BURTON STATIONSTRATEGIC GROWTH AREA PLAN UPDATE
CITY COUNCIL BRIEFING MAY 01, 2018
1Mark E. Shea, Comprehensive Planning Coordinator
![Page 2: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/2.jpg)
2
ORDER OF PRESENTATION
• Burton Station Strategic Growth Area Plan (SGA) actions to date
• Summary of 2009 Plan and reasons for updating the plan
• Capital Projects underway and programmed
• Highlights of Draft Plan Update
• Burton Crossing Rezoning
![Page 3: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/3.jpg)
SGA PLAN ACTIONS TO DATE
• Initial briefings held with City Council on Nov. 28, 2017 and Planning Commission Jan. 10, 2018.
• First public meeting was held Jan. 25, 2018. Focus of this meeting was on future land use for Burton Station Village.
• Briefing given to L and J Gardens Civic League on Feb. 22, 2018.
• Briefing given to Hampton Roads Association of Commercial Realtors (HRACRE) on March 7, 2018.
• Second public meeting held March, 26, 2018.
• First steering committee meeting on April 16, 2018.
• Third public meeting held on April, 19, 2018.
3
![Page 4: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/4.jpg)
4
EXISTING PLAN – ADOPTED JANUARY 27, 2009
![Page 5: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/5.jpg)
PLAN ADOPTION – JANUARY 27, 20093 Alternatives Presented for Burton Station Village:
Option 3 –Predominately High Density Commercial
Option 1 –Predominately Low Density Residential
Option 2 -Predominately High Density Residential
5
![Page 6: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/6.jpg)
PLAN ADOPTION – JANUARY 27, 2009Stakeholders Chose Option 1: Low Density Residential 31 existing homes 38 new single family
homes Corner shop Senior Living Facility Community Center Memorial Park Relocate Golf Course Truncate Burton
Station Rd, add loop road
6
![Page 7: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/7.jpg)
WHERE ARE WE NOW?• Things have
changed – Time for Plan Update
• No More Golf Course• Outlet Mall
Developed• Road network
changed (Wesleyan Dr. is now Premium Outlet Blvd, Burton Station Rd will now need to remain open to Miller Store Rd)
• 381-Unit Apartment Project Approved
• Airport Authority Re-zoned their property to I-1 in 2017
7
![Page 8: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/8.jpg)
WHERE ARE WE NOW?
8 8
![Page 9: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/9.jpg)
9
CAPITAL PROJECTS
![Page 10: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/10.jpg)
Burton Station RoadNorthampton Blvd to Tim Rd
Tolliver Road
300‘ west of Burton Station Road to RR
• Total Project Cost $15 million
• Construction awarded January 2018
• Construction start April 2018
• Construction completion Summer 2019
10
![Page 11: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/11.jpg)
Burton Station Road
Tolliver Road
11
![Page 12: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/12.jpg)
BS Lake Outfall Improvements
Scope: Piping and concrete flume from lake to Diamond Springs Road
Cost Participation Agreement: City design and acquire property; Developer to Construct
• Total Project Cost $1.5 million
• Acquisition Substantially Complete
• Construction start Summer 2018
• Construction Completion early 2019
12
![Page 13: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/13.jpg)
• New sewer pump station to serve projected development
• Total Project Cost = $2.15 million
• Construction start late 2018
• Construction Completion late 2019
Sanitary Sewer Pump Station
13
![Page 14: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/14.jpg)
14
PROPOSED FIRE/EMS STATION
Tolliver Road
Project Schedule/Cost
Design: May 2017 – Jun 2018Construction: Jan. 2019 – April 2020
Total CIP Funding $7,810,000
Project Summary• 14,300 Square Feet• 3-Apparatus Bays• One Engine Company• One Ladder Company• Technical Rescue Capabilities• EMS Advanced Life Support Unit• Mass Casualty Incident Support Unit
![Page 15: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/15.jpg)
Tolliver Road Extension
Extension of Tolliver Road from RR to Air Rail Avenue and Improvements along Air Rail Avenue to Thurston Avenue
• Project provides curb and gutter, sidewalks, sewer, water, storm water, LED street lights and relocates an existing pump station
• Design start fall 2018• Not funded for construction
15
![Page 16: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/16.jpg)
Burton Station Extension
• Extends Burton Station Road improvements from Tim Road to Miller Store Road
• Not funded
16
![Page 17: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/17.jpg)
17
VDOT NORTHAMPTON BLVD. /I-64 INTERCHANGE IMPROVEMENT PROJECT
![Page 18: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/18.jpg)
WHERE ARE WE NOW?
8 18
![Page 19: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/19.jpg)
19
DRAFT LAND USE PLAN
![Page 20: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/20.jpg)
20
BURTON STATION VILLAGE
Proposed Plan is for Mixed UseExisting Plan is for Single Family
![Page 21: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/21.jpg)
21
MIXED USE BUILDINGS
l height to be three to five stories insula Town Center development)
Building Heightsto be 3-5 stories
(PeninsulaTown Center)
![Page 22: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/22.jpg)
MULTI-USE DEVELOPMENTS
Multi-Use Development (Horizontal) in York County
22
![Page 23: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/23.jpg)
MIXED/MULTI USE OPEN SPACE
• Mixed and Multi-Use developments feature common open space networks and central gathering places. A key design feature is to ensure that the entire development is walkable
23
![Page 24: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/24.jpg)
A greenway/park system should be developed to replace the former existing and planned golf course. This system will serve to provide buffers, connections between land uses, and aesthetic enhancement of the built environment.
OPEN SPACE DEVELOPMENT STRATEGIES:• Incorporate centralized open
space with mixed-use development
• Design stormwater management facilities with parks and recreation component
• Create continuous greenway for recreation and pedestrian and bikeway connectivity throughout site and to other destinations
OPEN SPACE
24
![Page 25: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/25.jpg)
TOWN GREEN:• Central park &
gathering space in a mixed-use center or village
MIXED-USE DEVELOPMENT OPEN SPACE
25
![Page 26: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/26.jpg)
URBAN PLAZA:• Smaller-scale urban
open space within a mixed-use setting
MIXED-USE DEVELOPMENT OPEN SPACE
26
![Page 27: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/27.jpg)
ECO-GARDEN AND LAKE TRAILS:• Primary purpose – stormwater
management• Secondary purpose – recreational use
OPEN SPACE INTEGRATED WITH STORMWATER
27
![Page 28: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/28.jpg)
TRAIL NETWORK:• Accommodates multiple forms of
recreation, creates connections, and establishes a greenway framework throughout the area
OPEN SPACE GREENWAY SYSTEM
28
![Page 29: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/29.jpg)
NORFOLK’S LAKE WRIGHTCONCEPTUAL OPEN SPACE PLAN
Connect new greenway to Lake Wright Trail• New soft trail around lake• Existing crosswalk
29
![Page 30: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/30.jpg)
LAKE LAWSON / LAKE SMITH NATURAL AREA
Nearest City park with broad range of amenities
• Playground• Trails• Scenic Overlooks• Fishing• Boating & kayak access
30
![Page 31: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/31.jpg)
FUTURE TIMELINE FOR SGA PLAN UPDATE
• Brief City Council on Draft Plan changes on May 1, 2018
• Next Steering Committee meeting to be scheduled in May, 2018
• Complete Draft Plan Update Document and brief Planning Commission on May 9, 2018
• Planning Commission Public Hearing on June 13, 2018
• Tentative City Council Public Hearing July 10, 2018
31
![Page 32: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/32.jpg)
32
BURTON CROSSING REZONING (SCHEDULED FOR PLANNING COMMISSION IN MAY)
2018 SGA PlanPending rezoning application scheduled for
May Planning Commission
![Page 33: BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL … · 2018. 5. 1. · STRATEGIC GROWTH AREA PLAN UPDATE CITY COUNCIL BRIEFING MAY 01, 2018 1 Mark E. Shea, Comprehensive](https://reader035.fdocuments.us/reader035/viewer/2022071106/5fe0601aab655f4e62496b75/html5/thumbnails/33.jpg)
33
DISCUSSION