BE1401 Business Operations and Processes Exercises on Process Setups 1. Auto Parts Manufacturing A company specializing in auto parts manufacturing produces, among other items, two parts: A and B. Given the tolerance requirements of A and B, the parts are produced using a special purpose machine operated by a skilled machinist. Presently, the company has only one machinist capable of operating this machine, and hence the machine is operated only on a one-shift basis. After allowing for factors such as lunch break and rest periods, etc., the machinist operates the machine for 7 hours per day throughout the week. In fabricating parts A and B, the machine requires a set up time of 4 hours whenever switching between the two parts types. Once the machine is appropriately set up, the run time for either part A or for part B is only 0.01 hour per unit. Currently, the company rotates its production between one batch of 1000 for part A and one batch of 1000 for part B. a) The company has recently received an inquiry from a major auto manufacturer concerning the company’s ability to supply sets of parts A and B (with each set consisting of one part A and one part B) on a long-term basis. Specifically, the auto manufacturer wants to know how many sets per day can the company supply? Estimate the production capacity of the company (in terms of sets per day). b) Satisfied with the company’s estimate, the auto manufacturer has agreed to purchase sets of parts A and B from the company. However, it has added one condition in the contract: the company, on a sustained basis, should be able to supply sets of parts at a rate 10% more than the rate it has estimated above. For the company to achieve this higher production rate, what batch sizes would you recommend for A and for B? c) What other alternate actions would you recommend that the company evaluate to meet this condition? (The company has ruled out the overtime option.) What would be the potential drawbacks and benefits of these actions? (No computations pertaining to these alternate actions are required. A qualitative answer is adequate.)

description

Business Operations Exercises

Transcript of Business Operations Exercises Setups 20140210

Page 1: Business Operations Exercises Setups 20140210

BE1401 Business Operations and Processes Exercises on Process Setups

1. Auto Parts Manufacturing A company specializing in auto parts manufacturing produces, among other items, two parts: A and B. Given the tolerance requirements of A and B, the parts are produced using a special purpose machine operated by a skilled machinist. Presently, the company has only one machinist capable of operating this machine, and hence the machine is operated only on a one-shift basis. After allowing for factors such as lunch break and rest periods, etc., the machinist operates the machine for 7 hours per day throughout the week. In fabricating parts A and B, the machine requires a set up time of 4 hours whenever switching between the two parts types. Once the machine is appropriately set up, the run time for either part A or for part B is only 0.01 hour per unit. Currently, the company rotates its production between one batch of 1000 for part A and one batch of 1000 for part B. a) The company has recently received an inquiry from a major auto manufacturer

concerning the company’s ability to supply sets of parts A and B (with each set consisting of one part A and one part B) on a long-term basis. Specifically, the auto manufacturer wants to know how many sets per day can the company supply? Estimate the production capacity of the company (in terms of sets per day).

b) Satisfied with the company’s estimate, the auto manufacturer has agreed to

purchase sets of parts A and B from the company. However, it has added one condition in the contract: the company, on a sustained basis, should be able to supply sets of parts at a rate 10% more than the rate it has estimated above. For the company to achieve this higher production rate, what batch sizes would you recommend for A and for B?

c) What other alternate actions would you recommend that the company evaluate to

meet this condition? (The company has ruled out the overtime option.) What would be the potential drawbacks and benefits of these actions? (No computations pertaining to these alternate actions are required. A qualitative answer is adequate.)

Page 2: Business Operations Exercises Setups 20140210

2. Setups Everywhere Consider the following batch-flow process consisting of three process steps performed by three machines: Work is processed in batches at each step. Before a batch is processed at a step, the machine at that step must be set up. (During a setup, the machine is unable to process any product.) Assume that there is a dedicated setup operator for each machine (i.e. , there is always someone available to perform a setup at each machine.) (a) What is the process capacity if the batch size is 35 parts? Which step is the

bottleneck?

(b) For what batch sizes is step 1 the bottleneck? Step 2? Step 3? 3. Metal Box Production

Metal window boxes are manufactured in 5 basic colors in a small plant in Bangkok. The manufacturing process consists of 3 operations: stamping, painting, and assembly, as shown below.

Each window box is made up of three pieces: a base (one part A) and two sides (two part Bs). The parts are fabricated by a single stamping machine which requires a setup time of 100 minutes whenever switching between the two part types. Once the machine is setup, the run time for each part A is 1 minute while the run time for each part B is only 30 seconds. Currently, the stamping machine rotates its production between one batch of 300 for part A and one batch of 600 for part B. Completed parts move from the stamping machine onto the painting station.

At the painting station, parts are painted by a robot in 1 of 5 colors. The robot takes 30 seconds to paint one part A and 15 seconds to paint one part B. The robot can easily switch between painting the two parts, but a switch in color does require 20 minutes for setup. Once a piece is painted, it must wait 120 minutes to dry before moving to assembly. The painting robot is currently programmed to change color every time it

Step 1 Step 3 Step 2

Activity Time: 0.25 min/part Setup Time: 30 mins

Activity Time: 0.20 min/part Setup Time: 20 mins

Activity Time: 0.15 min/part Setup Time: 45 mins

Page 3: Business Operations Exercises Setups 20140210

finishes one batch of 300 component sets (i.e., 300 of part A and 600 of part B).

At assembly, parts of the same color are assembled manually to form the finished product. One base (part A) and two sides (two part Bs), as well as a number of small purchased components, are required for each unit of final product. Each product requires 26.67 minutes of labor time to assemble.

The factory runs on one shift per day, five days per week. Considering the need for lunch break, rest periods, etc., each operation (stamping, painting and assembly) is effectively run for only 400 minutes per shift. There are currently 15 workers: 12 assembly workers, two operators for the stamping machine, and one operator for the robot.

(a) Identify the bottleneck for the current process and calculate the maximum daily throughput rate in terms of the # of units of finished products produced per day. What is the throughput time for a batch of 300 units of finished products (i.e., from the time the stamping operation starts for a batch to the time the complete batch of 300 window boxes is assembled)?

(b) What impact would doubling the batch sizes at the stamping operation have on

total daily throughput? Be number specific. Explain qualitatively what other, possibly negative, effects this would have.

(c) Management is considering investing in a setup reduction program for the

stamping machine. Suppose the setup time could be reduced to 20 minutes, with some additional investment cost. What would happen to the throughput rate if the batch sizes remained the same (i.e., 300 for part A and 600 for part B)? Be number specific. What would be the potential benefits of such a reduction in setup time if the batch sizes were allowed to change (explain qualitatively)?