
!
! !
! ! !
!!
!!!!
!
! !! !
!
!
!!
! !!
!
! !!
!!
! !
!
! !
! !
!
! ! !!! ! !
!
! ! !
! !
!
! ! !
! !
! !
! !
! ! ! !
! ! !!! !
!
!
! !
!
! !! !
!!!!!!! ! !
!
!
! !
!
!
!
!
!
!
!
! !!
! !
!!! !!
! ! !
!
!
! !
! !
! !
!!
! ! !!
! !!
!
!
!
!
!!
! !
!
! ! !
!
! !!
!!! !
!
!! !!
!!! !
!
! ! !
! !
! !
!
! ! !
!! ! ! !
!
!
! !
! !!!
!
!
! !! !
! !
!!!! !! !!!
!!!!!
!!!
! ! !
! ! ! ! !
! ! !
!
! ! ! !
!! !
!
! ! !!!!
!!
!
! !
!
!
! !
! ! !
! !
! !
! !
!
!
!!
!
!
!
!
!
!
! !
!
! !!
! ! !! !
! !! !
! !
!
!
!
! !! !!
!
!
!
! !! !
!
! ! !!
! !
!!
! !
! !
!
!!!
!!! ! !
! !
! !
!!!!!! !
! !
!!
! ! !! !
!!!!
!
!
!
!
! !!
!
!! !! !
!
!
! ! !!
!
!!
! !!
!
! ! !
!
!!! ! !! !
! !
!
! ! ! !
!
!!
! ! !!!
! !!! !!
!!!
!
!
!
! !
! ! ! !
! !
!!
!
!
! !! !
! !!!!
! ! !
!
! !
!
!
!!
!
!
!
! ! !! ! !
!
!
! !
! !
!
! ! !! !
! !! !! ! !! !
! !!
!!
!!
!
! !!
!
! !
!
! !
! !
!
! !
!!! ! !
! !
! !
!
!
!! !
! !!! ! !
! ! !
! !!!!!!
!
!!!!
!
!
!
!
! ! !
!!
! !!
!! !
! ! !
!!!
!! !!
!
!!
!
! ! !
!
!
! !
!!
! !
! ! !!
!
!
!
!! !
!
!
! !
! !
!
! !! !
!!!! !!!!!!! !
! ! !
! !
!
! ! !! !
! ! ! !!
!
! !! ! ! !
! !
! !
! !
! !
!
!
! !! !
!!
!!! ! !
!!
!
!
!
!!
! !! !
!
! !
!!!!
!!
!!
!!
! !
!
!
! !!! !! !! !!! !! !
! !
!
! ! !
!!!!!
!
!!
!!!!! ! !
!! !
! !
!
! !! !!
!
!
!
! !
!
!
! !
!
! ! !!
!
! ! !
!
! ! ! !
!
!
!!! !
!
! !!
! !
! ! !
! ! !
! !! !
!
! ! !!! ! ! ! !
! !
!
!
! !!
!
!! !
! !
! !
!
! ! !
!
! !
!
!
! !!
!
!! !
!
!
!! !!! !! !! ! ! !
!
! !!
! ! ! ! !! !! !
!
!! ! !
! ! !
!
!
!
!
!
! !
!
!
!!
!! ! !
! !!!!!!
!!!!! !
! !
! !
!
!
!
!
!!! ! !
!
! !
!
!
!!!
!!!
! ! ! !
!!!!
!!
!
!
!
!
!!!!! ! !
!
!
!
!
! ! ! !
! !!
!
!
!! !! ! ! !!!
! !
!!
!
! ! !
!
! !
!
!!
! !
!!
! !!
!
!!! !!!!
!!
! ! ! !
!
!
!
!
! !
!! !
! ! ! !
!
! !!!
!!!! !
! !
!
! !
! !
!
!
!
! ! !!
! !
!
! !
!
!
! !
! !
! ! !
!
!
! !
!
!
! !
! !
! ! !!!!!
! !!!!! ! !
!!!
! ! !
!
!!! ! ! !! !
!!!!
!
!
!!! !
! !
!
!!
!!
!!
! !
! !
! !
!
!!! !
!! !
!
!
! !!!!
!
!
! ! !
!! !
! !
!
!
! !! !!!!!! ! !
!
! !
!!
!
!! ! !
! !
! !
! !
!
! !
!
!
!
! !
! !
!
!
!
!
!
!!
! !!
! !!
!!!
! !!!
!
!
!
!
! ! !
! !
!!!
! !
! !!
! !
!
! ! ! !
!
! ! ! !
! ! !!!!
!!
!!
! ! !! !
!!
!!
! !
!!! ! ! ! ! !
!!!
!
!
!!
!
!
! !!
! !!
! ! !
!
!
! !
!
! ! !
!!
! ! !
!
! ! !
!
!!
! !!
!
!
!
! !
!
! !
!
! ! !
! !
!!
! !! ! !! !
!! ! !
! !
!
!
!! !
!
! !
! !
!
! !!!
!
! !
!!! !
!
!
!
!
!!! !
!
! !
!
!
!
!
! ! ! !
!
!
!!
! ! !
!
!!! !
!!
!!
! !
!!
! ! !
!
!
! !
!
!
!!
!
!
!!!
!
!
!
!
!!
! !
!
!
!
!
! !
!!
! ! !
!! !
! !!
!
! !
!!!!
! !! !! !!!!! !
!
! !
! !
!
!
! !
! !
! !
! !
!
! !
!
!
!
! !
! ! !! !
!
! !
!
! !
!
!
! !
!
!
!
!!
! !
!
!
! !
! !
!!!
! ! !
!
!
!
!
!
!
!
!
!! ! ! ! !
!
! ! !
!
!!
!
! !
!
!
! !
!
!
!!!
!
!
! !
!
!
! !!
!
! ! !
!
!
! !
! !
!
!
!
!
!
! ! !
!!
! ! !
! ! ! ! !
!
!
!
!
! !
!
!
!
!
! !! !
!
!
!
!
! !
!!
!
!
!
!
!!
!
!
! !
! !
!
! !
!
! !
!
!
! ! !
!
!
!!
! !
!
!
!
!
!
!
! !
!
!
!
! !
!
!
!
!
!
!
!
!
!
Point Arena
!
Gualala !
!
!
!
!
!
!
!
!
!
!
!
!
Russian River
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
Pacific Ocean
LegendTechn
Figure 8Region 3 - Point Arena to Cambria (Central California)Windspeed 8.375 Transmission Line (kV)
Nevada Utah Technical Constraints7.375 8.625 60 kV7.625 8.875
!
ically Suitable Area (Depth + SLC)on AreaRegi Sources: Cierco, NOAA, CEC, 2021
Cape MendocPoint ArenaCambri to Po
mum Dept
ino to Point Arena o Cambri
69 kV!
115 kV!
230 kV a CiCADEMA Pro
7.875 9.1258.125 9.375
t ercoject
a Californii Concep
-50) it
( ta n
h on !
UTM Zone 11 NorthDat : NAD 1983
Mini AriI zonaum 0 10 20 June 07, 2021 Miles
-[ZJ
,L]
□
!
#
#
##
#
###
!
! !
!
!
!
!
!
!
! ! !
!
!
!
!
! !
!
!
!!
!!
!
!
!
! !
! !
! !
!
!!
!!
!
!!
!!
!
! ! !
! !
!
!
! !
!
!
! ! !
! ! ! ! ! !
! !
!!
! !
!
! ! !!
!
! ! !
!
!
!
!
! ! !
! !
!
! ! !
!
! ! !!! !
! !
! !
!! ! !!
! !
!
! !!
!!!
! !
!
!
!
!
!
!
! !
!! !
!
!
!
!
!
!
!
!
! !!
!
! !
!! !
! !! !!
!!
!
!
! !
!! !
!
! !
!!!!
!!!
!
!
! ! ! ! !
!! ! !
!
!
! ! !
!
!
! ! ! ! !
!
!
! !
! ! ! ! ! !
!!
!
!!!!
!
! !
!
!
! !
!
!!
!
! !
! ! !
! !!
!
!! !
!
! !
!
!! !
!
!
!
!
!
! !!!
!
! ! !
!
! !
!
! ! !
!
! !
!
!
! ! !
!
!
! !!
! ! ! !
!! !!!
!
! !
!
!
! !
! !
! ! !
!
!
!!
! !!
!
!! ! !! !
!
! !
!
! !!!
! !! !!
!! ! ! !
! ! !!
!
!
!
!
!!! ! ! !
!!
!
!
!!! !
! !!!
!
! ! !!!!
!
!
!
!
!
!
!
!!!
!!! !
! !
!! !!!
!! !! !
!
!
! ! !
!
!
! !!!
!!!!!
! ! ! !! !
!
! ! !
!!!
!
!
!
! ! !
!
!
! !
!
!
!!
!!! ! !
!
! ! !
!
!
!
!
! !
!!
!
!
!
!
! ! !
!
! !
! !
!
!! !
! !
!
! ! !!! ! !
! ! ! !
! !
! ! !
!
!!! ! ! !! !! !
!
!
!!
! !
! ! !
!
!
! ! !
!
! !!
!
! !
!
! ! ! !!!!
! !
!
!
!
!
!
! !
!!!
!
! !
! ! !!!!!!
! !! ! !
!
!!!! ! ! !
!!! !!!!!! ! !
!
!
! !
!!
!! !
!
!
!
!! !!
!
!
!
! ! ! !
! !
!
! !
!
!!
!
!
!!
!
!!
! !
!
!
! !
!!
!
! !
! !
! !
!
!
!
! !
!
! !!
!
!
! !
! ! ! !
!
!
!
! !
! !
!
! !
!
! !
!
! !
!
! !
!
!
!!
! !
! !
!
!
!
!
!
!! !
!
!
!!!!
!
! !
! !
!
! !
! ! ! !
!!
! !
! !!
!
!
! ! !
!
! !!
!
! ! ! !! !!!!
! ! !
!
!!!!
! !
!!
! ! !
!
!
!
! ! !
! !
!
!
! !
! !
! ! ! !
!
!
!! !! ! !!
! !
! !
! ! ! ! !
! !
!!! !
!
!! !
!!
!
! !
! !
!
!
!
! !
!
!
!
!
! ! !
!
! !
!
! !
!
!
! ! !
! !
! !!!
! !
!!
!! !
!
!
!
! !
!
!
! !
!
! ! !!
!
! !! ! !!
! !
! !
!
!
!!!
!
!
! !!
!
!!! !
!
!
!
!
! ! ! !
!
!
! !! !!!
!!!
!
!
! !! !!!!!!!!!
!
! !!!!!
! !! !
!
! !
!
! ! ! ! !
! !
!
!
!
!
!
! ! ! !!
!
! !! !
!
!
!
!
!
!! !
!
!
!
! ! !
!
!!!
!
!!
!
!
!
! ! ! !
! !
! !
! !
!
! !
!
!
! !
!
!
!!!
!
!
!
!
!
!
!
! !
!
!! !
!
!
!
!! !
!
! !
!
!
! !! !!!!!
!
! !
! !!
!
!!!
! ! !
! ! !!
! !
!! !
!! ! !
!
!
! !
!
! !
!!
! !
! ! !
!
! !
!
! !!
!
! !!!
! !
!
!
!
!
!
!!
!! !
! ! !
!
!!! !
! !
!
!
!!
!
!
! ! !!
!
!!!! !! !!
!
! !
! !! !!! ! !!
!
! !
!
!
! ! !
!
! !
!
!
!
!
! !
!
!! !
!
!
!!!! !!!
! !
! !!
!
!!
!
!
!
!
!
! !
! !
! !
!
! ! !
! ! !
!
!
!
!
!
! !
! ! !
!
!
! !
!
!
!
!
! !
!
!!! !
!!
!
!!
! !
!!! !
!
!
!
!! ! !
!
! ! !! !!!
!
!
! ! !!
!
! !
!! !!!! !
! ! !
!
!
!
!
!!!
! !
!
! !
!
! ! !! !!
!
! !
!
! !
! !
!
!
! ! !
! !
! ! !
!
! !
!
! !
!!
!!!
! !!!!!!! !
!
! !
!!
!
!
! !
! !
!
!! ! !
!
!!
!
!
!!!
!
!
! !
!
!
!
! !
! !
! !!
! !
!
!!
!
!
!
! ! ! !
!
!
! !
!
! ! !
!!
!!!!
!
! !! !
!
!
!!
! !!
!
! !!
!!
! !
!
! !
! !
!
! !!! ! !
!
! ! !
! !
!
! ! !
! !
! !
! !
! ! ! !
! ! !!! !
!
!
! !
! !! !
!!!!!!! ! !
!
!
! !
!
!
!
!
!
!
!
! !!
! !
!!! !!
! ! !
!
!
! !
! !
! !
!!
! ! !!
! !!
!
!
!
!
!!
! !
!
! ! !
!
! !!
!!! !
!
!! !!
!!! !
!
! ! !
! !
! !
!
! ! !
!! ! ! !
!
!
! !
!
!
!!!
!
!
! !! !
! !
!!!! !! !!!
!!!!!
!!
! ! !
! ! ! ! !
! ! !
!
! ! ! !
!! !
!
! ! !!!!
!!
!
! !
!
!
! !
! ! !
! !
! !
! !
!
!
!!
!
!
!
!
!
!
! !
!
! !!
! ! !! !
!
!
!! ! ! !
!
!
!
!! !!
!
!
!
! !! !
!
! ! !!
! !
!!
! !
! !
!
!!!
!!! ! !
! !
! !
!!!!!! !
! !
!!
! ! !! !
!!!!
!
!
!
!
! !!
!
!! !! !
!
!
! ! !!
! ! !!
!
! ! !
!
!!! ! !! !
! !
!
! ! ! !
!
!!
! ! !!!
! !!! !!
!!!
!
!
!
! !
! ! ! !
! !
!!
!
!
! !! !
! !!!!
! ! !
!
! !
!
!
!!
!
!
!
! ! !! ! !
!
!
! !
! !
!
! ! !! !
! !! !! ! !! !
! !
!!!
!!
!
! !!
!
! !
!
! !
! !
!
! !
!!! ! !
! !
! !
!
!
!! !
!!
! !!! ! !
! ! !
! !!!!!!
!
!!!!
!
!
!
!
! ! !
!!
! !!
!! !
! ! !
!!!
!! !!
!
!!
!
! ! !
!
!
! !
!!
! !
! ! !!
!
!
!
!! !
! ! !
! !
!
! !! !
!!!! !!!!!!! !
! ! !
! !
!
! ! !! !
! ! ! !!
!
! !! ! ! !
! !
! !
! !
! !
!
!
! !! !
!!
!!! ! !
!!
!
!
!
!!
! !! !
!
! !
!!!!
!!
!!
!!
! !
!
!
! !!! !! !! !!! !! !
! !
!
! ! !
!!!!!
!
!!
!!!!! ! !
!! !
! !
!
! !! !!
!
!
!
! !
!
!
! !
!
! ! !!
!
! ! !
!
! ! ! !
!
!
!!! !
!
! !!
!
! ! !
! ! !
! ! !! !
!
! ! !!! ! ! ! !
! !
!
!
! !!
!
!! !
! !
! !
!
! ! !
!
! !
!
!
! !!
!
!! !
!
!
!! !!! !! !! ! ! !
!
! !!
! ! ! ! !! !! !
!
!! ! !
! ! !
!
!
!
!
!
! !
!
!
!!
!! ! !
! !!!!!!
!!!!! !
! !
! !
!
!
!
!
!!! ! !
!
! !
!
!
!!!
!!!
! ! ! !
!!!!
!!
!
!
!
!
!!!!! ! !
!
!
!
!
! ! ! !
!
! !!
!
!
!! !! ! ! !!!
! !
!!
!
! ! !
!
! !
!
!!
! !
!!
! !!
!
!!! !!!!
!!
! ! ! !
!
!
!
!
! !
!! !
! ! ! !
!
! !!!
!!!! !
! !
!
! !
! !
!
!
!
! !
!
!!
! !
!
! !
!
! !
! !
! ! !
!
!
! !
!
! !
! !
! ! !!!!!
! !!!!! ! !
!!!
! ! !
!
!!! ! ! !! !
!!!!
!
!
!!! !
! !
!
!! !!
! !
! !
! !
!
!!! !
!! !
!
!
! !!!!
!
!
! ! !
!! !
! !
!
!
! !! !!!!!! ! !
!
! !
!!
!
!! ! !
! !
!
!
!
! !
!
! !
!
!
!
! !
! !
!
!
!
!
!!
! !!
! !!
!!!
! !!!
!
!
!
!
! ! !
! !
!!!
! !
! !!
! !
!
! ! ! !
!
! ! ! !
! ! !!!!
!
!! !
!!
!!
! !
!!! ! ! ! ! !
!!!
!
!
!!
!
!
! !!!
!
! !!
!
!! ! !
!
!
! !
! ! !
!!
! ! !
! !
! ! !
!
!!
! !!
!
!
!
! !
! !
! !
!
! ! !
! !
!!
! !! ! !! !
!
!! ! !
! !
!
!
!! !
!
! !
! !
!
! !!!
!
!
!
!
!
!!! !
!
!
!
!!! !
!
! !
!
!
!
!
! ! ! !
!
!
!!
! ! !
!
!!! !
!!
!!
! !
!!
! ! !
!
!
! !
!
!
!
!!
!
!
!!!
!
!
!
!
! !!
! !
! !!
!
!
!
! !
!!
! ! !
!! !
! !!
!
! !
!!!!
! !! !!!!!! !
!
!
! !
!
!
! !
! !
! !
! !
!
! !
!
!
!
! !
! ! !! !
!
! !
!
! !
!
!
! !
!
!
!
!!
! !
!
!
! !
! !
!!!
! ! !
!
!
!
!
!
!
!
!
!! ! ! ! !
!
! ! !
!
!!
!
! !
!
!
! !
!
!
!!!
!
!
! !
!
!
! !!
!
! ! !
!
!
! !
! !
!
!
!
!
! ! !
!!
! ! !
! ! ! ! !
!
!
!
!
! !
!
!
!
!
! !! !
!
!
!
!
! !
!!
!
!
!
!
!!
!
!
! !
! !
!
! !
!
! !
!
!
! ! !
!
!
!!
! !
!
!
!
!
! !
!
!
!
!
!
! !
!
!
!
!
!
#
!
!
!
!
## Point Arena
#
!
Gualala !
!
!
!
!
!
!
!
!
!
!
!
!
Russian River
!
!
!
#
#
# !
# ##
!
# !
# !
# !
#
#
#
!
# #
!
!
!
!
## !
#
#
!
!
#
Pacific Ocean #
#
# #
#
#
Legend#Vi
Figure 9Federal Protected Area Sources: Cierco, NOAA, CEC, Region 3 - Point Arena to Cambria (Central California)
Califronia, Offshore Wind Dat n, Utah Protected and Sensitive AreasState Protected AreaCoast l Tribal Lands
ta Points State of abasi NevadaESRI, 2021Technically Suitable Area (Depth + SLC)Region Area
a Ci
CADEMA Pro Mini
Transm mum Depission Li
th (-50)(kV) erco
jectCape Mendocino to Point ArenaPoint Arena to Cambri
Californiane UTM Zone 11 NorthDat : NAD 1983
60 kV69 kV
ArizonaIaConcep
!
Cambria to PoiPark Boundary
it t umn on 0 10 20!
115 kV !
!
230 kV June 07, 2021 Miles
- D D
[ZJ -a CJ [21
--
!
!
! !
!
!
!
!
!
!
! ! !
!
!
!
!
! !
!
!
!!
!!
!
!
!
! !
! !
! !
!
!!
!!
!
!!
!!
!
! ! !
! !
!
!
! !
!
!
! ! !
! ! ! ! ! !
! !
!!
! !
!
! ! !!
!
! ! !
!
!
!
!
! ! !
! !
!
! ! !
!
! ! !!! !
! !
! !
!! ! !!
! !
!
! !!
!!!
! !
!
!
!
!
!
!
! !
!! !
!
!
!
!
!
!
!
!
! !!
!
! !
!! !
! !! !!
!!
!
!
! !
!! !
!
! !
!!!!
!!!
!
!
! ! ! ! !
!! ! !
!
!
! ! !
!
!
! ! ! ! !
!
!
! !
! ! ! ! ! !
!!
!
!!!!
!
! !
!
!
! !
!
!!
!
! !
! ! !
! !!
!
!! !
!
! !
!
!! !
!
!
!
!
!
! !!!
!
! ! !
!
! !
!
! ! !
!
! !
!
!
! ! !
!
!
! !!
! ! ! !
!! !!!
! !
! !
!
!
!
! !
! ! !
!
!
!!
! !!
!
!! ! !! !
!
! !
!
! !!!
! !! !!
!! ! ! !
! ! !!
!
!
!
!
!!! ! ! !
!!
!
!
!!! !
! !!!
!
! ! !!!!
!
!
!
!
!
!
!
!!!
!!! !
! !
!! !!!
!! !! !
!
!
! ! !
!
!
! !!!
!!!!!
! ! ! !! !
!
! ! !
!!!
!
!
!
! ! !
!
!
! !
!
!
!!!! !
! !
!
! ! !
!
!
!
!
! !
!!
!
!
!
!
! ! !
!
! !
! !
!
!! !
! !
!
! ! !!! ! !
! ! ! !
! !
! ! !
!
!!! ! ! !! !! !
!
!
!!
! !
! ! !
!
!
! ! !
!
! !!
!
! !
!
! ! ! !!!!
! !
!
!
!
!
!
! !
!!!
!
! !
! ! !!!!!!
! !! ! !
!
!!!! ! ! !
!!! !!!!!! ! !
!
!
! !
!!
!! ! !
! !
!! !!
!
!
!
! ! ! !
! !
!
! !
!
!!
!
!
!!
!
!!
! !
!
!
! !
!!
!
! !
! !
! !
!
!
!
! !
!
! !!
!
!
! !
! ! ! !
!
!
!
! !
! !
!
! !
!
! !
!
! !
!
! !
!
!
!!
! !
! !
!
!
!
!
!
!! !
!
!
!!!!
!
! !
! !
!
! !
! ! ! !
!!
! !
! !!
!
!
! ! !
!
! !!
!
! ! ! !! !!!!
! ! !
!
!!!!
! !
!!
! ! !
!
!
!
! ! !
! !
!
!
! !
! !
! ! ! !
!
!
!! !! ! !!
! !
! !
! ! ! ! !
! !
!!! !
!
!! !
! ! !!
!
! !!
!
!
! !
!
!
!
!
! ! !
!
! !
!
! !
!
!
! ! !
! !
! !!!
! !
!!
!! !
!
!
!
! !
!
!
! !
!
! ! !!
!
! !! ! !!
! !
! !
!
!
!!!
!
!
! !!
!
!!! !
!
!
!
!
! ! ! !
!
!
! !! !!!
!!!
!
!
! !! !!!!!!!!!
!
! !!!!!
! !! !
!
! !
!
! ! ! ! !
! !
!
!
!
!
!
! ! ! !!
!
! !! !
!
!
!
!
!
!! !
!
!
!
! ! !
!
!!!
!
!!
!
!
!
! ! ! !
! !
! !
! !
!
! !
!
!
! !
!
!
!!!
!
!
!
!
!
!
!
! !
!
!! !
!
!
!
!! !
!
! !
!
!
! !! !!!!!
!
! !
! !!
!
!!!
! ! !
! ! !!
! !
!! !
!! ! !
!
!
! !
!
! !
!!
! !
! ! !
!
! !
!
! !!
!
! !!!
! !
!
!
!
!
!
!!
!! !
! ! !
!
!!! !
! !
!
!
!!
!
!
! ! !!
!
!!!! !! !!
!
! !
! !! !!! ! !!
!
! !
!
!
! ! !
!
! !
!
!
!
!
! !
!
!! !
!
!
!!!! !!!
! !
!
!!
!
!
!
!
!
! !
! !
! !
!
! ! !
! ! !
!
!
!
!!!!
!
! !
! ! !
!
!
! !
!
!
!
!
! !
!
!!! !
!!
!
!!
! !
!!! !
!
!
!
!! ! !
!
! ! !! !!!
!
!
! ! !!
!
! !
!! !!!! !
! ! !
!
!
!
!
! !
!
! !
!
! ! !! !!
!
! !
!
! !!! !
! !
!
!
! ! !
! !
! ! !
!
! !
!
! !
!!
!!!
! !!!!!!! !
!
! !
!!
!
!
! !
! !
!
!! ! !
!
!!
!
!
!!!
!
!
! !
! !
! !
! !
! !!
! !
!
!!
!
!
!
! ! ! !
!
!
! !
! ! !
!!
!!!!
!
! !! !
!
!
!!
! !!
!
! !!
!!
! !
!
! !
! !
!
! ! !!! ! !
!
! ! !
! !
!
! ! !
! !
! !
! !
! ! ! !
! ! !!! !
!
!
! !
!
! !! !
!!!!!!! ! !
!
!
! !
!
!
!
!
!
!
!
! !!
! !
!!! !!
! ! !
!
!
! !
! !
! !
!!
! ! !!
! !!
!
!
!
!
!!
! !
!
! ! !
!
! !!
!!! !
!
!! !!
!!! !
!
! ! !
! !
! !
!
! ! !
!! ! ! !
!
!
! !
! !!!
!
!
! !! !
! !
!!!! !! !!!
!!!!!
!!!
! ! !
! ! ! ! !
! ! !
!
! ! ! !
!! !
!
! ! !!!!
!!
!
! !
!
!
! !
! ! !
! !
! !
! !
!
!
!!
!
!
!
!
!
!
! !
!
! !!
! ! !! !
! !! !
! !
!
!
!
! !! !!
!
!
!
! !! !
!
! ! !!
! !
!!
! !
! !
!
!!!
!!! ! !
! !
! !
!!!!!! !
! !
!!
! ! !! !
!!!!
!
!
!
!
! !!
!
!! !! !
!
!
! ! !!
!
!!
! !!
!
! ! !
!
!!! ! !! !
! !
!
! ! ! !
!
!!
! ! !!!
! !!! !!
!!!
!
!
!
! !
! ! ! !
! !
!!
!
!
! !! !
! !!!!
! ! !
!
! !
!
!
!!
!
!
!
! ! !! ! !
!
!
! !
! !
!
! ! !! !
! !! !! ! !! !
! !
!!!
!!
!
! !!
!
! !
!
! !
! !
!
! !
!!! ! !
! !
! !
!
!
!! !
! !!! ! !
! ! !
! !!!!!!
!
!!!!
!
!
!
!
! ! !
!!
! !!
!! !
! ! !
!!!
!! !!
!
!!
!
! ! !
!
!
! !
!!
! !
! ! !!
!
!
!
!! !
!
!
! !
! !
!
! !! !
!!!! !!!!!!! !
! ! !
! !
!
! ! !! !
! ! ! !!
!
! !! ! ! !
! !
! !
! !
! !
!
!
! !! !
!!
!!! ! !
!!
!
!
!
!!
! !! !
!
! !
!!!!
!!
!!
!!
! !
!
!
! !!! !! !! !!! !! !
! !
!
! ! !
!!!!!
!
!!
!!!!! ! !
!! !
! !
!
! !! !!
!
!
!
! !
!
!
! !
!
! ! !!
!
! ! !
!
! ! ! !
!
!
!!! !
!
! !!
!
! ! !
! ! !
! ! !! !
!
! ! !!! ! ! ! !
! !
!
!
! !!
!
!! !
! !
! !
!
! ! !
!
! !
!
!
! !!
!
!! !
!
!
!! !!! !! !! ! ! !
!
! !!
! ! ! ! !! !! !
!
!! ! !
! ! !
!
!
!
!
!
! !
!
!
!!
!! ! !
! !!!!!!
!!!!! !
! !
! !
!
!
!
!
!!! ! !
!
! !
!
!
!!!
!!!
! ! ! !
!!!!
!!
!
!
!
!
!!!!! ! !
!
!
!
!
! ! ! !
! !!
!
!
!! !! ! ! !!!
! !
!!
!
! ! !
!
! !
!
!!
! !
!!
! !!
!
!!! !!!!
!!
! ! ! !
!
!
!
!
! !
!! !
! ! ! !
!
! !!!
!!!! !
! !
!
! !
! !
!
!
!
! ! !!
! !
!
! !
!
!
! !
! !
! ! !
!
!
! !
!
!
! !
! !
! ! !!!!!
! !!!!! ! !
!!!
! ! !
!
!!! ! ! !! !
!!!!
!
!
!!! !
! !
!
!!
!!
!!
! !
! !
! !
!
!!! !
!! !
!
!
! !!!!
!
!
! ! !
!! !
! !
!
!
! !! !!!!!! ! !
!
! !
!!
!
!! ! !
! !
! !
! !
!
! !
!
!
!
! !
! !
!
!
!
!
!
!!
! !!
! !!
!!!
! !!!
!
!
!
!
! ! !
! !
!!!
! !
! !!
! !
!
! ! ! !
!
! ! ! !
! ! !!!!
! ! !! !
!!
!!
! !
!!! ! ! ! ! !
!!!
!
!
!!
!
!
! !!!
!
! !!
!
!! ! !
!
!
! !
!
! ! !
!!
! ! !
!
! ! !
!
!!
! !!
!
!
!
! !
!
! !
!
! ! !
! !
!!
! !! ! !! !
!! ! !
! !
!
!
!! !
!
! !
! !
!
! !!!
!
! !
!!! !
!
!
!
!
!!! !
!
! !
!
!
!
!
! ! ! !
!
!
!!
! ! !
!
!!! !
!!
!!
! !
!!
! ! !
!
!
! !
!
!
!!
!
!
!!!
!
!
!
!
!!
! !
!
!
!
!
! !
!!
! ! !
!! !
! !!
!
! !
!!!!
! !! !! !!!!! !
!
! !
! !
!
!
! !
! !
! !
! !
!
! !
!
!
!
! !
! ! !! !
!
! !
!
! !
!
!
! !
!
!
!
!!
! !
!
!
! !
! !
!!!
! ! !
!
!
!
!
!
!
!
!
!! ! ! ! !
!
! ! !
!
!!
!
! !
!
!
! !
!
!
!!!
!
!
! !
!
!
! !!
!
! ! !
!
!
! !
! !
!
!
!
!
!
! ! !
!!
! ! !
! ! ! ! !
!
!
!
!
! !
!
!
!
!
! !! !
!
!
!
!
! !
!!
!
!
!
!
!!
!
!
! !
! !
!
! !
!
! !
!
!
! ! !
!
!
!!
! !
!
!
!
!
!
!
! !
!
!
!
! !
!
!
!
!
!
!
!
!
!
Point Arena
!
Gualala !
!
!
!
!
!
!
!
!
!
!
!
!
Russian River
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
Pacific Ocean
LegendTechn
Figure 10nt Arena to Cambriaically Suitable Area (Depth + SLC) Black Abalone Critical Habitat Region 3 - Poi
on Area Green Sturgeon Critical Habitat Audobon, 2021 NevadaCape Mendoc Leatherback Turtle Critical Habi o Cambri l Hab
(Central California)tatsSources: Cierco, NOAA, CEC, UtahRegi Sensitive Habi
ino to Point Arena tatPoint ArenaCambri o Po
rd Areas
Steller Sea Lion Critii h -50
i CiCADEMO Pro
t tata ca ercojecti Concep
(IBA) ion Min
Transm mum Dept ( )ission Line (kV) Californiat t ta
B n
tant UTM Zone 11 NorthDat : NAD 1983 Arizonampor
Gl Iobal 60 kVState
!
69 kV!
115 kV!
230 kV
um 0 10 20 June 07, 2021 Miles!
iI
- D
,z:J
□ [ZJ
D D D D -
!
! !
!
!
!
!
!!
!
!
!!
!
!
!!
!
!
!
!!
!
!
!
!
!
!
! !
! !!
!
!
!
! ! ! ! ! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! ! ! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
!
! !
!
!
!!
!
!
!
!!
!
!
!
!
!
!
! !
! ! ! ! !! !
! ! !
! !
!
!
!
Pacific Ocean !
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
! !
!
!
!
! !
!
!
!
!
!
!
!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! ! !!
!
!
! !
!
!
!
!
!!
! !
!
!
!
!
!
!
Point Arguello
!
!
!
!
!
!
!!
!!
!
!
!
!
!
!
!
!
! ! ! !! !
LegendTechnically Suitable Area (Depth + SLC) Windspeed
Region Area 7.375Point Arena to Cambria 7.625Cambria to Point Conception 7.875Point Conception to the Mexican BorderMinimum Depth (-50)
8.125 Transmission Line (kV)8.375 ! 60 kV8.625 ! 115 kV
! 230 kV
Sources: Cierco, NOAA, CEC, 2021 UtahNevada
California Arizona
Figure 11Region 4 - Cambria to Point Conception
Technical Constraints Cierco
CADEMO ProjectUTM Zone 11 NorthDatum: NAD 1983 I 0 5 10
MilesJune 07, 2021
-,z:J
[21
[ZJ
CII
, ,
... , - '
' \ \ " ' " I
I I I I I
' I C I t
' ' ' 1 I I \
~ I I ■- ■
!
! !
!
!
!
!
! !!
!!
!
!
!
!
!
!
!
!
!!
!
!
!
!
!
!
!
! !
! !!
!
!
!
! ! ! ! ! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! ! ! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
! ! ! ! !! !
! ! !
! !
!
!
#
! !
!
!
!
!
!
!
!
!
!
!
!
! !
!
! !
!
!
!!
!
!
!
!!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
!!
!
!!
! !
!
Pacific Ocean
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! ! !
! !
!
!
! !
!
!
!
!
!
Point Arguello
!!!
!
!!
!
!
!
!
!
!
! ! ! !! !
LegendDOD Restricted Area#Vista Point Minimum Depth (-50)
Technically Suitable Area (Depth + SLC) Transmission Line (kV)Region Area ! 60 kV
Point Arena to Cambria ! 115 kVCambria to Point Conception ! 230 kVPoint Conception to the Mexican BorderFederal Protected AreaState Protected Area
Sources: Sources: Cierco, NOAA, CEC,State of Califronia, Offshore Wind Databasin,
2021 UtahNevada
California Arizona
Figure 12Region 4 - Cambria to Point Conception
Protected and Sensitive Areas Cierco
CADEMO ProjectUTM Zone 11 NorthDatum: NAD 1983 I 0 5 10
MilesJune 07, 2021
-
! !
!!
! !
!
!
!
! !
!
! !
!
!
!
! !
!
! !
! ! ! ! !
!
!
! !
!
! !
!
!
! !
!
!
!
! !
! ! ! ! !!
!
!
! !! !
! !!
! !
!
! ! ! ! ! ! !
!!
! !
! ! ! ! ! !
!
!!
!
!
!
!
! !! !!
!
! ! !
! !
!
!
!
!
!
! !
!
! !
!
!
!
!
! !
!
!
!
!
!
!
! !
!
!
!
!
!
!
!
!
!
!
!
!
!
! ! ! !
!
!
!
!
!
! !
! ! !
!
!
!
!
!
!! !
!!!!
!
!
!
!
!
! !
! !
!
!
!
! ! ! ! !
!
!
!
!
!! !
! !
! !
!
! !!
!!
!
!! !!
!!
!!
!!
!!
! !
!
! ! !!
!
! ! !
! !
! !
!
!
! ! ! ! ! !
!
!
! ! !
! ! !
!
!
Pacific Ocean
Point Arguello
LegendTechn ically Suitable Area (Depth + S LC) D Black Abalone Critical Habitat
Region Area Leatherback Turtle Criti ca l Hab itat Po int Arena to Cambria Transmission Line (kV)Cambri a to Point Concept ion ! 60 kVPoin t Concept i on to the Mex i can Border ! 115 kVMi nimum Depth (-50) ! 230 kV
Important Bird Areas (IBA )Gl oba l State
Figure 13Region 4 - Cambria to Point Conception
Sensitive Habitats Sources: Cierco, NOAA, CEC,Audobon, 2021 UtahNevada
CiCADEMO Pro
ercojectUTM Zone 11 North
Dat : NAD 1983California
ArizonaIum 0 5June 07, 2021 Miles
10
-11 ■- . -
!!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
! !!
!
! !
!
!
!!
! !
!
! !
!
! !
!
!!
!
!
!
!
! ! ! !
! !!! !
! !
! !!
!
!
! !
!
!
! ! !
!
! !
!
!
! !! ! ! !
!
!! !
!
!
!
! ! !
! ! !
!! !
! ! !!
! ! !
! ! !
! !
! !
!
!
! !! !
!!! ! !
!
!
! !! ! !!!!!
!
!
!
! !!
!
! ! ! ! !
!!! ! ! !
! ! ! !
! ! ! !
!!
!
! !
!
!
!
! !
! !
! ! ! ! !
! !!
!
!
!! ! !! !!
!!
! !
!
!!!!
!
! !
!
! !
! ! !
!
! !
!!
!! !
! ! !
!
! !
!
!
! ! !
!!
!!!!
!! !
!!
!
!
! !
!! !!
!
! !!
!
!
!
!
! ! !
! ! ! ! !
! ! ! !!
! ! !
!
!
!!
!!
!
!!
!
!
!!
!
!
! ! !
! !
!
!
! !!
!
!
!
!
!
!
!
! !
! !!!! !
!
! ! !
! ! !
!
! ! !
! !
!
!
! ! ! !
!
!
!
!
!
!
! !
!
! !
!
!
!
! !! !
!
!
!
!
!!
!
! !
!
!
!!
!!
!
! ! !
! !
!
! !
!
! ! !
!
!
!
!!
! !!
!
!
!
!
! !
!
!! !
! !!
!
!
!
! !
!
!
! !
!
!!
!
!
! !!!
! !
! !
!!!
!!!
! !
!
!
!
! !! !!!
!! ! !!
!
!
!!!!
! !
!! !
!
!!
! ! !!!!
! !
!
!
!! !!
!
! !!! !!
!
!!!
!
! !! !
!
!
!
!
!!
! !
!
! !
!
!
!
!
!!!
!
! !
! !!
! ! !
!
! !
! ! !
!!
! ! !
!
! ! !
!
!
!!
!!!!!
!
!
!
! !! !
!!
!!! !
!
! !
! !
!
! !
!
! !
!
!
! !
! !
! !
!
!
!!
!
!
!
!
!!!
!
! !!
!
!!!!
!! !!! !
!! ! !!!!
! ! ! !!
!! ! !
! !!
!
! !
!! ! ! !!
!
! !
!!
!! !
!!
!
!!
!
!
!
! ! !
! ! ! !
!
! !
!
! ! !! !
!! ! !
!!
!! ! !!! !!
!
!
!
! !
! !
!!!
!
! ! !!
!
! !
!
!
!!!!
!
!
!
!
!
!
!
!
!
!
!
!!
! !
!
!
! !!
!
!!
!
! !
!
!
!!
!
!
!!
! !
! ! !
!!!
!!
! !
! !
!
!
! !
!
!!
!!!! !
! !
!!
! ! !
!
!
!
!
! !!
!!!!!!!
!! ! !
!
!!
!
!!
!! !! !!
!!
!
!
!!!! !!!!!
! !
!
!
!
!
! !
!
!
! !
! !
!
!
!! !
!
!!
!!
!
!
!
!! ! !
! !!
!!
!
!
!! ! !
!
! !! ! !
!
!
!
!! !!
! !
!
!
! !
!
!
!
!!
!!
!!
!
!
!
!!! ! ! !
! !!!!!
!
! !
!
!
!
!!
!!
!
! !
! !
! ! !!
!
! ! !
! !!!!!!
!!!
!
! !
!
!
! ! !
!! !
!
!
!
!
!
!
!
!
!!!
! ! !
! !
!!
!
! ! ! !
! !
!!
!
!! !
! !
! !
! ! !
! ! ! !
!
!
!
! !!
! !
!
! ! !
!! ! !
!!! !
!!
!
!
!
! !
! !
!!
! !
!
!
!
!
! ! !
!
!
!
!
!
!
! !
!
!
! !
!
!
! !
!
!
! !
! !
! !
! !
!
!
! !
!
!
!
! ! !
! !
!
!
! !
!
!
!
!
! !
! !
!
!
!
!
!
!
! !
!!
!
!
!
!
!
!
!
!
!
!
!
!!!
!
!
!
!
!
!
! !
!
!
!!
!
!
!!
!!
!
!
!
!
!
!
!
!
!
!!
!
!
!
!
!
!
c Ocean
!
Point Arguello
!
! !
!!
!!
!
!
!
!
!
!
!
! !
!
! !
!
!
!
!
!
!!
!
!
!!
!!!
!
!
!
!
!
!
!
Pacifi
!
!
!
LegendTechn ically Suitable Area (Depth + S LC) D 7.625 Transmission Line (kV)
Regi on Area D 7.875 ! 60 kV[ZJ Cambr ia to Point Conception D 8.125 ! 69 kV □ Poi n t Concepti on to the Mexican Border D 8.375 ! 115 kVCZ) The Channel Islands 8.625 ! 230 kV
Minimum Dept h (-50) ---8.875 Wi ndspeed 9.125D 7.375 9.375
Figure 14egion 5 - Poi nt Conception to the Mexican Border
Technical ConstraintsRUtahSources: Cierco, NOAA, CEC, 2021 Nevada
a CiCADEMO Pro
ercoject Californi
UTM Zone 11 NorthDat : NAD 1983 AriI zonaum 0 10
June 07, 2021 Miles
!
20
!!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
! !!
!
! !
!
! ! !
!!
!
! !
!
! !
!
!!
!
!
!
!
! ! ! !
! !!! !
! !
! !!
!
!
! !
!
!
! ! !
!
! !
!
!
! !! ! ! !
!
!! !
!
!
!
! ! !
! ! !
!! !
! ! !!
! ! !
! ! !
! !
! !
!
!
! !! !
!!! ! !
!
!
! !! ! !!!!!
!
!
!
! !!
!
! ! ! ! !
!!! ! ! !
! ! ! !
! ! ! !
!!
!
! !
!
!
!
! !
! !
! ! ! ! !
! !!
!
!
!! ! !! !!
!!
! !
!
!!!!
!
! !
!
! !
! ! !
!
! !
!!
!! !
! ! !
!
! !
!
!
! ! !
!!
!!!!
!! !
!!
!
!
! !
!! !!
!
! !!
!
!
!
!
! ! !
! ! ! ! !
! ! ! !!
! ! !
!
!
!!
!!
!
!!
!
!
!!
!
!
! ! !
! !
!
!
! !!
!
!
!
!
!
!
!
! !
! !!!! !
!
! ! !
! ! !
!
! ! !
! !
!
!
! ! ! !
!
!
!
!
!
!
! !
!
! !
!
!
!
! !! !
!
!
!
!
!!
!
! !
!
!
!!
!!
!
! ! !
! !
!
! !
!
! ! !
!
!
!
!!
! !!
!
!
!
!
! !
!
!! !
! !!
!
!
!
! !
!
!
! !
!
!!
!
!
! !!!
! !
! !
!!!
!!!
! !
!
!
!
! !! !!!
!! ! !!
!
!
!!!!
! !
!! !
!
!!
! ! !!!!
! !
!
!
!! !!
!
! !!! !!
!
!!!
!
! !! !
!
!
!
!
!!
! !
!
! !
!
!
!
!
!!!
!
! !
! !!
! ! !
!
! !
! ! !
!!
! ! !
!
! ! !
!
!
!!
!!!!!
!
!
!
! !! !
!!
!!! !
!
! !
! !
!
! !
!
! !
!
!
! !
! !
! !
!
!
!!
!
!
!
!
!!!
!
! !!
!
!!!!
!! !!! !
!! ! !!!!
! ! ! !!
!! ! !
! !!
!
! !
!! ! ! !!
!
! !
!!
!! !
!!
!
!!
!
!
!
! ! !
! ! ! !
!
! !
!
! ! !! !
!! ! !
!!
!! ! !!! !!
!
!
!
! !
! !
!!!
!
! ! !!
!
! !
!
!
!!!!
!
!
!
!
!
!
!
!
!
!
!
!!
! !
!
!
! !!
!
!!
!
! !
!
!
!!
!
!
!!
! !
! ! !
!!!
!!
! !
! !
!
!
! !
!
!!
!!!! !
! !
!!
! ! !
!
!
!
!
! !!
!!!!!!!
!! ! !
!
!!
!
!!
!! !! !!
!!
!
!
!!!! !!!!!
! !
!
!
!
!
! !
!
!
! !
! !
!
!
!! !
!
!!
!!
!
!
!
!! ! !
! !!
!!
!
!
!! ! !
!
! !! ! !
!
!
!
!! !!
! !
!
!
! !
!
!
!
!!
!!
!!
!
!
!
!!! ! ! !
! !!!!!
!
! !
!
!
!
!!
!!
!
! !
! !
! ! !!
!
! ! !
! !!!!!!
!!!
!
! !
!
!
! ! !
!! !
!
!
!
!
!
!
!
!
!!!
! ! !
! !
!!
!
! ! ! !
! !
!!
!
!! !
! !
! !
! ! !
! ! ! !
!
!
!
! !!
! !
!
! ! !
!! ! !
!!! !
!!
!
!
!
! !
! !
!!
! !
!
!
!
!
! ! !
!
!
!
!
!
!
! !
!
!
! !
!
!
! !
!
!
! !
! !
! !
! !
!
!
! !
!
!
!
! ! !
! !
!
!
! !
!
!
!
!
! !
! !
!
!
!
!
!
!
! !
!!
!
!
!
!
!
!
!
!
!
!
!
!!!
!
!
!
!
!
# !
! !
!
!
!!
!
!
!!
!!
!
!
!
!
!
!
!
!
!
!!
!
!
!
!
!
!
c Ocean
!
Point Arguello #
##
!
! !
!!
!!
!
!
!
!
!
!
!
! !
!
! !
!
!
!
!
!
!!
!
!
!!
!!!
!
!
!
#
!
!
!
!
Pacifi
!
!
!
!
Legend# Minimum Depth (-50) Vi s ta Point Transmission Line (kV)
Technically Suitable Area (Depth + S LC) ! 60 kV Region Area ! 69 kV
Cambria to Point Conception ! 115 kVPoi n t Concepti on to the Mex i can Border ! 230 kV The Channel I s l andsFederal Protected Area State Protected Area Coastal Tribal Lands
Figure 15Region 5 - Point Conception to the Mexican Border
Protected and Sensitive AreasSources: Sources: Sources: Cierco, NOAA, CEC, St ia, Offshore Wind Databasin, Utah2021 Nevada ate of Califron
a CiercoCADEMO ProjectCaliforni
UTM Zone 11 NorthDat : NAD 1983 AriI zonaum 0 10
June 07, 2021 Miles
20
-
-I I ■- ■
!!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
! !!
!
! !
!
! ! !
!!
!
! !
!
! !
!
!!
!
!
!
!
! ! ! !
! !!! !
! !
! !!
!
!
! !
!
!
! ! !
!
! !
!
!
! !! ! ! !
!
!! !
!
!
!
! ! !
! ! !
!! !
! ! !!
! ! !
! ! !
! !
! !
!
!
! !! !
!!! ! !
!
!
! !! ! !!!!!
!
!
!
! !!
!
! ! ! ! !
!!! ! ! !
! ! ! !
! ! ! !
!!
!
! !
!
!
!
! !
! !
! ! ! ! !
! !!
!
!
!! ! !! !!
!!
! !
!
!!!!
!
! !
!
! !
! ! !
!
! !
!!
!! !
! ! !
!
! !
!
!
! ! !
!!
!!!!
!! !
!!
!
!
! !
!! !!
!
! !!
!
!
!
!
! ! !
! ! ! ! !
! ! ! !!
! ! !
!
!
!!
!!
!
!!
!
!
!!
!
!
! ! !
! !
!
!
! !!
!
!
!
!
!
!
!
! !
! !!!! !
!
! ! !
! ! !
!
! ! !
! !
!
!
! ! ! !
!
!
!
!
!
!
! !
!
! !
!
!
!
! !! !
!
!
!
!
!!
!
! !
!
!
!!
!!
!
! ! !
! !
!
! !
!
! ! !
!
!
!
!!
! !!
!
!
!
!
! !
!
!! !
! !!
!
!
!
! !
!
!
! !
!
!!
!
!
! !!!
! !
! !
!!!
!!!
! !
!
!
!
! !! !!!
!! ! !!
!
!
!!!!
! !
!! !
!
!!
! ! !!!!
! !
!
!
!! !!
!
! !!! !!
!
!!!
!
! !! !
!
!
!
!
!!
! !
!
! !
!
!
!
!
!!!
!
! !
! !!
! ! !
!
! !
! ! !
!!
! ! !
!
! ! !
!
!
!!
!!!!!
!
!
!
! !! !
!!
!!! !
!
! !
! !
!
! !
!
! !
!
!
! !
! !
! !
!
!
!!
!
!
!
!
!!!
!
! !!
!
!!!!
!! !!! !
!! ! !!!!
! ! ! !!
!! ! !
! !!
!
! !
!! ! ! !!
!
! !
!!
!! !
!!
!
!!
!
!
!
! ! !
! ! ! !
!
! !
!
! ! !! !
!! ! !
!!
!! ! !!! !!
!
!
!
! !
! !
!!!
!
! ! !!
!
! !
!
!
!!!!
!
!
!
!
!
!
!
!
!
!
!
!!
! !
!
!
! !!
!
!!
!
! !
!
!
!!
!
!
!!
! !
! ! !
!!!
!!
! !
! !
!
!
! !
!
!!
!!!! !
! !
!!
! ! !
!
!
!
!
! !!
!!!!!!!
!! ! !
!
!!
!
!!
!! !! !!
!!
!
!
!!!! !!!!!
! !
!
!
!
!
! !
!
!
! !
! !
!
!
!! !
!
!!
!!
!
!
!
!! ! !
! !!
!!
!
!
!! ! !
!
! !! ! !
!
!
!
!! !!
! !
!
!
! !
!
!
!
!!
!!
!!
!
!
!
!!! ! ! !
! !!!!!
!
! !
!
!
!
!!
!!
!
! !
! !
! ! !!
!
! ! !
! !!!!!!
!!!
!
! !
!
!
! ! !
!! !
!
!
!
!
!
!
!
!
!!!
! ! !
! !
!!
!
! ! ! !
! !
!!
!
!! !
! !
! !
! ! !
! ! ! !
!
!
!
! !!
! !
!
! ! !
!! ! !
!!! !
!!
!
!
!
! !
! !
!!
! !
!
!
!
!
! ! !
!
!
!
!
!
!
! !
!
!
! !
!
!
! !
!
!
! !
! !
! !
! !
!
!
! !
!
!
!
! ! !
! !
!
!
! !
!
!
!
!
! !
! !
!
!
!
!
!
!
! !
!!
!
!
!
!
!
!
!
!
!
!
!
!!!
!
!
!
!
!
!
! !
!
!
!!
!
!
!!
!!
!
!
!
!
!
!
!
!
!
!!
!
!
!
!
!
!
c Ocean
!
Point Arguello
!
! !
!!
!!
!
!
!
!
!
!
!
! !
!
! !
!
!
!
!
!
!!
!
!
!!
!!!
!
!
!
!
!
!
!
Pacifi
!
!
!
!
LegendTechn ically Suitable Area (Depth + S LC) Minimum Depth (-50)
Regi on Area Transmission Line (kV) [ZJ Cambr ia to Point Conception ! 60 kV
-□ Poi n t Concepti on to the Mex i can Border ! 69 kV
-[21 The Channel I s l ands ! 115 kV Important Bird Areas (IBA) ! 230 kV
Global State
D Black Abalone Critical HabitatLeatherback Turtle Criti ca l Hab itat
Figure 16Region 5 - Point Conception to the Mexican Border
Sensitive Habitats Sources: Cierco, NOAA, CEC,Audobon, 2021 Nevada Utah
a CiCADEMO Pro
ercojectCaliforni
UTM Zone 11 NorthDat : NAD 1983 AriI zonaum 0 10 20
June 07, 2021 Miles
!
!
!
!
!
!
!
! !
! !
! !
!!
!!
!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!!!
!
!
!!! !
! !
!
!!!!
!!!
!!!
!!!
!!!
!
!
!!
!
!
!
!
!
!
!
!
! !
!
!
!
!
!
!
! !
! !
!
!
!
!
!
!
!
!
!!
!
!
!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!!
!
!!
!
!
!
!
!
!
!
!
!
!!!
!!!
!
!
!
!
!
!
!
!
!!
!
!
!
!
!!! !
!
!
!
!
!
!
!
!
!
!
! !
!!
!
!
!!
!
!
!
!!
!
!!!
!!!
!
!
!!!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!! !!
PointArguello
Arizona California
Nevada Utah Legend
Technically Suitable Area (Depth + S LC) Windspeed
---8.625 Transmission Line (kV)
Region Area D 7.375 8.875 ! 60 kV iz::::J Cambria to Point Conception D 7.625 9.125 ! 69 kV r::::zl Point Conception to the Mexican Border D 7.875
-9.375 ! 115 kV
[ZJ The Channel Islands D 8.125 9.625 ! 230 kV Minimum Depth (-50) CJ 8.375 9.875
0 10 20 Miles
Figure17Region6– TheChannelIslands
TechnicalConstraintsCierco
CADEMOProject
June 07, 2021 IUTM Zone 11 North
Datum: NAD 1983
Sources: Cierco, NOAA, CEC, 2021
Pacific Ocean
- --11 ■- .
-[ZJ
iz::::J [21
CII
l
!!
!
!
!
!
!
!
!
!
!
!
! !
!
!
!
!
!
!
!
!
!
!
!
!! !!
!
!!
!!
!
!! ! !
!
!
! !
!
! !
!
! ! ! !
!
!
!
!!
!
!
!
!!
!
!
! !!
!
!
!
! !
! !
!
! ! !
!!!
!
!
!!!
!
!
!! !
! !!
!
!!! !!!
!
!
! !!
!!
!
! !!! !!
!
! !
!! !!
!
!! ! !!
!!!!
! !
! !
!
!
!
! !!
! !
!
!
!
!
!
!!!! ! !
!
!
!!
!
!
!
!
! !
!
!!!
!
!
!
!!
! !!!!
! !!!
!! !
! !!!!
!
! !
!
!
!
! !!
!
!!!!! !
!
!
!
!
!
# PointArgu elo #
#
!
!
!!
!
!
Pacific Ocean
Figu re18LegendCoastal Tribal Lands Region6–TheChannelI#Vista Point Minimum Depth (-50) S ia, Offshore Wind Databasin, Utah2021 Nevada ProtectedandSensitiveAr
Transmission Line (kV)
slandseas
Sources: Sources: Cierco, NOAA, CEC,e of Califrontat
Technically Suitable Area (Depth + SLC)Region Area Cier60 kV co!
CaliforniaCambria to Point ConceptiPoi to the Mex
69 kV!
115 kV UTM Zone 11 North!
230 kV Dat : NAD 1983 CADEMOProjecton
int ConceptionI l
can Border ArizonaIThe ChanneFederal ProS
l andsed Area
ed Area
ums 0 10!
tect tate Protect June 07, 2021 Miles
20
!
!
!
!
!
!
!
! !
! !
! !
!!
!!
!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!!!
!
!
!!! !
! !
!
!!!!
!!!
!!!
!!!
!!!
!
!
!!
!
!
!
!
!
!
!
!
! !
!
!
!
!
!
!
! !
! !
!
!
!
!
!
!
!
!
!!
!
!
!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!!
!
!!
!
!
!
!
!
!
!
!
!
!!!
!!!
!
!
!
!
!
!
!
!
!!
!
!
!
!
!!! !
!
!
!
!
!
!
!
!
!
!
! !
!!
!
!
!!
!
!
!
!!
!
!!!
!!!
!
!
!!!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!! !!
PointArguello
Arizona California
Nevada Utah Legend
Technically Suitable Area (Depth + SLC)Region Area
Cambria to Point ConceptionPoint Conception to the Mexican BorderThe Channel Islands
Important Bird Areas (IBA)GlobalState
Black Abalone Critical HabitatLeatherback Turtle Critical HabitatMinimum Depth (-50)
Transmission Line (kV) ! 60 kV ! 69 kV ! 115 kV ! 230 kV 0 10 20
Miles
Figure19Region6–TheChannelIslands
SensitiveHabitatsCierco
CADEMOProject
June 07, 2021 IUTM Zone 11 North
Datum: NAD 1983
Sources: Cierco, NOAA, CEC,Audobon, 2021
Pacific Ocean
---C!I
-·
.
~/2 /,,0}; ,. .. . /,
~
Vandenberg SMR
Point Arguello
Point Conception SMR
Pacific Ocean
Legend Important Bird Areas (IBA)
CADEMO Turbine Location GlobalState
Technically Suitable Area (Depth + SLC) Leatherback Turtle Critical HabitatRegion Area DOD Restricted Zone
Cambria to Point Conception Minimum Depth (-50)Point Conception to the Mexican Border State Protected Area
Sources: Cierco,State of Califronia, 2021 Utah Nevada
California Arizona
Figure 20 Point Arguello Detailed Constraints
CiercoCADEMO Project UTM Zone 11 North
Datum: NAD 1983 I 0 2 4 Miles June 07, 2021