Butler County Regional Snow Summit October 18, 2009 9:00AM-12:00PM Butler County Engineers Office...
-
Upload
jerry-purifoy -
Category
Documents
-
view
212 -
download
0
Transcript of Butler County Regional Snow Summit October 18, 2009 9:00AM-12:00PM Butler County Engineers Office...
Butler County Regional Snow SummitOctober 18, 20099:00AM-12:00PM
Butler County Engineers Office1921 Fairgrove AvenueHamilton, Ohio 45011
Welcome………………..Gregory Wilkens, County Engineer, Butler County EngineersModerator………………Scott Bressler, Operations Deputy, Butler County Engineers
PresentersButler County Engineers Office ………….. Scott Bressler, Butler County Engineers Office
Butler County EMA…………………………… Jeff Galloway, Director, Butler County Emergency Management Agency
Butler County Sheriffs Office……………… Matt Franke, Butler County Sheriffs Office
ODOT……………………………………………… Diana Clonch, Office of Maintenance Operations
Moderated Discussion…………..Moderator, Scott Bressler
Butler County Engineers Office
2010-2011 Snow / Ice Control Plan
BCEO Plan
Winter 2009-10 Tons of salt spread: 7,202
(Avg. winter: 6000 tons)
Gallons of salt brine: 18,513 Gallons calcium chloride:
12,800 Labor hours: 7,607 Snow/Ice events: 18 Avg. cost per event: $59,398 Total cost for 2009-10 season
$1,069,165
BCEO PLAN
Responsible for 596 lane mileshttp://bceo.org/departments/operations/operations.html
Two teams, A-Team / B-Team
Each team includes 1 supervisor, 15 drivers, 1 mechanic, 1 operator, 2 back-up drivers (if needed).
BCEO PLAN Local Training / Roadeo October
28th and 29th
Start winter on-call November 5th
Each team works 12hr shifts if needed
Switch at 7:30AM and / or 8:00PM
Respond to answering service from BCSO / PD
Page teams
Goal, on routes within 90 minutes of call
BCEO PLAN
Monitor Weather Tap
Anti-icing-apply 25,000 gallons prior to snow
After hours, First flake, BCSO / PD needs to call main number, 513- 867-5744 for county roads
Don’t forget the twp crews, ODOT, cities
Know the difference / map
BCEO PLAN
If forecast warrants, we will load trucks previous night, come in prior to storm and be on routes before snow falls
BCEO PLAN
Please call the main number 513-867-5744 after hours and 513-785-4157 normal hours
Record of call, supervisors will be paged
Don’t call trucks off routes
Please help with traffic control if possible, if we are stuck in traffic we can’t help.
Continue to work with townships, remote salt pick-up
If truck breaks down or gets stuck in ditch we will notify townships, pull spare truck
BCEO PLAN
Anti-icing Planweather permitting apply liquid brine
Takes just over 8 hours to apply 25,000 gallons of brine using 5 distributors and 4 remote sites
Continue to Evaluate Beet Juice 2010
BCEO PLAN
Cargil ($64.48/ton)
BCEO currently has a full barn and enough on contract to get through the season
Twp. Cities and villages are also under same county contract
Order salt often
Be ready and have an alternate plan
BCEO PLAN
New Tools Plow Blades Beet Juice / Brine
Mix 800Mhz Radios
BCEO PLAN
Work together
Be patient
Use the press to help communicate to the public, keep them informed
Be safe