By Mayura Sri-on - WordPress.com
Transcript of By Mayura Sri-on - WordPress.com
By
Mayura Sri-on
Assistant Chief of Power Quality Analysis Section
Customer Service Division
Engineering and Service Department
PEA Area1(Northeast) Udon Thani Province, Thailand 1
Distribution System
Voltage Rise Effect
Study System
Result
Conclusion
Loss Analysis
2
Distributed Generation
Connected to Grid
3
Traditional Distribution Network
The voltage decrease along the feeder, from substation to the feeder-end.
The power flow is in one direction only, from the transmission system to the HV substations and to the MV&LV distribution system.
Subtrasmission
Customer 69kV, 115kV
Distribution
Customer 11kV,22kV,33kV
Low Voltage
Customer 220 V, 380 V
Trasmission
Lines 230kV, 500kV
4
The power voltage at DG will increase voltage, which may cause the
voltage at its connection point to be higher that voltage at the substation.
Figure 1 Illustration of a DN with DG connected
This circuit represents the basic features of a DN in which DG is connected to a DN feeder.
5
V2 V1
𝑉2 ≈ 𝑉1 + 𝑅 𝑃𝐺 − 𝑃𝐿 + ±𝑄𝐺 − 𝑄𝐿 𝑋
This simple equation can be used to qualitatively analyze the relationship
Between the voltage at 22 kV Bus and the amount of generation that can be connected to the DN.
Normally, before allowing the installation of DG, the Distribution System
Operation will ensure that the voltage, line thermal characteristics and
substation transformer capacity will not be violated for the worst
operating scenarios:
1) No generation and maximum load
2) Maximum generation and maximum load 3) Maximum generation and minimum load
6
V2 V1
(Eq.1)
Source Load
r
G
A simple model of the distribution system long G km.
𝑃𝑜𝑤𝑒𝑟𝑆𝑜𝑢𝑟𝑐𝑒 = 𝐿𝑜𝑎𝑑 + 𝑃𝑜𝑤𝑒𝑟 𝐿𝑜𝑠𝑠
I
𝑃𝑜𝑤𝑒𝑟 𝐿𝑜𝑠𝑠 = 𝐼2𝑟𝐺
7
(Eq.2)
(Eq.3)
r : Resistance of line (/km)
Figure 3 Simple model of Distribution system
Source Load
r
G
DG
G1 G2
i1 I
𝑃𝑜𝑤𝑒𝑟 𝐿𝑜𝑠𝑠𝑤𝑖𝑡ℎ 𝐷𝐺 = 𝑖12𝑟𝐺1 + 𝐼2𝑟𝐺2
𝑃𝑜𝑤𝑒𝑟 𝐿𝑜𝑠𝑠𝑤𝑖𝑡ℎ 𝐷𝐺 = 𝑃𝑜𝑤𝑒𝑟𝑆𝑜𝑢𝑟𝑐𝑒 + 𝑃𝑜𝑤𝑒𝑟𝐷𝐺 − 𝐿𝑜𝑎𝑑
8
(Eq.5)
(Eq.4)
Figure 4 Simple model of Distribution system with DG installation
Voltage level
Voltage Normal Contingency
Max Min Max Min
Transmission ±5% ±10%
115 kV 120.7 109.2 126.5 103.5
69 kV 72.4 65.5 75.9 62.1
Distribution ±5% ±10%
33 kV 34.7 31.3 36.3 29.7
22 kV 23.1 20.9 24.2 19.8
Low Voltage ±10% Approx. ±10% Approx.
380 V 418 342 418 342
220 V 240 200 240 200
9
Figure 4 Radial DN 22 kV of PEA in the northeast area of Thailand
The main feeder had been divided into 2 main branches at ‘B’ and each
branches protected by the line recloser.
‘C’ for connecting of DG2 (PV-DG 5.1 MW)
‘E’ for connecting of DG1 (Biomass-based DG 2.4 MW)
‘D’,’F’ the end of line.
A
B C D
E F
DG2
DG1
10
DigSILENT software
Geographic Information System (GIS)
SCADA system
Constant impedance load dispersed along line
Power quality measuring of
Substation, DG1 and DG2 follow
EN50160 std.
Dranetz model Power X
11
DG1
Biomass generation rating 2.4 MW
Sugarcane mill factory
22kV VSPP
Generation period during milling from Dec – Apr
DG2
PV generation rating 5.1 MW
22kV VSPP
Generation period during daytime
12
Rural area, small city
Commercial load
Small business load
Mining factory load
Residential load
Total average load 6.25 MW
Nominal Voltage: 22 kV
Sending Set Point Voltage: 22.51.25%
13
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
MW
Power Profile by hour DG1
DG2
DG1+DG2
SystemLoad
DG1 Biomass-based: generate power at 2.4 MW average
DG2 PV: generate power only day time vary by sunrise cycle, max at 5.1 MW
System load: dispersed along line, most are residential consumers.
Commercial & Business consumers: sugar factory and small business.
Peak load at night time(07.00-09.00 pm.) By day time total load was lower than the generation of DGs.
14
Figure 5 Power Profile of load and DG generation rating 24 hrs.
Network Modeling
Scaling load follow measuring data
Newton Raphson (Power Equation Classical) used
Run voltage profile with load profile 24 hrs.
Run power flow single short for voltage level by location. With and without DG
Vary load from 25% - 150%
Run power flow single short for power loss With and without DG
Vary DG Ration by vary load from 0.8 to 4.8
15
• DiSILENT Software
• Simulation data rechecked
with the result from
measuring data.
• Measuring data collected
at 3 points: substation,
DG1 and DG2.
• Collecting data period: 7 days
• Total Distribution Network
length: 45 km.
16
D
F
B
C
E
A
Figure 6 Network modeling export from GIS
17
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
110.00%
1.00
1.01
1.01
1.02
1.02
1.03
1.03
1.04
1.04
1.05
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
p.u
.
Substation Voltage Profile Vsub withDG
Vsub WoDG
Load-ratio
Voltage profile at substation with and without DGs
The figure showed the voltage of system with DG was higher.
Especially during day time (09.00 am-4.00pm) with generation of the PV-DG
raised significantly.
Load ratio: load/peak load ( avg. of peak load in a week 6.25MW) At peak load (Load-ratio = 100%) voltage at the substation also raised by DG.
18
Figure 7 Result of voltage profile 24 hrs. at Substation
Voltage
Level
pu. (22kV)
%Load
20%
40%
60%
80%
100%
120%
140%
0.92
0.94
0.96
0.98
1.00
1.02
1.04
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
p.u
.
Voltage Profile at Midline(B)
Vmid withDG Vmid WoDG Load-ratio
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
110.00%
0.950
0.960
0.970
0.980
0.990
1.000
1.010
1.020
1.030
1.040
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
p.u
.
Voltage Profile at Endline(D) Vend(D) withDG Vend(D) WoDG Load-ratio
19
Figure 8 Result of
voltage profile 24 hrs. at Midline (B)
Figure 9 Result of
voltage profile 24 hrs. at Endline (D)
19.500
20.000
20.500
21.000
21.500
22.000
22.500
23.000
A B C D E F
kV
Voltage by location
W/O DG DG1 DG2 DG1+DG2
At ‘E’ and ‘F’ end of line, voltage without DG was lower than limit of
Voltage level (20.9 kV). With support of DG the voltage level of ‘F’ rise from 20.6 kV to 21.8 kV.
Limit at 20.9 kV
20
W/O DG DG1 DG2 DG1+DG2
DG Ratio (DG/Load) 0 0.39 0.81 1.20
Figure 10 Result of voltage level at each location
Location W/O DG DG1 DG2 DG1+DG2
DG Ratio DG/Load 0 0.4 0.8 1.2
o Substation A 22.339
0.40%
(22.428)
0.91%
(22.543)
1.20%
(22.606)
o Middle of line B 21.278
1.55%
(21.608)
3.03%
(21.923)
4.34%
(22.201)
o DG2(PV 5.085MW) C 21.164
1.40%
(21.461)
4.35%
(21.084)
5.50%
(22.327)
o EndlineDG2 D 21.094
1.33%
(21.375)
3.71%
(21.876)
4.80%
(22.106)
o DG1(Gen 2.414MW) E 20.882
2.88%
(21.483)
3.25%
(21.560)
5.84%
(22.102)
o EndlineDG1 F 20.603
2.78%
(21.176)
3.34%
(21.291)
5.83%
(21.804)
DG Ratio VS Voltage Rise %
21
19.50
20.00
20.50
21.00
21.50
22.00
22.50
23.00
23.50
24.00
A B C D E F
kV
25%
50%
75%
100%
125%
150%
%Load
23.1 kV
DN with the support of voltage level by DG, voltage level in the range of
grid code event the high load without under voltage problem at end of line. Weak network, max DG with min load, voltage rise may occur.
20.9 kV
22
Voltage limit
Voltage limit
Figure 11 Result of voltage level with vary of load from 25% - 150%
20.50
21.00
21.50
22.00
22.50
23.00
23.50
24.00
24.50
25.00
A B C D E F
kV
Voltage by location with Cap
25%
50%
75%
100%
125%
150%
%Load
Traditional improving under voltage level is install a shunt capacitor
In the network. In this feeder, a 1500kVar shunt capacitor was used
to improve the voltage level before installing of DG.
This important, when DG integrated to DN, the voltage level was raised.
When switching shunt capacitor to DN, the Distribution operator should
consider carefully with load level.
23.1 kV
23
Voltage limit
Figure 12 Result of voltage level with vary of load from 25% - 150% with support of switching capacitor installation.
Effect on traditional improving under voltage level
DG Ratio (DG/load)
20.50
21.00
21.50
22.00
22.50
23.00
23.50
24.00
0.80 0.96 1.20 1.60 2.40 4.80
kV
Voltage level with DG
DG2(PV 5.1MW)
Midle
Sub
1.5
At DG Ratio higher than 1.5, voltage level along feeder inclined to be
higher than voltage at substation. With DG smaller than load the voltage may be raised by effect of DG but not higher than at substation.
24
Figure 13 Result of voltage level with vary of DG Ratio
0
0.05
0.1
0.15
0.2
0.25
0.3
No DG DG1 DG2 DG1+DG2
MW Loss
MW LossMW
In this case, with DG installation the power loss was less than without DG.
Due to DG smaller than Load, the incorporation of DG into a radial distribution system could result in line loss reduction.
25
Figure 14 Result of Power Loss with vary of DG installation rating
26
0.000
0.050
0.100
0.150
0.200
0.250
80% 96% 120% 160% 240% 480%
Power Losses
MW loss
MW lossTrend of losses
MW
DG Ratio (DG/load)
When DG-ration increased beyond 1.5, loss essentially increases. This showed
that the integration of DG into a radial distribution system may result in higher line loss if DG power rating and load were not properly related.
Figure 15 Result of Power Loss with vary of DG Ratio
DG could raise voltage level of Distribution
Network.
DG Ratio (DG/Load): the higher DG Ratio ,
the higher voltage rise % especially end of
line.
Weak network, maximum DG with minimum
load, leaded to voltage rise problem.
DG could reduce power loss with the proper
generation rating.
DG Ratio: the higher than 1.5, the increasing
of power loss in the DN.
27
28
29