Burj Dubai Concept, Design and Construction Presentation

120
Burj Dubai Concept, Design & Construction

Transcript of Burj Dubai Concept, Design and Construction Presentation

Page 1: Burj Dubai Concept, Design and Construction Presentation

Burj DubaiConcept Design amp Construction

Introductionbull Burj Khalifa (formally Dubai) is the new

tallest tower in the worldbull Construction began on 21 September

2004 amp completed on 1 October 2009 bull The building was officially opened on 4

January 2010bull Height of the Tower is 828m bull Itrsquos Owner is EMAAR Properties with total

investments of US$ 15 billionbull The tower is designed by Skidmore

Owings and Merrill (SOM) bull Adrian smith was chief architect

Worldrsquos Tallest Buildingbull From the head start it has been

intended that the Burj Dubai be the Worldsrsquo Tallest Building

bull The official arbiter of height is the Council on Tall Buildings and Urban the illinois Institute of Technology in Chicago Illinois

bull The CTBUH measures the height of buildings (measured from sidewalk at the main entrance)

bull Burj Dubai is the tallest skyscraper to top of spire 828 m

bull Building with highest occupied floor in the world163rd floor

Worldrsquos Tallest Buildingbull Highest outdoor observation deck in the

world (124th floor) at 452 m bull Worlds highest elevator installation

situated inside a rod at the very top of the building

bull Worlds fastest elevators at speed of 64 kmh (40 mph) or 18 ms

bull Highest vertical concrete pumping (for a building) 606 m

bull Worlds highest installation of an aluminum and glass facade at a height of 512 m

bull Worlds highest New Year fireworks display

Architectural ConceptThe context of the Burj

Dubai being located in the city of Dubai UAE drove the inspiration for the building form to incorporate cultural and historical particular to the region

The influences of the Middle Eastern domes and pointed arches in traditional buildings spiral imagery in Middle Eastern architecture resulted in the tri-axial shape of the building

Architecture

Burj Dubai includes163 habitable floors plus 46 maintenance levels in the spire and 9 parking levels in the basementFloor Area 309473 m2

The Residences900 residence from floor

Armani ResidencesArmani Residences Dubai

has been designed personally by Giorgio Armani 144 suites

Hotel (L39)

Residence (L108)

Spire

Observa-tory (L123)

Communication (L160)

Office (L153)

Pinnacle

ArchitectureThe observatory

On level 123 At the Top Burj Dubai is a must-see attraction and offers breathtaking views of the city and the surrounding emirateConnected to the tower are The Offices a 12-storey annex of prime office space

The Corporate Suites Are located on the highest levels of

the tower They occupy 37 floors with the top three floors merged into a single office Express lifts take office visitors directly to a lounge lobby at Level 123

Hotel (L39)

Residence (L108)

Spire

Observatory (L123)

Communication (L160)

Office (L153)

Pinnacle

ArchitectureMechanical Floors

Seven double-storey mechanical floors house the equipment that bring Burj Dubai to life Located every 30 storeys the mechanical floors house the electrical sub-stations water tanks and pumps air-handling units etc that are essential for the operation of the tower and the comfort of its occupantsBroadcast and Communications Floors

The top four floors have been reserved for communications and broadcasting These floors occupy the levels just below the spire

Main Structure amp DesignThe tower superstructure of Burj Dubai is designed

as an all reinforced concrete building with high performance concrete from the foundation level to level 156 and is topped with a structural steel braced frame from level 156 to the pinnacle

Designers purposely shaped the structural concrete Burj Dubai ndash ldquoYrdquo shaped in plan ndash to reduce the wind forces on the tower as well as to keep the structure simple and foster constructability

The structural system can be described as a ldquobuttressedrdquo core Each wing with its own high performance concrete corridor walls and perimeter columns buttresses the others via a six-sided central core or hexagonal hub

Main Structure amp Design

Structural Analysis amp Design

The top section of the Tower consists of a structural steel spire utilizing a diagonally braced lateral system

The structural steel spire was designed for gravity wind seismic and fatigue in accordance with the requirements of AISC Load and Resistance Factor Design Specification for Structural Steel Buildings (1999) The exterior exposed steel is protected with a flame applied aluminum finish

Main Structure amp Design The result is a tower that is

extremely stiff laterally and torsionally similar to a closed tube

Each tier of the building sets back in a spiral stepping pattern up the building The setbacks are organized with the towerrsquos grid such that the building stepping is accomplished by aligning columns above with walls below to provide a smooth load path

The advantage of the stepping and shaping is to ldquoconfuse the windrdquo The wind vortices never get organized because at each new tier the wind encounters a different building shape

Main Structure

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 2: Burj Dubai Concept, Design and Construction Presentation

Introductionbull Burj Khalifa (formally Dubai) is the new

tallest tower in the worldbull Construction began on 21 September

2004 amp completed on 1 October 2009 bull The building was officially opened on 4

January 2010bull Height of the Tower is 828m bull Itrsquos Owner is EMAAR Properties with total

investments of US$ 15 billionbull The tower is designed by Skidmore

Owings and Merrill (SOM) bull Adrian smith was chief architect

Worldrsquos Tallest Buildingbull From the head start it has been

intended that the Burj Dubai be the Worldsrsquo Tallest Building

bull The official arbiter of height is the Council on Tall Buildings and Urban the illinois Institute of Technology in Chicago Illinois

bull The CTBUH measures the height of buildings (measured from sidewalk at the main entrance)

bull Burj Dubai is the tallest skyscraper to top of spire 828 m

bull Building with highest occupied floor in the world163rd floor

Worldrsquos Tallest Buildingbull Highest outdoor observation deck in the

world (124th floor) at 452 m bull Worlds highest elevator installation

situated inside a rod at the very top of the building

bull Worlds fastest elevators at speed of 64 kmh (40 mph) or 18 ms

bull Highest vertical concrete pumping (for a building) 606 m

bull Worlds highest installation of an aluminum and glass facade at a height of 512 m

bull Worlds highest New Year fireworks display

Architectural ConceptThe context of the Burj

Dubai being located in the city of Dubai UAE drove the inspiration for the building form to incorporate cultural and historical particular to the region

The influences of the Middle Eastern domes and pointed arches in traditional buildings spiral imagery in Middle Eastern architecture resulted in the tri-axial shape of the building

Architecture

Burj Dubai includes163 habitable floors plus 46 maintenance levels in the spire and 9 parking levels in the basementFloor Area 309473 m2

The Residences900 residence from floor

Armani ResidencesArmani Residences Dubai

has been designed personally by Giorgio Armani 144 suites

Hotel (L39)

Residence (L108)

Spire

Observa-tory (L123)

Communication (L160)

Office (L153)

Pinnacle

ArchitectureThe observatory

On level 123 At the Top Burj Dubai is a must-see attraction and offers breathtaking views of the city and the surrounding emirateConnected to the tower are The Offices a 12-storey annex of prime office space

The Corporate Suites Are located on the highest levels of

the tower They occupy 37 floors with the top three floors merged into a single office Express lifts take office visitors directly to a lounge lobby at Level 123

Hotel (L39)

Residence (L108)

Spire

Observatory (L123)

Communication (L160)

Office (L153)

Pinnacle

ArchitectureMechanical Floors

Seven double-storey mechanical floors house the equipment that bring Burj Dubai to life Located every 30 storeys the mechanical floors house the electrical sub-stations water tanks and pumps air-handling units etc that are essential for the operation of the tower and the comfort of its occupantsBroadcast and Communications Floors

The top four floors have been reserved for communications and broadcasting These floors occupy the levels just below the spire

Main Structure amp DesignThe tower superstructure of Burj Dubai is designed

as an all reinforced concrete building with high performance concrete from the foundation level to level 156 and is topped with a structural steel braced frame from level 156 to the pinnacle

Designers purposely shaped the structural concrete Burj Dubai ndash ldquoYrdquo shaped in plan ndash to reduce the wind forces on the tower as well as to keep the structure simple and foster constructability

The structural system can be described as a ldquobuttressedrdquo core Each wing with its own high performance concrete corridor walls and perimeter columns buttresses the others via a six-sided central core or hexagonal hub

Main Structure amp Design

Structural Analysis amp Design

The top section of the Tower consists of a structural steel spire utilizing a diagonally braced lateral system

The structural steel spire was designed for gravity wind seismic and fatigue in accordance with the requirements of AISC Load and Resistance Factor Design Specification for Structural Steel Buildings (1999) The exterior exposed steel is protected with a flame applied aluminum finish

Main Structure amp Design The result is a tower that is

extremely stiff laterally and torsionally similar to a closed tube

Each tier of the building sets back in a spiral stepping pattern up the building The setbacks are organized with the towerrsquos grid such that the building stepping is accomplished by aligning columns above with walls below to provide a smooth load path

The advantage of the stepping and shaping is to ldquoconfuse the windrdquo The wind vortices never get organized because at each new tier the wind encounters a different building shape

Main Structure

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 3: Burj Dubai Concept, Design and Construction Presentation

Worldrsquos Tallest Buildingbull From the head start it has been

intended that the Burj Dubai be the Worldsrsquo Tallest Building

bull The official arbiter of height is the Council on Tall Buildings and Urban the illinois Institute of Technology in Chicago Illinois

bull The CTBUH measures the height of buildings (measured from sidewalk at the main entrance)

bull Burj Dubai is the tallest skyscraper to top of spire 828 m

bull Building with highest occupied floor in the world163rd floor

Worldrsquos Tallest Buildingbull Highest outdoor observation deck in the

world (124th floor) at 452 m bull Worlds highest elevator installation

situated inside a rod at the very top of the building

bull Worlds fastest elevators at speed of 64 kmh (40 mph) or 18 ms

bull Highest vertical concrete pumping (for a building) 606 m

bull Worlds highest installation of an aluminum and glass facade at a height of 512 m

bull Worlds highest New Year fireworks display

Architectural ConceptThe context of the Burj

Dubai being located in the city of Dubai UAE drove the inspiration for the building form to incorporate cultural and historical particular to the region

The influences of the Middle Eastern domes and pointed arches in traditional buildings spiral imagery in Middle Eastern architecture resulted in the tri-axial shape of the building

Architecture

Burj Dubai includes163 habitable floors plus 46 maintenance levels in the spire and 9 parking levels in the basementFloor Area 309473 m2

The Residences900 residence from floor

Armani ResidencesArmani Residences Dubai

has been designed personally by Giorgio Armani 144 suites

Hotel (L39)

Residence (L108)

Spire

Observa-tory (L123)

Communication (L160)

Office (L153)

Pinnacle

ArchitectureThe observatory

On level 123 At the Top Burj Dubai is a must-see attraction and offers breathtaking views of the city and the surrounding emirateConnected to the tower are The Offices a 12-storey annex of prime office space

The Corporate Suites Are located on the highest levels of

the tower They occupy 37 floors with the top three floors merged into a single office Express lifts take office visitors directly to a lounge lobby at Level 123

Hotel (L39)

Residence (L108)

Spire

Observatory (L123)

Communication (L160)

Office (L153)

Pinnacle

ArchitectureMechanical Floors

Seven double-storey mechanical floors house the equipment that bring Burj Dubai to life Located every 30 storeys the mechanical floors house the electrical sub-stations water tanks and pumps air-handling units etc that are essential for the operation of the tower and the comfort of its occupantsBroadcast and Communications Floors

The top four floors have been reserved for communications and broadcasting These floors occupy the levels just below the spire

Main Structure amp DesignThe tower superstructure of Burj Dubai is designed

as an all reinforced concrete building with high performance concrete from the foundation level to level 156 and is topped with a structural steel braced frame from level 156 to the pinnacle

Designers purposely shaped the structural concrete Burj Dubai ndash ldquoYrdquo shaped in plan ndash to reduce the wind forces on the tower as well as to keep the structure simple and foster constructability

The structural system can be described as a ldquobuttressedrdquo core Each wing with its own high performance concrete corridor walls and perimeter columns buttresses the others via a six-sided central core or hexagonal hub

Main Structure amp Design

Structural Analysis amp Design

The top section of the Tower consists of a structural steel spire utilizing a diagonally braced lateral system

The structural steel spire was designed for gravity wind seismic and fatigue in accordance with the requirements of AISC Load and Resistance Factor Design Specification for Structural Steel Buildings (1999) The exterior exposed steel is protected with a flame applied aluminum finish

Main Structure amp Design The result is a tower that is

extremely stiff laterally and torsionally similar to a closed tube

Each tier of the building sets back in a spiral stepping pattern up the building The setbacks are organized with the towerrsquos grid such that the building stepping is accomplished by aligning columns above with walls below to provide a smooth load path

The advantage of the stepping and shaping is to ldquoconfuse the windrdquo The wind vortices never get organized because at each new tier the wind encounters a different building shape

Main Structure

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 4: Burj Dubai Concept, Design and Construction Presentation

Worldrsquos Tallest Buildingbull Highest outdoor observation deck in the

world (124th floor) at 452 m bull Worlds highest elevator installation

situated inside a rod at the very top of the building

bull Worlds fastest elevators at speed of 64 kmh (40 mph) or 18 ms

bull Highest vertical concrete pumping (for a building) 606 m

bull Worlds highest installation of an aluminum and glass facade at a height of 512 m

bull Worlds highest New Year fireworks display

Architectural ConceptThe context of the Burj

Dubai being located in the city of Dubai UAE drove the inspiration for the building form to incorporate cultural and historical particular to the region

The influences of the Middle Eastern domes and pointed arches in traditional buildings spiral imagery in Middle Eastern architecture resulted in the tri-axial shape of the building

Architecture

Burj Dubai includes163 habitable floors plus 46 maintenance levels in the spire and 9 parking levels in the basementFloor Area 309473 m2

The Residences900 residence from floor

Armani ResidencesArmani Residences Dubai

has been designed personally by Giorgio Armani 144 suites

Hotel (L39)

Residence (L108)

Spire

Observa-tory (L123)

Communication (L160)

Office (L153)

Pinnacle

ArchitectureThe observatory

On level 123 At the Top Burj Dubai is a must-see attraction and offers breathtaking views of the city and the surrounding emirateConnected to the tower are The Offices a 12-storey annex of prime office space

The Corporate Suites Are located on the highest levels of

the tower They occupy 37 floors with the top three floors merged into a single office Express lifts take office visitors directly to a lounge lobby at Level 123

Hotel (L39)

Residence (L108)

Spire

Observatory (L123)

Communication (L160)

Office (L153)

Pinnacle

ArchitectureMechanical Floors

Seven double-storey mechanical floors house the equipment that bring Burj Dubai to life Located every 30 storeys the mechanical floors house the electrical sub-stations water tanks and pumps air-handling units etc that are essential for the operation of the tower and the comfort of its occupantsBroadcast and Communications Floors

The top four floors have been reserved for communications and broadcasting These floors occupy the levels just below the spire

Main Structure amp DesignThe tower superstructure of Burj Dubai is designed

as an all reinforced concrete building with high performance concrete from the foundation level to level 156 and is topped with a structural steel braced frame from level 156 to the pinnacle

Designers purposely shaped the structural concrete Burj Dubai ndash ldquoYrdquo shaped in plan ndash to reduce the wind forces on the tower as well as to keep the structure simple and foster constructability

The structural system can be described as a ldquobuttressedrdquo core Each wing with its own high performance concrete corridor walls and perimeter columns buttresses the others via a six-sided central core or hexagonal hub

Main Structure amp Design

Structural Analysis amp Design

The top section of the Tower consists of a structural steel spire utilizing a diagonally braced lateral system

The structural steel spire was designed for gravity wind seismic and fatigue in accordance with the requirements of AISC Load and Resistance Factor Design Specification for Structural Steel Buildings (1999) The exterior exposed steel is protected with a flame applied aluminum finish

Main Structure amp Design The result is a tower that is

extremely stiff laterally and torsionally similar to a closed tube

Each tier of the building sets back in a spiral stepping pattern up the building The setbacks are organized with the towerrsquos grid such that the building stepping is accomplished by aligning columns above with walls below to provide a smooth load path

The advantage of the stepping and shaping is to ldquoconfuse the windrdquo The wind vortices never get organized because at each new tier the wind encounters a different building shape

Main Structure

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 5: Burj Dubai Concept, Design and Construction Presentation

Architectural ConceptThe context of the Burj

Dubai being located in the city of Dubai UAE drove the inspiration for the building form to incorporate cultural and historical particular to the region

The influences of the Middle Eastern domes and pointed arches in traditional buildings spiral imagery in Middle Eastern architecture resulted in the tri-axial shape of the building

Architecture

Burj Dubai includes163 habitable floors plus 46 maintenance levels in the spire and 9 parking levels in the basementFloor Area 309473 m2

The Residences900 residence from floor

Armani ResidencesArmani Residences Dubai

has been designed personally by Giorgio Armani 144 suites

Hotel (L39)

Residence (L108)

Spire

Observa-tory (L123)

Communication (L160)

Office (L153)

Pinnacle

ArchitectureThe observatory

On level 123 At the Top Burj Dubai is a must-see attraction and offers breathtaking views of the city and the surrounding emirateConnected to the tower are The Offices a 12-storey annex of prime office space

The Corporate Suites Are located on the highest levels of

the tower They occupy 37 floors with the top three floors merged into a single office Express lifts take office visitors directly to a lounge lobby at Level 123

Hotel (L39)

Residence (L108)

Spire

Observatory (L123)

Communication (L160)

Office (L153)

Pinnacle

ArchitectureMechanical Floors

Seven double-storey mechanical floors house the equipment that bring Burj Dubai to life Located every 30 storeys the mechanical floors house the electrical sub-stations water tanks and pumps air-handling units etc that are essential for the operation of the tower and the comfort of its occupantsBroadcast and Communications Floors

The top four floors have been reserved for communications and broadcasting These floors occupy the levels just below the spire

Main Structure amp DesignThe tower superstructure of Burj Dubai is designed

as an all reinforced concrete building with high performance concrete from the foundation level to level 156 and is topped with a structural steel braced frame from level 156 to the pinnacle

Designers purposely shaped the structural concrete Burj Dubai ndash ldquoYrdquo shaped in plan ndash to reduce the wind forces on the tower as well as to keep the structure simple and foster constructability

The structural system can be described as a ldquobuttressedrdquo core Each wing with its own high performance concrete corridor walls and perimeter columns buttresses the others via a six-sided central core or hexagonal hub

Main Structure amp Design

Structural Analysis amp Design

The top section of the Tower consists of a structural steel spire utilizing a diagonally braced lateral system

The structural steel spire was designed for gravity wind seismic and fatigue in accordance with the requirements of AISC Load and Resistance Factor Design Specification for Structural Steel Buildings (1999) The exterior exposed steel is protected with a flame applied aluminum finish

Main Structure amp Design The result is a tower that is

extremely stiff laterally and torsionally similar to a closed tube

Each tier of the building sets back in a spiral stepping pattern up the building The setbacks are organized with the towerrsquos grid such that the building stepping is accomplished by aligning columns above with walls below to provide a smooth load path

The advantage of the stepping and shaping is to ldquoconfuse the windrdquo The wind vortices never get organized because at each new tier the wind encounters a different building shape

Main Structure

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 6: Burj Dubai Concept, Design and Construction Presentation

Architecture

Burj Dubai includes163 habitable floors plus 46 maintenance levels in the spire and 9 parking levels in the basementFloor Area 309473 m2

The Residences900 residence from floor

Armani ResidencesArmani Residences Dubai

has been designed personally by Giorgio Armani 144 suites

Hotel (L39)

Residence (L108)

Spire

Observa-tory (L123)

Communication (L160)

Office (L153)

Pinnacle

ArchitectureThe observatory

On level 123 At the Top Burj Dubai is a must-see attraction and offers breathtaking views of the city and the surrounding emirateConnected to the tower are The Offices a 12-storey annex of prime office space

The Corporate Suites Are located on the highest levels of

the tower They occupy 37 floors with the top three floors merged into a single office Express lifts take office visitors directly to a lounge lobby at Level 123

Hotel (L39)

Residence (L108)

Spire

Observatory (L123)

Communication (L160)

Office (L153)

Pinnacle

ArchitectureMechanical Floors

Seven double-storey mechanical floors house the equipment that bring Burj Dubai to life Located every 30 storeys the mechanical floors house the electrical sub-stations water tanks and pumps air-handling units etc that are essential for the operation of the tower and the comfort of its occupantsBroadcast and Communications Floors

The top four floors have been reserved for communications and broadcasting These floors occupy the levels just below the spire

Main Structure amp DesignThe tower superstructure of Burj Dubai is designed

as an all reinforced concrete building with high performance concrete from the foundation level to level 156 and is topped with a structural steel braced frame from level 156 to the pinnacle

Designers purposely shaped the structural concrete Burj Dubai ndash ldquoYrdquo shaped in plan ndash to reduce the wind forces on the tower as well as to keep the structure simple and foster constructability

The structural system can be described as a ldquobuttressedrdquo core Each wing with its own high performance concrete corridor walls and perimeter columns buttresses the others via a six-sided central core or hexagonal hub

Main Structure amp Design

Structural Analysis amp Design

The top section of the Tower consists of a structural steel spire utilizing a diagonally braced lateral system

The structural steel spire was designed for gravity wind seismic and fatigue in accordance with the requirements of AISC Load and Resistance Factor Design Specification for Structural Steel Buildings (1999) The exterior exposed steel is protected with a flame applied aluminum finish

Main Structure amp Design The result is a tower that is

extremely stiff laterally and torsionally similar to a closed tube

Each tier of the building sets back in a spiral stepping pattern up the building The setbacks are organized with the towerrsquos grid such that the building stepping is accomplished by aligning columns above with walls below to provide a smooth load path

The advantage of the stepping and shaping is to ldquoconfuse the windrdquo The wind vortices never get organized because at each new tier the wind encounters a different building shape

Main Structure

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 7: Burj Dubai Concept, Design and Construction Presentation

ArchitectureThe observatory

On level 123 At the Top Burj Dubai is a must-see attraction and offers breathtaking views of the city and the surrounding emirateConnected to the tower are The Offices a 12-storey annex of prime office space

The Corporate Suites Are located on the highest levels of

the tower They occupy 37 floors with the top three floors merged into a single office Express lifts take office visitors directly to a lounge lobby at Level 123

Hotel (L39)

Residence (L108)

Spire

Observatory (L123)

Communication (L160)

Office (L153)

Pinnacle

ArchitectureMechanical Floors

Seven double-storey mechanical floors house the equipment that bring Burj Dubai to life Located every 30 storeys the mechanical floors house the electrical sub-stations water tanks and pumps air-handling units etc that are essential for the operation of the tower and the comfort of its occupantsBroadcast and Communications Floors

The top four floors have been reserved for communications and broadcasting These floors occupy the levels just below the spire

Main Structure amp DesignThe tower superstructure of Burj Dubai is designed

as an all reinforced concrete building with high performance concrete from the foundation level to level 156 and is topped with a structural steel braced frame from level 156 to the pinnacle

Designers purposely shaped the structural concrete Burj Dubai ndash ldquoYrdquo shaped in plan ndash to reduce the wind forces on the tower as well as to keep the structure simple and foster constructability

The structural system can be described as a ldquobuttressedrdquo core Each wing with its own high performance concrete corridor walls and perimeter columns buttresses the others via a six-sided central core or hexagonal hub

Main Structure amp Design

Structural Analysis amp Design

The top section of the Tower consists of a structural steel spire utilizing a diagonally braced lateral system

The structural steel spire was designed for gravity wind seismic and fatigue in accordance with the requirements of AISC Load and Resistance Factor Design Specification for Structural Steel Buildings (1999) The exterior exposed steel is protected with a flame applied aluminum finish

Main Structure amp Design The result is a tower that is

extremely stiff laterally and torsionally similar to a closed tube

Each tier of the building sets back in a spiral stepping pattern up the building The setbacks are organized with the towerrsquos grid such that the building stepping is accomplished by aligning columns above with walls below to provide a smooth load path

The advantage of the stepping and shaping is to ldquoconfuse the windrdquo The wind vortices never get organized because at each new tier the wind encounters a different building shape

Main Structure

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 8: Burj Dubai Concept, Design and Construction Presentation

ArchitectureMechanical Floors

Seven double-storey mechanical floors house the equipment that bring Burj Dubai to life Located every 30 storeys the mechanical floors house the electrical sub-stations water tanks and pumps air-handling units etc that are essential for the operation of the tower and the comfort of its occupantsBroadcast and Communications Floors

The top four floors have been reserved for communications and broadcasting These floors occupy the levels just below the spire

Main Structure amp DesignThe tower superstructure of Burj Dubai is designed

as an all reinforced concrete building with high performance concrete from the foundation level to level 156 and is topped with a structural steel braced frame from level 156 to the pinnacle

Designers purposely shaped the structural concrete Burj Dubai ndash ldquoYrdquo shaped in plan ndash to reduce the wind forces on the tower as well as to keep the structure simple and foster constructability

The structural system can be described as a ldquobuttressedrdquo core Each wing with its own high performance concrete corridor walls and perimeter columns buttresses the others via a six-sided central core or hexagonal hub

Main Structure amp Design

Structural Analysis amp Design

The top section of the Tower consists of a structural steel spire utilizing a diagonally braced lateral system

The structural steel spire was designed for gravity wind seismic and fatigue in accordance with the requirements of AISC Load and Resistance Factor Design Specification for Structural Steel Buildings (1999) The exterior exposed steel is protected with a flame applied aluminum finish

Main Structure amp Design The result is a tower that is

extremely stiff laterally and torsionally similar to a closed tube

Each tier of the building sets back in a spiral stepping pattern up the building The setbacks are organized with the towerrsquos grid such that the building stepping is accomplished by aligning columns above with walls below to provide a smooth load path

The advantage of the stepping and shaping is to ldquoconfuse the windrdquo The wind vortices never get organized because at each new tier the wind encounters a different building shape

Main Structure

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 9: Burj Dubai Concept, Design and Construction Presentation

Main Structure amp DesignThe tower superstructure of Burj Dubai is designed

as an all reinforced concrete building with high performance concrete from the foundation level to level 156 and is topped with a structural steel braced frame from level 156 to the pinnacle

Designers purposely shaped the structural concrete Burj Dubai ndash ldquoYrdquo shaped in plan ndash to reduce the wind forces on the tower as well as to keep the structure simple and foster constructability

The structural system can be described as a ldquobuttressedrdquo core Each wing with its own high performance concrete corridor walls and perimeter columns buttresses the others via a six-sided central core or hexagonal hub

Main Structure amp Design

Structural Analysis amp Design

The top section of the Tower consists of a structural steel spire utilizing a diagonally braced lateral system

The structural steel spire was designed for gravity wind seismic and fatigue in accordance with the requirements of AISC Load and Resistance Factor Design Specification for Structural Steel Buildings (1999) The exterior exposed steel is protected with a flame applied aluminum finish

Main Structure amp Design The result is a tower that is

extremely stiff laterally and torsionally similar to a closed tube

Each tier of the building sets back in a spiral stepping pattern up the building The setbacks are organized with the towerrsquos grid such that the building stepping is accomplished by aligning columns above with walls below to provide a smooth load path

The advantage of the stepping and shaping is to ldquoconfuse the windrdquo The wind vortices never get organized because at each new tier the wind encounters a different building shape

Main Structure

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 10: Burj Dubai Concept, Design and Construction Presentation

Main Structure amp Design

Structural Analysis amp Design

The top section of the Tower consists of a structural steel spire utilizing a diagonally braced lateral system

The structural steel spire was designed for gravity wind seismic and fatigue in accordance with the requirements of AISC Load and Resistance Factor Design Specification for Structural Steel Buildings (1999) The exterior exposed steel is protected with a flame applied aluminum finish

Main Structure amp Design The result is a tower that is

extremely stiff laterally and torsionally similar to a closed tube

Each tier of the building sets back in a spiral stepping pattern up the building The setbacks are organized with the towerrsquos grid such that the building stepping is accomplished by aligning columns above with walls below to provide a smooth load path

The advantage of the stepping and shaping is to ldquoconfuse the windrdquo The wind vortices never get organized because at each new tier the wind encounters a different building shape

Main Structure

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 11: Burj Dubai Concept, Design and Construction Presentation

Structural Analysis amp Design

The top section of the Tower consists of a structural steel spire utilizing a diagonally braced lateral system

The structural steel spire was designed for gravity wind seismic and fatigue in accordance with the requirements of AISC Load and Resistance Factor Design Specification for Structural Steel Buildings (1999) The exterior exposed steel is protected with a flame applied aluminum finish

Main Structure amp Design The result is a tower that is

extremely stiff laterally and torsionally similar to a closed tube

Each tier of the building sets back in a spiral stepping pattern up the building The setbacks are organized with the towerrsquos grid such that the building stepping is accomplished by aligning columns above with walls below to provide a smooth load path

The advantage of the stepping and shaping is to ldquoconfuse the windrdquo The wind vortices never get organized because at each new tier the wind encounters a different building shape

Main Structure

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 12: Burj Dubai Concept, Design and Construction Presentation

Main Structure amp Design The result is a tower that is

extremely stiff laterally and torsionally similar to a closed tube

Each tier of the building sets back in a spiral stepping pattern up the building The setbacks are organized with the towerrsquos grid such that the building stepping is accomplished by aligning columns above with walls below to provide a smooth load path

The advantage of the stepping and shaping is to ldquoconfuse the windrdquo The wind vortices never get organized because at each new tier the wind encounters a different building shape

Main Structure

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 13: Burj Dubai Concept, Design and Construction Presentation

Main Structure

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 14: Burj Dubai Concept, Design and Construction Presentation

Structural Analysis amp DesignThe center hexagonal walls are

buttressed by the wing walls and hammer head walls which behave as the webs and flanges of a beam to resist the wind shears and moments

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 15: Burj Dubai Concept, Design and Construction Presentation

Structural Analysis amp DesignOutriggers at the mechanical floors

allow the columns to participate in the lateral load resistance of the structure hence all of the vertical concrete is utilized to support both gravity and lateral loads

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 16: Burj Dubai Concept, Design and Construction Presentation

Structural Analysis amp Design Concrete Dimensions

The core walls vary in thickness from 1300mm to 500mm The core walls are typically linked through a series of 800mm to 1100mm deep reinforced concrete or composite link beams at every level

The residential and hotel floor framing system of the Tower consists of 200mm to 300mm two-way reinforced concrete flat plate slabs spanning approximately 9 meters between the exterior columns and the interior core wall

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 17: Burj Dubai Concept, Design and Construction Presentation

Structural Analysis amp Design Link Beams

The demands on the link beams vary greatly

The typical link beams used in the Burj Dubai are quite stocky with a shear-span ratio (l2h) of 085 a width of 650 mm and a height of 825 mm

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 18: Burj Dubai Concept, Design and Construction Presentation

Structural Analysis amp Design Link Beams

For the design of reinforced concrete link beams1 The conventional deep beam design method in

the ACI 318-992 2 Strut-and-tie method in ACI 318-023 were used

with Appendix A enabling the design of link beams somewhat beyond the conventionally designed maximum deep beam stress limit

3 In the case of members subjected to very large shear forces embedded built-up structural steel sections were provided within the core of the concrete link beams to carry the entire shear and flexure demand

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 19: Burj Dubai Concept, Design and Construction Presentation

Strut and Tie model for the Link Beam

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 20: Burj Dubai Concept, Design and Construction Presentation

Design Details of Link Beams

The geometry factored loads and design methods of four Burj Dubai link beams LB1 to LB4 are shown in Table 1

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 21: Burj Dubai Concept, Design and Construction Presentation

Design Details of Link Beams

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 22: Burj Dubai Concept, Design and Construction Presentation

Structural Analysis amp DesignClear Heights

The tower is being constructed utilizing a horizontal compensation program Each story is being constructed incorporating a modest increase in the typical floor-to-floor height

This vertical compensation was selected to ensure the actual height of the structure after the time-dependant shortening effects of creep and shrinkage will be greater than the as-designed final height

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 23: Burj Dubai Concept, Design and Construction Presentation

Structural Analysis amp Design

The structure was analyzed for gravity (including P-Delta analysis) wind and seismic loadings by ETABS version 84

The three-dimensional analysis model consisted of the reinforced concrete walls link beams slabs raft piles and the spire structural steel system

The full 3D analysis model consisted of over73500 shells and 75000 nodes

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 24: Burj Dubai Concept, Design and Construction Presentation

Structural Analysis amp DesignDesign Code

The reinforced concrete structure was designed in accordance with the requirements of ACI 318-02 Building Code Requirements for StructuralConcrete

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 25: Burj Dubai Concept, Design and Construction Presentation

Structural Analysis amp DesignSeismic Loads

bull Dubai is situated towards the eastern edge of the geologically stable Arabian Plate and separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf The site is therefore considered to be located within a seismically active area

bull The Dubai Municipality (DM) specifies Dubai as a UBC97 Zone 2a seismic region with a seismic zone factor Z = 015 and soil profile Sc

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 26: Burj Dubai Concept, Design and Construction Presentation

Structural Analysis amp DesignSeismic Analysis

bull The seismic analysis consisted of a site-specific response spectra analysis

bull Seismic loading typically did not govern the design of the reinforced concrete tower structure But did govern the design of the steel spire

bull Dr Max Irvine developed site-specific seismic reports for the project including a seismic hazard analysis

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 27: Burj Dubai Concept, Design and Construction Presentation

Structural Analysis amp DesignDynamic Analysis

bull The dynamic analysis indicated the first mode is lateral sidesway with a period of 113 seconds

bull The second mode is a perpendicular lateral sidesway with a period of 102 seconds

bull Torsion is the fifth mode with a period of 43 seconds

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 28: Burj Dubai Concept, Design and Construction Presentation

Types of windWinds that are of interest in the

design of buildings can be classified into three major typesPrevailing Winds (Trade winds)seasonal windslocal winds

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 29: Burj Dubai Concept, Design and Construction Presentation

Types of windThe characteristics of the

prevailing and seasonal winds are analytically studied together whereas those of local winds are studied separately

The variations in the speed of prevailing and seasonal winds are referred to as fluctuations in mean velocity The variations in the local winds are referred to as gusts

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 30: Burj Dubai Concept, Design and Construction Presentation

CHARACTERISTICS OF WIND

bull Variation of wind velocity with heightbull Wind turbulencebull Statistical probabilitybull Vortex shedding phenomenonbull Dynamic nature of windndashstructure interaction

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 31: Burj Dubai Concept, Design and Construction Presentation

Variation of Wind Velocity with Height

The viscosity of air reduces its velocity adjacent to the earthrsquos surface to almost zero

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 32: Burj Dubai Concept, Design and Construction Presentation

Wind TurbulenceFor structural engineering purposes velocity

of wind can be considered as having two components Mean velocity component that increases with

height Turbulent velocity that remains the same over

height

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 33: Burj Dubai Concept, Design and Construction Presentation

Probabilistic Approach

In wind engineering the speed of wind is considered to vary with return periods

For example the fastest-mile wind 33 ft (10 m) above ground in Dallas TX corresponding to a 50-year return period(30 ms) compared to the value of (317 ms) for a 100-year recurrence interval

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 34: Burj Dubai Concept, Design and Construction Presentation

Vortex SheddingThe flow of wind is simplified and

considered two-dimensionalAlong wind transverse wind

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 35: Burj Dubai Concept, Design and Construction Presentation

Vortex SheddingAt low wind speeds shedding

occurs at the same instant on either side of the building It is therefore subject to along-wind oscillations parallel to the wind direction

At higher speeds the vortices are shed alternately first from one and then from the other side there is an impulse in the along-wind direction as before but in addition there is an impulse in the transverse direction

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 36: Burj Dubai Concept, Design and Construction Presentation

Wind behavior

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 37: Burj Dubai Concept, Design and Construction Presentation

Dynamic Nature of Wind

Wind loads associated with gustiness or turbulence creating effects much larger than if the same loads were applied gradually

Wind loads therefore need to be studied as if they were dynamic in nature

The intensity of a wind load depends on how fast it varies and also on the response of the structure

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 38: Burj Dubai Concept, Design and Construction Presentation

WIND CLIMATE STUDIES In the course of the Burj Dubai studies local

ground based data from several weather stations in the region were used including most importantly the data from Dubai International Airport

Gust data from all stations were merged into the equivalent a super-station to obtain an enlarged database

The 50 year 3 second gust from this analysis was estimated to be 377 ms in standard open terrain at the 10 m level

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 39: Burj Dubai Concept, Design and Construction Presentation

WIND CLIMATE STUDIESIn addition the mean hourly data from Dubai were

used to obtain a model of the parent distribution of hourly winds

This yielded a 50 year mean hourly speed of 235 ms again in standard open terrain conditions at 10 m

Depending on exactly which method one used to estimate the relationship between mean and gust speeds the corresponding gust was estimated to be in the range 357 ms to 376 ms

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 40: Burj Dubai Concept, Design and Construction Presentation

WIND CLIMATE STUDIESAn important question when designing a tower of

over 600 m height is the nature of the wind velocity profile and wind turbulence in the upper levels

It is a large extrapolation to go from ground-based data at the 10 m height to heights of over 600 m using standard assumptions

Therefore for Burj Dubai more direct measurements of upper level winds were sought The closest station with balloon records was Abu Dhabi where about 16 years of data were available taken on average about twice per day

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 41: Burj Dubai Concept, Design and Construction Presentation

WIND CLIMATE STUDIES

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 42: Burj Dubai Concept, Design and Construction Presentation

The Wind Engineering of the Burj Dubai TowerFor a building of this height and

slenderness wind forces and the resulting motions in the upper levels become dominant factors in the structural design

The local wind pressures on the building envelope and the wind speeds around the base of the building and on terraces at various levels were of concern

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 43: Burj Dubai Concept, Design and Construction Presentation

WIND-TUNNEL ENGINEERING

Therefore an extensive program of wind tunnel tests and other studies were undertaken

Rigid pressure model High-frequency force-balance technique Full multi-degree of freedom aeroelastic model

study Measurements of local pressures Pedestrian wind environment studies

bull These studies used models mostly at 1500 scale but for the pedestrian wind studies a larger scale of 1250 was utilized

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 44: Burj Dubai Concept, Design and Construction Presentation

Rigid Pressure Model (PM)The primary purpose of the

rigid-model test is for obtaining cladding design pressures get the floor-by-floor shear forces for the design of the overall main wind-force-resisting frame

The wind-tunnel test is run for a duration of about 60 sec which corresponds to approximately 1 hr in real time

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 45: Burj Dubai Concept, Design and Construction Presentation

Cladding Pressure Testing

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 46: Burj Dubai Concept, Design and Construction Presentation

Cladding Pressure Testing

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 47: Burj Dubai Concept, Design and Construction Presentation

High-Frequency Base Force Balance ModelThe effect of wind load on a flexible

building can be considered as an integrated action resulting from three distinct sourcesThe mean wind load that bends and

twists a buildingThe fluctuating load from the unsteady

nature of the wind that results in oscillation of the building

Inertia forces similar to the lateral forces induced in a building during earthquakes

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 48: Burj Dubai Concept, Design and Construction Presentation

High-Frequency Base Force Balance ModelA rigid model is convenient for

measuring local wind pressures consisting of positive and negative pressures distributed uniquely around a building

These local pressures are integrated to derive net lateral forces in two perpendicular directions and a torsional moment about a vertical axis at each level

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 49: Burj Dubai Concept, Design and Construction Presentation

High-Frequency Base Force Balance ModelThese values have been sufficient

for the design of buildings bracing system

HFBFB ignore the influence of gust factor

It is necessary to assume a conservative gust factor to increase the mean values

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 50: Burj Dubai Concept, Design and Construction Presentation

WIND LOADING ON THE MAIN STRUCTURETo determine the wind loading on the

main structure wind tunnel tests were undertaken early in the design using the high-frequency-force-balance technique

The model itself is rigid and is mounted on a fast response force balance

The technique is that it is relatively quick to undertake and provides the complete spectra of the wind generated modal forces acting on the tower

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 51: Burj Dubai Concept, Design and Construction Presentation

WIND LOADING ON THE MAIN STRUCTURE

The results of the force balance tests were used as early input for the structural design and allowed parametric studies to be undertaken on the effects of varying the towerrsquos stiffness and mass distribution

The wind tunnel data were then combined with the dynamic properties of the tower in order to compute the towerrsquos dynamic response and the overall effective wind force distributions at full scale using aeroelastic model analysis

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 52: Burj Dubai Concept, Design and Construction Presentation

The building has essentially siximportant wind directions

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 53: Burj Dubai Concept, Design and Construction Presentation

Orientation of the towerIt was noticed that the force

spectra for different wind directions showed less excitation in the important frequency range for winds impacting the pointed or nose end of a wing than from the opposite direction (tail)

most frequent strong wind directions for Dubai northwest south and east

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 54: Burj Dubai Concept, Design and Construction Presentation

High-Frequency Base Force Balance ModelSeveral rounds of force balance tests

were undertaken as the geometry of the tower evolved and was refined architecturally

After each round of wind tunnel testing the data was analyzed and the building was reshaped to minimize wind effects and accommodate unrelated changes in the Clientrsquos program

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 55: Burj Dubai Concept, Design and Construction Presentation

Original Configuration

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 56: Burj Dubai Concept, Design and Construction Presentation

Aeroelastic model studyAeroelastic model study attempts

to take the guesswork out of the gust factor computation by measuring directly the magnitude of dynamic loads

The aeroelastic studies require similarity of the inertia stiffness and damping characteristics of the building

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 57: Burj Dubai Concept, Design and Construction Presentation

Aeroelastic model studyAeroelastic study basically examines the wind-

induced sway response in addition to providing information on the overall wind-induced mean and dynamic loads

Factors may be used as a guide in making a decision aeroelastic model study

The building height-to-width ratio is greater than about 5 ie the building is slender

Approximate calculations show that there is a likelihood of vortex shedding phenomenon

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 58: Burj Dubai Concept, Design and Construction Presentation

Aeroelastic model studyThe structure is light in density on the

order of 8 to 10 lbft3 (125 to 157 kNm3)

The structural stiffness is concentrated in the interior of the building making it torsionally flexible A building with a braced central core is one such example

The calculated period of oscillation of the building is long in excess of 4 or 5 sec

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 59: Burj Dubai Concept, Design and Construction Presentation

Aeroelastic model studyIt is more accurate than a force

balance study since the aeroelastic interaction between the structure and wind is fully simulated

Accurate determination of the relationship between peak response and RMS response

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 60: Burj Dubai Concept, Design and Construction Presentation

Aeroelastic model studyFor the Burj Dubai the modal

deflection shapes were similar to those of a tapered cantilevered column

Therefore it was possible to obtain excellent agreement between frequencies and mode shapes on the model with those predicted at full scale by using a single machined metal spine in the model with outer shell segments attached to it

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 61: Burj Dubai Concept, Design and Construction Presentation

Aeroelastic model studyThe aeroelastic model was able

to model the first six sway modes Bending moments were measured at the base as well as at several higher levels Accelerations were also measured in the upper levels

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 62: Burj Dubai Concept, Design and Construction Presentation

Comparing aeroelastic model test results force balance resultsIt was found that the base

moment and the accelerations in the upper levels were significantly lower in the aeroelastic model results

Part of this was identified as a Reynolds number effect because the force balance tests had been run at lower Reynolds number

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 63: Burj Dubai Concept, Design and Construction Presentation

Comparing aeroelastic model test results force balance results

Differences between the force balance method and the aeroelastic method on Burj Dubai

Due to approximations in the force balance procedure as applied to a highly tapered towered

Force balance method keep model resonance frequencies high enough to avoid them interfering with the frequency range of interest and one solution is to run at lower tunnel wind speeds which entails reducing the Reynolds number

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 64: Burj Dubai Concept, Design and Construction Presentation

BUILDING MOTIONSBased on the High-Frequency-Force-Balance

test results combined with local wind statistics the building motions in terms of peak accelerations were predicted for various return periods in the 1 to 10 year range

Initial predictions obtained in May 2003 at over 37 milli-g for the 5 year return period

By the end of 2004 November 2003 they had come down to about 19 milli-g for the same return period

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 65: Burj Dubai Concept, Design and Construction Presentation

BUILDING MOTIONSHalf of this improvement came about as

a result of improved knowledge of the wind statistics and the rest through re-orientation structural improvements and shape adjustments

Several variations of tower height were tested using aeroelastic models

The accelerations were reduced to the range of 12 milli-g

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 66: Burj Dubai Concept, Design and Construction Presentation

Human Response to Building Motions

Building motion under the action of wind is a serviceability issue

A commonly used criterion is to limit the acceleration of a buildingrsquos upper floors to no more than 20 of gravity (20 mg) for a 10-year return period

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 67: Burj Dubai Concept, Design and Construction Presentation

PEDESTRIAN WIND STUDIES

A sheet of air moving over the earthrsquos surface is reluctant to rise when it meets an obstacle such as a tall building it prefers to flow around the building rather than over it

Wind is driven in two directions Some of it will be deflected upward but most of it will spiral to the ground creating a so-called standing vortex or mini tornado at sidewalk level

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 68: Burj Dubai Concept, Design and Construction Presentation

PEDESTRIAN WIND STUDIES

Smooth-skinned skyscrapers may be subjected to what is called the Mary Poppins syndrome referring to the tendency of the wind to lift the pedestrian literally off his or her feet

Another effect known as the Marilyn Monroe effect refers to the billowing action of womenrsquos skirts in the turbulence of wind around and in the vicinity of a building

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 69: Burj Dubai Concept, Design and Construction Presentation

PEDESTRIAN WIND STUDIES

The comfort of pedestrians at ground level and on the numerous terrace levels was evaluated by combining wind speed measurements on wind tunnel models with the local wind statistics and other climatic information

Two aspects of pedestrian comfort were considered the effect of the mechanical force of the wind thermal comfort

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 70: Burj Dubai Concept, Design and Construction Presentation

PEDESTRIAN WIND STUDIES

Initial wind tunnel tests used 1500 scale models

Subsequently three 1250 scale partial models were employed to examine ground level areas

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 71: Burj Dubai Concept, Design and Construction Presentation

Foundations

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 72: Burj Dubai Concept, Design and Construction Presentation

Soil InvestigationHyder Consulting (UK) Ltd (HCL) were appointed geotechnical consultant for the works by Emaar and carried out the design of the foundation system

Soil Investigation in 4 stages includedbull 23 boreholesbull in situ SPTrsquosbull 40 pressuremeter tests in 3 boreholes bull installation of 4 standpipe piezometers bull laboratory testing specialist laboratory testing and

contamination testingbull 3 geophysical boreholes with cross-holebull tomography geophysical surveys

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 73: Burj Dubai Concept, Design and Construction Presentation

Soil Investigationbull The quality of core recovered in some of

the earlier boreholes was somewhat poorer than that recovered in later boreholes

bull therefore the defects noted in the earlier rock cores may not have been representative of the actual defects present in the rock mass

bull Phase 4 of the investigation was targeted to assess the difference in core quality and this indicated that the differences were probably related to the drilling fluid used and the overall quality of drilling

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 74: Burj Dubai Concept, Design and Construction Presentation

Soil Investigation amp Ground Waterbull The groundwater in which the Burj Dubai

substructure is constructed is particularly severe

bull The chloride and sulfate concentrations found in the groundwater are even higher than the concentrations in sea water

bull Measures implemented include specialized waterproofing systems1 Increased concrete cover2 Addition of corrosion inhibitors to the

concrete mix3 Stringent crack control design criteria

and 4 Impressed current cathodic protection

system utilizing titanium mesh 5 A controlled permeability formwork

liner

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 75: Burj Dubai Concept, Design and Construction Presentation

Ground Water amp Concrete Mix

bull A specially designed concrete mix was formulated to resist attack from the ground water

bull The concrete mix for the piles was a 60 MPa mix based on a triple blend with 25 fly ash 7 silica fume and a water to cement ratio of 032

bull The concrete was also designed as a fully self consolidating concrete A robust cathodic protection system for both the bored piles and the raft foundation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 76: Burj Dubai Concept, Design and Construction Presentation

PilesThe Tower raft is supported by 194 boredcast-

in-place piles15m diameter and 4745m long with the

tower raft founded at -755mThe C60 (cube strength) SCC concrete was

placed by the tremie method utilizing polymer slurry When the rebar cage was placed in the piles special attention was paid to orient the rebar cage such that the raft bottom rebar could be threaded through the numerous pile rebar cages without interruption which greatly simplified the raft construction

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 77: Burj Dubai Concept, Design and Construction Presentation

Pile Testing1 Static load tests on seven trial piles

prior to foundation construction 2 Static load tests on eight works piles

carried out during the foundation construction phase (ie on about 1 of the total number of piles constructed)

3 In addition dynamic pile testing was carried out on 10 of the works piles for the tower and 31 piles for the podium ie on about 5 of the total works piles

4 Sonic integrity testing was also carried out on a number of the works piles

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 78: Burj Dubai Concept, Design and Construction Presentation

Static Testing on trial pilesThe main purpose of the tests was to assess

the general load-settlement behaviour of piles of the anticipated length below the tower and to verify the design assumptions Each of the test piles was different allowing various factors to be investigated as follows

1 The effects of increasing the pile shaft length2 The effects of shaft grouting3 The effects of reducing the shaft diameter4 The effects of uplift (tension) loading5 The effects of lateral loading6 The effect of cyclic loading

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 79: Burj Dubai Concept, Design and Construction Presentation

Static Working Pile TestThe Tower raft is supported by 194

bored cast-in-place piles The piles are 15 meter in diameter and approximately 43 meters long with a design capacity of 3000 ton each

The Tower pile load test supported over 6000 ton

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 80: Burj Dubai Concept, Design and Construction Presentation

Settlement It was determined the maximum

long-term settlement over time would be about a maximum of 80mm

This settlement would be a gradual curvature of the top of grade over the entire large site When the construction was at Level 135 the average foundation settlement was 30mm

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 81: Burj Dubai Concept, Design and Construction Presentation

Construction Achieve a three (3) day-cycle for structural

worksDevelop optimum transportation systems

with large capacity high speed equipmentUtilize optimum formwork system to

accommodate various building shapes along the building height

Develop organized logistic plans throughout the construction period

Apply all high-rise construction technologies available at the time of construction

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 82: Burj Dubai Concept, Design and Construction Presentation

Planning for the concrete workbull Prior to the construction of the tower

extensive concrete testing and quality control programs were put in place to ensure that all concrete works are done in agreement with all parties involved

bull Tests are needed to confirm the construction sequence of these large elements and to develop curing plans that are appropriate for the project considering major daily and seasonal temperature fluctuations

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 83: Burj Dubai Concept, Design and Construction Presentation

Testing Regimes for Concretebull Trial mix designs for all concrete types needed for the

projectbull Mechanical properties including compressive strength

modulus of elasticity and split tensile strengthbull Durability tests which included initial surface

absorption test and 30 minute absorption testbull Creep and shrinkage test program for all concrete mix

designbull Water penetration tests and rapid chloride permeability

testbull Shrinkage test program for all concrete mix designsbull Pump simulation test for all concrete mix design grades

up to at least 600 metersbull Heat of hydration analysis and tests

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 84: Burj Dubai Concept, Design and Construction Presentation

Testing Regimes for Concretebull Creep Test

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 85: Burj Dubai Concept, Design and Construction Presentation

Testing Regimes for Concrete

bull Pump Simulation Test using over 600m of pipe length to confirm the pump capacity and evaluate the overall pressure losses in the pipes due to friction connections concrete type

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 86: Burj Dubai Concept, Design and Construction Presentation

Testing Regimes for Concretebull Pump Simulation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 87: Burj Dubai Concept, Design and Construction Presentation

Testing Regimes for Concretebull Heat of Hydration Make-op Test

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 88: Burj Dubai Concept, Design and Construction Presentation

Technologies used to achieve 3-day cycles

bull Auto Climbing formwork system (ACS)bull Rebar pre-fabricationbull High performance concrete suitable for

providing high strength high durability requirement high modulus and pumping

bull Advanced concrete pumping technologybull Simple drop head formwork system that

can be dismantled and assembled quickly with minimum labor requirements

bull ColumnWall proceeding method part of ACS formwork system

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 89: Burj Dubai Concept, Design and Construction Presentation

Technologies used to achieve 3-day cycles

>

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 90: Burj Dubai Concept, Design and Construction Presentation

Sequence of Construction and ACSThe ACS form work is divided into four sections consisting of the center core wall that is followed by the wing wall construction along each of the three tower wings

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 91: Burj Dubai Concept, Design and Construction Presentation

Sequence of Construction and ACS

>

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 92: Burj Dubai Concept, Design and Construction Presentation

Rebar Pre-fabrication bull Most of the reinforcing

bars for the core walls wing walls and the nose columns were prefabricated at the ground level

bull This rebar fabrication and pre-assembly method resulted in man quality control advantages and reduced the number of workers going up and down the tower

bull The rebar was assembled in double story modules to speed up the vertical element construction time

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 93: Burj Dubai Concept, Design and Construction Presentation

Slab Formwork SystemDrop head system (also known as slab support system is specially designed to sustain a large combination of grid sizes resulting in maximum reusability of formwork amp economy) used for the slab construction

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 94: Burj Dubai Concept, Design and Construction Presentation

Slab Formwork SystemThe slab shoring system consists of four levels of shores and one level of re-shore to control the maximum loads in the slabs at the lowest level However the shoring props at the upper-most slab were left undisturbed

Day 0

Conrsquoc Pouring

Day 1

Slab formwork

Day 2

Slab formwork

Rebar Installation

MEP

Day 3

Conrsquoc Pouring

13 of Prop

23 of Prop

Form

23 of Prop

12 of Raking Shore

Form Form

12 of Raking Shore

23 of Prop

12 of Raking Shore

N-1

N-2

N-3

N-4

N-5

N+0

Additional Raking Shore

N+1

Form

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 95: Burj Dubai Concept, Design and Construction Presentation

Concrete Pumping

CPB1CPB3

CPB4

CPB2

Level Height Pouring Method Remarks

Ground ~ L145 531 m Direct PumpingTarget Height (RC Structure)

L146 ~ L160M 624 m Re-pumpingSecondary Pump on

L124 (East wing 442m)

L160M ~ Spire1 6817 m Hopper by TC From Ground Level

Level Pressure OutputEngin

eRemarks

Pump1~3

185 320 bar

71 36 m3hr

470 kw

2 nos of Main1 no of Stand by

Pump4220 260 bar

110 m3hr200 kw

SecondaryPumping

Pumping Area (Ground Level)

Pipe Lines

Concrete Pump

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Placing Boom

- 32m boom for Center Core- 3nos of 28m boom for Wing Core

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 96: Burj Dubai Concept, Design and Construction Presentation

Concrete Pumping

TIER 24 FINIAL HIGH

TOF

TIER 23 FINIAL MID

TIER 22 FINIAL LOW

TIER 21 SPIRE L5TIER 20 SPIRE L4

TIER 19 SPIRE L3

TIER 18 SPIRE L2

TIER 17 LEVEL 161

TIER 16 LEVEL 158

TIER 15 LEVEL 155

TIER 14 LEVEL 151

TIER 13 LEVEL 147

TIER 12 LEVEL 142

TIER 11 LEVEL 126

TIER 10 LEVEL 112

TIER 9 LEVEL 99

TIER 8 LEVEL 87

TIER 7 LEVEL 76

TIER 6 LEVEL 64

TIER 5 LEVEL 53

TIER 4 LEVEL 43

TIER 3 LEVEL 34

TIER 2 LEVEL 26

TIER 1 LEVEL 19

TIER 0 LEVEL 7

Line2 (L139)for South Wing

Line3 (L124)for East Wing

Line4 (L112)for West Wing

Pump4 (Secondary Pump on L124)

Line1 (L160) for Center Core

Line5 (L160) for Back up

L154 RC Structure

L160Mezzanine Steel Structure

Top of Finial Spire

Pinnacle

Pumping AreaPump1~3

Pipe Lines

- D150mm THK 11mm- 5 Lines (1 for back up)

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 97: Burj Dubai Concept, Design and Construction Presentation

Concrete Pumping

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 98: Burj Dubai Concept, Design and Construction Presentation

Concrete Pumping

>

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 99: Burj Dubai Concept, Design and Construction Presentation

Spire Erection and Pinnacle Assemblybull At Level 156 the reinforced concrete core wall

will reach its highest point and serves as the foundation for the spirersquos structural steel works

bull The central pinnacle structure which consists of 1200mm-2100mm diameter structural steel pipe varies in thickness from 60mm at the lowest level to 30mm at the top

bull The erection of the spire and the pinnacle starts from level 156 and the erection of the spire was done in traditional steel construction method However the pinnacle pipe sections are stacked from level 156 and lifted to the final position from within the spire

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 100: Burj Dubai Concept, Design and Construction Presentation

Spire Erection and Pinnacle AssemblyThe sequence of the pinnacle installation is shown in Figure below and as follows

bull Erection of the spire structurebull Installation of the support beambull Installation of the lifting block and assembliesbull Installation of the lifting equipment and

assembliesbull Lifting the pinnacle in a three step processbull Installing cladding after each liftbull Completing lift of the pinnacle and all connection

connections (gravity and lateral)bull Completion of the cladding installation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 101: Burj Dubai Concept, Design and Construction Presentation

Spire Erection and Pinnacle Assembly

>

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 102: Burj Dubai Concept, Design and Construction Presentation

Survey amp Monitoring

bull Low Level Tower Control (Classical Control Method )

XYZ

XYZ

XYZ

XYZ

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 103: Burj Dubai Concept, Design and Construction Presentation

Survey amp Monitoring bull Hight Level Tower Control (GPS

Real Time Kinematic)

>

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 104: Burj Dubai Concept, Design and Construction Presentation

EvacuationBurj Dubai has built in fire protection as its concrete back bone is naturally fire resistantBut how will people go out in an emergencyThe answer they donrsquot bull The burj dubai contains 9 special rooms build

throw layers of reinforced concrete and fire proof sheeting

bull The walls of these rooms will stand the heat of a fire for 2 hours

bull Each room has special supply of air pumped throw fire resistant pipes sealed fire proofed doors stop smoke from leaking in

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 105: Burj Dubai Concept, Design and Construction Presentation

Evacuationbull There is 1 of these rooms in about every 30 floors How they prevent the smoke from blocking the

access route to the roomsbull Early warning system

bull Fire activate a smoke detectorbull Heat sensorbull Water sprinklersbull Net work of high power fans kick inbull Fans force new clean cool air throw fire

resistant ducts into the buildingbull The fresh air pushes the smoke out of the

stair way keeping the evacuation route clear

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 106: Burj Dubai Concept, Design and Construction Presentation

Evacuation

>

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 107: Burj Dubai Concept, Design and Construction Presentation

Cladding bull 30000 glass panels of high quality European

glass enough to cover 17 football fields

bull The glass is thicker at the top to resist the high wind

bull Its designed to let the maximum light in and to keep heat out

Sun screen (inside face) is useless against infrared

from the hot desert sun so the inner plan is coated

with a thin layer of silver that keeps the heat rays

out

Outside coat reflects the daily solar heat comes direct from the

sun

The metal coating deflects UV Radiation that will otherwise heat

up the building

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 108: Burj Dubai Concept, Design and Construction Presentation

Cladding Test 1 Air infiltration test To measure how much air gets in through the joints

Test 2 static water test bull Water is spread

evenly for 15 minutes from nozles attached to the glass

bull Transducers measures how much water gets in

bull The data is transferred to computer for analysis

>

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 109: Burj Dubai Concept, Design and Construction Presentation

Cladding Test 3 Dynamic water Test

bull Itrsquos a simulation for a desert ndash Storm

bull The wind is Generated by a giant Fan and its Spread water against the glass for 15 minutes

>

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 110: Burj Dubai Concept, Design and Construction Presentation

Cladding Test 4 Earthquake Test

bull Earthquake Simulation which move the mock-up floor of curtain walls 10 mm in two directions

bull With this test the know that curtain wall wonrsquot break

>

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 111: Burj Dubai Concept, Design and Construction Presentation

Faccedilade Maintenance bull The towers primary window washing and facade

maintenance system consists of three permanently-installed track-mounted telescopic building maintenance machines located in internal garage positions on uppermost levels

bull it will take 36 workers three to four months to clean the entire exterior facade

>

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 112: Burj Dubai Concept, Design and Construction Presentation

Elevatorsbull With an lsquointelligent

elevator installationrsquo mechanism builders of Burj Dubai ensure a speedy journey from the ground to the 160th floor

bull 57 elevators and eight escalators to streamline the needs of the residents and visitors to commute within the tower These elevators mark the highest installation in any building and have been developed by Otis

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 113: Burj Dubai Concept, Design and Construction Presentation

Elevatorsbull The main service

elevator that is positioned in the central core of Burj Dubai has the worldrsquos highest elevator rise at 504 metres

bull It moves at a speed of 9 metres per second and also has the worldrsquos longest travelling distance for an elevator The lift to the spire has the worldrsquos highest landing at 6369 meters

>

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 114: Burj Dubai Concept, Design and Construction Presentation

Elevatorsbull Elevators are placed into

different zones Each elevator zone serves different audiences maximizing the efficiency and saving time

bull The sky lobby is an intermediate floor where residents guests office staff will change from an express elevator to a local elevator which stops at each floor within a certain segment of the building The sky lobbies are located on level 43 76 and 123 and will include a lounge area

>

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120
Page 115: Burj Dubai Concept, Design and Construction Presentation

Thank YouMosatafa atteya Ahmed Essam Ramez Nazir

Mohamed Salah

  • Burj Dubai Concept Design amp Construction
  • Introduction
  • Worldrsquos Tallest Building
  • Worldrsquos Tallest Building (2)
  • Architectural Concept
  • Architecture
  • Architecture (2)
  • Architecture (3)
  • Slide 9
  • Main Structure amp Design
  • Main Structure amp Design (2)
  • Structural Analysis amp Design
  • Main Structure amp Design (3)
  • Main Structure
  • Structural Analysis amp Design (2)
  • Structural Analysis amp Design (3)
  • Structural Analysis amp Design Concrete Dimensions
  • Structural Analysis amp Design Link Beams
  • Structural Analysis amp Design Link Beams (2)
  • Strut and Tie model for the Link Beam
  • Design Details of Link Beams
  • Design Details of Link Beams (2)
  • Structural Analysis amp Design Clear Heights
  • Structural Analysis amp Design (4)
  • Structural Analysis amp Design Design Code
  • Structural Analysis amp Design Seismic Loads
  • Structural Analysis amp Design Seismic Analysis
  • Structural Analysis amp Design Dynamic Analysis
  • Types of wind
  • Types of wind (2)
  • CHARACTERISTICS OF WIND
  • Variation of Wind Velocity with Height
  • Wind Turbulence
  • Probabilistic Approach
  • Vortex Shedding
  • Vortex Shedding (2)
  • Wind behavior
  • Dynamic Nature of Wind
  • WIND CLIMATE STUDIES
  • WIND CLIMATE STUDIES (2)
  • WIND CLIMATE STUDIES (3)
  • WIND CLIMATE STUDIES (4)
  • The Wind Engineering of the Burj Dubai Tower
  • WIND-TUNNEL ENGINEERING
  • Rigid Pressure Model (PM)
  • Slide 46
  • Cladding Pressure Testing
  • Cladding Pressure Testing (2)
  • High-Frequency Base Force Balance Model
  • High-Frequency Base Force Balance Model (2)
  • High-Frequency Base Force Balance Model (3)
  • WIND LOADING ON THE MAIN STRUCTURE
  • WIND LOADING ON THE MAIN STRUCTURE (2)
  • The building has essentially six important wind directions
  • Orientation of the tower
  • High-Frequency Base Force Balance Model (4)
  • Original Configuration
  • Slide 58
  • Aeroelastic model study
  • Slide 60
  • Aeroelastic model study (2)
  • Aeroelastic model study (3)
  • Aeroelastic model study (4)
  • Aeroelastic model study (5)
  • Aeroelastic model study (6)
  • Comparing aeroelastic model test results force balance results
  • Comparing aeroelastic model test results force balance results (2)
  • Slide 68
  • BUILDING MOTIONS
  • BUILDING MOTIONS (2)
  • Human Response to Building Motions
  • PEDESTRIAN WIND STUDIES
  • PEDESTRIAN WIND STUDIES (2)
  • PEDESTRIAN WIND STUDIES (3)
  • PEDESTRIAN WIND STUDIES (4)
  • Foundations
  • Soil Investigation
  • Soil Investigation (2)
  • Soil Investigation amp Ground Water
  • Ground Water amp Concrete Mix
  • Piles
  • Pile Testing
  • Static Testing on trial piles
  • Static Working Pile Test
  • Settlement
  • Slide 86
  • Planning for the concrete work
  • Testing Regimes for Concrete
  • Testing Regimes for Concrete (2)
  • Testing Regimes for Concrete (3)
  • Testing Regimes for Concrete (4)
  • Testing Regimes for Concrete (5)
  • Technologies used to achieve 3-day cycles
  • Technologies used to achieve 3-day cycles (2)
  • Sequence of Construction and ACS
  • Sequence of Construction and ACS (2)
  • Rebar Pre-fabrication
  • Slab Formwork System
  • Slab Formwork System (2)
  • Concrete Pumping
  • Concrete Pumping (2)
  • Concrete Pumping (3)
  • Concrete Pumping (4)
  • Spire Erection and Pinnacle Assembly
  • Spire Erection and Pinnacle Assembly (2)
  • Spire Erection and Pinnacle Assembly (3)
  • Survey amp Monitoring
  • Survey amp Monitoring (2)
  • Evacuation
  • Evacuation (2)
  • Evacuation (3)
  • Cladding
  • Cladding (2)
  • Cladding (3)
  • Cladding (4)
  • Faccedilade Maintenance
  • Elevators
  • Elevators (2)
  • Elevators (3)
  • Slide 120