C02F
-
Upload
lo-shun-fat -
Category
Documents
-
view
218 -
download
0
Transcript of C02F
7/27/2019 C02F
http://slidepdf.com/reader/full/c02f 1/3
TRAINING SUPPORT PACKAGE (TSP)
09/25/9862G1@BCL@2401F34C
C-1
TSP
Number/Title
PFN: 051-62G1-C02 Set Up a 150-TPH Crusher Plant
Effective Date
Supersedes TSP(s) All previous TSPs and LPs on this subject dated prior to 10 January 1997
TSP User United States Army Engineer SchoolFort Leonard Wood, MO 65473-5000
Proponent U.S. Army Engineer SchoolDirectorate of Training and Doctrine DevelopmentFort Leonard Wood, MO 65473-5000
Comments/
Recommendations
Send comments and recommendations directly to:Commandant ATTN: ATSE-TDUnited States Army Engineer SchoolFort Leonard Wood, MO 65473-5000
Foreign Disclosure
Restrictions
This product has been reviewed by the product developers in coordination with theFort Leonard Wood foreign disclosure authority. This product is releasable to militarystudents from foreign countries on a case-by-case basis.
7/27/2019 C02F
http://slidepdf.com/reader/full/c02f 2/3
TRAINING SUPPORT PACKAGE (TSP)
09/25/9862G1@BCL@2401F34C
C-2
Preface
Purpose To provide 62G skill level one soldiers the skills and knowledge required to set up a150-TPH crusher plant
Task Number: 051-251-XXXX
Task Title: Set Up a 150-TPH Crusher Plant
Condition: Given a 150-TPH crusher plant, job specifications, TM 5-331C*TM 5-332, TM 5-3820-255-14&P, TM 5-3820-256-14&P,TM 5-3820-257-14&P, TM 5-3820-258-14&P,TM 5-3820-259-14&P, TM 5-3820-260-14&P,
TM 5-3820-261-14&P, TM 5-3820-262-14&P,TM 5-3820-263-14&P, a general mechanic's tool kit, a ¾” driveset with sockets, an 18” pipe wrench, a 24” adjustable wrench, a12” ruler, replacement screens, a cone and jaw adjustmentpump, a grease gun, petroleum, oil, lubricants, penetrating oil,rags, appropriate maintenance forms, an equipment recordsfolder, coveralls, safety boots, goggles, gloves, hearingprotection, a hard hat, paper, and a pencil
Standards: Identify the setup procedures and calibrate a 150-TPH crusher plant in accordance with (IAW) job specifications, TM 5-331C,*TM 5-332, TM 5-3820-255-14&P, TM 5-3820-256-14&P,TM 5-3820-257-14&P, TM 5-3820-258-14&P,TM 5-3820-259-14&P, TM 5-3820-260-14&P,
TM 5-3820-261-14&P, TM 5-3820-262-14&P, andTM 5-3820-263-14&P, without damage to equipment or theenvironment and without injury to personnel.
*This reference is currently being revised as a Field Manual
7/27/2019 C02F
http://slidepdf.com/reader/full/c02f 3/3
TRAINING SUPPORT PACKAGE (TSP)
09/25/9862G1@BCL@2401F34C
C-3
This TSP
ContainsTABLE OF CONTENTS
Page
Preface C-2
Lesson Plan Section I - Administrative Data C-I-1
Section II - Introduction C-II-1
Terminal Learning Objective C-II-2
Section III - Presentation
A - Identify Setup Procedures for a 150-TPH Crusher Plant
C-III-A1
B - Calibrate a 150-TPH Crusher Plant C-III-B1
Section IV - Summary C-IV-1
Section V - Student Evaluation C-V-1
Appendixes Section VI - Appendixes C-VI-1 A - Viewgraph Transparency (VGT)
MastersC-VI-A1
B - Practical Exercises and Solutions C-VI-B1
C - Test and Test Solutions C-VI-C1