by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil...

158
ADHESIVE BONDING OF CONCRETE-STEEL COMPOSITE BRIDGES BY POLYURETHANE ELASTOMER by Billy Siu Fung Cheung A thesis submitted in conformity with the requirements for the degree of Master of Applied Science Graduate Department of Civil Engineering University of Toronto © Copyright by Billy Siu Fung Cheung, 2008

Transcript of by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil...

Page 1: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

ADHESIVE BONDING OF CONCRETE-STEEL COMPOSITE BRIDGES BY

POLYURETHANE ELASTOMER

by

Billy Siu Fung Cheung

A thesis submitted in conformity with the requirements

for the degree of Master of Applied Science

Graduate Department of Civil Engineering

University of Toronto

© Copyright by Billy Siu Fung Cheung, 2008

Page 2: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

ii

ADHESIVE BONDING OF CONCRETE-STEEL

COMPOSITE BRIDGES WITH A POLYURETHANE ELASTOMER

Master of Applied Science (2008)

Billy Siu Fung Cheung

Department of Civil Engineering

University of Toronto

ABSTRACT

This thesis is motivated by the use of full-depth, precast, prestressed concrete

panels to facilitate deck replacement of composite bridges. The shear pockets required in

using convention shear stud connections, however, can cause durability problems. The

objective of this study is to investigate the possibility of eliminating the use of shear studs,

and adhesively bond the concrete and steel sections.

The feasibility of the developed polyurethane adhesive joint is defined based on

the serviceability and ultimate limit states. The joint must have sufficient stiffness that

additional deflection due to slip must not be excessive. The adhesive and bond must also

have sufficient strength to allow the development of the full plastic capacity of the

composite section. The use of the developed adhesive joint in typical composite bridges

was found to be feasible. The behaviour under live load was found to be close to a fully

composite section.

Page 3: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

iii

For my family.

Mom and Dad,

your unconditional love, sacrifice, and support

have made this possible.

I love you.

Brother,

Thank you.

Page 4: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

iv

ACKNOWLEDGEMENT

I would like to thank my supervisor, Professor P. Gauvreau, for his advice and

valuable comments toward this thesis. This project would not have been possible without

him. I would also like to thank Professor Birkemoe for his valuable opinions and

comments toward this thesis.

Sponsorship of BASF Canada Inc. has made this research study possible. Great

thanks go to Greg Gardin, from BASF Canada Inc., for his dedication into this project

and his help at every step of the adhesive development. Thanks also go to his lab assistant

Melody Zhang.

The assistance of the structural laboratory staff is greatly appreciated. Special

thanks go to Jimmy Susetyo and Sylvio Tam for their help at every stage of the lab work.

I would also like to thank my summer lab assistant Erica Wong for her help. Thanks also

go to Carlene Ramsay for giving me a great head start on this project. The technical help

at every step of this project from my colleagues in GB231 is also greatly appreciated.

Thanks go to my friends Mike Cavers and Jessica Wong for reading over my work.

Encouragement and understanding from all my friends are much appreciated.

Lastly, I would like to thank my family for their full support. Your love and

sacrifice have made this possible. You have been there with me through the ups and

downs. Thank you.

Page 5: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

v

TABLE OF CONTENTS

CHAPTER 1: INTRODUCTION 1 1.1. RAPID CONCRETE DECK REPLACEMENT FOR COMPOSITE BRIDGES ............................................. 1 1.2. FULL-DEPTH PRECAST CONCRETE PANELS.................................................................................. 2 1.3. SHEAR CONNECTION SYSTEM IN FULL-DEPTH PRECAST, PRESTRESSED CONCRETE PANELS....... 6 1.4. THE USE OF ADHESIVES IN BRIDGE CONSTRUCTION.................................................................... 9 1.5. OBJECTIVE AND SCOPE OF THE THESIS....................................................................................... 11 1.6. EXPERIMENTAL PROGRAM ......................................................................................................... 13 1.7. ANALYTICAL PROGRAM............................................................................................................. 13 1.8. THESIS OUTLINE ........................................................................................................................ 14

CHAPTER 2: DESIGN FACTORS FOR ADHESIVE BONDING 17 2.1. INTERACTION IN COMPOSITE BEAMS ......................................................................................... 17

2.1.1. Full and No Interaction ........................................................................................................ 17 2.1.2. Partial Interaction ................................................................................................................ 20

2.2. LIMIT STATE DESIGN ................................................................................................................. 23 2.2.1. Ultimate Limit States ............................................................................................................ 23 2.2.2. Failure Mode ........................................................................................................................ 24 2.2.3. Deflection under the Serviceability Limit State .................................................................... 25

2.3. CHARACTERIZATION OF THE LOAD - SLIP BEHAVIOUR OF A SHEAR CONNECTION..................... 26 2.4. THE CONNECTOR STIFFNESS, CONNECTION AREA STIFFNESS, AND SHEAR MODULUS .............. 28

2.4.1. Determination of the Shear Stiffness of the Connection ....................................................... 31 2.4.2. Bedding Layer....................................................................................................................... 31

2.5. ADHESIVE CONSIDERATIONS ..................................................................................................... 34 2.5.1. Material Properties .............................................................................................................. 35 2.5.2. Cure Time ............................................................................................................................. 35

2.6. POLYURETHANE ELASTOMER ADHESIVE ................................................................................... 38 2.7. CONSTRUCTION CONSIDERATION............................................................................................... 39

2.7.1. Surface Treatment................................................................................................................. 39 2.7.2. Moisture................................................................................................................................ 40 2.7.3. Temperature ......................................................................................................................... 40

2.8. SUMMARY.................................................................................................................................. 41

CHAPTER 3: LITERATURE REVIEW 43 3.1. THE DEVELOPMENT OF THE COMPOSITE STRUCTURAL LAMINATE (CSL) PLATE SYSTEM, BY

CARLETON UNIVERSITY, OTTAWA ........................................................................................................... 43

Page 6: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

vi

3.2. STATIC BEHAVIOUR OF STEEL CONCRETE BEAM CONNECTED BY BONDING, BY SI LARBI ET AL.

(2006) ................................................................................................................................................... 50

3.3. EXPERIMENTAL STUDY OF BONDED STEEL CONCRETE COMPOSITE STRUCTURES, BOUAZAOUI ET

AL. (2006) ................................................................................................................................................ 58 3.4. SHEAR RESISTANCE OF A POLYURETHANE INTERFACE IN CONCRETE-STEEL COMPOSITE BEAMS,

BY RAMSAY (2007) .................................................................................................................................. 64 3.5. SUMMARY.................................................................................................................................. 66

CHAPTER 4: EXPERIMENTAL PROGRAM 67 4.1. MODIFIED PUSH-OFF TEST SPECIMENS...................................................................................... 67

4.1.1. Scope of the Experimental Program..................................................................................... 68 4.1.2. Design Consideration for the Specimens.............................................................................. 69 4.1.3. Fabrication of the Specimens ............................................................................................... 72 4.1.4. Materials............................................................................................................................... 74 4.1.5. Test Variables ....................................................................................................................... 76 4.1.6. List of Specimens and Variables........................................................................................... 81 4.1.7. Push-Out Test Setup and Instrumentation ............................................................................ 82

CHAPTER 5: TEST RESULT AND DISCUSSIONS 86 5.1. ULTIMATE LOAD AND DEFLECTION ........................................................................................... 86 5.2. RESULTS AND DISCUSSION......................................................................................................... 88

5.2.1. Series One............................................................................................................................. 88 5.2.2. Series Two ............................................................................................................................ 89 5.2.3. Series Three .......................................................................................................................... 92 5.2.4. Series Four ........................................................................................................................... 95 5.2.5. Series Five ............................................................................................................................ 97

5.3. SHEAR STIFFNESS OF THE ADHESIVE CONNECTION.................................................................. 100

CHAPTER 6: ANALYTICAL PROGRAM 102 6.1. DEGREE OF INTERACTION IN COMPOSITE BEAMS..................................................................... 103

6.1.1. Full Interaction Analysis in Composite Beams................................................................... 108 6.1.2. No Interaction Analysis in Composite Beams..................................................................... 109 6.1.3. Partial Interaction Analysis of Composite Beam by Girhammar and Gopu (1993)........... 110

6.2. COMPUTER ANALYSIS USING FRAME AND SPRING ELEMENTS ................................................. 116 6.2.1. Material Properties and Element Representation .............................................................. 117

6.3. PROBLEM DEFINITION .............................................................................................................. 119 6.4. RESULTS AND DISCUSSION – SERVICEABILITY LIMIT STATE.................................................... 121 6.5. FLEXURAL STRENGTH AT ULTIMATE LIMIT STATE .................................................................. 126

6.5.1. Rigid Plastic Analysis by Oehlers and Bradford (1995)..................................................... 126

Page 7: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

vii

6.5.2. Results and Discussion – Ultimate Limit State ................................................................... 131 6.6. CRITERIA.................................................................................................................................. 132

CHAPTER 7: SUMMARY, CONCLUSION AND RECOMMENDATIONS 134 7.1. SUMMARY................................................................................................................................ 134 7.2. CONCLUSION............................................................................................................................ 135 7.3. RECOMMENDATIONS AND FUTURE WORK ............................................................................... 137

Page 8: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

viii

LIST OF TABLES Table 1.1: Examples of Deck Replacement Projects with Precast Concrete Panels .......... 7

Table 1.2: Mechanical Properties of the Polyurethane Elastomer Core used in the SPS

(Minten et al., 2007)........................................................................................ 10

Table 2.1: Comparison of General Properties of Epoxy and Polyurethane...................... 36

Table 3.1: Mechanical Properties of EC-609-002/18 (after Braun, 1999) ....................... 45

Table 3.2: Tension Bond Test of the Polyurethane Elastomer Core (after Braun, 1999). 45

Table 3.3: Summary of Adhesive Push-Off Tests by Si Larbi et al. (2006)..................... 53

Table 3.4: Comparison of the Stiffness between Connectors and Bonding (after Si Larbi

et al., 2006) ..................................................................................................... 55

Table 3.5: Behaviour of the beams with different types of connection under a

concentrated load, 250KN, applied at midspan (after Si Larbi et al., 2006) .. 57

Table 3.6: Geomety of Beams Studied by Bouazaoui et al. (2006).................................. 59

Table 3.7: Comparison between Experimental Ultimate Load, F u,c and Theoretical

Ultimate Load, Fu,t .......................................................................................... 61

Table 4.2: General Properties of the Formulations of Polyurethane ................................ 76

Table 4.2: List of Specimens and Corresponding Variables............................................. 81

Table 5.1: Results from the Push-Off Tests...................................................................... 87

Table 5.2: Stiffness of Polyurethane Adhesive Joints .................................................... 101

Table 6.1: Dimensions of the Studied Composite Bridges ............................................. 121

Table 6.2: Results of the Partial Interaction Analysis..................................................... 122

Table 6.3: Comparison of Results from SAP2000™ and Equation 6.21. ...................... 123

Table 6.4: Results from the Rigid Plastic Analysis ........................................................ 131

Page 9: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

ix

LIST OF FIGURES

Figure 1.1 A Full Depth, Precast Concrete Panels System (Figures taken from Shim et al.,

1999) ................................................................................................................. 3

Figure 1.2: Shear Pocket Design Used by Culmo (2000)................................................... 5

Figure 1.3: Conventional Mechanical Shear Connectors (Figures taken from Oehlers &

Bradford, 1995)................................................................................................. 7

Figure 1.4: a) Typical Shear Pockets; b) Cracking Between Shear Pockets (Figures taken

from Issac et. al, 1995)...................................................................................... 8

Figure 1.5: The SPS System Developed by Intelligent Engineering. 1) Steel face sheets

with thickness, t. 2 - Polyurethane Elastomer Core with Thickness h. (Figures

taken from Minten et al., 2007) ...................................................................... 10

Figure 1.6: Shenley Bridge, Quebec, Canada (Picture taken from Intelligent Engineer,

2007) ............................................................................................................... 11

Figure 2.2: Slip in a Composite Beam.............................................................................. 20

Figure 2.3: Degree of Interaction (Picture from Oehlers & Bradford, 1995) ................... 20

Figure 2.4: Cross-Section of a 50m Span Composite Bridge ........................................... 26

Figure 2.5: Standard Push-Off Test Configuration in Accordance to Eurocode ENV-

1994-1-1 (Picture from Johnson, 2004) .......................................................... 27

Figure 2.6:Typical Load-Slip Behaviour of Shear Connectors (Si Larbi et al., 2006) ..... 28

Figure 2.7: Length Used to Determine Connection Stiffness, k - a) Connector Spacing, Ls;

b) Length of Joint, Ljoint .................................................................................. 29

Figure 2.8: Shear Deformation of a Joint with Shear Modulus, G and Thickness, t. ....... 29

Figure 2.9: Bedding Layer in a Precast Panel System (Figure taken from Kim et al., 2002)

......................................................................................................................... 32

Figure 2.10: Strength Gain Behaviour of Elastocast C5039, BASF Canada (Gardin, 2007)

......................................................................................................................... 37

Figure 3.1: Composite Structural Laminate Plate System Used as the Outer Hull of the

Product Oil Tanker (Figures taken from Linder, 1995).................................. 44

Figure 3.2: a) Shear Bond Test b) Direct Tension Bond Test used by Braun (1999)...... 45

Page 10: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

x

Figure 3.3: Finite Element Models Used for the Study of Flexural Behaviour of CSL

Beams - a) Shell Element Model; b) Solid Element Model (Figures taken from

Braun, 1999) ................................................................................................... 47

Figure 3.4: Moment-Deflection Plots of the Analyses of the CSL Beam in Flexure with

Various Polyurethane Stiffness (Figures taken from Braun, 1999)................ 47

Figure 3.5: Moment Versus Mid-Span Deflection for Flexural Specimens by Funnell

(2000).............................................................................................................. 49

Figure 3.6: Push-Off Tests Conducted by Si Larbi et al. (2006), as adopted from the

Eurocode (1994).............................................................................................. 51

Figure 3.7: General Properties of the Adhesives (Figure taken from Si Larbi et al., 2006)

......................................................................................................................... 51

Figure 3.8: Average Shear Stress versus Slip from Push-Off Tests (Figure taken from Si

Larbi, 2006)..................................................................................................... 53

Figure 3.9: Failure Modes in Push-Off Tests a) Failure in Calamine; b) Failure in

Concrete (Photos taken from Si Larbi, 2006) ................................................. 54

Figure 3.10: Characteristics of Connectors (Figure taken from Si Larbi et al., 2006) ..... 54

Figure 3.11: Cross Section of the Composite Beam Studied by Si Larbi et al. (2006) .... 55

Figure 3.12: Strain Distribution at Midspan (Si Larbi et al., 2006).................................. 57

Figure 3.12: Cross-Section of the Beams Studied by Bouazaoui et al. (2006) - a) Constant

Joint Thickness; b) Varying Joint Thickness in the Transverse Direction

(FIgures taken from Bouazaoui et al., 2006) ............................................... 59

Figure 3.13: Composite Beams Studied by Bouazaoui et al. (2006) - a) Constant Joint

Thickness; b) Varying Joint Thickness in the Longitudinal Direction

(Figures taken from Bouazaoui et al., 2006)................................................ 59

Figure 3.14: Stress Distribution of Composite Section at its Plastic Capacity (Figure

taken from Bouazaoui et al., 2006).............................................................. 61

Figure 3.15: Failure Modes of Beams - a) P1 with concrete crushing; b) P2 with yielding

of steel, shearing of the adhesive joint and concrete cracking (Pictures taken

from Bouazaoui et al., 2006)........................................................................ 62

Figure 3.16: Deflection at the Midspan (Figure taken from Bouazaoui et al., 2006)....... 62

Page 11: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

xi

Figure 3.17: Strain Distributions of the Section with a) Epoxy Joint; b) Polyurethane Joint

(Bouazaoui et al., 2006) ............................................................................... 63

Figure 3.18: Push-Off Specimens (Ramsay, 2007) .......................................................... 65

Figure 3.19: Debonding of the Push-Off Specimens (Ramsay, 2007) ............................. 65

Figure 4.1: Small Scale Push-Off Specimens for the Experimental Program .................. 70

Figure 4.2: Wooden Form used in the Fabrication of the Specimens............................... 71

Figure 4.3: Silicone Sealant Required to Avoid Leakage at the Joint .............................. 72

Figure 4.4: a) Setup for polyurethane pour; b) C-clamps used to tighten tubes after pour

......................................................................................................................... 73

Figure 4.5: Components of Polyurethane - a) Polyol and Chain Extender, b)

Isocyrange used in Type A ............................................................................. 75

Figure 4.6: Polyurethane Compressible Form .................................................................. 79

Figure 4.7: Experimental Test Setup ................................................................................ 82

Figure 4.8: Riehle Machine, University of Toronto ......................................................... 83

Figure 4.9: Location of LVDT.......................................................................................... 83

Figure 5.1: a) Visible Shrinkage in Specimen 1-1, b) Reduced Shrinkage in Specimen 1-3

......................................................................................................................... 88

Figure 5.2: Leakage Caused by Expansion of Polyurethane ............................................ 90

Figure 5.3: Shear Stress vs. Average Girder Displacement for Series 2. ......................... 91

Figure 5.4: Failure Surfaces of Specimen 2-1 a) Polyurethane Layer; b) Concrete Slab. 92

Figure 5.3: Improper Curing of the Polyurethane in Specimen 3-1 ................................. 93

Figure 5.6: Shear Stress vs. Average Girder Displacement for Series 3 .......................... 94

Figure 5.7: Polyurethane Layer in Specimen 3-3 with PU form ...................................... 95

Figure 5.8: Shear Stress vs. Average Displacement for Series Four. ............................... 96

Figure 5.9: Specimen 4-6 at Failure.................................................................................. 96

Figure 5.10: Shear Stress vs. Average Displacement for Series Five............................... 98

Figure 5.11: Specimen 5-1 at Failure................................................................................ 99

Figure 6.1: Length used to determine connection stiffness, k – a) Connector Spacing, Ls;

b) Length of Joint, Ljoint ................................................................................ 103

Figure 6.2: Schematic Composite Section in Partial Interaction Analysis (Picture taken

from Girhammar & Gopu, 1993) .................................................................. 107

Page 12: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

xii

Figure 6.3: Uniformly Distributed Load Acting on the Composite Beam (Picture taken

from Girhammar & Gopu, 1993) .................................................................. 107

Figure 6.4: Differential Element in a Composite Beam Subjected to an Axial Load, F, and

a Uniformly Distributed Load, q(x) (Girhammar & Gopu, 1993)................ 111

Figure 6.5: Graphical Presentation of Equation 6.28 (after Wang, 1998) ...................... 115

Figure 6.6: β versus dβ /d(αL) ........................................................................................ 116

Figure 6.8: 2D SAP2000™ Model – a) A Complete Span b) Detail of the Elements.... 118

Figure 6.9: Figure 6.9: Overall Cross-Section of the Composite Bridge with 13m with

Deck Supported on four Steel beams............................................................ 120

Figure 6.10: Parameters of the Beam Studied – Thickness of Slab dc, Depth of Steel

Beam ds, Width of Flanges, wf, Thickness of web tw, and Thickness of Flanges

tf..................................................................................................................... 120

Figure 6.11: Strain Distributions of the Cross-Section at Midspan for Polyurethane Layer

Thickness of 25mm, 35mm, 45mm and 50mm – 50m-Span Design............ 124

Figure 6.12: Strain Distributions of the Cross-Section at Midspan for Polyurethane Layer

Thickness of 25mm, 35mm, 45mm and 50mm – 25m-Span Design............ 124

Figure 6.13: Relationship between the percentage increase in maximum deflection versus

shear connection stiffness, K, for 25m and 50m-span designs according to

Equation 6.21. ............................................................................................... 125

Figure 6.14: Three Possible Strain and Stress Distributions (Figures taken from Oehlers

& Bradford, 1995)......................................................................................... 128

Figure 6.15: Stresses of the Composite Section with Full Interaction at the Ultimate Limit

State Neutral Axis in the Steel Beam. (Figures taken from Oehlers & Bradford,

1995) ............................................................................................................. 130

Figure 6.16: Stresses of the Composite Section with Partial Shear Connection at the

Ultimate Limit State (Figures taken from Oehlers & Bradford, 1995)......... 130

Page 13: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

xiii

NOMENCLATURE Latin Symbols Ac area of concrete section

AL longitudinal area of an adhesive joint

As area of steel section

beff effective slab width

d1 distance between centroid of the concrete section to centroid of the

composite section

d2 distance between centroid of the steel section to centroid of the composite

section

dc depth of concrete slab

E Young’s Modulus

Fc force in concrete section

f’c concrete compressive strength

f’t concrete tensile strength

f’τ concrete shear strength

Fs force in steel section

Fy steel yield strength

Fult ultimate strength of a shear connector

G shear modulus

Ic moment of inertia of a concrete section

Is moment of inertia of a steel section

K stiffness of a connector

k area stiffness of a connection

L span length

Ljoint length of an adhesive joint

Lmodel spacing of frame elements used in finite element analysis

Ls center to center spacing of studs

M applied moment

Page 14: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

xiv

Mc moment distributed to a concrete section

Ms moment distributed to a steel section

n modular ratio

N axial force at a section

Pconcrete plastic strength of a concrete section

Ps,req required shear strength of the connection for full interaction

Pshear shear strength of connection

Psteel plastic strength of a steel section

q applied uniformly distributed load

s slip

sult slip at failure

t thickness of an adhesive joint

Tg Glass Transition Temperature

tw thickness of web of a steel girder

u horizontal displacement

V applied shear force

w deflection of a beam

w0 total deflection of a composite section with no interaction

wf total deflection of a composite section with full interaction

wjoint width of the adhesive joint in experiment

wmodel width of steel flanges of the studied beams

wp total deflection of a composite section with partial interaction

wslip deflection of a composite section due to interlayer slip

x longitudinal distance along a beam

z vertical distance along a cross section

Greek Symbols

α shear connection stiffness parameter

β partial interaction parameter

γ shear deformation of a joint

δ the mass density

Page 15: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

xv

∆ horizontal deformation of a joint

ε strain

К curvature of a beam

η degree of shear interaction

τ shear stress

Page 16: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

1

CHAPTER 1: INTRODUCTION

1.1. Rapid Concrete Deck Replacement for Composite Bridges

The objective of this research is motivated by the need for rapid bridge deck

replacement in rehabilitation of concrete-steel composite bridges. As the volume of

highway traffic increases, major delays due to road construction are generally not

tolerated by the public. Often bridges can only be closed during periods of low traffic or

during the nighttime and the construction work must be completed before the next

morning in order to minimize the impact to the public. The need for new methods in

rapid deck replacement has led to research studies such as that by Tadros et al. (1999),

who suggested that the reduction in reconstruction time not only can reduce the overall

cost of the project, but can also help improve public acceptance, reduce accident risk, and

yield environmental benefits. Therefore, any method to facilitate the construction time in

bridge rehabilitation projects would be desirable.

Conventional technology can be improved to minimize the construction time in

composite bridge rehabilitations by modifying both the bridge deck system and the

girder-to-deck connection system (Tadros et al., 1999). Typically bridge decks are

designed using cast-in-place concrete according to well established standards such as the

Canadian Highway Bridge Design Code (CAN-CSAS6-06). Provided that time is not a

constraint on the projects, cast-in-place concrete bridge decks are often promising

solutions since adjustments can be easily made in the field to achieve the required

geometry or profile. However, in projects where time is a constraint, alternative bridge

deck designs that utilize full-depth precast concrete slabs as an alternative to cast-in-place

Page 17: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

2

concrete could provide a great potential to reduce the construction time. This,

unfortunately, leads to potential durability problems because conventional shear

connectors cannot be well adapted to the use of precast concrete panels. Openings in the

precast panels, called shear pockets or shear blockouts, are required so connectors can be

welded on site after the panels have been placed properly onto the girders. The shear

pockets would then be filled with a grouting material to form a sound mechanical shear

connection. Not only can the numerous pours for the shear pockets cause extensive

delays, these shear pockets can also create vulnerable areas that are prone to durability

problems, which could result in premature deterioration of the concrete bridge decks.

This research study investigates an alternate connection method to connect

concrete panels to steel girders by adhesively bonding to enhance the technology in rapid

concrete deck replacement for steel-concrete composite bridges.

1.2. Full-Depth Precast Concrete Panels

In concrete-steel composite bridges, the replacement of concrete decks can be

facilitated by using full-depth precast panels. An example of a full-depth precast,

prestressed concrete deck panel system is shown in Figure 1.1. As shown, a composite

section consists of a concrete deck, which can be precast or cast in-situ, and the concrete

deck is supported by steel beams. In the case where precast panels are used, prestressing

of the panels is usually recommended (Issa et al., 1995) to ensure that the transverse

joints between the panels are sealed. Traditionally, the concrete deck is connected to the

steel beams through mechanical shear connectors, such as the commonly used headed

shear studs shown in Figure 1.1. For a cast-in-place concrete deck, the concrete is poured

directly onto the headed studs that would have be welded to the steel beams, however, the

Page 18: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

3

use of a precast concrete deck require openings called shear pockets, shown in Figure 1.1,

which must be grouted after the placement of the panels in order for the deck and the

beams to act compositely. Lastly, a gap created by rubber strips along the edge of the top

flanges of the steel beam is usually present to provide geometric tolerances, and this gap

is usually referred as the haunch if the concrete deck is cast-in-place, and is referred as

the bedding layer if the concrete deck is precast.

As discussed in the research study by Culmo (2000), the use of precast panels

avoids the extensive curing periods and eliminates the time consuming and labour

intensive formwork installation required for cast-in-place concrete, hence making rapid

overnight deck construction feasible.

Figure 1.1 A Full Depth, Precast Concrete Panels System (Figures taken from Shim et al., 1999)

Efficient implementation of full-depth precast concrete panels in bridge deck

reconstruction has been well documented. In the investigation performed by the Illinois

Department of Transportation rehabilitation program (Issa et al. 1995), the authors

presented the findings from the inspection of selected bridges in the United States that

were rehabilitated with full-depth precast, prestressed concrete panels. The field

Page 19: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

4

investigation led to the conclusion that, in general, the use of precast concrete panels in

replacing deteriorated bridge decks can be efficient and economical. Although not all the

bridges inspected were performing at a satisfactory level, recommendations were made in

the study outlining the appropriate detailing required to avoid the durability problems

encountered, which includes leaking at the transverse joints and spalling and cracking of

the concrete decks between shear pockets. In general, Issac et al. (1995) recommended

that the precast panels should be post-tensioned longitudinally to secure all the joints to

prevent leakage. Secondly, a sufficient amount of transverse prestressing should also be

provided to avoid cracking of the deck during handling of the units. A waterproof

membrane system and an overlay are also essential to keep the deck in a good condition.

The shear keys should be designed to ease the grouting process and to take into account

potential irregularities.

With the intention to advance its bridge rehabilitation technology, the Connecticut

Department of Transportation also investigated the use of full-depth precast concrete

slabs in two bridge rehabilitation projects that required a rapid deck replacement system

(Culmo, 2000). At the initial stage of the investigation, Culmo (2000) studied a design

that required only night closures of the bridge with days opened to traffic. This, however,

was considered problematic because firstly, both the bridges that needed deck

replacement were composite, and the removal of the existing deck would be time

consuming because of the existing shear connectors. Therefore, only a small portion of

the bridge could be removed and replaced in each night closure. Secondly, when only a

portion of the bridge deck could be replaced each night, a construction joint between the

old and new slabs could be present when the bridge re-opened to public traffic. This open

Page 20: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

5

joint would be a non-composite section and Culmo (2000) discovered that the steel

girders would be stressed beyond allowable limits from the full dead and live load that

would act on it during the normal traffic periods. These concerns have led to the

development of a deck system that required precast, prestressed full-depth concrete

panels so it would be possible for the rehabilitation work to be completed in a weekend

closure. A typical span layout consists of concrete panels that were 2400mm wide and

200mm thick, which could provide adequate room for the post-tensioning ducts. The

shear pockets, as shown in Figure 1.2, were spaced at 600mm center-to-center and two to

four welded studs could be placed in each pocket. The transverse joints between the

panels were sealed by a high-strength non-shrink grout, which was allowed to set before

the panels were post-tensioned together. The two bridge decks were still in excellent

condition five years after the replacement, therefore the author concluded that the

solution was viable.

Figure 1.2: Shear Pocket Design Used by Culmo (2000)

The abovementioned research projects have demonstrated that the use of full-

depth precast concrete panels can be a promising solution to rapid bridge deck

replacement projects with only weekend closures and minimal impact to the public.

Furthermore, the high quality control inherent to the fabrication of the precast panels

Page 21: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

6

under plant conditions is another advantage that warrants it as an excellent alternative to

cast-in-place concrete decks. Culmo (2000) discussed that the use of precast concrete

panels requires considerations of the variable field conditions and tolerances in both the

original structures and the new components. To ensure that the concrete panels could fit

together on-site, they need to be fabricated with accurate geometry. This requires high

quality control, which includes proper curing of the concrete to avoid excess shrinkage.

Proper curing is easier to achieve under plant conditions compared to casting in-situ

because the moisture and temperature can be controlled and monitored. Since durability

of the concrete greatly depends on the curing, therefore, concrete deck panels fabricated

under plant conditions can be more durable than concrete decks that are cast-in-situ of

which the curing conditions greatly depends on the field conditions. In addition to

projects discussed by Culmo (2000) and Issac et al. (1995), other examples of deck

replacement projects that used precast concrete panels are summarized in Table 1.1.

1.3. Shear Connection System in Full-Depth Precast, Prestressed Concrete Panels

In conventional composite bridge construction, the concrete slab and the steel

girders are connected through conventional mechanical shear connectors, such as channel

or bar connectors and most commonly, welded headed shear studs, as shown in Figure

1.3. In practice, if the concrete was cast in-situ, the headed studs would be welded onto

the steel girders prior to the concrete pour. However, when precast panels have been used

in the past, shear pockets, which are openings in the panels as shown in Figure 1.2, were

required for the shear studs to be welded on site. Since the grout is poured in-situ under

Page 22: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

7

Table 1.1: Examples of Deck Replacement Projects with Precast Concrete Panels

Name of Bridge Year of

Construction or Reconstruction

Type of Bridge Total Length (m)

Tappan Zee Bridge, New York 2006 Steel Truss, Slab-on-Girders 4800

Jacques Cartier Bridge, Montreal, Canada 2001 Slab-on-Girders

or Floor Truss 2700

Chulitna River Bridge, Alaska 1992 Slab-on-Girders 241

Burlington Bridge, Iowa 1992 Cable-Stayed 324

Interstate 84-Connecticut Route 8 Interchange, Waterbury, Connecticut 1989 Slab-on-Girders 213

Batchellerville Bridge, New York 1982 Slab-on-Girders 937

Seneca Bridge, Illinois 1986 Steel Truss 460

Dublin 0161 Bridge, Ohio 1986 Concrete Arch 162

Clark Summit Bridge, Pennsylvania 1980 Slab-on-Girders 496

Figure 1.3: Conventional Mechanical Shear Connectors (Figures taken from Oehlers & Bradford, 1995)

Page 23: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

8

field conditions after the concrete decks are prestressed, these shear pockets can create

vulnerable areas at which durability problems could occur. The corners of rectangular

shear pockets, for example, could promote stress concentration, which could result in

cracking of the concrete deck at areas between the shear pockets. In fact, many of the

bridges investigated in the research study by Issa et al. (1995) showed signs of cracking

and spalling problems in the concrete that were initiated by the shear pockets, as shown

in Figure 1.4.

a. b.

Figure 1.4: a) Typical Shear Pockets; b) Cracking Between Shear Pockets (Figures taken from Issac et. al, 1995)

This problem with the current practice of connecting precast concrete bridge deck

panels to steel girders is the primary motivation of this thesis. This research study

investigates an alternative way to connect the concrete to steel by using a polyurethane

adhesive to avoid the need for shear pockets required for headed shear stud connections.

Page 24: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

9

1.4. The Use of Adhesives in Bridge Construction

The use of adhesive materials in bridge construction has become more common as

new technology for construction and materials are introduced to bridge designs and

rehabilitation. With the introduction of precast segmental bridge construction, for

example, epoxy resins have been used as a sealant at the transverse joints between the

precast concrete segments. Research studies that investigated the strengthening of

concrete or steel structures by adhesively bonding fibre-reinforced polymer

reinforcement or steel plates to the beams or columns are also well documented (Example:

Tumialan et al., 2002; Triantafillou, 1998). The use of adhesives, however, as a shear

connector in composite structures is less common. It was not until recent years that

experimental investigations have been conducted to connect materials that act

compositely through adhesive bonding.

Application of adhesives in bridge construction has greatly evolved with the

introduction of Sandwich Plate System (SPS), which was jointly developed by BASF and

Intelligent Engineering (Excell, 2004). The SPS, shown in Figure 1.5, composed of two

steel plates bonded to a polyurethane elastomer core, was first introduced in the marine

industry to replace the conventional outer hull in double hull oil tankers to eliminate

fatigue and corrosion problems caused by steel stiffening plates. Since polyurethane has a

wide range of achievable stiffness (a Young’s Modulus ranging from 20MPa to 2300

MPa) and the SPS is light in weight (approximately 1100 kg/m3) (Funnell, 2000), the

application of the system has been extended to civil engineering projects including bridge

deck replacements. Table 1.2 summarizes the properties of the polyurethane elastomer

core used in the SPS system.

Page 25: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

10

The Shenley Bridge in Quebec, Canada, shown in Figure 1.6, was one of its first

applications in bridge construction (Farmer, 2006). The prefabricated SPS deck plates

were bolted together and to the steel girders and the system was designed to act

compositely. Other bridge projects that used the SPS system include the deck

replacement of the Lennoxville Bridge in Quebec, Canada and the deck strengthening of

the Schönwassenpark Bridge in Krefeld, Germany (Intelligent Engineering, 2007). The

developer of the SPS system continues to investigate the possibility for other applications

in civil engineering projects with either the existing or a modification of the SPS system

(Excell, 2004).

Figure 1.5: The SPS System Developed by Intelligent Engineering. 1) Steel face sheets with thickness,

t. 2 - Polyurethane Elastomer Core with Thickness h. (Figures taken from Minten et al., 2007)

Table 1.2: Mechanical Properties of the Polyurethane Elastomer Core used in the SPS (Minten et al., 2007)

Density ∆ = 1150 kg/m3

Young’s Modulus E = 874 MPa

Shear Modulus G = 285 MPa

f’c = 18 MPa, at ε = 0.2% Compressive Strength

f’cu = 32 MPa, at ε = 10 %

ft = 16.1 MPa, at ε = 0.2% Tensile Strength

ftu = 33.9 MPa at ε = 32%

Shear Strength fτ = 18 MPa

Page 26: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

11

Figure 1.6: Shenley Bridge, Quebec, Canada (Picture taken from Intelligent Engineer, 2007)

1.5. Objective and Scope of the Thesis

The main objective of this research study is to investigate the feasibility of

adhesively bonding precast concrete deck panels and steel girders using a polyurethane

elastomer. The target application of the study is the rapid replacement of concrete decks

in concrete-steel composite bridges. The use of full-depth precast, post-tensioned

concrete slabs connected to steel girders is assumed. The concrete is assumed to have a

compressive strength, f’c, of approximately 45 MPa and the steel girders are assumed to

have an yield strength, Fy, of 350 MPa. The adhesive is assumed to replace conventional

headed stud connections, and act as the conventional bedding layer that has normally

been filled with a mortar material. Kim (2002) suggested that the minimum thickness of

should be at least 25 mm, which is the typical thickness of the bedding layer that could

provide sufficient construction tolerance under field conditions.

Page 27: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

12

This research study is designed to:

1) Establish the criteria to define the feasibility of bonding concrete to steel with a

polyurethane adhesive as the shear connector in composite bridges through an

analytical program. The criteria to be established will be based on the following:

a) Under the serviceability limit state, the adhesive joint must have

sufficient stiffness to minimize additional deflection due to interlayer

slip.

b) Under the ultimate limit state, the adhesive bond must be strong

enough to allow the full development of the plastic capacity of the

concrete and the steel sections.

2) Develop a formulation of the polyurethane adhesive and an adhesive joint

configuration that could be used to meet the abovementioned criteria through an

experimental program.

3) Study the influence of the pouring methods, the different formulations of the

polyurethane elastomer, the curing time of the elastomer, the temperature of the

specimens during the pour of the elastomer, and the different surface treatments

on the bonding of the adhesive layer to the concrete and steel surfaces.

4) Investigate the feasibility of bonding concrete decks to steel beams in composite

bridges using the polyurethane elastomer developed in the experimental program

based on the criteria established.

Page 28: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

13

1.6. Experimental Program

The experimental part of the research involved the use of a commonly used shear

connection test, called the push-off test, to investigate the use of a polyurethane elastomer

to adhesively bond concrete to steel. Nineteen small-scale push-off tests were conducted

with the goal to investigate the influence of several factors on the bond strength of the

polyurethane and substrates. The factors examined included the pouring method of the

adhesive layer, the surface treatment of the concrete slabs and the steel girders, the

characteristics of the polyurethane adhesive, and the temperature of the specimens at the

time when the polyurethane layer is poured. The second goal of the experimental

program was to characterize the load-slip behaviour of the shear connection. The stiffness

of the shear connections was then determined from the results of the push-off tests and

the values were used in the analytical part of the study.

1.7. Analytical Program

The analytical part of the research involved the use of a partial interaction

analysis that was outlined by Girhammar and Gopu (1993), which provides analytical

solutions that describe the behaviour of a simply supported composite beam with partial

shear connection. The analysis is then compared to a computer model designed with

program SAP2000™, which was used to study the overall effect of the shear deformation

in the polyurethane layer on the deflection of a composite bridge. Perfect bond is

assumed between the polyurethane and the concrete interface, as well as the polyurethane

and the steel interface. A parametric study that examined the effects of varying the

thickness of the adhesive layer and the stiffness of the polyurethane elastomer to the

deflection of the bridge was conducted. The relationship between the span lengths and the

Page 29: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

14

stiffness of the shear connection was also examined. A rigid plastic analysis outlined by

Oehlers and Bradford (1995) was used to study the behaviour of the composite sections

under the ultimate limit state. The results were used to determine if the polyurethane

adhesive bond developed in the experimental program had sufficient strength to be used

as the shear connection in composite bridges. A list of criteria used to define the

feasibility of adhesively bonded shear connection was established based on analyses

under the serviceability and the ultimate limit state.

1.8. Thesis Outline

Chapter 1 of this report has provided an introduction to rapid deck replacement of

bridge decks to minimize public disruption during bridge rehabilitation constructions.

The chapter has also described the advantages in using full-depth precast, prestressed

concrete panels in rapid deck replacement and the potential problems of using headed

shear studs with the precast panels. Various applications of adhesives in composite

bridges have also been presented. Lastly, the experimental and analytical programs of the

research study have been outlined.

Chapter 2 outlines the general design considerations necessary in composite

bridges. The standard push-off test used to determine the load-slip behaviour of a shear

connection is described. This is followed by a discussion of the considerations regarding

to the selection of an adhesive suitable for the purpose of this research study. The chapter

concludes with an outline of construction requirements specific to the use of the selected

adhesive.

Chapter 3 begins with a discussion of the series of research of the composite

structural laminate plate system by Carleton University that inspired the design of the

Page 30: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

15

adhesively bonded shear connection developed in this study. An overview of two recent

research studies that investigated concrete and steel composite structures connected by

adhesive bonding is then provided. Lastly, the research study conducted by Ramsay

(2007) is summarized.

Chapter 4 describes the experimental program, including a description of the

specimens and their fabrication, a description of the test set-up, an outline of the testing

procedures, and an explanation of the variables that could affect the bond strength at the

polyurethane to concrete and polyurethane to steel interfaces.

Chapter 5 provides the results of the experimental program, including the stress-

slip behaviour of each specimen, the estimation of the stiffness of the polyurethane

adhesive connection, the shear strength of the adhesive bond, and the description of the

failure modes and surfaces.

Chapter 6 describes the analytical model of concrete-steel composite bridges that

use the polyurethane elastomer adhesive as the shear connection. An overview of the

analyses involved in studying composite beams with full, partial and no interaction is

provided. The numerical solutions to the partial interaction analysis described by

Girhammar and Gopu (1993) are outlined. Adhesively bonded composite sections with

polyurethane layer ranging from 25mm to 50m and span lengths of 25m, 50m, and 75m

were analyzed under the serviceability limit state. The chapter continues with the

analyses of the composite sections under ultimate limit state based on the rigid plastic

analysis as described by Oehlers and Bradford (1995). Lastly, a list of criteria that defines

the feasibility of the polyurethane adhesive bond was established.

Page 31: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

16

Chapter 7 concludes the thesis with a brief summary of the results obtained from

the experimental and analytical program. The feasibility of using the polyurethane

adhesive as a mean of shear connection based on the results of the experimental program

and the criteria established from the analytical program are discussed. Finally,

recommendations for future research are provided.

Page 32: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

17

CHAPTER 2: DESIGN FACTORS FOR ADHESIVE BONDING

One of the main reasons in assembling concrete and steel in composite bridges is

to combine the high compressive strength of concrete and the high tensile strength of

steel to create a stiffer and stronger structure (Bouazaoui et al., 2006). To ensure that the

two components are connected properly, the connection must be capable of transferring

the loads between the concrete and the steel. This chapter begins with a discussion of the

interaction in composite beams. The limit state designs that have to be considered will

then be discussed and a set of criteria based on these requirement will be proposed. The

standard push-off test used to characterize a shear connection is then described. The

different stiffness parameters used to characterize a shear connection will then be defined.

The chapter continues with a discussion of the field requirements that are specific to the

use of adhesives in construction. A comparison of the relevant properties of two typical

adhesive materials that can be used as a shear connection: an epoxy and polyurethane will

be given. The chapter concludes with a description of the design considerations that is

specific to the use of polyurethane in adhesively bonded connections.

2.1. Interaction in Composite Beams

2.1.1. Full and No Interaction

The degree of shear interaction of the concrete slab and steel girder in composite

bridges is dependent on the stiffness and strength of the shear connectors. Often the

degree of shear connection, denoted by η, is expressed as:

Page 33: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

18

,

shear

s req

PP

η =

where Pshear is the ultimate strength of the shear connection and Ps, req is the connection

strength required to allow the concrete and steel sections of a composite beam to attain

their plastic strength under ultimate loading. This will be discussed further in the

analytical program in Chapter 6.

Figure 2.1: Cross Section of a Composite Beam

One of the most important behaviours that designers must consider when

designing for service loads is the deflection of the beam, which is a function of the

overall stiffness of the composite section. The stiffness of the shear connection also

influences the degree of interaction between the composite components, which in turns

affects the overall deflection of the beam. The two limiting cases for this interaction are

when no shear connection is provided and when the connection is very stiff. Consider a

composite cross-section shown in Figure 2.1. When no connection is provided, a case in

which the beam is referred to as non-composite and there is no interaction between the

Page 34: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

19

concrete and steel sections, the concrete slab and the steel girder act independently and

share the loads applied to the structure proportional to their stiffness. The bending

stiffness of a non-composite section can be described as:

( ) c c s soEI E I E I= + Eq. 2.1

where (EI)o denotes the non-composite stiffness and EcIc and EsIs are the bending

stiffness of the concrete slab and steel girder respectively. On the contrary, when the

shear connection is very stiff, the beam is referred to as being fully composite with a

perfect bond between the concrete and steel sections, and there is full interaction between

the two sections. When the beam has a perfect bond, the assumption that plane sections

remain plane is valid and the bending stiffness of the fully composite section can be

calculated by transforming the concrete slab into an equivalent steel section according to

the modular ratio, n, which is the ratio of the Young’s modulus of concrete, Ec, to that of

steel, Es. This can be done by determining the effective width, beff, which can be

calculated by dividing the width of the concrete slab, b, by the modular ratio. The

bending stiffness of the section with full interaction, (EI)f, can then be estimated by this

equivalent section of steel as:

( ) ⎟⎟⎠

⎞⎜⎜⎝

⎛+++= 2

22

1

3

12dAIdA

dbEEI ssc

ceffsf Eq. 2.2

Page 35: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

20

2.1.2. Partial Interaction

In reality, it is difficult to achieve either of the limiting cases: there will always be

some frictional forces between the two materials even if the two materials are not

connected, and if they are connected, the connectors will never be completely rigid.

There will always be relative horizontal movement, or slip, between the two materials as

they deflect under bending, as shown schematically in Figure 2.2. A composite beam that

cannot attain full interaction is said to have partial interaction. The strain distributions of

a beam with full, partial, and no interaction under bending are shown in Figure 2.3.

Figure 2.2: Slip in a Composite Beam

Figure 2.3: Degree of Interaction (Picture from Oehlers & Bradford, 1995)

Page 36: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

21

A perfect bond is characterized by a linear strain distribution across the section with no

change in the strain at the concrete-steel interface. As seen from Figure 2.3, the strain ε at

any distance z from the bottom of the steel can be described as (Si Larbi et al., 2006):

ε(z)= εs + z К Eq. 2.3

where εs is the strain at the top fibre of the steel girder, К is referred to as the curvature of

the beam, and z is the vertical distance along the cross-section. A partial interaction

between two composite materials is characterized by linear strain distributions across

each of the section, with a difference in strain across the interface, which is usually

referred to as the slip strain, denoted by dsdx , where s is the slip between the two

components and x is the longitudinal distance along the beam. Since the slip is sometimes

denoted by ∆u, the slip strain can also be denoted by 'u∆ .

Assuming that there is no uplift between the concrete slab and steel girder, the

curvatures of both sections will be the same, as shown by the following. Consider the

case when the beam is fully composite and the bending stiffness of the section is (EI)f as

calculated from Equation 2.2, the applied moment, M, distributed to each section is:

⎟⎟⎠

⎞⎜⎜⎝

⎛=

f

ccc EI

IEMM)(

Eq. 2.4

( )

s ss

f

E IM MEI

⎛ ⎞= ⎜ ⎟⎜ ⎟

⎝ ⎠ Eq. 2.5

where, c sM M M= + Eq. 2.6

The curvature in each component can be calculated by:

Page 37: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

22

cc

cc IE

M=κ Eq. 2.7

ss

ss IE

M=κ Eq. 2.8

Substituting Equations 2.4 and 2.5 into Equations 2.6 and 2.7, it can be shown that:

f

sc EIM

)(=== κκκ Eq. 2.9

As will be seen in Chapter 6, this assumption is relevant because many of the

numerical solutions developed to analyze the behaviour of composite beams with partial

interaction are based on the assumption that there is no uplift between the components

and the curvatures of the components are the same (Example: Newmark et al., 1951;

Girhammer and Gopu, 1993).

The guideline in the Canadian Highway Bridge Design Code (CAN/CSA-S6-06)

is designed for headed stud connections and there is no guideline proposed for adhesive

connection. An adhesive connection is continuous as opposed to the discrete shear stud

connections, and the slip in a composite beam bonded by an adhesive would be dictated

by the overall shear deformation of the adhesive joint as opposed to the stiffness of the

individual connectors. Therefore, the adhesive joint must have the required shear stiffness

to ensure that a sufficient interaction between the concrete slab and the steel girder can be

attained. Unfortunately, the current guideline does not provide a clear deflection limit that

is directly related to the flexural stiffness of a bridge, but rather the deflection limit is

based on its dynamic behaviour, namely the vibration of the bridge. Therefore, a set of

criteria must be proposed in order to determine the minimum allowable connection

stiffness for an adhesive bond. The following sections will discuss the required limit state

Page 38: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

23

designs, and general criteria required to determine the feasibility of the adhesive bond

connections will be proposed.

2.2. Limit State Design

While understanding the composite interaction between the concrete slab and the

steel girder is important, limit states relevant to the design of an adhesive as the shear

connection in composite bridges must also be considered. This section discusses the

design factors relevant to the use of adhesive in bonding concrete slab to steel girders in

composite bridges.

2.2.1. Ultimate Limit States

As discussed by Keller & Gürtler (2005), the current design method for concrete-

steel composite bridges requires that global failure in the beam at ultimate limit state to

occur before the failure of the deck-to-girder connection. This suggests that in adhesively

connected composite beams, the shear strength and the bond strength should be high

enough to allow the concrete slab to crush and the steel girder to yield at failure. As will

be outlined in detail in the discussion of the analytical program in Chapter 6, the shear

connection must have sufficient strength to transfer the forces between the concrete slab

and the steel girder under ultimate limit state in a plastic analysis.

As demonstrated in the analytical program in Chapter 6, the maximum

longitudinal shear stress encountered at the shear connection of simply supported

composite bridges with spans ranging from 25m to 75m and concrete strength ranging

from 25MPa to 55 MPa is found to be less than 3MPa. Although this value greatly

depends on the actual design of the beam, it correlates well with the results and

Page 39: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

24

conclusion by Si Larbi et al. (2000), who had advised that the adhesive used in as the

shear connection of composite bridges should be able to resist a longitudinal stress of at

least 3 MPa.

2.2.2. Failure Mode Generally the failure mode in any structure at ultimate limit state should be as

ductile as possible to avoid sudden catastrophic failure. As already mentioned, the failure

of composite bridges should not happen at the connection because bond failures tend to

be brittle, therefore, the adhesive connection must be able to provide sufficient bond

strength so that the concrete slab crushes and the steel yields prior to the shear failure at

the connection. In the case where the failure occurs at the connection, the adhesive joint

should have sufficient ductility to allow visible plastic deformation at ultimate load

before failure. The two different failure modes are demonstrated by the study of

Bouazaoui et al. (2006), where two different adhesively bonded shear connections in

composite bridges were compared. Generally, the beam with the stiffer adhesive and

sufficient bond strength failed with crushing of concrete and yielding of steel, whereas

the beam with a softer adhesive and insufficient bond strength failed in a ductile manner,

with visible vertical deflection and failure started with the shearing of the adhesive layer

followed by the cracking of concrete and buckling of the top steel flange.

In addition, adhesive joints are usually weak against stresses normal to the

bonding surface (Adderley, 1988), usually referred as the tearing or peeling stress, and

failure in this manner is usually brittle due to a quick propagation of the stress along the

failure interface, therefore, tearing stress on the adhesive joint should be avoided.

Page 40: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

25

2.2.3. Deflection under the Serviceability Limit State Deflection of a beam under bending is dictated by the sectional stiffness, EI,

which is in turn a function of the stiffness of the shear connection. Similar to the slip, the

maximum deflection of a composite beam under bending is highest when no shear

connection is provided between the concrete slab and the steel girder, and is lowest when

the two materials are perfectly bonded together. This suggests that in a bonded

composite beam with partial interaction, the deflection can be reduced by choosing a

stiffer adhesive material. As will be further discussed in Chapter 6, the closed-form

analytical solutions derived by Girhammar and Gopu (1993) suggest that the

displacement of a beam with partial interaction is the sum of the deflection of the

corresponding fully composite section, wf and the deflection caused by slip between the

two materials, ws. It is important to choose an adhesive material and design the adhesive

joint to minimize additional deflection due to the interlayer slip between the sections. The

deflection limits set by the Canadian Highway Bridge Design Code (CAN/CSA-S6-06)

are based on the vibration of the bridge, and the code does not have a clear guideline that

directly relates deflection limits to the stiffness of the bridge. As a result, the criteria

necessary to determine the minimum allowable stiffness of the adhesive connection to

avoid excessive deflection due to slip are also unclear. This research study proposes a

criterion by limiting the additional deflection due to interlayer slip relative to the overall

deflection of the bridge with perfect bond connection.

The criterion can be determined by first examining the increase of the deflection

of a bridge with no interaction compared to the same design with full interaction.

Consider the composite cross-section, shown in Figure 2.4, for a 50m span bridge. The

Page 41: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

26

geometry is based on the typical designs of composite bridges with a span to depth ratio

of approximately 1 to 28. Under any given load, if the design is non-composite, the

bridge would deflect 130% more than that of the corresponding fully composite section.

Based on this deflection range, this study proposes that the maximum additional

deflection of a composite bridge with partial interaction allowed shall be less than 20% of

the overall deflection of the bridge with full interaction. If the additional deflection due to

the interlayer slip exceeds this 20% limit, further investigation that is beyond the scope of

this thesis is required.

Figure 2.4: Cross-Section of a 50m Span Composite Bridge

2.3. Characterization of the Load - Slip Behaviour of a Shear Connection

In order to determine the structural performance of a composite beam, the

behaviour of the connection under shear loading should be characterized. A common

method, called the push-off test, has been developed to characterize the behaviour of

conventional mechanical connections under shear stresses. A standard push-off test

recommended by the Eurocode ENV-1994-1-1 is shown in Figure 2.5. The push-off test

Page 42: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

27

consists of a steel I-girder connected to two concrete slabs by the shear connectors under

consideration. The girder is then loaded under a constant load and the slip between the

steel and the concrete is measured. The result of a push-off test is a characterization of

the load-slip behaviour of the shear connection. Typical load-slip plots are shown in

Figure 2.6. Important information about the shear connection, such as the shear stiffness

in the elastic range and the ultimate shear strength, can be determined from the load-slip

plot. As shown from the plot, the shear connectors can be classified, based on the

Eurocode, as rigid or ductile depending on the slip they allowed at ultimate load. The

results can be used, for example, to validate results in a full composite beam test or an

analytical model.

Figure 2.5: Standard Push-Off Test Configuration in Accordance to Eurocode ENV-1994-1-1 (Picture from Johnson, 2004)

Page 43: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

28

Figure 2.6:Typical Load-Slip Behaviour of Shear Connectors (Si Larbi et al., 2006)

2.4. The Connector Stiffness, Connection Area Stiffness, and Shear Modulus

Since the degree of interaction in a composite section is directly related to the

stiffness of the connection, one of the most important values that can be obtained from a

load-slip plot is the connection stiffness. The connection stiffness can be expressed in

terms of the stiffness of the connector, K [N/mm], as determined from the push-off test,

or sometimes the connection area stiffness, k [N/mm2]. As shown in Figure 2.6, K can be

obtained from the push-off test by determining the slope of the load-slip curve, and the

stiffness value is unique to the configuration and geometry of the shear connection used

in the push-off test. When the stiffness of the individual connectors is required to be

distributed along the length of the beam, the area stiffness, k, is often used. This allows

designers to, in the case of the conventional stud connections, simplify analyses by

assuming a continuous connection as opposed to connectors at discrete locations

(Girhammer & Gopu, 1993). As a result, the continuous nature of adhesively bonded

Page 44: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

29

connections allows the use of the connection area stiffness in their analyses. Consider the

headed stud connection and the adhesive joint connection as shown in Figure 2.7, where

Ls is the spacing between the connection, and Ljoint is the length of the adhesive joint. The

area stiffness of the connection can be calculated by:

L jointL s

a. b. Figure 2.7: Length Used to Determine Connection Stiffness, k - a) Connector Spacing, Ls; b) Length of Joint, Ljoint

1) In the case with mechanical shear connectors:

sL

Kk = Eq. 2.10

where Ls is the spacing between the shear connectors, or:

2) In the case with adhesively bonded joint:

intjoL

Kk = Eq. 2.11

D

g

Figure 2.8: Shear Deformation of a Joint with Shear Modulus, G and Thickness, t.

Page 45: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

30

The shear modulus of an adhesive used in a bonded connection can also be determined

from the connection stiffness, K. Consider the adhesive joint shown in Figure 2.8. The

shear load, V, and the shear deformation, γ, can be related by:

γLA

VG = Eq. 2.12

where AL is the area of the joint. For small shear deformation, γ, the following

relationship can be assumed:

t∆

=γ Eq. 2.13

where t is the thickness of the joint and ∆ is the horizontal deformation, therefore,

VK =∆

Eq. 2.14

GAVt

=∆ Eq. 2.15

Since the connection stiffness, K, can be related to V and ∆ by,

VK =∆

Eq. 2.16

Substituting, K can be related to G as:

GAKt

= Eq. 2.17

Equation 3.5 can be used to either determine the shear modulus of the adhesive material

from the results obtained in a push-off test or, if the shear modulus of the adhesive is

known, the stiffness of a bonded connection can be estimated.

Page 46: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

31

2.4.1. Determination of the Shear Stiffness of the Connection

The behaviour of composite beams at the serviceability limit states greatly

depends on the stiffness of the shear connection. However, most studies usually use the

push-off test to determine the shear strength of the connector and are less interested in

determining the stiffness of the connector (Wang, 1998). The reasons for this is because

designs of composite bridges connected with conventional shear studs usually assume

perfect bond, therefore, designer are mainly concerned with the ultimate strength of the

connectors. In spite of the numerous investigations conducted on shear connectors, the

definition of the shear stiffness is not unified among researchers and scholars, especially

when the load-slip behaviour of the shear connection is nonlinear (Wang, 1998). If the

shear connector is rigid with a linear elastic range in the load-slip curve, the connection

stiffness can usually be defined as the tangent stiffness of the plot. This assumption,

however, would not be valid if the connector is ductile with nonlinear load-slip behaviour.

Although there is not a general agreement of where the secant tangent should be

measured from, Oehlers and Coughlan (1986) have studied the load-slip plots of 116

push-tests and derived that the Ksecant can be taken at a load of 0.5Fult, where Fult is the

strength of the connector based on the push-off test. In the study by Si Larbi et al. (2000),

the secant tangent is taken as 0.6Fult according to the Eurocode.

2.4.2. Bedding Layer

Most of the current design codes for composite bridges are based on

investigations done on cast-in-place concrete decks with headed shear studs, and do not

apply specifically to full-depth precast concrete decks (Kim et al., 2002). When the

Page 47: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

32

concrete deck is cast-in-place, there is often a gap between the steel beams and the

concrete deck, called the haunch, which is usually filled with concrete. In the case where

the deck is precast, this gap is referred to as a bedding layer, as shown in Figure 2.9. The

bedding layer is necessary in construction with precast concrete decks in order to provide

tolerance for changes in the dimensions of the steel girders due to field splices,

cambering, and other geometric variations. The adhesive bond connection being

developed in this research study eliminates the use of headed studs and uses a

polyurethane adhesive joint to act as the bedding layer.

Figure 2.9: Bedding Layer in a Precast Panel System (Figure taken from Kim et al., 2002)

Kim et al. (2002) studied the influence of the bedding layer on the strength of the

shear connection in full-depth precast decks and discovered that as the bedding layer

thickness increases, the slip in the connection also increases. The reason for this is

because the thin and unreinforced bedding layer has a lower compressive strength

compared to the concrete deck, and stress concentrations at the shear studs would cause

Page 48: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

33

cracking of the mortar, hence allowing a larger deformation of the shear studs. Although

shear studs would not be present in an adhesively bonded system, the adhesive layer

would also be a more flexible layer compared to the concrete deck and the steel girder.

As the thickness of the adhesive joint increases, the shear deformation in the layer would

increase under a given load since the stiffness of the layer is a function of its thickness.

This can be shown by considering the deformed joint shown in Figure 2.8 again. Recall,

from Equation 2.15 that:

GAVt

=∆

Therefore, Equation 2.15 shows that the shear deformation ∆ is proportional to

the thickness of the joint. It is therefore necessary to determine the bedding layer

thickness that could provide the field tolerance required, but at the same time as thin as

possible to avoid the reduction in the overall stiffness of the structure. The thickness of

the bedding layer required usually depends on the configuration of the bridge and the

geometric tolerance required, but in practice the thickness is usually around 20 to 40mm

(Kim et al., 2002; Shim et al., 2001).

Page 49: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

34

2.5. Adhesive Considerations

The selection of an adhesive suitable for structural purposes requires

consideration of the strength of the adhesive, its stiffness, the temperature required for

proper curing, and the sensitivity to field conditions such as moisture and contamination.

In addition, the adhesive selected for the use in rapid bridge rehabilitation must also be

able to develop sufficient strength in a short time when the bridge reopens to traffic after

the construction. One class of adhesives that can be used for structural applications is the

thermosets – a class of adhesive that sets by a chemical reaction, since they are capable of

resisting high sustained loading (Adderley, 1988). Two commonly used thermosets in

civil engineering applications are the epoxy and the polyurethane.

Epoxy adhesives consist of an epoxy resin combined with a hardener. The

versatility in its formulation allows a wide range of application. Though epoxies can

provide good thermal, environmental and creep resistance, these adhesives tend to have

long curing time and low toughness (Adderley, 1988). The application of epoxy in civil

engineering projects such as bridge rehabilitation, concrete beam strengthening, and

composite bridge construction has been well documented (Hänsch, 1978; Bouazaoui et

al., 2006).

Polyurethane is a two-part adhesive that cures quickly at ambient temperature.

Polyurethane has been successfully applied to civil engineering applications such as the

sandwich plate system (Linder, 1995; Braun 1999; Funnell 2000), which was first

developed for ship outer hulls and then was adapted to bridge deck replacements, as will

be discussed in the literature review in Chapter 3. The following sections will provide a

Page 50: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

35

comparison of the properties of epoxy and polyurethane and explain why polyurethane is

considered more suitable for rapid deck replacement.

2.5.1. Material Properties

Unlike steel and other common materials, properties of the adhesives are not

standardized since the adhesive can be customized to achieve a wide range of properties

depending on the usage. Table 2.1 presents a comparison of the general properties of

epoxy and polyurethane gathered from different sources including data from various

research studies and data provided by BASF Canada Inc., who is the industrial partner in

this study. The values presented in Table 2.1 are only provided as a comparison between

the two adhesives and the values can vary according to the actual formulations of the

adhesives. Generally, it can be concluded that polyurethane is relatively less stiff than

epoxy and is a more ductile material.

2.5.2. Cure Time

As discussed by Adderley (1988), one of the concerns in using epoxy is the long

setting time. The setting time can be defined as the point at which the adhesive solidifies.

The different components of the adhesive will continue to react and the adhesive will

gradually gain its strengths over time. The study by Issa et al. (1995) stated that the

epoxy resin used in filling the shear pockets during the rehabilitation of the Amsterdam

Interchange Bridge that used precast full-depth concrete panels required up to 2 hours to

set and in the case when the same resin is used as a sealant in the transverse keys, the

setting time took up to 5 hours due to the low mass of material in the thin joint. A study

Page 51: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

36

Table 2.1: Comparison of General Properties of Epoxy and Polyurethane

Epoxy Polyurethane

Young’s Modulus, E (MPa) 12300 1 45 - 2200 3

Shear Modulus, G (MPa) 4580 1 15 – 700 3

Tensile Strength, Fu (MPa) 19.5 1 9.2 - 704

Elongation at Failure (%) 16 1 300 4

Poisson’s Ratio 0.34 1 0.49 3

Pot Life (min) 90 5 2 - 13 4

Bond Strength – Concrete to Steel (MPa) 18 5 5.51

Note: 1. From Si Larbi et al. (2006) 2. From Issac et al. (1998) 3. From Braun (1999) 4. From Hepburn (1992) 5. From SIKA 30 Technical Data Sheet (2007)

by Li et al. (2000) that investigated the strengthening of concrete beams with adhesively

bonded steel plates used an epoxy resin that required a minimum curing time of 20 hours.

In addition to the long setting time, the strength gain of an epoxy adhesive is also slow.

After 24 hours of curing at 15 oC, an epoxy could only gain approximately 20% of its full

shear strength (SIKA, 2007). The long curing time, however, permits the application of

the epoxy adhesive without any special machinery.

On the contrary, the polyurethane is characterized by its fast setting time. For

example, one of the formulations of polyurethane developed for this research study has a

setting time of only 13 minutes (Gardin, 2007). Furthermore, polyurethane generally

gains strength relatively faster than an epoxy resin. Figure 2.10 shows the flexural

strength development of the Elastocast 5039, formulated by BASF Canada Inc. for this

Page 52: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

37

research. As shown on the plot, the flexural stffiness of the polyurethane reaches

approximately 750 MPa after 4 hours of curing, which is 55% of its designed stiffness

and after 24 hours of curing, the polyurethane reaches approximately 83% of its full

strength.

Flexural Stiffness vs. Time

0200400600800

1000120014001600

0 25 50 75 100 125 150 175 200

Hours of Cure

Flex

ural

Stif

fnes

s, M

Pa

Figure 2.10: Strength Gain Behaviour of Elastocast C5039, BASF Canada (Gardin, 2007)

Although both an epoxy and polyurethane could be a suitable adhesive as the

shear connector in composite bridges in terms of their strengths, the fast curing time and

quick strength gain of polyurethane makes it a better choice in rapid deck replacement.

The long setting time of epoxy would become impractical when the window of

construction time is only six to eight hours in a night closure.

The remaining sections of this chapter will focus the discussion on using

polyurethane as the adhesive for bonding concrete decks to steel girders in composite

bridges.

Page 53: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

38

2.6. Polyurethane Elastomer Adhesive

Prior to further discussion of the design considerations necessary for the use of

polyurethane, a brief description of its chemical properties and processing procedures is

necessary. In general, polyurethane elastomer is a polymer of which the chemical

structure consists of three main building blocks: a polyol, an isocyanate, and a chain

extender (Hepburn, 1992). The physical and mechanical properties of the polyurethane

elastomer are dependent on the properties related to these three building blocks, which

dictates the flexibility of the chain segments, the entanglement of the chains, and the

forces between the chains. The unusual higher strength, hardness, modulus and

elongation at failure of polyurethane compared to most elastomers are a result of the long

polyurethane chains that contain large number of polar groups that are free to align

themselves to form strong physical and chemical bonds (Hepburn, 1992). These bonds

prevent the chains from sliding over each other under an applied stress, therefore,

yielding a high modulus and a high strength.

A common method in processing and manufacturing polyurethane involves the

pre-mixing of the polyol and chain extender, which results in a resin that will be mixed

together with the isocyanate and injected in the mould. This is referred to as the Reaction

Injection Moulding (RIM) or Liquid Injection Moulding (LIM). This method requires

accurate consideration of the temperature, pressure and moisture content of the materials

for the proper formation of the polyurethane. This was the method used in the pilot

testing conducted by Ramsay (2007), but the pressure of the injection might have caused

turbulence in the polyurethane that resulted in foaming and improper bonding of the

Page 54: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

39

polyurethane to the concrete and steel. In this study, the resin and the isocyanate were

hand-mixed for two minutes to address this problem.

2.7. Construction Consideration

Since no mechanical connection is provided between the two composite

components, it is important that the polyurethane adhesive can develop its required

strength under field conditions. The setting of polyurethane is a chemical reaction and is

very sensitive to variables such as the presence of contaminants at the bonding surfaces,

presence of moisture in the uncured state of the adhesive, and the temperature during the

cure. This section briefly provides a guideline to address these issues under the field

conditions.

2.7.1. Surface Treatment

One essential condition for good bond development is a contaminant-free surface.

Any form of contaminant – oil, grease, dust, metal corrosion product or release agents

can cause an improper bonding between the adhesive and the adherends. Sandblasting of

the steel girder preceded and followed by a solvent wash can easily remove any

contaminants that could cause bonding problem (Adderley, 1988). A primer and other

additives, such as a wetting or foaming agent, can also be used to enhance the bond at the

steel interface (Gardin, 2007).

Page 55: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

40

2.7.2. Moisture

Uncured polyurethane is very sensitive to the presence of moisture (Adderley,

1988). The moisture content must be strictly controlled before the mixing the components.

A moisture content of less than 0.07% is desirable for a satisfactory processing (Hepburn

1992). An increase in moisture content can affect all of the structural properties, namely

up to a 40% decrease in tensile strength. It is necessary to make sure that the materials are

relatively dry when the polyurethane is applied. This also means that the concrete panels

must be air dried after reaching the necessary compressive strength under standard moist

curing. Furthermore, the moisture content of the two components, the resin and the

isocyanate, must also be monitored closely before and during the mixing to ensure proper

curing of the polyurethane.

2.7.3. Temperature

The working temperature of the adhesive material should be above -450C, below

which the chemical structure of the polyurethane would change and would fail in a brittle

manner. During the processing of the polyurethane, the adherends must be heated to a

temperature of at least 40 oC for the proper curing of the adhesive. The reason for this is

because the formation of the polyurethane is an exothermic reaction and substrates at a

lower temperature would act as a heat sink, which would result in an inconsistent curing

of the polyurethane because the reaction rates of the different chemical components

change with temperature. Although this might only be practical for construction in the

summer or in locations with a hot climate, the scope of this research is to develop a

feasible adhesive connection under ideal lab conditions. Further development of the

Page 56: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

41

formulation and special treatment of the substrates are needed for applications in lower

temperatures, which would usually involve the addition of a catalyst to facilitate the

reactions of the components.

2.8. Summary

The effects of the slip on the overall stiffness of the structure requires that the

selected adhesive must have sufficient shear stiffness to ensure that the shear deformation

in the adhesive joint will not significantly increase the deflection of the bridge at service

loads. This study proposes two limit state criteria:

1) At serviceability limit state:

The additional deflection of a composite bridge with partial interaction between

the concrete and steel shall not exceed 20% of the overall deflection of its design with

full interaction. This proposed value will be examined in the analytical component of this

study in Chapter 6. If the additional deflection exceeds this limit, further investigation

that is beyond the scope of this project is needed.

2) At ultimate limit state:

The adhesively bonded connection must also have sufficient shear strength to

allow the concrete deck and steel girder to develop their full plastic capacity under

ultimate loading. Based on the criteria determined from the analytical component that

will be discussed in Chapter 6 of this study, the adhesive bond should be able to resist a

minimum stress of 3MPa under the ultimate limit state.

A comparison between epoxy and polyurethane shows that the use of

polyurethane is more appropriate in rapid deck rehabilitation. The experimental program

Page 57: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

42

in this research study, conducted in association with the BASF Canada Group, was

designed to develop and characterize a formulation of polyurethane elastomer adhesive

that will satisfy the criteria under the serviceability and ultimate limit states.

Page 58: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

43

CHAPTER 3: LITERATURE REVIEW

The chapter begins with a discussion of the series of research studies by Carleton

University in Ottawa (Linder, 1995; Braun, 1999; Funnell, 2006) on the composite

structural laminate (CSL) plate system that inspired the development of the adhesive

shear connection discussed in this study. This is followed by a brief summary of two

recent research studies, one by Si Larbi et al. (2006) and one by Bouazaoui et al (2006),

which investigated steel-concrete composite beams connected by bonding. Lastly, the

pilot study conducted by Ramsay (2007) at the University of Toronto on using a

polyurethane adhesive as a shear connection in concrete-steel composite beams is

outlined.

3.1. The Development of the Composite Structural Laminate (CSL) Plate System, by Carleton University, Ottawa

An extensive series of research studies under taken at the Carleton University in

Ottawa investigated a new sandwich plate system called the composite structural

laminate (CSL) plate system, which consists of two steel plates bonded to a polyurethane

elastomer core (Linder, 1995; Braun, 1999; Funnell, 2000). This system was developed to

replace the conventional outer hull in double hull oil tankers in order to eliminate steel

stiffening plates, which were the major causes for fatigue and corrosion problems. The

system that was investigated is shown in Figure 3.1.

The initial investigation in this series of research studies conducted exploratory

tests of the system to determine its behaviour and to determine a plastic core material

Page 59: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

44

appropriate for such system (Linder, 1995). The study conducted by Braun (1999)

involved an experimental program to test the design philosophy of the system and to

Figure 3.1: Composite Structural Laminate Plate System Used as the Outer Hull of the Product Oil Tanker (Figures taken from Linder, 1995)

develop, with an industrial partner, a polyurethane elastomer formulation that was

suitable for maritime structures. Lastly, Funnell (2000) conducted large scale experiment

on the CSL system based on the results from Braun (1999).

The polyurethane elastomer used was the EC-609-002/18 developed by

Elastogran to attain a minimum required modulus of 275MPa at a maximum temperature

of 100oC. The properties of EC-609-002/18 is provided in Table 3.1. Shrinkage must also

be controlled to ensure the integrity of the bond between the steel plates and the core.

Braun (1999) suggested that flocculates such as calcium carbonate or 5% to 10% of air

entrainment could be used to control the shrinkage provided that they do not significantly

reduce the strength and stiffness of the material. The direct shear and direct tension bond

Page 60: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

45

Table 3.1: Mechanical Properties of EC-609-002/18 (after Braun, 1999)

Mechanical Properties Measurements Units Test Procedure

Hardness 70 Shore D DIN 53 505

Tensile Strength 22.7 MPa DIN 53 504

Elongation at Fracture 26 % DIN 53 504

Young’s Modulus 517 MPa DIN 53 497

Table 3.2: Tension Bond Test of the Polyurethane Elastomer Core (after Braun, 1999)

Test Bond Strength, MPa

-40oC 7.24 20 oC 7.68 Shear 60 oC 6.45 -40oC 6.06 20 oC 4.18 Tension 60 oC 3.72

a. b.

Figure 3.2: a) Shear Bond Test b) Direct Tension Bond Test used by Braun (1999)

Page 61: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

46

test used in the study by Braun (1999) are shown in Figure 3.2 a and b, respectively. The

results of the bond tests at -40oC, 20oC, and 60oC are shown in Table 3.2. Generally,

Braun (1999) found that the values obtained from the direct tension tests were not

representative of the actual bond strengths because the additional shear stress at the

corners of the polyurethane-steel plate interface due the poisson affect would cause

peeling of the elastomer core from the steel plates and result in a sudden bond failure.

In addition to the experimental analysis, Braun (1999) also performed numerical

analyses to accurately describe the flexure and in-plane compressive behaviours of the

plate system. Figure 3.3 shows schematically the finite element models used by Braun

(1999), who suggested that the system should be designed so that the section could reach

the plastic moment capacity of the plates without local failure, namely debonding with a

local buckling of the plates. The beams studied have a total length of 2m and width of

200mm, and the CSL plate system is composed of two 10mm plates with a 50mm

polyurethane elastomer core. The plates were modeled assuming perfect bonding

between the materials and plane section would remain plane. The results, shown in

Figure 3.4, are presented in moment – mid-span deflection plots, of which the moment

was expressed as a ratio of the plastic capacity of the steel plates. The two dotted lines

represent the elastic and the plastic capacity of 33.8 kN-m and 44.02 kN-m, respectively.

Due to the non-linear behaviour of the polyurethane core, the stiffness of the beam

reduces gradually, as opposed to a significant loss in stiffness as expected from a regular

steel beam. As can be seen from Figure 3.4, the maximum moment capacity of the

sections was dictated by the plastic capacity of the steel plates without any local failures.

Page 62: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

47

Figure 3.3: Finite Element Models Used for the Study of Flexural Behaviour of CSL Beams - a) Shell

Element Model; b) Solid Element Model (Figures taken from Braun, 1999)

Figure 3.4: Moment-Deflection Plots of the Analyses of the CSL Beam in Flexure with Various

Polyurethane Stiffness (Figures taken from Braun, 1999)

Page 63: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

48

The analysis showed that the systems would become more flexible as the Young’s

modulus decreased due to an increase in shear deformation of the polyurethane core.

Lastly, the maximum transverse shear stress was found to be approximately 8.5 MPa,

therefore, a minimum bond strength of 8.5 MPa must be provided to avoid a brittle bond

failure. The preliminary numerical analyses conducted by Braun (1999) had provided

insights into the minimum bond strength and the minimum modulus of the elastomer

required for the sandwich plate system to reach its full plastic capacity at failure, in both

flexure and compression. These results were used and compared in the next phase of the

experimental program conducted by Funnell (2000).

Funnell conducted a large-scale experimental program that tested the CSL plate

system in flexure and in-plane compression to verify the numerical models that were

developed in the previous phases of the research. The expected behaviour of the beams

were calculated based on an equivalent section of steel, which was basically the two

plates separated by an equal distance from the centroid of the section since the modular

ratio of the polyurethane to steel is minimal (approximately 0.0032). Therefore, the

flexural moment capacity of the specimens would be equal to the plastic capacity of the

steel plates. The results of the tests are shown in Figure 3.5. Funnell (2000) encountered

premature failures in flexure caused by unexpected torsional effects due to the test setup,

which added to the expected shear stresses at the interface causing debonding of the steel

plates. The tests were modified and the experiment results for the remaining specimens

generally agreed with the analyses from the numerical study by Braun (1999). Therefore,

Braun’s model predicted the results well with tests-to-predict ratio of around 0.98 and

0.96 for flexural stiffness and plastic moment capacity, respectively. The maximum

Page 64: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

49

Figure 3.5: Moment Versus Mid-Span Deflection for Flexural Specimens by Funnell (2000)

transverse shear stress value measured during the tests was 5.1 MPa, which was lower

than the bond strength of 8.5 MPa.

Funnell (2000) concluded in the research study that the developed elastomer met

the design specifications for maritime structures. The techniques in the finite element

analysis models established by Braun (1999) were also verified. Therefore, the series of

research studies undertaken at the Carleton University has successfully designed a

sandwich plate system, of which the flexural and in-plane compressive behaviour can be

accurately described by numerical models.

The series of research on the CSL system by Carleton University sets an

encouraging precedent of implementing polyurethane into structural systems. This

extensive series of research studies has also provided an example to the necessary

analyses necessary to determine and define the feasibility of a structural system that usesf

an adhesive bond as a mean of shear connection. The system, which is now named the

Page 65: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

50

Sandwich Plate System (SPS), has been well adopted in the maritime, as well as civil

engineering applications (Farmer, 2006).

3.2. Static Behaviour of Steel Concrete Beam Connected by Bonding, by Si Larbi et al. (2006)

The research study by Si Larbi et al. (2006) examined adhesive connections in

steel-concrete composite highway bridges. Two types of adhesives for the shear

connections were investigated: epoxy mixed with silica sand and polyurethane. The

study included an experimental component and an analytical component. The

experimental component involved push-off tests of the adhesive connections, as shown in

Figure 3.6, and the results were verified with computer models of the specimens. The

analytical component involved computer modeling of steel-concrete composite beams

with either conventional headed stud connections or adhesively bonded shear connections.

The different types of connections were compared in terms of the deflection, slip, strain,

and stress of the computer models in the analysis.

Si Larbi et al. (2006) examined the effects of the types of resins, the thickness of

bonding joints, and the surface treatments in the experimental part of the study. The

details of the parameters are summarized in Table 3.3 and the properties of the adhesives

used in the study are shown in Figure 3.7. As can be seen, the epoxy had a higher

Page 66: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

51

Figure 3.6: Push-Off Tests Conducted by Si Larbi et al. (2006), as adopted from the Eurocode (1994)

Figure 3.7: General Properties of the Adhesives (Figure taken from Si Larbi et al., 2006)

ultimate strength, Fu, and was much stiffer compared to the polyurethane, which had a

lower strength but a larger elastic deformation. Tg is defined as the Glass Transition

Temperature, under which the properties adhesive will change and it will fail in a brittle

Page 67: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

52

manner. High strength concrete with 28 days compressive strength of 67 MPa was used

in the push-off tests to prevent tensile and shear failures in the concrete. The steel girder

were 300mm sections cut from an HEA 100 rolled beam with a yield strength of 235

MPa. The adhesive was allowed to cure for 7 days at 20 oC to allow full polymerization

of the materials. The concrete slabs were sandblasted an hour before the bonding, and the

steel girders were either washed once by acetone, a solvent used to eliminate the

contaminants at the steel surfaces, or sandblasting followed by an acetone wash and a

primer dump, a chemical agent that is used to enhance the bonding between the

polyurethane and steel. A 1mm layer of calamine was applied to the surface of the steel

after sandblasting to aid the bonding of the adhesive to the steel surface. The results of

the push-off tests are shown in Table 3.3 and Figure 3.8. The specimen with the 3mm

thick polyurethane joint was deemed unsuccessful because of the unexpected failure that

happened at the interface due to an incomplete bonding. The reason was not clear but Si

Larbi et al. (2006) related the problem to the high fluidity of the polyurethane

formulation used that prevented it to bond properly when the thickness is higher.

Failures in the other specimens were cohesive, meaning it was a material failure that

happened in the adherends. The cohesive failure happened either in the 1mm calamine

layer or in the concrete, as shown in the Figures 3.9. The ultimate shear stress averaged

between 5.0 to 5.9 MPa. Though the ultimate shear stress depended only slightly on the

parameters examined, the stiffness of the connections varied greatly between 12 to 46

MN/mm, with epoxy connections being twice to four times more stiff than those of the

polyurethane.

Page 68: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

53

Table 3.3: Summary of Adhesive Push-Off Tests by Si Larbi et al. (2006)

Resin Surface Treatment

Joint Thickness

(mm) Failure Mode

Ultimate Average

Load (kN)

Ultimate Average

Shear stress (MPa)

Tangent Bonding Stiffness

(MN/mm)

Acetone 1.2 Cohesive in Calamine 104 5.2± 0.3 46

Corumdum + Primer 1.2 Cohesive in

Concrete 118 5.9± 0.1 47 Epoxy

Corumdum + Primer 3 Cohesive in

Concrete 110 5.5± 0.1 23

Acetone 0.2 Cohesive in Calamine 100 5.2± 0.0 11

Corumdum + Primer 0.2 Cohesive in

Concrete 104 5.2± 0.3 12 Polyurethane

Corumdum + Primer 3 Interface 7 0.3± 0.1 -

Figure 3.8: Average Shear Stress versus Slip from Push-Off Tests (Figure taken

from Si Larbi, 2006)

Page 69: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

54

a. b.

Figure 3.9: Failure Modes in Push-Off Tests a) Failure in Calamine; b) Failure in Concrete (Photos taken from Si Larbi, 2006)

Figure 3.10: Characteristics of Connectors (Figure taken from Si Larbi et al., 2006)

Two shear stud connections were compared to the adhesively connections bonded

by polyurethane and epoxy, respectively. The load-slip behaviour of the shear stud

connections is shown in Figure 3.10. The shear connectors were classified as rigid,

ductile and semi-ductile depending on the slips at their ultimate stress, sult. The

connection stiffness, k, used in the numerical analysis was calculated based on the

tangent stiffness, Ktangent of the connectors, as shown in Figure 3.10, divided by a spacing

Page 70: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

55

of 150mm. The stiffness values were then compared to those of the bonded connections,

which can be calculated by dividing the tangent stiffness values obtained from the push-

off tests by the length of the adhesive bond of the specimens. The stiffness values are

shown in Table 3.4. Generally, the stiffness of the adhesive bond connection is

comparable to that of a rigid headed stud connection.

Table 3.4: Comparison of the Stiffness between Connectors and Bonding (after Si Larbi et al., 2006)

Connection Rigid Connector

Semi-Rigid

Connector

Ductile Connector

Epoxy 1.2mm

Epoxy 3mm

Polyurethane 0.2mm

k (MN/m2) 16000 3333 2000 37600 18400 8800

Figure 3.11: Cross Section of the Composite Beam Studied by Si Larbi et al. (2006)

The cross-section of the 5m beam studied by Si Larbi et al. (2006) is shown in

Figure 3.11. The numerical analysis used was based on a model that provided closed-

form solutions to the behaviour of a composite beam by taking into account the interlayer

slip between the concrete and steel sections. The model was designed to analyze

composite beams connected by mechanical connectors, and the stiffness of the connectors

Page 71: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

56

was assumed to be distributed uniformly along the length of the beam. The bonded

connections were compared to two ductile stud arrangements, with two rows of 19mm

diameter studs, 80mm in height and spaced at 150mm or 450mm. The connections were

also compared to the case where there was no slip between the concrete deck and the

steel beam, often referred to as a perfect bond where the assumption of plane sections

remain plane remains valid. The strain distributions at the mid-span of the composite

beams with the different connection configurations are shown in Figure 3.12, and the

corresponding stress values are presented in Table 3.5. The value k shown in Table 3.5

corresponds to the connection area stiffness, as discussed in Chapter 2. As can be seen

from the strain distributions, the adhesively bonded connections were very stiff compared

to those of the conventional studs that the slips at the interfaces of the bonded

connections were less than 5% of those in headed studs. In fact, both bonded connections

had a linear distribution of strains, which is characteristic to a perfect bond. The computer

analysis also showed that the maximum shear stress at the bonding interface remained

lower than 3 MPa and the yielding of the steel girder occurred before failure at the joint.

This indicates that the bond was strong enough to allow the development of the full

plastic strength of the steel section at ultimate limit state.

The study by Si Larbi et al. (2000) has provided insights into the behaviour of

adhesively bonded composite sections under loading. Although the stiffness of the

adhesive joint greatly depends on the thickness of the joint and the nature of the adhesive,

the study suggested that an adhesive bond can be very stiff that the interlayer slip

between the concrete and steel sections can be ignored. Si Larbi et al. (2000) also

suggested that adhesively bonded connection must be able to resist a longitudinal shear

Page 72: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

57

stress of at least 3MPa, which will be verified in the analytical program of the current

study in Chapter 6.

Figure 3.12: Strain Distribution at Midspan (Si Larbi et al., 2006)

Table 3.5: Behaviour of the beams with different types of connection under a concentrated load, 250KN, applied at midspan (after Si Larbi et al., 2006)

Studs, spa. = 450 mm

Studs, spa. = 150mm

Bonding PU

t = 0.2mm

Bonding Epoxy

t = 1.2 mm

Perfect Bond

(no slip)

k (MPa) 667 2000 88000 376000 infinity

Deflection (mm) 9.9 8.4 7.6 7.6 7.5

σc,top (MPa) -17.0 -16.9 -16.8 -16.8 -16.8

σc,bottom (MPa) 2.1 -0.5 -3.9 -3.9 -4.2

σs,top (MPa) -131.1 -86.4 -34.4 -29.6 -25.1

Mid-Span

σs,bottom(MPa) 256.6 246.2 234.1 232.9 231.9

Slip (µm) 470 167 4 1 0 Extremity Shear Stress

(MPa) - - 2.2 2.4 -

Page 73: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

58

3.3. Experimental Study of Bonded Steel Concrete Composite Structures, Bouazaoui et al. (2006)

The research study by Bouazaoui et al. (2006) involved an experimental analysis

of adhesively bonded steel-concrete composite beams. They explained that the use of an

adhesive material to replace conventional shear studs can: 1) Eliminate stress

concentration at the connections; 2) Create a lighter structure; 3) Protect the steel girder

from corrosion; and 4) Allow the use of precast concrete slabs instead of cast-in-place

concrete.

Similar to the experiment by Si Larbi et al. (2006), the study investigated two

different adhesives: an epoxy with a Young’s Modulus of 12300 MPa and a polyurethane

elastomer with a Young’s Modulus of 80 MPa. The effects of two parameters on the

overall structural performance of composite beams were examined: 1) The characteristics

of the adhesives; 2) The variable thickness of the adhesive joint in the transverse and

longitudinal directions, as demonstrated in Figure 3.12b and 3.13b. The beam sections

that were used in the experiment are shown in Figure 3.12. Four beams were tested in the

study: Three connected with the epoxy adhesive; and one with the polyurethane adhesive.

Of the three connected with the epoxy adhesive, one had variable thickness from 3 to

5mm in the transverse direction (Figure 3.12b) and the other from 3 to 7mm in the

longitudinal direction (Figure 3.13b). Table 3.6 summarizes the geometry of the beams

studied by Bouazaoui et al. (2006).

Page 74: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

59

Table 3.6: Geomety of Beams Studied by Bouazaoui et al. (2006)

Beam Transverse Thickness Longitudinal Thickness Adhesive

P1 Constant – 3 mm Constant – 3mm Epoxy

P2 Constant – 3 mm Constant – 3 mm Polyurethane

P3 Constant – 3 mm Varies – 3mm to 5mm Epoxy

P4 Varies – 3mm to 7mm Constant – 3mm Epoxy

/

a. b.

Figure 3.12: Cross-Section of the Beams Studied by Bouazaoui et al. (2006) - a) Constant Joint Thickness; b) Varying Joint Thickness in the Transverse Direction (FIgures taken from Bouazaoui et al., 2006)

a. b.

Figure 3.13: Composite Beams Studied by Bouazaoui et al. (2006) - a) Constant Joint Thickness; b) Varying Joint Thickness in the Longitudinal Direction (Figures taken from Bouazaoui et al., 2006)

Page 75: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

60

The beams in the tests were compared in terms of the failure mode, the ultimate

deflection at midspan, the strains in the concrete and steel at midspan, the relative slip

between the concrete slab and the steel beam, and the ultimate load. The theoretical

ultimate load was calculated based on the plastic capacity of the beams, which was

calculated assuming that:

a) The steel and concrete reach their maximum strength

b) The entire steel beam section has yielded, with stresses equal to the yield

stress, Fy.

c) The entire concrete section has a uniform compressive stress of 0.85f’c,

which is the plastic capacity of concrete.

d) The plane section remains plane for the entire cross-section.

e) The tensile strength of the concrete can be neglected.

The stress distribution and the corresponding forces in the concrete and steel, Fc

and Fs, at the cross-section at its plastic capacity are illustrated in Figure 3.14. In this

study, Bouazaoui et al. (2006) designed the cross-sections to maximize the shear stress at

the adhesive layer to allow the development of the maximum compressive strength of the

concrete slab and the maximum tensile strength of the steel girder, therefore, the plastic

neutral axis should be situated right below the concrete section in the steel top flange.

The plastic moment capacity could then be determined by taking moment of all the forces

in the cross- section.

Page 76: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

61

Figure 3.14: Stress Distribution of Composite Section at its Plastic Capacity (Figure taken from

Bouazaoui et al., 2006)

Table 3.7: Comparison between Experimental Ultimate Load, F u,c and Theoretical Ultimate Load, Fu,t

Composite Beam Fu,c (kN) Fu,t (kN) , ,

,

*100u c u t

u c

F FF

⎛ ⎞−⎜ ⎟⎜ ⎟⎝ ⎠

P1 238 206 13.4 P2 185 206 -11.4 P3 246 206 16.3 P4 219 206 5.9

The results of experimental beams and the theoretical beams are shown in Table

3.7. In general, the three epoxy connected beams had similar behaviour despite the

irregularities in the thickness of the joint. Figures 3.15 and 3.16 show the failure modes

and the ultimate deflection of the beams, respectively. The beams with the epoxy joint

were stiffer and the failure modes were always brittle with steel yielding and concrete

crushing, as shown in Figure 3.15a. The beam connected by the polyurethane adhesive,

however, was significantly more flexible with a greater vertical deflection and a greater

shear deformation in the joint, as shown in Figure 3.15b. The ultimate load of the beam

Page 77: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

62

a. b.

Figure 3.15: Failure Modes of Beams - a) P1 with concrete crushing; b) P2 with yielding of steel, shearing of the adhesive joint and concrete cracking (Pictures taken from Bouazaoui et al., 2006)

Figure 3.16: Deflection at the Midspan (Figure taken from Bouazaoui et al., 2006)

connected by the polyurethane adhesive was 11% less than the theoretical ultimate load

due to the lower strength of the adhesive. This suggests that the ultimate strength of the

adhesively bonded composite beams greatly depends on the strength of the adhesive bond.

The beams with the epoxy connection were found to have a linear strain

distribution with no slip between the concrete and steel, while the cross-section with the

polyurethane adhesive experienced an interlayer slip between the concrete slab and the

steel beam, as shown in Figure 3.17.

Page 78: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

63

The above review of the study by Bouazaoui et al., (2006) suggests that the

behaviour of the adhesively bonded composite section greatly depend on the stiffness of

the adhesive and the strength of the adhesive bond. The experimental results demonstrate

that the connections bonded with an epoxy, a stiffer adhesive, had lower deflection at

failure, but the failures were always brittle. The epoxy connections had sufficient bond

strength that allowed the concrete and steel sections to reach their plastic strength at

failure. In the case where the connections were bonded with polyurethane, the deflection

at failure was higher, but the connection did not have sufficient bond strength to allow the

full development of the plastic strength of the concrete slabs and the steel beams, that is,

it had a bond strength that was lower than the plastic capacity of the concrete or the steel

section, which resulted in a reduction of the ultimate flexural strength of the section.

a. b.

Figure 3.17: Strain Distributions of the Section with a) Epoxy Joint; b) Polyurethane Joint (Bouazaoui et al., 2006)

Page 79: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

64

3.4. Shear Resistance of a Polyurethane Interface in Concrete-Steel Composite Beams, by Ramsay (2007)

A preliminary investigation that involved the testing of twenty specimens using

standard push-out tests, as recommended by the Eurocode 4 (ENV 1994-1-1), was

performed by Ramsay (2007) with the objective to develop a feasible configuration of

adhesive shear connection between concrete and steel. The resin and isocyanate were

mixed in a machine to form the two-part polyurethane and the mixture was then injected

into the cavity created between the precast concrete slab and the steel girder at a pressure

of 13.8 MPa (2000 psi) (Ramsay, 2007). Figure 3.19 shows the design of a typical push-

off specimen. After proper curing of the adhesive, the specimens were tested with the

goal to obtain the load-slip behaviour of the various connections.

The tests were not conclusive in characterizing the behaviour of the adhesive

shear connections. The polyurethane layers in the specimens were not adhering properly

to the substrates and premature brittle bond failures occurred in all of the tests conducted.

Figure 3.18 shows the debonding of the girder from the concrete slab. Generally, air

bubbles and a layer of foam were found in the polyurethane layers, and there also

appeared to be a lack of adherence of the joint to the steel surfaces. Representative from

BASF Canada Inc. (Gardin, 2007) had hypothesized the following possible causes of the

bonding failure:

1) The injection of the polyurethane under the high pressure might have caused

turbulence in the polyurethane layer, which might have been the cause for the

layer of foam and bubbles near the surface of the adhesive joint.

Page 80: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

65

Figure 3.18: Push-Off Specimens (Ramsay, 2007)

Figure 3.19: Debonding of the Push-Off Specimens (Ramsay, 2007)

Page 81: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

66

2) Shrinkage of the polyurethane material might be responsible for the unbonded

areas between the adhesive layer and the substrates.

3) Pressure from the chemical reaction of the two-parts polyurethane might have

lifted the concrete slab slightly and induced air bubbles near the surface of the

polyurethane layer.

The hypotheses of the possible causes of the bonding problems and the insights

obtained from the pilot testing have led to the design of the new experimental program in

this research study.

3.5. Summary

The literature review presents the research of the composite structural plates that

inspired the use of polyurethane to adhesively bond precast concrete panels and steel

girders for composite interaction. The two recent research studies discussed also

demonstrated the possibility of replacing a conventional headed shear stud connection by

an adhesive bond in concrete-steel composite beams. The research studies have also

presented the possible failure modes that should be considered when adhesively bonded

shear connections are considered. Lastly, the study by Ramsay (2007) has provided

insights into the development of the polyurethane adhesives and the adhesive joint

configuration used in the experimental program in this research study.

Page 82: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

67

CHAPTER 4: EXPERIMENTAL PROGRAM

The goal of the experimental component of this research study was to develop a

polyurethane formulation that will meet the criteria for its use as a shear connection in

composite bridges. Although considerations of field conditions, such as the moisture and

temperature, are important, the scope of the experimental part of this study is to develop

the polyurethane adhesive under lab conditions by focusing mainly on the strength and

stiffness of the connection. The push-off tests were used to characterize the strength and

the stiffness of the polyurethane adhesive layer. Nineteen small-scale push-out specimens

were used to study the effects of the different variables on the bond strength of the

adhesive shear connection. The load-slip behaviour of each of the shear connections was

characterized. The results obtained from the experiments would then be used in the

analytical part of this research study.

This chapter begins with a description of the fabrication process of the specimens.

This is followed by a discussion of the different variables that were considered to have a

potential influence on the bond strength of the adhesive connection. Lastly, the setup and

the instrumentation of the push-off tests are presented.

4.1. Modified Push-Off Test Specimens

With the insights obtained from the pilot testing by Ramsay (2007), a new set of

push-off test specimens were designed for this study. The objectives of the experimental

component of this research study were to:

Page 83: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

68

1) Develop a shear connection system using a polyurethane adhesive that can

adequately bond concrete slab and steel girders in composite bridge construction.

Minimum bond strength of 3MPa should be achieved.

2) Investigate the variables that can affect the bond strength between the

polyurethane and the substrates.

3) Characterize the load-slip behaviour of the adhesive bond connection.

4.1.1. Scope of the Experimental Program

An adequate adhesive shear connection system should satisfy the criteria

described in Chapter 3, namely the minimum shear and bond strength for the full

development of the plastic capacity of the concrete deck and the steel girders and

sufficient stiffness to minimize the deflection under service loads. Although the

compatibility with field conditions such as the moisture and temperature should also be

considered, the current experimental program was designed to perform under ideal lab

conditions with strictly controlled temperature and moisture level. The adequacy of the

adhesive connection is therefore defined as the following:

1) The polyurethane adhesive connection must have sufficient shear strength to resist

a minimum shear stress of 3 MPa, as verified in the analytical program

2) The polyurethane must be formulated to have sufficient stiffness that will

minimize additional deflection due the interlayer slip between the concrete slab

and steel girders in a composite bridge. Due to the lack of guideline in the current

design code to limit the deflection according to the stiffness of a bridge, this study

proposes that the adhesive connection should be stiff enough so that the ratio of

Page 84: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

69

the deflection of a composite bridge with slip to the deflection of the same design

without slip should be less than 1 to 1.2.

3) If the bond strength is below 3 MPa, the failure mode should be ductile and

failure should occur in the adhesive and not brittle bond failure at the interfaces.

4.1.2. Design Consideration for the Specimens

The push-out specimens were designed to connect two concrete slabs and a steel

girder by a polyurethane adhesive layer. The design of the specimens is shown in Figure

4.1. Several modifications were made to standard push-off tests to suit the need for the

adhesive connection. Firstly, the specimens were designed to be one-third of the size of

the full-sized specimens used in the research study by Ramsay, which were designed

according to the Eurocode (ENV 1994-1-1). The specimens were designed to be smaller

to ease the pouring process of the polyurethane that had to be done in a chemical lab. As

will be discussed, the polyurethane needed to be hand-poured instead of being injected

from a machine and, therefore, with the quick setting time of the polyurethane, manual

pouring of the adhesive layer of a full size specimen would be difficult. The slab

measured 180mm by 180mm with a thickness of 40mm. The steel section used was the

W100 x 19 produced according to the G40.21 350W. Secondly, due to an error in the

fabrication of the specimens, the steel girders were adhered flush to the concrete slabs as

opposed to being offset. Lastly, the concrete slabs were not reinforced as failure is not

expected to be in the concrete, and the slabs would be too small to provide sufficient

development length for the reinforcement.

Page 85: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

70

Figure 4.1: Small Scale Push-Off Specimens for the Experimental Program

The design of the specimens is shown in Figure 4.1. Three plastic tubes were

required for the pouring of the polyurethane into the cavity, which was created by

sandwiching a wooden form between the concrete slabs and the steel girder, as shown in

Figure 4.2. The 25mm plastic tubes were the pour tubes for the polyurethane and the

10mm tubes were the venting tubes from which any air in the cavity could escape as the

polyurethane adhesive filled the gap. The tubes were located as close to the edges of the

polyurethane layer as possible to allow as much air to escape from the cavity as possible.

Page 86: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

71

Figure 4.2: Wooden Form used in the Fabrication of the Specimens

As discussed in Chapter 3, the proposed polyurethane adhesive joint would

replace the bedding layer that, conventionally, would have been filled with a grouting

material. In practice, the thickness of the bedding layer can range between 20mm to

40mm depending on the geometric tolerance required. A thickness of 25mm thickness

was for the push-out specimens in the experimental program. The edges around the

wooden frame were sealed with a silicone sealant to prevent any leakage of the

polyurethane due to its low viscosity nature in the uncured state, as shown in Figure 4.3.

Page 87: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

72

Figure 4.3: Silicone Sealant Required to Avoid Leakage at the Joint

4.1.3. Fabrication of the Specimens

The specimens were fabricated in two phases: the first phase included the

fabrication of the concrete slabs, the steel girders, and the necessary formwork; the

second phase involved the assembly of the specimens and the pouring of the

polyurethane. Prior to the casting of the concrete, a layer of surface retarder, MBT®

DN320 (Master Builder Technical Data Sheet) was applied to the bottom face of the form

to delay the setting time of the concrete surface in order to create the roughened exposed

aggregate surface. The cementious material on the surface at which the retarder was

applied to was washed off with a pressure washer twenty-four hours after the concrete

casting. The roughness of the surface corresponds to a medium etch (5mm). (Master

Builders Technology Technical Datasheet). The concrete slabs were then moist-cured for

twenty-eight days under 70% humidity.

Once the concrete had reached its twenty-eight days strength, the slabs and steel

girders were transported to BASF for the pour of the polyurethane. The specimens could

not be assembled until the steel surfaces had been sandblasted, which must be done at

most twenty-four hours before the polyurethane pour. After the concrete slab, steel girder,

Page 88: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

73

and the wooden frames were assembled, the composite sections were heated in an oven to

a minimum temperature of 37 oC and stored until the time of the pour.

The two components of the polyurethane, a resin and the isocyanate, were

manually mixed and poured into the cavity through the pour tubes. The pouring setup is

shown in Figure 4.4a. Once the polyurethane began to exit from both vent tubes – an

indication that the cavity was completely filled and all the air had escaped, all three tubes

were immediately tightened by C-clamps, as shown in Figure 4.4b. Since the specimens

must be laid flat on one of the concrete slab for each pour, only one cavity could be filled

at a time and the second pour must wait until the first polyurethane layer had properly set.

After the pour were completed, the specimens were allowed to cure at room temperature

for at least seven days before they were shipped to University of Toronto for the push-off

tests.

a. b.

Figure 4.4: a) Setup for polyurethane pour; b) C-clamps used to tighten tubes after pour

Page 89: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

74

4.1.4. Materials

Concrete and Steel

All the concrete slabs were cast at the same time and stored under the same

ambient conditions. A concrete mix with a 28-days compressive strength of 55 MPa was

used for the slabs. The steel girders were 180mm in length cut from a W100 x 19 rolled

beam as specified according to the G40.21 350W with a nominal strength, f’y = 350MPa.

Polyurethane Adhesive

As discussed in Chapter 3, polyurethane was chosen as the bonding material for

the concrete and steel because it has a fast curing time and is usually ductile. Two

different polyurethane elastomer were formulated: The first one, which will be referred as

the Type A, contains three variations – CAE 1-1, CAE 2-1, and CAE 2-3a; and the

second type, which will be referred as the Type B, also contains three variations —

CAE 1-3, CAE 1-9, and CAE 1-10. The difference between the two formulations is the

different isocyanate that was used in each one. Type A was used in series 1 to 4 of the

push-off tests and the polyurethane was brown in colour, and Type B was used in series 5

of the tests and the polyurethane was white. The detailed chemical compositions of the

polyurethane adhesive are proprietary information that cannot be disclosed, but all the

formulations developed for the experimental program is a combination of the basic resin

processed by mixing the polyol and the chain extender, and the isocyanate, as seen in

Figure 4.5. The general properties of the formulations are summarized in Table 4.2.

Page 90: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

75

a. b.

Figure 4.5: Components of Polyurethane - a) Polyol and Chain Extender, b) Isocyanate used in Type A

The main difference between the three variations, CAE 1-1, 2-1 and 2-3a, of the

Type A polyurethane formulation is the amount of shrinkage that would occur as the

polyurethane cure and the different additives mixed into the formulation to promote

better bonding. Since one of the hypothesis for the cause of unsatisfactory bonding in the

pilot testing is the shrinkage in the polyurethane layer (Ramsay, 2007), the different

formulations were considered to address this issue. Consequently, the different

formulations also have different setting times and strength gain behaviour since the

shrinkage of the polyurethane is dictated by the curing behaviour; the faster the

polyurethane cures, the more shrinkage will occur. The CAE 2-1 and CAE 2-3a has a gel

time of 7 minutes and a shrinkage value of approximately 3-5 %, while the CAE 1-1 has

a gel time of 33 minutes and negligible shrinkage (Gardin, 2007). Variations of these

formulations with additives such as a wetting agent that could reduce the surface tension

of the polyurethane at its liquid state to promote better adhesion were also used.

Page 91: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

76

Table 4.2: General Properties of the Formulations of Polyurethane

Formulation Gel Time (min)

Shrinkage Level

Flexural Modulus

(MPa) Comments

CAE 1-1 33 Negligible 1031 Exhibit Better Elongation

CAE 2-1 13 Medium 1370 Slight amount of foaming agent

CAE 2-3a 13 High 1370 Contains foaming and wetting agent

CAE 1-3 13 Negligible 800 Softer material with better tolerance to tearing stress;

contains wetting agent

CAE 1-9 13 Negligible 800 Softer material with better tolerance to tearing stress

CAE 1-10 13 Negligible 800 Softer material with better tolerance to tearing stress

The Type B polyurethane contains a different isocyanate that resulted in a softer

material that was designed to allow more tolerance for tearing stress. This formulation

was used in Series 5 of the push-off specimens.

4.1.5. Test Variables

In addition to the different formulations of polyurethane, other variables and

parameters that could influence the bond strength of the adhesive connection were

examined. The specimens were divided in four series and each series was fabricated after

the previous series of specimens had been tested. This allowed modifications to the test

matrix and introduction of new variables as more insights were provided from the testing

of each series. The first series, consisted of three specimens, explored the pouring method,

Page 92: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

77

surface treatment, shrinkage in the polyurethane, and the temperature at which the

polyurethane was poured. The second series, with four specimens, examined the effect of

elevated specimen temperature when pouring the polyurethane and introduced a new type

of formwork for the cavity. The third series, consisted of three specimens, modified the

surface treatment of the steel girders. The fourth series introduced a primer and various

additives, including the polyol and the wetting agents. Lastly, the fifth series examined a

new type of polyurethane elastomer formulation. The following sections will discuss

these variables in details.

Two important surface treatments were kept common in all the specimens. Firstly,

the surfaces of all the concrete slabs that adhered to the polyurethane layer were

roughened, with exposed aggregates, because it would allow mechanical interlocking

between the adhesive and the concrete slab. Secondly, all the flanges of the steel girders

were sandblasted to ensure that the surfaces were free of rust and other surface

contaminants. This had to be done at maximum twenty-four hours before the pouring of

the polyurethane to avoid oxidation of the sandblasted surfaces.

Pouring Method

The first series consisted of three specimens that were used to explore some of the

insights obtained from the pilot investigation by Ramsay (2007). First of all, since the

turbulence, which was caused by the injection of the polyurethane through the machine at

a high pressure was hypothesized as the main cause of the foam and air bubbles in the

polyurethane layer in the pilot testing, the polyurethane adhesive was to be hand-mixed

and manually poured into the cavity of the new specimens. This eliminated all the air

bubbles and foam in the polyurethane layer in the hardened state.

Page 93: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

78

Temperature of Substrates

The formation of the polyurethane is an exothermic reaction and substrates at a

low temperature would act as a heat sink that could greatly affect the curing of the

polyurethane near the surfaces. Initially when the first series was being fabricated, the

specimens were kept in an oven prior to the polyurethane pour so the temperature of

specimens would be at approximately 37 oC. This was the minimum temperature required

for the proper curing of the polyurethane elastomer (Gardin, 2007). However, as will be

discussed in Chapter 5, unexpected bonding problems between the polyurethane and steel

girder led to the realization that a higher temperature might be necessary for proper

bonding between the polyurethane and the steel surface. The temperature of the

specimens was then elevated to 50 oC for in the latter series with the goal to achieve

better adhesion to the steel girder.

Shrinkage The effects of shrinkage in the polyurethane on the bond strength were explored

through the different formulations. As the bond layer shrinks, the expected volume of

polyurethane in the cavity would be lower than expected. Since the wooden formwork

used to create the cavity is incompressible, the intimate contact required between the

polyurethane and the substrates might be lost. Shrinkage is addressed by using a

formulation with negligible shrinkage, and a compressible form that would allow the

polyurethane to be under constant compression.

Page 94: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

79

Compressible Formwork and Clamping Force

One of the hypotheses for the cause of the premature bond failure in the pilot

testing by Ramsay (2007) is the pressure force generated in the chemical reaction of the

polyurethane that might have lifted the concrete slab slightly. A proposed solution to this

problem is the use of a compressible polyurethane formwork instead of wood. This

compressible formwork would allow the polyurethane layer to cure under compression

due to the self weight of the concrete slab. This not only could solve the potential

problem of the concrete slab being lifted, but it could also solve other contact problems

caused by shrinkage or occasional small leakage during the pour. The polyurethane used

as the formwork has very different properties of that used as the adhesive and the

dimensions of the forms are identical to that of the wooden forms. Figure 4.6 shows the

compressible polyurethane used in place of the wooden formwork.

Figure 4.6: Polyurethane Compressible Form

Page 95: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

80

An alternative solution was proposed to address the problem that could have been

caused by the pressure from the curing process of the polyurethane. A clamping force

was applied to the concrete slab and the steel girder as the polyurethane layer cured to

restrain any movement in the concrete slab and prevent any potential lifting. This was

achieved by fixing each corner of the slab to the flange of the steel girder a C-Clamp.

Surface Treatment

As already discussed, all the steel girders were sandblasted twenty-four hours

before the pouring of the polyurethane to remove any existing rust and contaminants.

Given previous experience of adhering polyurethane to steel, the sandblasting was

thought to be sufficient to provide a contaminant-free surface for appropriate adhesion.

However, as will be discussed further in Chapter 5, the consistent bond failures at the

steel interfaces suggested that the polyurethane was not adhering properly to the steel

surface. Therefore, different steel surface treatments were explored in the third and fourth

series of specimens.

In addition to the sandblasting, an acetone solvent was used to clean the steel

surfaces of the specimens fabricated in the fourth series. The surfaces were either only

washed once with the acetone solvent prior to the sandblasting; or twice, before and after

the sandblasting. Furthermore, the effect of using a primer to promote better adhesion of

the polyurethane adhesive to the steel surfaces was also studied. A primer was applied to

the specimens in series four and five series with two acetone solvent wash preceding and

following the sandblasting.

Page 96: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

81

4.1.6. List of Specimens and Variables

Table 4.2 lists the sixteen specimens and the variables associated with each one. As

shown in the table, three specimens were fabricated in series one, four in series two, three

in series three and the rest in series four.

Table 4.2: List of Specimens and Corresponding Variables

Series Specimen Polyurethane Formulation

Steel Surface Treatment

Temperature at Pour (oC) Other Variables

1-1 CAE 2-3a SB 37 1-2 CAE 2-1 SB 37 1 1-3 CAE 1-1 SB 37 2-1 CAE 1-1 SB 50 2-2 CAE 2-1 SB 50 2-3 CAE 2-3a SB 50

2

2-4 CAE 2-3a SB 50 Clamped 3-1 CAE 1-1 SB, AW1 50 3-2 CAE 1-1 SB, AW2 50 3 3-3 CAE 1-1 SB, AW2 50 PU Formwork 4-1 CAE 2-3a1 Primer 50 4-2 CAE 2-3a2 Primer 50 4-3 CAE 2-3a1 Primer 50 4-4 CAE 2-3a2 Primer 50 4-5 CAE 2-3a2 SB, AW2 50

4

4-6 CAE 2-3a2 SB, AW2, Primer

50

5-1 CAE 1-3 SB, AW2, Primer 50

5-2 CAE 1-9 SB, AW2, Primer 50 5

5-3 CAE 1-10 SB, AW2,

Primer 50 Note: SB - Sandblasting

AW1 - One acetone solvent wash prior to sandblasting AW2 - Acetone solvent wash before and after sandblasting PU - Compressible polyurethane material Primer - Prime applied to steel beams to enhance bonding

Page 97: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

82

4.1.7. Push-Out Test Setup and Instrumentation

The test-setup is shown in Figure 4.7. Since the steel beams were adhered flush to

the concrete slabs, the specimens had to be rested on two steel blocks, measured 200 x 60

x 80 mm, to allow room for the steel girder to displace. Furthermore, in order to

minimize the resultant horizontal forces acting on the adhesive joint that would cause

undesirable peeling stresses at the interfaces, two rectangular steel blocks were placed

directly on the top of the steel flanges so the load could be applied directly to the

adhesive joint.

Figure 4.7: Experimental Test Setup

Page 98: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

83

Figure 4.8: Riehle Machine, University of Toronto

Figure 4.9: Location of LVDT

Page 99: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

84

The applied load was measured by a load cell and the displacements of the steel

girders were recorded by two Linear Variable Differential Transformers (LVDT). The

relative displacements between the magnetic steel plates attached to the steel beam at the

bottom right corner of each side of the web to the floor were measured, as shown in

Figures 4.7 and 4.9. Each specimen was loaded up to failure without any unloading at a

rate of approximately 0.50 kN per seconds. Due to the sensitivity of the adhesive joint to

peeling stresses, the following preparation and loading procedures were used to prevent

any uneven loading that could cause rotation in the steel girder:

Preparation

1. Ensure the top of the steel girder has a flat surface for the load cell to rest on and

any caulking should be removed.

2. Prepare plastic for the plastering at the base of the concrete slabs on the steel

blocks. The size of the plastic should be approximately 100mm x 400mm. The

plastic should be wrapped around the base of the concrete immediately after the

plaster is poured and precautions must be made to ensure that the plaster/plastic

will not interfere with the polyurethane layer and the steel girder during the test.

Testing

1. Center the specimen to the load cell

2. Setup the LVDT at the bottom right corners on each face of the girder web. The

LVDT should rest on clamps on magnetic stands and should be in compression

for the test.

Page 100: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

85

3. Center the rectangular steel blocks onto the flanges of the girder. This ensures that

load is applied directly to the shear connections. Shimming might be necessary to

ensure that the rectangular blocks are resting completely on the flanges.

4. Load the specimens to failure at a rate of approximately 100 lb/sec (0.445kN/ sec).

Displacements of the girder should be noted every 1000 lb (4.451 kN).

5. At failure, note the failure mode, failure surface, and any rotation that might have

occurred.

Page 101: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

86

CHAPTER 5: TEST RESULT AND DISCUSSIONS

After the polyurethane had completely cured at approximately seven days after

the day of pour, the push-off tests specimens were tested and the load-deflection

behaviour was recorded for each specimen with the exception for the first three

specimens. This chapter presents the results from the push-off tests and summarizes the

failure mode and the failure surface for each specimen. The effects of the variables in

each set of tests on the adhesive joint are then discussed in their respective sections. The

estimation of the stiffness of the polyurethane adhesive joint from the load-deflection

plots is then provided.

5.1. Ultimate Load and Deflection

The ultimate loads and the deflections at failure recorded from the push-out tests

are summarized in Table 5.1. Cohesion failure refers to material failures in either the

concrete or within the polyurethane layer and the load-slip behaviour of the connection is

usually ductile. Bond failure refers to brittle failure at the interface between the

polyurethane and the concrete or steel. The ultimate load at each adhesive bond was

taken as half of the applied load and the ultimate shear stresses were calculated from the

as-built dimensions of the polyurethane layer. The displacement at failure is the

displacement of the steel girder taken as the average between the two LVDT sensors.

Failure surface “a” denotes that it failed on the side that was poured first, and “b” denotes

the side that was poured second. This was noted to study the possible effect of the

temperature increase of the steel girders on the curing of the second polyurethane layer as

the first layer cured and released heat from the exothermic chemical reaction.

Page 102: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

87

Table 5.1: Results from the Push-Off Tests

Series Specimen Nominal PU Area (mm2)

Peak Load (kN)

Peak Stress (MPa)

Slip at Failure (mm)

Failure Mode

Failure Surface (a or b)

1-1 14400 13.2 0.92 N/A Bond Steel (b)

1-2 14400 24.2 1.68 N/A Bond Steel (b) 1

1-3 14400 13.2 0.92 N/A Bond Steel (b)

2-1 14900 20.8 1.39 2.50 Cohesion Concrete (b)

2-2 14600 18.5 1.29 0.34 Bond Steel (b)

2-3 14900 18.0 1.21 N/A Bond Steel (b) 2

2-4 14470 18.2 1.26 1.88 Bond Steel (b)

3-1 N/A

3-2 14560 16.8 1.65 1.75 Bond Steel (b) 3

3-3 13560 27.8 2.05 1.25 Bond Steel (b)

4-1 14500 26.5 1.94 0.64 Bond Steel (b)

4-2 14600 15.0 1.11 0.54 Bond Steel (b)

4-3 14600 35.0 2.43 0.58 Bond Steel (b)

4-4 14500 26.0 1.46 0.66 Bond Steel (b)

4-5 14600 26.5 1.82 2.29 Cohesion Steel (b)

4

4-6 14400 20.5 1.92 2.94 Cohesion Steel (b)

5-1 14400 42.5 2.91 1.68 Cohesion Concrete (b)

5-2 14400 50.5 3.51 3.08 Cohesion Concrete (a) 5

5-3 14600 23.5 1.55 3.55 Cohesion Concrete (b)

Page 103: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

88

5.2. Results and Discussion

The following sections will demonstrate the successful development of a

polyurethane formulation and the necessary surface treatment for an adequate adhesively

bonded shear connection. The results from each series will be presented and a discussion

of the effects of the variables studied in each series will also be given in their respective

section.

5.2.1. Series One Specimens 1-1, 1-2 and 1-3 were tested to explore the effects of shrinkage on the

adhesion of the polyurethane to the substrates between the three different formulations of

polyurethane CAE 1-1, 2-1 and 2-3a. For this purpose, the displacement of the steel

girder was not measured. The polyurethane layers in all the specimens were manually

mixed and poured, as opposed to being mixed in a machine and injected at a high

pressure. The resulting polyurethane layer cured properly without any visible bubbles or

foam that was present in the specimens of the pilot testing by Ramsay (2007).

a. b.

Figure 5.1: a) Visible Shrinkage in Specimen 1-1, b) Reduced Shrinkage in Specimen 1-3

Page 104: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

89

As shown in Figures 5.1, the shrinkage of the polyurethane was visible in

specimen 1-1 and no visible shrinkage was observed in specimen 1-3. The shrinkage,

however, did not appear to be the cause of the failure. All three specimens failed in a

brittle manner and the failure load did not correlate with the shrinkage level represented

by each specimen. The surface of steel flanges after the specimen had failed, as seen in

Figure 5.1, showed that there was a lack of adhesion between the polyurethane and steel

surface in all three specimens. The steel surfaces were clean, which demonstrated that the

polyurethane was not adhering to the surface at all. All the failures happened at the

steel/polyurethane interface in all three specimens (Gardin, 2007). The reason behind the

unsatisfactory adhesion that caused the premature bond failure was not clear, but Gardin

(2007) suggested that the temperature of the specimens at the time of the polyurethane

pour could be elevated to 50 oC to promote better curing at the steel surface due to the

exothermic nature of the formation of the polyurethane. The exertion of pressure from the

polyurethane onto the concrete slab could also have lifted it slightly, allowing air to stay

in the cavity during the pour. Lastly, small leakages during the polyurethane pour, which

was thought to be negligible, might have promoted additional air voids in the cavity.

5.2.2. Series Two

Four specimens, 2-1 to 2-4, were fabricated in series two with the goal to

investigate the possibility of promoting better adhesion between the steel girders and the

polyurethane at an elevated temperature of 50oC when the polyurethane was poured. The

effect of manually clamping the specimen was also examined with Specimen 2-4.

Page 105: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

90

Figure 5.2: Leakage Caused by Expansion of Polyurethane

Unexpected expansion in Specimen 2-1 occurred during the curing of the

polyurethane, as shown in Figure 5.2. The expansion was large enough that the concrete

slab was detached from the wooden formwork and resulted in observable leakage.

However, the leakage did not result in a significant net loss of polyurethane and the

contact between the polyurethane and the substrates were still adequate, therefore, the

testing proceeded despite of a slight distortion in the geometry of the polyurethane layer –

The layer was approximately 3mm thicker at near the bottom of the specimen than the

other end.

The load-displacement behaviour from the push-off tests of 2-1, 2-2 and 2-4 are

presented in Figure 5.3. An error occured in the LVDT setup during the test of Specimen

2-3 and the displacement of the steel beam could not be recorded, however, specimen 2-3

appeared to have a similar behaviour as Specimen 2-4.

Page 106: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

91

Shear Stress vs. Average Girder Displacement

0

0.125

0.25

0.375

0.5

0.625

0.75

0.875

1

1.125

1.25

1.375

1.5

0 0.25 0.5 0.75 1 1.25 1.5 1.75 2 2.25 2.5 2.75 3 3.25

Average Girder Displacement (mm)

Shea

r Str

ess

(MPa

)

Specimen 2-1Specimen 2-2Specimen 2-4

Figure 7 5.3: Shear Stress vs. Average Girder Displacement for Series 2.

Specimen 2-2 and 2-4 failed in a brittle manner with bond failures at the steel

surfaces similar to those in series one. The excessive initial deflection readings in

specimen 2-4 could have been caused by the initial settlement of the plaster at the base

and the shimming at the loading blocks. Furthermore, clamping of specimen 2-4 did not

appear to have improved the bonding of the polyurethane to the steel. Contrarily, despite

the expansion of the polyurethane and the leakage, specimen 2-1 exhibited ductile

behaviour and the displacement of the girder at failure was approximately 2.50 mm. The

adhesive connection sustained a peak load of 42 kN, which corresponded to a shear stress

of approximately 1.4 MPa at each joint. The failure plane of specimen 2-1 is shown in

Figure 5.4. As can be seen, the failure did not happen at the steel interface, but rather, it

was a cohesion failure in the polyurethane near the concrete roughened surface.

Page 107: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

92

(a) (b)

Figure 5.4: Failure Surfaces of Specimen 2-1 a) Polyurethane Layer; b) Concrete Slab

Although the peak stress was lower than the expected stress of at least 5 MPa, the

ductile behaviour of specimen 2-1 suggests that satisfactory bonding between the

polyurethane and the substrates can be achieved. The unexpected expansion of the

polyurethane, which used the CAE 1-1 formulation that has a thirty minutes curing time,

might have encouraged more intimate contact between the polyurethane and the

substrates, and resulted in better adhesions.

5.2.3. Series Three

Three specimens, 3-1 to 3-3 were fabricated in the third series of the push-off

tests. However, the polyurethane did not cure properly in specimen 3-1, as seen in Figure

5.5, and the concrete slab was detached from the polyurethane layer during the

Page 108: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

93

disassembly of the formwork. The polyurethane was still soft and had a viscosity similar

to honey. This might have been caused by either an error in the proportioning of the resin

and the isocyanate or an error in the mixing of the two components. Specimen 3-1,

therefore, could not be tested.

Figure 5.3: Improper Curing of the Polyurethane in Specimen 3-1

All of the specimens in this series were washed with an acetone solvent either

once before the sandblasting as in the case for specimen 3-1 or twice, before and after the

sandblasting, which was done for specimens 3-2 and 3-3. Unfortunately the difference

between one and two acetone wash could not be compared because of the improper

curing of the polyurethane in 3-1. The specimens, however, could be compared to the

results from series two to determine the effects of the acetone solvent wash to the bond

strength. Furthermore, the polyurethane layer in specimen 3-3 was poured in a

compressible polyurethane form that allowed the layer to be compressed under the self

weight of concrete as it cured. Similar to specimen 2-1, the slow-curing formulation of

polyurethane was used in specimen 3-3 and it expanded during the cure. The concrete

slab was partially detached from the polyurethane form and leakage occurred.

Page 109: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

94

The load-displacement plots from the push-out tests of specimens 3-2 and 3-3 are

presented in Figure 5.6. The plots from specimens 2-1, 2-2 and 2-4 are also provided in

dotted lines for comparison purposes. As can be seen, both specimens 3-2 and 3-3

Shear Stress vs. Average Displacement

0

0.25

0.5

0.75

1

1.25

1.5

1.75

2

2.25

0 0.25 0.5 0.75 1 1.25 1.5 1.75 2 2.25 2.5 2.75 3 3.25

Average Girder Displacement (mm)

Shea

r Str

ess

(MPa

)

Specimen 2-1Specimen 2-2Specimen 2-4Specimen 3-2Specimen 3-3

Figure 5.6: Shear Stress vs. Average Girder Displacement for Series 3

exhibited brittle behaviour and the failure happened in the bond between the polyurethane

and the steel. The failure surface of specimen 3-3 is shown in Figure 5.7. As the figure

shows, the leakage caused the flexible polyurethane form to distort and the contact area

between the polyurethane and the steel was reduced by approximately 10%. However,

plot shows that the specimen 3-3 has reached a peak load of 56 kN, which corresponds to

a peak stress of 2.05 MPa at each adhesive joint before failure occurred.

Page 110: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

95

Figure 5.7: Polyurethane Layer in Specimen 3-3 with PU form

5.2.4. Series Four

Six specimens, 4-1 to 4-6 were fabricated in series four of the push-out tests. The

effects of using a primer on the steel surfaces were examined. A primer, a bonding agent

commonly used to promote better adhesion between two materials, was applied to all of

the steel surfaces in this series to promote better adhesion to the polyurethane. Different

chemical additives were also mixed into the basic formulation of CAE 2-3a in different

specimens to assist in adhesion of the polyurethane to the substrates. All of the specimens

were washed with the acetone solvent before and after the sandblasting of the steel

surfaces.

The results of the push-out tests in series four is presented in Figure 5.8. First of

all, as can been seen from the plots, specimens 4-1 to 4-4 exhibited brittle behaviour with

peak load ranging from 32 kN to 70kN; specimens 4-5 and 4-6 exhibited ductile

behaviour with a peak load of approximately 53 kN and 41 kN, respectively. Specimens

Page 111: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

96

Shear Stress Vs. Average Displacement

0

0.25

0.5

0.75

1

1.25

1.5

1.75

2

2.25

2.5

2.75

0 0.25 0.5 0.75 1 1.25 1.5 1.75 2 2.25 2.5 2.75 3 3.25

Average Girder Displacement (mm)

Shea

r Str

ess

(MPa

)

Specimen 4-6Specimen 4-5Specimen 4-4Specimen 4-3Specimen 4-2Specimen 4-1

Figure 5.8: Shear Stress vs. Average Displacement for Series Four.

Figure 5.9: Specimen 4-6 at Failure

Page 112: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

97

4-5 and 4-6 experienced similar cohesion failures in the polyurethane, as shown in Figure

5.9. The failure began near the bottom of the steel girder and progressed slowly along the

flange, resulting in a slow and ductile failure. Although specimen 4-3 behaved in a brittle

manner, the connection yielded the greatest shear stiffness value and it sustained the

highest load among all specimens – 70kN, which corresponds to a shear stress of around

2.9 MPa. The low failure load – 32 kN, of specimen 4-2 could be a result of the high

moisture content of the resin and the isocyanate at the time of mixing that prevented the

proper curing of the polyurethane.

The results from the push-out tests in this series are encouraging because results

of specimens 4-5 and 4-6 further suggest that sufficient adhesion can be promoted in the

steel surface to allow a ductile behaviour in the adhesion joint. Despite of the brittle

failure, results of specimen 4-3 have demonstrated that the adhesive joint is capable of

achieving a shear stress of 2.5 MPa.

5.2.5. Series Five

Three specimens, 5-1 to 5-3 were fabricated for the last series of tests in the

experimental program. A different polyurethane formulation with three slight variations

was used in this series – namely CAE 1-3, CAE 1-9, and CAE 1-10. The basic

formulation used a different isocyanate than the one used in the previous series to form

the two-parts polyurethane. The formulation was also varied by adding different additives,

namely a wetting agent and a polyol additive, to the polyurethane with the goal to

promote better adhesion. Generally, the resulting polyurethane should have a similar

stiffness value, but it should allow a greater elongation compared to the polyurethane

Page 113: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

98

used in the previous series (Gardin, 2007). The new softer formulation was made to

investigate the possibility of preventing brittle failure by allowing more shear

deformation in the polyurethane layer and more deformation due to tearing stress.

The load-deflection plot from series five is shown in Figure 5.10. All three

connections exhibited ductile behaviour with failures in the cohesion of the polyurethane,

shown in Figure 5.11. Peak stresses of 2.9 MPa, 3.5 MPa, and 1.7MPa were reached,

respectively in specimens 5-1 to 5-3. The post-peak deformation shown in the load-

deflection plot of specimens 5-1 and 5-3 before failure was unprecedented in the previous

series. This could be an indication that the polyurethane might have yielded and have

undergone plastic deformation before reaching failure in cohesion. Furthermore, the non-

linear characteristic shown in the plot of specimen 5-1 suggests a constant redistribution

of load in the polyurethane layer.

Shear Stress vs. Average Displacement

0

0.5

1

1.5

2

2.5

3

3.5

4

0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 2.2 2.4 2.6 2.8 3 3.2 3.4 3.6 3.8

Average Girder Displacement (mm)

Shea

r Str

ess

(MPa

)

Specimen 5-1Specimen 5-2Specimen 5-3

Figure 5.10: Shear Stress vs. Average Displacement for Series Five.

Page 114: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

99

Figure 5.11: Specimen 5-1 at Failure

This last series of test has yielded agreeable results that suggest the use of a

polyurethane adhesive as the shear connection in composite bridges might be viable. First

of all, the result from specimen 5-2 indicates that the connection could sustain a

maximum shear stress of 3.5 MPa, which met the criteria as outlined in Chapter 3.

Secondly, although the connection of specimen 5-1 attained a maximum shear stress of

only 2.9 MPa that is lower than that required by the criteria, the behaviour was ductile

with plastic deformation in the polyurethane layer followed by a failure in cohesion,

which is usually desirable in the design of shear connections that do not have sufficient

bond strength. The inconsistency among the results of the three specimens could have

been caused by the different additives used in the formulations, or an imperfection in the

geometry of the test setup resulting in possible rotation during the test, which could

significantly affect the characteristic of the connection as the adhesive is very sensitive to

peeling stresses. Nevertheless, the required stress value of 3MPa as outlined by the

criteria has been met.

Page 115: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

100

5.3. Shear Stiffness of the Adhesive Connection

As discussed in Chapter 2, the definitions of the shear stiffness from the load-slip

plot are not unified among researchers (Wang, 1998). If the behaviour of a shear

connector is linear, the shear stiffness of the connection can usually be defined as the

tangent stiffness of the load-slip plot. However, when a shear connection exhibits ductile

behaviour characterized by a nonlinear load-slip plot, the tangent stiffness would not

realistically represent the stiffness of the connection, and the secant stiffness must be

used instead. Generally, the shear connections tested in this study exhibited linear

elastically behaviour, therefore, the stiffness of the connection is taken as the tangent

stiffness, Ktangent, as determined from the load-slip plots. Table 5.2 summarizes the

stiffness of the adhesive joints tested. The area stiffness k [N/mm2] is calculated by

dividing the Ktangent by the length of the bond, which is taken as 160mm for all the

specimens. This value is important for the application of the partial interaction theory that

will be outlined in the Chapter 6.

Page 116: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

101

Table 5.2: Stiffness of Polyurethane Adhesive Joints

Series Specimen *Ktangent (N/mm) x103 *k (N/mm2)

2-1 20 125

2-2 46 288 2

2-4 10 62.5

3-2 35 188 3

3-3 12 75.0

4-1 48 300

4-2 32 200

4-3 70 438

4-4 36 225

4-5 34 188

4

4-6 35 188

5-1 43 269

5-2 50 313 5

5-3 28 175

*intjo

KkL

= and Ktangent is the slope of the load-slip plot, as shown:

Load - Slip Plot

0

10

20

30

40

50

60

70

80

90

0 0.5 1 1.5 2 2.5 3 3.5

Slip (mm)

Load

(kN

)

Ktangent

Page 117: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

102

CHAPTER 6: ANALYTICAL PROGRAM

The goal of the analytical component of this research project is to investigate the

feasibility of using the polyurethane adhesive developed in the experimental program as a

mean of shear connection in concrete-steel composite bridges. The analytical program is

designed to verify the proposed criteria discussed in Chapter 2 for the minimum adhesive

bond strength and stiffness required to implement the adhesive as an efficient shear

connection in composite bridges. As discussed in Chapter 2, the adhesive bond must have

sufficient strength so that the adhesive joint will not fail under loading in the ultimate

limit state and, at the same time, the adhesive must have sufficient stiffness to minimize

any additional deflection due to the slip between the concrete deck and steel girders under

loading in the serviceability limit states. Numerical analyses are used to verify that the

polyurethane adhesive developed in the experimental program has sufficient bond

strength and stiffness to meet the criteria.

The chapter begins with a brief review of the full interaction and no interaction

analysis followed by a discussion of the partial interaction theory of composite beams

proposed by Girhammar and Gopu (1993). The behaviour of ten bridges designed for

spans of 25m, 50m, and 75m under the serviceability limit state will then be investigated

and discussed based on the theories by Girhammar and Gopu (1993) and a computer

analysis by SAP2000™. The behaviour of the bridges under the ultimate limit state will

then be analyzed using a rigid plastic analysis as outlined by Oehlers and Bradford (1995).

The chapter concludes with an outline of the criteria for the minimum strength and

stiffness of the polyurethane adhesive based on the results of the numerical analyses

under both limit states.

Page 118: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

103

6.1. Degree of Interaction in Composite Beams As already discussed in Chapter 3, composite beams can have various degrees of

interaction between the two composite components. The degree of interaction in a

conventional composite bridge with mechanical connectors is dependent on the stiffness

of the shear connection, k, which is calculated by dividing the individual connector

stiffness, Ktangent, by the spacing between the connectors, Ls. A similar analogy can be

applied to adhesively bonded shear connections, in which the shear connection stiffness

can be defined as the stiffness of the adhesive joint divided by the bond length, Ljoint, as

shown in Figure 6.1. As previously mentioned, when K approaches infinity, the shear

connection is stiff enough that a full interaction between the two materials can be

achieved. This is characterized by a linear distribution of strains along the whole cross

section at any distance, x, along the beam, as discussed in Chapter 3. When K approaches

zero, the beam is described as having no interaction between the two materials. In reality,

a composite beam can never be fully composite or completely non-composite, in another

word, the value of K is always between zero and infinity, and the subcomponents are

described as having partial interaction. Partial interaction is characterized by a slip, ∆u,

between the two composite materials, and the strain distribution along the cross-

L jointL s

a. b. Figure 6.1: Length used to determine connection stiffness, k – a) Connector Spacing, Ls; b) Length of Joint, Ljoint

Page 119: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

104

section is characterized by individual linear distributions along each composite material

with a break at the shear connection, the difference in strain at the shear connection is

referred as the as the slip strain, ds/dx or ∆u’.

In practice, when headed shear connectors are used, the connectors would be

spaced close enough to allow a full interaction between the two composite elements.

Designers would usually provide sufficient shear connectors to avoid the complexity of a

partial interaction analysis. However, in the case of an adhesively bonded connection,

the strength and stiffness of the bond depends on the properties of the adhesive and the

width and thickness of the adhesive joint.

In the case where the strength of the composite beam is dictated by the strength of

the shear connection, the beam is referred to as having partial shear connection, and a

partial interaction analysis must be used to study the exact behaviour of the beam. As will

be discussed further, the simple rigid plastic analysis outlined by Oehlers and Bradford

(1995) can be used to determine the ultimate flexural strength of the composite section

under the ultimate limit state. The analysis by Oehlers and Bradford (1995) is simple

because the concrete deck and the steel girder are assumed to have reached their plastic

capacity, therefore, the distribution of forces within the composite section is known.

However, when the beam is subjected to service loads and the elements in the section

remain elastic, the distribution of strains and forces within the cross-section will not be

obvious. The use of partial interaction analysis to determine the maximum deflection of a

partially composite beam under serviceability limit state requires more a complicated

analysis that often involves complex closed-form solutions. Guidelines, such as the

Eurocode (1994), usually recommend a simpler approach by using an empirical formula

Page 120: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

105

to determine the deflection of a concrete-steel composite beam with partial shear

connection. An example of such formula as outlined by the Eurocode (1994) is shown in

Equation 6.1,

wp = wf + α ( wo - wf) (1- η) Eq. 6.1

where wp, wo and wf represent the deflection of the beam with partial interaction, no

interaction, and full interaction respectively. η is referred to as the degree of shear

connection, and is determined by the ratio of the shear connection strength to the required

shear connection strength for full composite interaction between the materials. α is a

value less than unity that is empirically determined by experimental data, and values of

around 0.4 are recommended by the Eurocode for the use of shear studs.

Although Equation 6.1 can be used to estimate the increase in deflection due the

slip between the concrete section and the steel section, the equation does not demonstrate

the actual behaviour of the beam under service loads. The study of the partial interaction

behaviour in composite beams is well documented, in fact, one of the first theories of

incomplete interaction in composite beams dates back to as early as 1951, by Newmark et

al. The theory developed was derived based on several assumptions: 1) the shear

connection is continuous; 2) the amount of slip of the connector is proportional to the

shear force transmitted; 3) the behaviour of all the individual components of the

composite beam is linear elastic; and 4) the curvature and vertical deflection of both

components of the composite beam are the same. In addition to the research study by

Newmark et al. (1951), Granholm (1949) also conducted a study on beams with partial

Page 121: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

106

composite action, which was based on similar assumptions and resulted in similar

second-order differential equations, of which the solutions showed that the total

deflection of a beam with incomplete interaction is the sum of the deflection of the

corresponding beam with full interaction plus an additional deflection due to slip.

Numerous studies on partial interaction behaviour have been conducted since (Example:

Girhammar & Gopu, 1993; Wang, 1998; Seracino et al. 2000), and a recent study based

on similar assumptions conducted by Girhammar and Gopu (1993) have provided closed-

form solutions to the second-order differential equations. The following sections will

outline the theory proposed by Girhammar and Gopu (1993) and its application in the

analytical program to determine the behaviour of composite bridges connected with the

polyurethane adhesive developed in the experimental program.

Prior to understanding the analysis outlined by Girhammar and Gopu (1993), the

analyses used to predict the behaviour of the composite beams with full interaction and

no interaction should be understood, since they are the upper and lower bounds of the

solutions to beams with partial interaction. The discussion in the following sections is

based on a composite section, shown schematically in Figures 6.3, that the analysis by

Girhammar and Gopu (1993) was developed for. The cg,f represents the neutral axis of

the composite section with full interaction. Each subcomponent i, where i = 1 or 2 in the

case shown in Figure 6.2, has a corresponding Young’s modulus Ei, Moment of Inertia, Ii.

and cross-sectional area Ai. bi and hi represents the width and height of each component.

ri represents the distance between the centroid of each component to the shear connection,

and r is the distance between the centroid of the two elements.

Page 122: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

107

1

2

b1

h1

h2

b2

cg, 1

cg, 2

r1

r2r

zcg,

r - zcg,

cg, f

f

f

Figure 6.2: Schematic Composite Section in Partial Interaction Analysis (Picture taken from Girhammar & Gopu, 1993)

cg,∞

z, w

x, u

q

L

Figure 6.3: Uniformly Distributed Load Acting on the Composite Beam (Picture taken from Girhammar & Gopu, 1993)

In the case where conventional mechanical shear connectors are used, r is simply:

Eq. 6.2

If the two components are connected by an adhesive layer with thickness, t, r should

be taken as:

trrr ++= 21 Eq. 6.3

21 rrr +=

Page 123: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

108

6.1.1. Full Interaction Analysis in Composite Beams To analyze the behaviour of the beam when the shear connectors are strong

enough to allow full interaction, one of the components needs to be transformed into an

equivalent section of the material of the other component. This can be achieved by

dividing the width of its section by the modular ratio n, where n is ratio of the Young’s

Modulus, Ei, of the two components. For example, in the cross section shown in Figure

6.2, Section 1 can be transformed into an equivalent section of the material in Section 2

by dividing b1 by n, where n is the ratio of E2 to E1, shown in Equation 6.4:

1

2

EEn = Eq. 6.4

Based on the equivalent section, the section properties can be re-evaluated and the

deflection of a simply supported beam, under uniformly distributed load as shown in

Figure 6.3, can be predicted by Equation 6.5:

45

384ff

qLwEI

= Eq. 6.5

where q is the magnitude of the distributed load, L is the span, and (EI)f is the stiffness of

the transformed section with full interaction. As already discussed, this prediction serves

as the upper bound of the deflection of composite beams with only partial interaction.

The distributions of strains under service loads can be assumed to be linear along the

whole cross-section and the stresses in each subcomponent can be evaluated accordingly

based on the equilibrium of forces.

Page 124: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

109

6.1.2. No Interaction Analysis in Composite Beams In the case when there is no interaction between the two composite elements, the

applied load is simply distributed to each section according to their corresponding

stiffness. Therefore, an applied load, q, can be proportioned to section 1 and 2 according

to Equation 6.6 and 6.7:

( )

1 11

0

E Iq qEI

= Eq. 6.6

( )

2 22

0

E Iq qEI

= Eq. 6.7

where,

( ) 1 1 2 20EI E I E I= + Eq. 6.8

The deflection of the beam with no interaction can then be estimated by:

4

20

2 2

5384

q LwE I

= Eq. 6.9

Often when Section 1 is a concrete slab and Section 2 is a steel beam, as in the

case in this study, all the loads are assumed to be taken by the steel section since most of

the concrete section will be cracked under bending, as demonstrated by Oehlers &

Bradford (1995). Contrary to the case with full interaction, the deflection of the beam

with no interaction serves as the lower bound to the deflection with only partial

interaction.

Page 125: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

110

6.1.3. Partial Interaction Analysis of Composite Beam by Girhammar and Gopu (1993)

The study conducted by Girhammar and Gopu (1993) provides closed-form

solutions to the displacement functions and the internal forces of simply supported

composite beams with interlayer slip under a distributed load. Similar to the analyses by

Newmark et al. (1951) and Granholm (1949), the equations are designed for conventional

mechanical shear connectors, but the stiffness of discrete connectors are assumed to be

distributed uniformly along the length of the member. This assumption allows the

application of the analysis to be extended to adhesive bonds that provide a continuous

shear connection. Furthermore, Girhammar and Gopu (1993) also assumed that:

1) The relative slip is small and it occurs at the interface of the two

components

2) Any friction and uplift between the subcomponents are ignored. As a

result, the curvature of the subcomponents is assumed to be equal;

3) The load-slip behaviour of the shear connectors is assumed to be linear

elastic, therefore, the slip modulus k (N/m2) is assumed to be constant;

4) The behaviours of the constituent materials are linearly elastic and the

assumption that plane sections remain plane still applies to the individual

components of the beam.

The analysis by Girhammar and Gopu (1993) also extends to include the effect of

an applied axial load on the beam, and outlines a second-order analysis that takes into

Page 126: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

111

account the P-Delta effect of the axial load on the beam. This, however, is beyond the

scope of the current study, so only the first-order analysis of their study will be adopted.

Consider a differential element, shown in Figure 6.4, of a composite beam

subjected to a uniformly distributed load q. The internal forces, including bending

moment, the vertical shear, axial force, and the slip force per unit length, which is often

referred as the shear flow, are denoted by Mi, Vi, Ni and Vs, respectively, where i = 1 or 2

denotes the subcomponent. The applied force, F, is taken as zero for all the analyses in

this study. The first and second derivative of the deflection, w, of the beam at any

distance x along the beam is often referred as the rotation and the curvature, respectively.

1d1 VV +

2d2 VV +

1d1 NN +1d1 MM +

2d2 MM +

2d2 NN +

sV

1V

2V

1N

1M

2N

2M

xd

q(x)

'w

' ' 'w w dx+

,cg

, 2cg

, 1cg

,cgz

x

MV

M dM+

V dV+

N F

N F

f

f

Figure 6.4: Differential Element in a Composite Beam Subjected to an Axial Load, F, and a Uniformly Distributed Load, q(x) (Girhammar & Gopu, 1993)

Since Girhammar and Copu (1993) assumed that all the materials in the analysis

behave linear elastically, the theory is based on a constant shear connection area stiffness,

k [N/mm2], which should not be confused with the individual shear connector stiffness, K

Page 127: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

112

[N/mm]. K is usually obtained from push-off tests, as described in Chapter 3, and usually

taken as the tangent stiffness.

Based on this stiffness, Girhammar and Gopu (1993) analyzed the behaviour of

the beam with partial interaction based on the following equations from equilibrium of

internal and external forces:

21 NN −= Eq. 6.10

21 VVV += Eq. 6.11

rNMMM 121 −+= Eq. 6.12

rwuuu ′+−=∆ 21 Eq. 6.13

rwu ′′+−=′∆ 21 εε Eq. 6.14

where u is the individual horizontal displacement of each component and ∆u is the

relative slip between the two components. u′∆ represents the difference in strain at the

shear interface, which more commonly referred as the slip strain. The first and second

derivative of the vertical deflection, w, denoted by w′and w ′′ , represent the rotation and

curvature of the beams, respectively.

The analysis by Girhammar and Gopu (1993) has yielded the following governing

differential equation in terms of the displacement function, w:

0

22

EIM

EIMww

f

IV ′′−=′′− αα Eq. 6.15

where α is a shear connection stiffness parameter defined as:

( )( ) ( )

22 0

0p

EA rKEA EI

α⎛ ⎞⎜ ⎟= +⎜ ⎟⎝ ⎠

Eq. 6.16

Page 128: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

113

and,

( ) 1 1 2 20EA E A E A= + Eq. 6.17

( ) 1 1 2 2pEA E A E A= ∗ Eq. 6.18

Girhammer and Gopu (1993) have solved the differential equation and provided the

general equation for the deflection, at any distance x along the beam, for a simply

supported beam with partial composite action, subjected to a uniformly distributed load, q,

shown in Equation 6.19:

( )

( )( )

( )

4 3 30 04

0

2 2 2 2

( 2 ) 124

1 1tanh sinh( ) cosh 12 2 2

f

f

EIq qw x x xLEI EI EI

L x x x x L

α

α α α α α

⎛ ⎞= − + + −⎜ ⎟⎜ ⎟∞ ⎝ ⎠

⎡ ⎤⎛ ⎞− + − + −⎜ ⎟⎢ ⎥⎝ ⎠⎣ ⎦

Eq. 6.19

slipfp www += Eq. 6.20

where the first term is the deflection of a section with full interaction and the second term

is the additional deflection due to interlayer slip of a partial composite section.

Girhammer and Gopu (1993) have also deduced the equations for the maximum

deflection and the maximum internal forces, and they are given as:

⎥⎥⎥⎥

⎢⎢⎢⎢

−+⎟⎠⎞

⎜⎝⎛⎟⎟

⎞⎜⎜⎝

⎛−+= 1

81

2cosh

113845 22

04

04

0max, L

LEIEI

EIq

EILqw f

ffp α

αα Eq. 6.21

Page 129: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

114

⎥⎥⎥⎥

⎢⎢⎢⎢

⎟⎠⎞

⎜⎝⎛

−⎟⎟⎠

⎞⎜⎜⎝

⎛−+=

2cosh

1118 0

2011

2011

max,1 LEIEIq

EIIELq

EIIE

M f

ff αα Eq 6.22

max,111

22max,2 M

IEIEM = Eq 6.23

⎪⎭

⎪⎬⎫

⎪⎩

⎪⎨⎧

⎥⎥⎦

⎢⎢⎣

⎡⎟⎠⎞

⎜⎝⎛

⎟⎟⎠

⎞⎜⎜⎝

⎛−+

−++=

2tanh1211

2 01

101112

0max,1

LEIEI

LrEIrEIrIE

rrLq

V f

f

αα

Eq 6.24

⎪⎭

⎪⎬⎫

⎪⎩

⎪⎨⎧

⎥⎥⎦

⎢⎢⎣

⎡⎟⎠⎞

⎜⎝⎛

⎟⎟⎠

⎞⎜⎜⎝

⎛−+

−++=

2tanh1211

2 02

202222

0max,2

LEIEI

LrEIrEIrIE

rrLq

V f

f

αα

Eq 6.25

the slip can also be estimated by considering that:

uKVs ∆⋅−=− eq. 6.26

Equations 6.21 to 6.26 can be used to predict the behaviour of the beam and determine

the strain distribution along the cross-section under service loads. This will allow

designers to decide if the shear connection is stiff enough that the additional deflection

due to interlayer slip is acceptable within deflection limits. Equation 6.21 can be re-

arranged to a simpler form, shown by Wang (1998) as the following:

⎟⎟⎠

⎞⎜⎜⎝

⎛−+= 11

0EIEI

ww f

f

p β Eq. 6.27

where

Page 130: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

115

( )( )4

2

53841

81

2cosh

1L

LL α

αα

β⎟⎟⎟⎟

⎜⎜⎜⎜

−+⎟⎠⎞

⎜⎝⎛

= Eq. 6.28

As can be seen, β is a function of the shear connection stiffness parameter αL.

Figure 6.5 shows the plot of β against αL, where β = 1 and β = 0 represent the beam with

non-composite and fully composite behaviour, respectively. As shown from the plot, the

relationship is non-linear and the range of interest for partial interaction analysis is

usually when 1 < αL <10. When αL < 1, the beam essentially behaves with no interaction

between the composite materials, on the other hand, when αL > 10, the value of β

becomes really small and the increase in deflection due to the interlayer slip is minimal

compared to the overall deflection, as shown in Figure 6.6.

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

αL

β

Figure 6.5: Graphical Presentation of Equation 6.28 (after Wang, 1998)

Page 131: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

116

β versus dβ/d(αL)

-0.25

-0.2

-0.15

-0.1

-0.05

00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

αL

β

Figure 6.6: β versus dβ /d(αL)

The study conducted by Wang (1998) that investigated the deflection of steel-

concrete composite beams with partial shear interaction has verified the analysis of

Girhammer and Gopu (1993) with a finite element analysis. Generally, Wang found that

the predicted deflections of the finite element analysis are within 4% of those predicted

by Equation 6.21.

6.2. Computer Analysis using Frame and Spring Elements

In additional to the numerical analyses mentioned in the previous section, a

computer model designed using the program SAP2000™ is used as part of the analytical

program. The computer model is used to:

1) Determine the increase in deflection of a composite beam that is connected by the

polyurethane adhesive developed in the experimental program;

Page 132: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

117

2) Conduct a parametric study to analyze the effect of varying the thickness of the

polyurethane layer and the stiffness of the shear connection on the deflection and

interlayer slip of composite beams;

3) Validate the results predicted by the equations outlined by Girhammar and Gopu

(1993).

6.2.1. Material Properties and Element Representation

The 2-D frame model designed for a typical composite bridge section shown in

Figure 6.3 is presented in Figure 6.7. Frame elements are used to represent the concrete

deck, the steel beam, and the discrete rigid links that are used to transfer the forces

between the subcomponents. The adhesive bond layer is represented by discrete spring

elements, which are rigid and fixed in the vertical direction, but only partially fixed in the

horizontal direction. The stiffness of the springs in the horizontal direction is based on

the shear connector stiffness, K, from the experimental program. Since the stiffness of the

adhesive bond is also dictated by the thickness, the width and the length of the joint, the

value K from the push-off tests has to be magnified based on the respective ratios of the

geometry of the joint in the push-off tests to the geometry of the model. For example, if

the stiffness of the joint obtained from the push-off test is Ktangent, the K of the studied

beam can be calculated by:

model modeltangent

joint joint

L wKL w

⎛ ⎞⎛ ⎞⎜ ⎟⎜ ⎟⎜ ⎟⎜ ⎟⎝ ⎠⎝ ⎠

Eq. 6.31

where Lmodel is the spacing of the frame elements in the model, wmodel is the width of the

adhesive joint of the studied beam, and Ljoint and wjoint are the length and the width of the

Page 133: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

118

joint of the push-off specimens, respectively. All the materials, namely the concrete, steel

and the polyurethane are assumed to be linear, elastic, and isotropic. To ensure that the

links are rigid, the frame elements that are used to represent them are assigned a Young’s

Modulus that is one hundred times that of steel, therefore, an E value of around 20 x 106

MPa. Lastly, the beam was simply supported and a uniformly distributed load was

applied to the concrete frame element.

Figure 6.8: 2D SAP2000™ Model – a) A Complete Span b) Detail of the Elements

Page 134: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

119

6.3. Problem Definition To determine if the polyurethane adhesive developed in the experimental program

is a suitable material to bond the concrete deck to the steel beams in composite bridges,

the computer model and the equations discussed in the previous sections will be used to

predict the behaviour of the composite bridges that use a polyurethane adhesive as the

shear connection. The typical section analyzed is depicted in Figure 6.9 and Figure 6.10.

The concrete deck is designed to have a width of 13m and supported by four steel I-

beams, therefore, the composite sections to be studied will have a constant concrete deck

width of 3.25m. The parameters considered include the span of the bridge, the thickness

of the polyurethane layer, the shear stiffness of the polyurethane adhesive joint, and the

width of the polyurethane layer. The concrete is assumed to have a strength of f’c = 45

MPa, and the steel is assumed to have a yield strength of f’y = 350 MPa. The geometry of

the concrete slab and the steel beams depend on the span of the bridge, but the overall

depth to span ratio is kept at a typical value of approximately 1 to 25. Table 6.1

summarizes the design of the composite bridges studied in the analytical program. Since

the range of the typical shear connection stiffness values, K, of the polyurethane joint

obtained from the experimental program are within 35 kN/mm to 55 kN/mm, therefore,

the stiffness values considered in the analytical program will be based on the adhesive

joint with K= 35 kN/mm and 55 kN/mm.

The bridges are analyzed under the serviceability limit state, where the loading

considered is the nominal, unfactored live load. Dead load is not included in the analysis

because during the construction of composite bridges, all the dead load, namely the self

weight of the steel girders and the wet concrete, are assumed to be taken by the steel

Page 135: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

120

girders alone. Designers usually provide sufficient camber so that the net deflection is

zero when the concrete decks (cast in-situ or precast) are placed on the girders. Since this

chapter focuses on developing and verifying the criteria proposed in Chapter 2, namely,

the additional deflection due to slip shall not exceed 20% of that of the design that is fully

composite, therefore, a constant live load of 100kN/m will be applied to all the bridges

and the percentage increase in deflection due to slip will be noted.

Figure 6.9: Figure 6.9: Overall Cross-Section of the Composite Bridge with 13m with Deck Supported on four Steel beams

Figure 6.10: Parameters of the Beam Studied – Thickness of Slab dc, Depth of Steel Beam ds, Width of Flanges, wf, Thickness of web tw, and Thickness of Flanges tf

Page 136: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

121

Table 6.1: Dimensions of the Studied Composite Bridges

Design L (m) tpu (mm) ds (mm) wf (mm) tw (mm) tf (mm)

1 25 1500 600 20 30

2 35 1500 600 20 30

3 45 1500 600 20 30

4

50

50 1500 600 20 30

5 25 1000 400 20 25

6 35 1000 400 20 25

7 45 1000 400 20 25

8

25

50 1000 400 20 25

9 25 2100 700 25 50

10 75

50 2100 700 25 50 *the effective width with L = 25m is 0.125L = 3.13m (Eurocode 4, 1994)

6.4. Results and Discussion – Serviceability Limit State The properties of the sections for each design are calculated based on the

dimensions summarized in Table 6.1. The maximum deflections at the midspan, the

maximum slips and the maximum longitudinal shear stresses at serviceability limit states

are summarized in Table 6.2. The stiffness connector values, K, shown are based on the

35 N/mm or 50 N/mm obtained from the push-out tests and modified by taking the ratios

of thickness of the layer in the designs to the 25mm thickness of the joint in the push-off

tests. A comparison between the deflections of the designs with connection stiffness of 35

N/mm calculated from Equation 6.21 and the computer model is shown in Table 6.3. wf,

wslip and wtotal are the deflection of the bridge with full interaction, the additional

deflection due to slip, and the total overall deflection, respectively. The percentage

increase represents the percentage increase in deflection due to slip compared to the

Page 137: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

122

Table 6.2: Results of the Partial Interaction Analysis

Design *K

(N/mm) x 103

k (MPa)

wf (mm)

wslip (mm)

wp (mm)

% increase

∆u

(mm)

τs (MPa)

35.0 1310 168 1.82 169 1.08 0.230 0.546 1

50.0 1870 168 1.27 169 0.76 0.162 0.551 25.0 934 166 2.53 168 1.53 0.318 0.539

2 35.7 1330 166 1.78 167 1.07 0.225 0.546 19.4 725 164 3.24 167 1.98 0.405 0.533

3 27.7 1030 164 2.45 166 1.50 0.309 0.539 17.5 653 163 3.21 166 1.98 0.402 0.533

4 25.0 931 163 2.51 165 1.54 0.317 0.538 35 594 41.0 2.06 43.1 5.01 0.297 0.705

5 50 849 41.0 1.45 42.5 3.54 0.212 0.719

25.0 424 40.2 2.83 43.0 7.03 0.405 0.687 6

35.7 606 40.2 2.00 42.2 4.98 0.290 0.704 19.4 329 39.4 3.58 43.0 9.08 0.510 0.672

7 27.7 490 39.4 2.80 42.2 7.11 0.403 0.685 17.5 297 39.0 3.93 42.9 10.1 0.559 0.665

8 25 424 39.0 2.79 41.8 7.15 0.403 0.684

35.0 1660 337 2.00 339 0.59 0.234 0.556 9

50.0 2380 337 1.40 338 0.42 0.165 0.561 17.5 832 337 3.98 341 1.18 0.458 0.545

10 25.0 1190 337 2.80 339 0.83 0.325 0.551

*K values need to be proportioned according the thickness. i.e. K of a 50mm thick joint is calculated by: K*(25/50)

deflection of the same design with full interaction. ∆u is the maximum slip between the

concrete deck and the steel girder. Generally, the results of the computer model and the

prediction by Equation 6.21 are agreeable and the discrepancies are usually within 5%.

The SAP2000™ model tends to overestimate the deflection and underestimate the slip.

Page 138: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

123

Table 6.3: Comparison of Results from SAP2000™ and Equation 6.21.

Design wp from Eq. 6.8 (mm)

wp from SAP2000™

(mm)

% Difference*

∆u from Eq. 6.8 (mm)

∆u from SAP2000™

(mm)

% Difference*

1 171 168 2.1 0.223 0.230 -3.0 2 169 166 1.8 0.307 0.318 -3.3 3 168 164 2.1 0.397 0.405 -1.8 4 166 163 1.8 0.393 0.402 -2.3 5 42.7 41 4.0 0.285 0.297 -4.0 6 42.3 40.2 5.0 0.385 0.405 -5.0 7 41.0 39.4 4.0 0.501 0.510 -1.7 8 39.9 39.0 2.3 0.547 0.559 -2.1 9 345 337 2.4 0.227 0.234 -2.8 10 341 337 1.3 0.452 0.458 -1.4

*% Difference calculated by: -(value of Eq. 6.8 - value of SAP2000™ ) / (value of Eq. 6.8)

The distributions of strains along the composite sections of the 50m and the 25m

span are shown in Figures 6.11 and 6.12, respectively. As can be seen, the slip strains in

the 50m-span section are small (a maximum value of approximately 0.03 µε) and the

strain distributions are similar to that of a composite section with perfect bond. However,

the distributions of the strains in the 25m-span section start to deviate from that of a

perfect bond, with a noticeable slip strain of approximately 0.096 µε.

Generally, the increase in deflection at midspan due to the interlayer slip between

the concrete and steel sections of the 50m and 75m-span designs is less than 5% of the

maximum deflection of a fully composite section. However, the increase in deflection of

the 25m-span design ranges from approximately 7% to as high as 10%. Figure 6.13

shows the relationship between the percentage increase in the maximum deflection due to

slip and the decrease in stiffness. As can be seen, the decrease in K has a much greater

effect on the 25m-span design than it does on the 50m-span design. The reason why the

Page 139: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

124

Strain Distribution at Midspan with Different PU Thickness (50m Span)

0

200

400

600

800

1000

1200

1400

1600

1800

2000

-0.750 -0.250 0.250 0.750 1.250 1.750

Strain (x 10E-3)

Dist

ance

from

the

Botto

m o

f the

Cr

oss-

Sec

tion

(mm

)25mm35mm45mm50mmPerfect Bond

Figure 6.11: Strain Distributions of the Cross-Section at Midspan for Polyurethane Layer Thickness of 25mm, 35mm, 45mm and 50mm – 50m-Span Design

Strain Distribution at Midspan with Different PU Thickness (25m Span)

0100200300400500600700800900

100011001200

-0.500 -0.250 0.000 0.250 0.500 0.750 1.000 1.250 1.500 1.750

Strain (x10E-3)

Dis

tanc

e fro

m th

e Bo

ttom

of t

he

Cros

s-S

ectio

n (m

m)

25mm35mm45mm50mmPerfect Bond

Figure 6.12: Strain Distributions of the Cross-Section at Midspan for Polyurethane Layer Thickness of 25mm, 35mm, 45mm and 50mm – 25m-Span Design

Page 140: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

125

% Increase in Max. Deflection vs. Connection Stiffness

0

2

4

6

8

10

12

14

16

0 10 20 30 40 50 60

Shear Connector Stiffness, K (N/mm) x10E3

% In

crea

se in

Max

imum

Def

lect

ion

25m50m

Figure 6.13: Relationship between the percentage increase in maximum deflection versus shear connection stiffness, K, for 25m and 50m-span designs according to Equation 6.21.

shorter spans tend to be more sensitive to a decrease in the shear connection stiffness than

the longer spans are is because of the non-linear relationship between the stiffness

parameter αL and the deflection function of beams with partial shear connection, as

already shown in Figure 6.5. The rate at which the deflection increases at lower αL values

is much greater than it is at higher values of αL. As the connection stiffness and the span

length decreases, the parameter αL also decreases since α is directly proportional the

connection stiffness. For example, the αL values for the designs of the 50m-span range

approximately from 19 to 26, where the αL values for the designs of the 25m-span range

from 11 to 15.

Results from the analysis shows that, in general, the additional deflection due to

slip in adhesively bonded composite bridges is insignificant compared to its overall

deflection. Therefore, it is reasonable to conclude that adhesively bonded connections can

be designed and the adhesive can be formulated to provide sufficient stiffness that

Page 141: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

126

additional deflection due to slip can be limited to be under 20% of the deflection of the

same design with full interaction, as was proposed in Chapter 2.

Although the cross-sections discussed above are designed according to the typical

span to depth ratio of 25 to 28 (Brozzetti, 2003), parameter such as the width of the top

steel flange can greatly affect the behaviour of the composite sections since the stiffness

of the adhesive bond connection is proportional to the width of the joint, which cannot be

greater than the width of the top flange of the steel beam.

6.5. Flexural Strength at Ultimate Limit State In addition to having sufficient stiffness to satisfy the deflection limit of the

composite beams in the serviceability limit state, the adhesive layer must also have

sufficient strength to allow the development of the full capacity of the concrete and steel

sections under the ultimate limit state. The ultimate flexural capacity of a composite

section can be determined using a rigid plastic analysis outlined by Oehlers and Bradford

(1995). The analysis is based on equilibrium of forces at the cross-section assuming that

the concrete and steel have developed their full plastic strength. The following sections

will discuss and outline the rigid plastic analysis and its application to determine if the

polyurethane adhesive joint developed has sufficient bond strength under loadings in the

ultimate limit states.

6.5.1. Rigid Plastic Analysis by Oehlers and Bradford (1995) Consider the three possible stress distributions of a concrete-steel composite

section at its maximum strength, as shown in Figure 6.14. Cases 1 and 2 represent the

states of stress when the neutral axis is in the concrete and steel, respectively, and that the

Page 142: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

127

shear connection has sufficient strength to fully transfer the forces between the two

sections, hence a full shear connection. Case 3 represents the state of stress where the

shear connection has lower strength than that of the concrete and steel sections, and the

forces in each section are dictated by the ultimate strength of the shear connection. The

composite beam in this case is referred to as having a partial shear connection. In the

current study, only Cases 2 and 3 will be considered because Case 1 involves possible

cracking of the concrete at the shear connection, which should be avoided in adhesive

bond connection to avoid detachment of the polyurethane layer from the concrete surface.

The strength of the adhesive bond required for full shear connection and the

ultimate flexural strength of a composite section can be estimated by the following

procedure:

1) Fix the stresses on the concrete and steel sections at their plastic strengths, namely

cfPconcrete ′= 85.0 for concrete in compression (Oehlers & Bradford, 1995) and

ysteel fP = , the yield strength for steel in both tension and compression, as shown

in Figure 6.15.

2) Determine the position of the neutral axis that will allow equilibrium of forces at

the cross-section. In other words, the sum of the compression forces above the

neutral axis must equal to the sum of the tension forces below the neutral axis.

3) The minimum shear connection strength, shearP , required is the force that needs to

be transferred between the concrete and steel sections. In the case where the

neutral axis is in the steel section, concreteshear PP = .

Page 143: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

128

Figure 6.14: Three Possible Strain and Stress Distributions (Figures taken from Oehlers & Bradford, 1995)

Page 144: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

129

4) If the shear connection has sufficient strength to transfer the forces between the

two sections, the flexural strength can be determined by taking moment of all the

forces at the cross section.

5) If the shear connection does not have sufficient strength to transfer the forces, the

resultant forces in the concrete and steel sections must be set to shearP , since

neither the concrete nor the steel section can develop its full strength. As shown in

Figure 6.16, the positions of the neutral axes that will result in a force of Pshear in

each section must be determined.

The outlined procedure is used to analyze the composite beams summarized in

Table 6.1 and the strengths of the polyurethane adhesive bond required for full shear

connections are determined. The predicted strengths will be compared to the shear

strengths of the polyurethane adhesive joints tested in the experimental program to

investigate the feasibility of using the developed formulation as the shear connection of

composite bridges. Since the polyurethane joints of the push-out specimens in the

experimental program are all 25mm thick and the effect of the thickness on the bond

strength is unknown, only the designs with an adhesive layer of 25mm are analyzed. The

analysis is also used to verify the suggestion by Si Larbi et al. (2006) that the longitudinal

shear stress at the shear connection in typical composite bridges do not exceed 3MPa.

Page 145: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

130

Figure 6.15: Stresses of the Composite Section with Full Interaction at the Ultimate Limit State Neutral Axis in the Steel Beam. (Figures taken from Oehlers & Bradford, 1995)

Figure 6.16: Stresses of the Composite Section with Partial Shear Connection at the Ultimate Limit State (Figures taken from Oehlers & Bradford, 1995)

Page 146: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

131

6.5.2. Results and Discussion – Ultimate Limit State Table 6.4 summarizes the flexural strengths, the maximum load at the connection

at the midspan, and the required strength of the shear connection of the 25m, 50m, and

75m-span designs with a 25mm thick polyurethane adhesive layer under the ultimate

limit state based on the rigid plastic analysis. Different concrete strengths are also

considered since that will greatly influence the plastic strength of the concrete slabs.

Table 6.4: Results from the Rigid Plastic Analysis

Span Concrete Strength

Maximum Load at the Connection at Midspan

(kN)

Required Shear Connection Strength

(MPa)

25 25 13700 2.73 35 13700 2.73 45 13700 2.73 55 13700 2.73

50 25 15500 0.89 35 21800 1.24 45 28000 1.60 55 34200 1.95

75 25 15500 0.59 35 21800 0.83 45 28000 1.06 55 34200 1.23

As can be seen, the required strength of the shear connection in all the cases does

not exceed 3 MPa. This conforms to the results from the study of Si Larbi et al. (2006),

which suggested that the longitudinal shear stress in typical composite sections usually do

not exceed 3 MPa. Results of Specimens 5-1 and 5-3 from the push-off tests, summarized

Page 147: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

132

in Chapter 4, demonstrate that the polyurethane elastomer can be formulated to withstand

a maximum shear stress of approximately 2.9 MPa and 3.5 MPa, respectively. The results

suggest that the polyurethane adhesive joint developed in the experimental program has

sufficient strength to allow the full development of the plastic flexural strength in

composite bridges spanning from 25m to 75m. Although the results shown in Table 6.4

are specific to the proposed designs, which can change depending on numerous

parameters such as the number of steel girders, the thickness of the concrete slab, the

widths of the top flanges of the steel beams, and the concrete strength. However, the

results demonstrate, at a preliminary level, that the composite sections can be designed to

adopt the adhesive bond and satisfy the requirements under the ultimate limit state.

6.6. Criteria Having demonstrated the feasibility of using the polyurethane adhesive developed

in the experimental program as the shear connection in composite bridges, general

criteria for the use of the adhesive bond can be established. In general, the adhesive layer

should be stiff enough to minimize the interlayer slip between the two composite

components under the serviceability limit state, and also, the adhesive bond must have

sufficient strength to transfer the forces between the subcomponents to allow the full

development of the plastic capacity of the composite section. Based on the results from

the analytical program, the criteria for the two limit states are:

Under the serviceability limit state:

1) The additional deflection due to slip should not exceed 20% of the overall

deflection of the design with full interaction.

Page 148: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

133

2) The stiffness parameter of the connection, αL, should be at least 10. As shown in

Figures 6.6 and 6.7, the additional deflection due to slip increases at a quick rate

when αL < 10. The typical span range of composite bridges, from 25m to 75m,

can be designed to have a αL value from 11 to 25.

3) The materials of the composite sections should remain elastic and the stiffness of

the connection required must be within the linearly elastic range due to the

assumptions made in the analysis proposed by Girhammar and Gopu (1993).

4) For the prediction of the deflection, full composite assumption can be assumed for

αL values greater than 10, since the increase of deflection due to slip is usually

less than 10%.

5) Since shorter spans are more sensitive to changes in the shear connection stiffness,

increasing the thickness of the adhesive layer from 25mm should be avoided in

shorter spans of 20m to 30m as it will significantly decrease the stiffness of the

connection.

6) The stiffness, K, can be increased easily by increasing the width of the adhesive

layer, which is dictated mainly by the width of the top flange of the steel beams.

Under the ultimate limit state:

1) Generally, the adhesive layer should be able to resist a minimum longitudinal

shear stress of 3 MPa, as suggested by Si Larbi (2003) and verified by the

analytical program.

2) The maximum shear stress in the adhesive layer can easily be decreased by

increasing the width of the adhesive layer to increase the shear area at the

interfaces.

Page 149: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

134

CHAPTER 7: SUMMARY, CONCLUSION AND RECOMMENDATIONS

7.1. Summary The primary motivation behind this research study was to develop a system that

can facilitate bridge deck rehabilitation projects of composite bridges, and this can

usually be achieved by using full-depth precast concrete decks. However, conventional

headed stud connectors require shear pockets in the precast decks, which can become

vulnerable areas for durability problems. The objective of this research is to investigate

the feasibility of adhesively bonding the concrete deck to the steel girders in composite

bridges with a polyurethane elastomer adhesive, which not only has a quick curing and

setting time, but it can also provide sufficient strength and stiffness to be used in civil

engineering application.

The feasibility of the adhesively bonded connection is determined based on the

deflection requirement according to the serviceability limit state and the strength

requirement of the ultimate limit state. The adhesive joint should:

1. Have sufficient strength to allow the full development of the plastic

capacity of the concrete and steel sections. The minimum shear stress that

the adhesive joint should be able to resist was determined to be 3MPa.

2. Have sufficient stiffness that additional deflection due to the interlayer slip

between the concrete and steel is minimum and full composite behaviour

can be attained.

This research study included an experimental program that tested 19 small-scale

push-off tests to develop a polyurethane elastomer adhesive that could satisfy the

Page 150: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

135

abovementioned criteria. The strength and stiffness of adhesive joints were also

characterized in the push-off tests. These values were then used in the analytical program

of this research study.

The analytic program was designed to establish a list of criteria used to determine

the feasibility of using the polyurethane adhesive as a shear connection in composite

bridges. The partial interaction theory proposed by Girhammar and Gopu (1993) was

used to determine the maximum deflection of the composite bridges with spans of 25m,

50m, and 75m, which were designed to have a bonded shear connection using the

polyurethane adhesive developed in the experimental program. A SAP2000™ computer

model was also designed to verify the results obtained from the partial interaction theory.

The analytical program also studied the behaviour of the bridges under ultimate limit

state using a rigid plastic analysis proposed by Oehlers and Bradford (1996). The analysis

was used to determine if the polyurethane adhesive bond tested in the experimental

program had sufficient strength to allow the composite sections to develop their full

plastic flexural strength.

7.2. Conclusion The following conclusions can be made for this research study:

1) According to the criteria established in this study, the use of polyurethane

adhesive as the shear connection in composite bridges is feasible.

2) The maximum shear stress that a shear connection must resist in typical

composite bridges is lower than 3MPa.

Page 151: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

136

3) The polyurethane adhesive joint developed in the experimental program

could provide sufficient strength for the development of the plastic capacity

of composite bridges with spans of 25m, 50m and 75m.

4) The adhesive joint developed had sufficient stiffness that the behaviour of

the bridges study was close to that of a fully composite bridge.

5) The additional deflection due to interlayer slip when an adhesive bond is

used is insignificant compared to the overall deflection. The maximum

additional deflection due to slip of a composite bridge when the adhesively

bonded connection is used shall not exceed 20% of overall deflection of the

corresponding design with full interaction.

6) The strength and stiffness of the polyurethane layer used as the shear

connection greatly depends on the width of adhesive joint, which cannot be

greater than the width of the top flange of the steel girders.

7) The partial interaction theory proposed by Girhammar and Gopu (1993) can

be used to analysis composite beams with only partial shear connection.

8) Bridges with shorter spans are more sensitive to a decrease in the stiffness of

the shear connection due to the non-linear relationship between the increase

in deflection with the stiffness parameter, αL, used in the partial interaction

theory. To ensure a full interaction, αL should be kept at above 10.

Page 152: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

137

7.3. Recommendations and Future Work

Since a formulation of the polyurethane that can provide sufficient strength and

stiffness was developed in the experimental program, full-scale standard push-off tests

should be conducted to obtain more consistent load-slip plots for the adhesive joint. An

experimental program should be designed to test composite beams that use the adhesive

bond as the shear connection, where the degree of interaction can be studied. Production

of the polyurethane outside of ideal lab conditions will be necessary to ensure that the

adhesive can be used under field conditions. Factors that greatly influence the properties

of the curing of polyurethane such as the temperature, moisture content, and different

surface conditions should be examined. Lastly, the behaviour of the adhesively bonded

composite bridges under long-term loading, and the behaviour in the fatigue limit state

should be examined.

Page 153: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

138

REFERENCE

Adderley, C. S. (1988) “Adhesive Bonding.” Materials & Design, v 9, n 5, Sep-Oct, p 287-293 Bouazaoui, L., Perrenot, G., Delmas, Y. and Li, A. (2006) “Experimental Study of Bonded Steel Concrete Composite Structures”. Journal of Constructional Steel Research, v 63, n 9, September, 2007, p 1268-1278 Braun, Dale. (1999). “Behaviour of Composite Structural Laminate Plates.” Master’s Thesis, Carleton University, Ottawa, Canada. Brozzetti, Jacques. (2000). “Design development of steel-concrete composite bridges in France.” Journal of Constructional Steel Research, v 55, n 1, Apr, 2000, p 229-243. Canadian Standards Association. (2006). Canadian Highway Bridge Design Code (CAN/CSA S6-06), CSA, Rexdale, Ontario. Culmo, Michael P. (2000). “Rapid Bridge Deck Replacment with Full-Depth Precast Concrete Slabs.” Transportation Research Record, n 1712, 2000, p 139-146. Eurocode 4 (1992). Design of Composite Steel and Concrete Structure (ENV 1994-1-1). European Committee for Standardization, Brussels. Excell, Jon. (2004). “Sandwich Strength”. Engineer, v 293, n 7653, 11 June 2004, p 30-1. Farmer, Ian. (2006) “Sandwich Plate System for New Buiild and Repair”. Structural Engineer, v 84, n 5, 2006, p 22 Funnell, Scott E. (2000) “Flexural and In Plane Compressive Behaviour of Composite Structural Laminate Plates.” Master’s Thesis, Carleton University, Ottawa, Canada. Gardin, Greg. (2007). Personal Communication. Girhammar, Ulf Arne and Copu, Vijaya K. A. (1993). “Composite Bean-Columns with Interlayer Slip – Exact Analysis.” Journal of Structural Engineering, v.119, n4, April, p. 1265-1283. Hänsch, H. (1978). Epoxy Bonding Compounds as Shear Connectors in Composite Beam. Schweisstechnik (Berlin), 28(11), 499-502. Haven, P. (1978). Missouri River bridge gets epoxy bonded prestressed slab deck. Railway Track and Structures, 74(9), 40-42.

Page 154: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

139

Hepburn, C. (1992). Polyurethane Elastomer. Elsevier Science Publisher Ltd. New York. USA. Intelligent Engineering. (2007). “The Sandwich Plate System.” [Internet]. <http://www.ie-sps.com> Retrieved: August, 2007. Issa, Mohsen A., Khayyat, Salah Y., Issa, Mahmoud A., Yousif, Kaspar, Iraj I. and Alfred A. (1995) “Field Performance of Full Depth Precast Concrete Panels in Bridge Deck Reconstruction.” PCI Journal, v 40, n 3, May-Jun, 1995, p 82-108. Keller, Thomas and Gürtler, Herbert. (2005). “Quasi-static and fatigue performance of a cellular FRP bridge deck adhesive bonded to steel girders.” Composite Structures, v 70, n 4, Oct. 2005, p 484-96 Kim, Jong-Hee, Shim, Chang-su, Matsui, Shigeyuki, and Chang, Sung-Pil. (2002). “The Effect of Bedding Layer o the Strength of Shear Connection in Full-Depth Precast Deck.” Engineering Journal, v 39, n 3, Third Quarter, p 127-135 Li, A., Assih, T., and Delmas, Y. (2000) “Influence of the adhesive thickness and steel plate thickness on the behaviour of strengthened concrete beams.” Journal of Adhesion Science and Technology, v 14, n 13, 2000, p 1639-1656. Linder, Josef. (1995). “Development and Behaviour of Advanced Double Hull Sandwich Plate Systems Experimental Investigation.” Master’s Thesis, Carleton University, Ottawa, Canada. Minten, Joachim, Sedlacek, Gerhard, Paschen, Michael, Feldmann, Markus, and Gessler, Achim. (2007) “SPS - Ein neues Verfahren zur Instandsetzung und Ertuchtigung von Stahlernen Orthotropen Fahrbahnplatten (SPS - An innovative method for the repair and refurbishment of orthotropic deck-plates of steel-bridges)”. Stahlbau, v 76, n 7, July, 2007, p 438-454. Oehlers, Deric J. and Bradford, Mark A. (1995). Composite Steel and Concrete Structural Members: Fundamental Behaviour. Elsevier Science Lrd. New York. USA. Oehlers, D.J. and Coughlan, C.G. (1986) “The shear stiffness of stud shear connections in composite beams.” Journal of Constructional Steel Research, Vol 6, p. 273-284. Ramsay, Carlene (2007). “Shear Resistance of a Polyurethane Interface in Concrete-Steel Composite Beams.” Master’s Thesis, Department of Civil Engineering, University of Toronto, Ontario, Canada. Shim, Chang-Su, Lee, Pil-Goo, and Chang, Sung-Pil. (2001) “Design of Shear Connection in Composite Steel and Concrete Bridges with Precast Decks.” Journal of Constructional Steel Research, v 57, n 3, p 203-219

Page 155: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

140

Si Larbi, A. Ferrier, E., Jurkiewiez, B., and Hamelin, P. (2006). “Static Behaviour of Steel Concrete Beam Connected by Bonding”. Engineering Structures. [internet] doi:10.1016/j.engstruct.2006.06.015 Tadros , Maher K,, Baishya, Mantu C., Rossbach, Phillip E. and Pietrok, Gary A. (1999). “Rapid Replacement of Bridge Decks.” Concrete International, v 21, n 2, Feb, 1999, p 52-55. Triantafillou, Thanasis C. (1998). “Shear Strengthening of Reinforced Concrete Beams using Epoxy-Bonded FRP Composites”. ACI Structural Journal, v 95, n 2, Mar-Apr, 1998, p 107-115 Tumialan, Gustavo, Nanni, Antonio, Ibell, Timothy, and Fukuyama, Hiroshi. (2002).“FRP Composites for Strengthening Civil Infrastructure Around the World” SAMPE Journal, v 38, n 5, September/October, 2002, p 9-15 Wang, Y.C. (1998). “Deflection of Steel-Concrete Composite Beams with Partial Shear Connection.” Journal of Structural Engineering, v 124, n 10, Oct, 1998, p 1159-1165 Zaki, Adel R. and Mailhot, Guy. (2003). “Deck Reconstruction of Jaques Cartier Bridge Using Precast Prestresesd High Performance Concrete Panels”. PCI Journal, v 48, n 5, September/October, p 20-33

Page 156: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

141

Appendix A:

Data Input for Finite Element Analysis

Program used: SAP2000™

Frame Elements:

Concrete Slab

Material Properties:

Material Type: Reinforced Concrete

Concrete Strength: 45MPa

Reinforcement Yield Strength: 413MPa

Modulus of Elasticity: 36900MPa

Poisson Ratio: 0.2

Assumed Linearly Elastic, Isotropic

Sectional Properties

Section Type: Rectangular Section

Width: 3250mm

Depth: 225mm

Steel Girder

Material Properties

Material Type: Steel

Strength: Fy = 350MPa

Fu = 450 MPa

Modulus of Elasticity: 200000MPa

Poison Ratio: 0.3

Page 157: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

142

Assumed Linearly Elastic, Isotropic

Sectional Properties

Section Type: I-Beam

Geometry Varies

Rigid Frame Elements

Material Properties:

Material Type: None

Modulus of Elasticity: 2x107MPa

Poisson Ratio: 0.3

Assumed Rigid, Isotropic

Sectional Properties

Section Type: Rectangular Section

Width: 100mm

Depth: 100mm

*Rigid Frame Elements are spaced 100mm apart over the span of the studied bridges.

Spring Elements

Constraints:

U1 – Fixed

U2 – Partially Fixed, with stiffness K

Free in other directions

Page 158: by Billy Siu Fung Cheung - University of Toronto T-Space...Billy Siu Fung Cheung Department of Civil Engineering University of Toronto ABSTRACT This thesis is motivated by the use

143

Adhesive joint stiffness 35kN/m or 50kN/m is used. The K input can be calculated as

follows:

Since the stiffness if for a 25mm thick joint with a bond length of 160mm and width of

92mm, the experimental stiffness value must be proportioned according to the geometry

of the model of the studied bridges. For example, if the adhesive layer of the bridge in

consideration has a joint width of 400mm, thickness of 50mm, and the experimental

stiffness of 35kN/m is used, K can be calculated by:

100 400 2535160 92 50input

kN mm mm mmKm mm mm mm

⎛ ⎞ ⎛ ⎞ ⎛ ⎞= ⎜ ⎟ ⎜ ⎟ ⎜ ⎟⎝ ⎠ ⎝ ⎠ ⎝ ⎠i i i

The first term is the experimental stiffness, second term is the ratio of the frame element

spacing to the joint length, third term is the ratio of the joint width in the studied bridge to

the experimental joint width, and the last term is the ratio of the joint thicknesses. This

Kinput is that entered as the spring stiffness of the spring element in the U2 direction.