Supplemental Drawings
p r e s e n t a t i o n
April 18, 2007 eu:a eppstein uhen architects 2
Presentation Outline
Supplemental Drawings
ADT Process
Revit Demonstration
Construction Bulletins
April 18, 2007 eu:a eppstein uhen architects 3
Supplemental Drawings
Supplemental Drawings:
The graphic deliverable to identify revisions.
Included with front-end documentation which describes the revision.
Revisions:
Modifications, clarifications, or interpretations made to the Construction Documents
Bidding Phase:
Addendum
Construction Administration:
Construction Bulletin (CB)
April 18, 2007 eu:a eppstein uhen architects 4
Revision Work Flow
Const Docs Bidding Construction
Incorporated in
ContractGC &
Subs
ADDENDUMDESIGN
TEAMCB
CONTRACT
Change Order
April 18, 2007 eu:a eppstein uhen architects 5
Supplemental Drawings
Sheet Formats
8.5” x 11”
TB - CA 8.5 x 11 (Landscape)
TB - CA 8.5 x 11 (Portrait)
11” x 17”
TB - CA 11 x 17 (Landscape)
TB - CA 11 x 17 (Portrait)
April 18, 2007 eu:a eppstein uhen architects 6
Sheet Formats
April 18, 2007 eu:a eppstein uhen architects 7
Supplemental Sheet Info
Construction Set
or
Bid Set #1
MM/DD/YY
e.g. 04/18/07
Per Vision
April 18, 2007 eu:a eppstein uhen architects 8
Supplemental Sheet Info
Acme Warehouse
1234 Main Street
Anywhere, WI
54321
April 18, 2007 eu:a eppstein uhen architects 9
Supplemental Sheet Info
Abbreviation + Number
Construction Bulletin CB #000
Addendum ADD #00
Request for Information RFI #000
April 18, 2007 eu:a eppstein uhen architects 10
Supplemental Sheet Info
Date of Revision
Different from “ISSUANCE DATE”
Date of CB or Addendum or RFI
April 18, 2007 eu:a eppstein uhen architects 11
Supplemental Sheet Info
Axxx : Sheet Number
•A105 5th Flr Plan
•A200 Exterior Elevations
X01 : Consecutive Revision
•X01 1st Revision
•X15 15th Revision
April 18, 2007 eu:a eppstein uhen architects 12
Nomenclature: Supplemental Dwgs
CD sheet + Dash + X suffix + (2) Sequential NumbersA0000-X00 A1001-X01
A00-X00 A201-X13
A0-X00 A5-X02
Naming convention:Modifications :
a. Construction Bulletin CB #000
b. Construction Change Directive CCD #000
c. Proposal Request PR #000
Clarificationsa. Addendum ADD #00
b. Architectural Supplemental Information ASI #000
c. Field Directives FD #000
Interpretations
a. Request for Information RFI #000
April 18, 2007 eu:a eppstein uhen architects 13
Supplemental Dwgs
Architectural Examples G103-X11 11th revision to sheet G103 - First Floor Life Safety Plan
A101-X01 1st revision to sheet A101 - First Floor Plan
A1021-X03 3rd revision to sheet A1021 - Twenty-First Floor Plan
A501-X29 29th revision to sheet A501 - Exterior Plan Details
Consultant Examples Would follow this same naming convention:
S103-X06 6th revision to sheet S103 - Third Floor Framing Plan
E101-X01 1st revision to sheet E101 - First Floor Electrical Plan
H1021-X03 3rd revision to sheet A1021 - Twenty-First Floor HVAC Plan
P105-X11 11th revision to sheet P105 - Fifth Floor Plumbing Plan
April 18, 2007 eu:a eppstein uhen architects 14
ADT Process
Cloud the revision in the MS (model space) of the source
drawing (plan, elevation, section, etc) on layer A-Anno-Revs
Open the sheet affected (GXXX.dwg, AXXX.dwg, etc)
Copy view from the “Main” Sheet tab into a Supplemental
Sheets’ tab.
Resize the view to fit the page.
Print Supplemental Sheet to PDF (AXXX-00.pdf)
Save to 00000-00\Documents\CA\Construction Bulletins
Once CB’s itemized proposal has been received & accepted:
Bluebeam Staple all associated PDF’s into a single PDF (CB-000)
Copy Supplemental Drawing PDF’s (only!) into:
Record Documents\Contract Drawings\Supplemental Dwgs
April 18, 2007 eu:a eppstein uhen architects 15
Revit Demonstration
April 18, 2007 eu:a eppstein uhen architects 16
Conclusion
Questions???