Building Structure Project 2 report

99
Building Structures (ARC 2522/2523) Project 2: Structural Analysis of a Bungalow Group Member: Tan Wen Hao (0319923) Ong Min Junn (0317767) Ong Jia Hui (0317752) Tutor: Ms Norita

Transcript of Building Structure Project 2 report

Page 1: Building Structure Project 2 report

Building Structures (ARC 2522/2523) Project 2: Structural Analysis of a Bungalow

Group Member: Tan Wen Hao (0319923)

Ong Min Junn (0317767)

Ong Jia Hui (0317752)

Tutor: Ms Norita

Page 2: Building Structure Project 2 report

Building Structure 2 Project 2

Table of Content

1. Brief description of bungalow 3

2. Floor plans

Foundation plan 4

Ground floor plan 5

First floor plan 6

Roof plan 7

3. Structural plans (beam and column diagram)

Ground floor structural plan 8

First floor structural plan 10

Roof structural plan 12

4. Design brief 14

5. Beam analysis report

By Tan Wen Hao (0319923) 15

By Ong Min Junn (0317767) 20

By Ong Jia Hui (0317752) 23

6. Column analysis report

By Tan Wen Hao (0319923) 15

By Ong Min Junn (0317767) 20

By Ong Jia Hui (0317752) 23

Page 3: Building Structure Project 2 report

Building Structure 3 Project 2

1. Brief description of bungalow

The bungalow is designed to have a mixture a two different build up

areas for different floors and thus has led to a more complicated design.

In this bungalow, it has a total floor area of approximately 520 square

meters that spans up to two floors. The bungalow is suitable to house a

large family with a few guests as the each space and room are quite large

and spacious. There are a total of 4 bedrooms; 1 master bedroom, 2 single

bedrooms and 1 guest room. As to accommodate a large crowd, the living

and dining areas are suitable to house 10 people comfortably each time

while having two kitchens; a dry kitchen and a wet kitchen for ease of

usage and cooking. There is an additional television room which can be

used as a mini theatre or a game room for the family, providing a

comfortable area for relaxing activities. Miscellaneous spaces include 1

storeroom, 4 washrooms and a porch to welcome people.

Page 4: Building Structure Project 2 report

Building Structure 4 Project 2

2. Floor plans

Page 5: Building Structure Project 2 report

Building Structure 5 Project 2

Page 6: Building Structure Project 2 report

Building Structure 6 Project 2

Page 7: Building Structure Project 2 report

Building Structure 7 Project 2

Page 8: Building Structure Project 2 report

Building Structure 8 Project 2

3. Structural plans

Beam analysis by

Ong Jia Hui

Beam analysis by

Ong Min Junn

Beam analysis by

Tan Wen Hao

Ground floor beams analysis diagram

Page 9: Building Structure Project 2 report

Building Structure 9 Project 2

Column analysis by

Ong Jia Hui

Column analysis by

Ong Min Junn

Column analysis by

Tan Wen Hao

Ground floor columns analysis diagram

Page 10: Building Structure Project 2 report

Building Structure 10 Project 2

Beam analysis by

Ong Jia Hui

Beam analysis by

Ong Min Junn

First floor beams analysis diagram

Page 11: Building Structure Project 2 report

Building Structure 11 Project 2

First floor columns analysis diagram

Column analysis by

Ong Jia Hui

Column analysis by

Ong Min Junn

Column analysis by

Tan Wen Hao

Page 12: Building Structure Project 2 report

Building Structure 12 Project 2

Roof beams analysis diagram

Page 13: Building Structure Project 2 report

Building Structure 13 Project 2

Roof columns analysis diagram

Column analysis by

Ong Jia Hui

Column analysis by

Ong Min Junn

Column analysis by

Tan Wen Hao

Page 14: Building Structure Project 2 report

Building Structure 14 Project 2

4. Design brief

The bungalow consists of different sizes of beams to create a variety in

design while it helps to save construction and material costs. As such,

smaller beams are only needed for areas with lightweight and short span

while thicker beams are used for main beams that span longer and

support the sub beams. Within this bungalow, there are four types of RC

beams used:

200mm X 600mm (Main beam type 1)

200mm X 500mm (Main beam type 2) 200mm X 400mm (Sub beam type 1)

200mm X 300mm (Sub beam type 2)

However for the RC columns, a standard size is only required as the

building rises 2 storeys and acts as a residential building. Hence, larger

columns are not required to save material cost. The dimension of the

standard column size is as stated:

300mm X 400mm (cross-section)

Height of ground floor and second floor is 3m from ground to ceiling

with each RC slab having a thickness of 150mm. As for the walls, bricks

are used to construct the walls. Thus, the walls are 150mm thick due the

thickness of the bricks.

Page 15: Building Structure Project 2 report

Building Structure 15 Project 2

Beam analysis report

By Tan Wen Hao (0319923)

Page 16: Building Structure Project 2 report

Building Structure 16 Project 2

UDL Dead load analysis (Beam F-H/6)

Beam Self Weight

= beam size (Sub beam type 1)

X concrete density

= (0.4m X 0.2m) X 24kN/m3

= 1.92kN/m

Brick wall Weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3

= 8.55kN/m

Dead load of F-H/4-6

= Dead load (UBBL) X (Lx/2)

(two-way trapezoidal)

= 0.15m X 24kN/m3 X (3.8m/2)

= 6.84kN/m

Dead load of F-H/6-7

= Dead load (UBBL) X (Lx/2) (one-way)

=0.15m X 24kN/m3 X (2.2m/2)

= 3.96kN/m

Total dead load

For F-G = 21.27kN/m

Live load analysis (Beam F-H/6) For F-H :

(Left slab)

= Live Load Factor (UBBL) X (Lx/2) (two-way trapezoidal)

= 1.5 kN/m2 X (3.8m/2)

=2.85 kN/m

(right slab)

= Live Load Factor (UBBL) X (Lx/2) (one-way)

= 1.5 kN/m2 X (2.2m/2)

= 1.65 kN/m

Total live load = 4.5 kN/m2

Page 17: Building Structure Project 2 report

Building Structure 17 Project 2

The Ultimate Load Ultimate dead load at F-H = 21.27kN/m X 1.4 = 29.778kN/m

Ultimate live load at F-H = 4.5kN/m X 1.6 = 8.8kN/m

Ultimate load on F-H = 38.578kN/m

Reaction forces Transforming ultimate load into point load

F-H = 38.578kN/m X 5.7m = 219.895kN

Free body diagram

Calculating reaction forces

∑MB = (Ra X 5.7) – (219.895 X 2.85)

0 = 5.7 Ra – 626.7

5.7Ra = 626.7

Ra = 109.95 kN

∑Fy =0

Ra + Rb – 219.89 = 0

Rb + 109.95 – 219.89= 0

Rb = 109.95kN

Shear force diagram and Bending Moment Diagram

Page 18: Building Structure Project 2 report

Building Structure 18 Project 2

UDL Dead load analysis (Beam 5-7/E)

Beam Self Weight

= beam size (Main beam type 2)

X concrete density

= (0.5m X 0.2m) X 24kN/m3

= 2.4kN/m

Brick wall Weight

=0

Dead load of B-E/5-7

= [Dead load (UBBL) X (Lx/2)] 2/3

(two-way triangular)

= [0.15m X 24kN/m3 X (4.7m/2)] 2/3

= 5.64kN/m

Dead load of E-F/4-7

= Dead load (UBBL) X (Lx/2) (one-way)

=0.15m X 24kN/m3 X (3m/2)

= 5.4kN/m

Total dead load

For 5-7 = 21.99kN/m

Live load analysis (Beam 5-7/E) For 5-7 :

(Left slab)

= Live Load Factor (UBBL) X (Lx/2) (two-way triangular)

= 1.5 kN/m2 X (4.7m/2)

=3.525 kN/m

(Right slab)

= Live Load Factor (UBBL) X (Lx/2) (one-way)

= 1.5 kN/m2 X (3m/2)

= 2.25 kN/m

Total live load = 5.775 kN/m2

Page 19: Building Structure Project 2 report

Building Structure 19 Project 2

The Ultimate Load Ultimate dead load at F-H = 21.99kN/m X 1.4 = 30.786kN/m

Ultimate live load at F-H = 5.775kN/m X 1.6 = 9.24kN/m

Ultimate load on F-H = 40.026kN/m

Reaction forces Transforming ultimate load into point load

F-H = 40.026kN/m X 4.7m = 188.122kN

Free body diagram

Calculating reaction forces

∑MB = (Ra X 4.7) – (188.122 X 2.35)

0 = 4.7 Ra – 442.087

4.7Ra = 442.087

Ra = 94.06 kN

∑Fy =0

Ra + Rb –188.122 = 0

Rb + 94.06 – 188.122= 0

Rb = 94.06kN

Shear force diagram and Bending Moment Diagram

Page 20: Building Structure Project 2 report

Building Structure 20 Project 2

UDL Dead load analysis (Beam 4-7/F)

Beam Self Weight

= beam size (Main beam type 2)

X concrete density

= (0.5m X 0.2m) X 24kN/m3

= 2.4kN/m

Brick wall Weight

= height X thickness X brick density

= 3.0m X 0.15m X 19kN/m3

= 8.55kN/m

Dead load of E-F/4-7

= Dead load (UBBL) X (Lx/2) (one-way)

=0.15m X 24kN/m3 X (3m/2)

= 5.4kN/m

Dead load of F-H/4-6

= [Dead load (UBBL) X (Lx/2)] 2/3

(two-way triangular)

= [0.15m X 24kN/m3 X (3.8m/2)] 2/3

= 4.56kN/m

Dead load of F-H/6-7

= 0 (One way slab distributed to Ly)

Total dead load for each sector

For 4-5 = 20.91kN/m

For 5-6: (i) 12.36kN/m

(ii) 20.91kN/m

For 6-7 = 7.8kN

Live load analysis (Beam 4-7/F) For 4-5

= Left slab + right slab

= 1.5 kN/m2 X (3m/2) (one-way) + [1.5kN/m

2 X (3.8/2)] 2/3 (two-way

triangular)

= 2.25 + 1.9 = 4.15kN/m

For 5-6

= Left slab + right slab

Page 21: Building Structure Project 2 report

Building Structure 21 Project 2

= 1.5 kN/m2 X (3m/2) (one-way) + [1.5kN/m

2 X (3.8/2)] 2/3 (two-way

triangular)

= 2.25 + 1.9 = 4.15kN/m

For 6-7

= Left slab + right slab

=1.5 kN/m2 X (3m/2) (one-way) + 0

= 2.25kN/ml

The Ultimate Load Ultimate dead load at 4-5 = 20.91kN/m X 1.4 = 29.274kN/m

Ultimate dead load at 5-6 = (i) 12.36kN/m X 1.4 = 17.304kN/m

(ii) 20.91kN/m X 1.4 = 29.274kN/m

Ultimate dead load at 6-7 = 7.8kN/m X 1.4 = 10.92kN/m

Ultimate live load at 4-5 = 4.15kN/m X 1.6 = 6.64kN/m

Ultimate live load at 5-6 = 4.15kN/m X 1.6 = 6.64kN/m

Ultimate live load at 6-7 = 2.25kN/m X 1.6 = 3.6kN/m

Total load on 4-5 = 35.914kN/m

Total load on 5-6 = (I) 23.944kN/m; (ii) 35.914kN/m

Total load on 6-7 = 14.52kN/m

Reaction forces Point loads acting at beam

Sub beam F-H/6

Reaction force Ra = point load @6 = 109.95kN

(as calculated in Beam F-H/6 analysis)

Transforming ultimate load into point load

4-5 = 20.91kN/m X 1.3m = 27.183kN

5-6 = (i) 12.36kN/m X 1.25m = 15.45kN

(ii) 20.91kN/m X 1.3m = 27.183kN

6-7 = 7.8kN/m X 2.2m = 17.16kN

Free body diagram

Page 22: Building Structure Project 2 report

Building Structure 22 Project 2

Calculating reaction forces

∑MB = (Ra X 6) – (27.183 X 5.35) – (15.45 X 4.075) –(27.183 X 2.825)

– (109.95 X 2.2) – (17.16 X 1.1)

0 = 6Ra – 545.946

6Ra = 545.946

Ra = 90.99kN

∑Fy =0

Ra + Rb – 27.183 – 15.45 – 27.183 – 109.95 – 17.16 = 0

Rb + 90.991 – 196.926 = 0

Rb = 105.94kN

Shear force diagram and Bending Moment Diagram

Page 23: Building Structure Project 2 report

Building Structure 23 Project 2

UDL Dead load analysis (Beam E-G/4)

Beam Self Weight

= beam size (Main beam type 2)

X concrete density

= (0.5m X 0.2m) X 24kN/m3

= 2.4kN/m

Brick wall Weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3

= 8.55kN/m

Dead load of E-G/3-4

= Dead load (UBBL) X (Lx/2)

(two-way trapezoidal)

= 0.15m X 24kN/m3 X (4m/2)

= 7.2kN/m

Dead load of E-F/4-7

=0 (One way slab distributed to Ly)

Dead load of F-H/4-6

= Dead load (UBBL) X (Lx/2)

(two-way trapezoidal)

= 0.15m X 24kN/m3 X (3.8m/2)

= 6.84kN/m

Total dead load for each sector

For E-F = 18.15kN/m

For F-G = 16.44kN/m

Live load analysis (Beam E-G/4) For E-F

= Left slab + right slab

= Live Load Factor (UBBL) X (Lx/2) (two-way trapezoidal) + 0 (one way

slab distributed on longer side)

= 1.5 kN/m2 X (4m/2)

=2.75 kN/m

Page 24: Building Structure Project 2 report

Building Structure 24 Project 2

For F-G

= Left slab + right slab

= Live Load Factor (UBBL) X (Lx/2) (two-way trapezoidal) (both left and

right)

= [1.5 kN/m2 X (4m/2)] + [1.5 kN/m

2 X (3.8m/2)]

= 5.85kN/m

The Ultimate Load Ultimate dead load at E-F = 18.15kN/m X 1.4 = 25.41kN/m

Ultimate dead load at F-H = 16.44kN/m X 1.4 = 23.016kN/m

Ultimate live load at E-F = 2.75kN/m X 1.6 = 4.4kN/m

Ultimate live load at F-G = 5.85kN/m X 1.6 = 9.36kN/m

Total load on E-F = 29.81kN/m

Total load on F-G = 32.376kN/m

Reaction forces

Point loads acting at beam

Sub beam 4-7/F

Reaction force Ra = point load @F = 90.99kN

(as calculated in Beam 4-7/F analysis)

Transforming ultimate load into point load

E-F = 29.81kN/m X 3m = 89.43kN

F-G = 32.376kN/m X 3m = 87.415kN

Free body diagram

Calculating reaction forces

∑MB = (Ra X 5.7) – (89.43 X 4.2) – (90.99 X 2.7) – (87.415 X 1.35)

0 = 5.7Ra – 739.289

5.7Ra = 739.289

Ra = 129.7kN

∑Fy =0

Ra + Rb – 89.43 – 90.99 – 87.415 = 0

Rb + 129.7 – 267.835 = 0

Rb = 138.14kN

Page 25: Building Structure Project 2 report

Building Structure 25 Project 2

Shear force diagram and Bending Moment Diagram

Page 26: Building Structure Project 2 report

Building Structure 26 Project 2

UDL Dead load analysis (Beam 3-5/E)

Beam Self Weight

= beam size (Main beam type 1)

X concrete density

= (0.6m X 0.2m) X 24kN/m3

= 2.88kN/m

Brick wall Weight

= height X thickness X brick density

= 3.0m X 0.15m X 19kN/m3

= 8.55kN/m

Dead load of E-G/3-4

= [Dead load (UBBL) X (Lx/2)] 2/3

(two-way triangular)

= [0.15m X 24kN/m3 X (4m/2)] 2/3

= 4.8kN/m

Dead load of E-F/4-7

= Dead load (UBBL) X (Lx/2) (one-way)

=0.15m X 24kN/m3 X (3m/2)

= 5.4kN/m

Total dead load for each sector

For 3-4 = 16.23kN/m

For 4-5 = 16.83kN/m

Live load analysis (Beam 3-5/E) For 3-4

= [1.5kN/m2

X (4m/2)] 2/3 (two-way triangular)

= 2kN/m

For 4-5

= 1.5 kN/m2 X (3m/2) (one-way)

= 2.25kN/m

Page 27: Building Structure Project 2 report

Building Structure 27 Project 2

The Ultimate Load Ultimate dead load at 3-4 = 16.23kN/m X 1.4 = 22.722kN/m

Ultimate dead load at 4-5 = 16.83kN/m X 1.4 = 23.562kN/m

Ultimate live load at 3-4 = 2kN/m X 1.6 = 3.2kN/m

Ultimate live load at 4-5 = 2.25kN/m X 1.6 = 3.6kN/m

Total load on 3-4 = 25.922kN/m

Total load on 4-5 = 27.162kN/m

Reaction forces

Point loads acting at beam

Sub beam E-G/4

Reaction force Ra = point load @E = 129.7kN

(as calculated in Beam E-G/4 analysis)

Transforming ultimate load into point load

3-4 = 25.922kN/m X 4m = 103.688kN

4-5 = 27.162kN/m X 1.3m = 35.311kN

Free body diagram

Calculating reaction forces

∑MB = (Ra X 4.3) – (103.688 X 3.3) – (129.7 X 1.3) – (35.311 X 0.65)

0 = 4.3Ra – 533.733

4.3Ra = 533.733

Ra = 124.12kN

∑Fy =0

Ra + Rb – 103.688 – 129.7 – 35.311 = 0

Rb + 124.12 – 268.699 = 0

Rb = 144.58kN

Page 28: Building Structure Project 2 report

Building Structure 28 Project 2

Shear force diagram and Bending Moment Diagram

Page 29: Building Structure Project 2 report

Building Structure 29 Project 2

UDL Dead load analysis (Beam D-G/7)

Beam Self Weight

= beam size (Main beam type 1)

X concrete density

= (0.6m X 0.2m) X 24kN/m3

= 2.88kN/m

Brick wall Weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3

= 8.55kN/m

Dead load of B-E/5-7

= Dead load (UBBL) X (Lx/2)

(two-way trapezoidal)

= 0.15m X 24kN/m3 X (4.7m/2)

= 6.84kN/m

Dead load of E-F/4-7

= 0 (One way slab distributed to Ly)

Dead load of F-H/6-7

= Dead load (UBBL) X (Lx/2) (one-way)

=0.15m X 24kN/m3 X (2.2m/2)

= 3.96kN/m

Total dead load

For D-E = 18.27kN/m

For E-F = 11.43kN/m

For F-G = 15.39kN/m

Live load analysis (Beam D-G/7) For D-E:

= Live Load Factor (UBBL) X (Lx/2) (two-way trapezoidal)

= 1.5 kN/m2 X (4.7m/2)

=3.525 kN/m

For E-F:

= 0 (One way slab distributed to Ly)

For F-G:

= Live Load Factor (UBBL) X (Lx/2) (one-way)

= 1.5 kN/m2 X (2.2m/2)

=1.65 kN/m

Page 30: Building Structure Project 2 report

Building Structure 30 Project 2

The Ultimate Load Ultimate dead load at D-E = 18.27kN/m X 1.4 = 25.578kN/m

Ultimate dead load at E-F = 11.43kN/m X 1.4 = 16kN/m

Ultimate dead load at F-G = 15.39kN/m X 1.4 = 21.546kN/m

Ultimate live load at D-E = 3.525kN/m X 1.6 = 5.64kN/m

Ultimate live load at E-F = 0

Ultimate live load at F-G = 1.65kN/m X 1.6 = 2.64kN/m

Total load on D-E = 29.103kN/m

Total load on E-F = 16kN/m

Total load on F-G = 24.186kN/m

Reaction forces Point loads acting at beam

Sub beam 5-7/E

Reaction force Rb= point load @E = 94.06kN

(as calculated in Beam 5-7/E analysis)

Sub beam 4-7/F

Reaction force Rb= point load @F = 105.94kN

(as calculated in Beam 4-7/F analysis)

Transforming ultimate load into point load

D-E = 18.27kN/m X 2m = 36.54kN

E-F 11.43kN/m X 3m = 34.29kN

F-G = 15.39kN/m X 2.7m = 41.553kN

Free body diagram

Page 31: Building Structure Project 2 report

Building Structure 31 Project 2

Calculating reaction forces

∑MB = (Ra X 7.7) – (36.54 X 6.7) – (94.06 X 5.7) – (34.29 X 4.2) – (105.94 X 2.7) –

(41.553 X 1.35)

0 = 7.7Ra – 1267.113

7.7Ra = 1267.113

Ra = 164.56kN

∑Fy =0

Ra + Rb – 36.54 – 94.06 – 34.29 – 105.94 – 41.553 = 0

Rb + 164.56 – 312.383= 0

Rb = 147.82kN

Shear force diagram and Bending Moment Diagram

Page 32: Building Structure Project 2 report

Building Structure 32 Project 2

Beam analysis report

By Ong Min Junn (0317767)

Page 33: Building Structure Project 2 report

Building Structure 33 Project 2

UDL Dead load analysis (Beam E/1-2)

Beam Self Weight

= beam size (Sub beam type 2)

X concrete density

= (0.2m X 0.3m) X 24kN/m3 = 1.44kN/m

Brick wall Weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Dead load from slab C-E/1-2

= Dead load (UBBL) X (Lx/2)(2/3)

(two-way triangular)

= 0.15m X 24kN/m3 X (3.2m/2)(2/3)

= 3.84kN/m

Dead load from slab E-F/1-2

= Dead load (UBBL) X (Lx/2)

(two-way trapezoidal)

=0.15m X 24kN/m3 X (3m/2)

= 5.4kN/m

Total dead load

For 1-2 = 1.44 + 8.55 + 3.84 + 5.4

= 19.23kN/m

Live load analysis (Beam E/1-2) Live load from slab C-E/1-2

= Live Load Factor (UBBL) X (Lx/2)(2/3)

= 1.5kN/m2 X (3.2m/2)(2/3)

= 1.6kN/m

Live load from slab E-F/1-2

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (3m/2)

= 2.25kN/m

Total live load

= 1.6 + 2.25 = 3.85kN/m

Page 34: Building Structure Project 2 report

Building Structure 34 Project 2

The Ultimate Load Ultimate dead load at 1-2 = 19.23kN/m X 1.4 = 26.922kN/m

Ultimate live load at 1-2 = 3.85kN/m X 1.6 = 6.16kN/m

Ultimate load on 1-2 = 33kN/m

Reaction forces Transforming ultimate load into point load

1-2 = 33kN/m X 3.2m = 105.6kN

Free body diagram

Calculating reaction forces

∑MA = 0

0 = (105.6kN x 1.6m) – 3.2 RB

3.2RB = 168.96kN

RB = 52.8kN

Total Load = RA + RB

RA = 105.6-52.8

= 52.8kN

Page 35: Building Structure Project 2 report

Building Structure 35 Project 2

Shear force diagram and Bending Moment Diagram

Page 36: Building Structure Project 2 report

Building Structure 36 Project 2

UDL Dead load analysis (Beam C-F/2)

Beam Self Weight

= beam size (Sub beam type 1)

X concrete density

= (0.2m X 0.4m) X 24kN/m3

= 1.92kN/m

Brick wall Weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3

= 8.55kN/m

Dead load from slab C-E/1-2

= Dead load (UBBL) X (Lx/2)

(two-way trapezoidal)

= 0.15m X 24kN/m3 X (3.2m/2)

= 5.76kN/m

Dead load from slab E-F/1-2

= Dead load (UBBL) X (Lx/2)(2/3)

(two-way triangular)

=0.15m X 24kN/m3 X (3m/2)(2/3)

= 3.6kN/m

Dead load from slab C-F/2-3

= Dead load (UBBL) X (Lx/2)

(two-way trapezoidal)

=0.15m X 24kN/m3 X (4.5m/2)

= 8.1kN/m

Total dead load

For C-E = 1.92 + 8.55 + 5.76 + 8.1

= 24.33kN/m

For E-F= 1.92 + 8.55 + 3.6 + 8.1

= 22.17kN/m

Page 37: Building Structure Project 2 report

Building Structure 37 Project 2

Live load analysis (Beam C-F/2) Live load from slab C-E/1-2

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (3.2m/2)

= 2.4kN/m

Live load from slab E-F/1-2

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (3m/2)(2/3)

= 1.5kN/m

Live load from slab C-F/2-3

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (4.5m/2)

= 3.375kN/m

Total dead load

For C-E = 2.4 + 3.375

= 5.775kN/m

For E-F= 1.5 + 3.375

= 4.875kN/m

The Ultimate Load Ultimate dead load at C-E= 24.33kN/m X 1.4 = 34.062kN/m

Ultimate dead load at E-F = 22.17kN/m X 1.4 = 31.038kN/m

Ultimate live load at C-E = 5.775kN/m X 1.6 = 9.24kN/m

Ultimate live load at E-F = 4.875kN/m X 1.6 = 7.8kN/m

Ultimate load on C-E = 43.3kN/m

Ultimate load on E-F = 38.8kN/m

Reaction forces Point loads acting at beam

Sub beam E/1-2

Reaction force RB = point load = 52.8kN

(as calculated in Beam E/1-2 analysis)

Transforming ultimate load into point load

C-E = 43.3kN/m X 4m = 173.2kN

E-F = 38.8kN/m X 3m = 116.4kN

Free body diagram

2.4kN/m

1.5kN/m

116.4kN

Page 38: Building Structure Project 2 report

Building Structure 38 Project 2

Calculating reaction forces

∑MA = 0

0 = (173.2kN x 2m) + (52.8kN x 4m) + [116.4kN x (1.5m + 4m)] - 7 RB

7 RB = 1197.8 kN

RB = 171.1 kN

Total Load = RA + RB

RA = 342.4 – 171.1

= 171.3 kN

Shear force diagram and Bending Moment Diagram

Page 39: Building Structure Project 2 report

Building Structure 39 Project 2

UDL Dead load analysis (Beam C/1-3)

Beam Self Weight

= beam size (Main beam type 1)

X concrete density

= (0.2m X 0.6m) X 24kN/m3 = 2.88kN/m

Brick wall Weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Dead load from slab C-E/1-2

= Dead load (UBBL) X (Lx/2)(2/3)

(two-way triangular)

= 0.15m X 24kN/m3 X (3.2m/2)(2/3)

= 3.84kN/m

Dead load from slab C-F/2-3

= Dead load (UBBL) X (Lx/2)(2/3)

(two-way triangular)

=0.15m X 24kN/m3 X (4.5m/2)(2/3) = 5.4kN/m

Total dead load

For 1-2 = 2.88 + 8.55 + 3.84

= 15.27kN/m

For 2-3 = 2.88 + 8.55 +5.4

= 16.35kN/m

Live load analysis (Beam F-H/6) Live load from slab C-E/1-2

= Live Load Factor (UBBL) X (Lx/2)(2/3)

= 1.5 kN/m2 X (3.2m/2)(2/3)

= 1.6 kN/m

Live load from slab C-E/2-3

= Live Load Factor (UBBL) X (Lx/2)

= 1.5 kN/m2 X (4.5m/2)(2/3)

= 2.25 kN/m

Page 40: Building Structure Project 2 report

Building Structure 40 Project 2

The Ultimate Load Ultimate dead load at 1-2 = 15.27kN/m X 1.4 = 21.378kN/m

Ultimate dead load at 2-3 = 16.5kN/m X 1.4 = 23.1kN/m

Ultimate live load at 1-2 = 1.6kN/m X 1.6 = 2.56kN/m

Ultimate live load at 2-3 = 2.25kN/m X 1.6 = 3.6kN/m

Ultimate load on 1-2 = 23.94kN/m

Ultimate load on 2-3 = 26.7kN/m

Reaction forces

Point loads acting at beam

Sub beam C-F/2

Reaction force Ra = point load = 171.3kN

(as calculated in Beam C-F/2 analysis)

Transforming ultimate load into point load

1-2 = 23.94kN/m X 3.2m = 76.6kN

2-3 = 26.7kN/m X 4.5m = 120.15kN

Free body diagram

Calculating reaction forces

∑MA = 0

0 = (76.6kN x 1.6m) + (171.3kN x 3.2m) + [120.15 x (3.2m + 2.25m)] - 7.7 RB

7.7RB = 1325.53 kN

RB = 172.15 kN

Total Load = RA + RB

RA = 368.05-172.15

= 195.9 kN

Page 41: Building Structure Project 2 report

Building Structure 41 Project 2

Shear force diagram and Bending Moment Diagram

Page 42: Building Structure Project 2 report

Building Structure 42 Project 2

UDL Dead load analysis (Beam G/2-3)

Beam Self Weight

= beam size (Sub beam type 2) X concrete density

= (0.2m X 0.3m) X 24kN/m3 = 1.44kN/m

Brick wall Weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Dead load from slab E-G/2-3

= Dead load (UBBL) X (Lx/2)(2/3) (two-way triangular)

= 0.15m X 24kN/m3 X (4.5m/2)(2/3) = 5.4kN/m

Dead load from slab G-H/2-3

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

=0.15m X 24kN/m3 X (3m/2) = 5.4kN/m

Total dead load

For 1-2 = 1.44 + 8.55 + 5.4 + 5.4

= 20.79kN/m

Live load analysis (Beam G/2-3) Live load from slab E-G/2-3

= Live Load Factor (UBBL) X (Lx/2)(2/3)

= 1.5kN/m2 X (4.5m/2)(2/3)

= 2.25kN/m

Live load from slab G-H/2-3

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (3m/2)

= 2.25kN/m

Total live load

= 2.25 + 2.25 = 4.5kN/m

Page 43: Building Structure Project 2 report

Building Structure 43 Project 2

The Ultimate Load Ultimate dead load at 2-3 = 20.79kN/m X 1.4 = 29.1kN/m

Ultimate live load at 2-3 = 4.5kN/m X 1.6 = 7.2kN/m

Ultimate load at 2-3 = 36.3kN/m

Reaction forces Transforming ultimate load into point load

At 2-3 = 36.3kN/m X 3.2m = 116.16kN

Free body diagram

Calculating reaction forces

∑MA = 0

0 = (163.35kN x 2.25m) – 4.5 RB

4.5RB = 367.538kN

RB = 81.68kN

Total Load = RA + RB

RA = 163.36 – 81.68

= 81.68kN

Page 44: Building Structure Project 2 report

Building Structure 44 Project 2

Shear force diagram and Bending Moment Diagram

Page 45: Building Structure Project 2 report

Building Structure 45 Project 2

UDL Dead load analysis (Beam F/3-4)

Beam Self Weight

= beam size (Sub beam type 2) X concrete density

= (0.2m X 0.3m) X 24kN/m3 = 1.44kN/m

Brick wall Weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Dead load from slab E-F/3-4

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

= 0.15m X 24kN/m3 X (3m/2) = 5.4kN/m

Dead load from slab F-H/3-4

= Dead load (UBBL) X (Lx/2)(2/3) (two-way triangular)

=0.15m X 24kN/m3 X (4m/2)(2/3) = 5.4kN/m

Total dead load

For 3-4 = 1.44 + 8.55 + 5.4 + 4.8

= 20.19kN/m

Live load analysis (Beam F/3-4) Live load from slab E-G/2-3

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (3m/2)

= 2.25kN/m

Live load from slab G-H/2-3

= Live Load Factor (UBBL) X (Lx/2)(2/3)

= 1.5kN/m2 X (4m/2)(2/3)

= 2kN/m

Total live load

= 2.25 + 2 = 4.25kN/m

Page 46: Building Structure Project 2 report

Building Structure 46 Project 2

The Ultimate Load Ultimate dead load at 3-4 = 20.19kN/m X 1.4 = 28.266kN/m

Ultimate live load at 3-4 = 4.25kN/m X 1.6 = 6.8kN/m

Ultimate load at 3-4 = 35kN/m

Reaction forces Transforming ultimate load into point load

At 3-4 = 35kN/m X 4.5m =157.5kN

Free body diagram

Calculating reaction forces

∑MA = 0

0 = (157.5kN x 2.25m) – 4.5 RB

4.5RB = 354.375kN

RB = 78.75kN

Total Load = RA + RB

RA = 157.5 – 78.75

= 78.75 kN

Page 47: Building Structure Project 2 report

Building Structure 47 Project 2

Shear force diagram and Bending Moment Diagram

Page 48: Building Structure Project 2 report

Building Structure 48 Project 2

UDL Dead load analysis (Beam E-H/3)

Beam Self Weight

= beam size (Main beam type 2) X concrete density

= (0.2m X 0.5m) X 24kN/m3 = 2.4kN/m

Brick wall Weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Dead load from slab E-G/2-3

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

= 0.15m X 24kN/m3 X (4.5m/2) = 8.1kN/m

Dead load from slab G-H/2-3

= Dead load (UBBL) X (Lx/2)(2/3) (two-way triangular)

=0.15m X 24kN/m3 X (3m/2)(2/3) = 3.6kN/m

Dead load from slab E-F/3-4

= Dead load (UBBL) X (Lx/2)(2/3) (two-way triangular)

=0.15m X 24kN/m3 X (3m/2)(2/3) = 3.6kN/m

Dead load from slab F-H/3-4

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

=0.15m X 24kN/m3 X (4m/2) = 7.2kN/m

Total dead load

From E-F= 2.4 + 8.55 + 8.1 + 3.6

= 22.65kN/m

From F-G= 2.4 + 8.1 + 7.2

= 17.7

From G-H= 2.4 + 8.55 + 3.6 + 72

= 21.75

Page 49: Building Structure Project 2 report

Building Structure 49 Project 2

Live load analysis (Beam E-H/3) Live load from slab E-G/2-3

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (4.5m/2)

= 3.375kN/m

Live load from slab G-H/2-3

= Live Load Factor (UBBL) X (Lx/2)(2/3)

= 1.5kN/m2 X (3m/2)(2/3)

= 1.5kN/m

Live load from slab E-F/3-4

= Live Load Factor (UBBL) X (Lx/2)(2/3)

= 1.5kN/m2 X (3m/2)(2/3)

= 1.5kN/m

Live load from slab F-H/3-4

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (4m/2)

= 3kN/m

Total live load

For E-F = 3.375 + 1.5 = 4.875kN/m

For F-G= 3.375 + 3 = 6.375 kN/m

For G-H= 1.5 + 3 = 4.5

The Ultimate Load Ultimate dead load at E-F = 22.65kN/m X 1.4 = 31.71kN/m

Ultimate dead load at F-G = 17.7kN/m X 1.4 = 24.78kN/m

Ultimate dead load at G-H = 21.75kN/m X 1.4 = 30.45kN/m

Ultimate live load at E-F = 4.875kN/m X 1.6 = 7.8kN/m

Ultimate live load at F-G = 6.375kN/m X 1.6 = 10.2kN/m

Ultimate live load at G-H = 4.5kN/m X 1.6 = 7.2kN/m

Ultimate load at E-F = 39.51kN/m

Ultimate load at F-G = 34.98kN/m

Ultimate load at G-H = 37.65kN/m

Total live load

Page 50: Building Structure Project 2 report

Building Structure 50 Project 2

Reaction forces Point loads acting at beam

Sub beam F/3-4

Reaction force RA = point load = 78.75kN

(as calculated in Beam F/3-4 analysis)

Sub beam G/2-3

Reaction force RB = point load = 81.68kN

(as calculated in Beam G/2-3 analysis) Transforming ultimate load into point load

At E-F = 39.51kN/m X 3m =118.53kN

At F-G = 34.98kN/m X 2.7m = 94.45kN

At G-H = 37.65kN/m X 3m = 112.95 kN

Free body diagram

Calculating reaction forces

∑MA = 0

0 = (118.53kN x 1.5m) + (78.75kN x 3m) + (94.45kN x 4.35) + (81.68kN x 5.7m)

+ (112.95kN x 7.2m) – 8.7 RB

8.7RB = 2103.7kN

RB = 241.8kN

Total Load = RA + RB

RA = 486.36 – 241.8

= 244.56kN

Free-body diagram Free-body diagram

Page 51: Building Structure Project 2 report

Building Structure 51 Project 2

Shear force diagram and Bending Moment Diagram

Page 52: Building Structure Project 2 report

Building Structure 52 Project 2

Beam analysis report

By Ong Jia Hui (0317752)

Page 53: Building Structure Project 2 report

Building Structure 53 Project 2

UDL Dead Load Analysis (Beam F/2-3)

Beam Self Weight

= beam size (sub beam type 2) X concrete density

= (0.3m X 0.2m) X 24kN/m3 = 1.44kN/m

Brick Wall Weight

= height X thickness X brick density

= 3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Dead load from slab C-F/2-3

= [Dead load (UBBL) X (Lx/2)] 2/3 (two-way triangular)

= 0.15m X 24kN/m3 X (4.5m/2) 2/3 = 5.40kN/m

Dead load from slab F-H/2-3

= [Dead load (UBBL) X (Lx/2)] 2/3 (two-way triangular)

=0.15m X 24kN/m3 X (4.5m/2) 2/3 = 5.40kN/m

Total Dead Load

For 2-3 (i) = 20.79kN/m

(ii) = 12.24kN/m

Live Load Analysis (Beam F/2-3) Live load from slab C-F/2.3

= [Live load Factor (UBBL) X (Lx/2)] 2/3

= 1.5kN/m2 X (4.5m/2) 2/3

= 2.25kN/m

Live load from slab F-H/2-3

= [Live load Factor (UBBL) X (Lx/2)] 2/3

= 1.5kN/m2 X (4.5m/2) 2/3

= 2.25kN/m

Total Live Load = 4.5kN/m

Page 54: Building Structure Project 2 report

Building Structure 54 Project 2

Ultimate Load Ultimate dead load at 2-3 = (i) 20.79kN/m X 1.4 = 29.10kN/m

(ii) 12.24kN/m X 1.4 = 17.13kN/m

Ultimate live load at 2-3 = 4.5kN/m X 1.6 = 7.2kN/m

Ultimate load on 2-3 (i) = 36.3kN/m

(ii) = 24.33kN/m

Reaction forces Transforming ultimate load into point load

2-3 = (i) 36.3kN/m X 1.75m = 63.52kN

(ii) 24.33kN/m X 2.75m = 66.90kN

Free Body Diagram

Calculating Reaction Forces

∑MA = 0

0 = [(36.3kN/m X 1.75m) X 1.75m/2] + [(24.33kN/m X 2.75m) X (2.75m/2 +

1.75m)] - 4.5RB

4.5RB = 55.89kN + 209.06kN

RB = 58.87kN

Total Load = RA + RB

RA = Total load - RB

RB = 63.52kN + 66.90kN – 58.87kN

RA = 71.55kN

Page 55: Building Structure Project 2 report

Building Structure 55 Project 2

Shear Force Diagram and Bending Moment Diagram

Page 56: Building Structure Project 2 report

Building Structure 56 Project 2

UDL Dead Load Analysis (Beam G/3-4)

Beam Self Weight

= beam size (sub beam type 2) X concrete density

= (0.3m X 0.2m) X 24kN/m3 = 1.44kN/m

Brick Wall Weight

= height X thickness X brick density

= 3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Dead load from slab E-G/3-4

= [Dead load (UBBL) X (Lx/2)] 2/3 (two-way triangular)

= 0.15m X 24kN/m3 X (4m/2) 2/3 = 4.80kN/m

Dead load from slab G-H/3-4

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

= 0.15m X 24kN/m3 X (3m/2) = 5.40kN/m

Total Dead Load

For 3-4 = 11.64kN/m

Live Load Analysis (Beam G/3-4) Live load from slab E-G/3-4

= Live Load Factor (UBBL) X (Lx/2) 2/3

= 1.5kN/m2 X (4m/2) 2/3

= 2.0kN/m

Live load from slab G-H/3-4

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (3m/2)

= 2.25kN/m

Total Live Load = 4.25kN/m

Page 57: Building Structure Project 2 report

Building Structure 57 Project 2

Ultimate Load Ultimate dead load at 3-4 = 11.64kN/m X 1.4 = 16.30kN/m

Ultimate live load at 3-4 = 4.25kN/m X 1.6 = 6.80kN/m

Ultimate load on 3-4 = 23.10kN/m

Reaction forces Transforming ultimate load into point load

3-4 = 23.10kN/m X 4m = 92.40kN

Free Body Diagram

Calculating Reaction Forces

∑MA = 0

0 = [(23.1kN/m X 4m) X 4m/2] - 4RB

4RB = 184.8kN

RB = 46.20kN

Total Load = RA + RB

RA = Total load - RB

RB = 92.4kN – 46.2kN

RB = 46.2kN

Page 58: Building Structure Project 2 report

Building Structure 58 Project 2

Shear Force Diagram and Bending Moment Diagram

Page 59: Building Structure Project 2 report

Building Structure 59 Project 2

UDL Dead load analysis (Beam E-H/3)

Beam Self Weight

= beam size (main beam type 2) X concrete density

= (0.5m X 0.2m) X 24kN/m3 = 2.40kN/m

Brick Wall Weight

= height X thickness X brick density

= 3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Dead load from slab E-F/2-3

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

= 0.15m X 24kN/m3 X (4.2m/2) = 7.56kN/m

Dead load from slab F-H/2-3

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

= 0.15m X 24kN/m3 X (4.2m/2) = 7.56kN/m

Dead load from slab E-G/3-4

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

= 0.15m X 24kN/m3 X (3.7m/2) = 6.66kN/m

Dead load from slab G-H/3-4

= [Dead load (UBBL) X (Lx/2)] 2/3 (two-way triangular)

= 0.15m X 24kN/m3 X (2.7m/2) 2/3 = 3.24kN/m

Total Dead Load

For E-F = 16.62kN/m

F-G = 25.17kN/m

G-H = 21.75kN/m

Page 60: Building Structure Project 2 report

Building Structure 60 Project 2

Live Load Analysis (Beam E-H/3) Live load from slab E-F/2-3

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (4.2m/2)

= 3.15kN/m

Live load from slab F-H/2-3

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (4.2m/2)

= 3.15kN/m

Live load from slab E-G/3-4

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (3.7m/2)

= 2.77kN/m

Live load from slab G-H/3-4

= [Live Load Factor (UBBL) X (Lx/2)] 2/3

= 1.5kN/m2 X (2.7m/2) 2/3

= 1.35kN/m

Total Live Load at E-F = 5.92kN/m

F-G = 5.92kN/m

G-H = 4.50kN/m

Ultimate Load Ultimate dead load at E-F = 16.62kN/m X 1.4 = 23.26kN/m

Ultimate dead load at F-G = 25.17kN/m X 1.4 = 35.23kN/m

Ultimate dead load at G-H = 21.75kN/m X 1.4 = 30.45kN/m

Ultimate live load at E-F = 5.92kN/m X 1.6 = 9.47kN/m

Ultimate live load at F-G = 5.92kN/m X 1.6 = 9.47kN/m

Ultimate live load at G-H = 4.5kN/m X 1.6 = 7.2kN/m

Ultimate load on E-F = 32.73kN/m

Ultimate load on F-G = 32.73kN/m

Ultimate load on G-H = 37.65kN/m

Page 61: Building Structure Project 2 report

Building Structure 61 Project 2

Reaction forces Point loads acting at beam

Sub beam F/2-3

Point load at F3 = 58.87kN

(as calculated in Beam F/2-3 analysis)

Sub beam G/3-4

Point load at G3 = 46.20kN

(as calculated in Beam G/3-4 analysis)

Transforming ultimate load into point load

E-F = 32.73kN/m X 2.7m = 88.37kN

F-G = 32.73kN/m X 2.7m = 88.37kN

G-H = 37.65kN/m X 3m = 112.95kN

Free Body Diagram

Calculating Reaction Forces

∑MA = 0

0 = [(32.73kN/m X 2.7m) X 2.7m/2] + (28.87kN X 2.7m) + [(32.73kN/m X 2.7m)

X 2.7m/2 + 2.7] + [46.2kN X (2.7m+2.7m)] + [(37.65kN X 3m) X

(3/2+2.7m+2.7m)] – 8.4RB

8.4RB = 1664.96kN

RB = 198.21kN

Total Load = RA + RB

RA = Total load - RB

RB = 394.76kN – 198.21kN

RB = 196.55kN

Page 62: Building Structure Project 2 report

Building Structure 62 Project 2

Shear Force Diagram and Bending Moment Diagram

Page 63: Building Structure Project 2 report

Building Structure 63 Project 2

UDL Dead Load Analysis (Beam E/2-3)

Beam Self Weight

= beam size (sub beam type 2) X concrete density

= (0.3m X 0.2m) X 24kN/m3 = 1.44kN/m

Brick Wall Weight

= 0

Dead load from slab E-G/2-3

= [Dead load (UBBL) X (Lx/2)] 2/3 (two-way triangular)

= 0.15m X 24kN/m3 X (4.5m/2) 2/3 = 5.40kN/m

Dead load from C-E/2-3

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

= 0.15m X 24kN/m3 X (4m/2) = 7.20kN/m

Total Dead Load

For 2-3 = 14.04kN/m

Live Load Analysis (Beam E/2-3) Live load from slab E-G/2-3

= [Live Load Factor (UBBL) X (Lx/2)] 2/3

= 1.5kN/m2 X (4.5m/2) 2/3

= 2.25kN/m

Live load from slab E-G/3-4

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (4m/2)

= 3.00kN/m

Total Live Load = 5.25kN/m

Page 64: Building Structure Project 2 report

Building Structure 64 Project 2

Ultimate Load Ultimate dead load at 2-3 = 14.04kN/m X 1.4 = 19.65kN/m

Ultimate live load at 2-3 = 5.25kN/m X 1.6 = 8.40kN/m

Ultimate load on 2-3 = 28.05kN/m

Reaction forces Transforming ultimate load into point load

2-3 = 28.05kN/m X 4.5m = 126.22kN

Free body diagram

Calculating Reaction Forces

∑MA = 0

0 = [(28.05kN/m X 4.5m) X 4.5m/2] – 4.5RB

4.5RB = 126.22kN X 2.25m

RB = 63.11kN

Total Load = RA + RB

RA = Total load - RB

RB = 126.22kN – 63.11kN

RB = 63.11kN

Page 65: Building Structure Project 2 report

Building Structure 65 Project 2

Shear Force Diagram and Bending Moment Diagram

Page 66: Building Structure Project 2 report

Building Structure 66 Project 2

UDL Dead load analysis (Beam E/1-2)

Beam Self Weight

= beam size (sub beam type 2) X concrete density

= (0.3m X 0.2m) X 24kN/m3 = 1.44kN/m

Brick Wall Weight

= height X thickness X brick density

= 3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Dead load from slab C-E/1-2

= [Dead load (UBBL) X (Lx/2)] 2/3 (two-way triangular)

= 0.15m X 24kN/m3 X (3.2m/2) 2/3 = 3.84kN/m

Total Dead Load = 13.83kN/m

Live load analysis (Beam E/1-2) Live load from slab C-E/1-2

= [Live Load Factor (UBBL) X (Lx/2)] 2/3

= 1.5kN/m2 X (3.2m/2) 2/3

= 1.60kN/m

Page 67: Building Structure Project 2 report

Building Structure 67 Project 2

Ultimate Load Ultimate dead load at 1-2 = 13.83kN/m X 1.4 = 19.36kN/m

Ultimate live load at 1-2 = 1.6kN/m X 1.6 = 2.56kN/m

Ultimate load on 1-2 = 21.92kN/m

Reaction Forces

Transforming ultimate load into point load

1-2 = 21.92kN/m X 3.2m = 70.14kN

Free Body Diagram

Calculating Reaction Forces

∑MA = 0

0 = [(21.92kN/m X 3.2m) X 3.2m/2] – 3.2RB

3.2RB = 70.14kN X 1.6m

RB = 35.07kN

Total Load = RA + RB

RA = Total load - RB

RB = 70.14kN – 35.07kN

RB = 35.07kN

Page 68: Building Structure Project 2 report

Building Structure 68 Project 2

Shear Force Diagram and Bending Moment Diagram

Page 69: Building Structure Project 2 report

Building Structure 69 Project 2

UDL Dead Load Analysis (Beam C-F/2)

Beam Self Weight

= beam size (main beam type 2) X concrete density

= (0.2m X 0.5m) X 24kN/m3 = 2.40kN/m

Brick Wall Weight

= height X thickn3ess X brick density

= 3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Dead load from slab C-E/1-2

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

= 0.15m X 24kN/m3 X (3.2m/2) = 5.76kN/m

Dead load from slab E-F/1-2

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

= 0.15m X 24kN/m3 X (3.2m/2) = 5.76kN/m

Dead load from slab C-E/2-3

= [Dead load (UBBL) X (Lx/2)] 2/3 (two-way triangular)

= 0.15m X 24kN/m3 X (4m/2) 2/3 = 4.80kN/m

Dead load from slab G-H/3-4

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

= 0.15m X 24kN/m3 X (4.5m/2) = 8.1kN/m

Total Dead Load

For C-E = 21.51kN/m

E-F = 24.81kN/m

Page 70: Building Structure Project 2 report

Building Structure 70 Project 2

Live Load Analysis (Beam C-F/2) Live load from slab C-E/1-2

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (3.2m/2)

= 2.40kN/m

Live load from slab E-F/1-2

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (3.2m/2)

= 2.40kN/m

Live load from slab C-E/2-3

= [Live Load Factor (UBBL) X (Lx/2)] 2/3

= 1.5kN/m2 X (4m/2) 2/3

= 4.80kN/m

Live load from slab E-F/2-3

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (4.5m/2)

= 3.37kN/m

Total Live Load at C-E = 7.2kN/m

E-F = 5.77kN/m

Ultimate Load Ultimate dead load at C-E = 21.51kN/m X 1.4 = 30.11kN/m

Ultimate dead load at E-F = 24.81kN/m X 1.4 = 34.73/m

Ultimate live load at C-E = 7.2kN/m X 1.6 = 11.52kN/m

Ultimate live load at E-F = 5.77kN/m X 1.6 = 9.23kN/m

Ultimate load on C-E = 41.63kN/m

Ultimate load on E-F = 43.96kN/m

Page 71: Building Structure Project 2 report

Building Structure 71 Project 2

Reaction forces Point loads acting at beam

Sub beam E/1-2

Point load at E2 = 35.07kN

(as calculated in Beam E/1-2 analysis)

Sub beam E/3-4

Point load at E2 = 63.11kN

(as calculated in Beam E/3-4 analysis)

Transforming ultimate load into point load

C-E = 41.63kN/m X 4m = 166.52kN

E-F = 43.96kN/m X 3m = 131.88kN

Free Body Diagram

Calculating Reaction Forces

∑MA = 0

0 = [(41.63kN/m X 4m) X 4m/2] + (98.18kN X 4m) + [(43.96kN/m X 3m) X

(3m/2+4m)] - 7RB

7RB = 1451.10kN

RB = 207.30kN

Total Load = RA + RB

RA = Total load - RB

RB = 166.52kN + 35.07kN + 131.88kN + 63.11kN – 207.30kN

RB = 189.28kN

Page 72: Building Structure Project 2 report

Building Structure 72 Project 2

Shear Force Diagram and Bending Moment Diagram

Page 73: Building Structure Project 2 report

Building Structure 73 Project 2

UDL Dead Load Analysis (Beam C/1-3)

Beam Self Weight

= beam size (main beam type 2) X concrete density

= (0.5m X 0.2m) X 24kN/m3 = 2.40kN/m

Brick Wall Weight

= height X thickness X brick density

= 3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Dead load from slab A-C/1-3

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

= 0.15m X 24kN/m3 X (6m/2) = 10.80kN/m

Dead load from slab C-E/1-2

= [Dead load (UBBL) X (Lx/2)] 2/3 (two-way triangular)

= 0.15m X 24kN/m3 X (3.2m/2) 2/3 = 3.84kN/m

Dead load from slab C-E/2-3

= Dead load (UBBL) X (Lx/2) (two-way trapezoidal)

= 0.15m X 24kN/m3 X (4m/2) = 7.20kN/m

Total Dead Load

For 1-2 = 25.59kN/m

2-3 = 28.95kN/m

Live Load Analysis (Beam C/1-3) Live load from slab A-C/1-3

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (6m/2)

= 4.50kN/m

Live load from slab C-E/1-2

= [Live Load Factor (UBBL) X (Lx/2)] 2/3

= 1.5kN/m2 X (3.2m/2) 2/3

= 1.60kN/m

Live load from slab C-E/2-3

= Live Load Factor (UBBL) X (Lx/2)

= 1.5kN/m2 X (4m/2)

= 3.00kN/m

Total Live Load at 1-2 = 6.10kN/m

2-3 = 7.50kN/m

Page 74: Building Structure Project 2 report

Building Structure 74 Project 2

Ultimate Load Ultimate dead load at 1-2 = 25.59kN/m X 1.4 = 35.82kN/m

Ultimate dead load at 2-3 = 28.95kN/m X 1.4 = 40.53/m

Ultimate live load at 1-2 = 6.1kN/m X 1.6 = 9.76kN/m

Ultimate live load at 2-3 = 7.5kN/m X 1.6 = 12.00kN/m

Ultimate load on 1-2 = 45.58kN/m

Ultimate load on 2-3 = 52.53kN/m

Reaction forces Point loads acting at beam

Sub beam C/1-3

Point load at C2 = 189.28kN

(as calculated in Beam C/1-3 analysis)

Transforming ultimate load into point load

1-2 = 45.58kN/m X 3.2m = 145.85kN

2-3 = 52.53kN/m X 4.5m = 236.38kN

Free Body Diagram

Calculating Reaction Forces

∑MA = 0

0 = [(45.58kN/m X 3.2m) X 3.2m/2] + (189.28kN X 3.2m) + [(52.53kN/m X

4.5m) X (4.5m/2 + 3.2m)] – 7.7RB

7.7RB = 2127.279kN

RB = 276.27kN

Total Load = RA + RB

RA = Total load - RB

RB = 145.85kN + 189.28kN + 236.38kN – 276.27kN

RB = 295.24kN

Page 75: Building Structure Project 2 report

Building Structure 75 Project 2

Shear Force Diagram and Bending Moment Diagram

Page 76: Building Structure Project 2 report

Building Structure 76 Project 2

Column analysis report

By Tan Wen Hao (0319923)

Page 77: Building Structure Project 2 report

Building Structure 77 Project 2

Tributary area method load analysis on column G7

Height of floors = 3m

Brick wall weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Beam self weight

I. (GF) D-G/7, G-H/7, (1F) D-G/7, 4-7/G, (RF) D-G/7, 4-7/G

= beam size (Main beam type 1) X concrete density

= (0.6m X 0.2m) X 24kN/m3 = 2.88kN/m

II. (GF) 4-7/F, F-H/6, (RF) 4-7/F

= beam size (sub beam type 1) X concrete density

= (0.4m X 0.2m) X 24kN/m3 = 1.92kN/m

Slab weight

= thickness X concrete density

=0.15m X 24kN/m3 = 3.6kN/m

2

Column self weight

= beam size X height X concrete density

= 0.3m X 0.4m X 3m X 24kN/m3 = 8.64kN

Page 78: Building Structure Project 2 report

Building Structure 78 Project 2

Dead load acting on column G7

Roof level Slabs (Flat roof) 12.6m2 (ttl slab area) X 3.6kN/m

2 45.36kN

Roof beams (6.85m X 2.88kN/m) + (3m X 1.92kN/m) 25.488kN

1st floor Wall self weight 6.85m (ttl wall length) X 8.55kN/m 58.568kN

Slabs 12.6m2 (ttl slab area) X 3.6kN/m

2 45.36kN

Beams 6.85m X 2.88kN/m 19.728kN

Column - 8.64kN

Grd

floor Wall self weight 10.65m (ttl wall length) X 8.55kN/m 91.058kN

Slabs 16.203m2 (ttl slab area) X 3.6kN/m

2 58.331kN

Beams (5.35m X 2.88kN/m) + (7.2m X

1.92kN/m)

29.232kN

Column - 8.64kN

Total dead load 390.405kN

Apply 1.4 dead load factor 546.567kN

Live load acting on column G7

1st floor Residential 12.6m

2 (ttl slab area) X 1.5kN/m

2 18.9kN

Grd

floor Residential 16.203m2 (ttl slab area) X 1.5kN/m

2 24.305kN

Total live load 43.205kN

Apply 1.6 Live load factor 69.128kN

Ultimate load on column G7 = 615.695kN

Page 79: Building Structure Project 2 report

Building Structure 79 Project 2

Tributary area method load analysis on column G4

Height of floors = 3m

Brick wall weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Beam self weight

I. (GF) G-H/4 (1F) G-H/4, 4-7/G (RF) G-H/4, 4-7/G

= beam size (Main beam type 1) X concrete density

= (0.6m X 0.2m) X 24kN/m3 = 2.88kN/m

II. (GF)E-G/4, 3-4/G (1F) E-G/4 (RF) F-G/4

= beam size (Main beam type 2) X concrete density

= (0.5m X 0.2m) X 24kN/m3 = 2.4kN/m

III. (GF) 4-7/F (1F) 3-4/F (RF) 3-4/F, 4-7/F

= beam size (sub beam type 1) X concrete density

= (0.4m X 0.2m) X 24kN/m3 = 1.92kN/m

Slab weight

= thickness X concrete density

=0.15m X 24kN/m3 = 3.6kN/m

2

Column self weight

= beam size X height X concrete density

= 0.3m X 0.4m X 3m X 24kN/m3 = 8.64kN

Page 80: Building Structure Project 2 report

Building Structure 80 Project 2

Dead load acting on column G4

Roof level Slabs (Flat roof) 22.903m2 (ttl slab area) X 3.6kN/m

2 82.451kN

Roof beams (4.5m X 2.88kN/m) + (3.85m X

2.4kN/m) + (5m X 1.92kN/m)

31.8kN

1st floor Wall self weight 10.35m (ttl wall length) X 8.55kN/m 88.493kN

Slabs 22.903 m2 (ttl slab area) X 3.6kN/m

2 82.451kN

Beams (4.5m X 2.88kN/m) + (3.85m X

2.4kN/m) + (2m X 1.92kN/m)

26.04kN

Column - 8.64kN

Grd

floor Wall self weight 5.65m (ttl wall length) X 8.55kN/m 48.308kN

Slabs 21.098m2 (ttl slab area) X 3.6kN/m

2 75.953kN

Beams (1.5m X 2.88kN/m) + (4.7m X

1.92kN/m) + (3m X 1.92kN/m)

19.104kN

Column - 8.64kN

Total dead load 471.88kN

Apply 1.4 dead load factor 660.632N

Live load acting on column G4

1st floor Residential 22.903m

2 (ttl slab area) X 1.5kN/m

2 34.355kN

Grd

floor Residential 21.098m2 (ttl slab area) X 1.5kN/m

2 31.647kN

Total live load 66.002kN

Apply 1.6 Live load factor 105.603kN

Ultimate load on column G4 = 766.235kN

Page 81: Building Structure Project 2 report

Building Structure 81 Project 2

Tributary area method load analysis on column E3

Height of floors = 3m

Brick wall weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Beam self weight

I. (GF) C-E/3, 3-5/E (1F) C-E/3, 3-7/D (RF) C-E/3, 3-7/D

= beam size (Main beam type 1) X concrete density

= (0.6m X 0.2m) X 24kN/m3 = 2.88kN/m

II. (GF) E-H/3, 2-3/F (1F) 2-3/E, 3-4/E, E-H/3 , D-G/4 (RF) E-H/3

= beam size (Main beam type 2) X concrete density

= (0.5m X 0.2m) X 24kN/m3 = 2.4kN/m

III. (1F) 3-4/F (RF) D-F/4, 2-3/F, 3-4/F

= beam size (sub beam type 1) X concrete density

= (0.4m X 0.2m) X 24kN/m3 = 1.92kN/m

Slab weight

= thickness X concrete density

=0.15m X 24kN/m3 = 3.6kN/m

2

Column self weight

= beam size X height X concrete density

= 0.3m X 0.4m X 3m X 24kN/m3 = 8.64kN

Page 82: Building Structure Project 2 report

Building Structure 82 Project 2

Dead load acting on column E3

Roof level Slabs (Flat roof) 39.625m2 (ttl slab area) X 3.6kN/m

2 142.65kN

Roof beams (7m X 2.88kN/m) + (4.35m X

2.4kN/m) + (8.1m X 1.92kN/m)

46.152kN

1st floor Wall self weight 14.195m (ttl wall length) X

8.55kN/m

121.367kN

Slabs 39.625m2 (ttl slab area) X 3.6kN/m

2 142.65kN

Beams (7m X 2.88kN/m) + (10.6m X

2.4kN/m) + (2m X 1.92kN/m)

49.44kN

Column - 8.64kN

Grd

floor Wall self weight 8.4m (ttl wall length) X 8.55kN/m 71.82kN

Slabs 28.14m2 (ttl slab area) X 3.6kN/m

2 101.304kN

Beams (4.65m X 2.88kN/m) + (6.6m X

2.4kN/m)

29.232kN

Column - 8.64kN

Total dead load 721.895kN

Apply 1.4 dead load factor 1010.653kN

Live load acting on column E3

1st floor Residential 39.625m

2 (ttl slab area) X 1.5kN/m

2 59.438kN

Grd

floor Residential 28.14m2 (ttl slab area) X 1.5kN/m

2 42.21kN

Total live load 101.648kN

Apply 1.6 Live load factor 162.637kN

Ultimate load on column E3 = 1173.29kN

Page 83: Building Structure Project 2 report

Building Structure 83 Project 2

Efficiency of column

N = 0.4fcuAc + 0.8 fyAsc

N = capacity of concrete

Fcu = concrete strength (N/mm2) = 30N/mm2

Ac = cross section of concrete column

fy = yield strength of steel (N/mm2) = 460N/mm2

Asc = steel content in a column

Ac = 300 x 400 = 120,000

Asc

= 2 % x 120,000 = 2,400

N = 0.4fcu

Ac + 0.8 f

yA

sc

= 0.4(30)(120000) + 0.8(460)(2400) = 1440,000 + 883,200

= 2323200 N = 2323.2kN

300mm

400mm

For column G7 = 615.695kN (sustainable load) For column G4 = 766.235kN (sustainable load) For column E3 = 1173.29kN (sustainable load)

Page 84: Building Structure Project 2 report

Building Structure 84 Project 2

Column analysis report

By Ong Min Junn (0317767)

Page 85: Building Structure Project 2 report

Building Structure 85 Project 2

Tributary area method load analysis on column C1

Height of floors = 3m

Brick wall weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Beam self weight

III. (GF) C/1-3, C-E/1, (FF) A-C/1, C-E/1, C/1-3, (RF) A-C/1, C-E/1, C/1-3

= beam size (Main beam type 1) X concrete density

= (0.2m X 0.6m) X 24kN/m3 = 2.88kN/m

IV. (GF) C-F/2, (FP) C-F/2, (RF) A-C/2 C-F/2

= beam size (Sub beam type 1) X concrete density

= (0.2m X 0.4m) X 24kN/m3 = 1.92kN/m

Slab weight

= thickness X concrete density

=0.15m X 24kN/m3 = 3.6kN/m

2

Column self weight

= beam size X height X concrete density

= 0.3m X 0.4m X 3m X 24kN/m3 = 8.64kN

Page 86: Building Structure Project 2 report

Building Structure 86 Project 2

Dead load acting on column C1

Roof level Slabs (Flat roof) 26m2 (ttl slab area) X 3.6kN/m

2 93.6kN

Roof beams (10.35m X 2.88kN/m) + (6.5m X

1.92kN/m)

42.288kN

1st floor Wall self weight 13.85m (ttl wall length) X 8.55kN/m 118.418kN

Slabs 26m2 (ttl slab area) X 3.6kN/m

2 93.6kN

Beams (10.35m X 2.88kN/m) + (3.5m X

1.92kN/m)

36.528kN

Column Standard column self weight 8.64kN

Grd

floor Wall self weight 10.85m (ttl wall length) X 8.55kN/m 92.768kN

Slabs 14.6m2 (ttl slab area) X 3.6kN/m

2 52.56kN

Beams (7.35m X 2.88kN/m) + (3.5m X

1.92kN/m)

27.888kN

Column Standard column self weight 8.64kN

Total dead load 574.93N

Apply 1.4 dead load factor 804.902kN

Live load acting on column C1

1st floor Residential 26m

2 (ttl slab area) X 1.5kN/m

2 39Kn

Grd

floor Residential 14.6m2 (ttl slab area) X 1.5kN/m

2 21.9kN

Total live load 60.9kN

Apply 1.6 Live load factor 97.44kN

Ultimate load on column C1 = 902.342kN

Page 87: Building Structure Project 2 report

Building Structure 87 Project 2

Tributary area method load analysis on column F1

Height of floors = 3m

Brick wall weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Beam self weight

V. (GF) C-F/1, F-H/1 (FF) C-F/1, F-H/1 (RF) C-F/1, F-H/1

= beam size (Main beam type 1) X concrete density

= (0.2m X 0.6m) X 24kN/m3 = 2.88kN/m

VI. (GF) E/1-2, F/1-2 (FP) E/1-2 (RF) F/1-2

= beam size (Sub beam type 2) X concrete density

= (0.2m X 0.3m) X 24kN/m3 = 1.44kN/m

Slab weight

= thickness X concrete density

=0.15m X 24kN/m3 = 3.6kN/m

2

Column self weight

= beam size X height X concrete density

= 0.3m X 0.4m X 3m X 24kN/m3 = 8.64kN

Page 88: Building Structure Project 2 report

Building Structure 88 Project 2

Dead load acting on column F1

Roof level Slabs (Flat roof) 11.11m2 (ttl slab area) X 3.6kN/m

2 39.996kN

Roof beams (6.35m X 2.88kN/m) + (1.6m X

1.44kN/m)

20.592kN

1st floor Wall self weight 7.95m (ttl wall length) X 8.55kN/m 67.973kN

Slabs 11.11m2 (ttl slab area) X 3.6kN/m

2 39.996kN

Beams (6.35m X 2.88kN/m) + (1.6m X

1.44kN/m)

20.592kN

Column Standard column size 8.64kN

Grd

floor Wall self weight 9.55 m (ttl wall length) X 8.55kN/m 81.65kN

Slabs 11.11m2 (ttl slab area) X 3.6kN/m

2 39.996kN

Beams (6.35m X 2.88kN/m) + (3.2m X

1.44kN/m)

22.896kN

Column Standard column self weight 8.64kN

Total dead load 350.971kN

Apply 1.4 dead load factor 491.36kN

Live load acting on column F1

1st floor Residential 11.11m

2 (ttl slab area) X 1.5kN/m

2 16.665Kn

Grd

floor Residential 11.11m2 (ttl slab area) X 1.5kN/m

2 16.665kN

Total live load 33.33kN

Apply 1.6 Live load factor 53.328kN

Ultimate load on column F1 = 544.688kN

Page 89: Building Structure Project 2 report

Building Structure 89 Project 2

Tributary area method load analysis on column F2

Height of floors = 3m

Brick wall weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Beam self weight

VII. (GF) C-F/2, F-H/2, F/2-3 (FF) C-F/2, F-H/2 (RF) C-F/2, F-H/2

= beam size (Sub beam type 1) X concrete density

= (0.2m X 0.4m) X 24kN/m3 = 1.92kN/m

VIII. (GF) E/1-2, F/1-2 (FF) E/1-2, E/2-3, G/2-3 (RF) F/1-2, F/2-3

= beam size (Sub beam type 2) X concrete density

= (0.2m X 0.3m) X 24kN/m3 = 1.44kN/m

Slab weight

= thickness X concrete density

=0.15m X 24kN/m3 = 3.6kN/m

2

Column self weight

= beam size X height X concrete density

= 0.3m X 0.4m X 3m X 24kN/m3 = 8.64kN

Page 90: Building Structure Project 2 report

Building Structure 90 Project 2

Dead load acting on column F2

Roof level Slabs (Flat

roof)

24.45m2 (ttl slab area) X 3.6kN/m

2 88.02kN

Roof beams (6.35m X 1.92kN/m) + (3.85m X

1.44kN/m)

17.736kN

1st floor Wall self

weight

10.2m (ttl wall length) X 8.55kN/m 87.21kN

Slabs 24.45m2 (ttl slab area) X 3.6kN/m

2 88.02kN

Beams (6.35m X 1.92kN/m) + (6.1m X

1.44kN/m)

20.98kN

Column Standard column size 8.64kN

Grd

floor Wall self

weight

9.55m (ttl wall length) X 8.55kN/m 81.65kN

Slabs 24.45m2 (ttl slab area) X 3.6kN/m

2 88.02kN

Beams (8.6m X 1.92kN/m) + (3.2m X

1.44kN/m)

21.12kN

Column Standard column size 8.64kN

Total dead load 510.036kN

Apply 1.4 dead load factor 714.05kN

Live load acting on column F2

1st floor Residential 24.45m

2 (ttl slab area) X 1.5kN/m

2 36.675Kn

Grd

floor Residential 24.45m2 (ttl slab area) X 1.5kN/m

2 36.675kN

Total live load 73.35kN

Apply 1.6 Live load factor 117.36kN

Ultimate load on column F2 = 831.41kN

Page 91: Building Structure Project 2 report

Building Structure 91 Project 2

Efficiency of column N = 0.4fcuAc + 0.8 fyAsc

N = capacity of concrete

Fcu = concrete strength (N/mm2) = 30N/mm2

Ac = cross section of concrete column

fy = yield strength of steel (N/mm2) = 460N/mm2

Asc = steel content in a column

Ac = 300 x 400 = 120,000

Asc

= 2 % x 120,000 = 2,400

N = 0.4fcu

Ac + 0.8 f

yA

sc

= 0.4(30)(120000) + 0.8(460)(2400)

= 1440,000 + 883,200

= 2323200 N = 2323.2kN

300mm

400mm

For column C1 = 902.342kN (sustainable load) For column F1 = 544.688kN (sustainable load) For column F2 = 831.41kN (sustainable load)

Page 92: Building Structure Project 2 report

Building Structure 92 Project 2

Column analysis report

By Ong Jia Hui (0317751)

Page 93: Building Structure Project 2 report

Building Structure 93 Project 2

Tributary area method load analysis on column C3

Height of floors = 3m

Brick wall weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Beam self weight

I. (GF) C/1-3 (1F) C/1-3, A-C/3 (RF) C/1-3, A-C/3

= beam size (main beam type 2) X concrete density

= (0.5m X 0.2m) X 24kN/m3 = 2.40kN/m

II. (GF) C-E/3 (1F) C-E/3 (RF) C-E/3

= beam size (sub beam type 2) X concrete density

= (0.3m X 0.2m) X 24kN/m3 = 1.44kN/m

Slab weight

= thickness X concrete density

=0.15m X 24kN/m3 = 3.6kN/m

2

Column self weight

= beam size X height X concrete density

= 0.3m X 0.4m X 3m X 24kN/m3 = 8.64kN

Page 94: Building Structure Project 2 report

Building Structure 94 Project 2

Dead load acting on column C3

Roof

level

Slabs (Flat

roof)

22.4m2 (ttl slab area) X 3.6kN/m

2 80.64kN

Roof beams (6.85m X 2.40kN/m) + (2m X

1.44kN/m)

19.32kN

1st floor Wall self

weight

8.85m (ttl wall length) X 8.55kN/m 75.66kN

Slabs 22.4m2 (ttl slab area) X 3.6kN/m

2 80.64kN

Beams (6.85m X 2.40kN/m) + (2m X

1.44KN/m)

19.32kN

Column - 8.64kN

Grd

floor Wall self

weight

5.85m (ttl wall length) X 8.55kN/m 50.01kN

Slabs 8.6m2 (ttl slab area) X 3.6kN/m

2 30.96kN

Beams (3.85m X 2.4kN/m) + (2m X

1.44kN/m)

12.12kN

Column - 8.64kN

Total dead load 385.95kN

Apply 1.4 dead load factor 540.34KN

Live load acting on column C3

1st floor Residential 22.4m

2 (ttl slab area) X 1.5kN/m

2 33.60kN

Grd

floor Residential 8.6m2 (ttl slab area) X 1.5kN/m

2 12.90kN

Total live load 46.50kN

Apply 1.6 Live load factor 74.40kN

Ultimate load on column C3 = 617.74kN

Page 95: Building Structure Project 2 report

Building Structure 95 Project 2

Tributary area method load analysis on column H2

Height of floors = 3m

Brick wall weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Beam self weight

I. (GF) H/2-3 (1F) H/2-3 (RF) H/2-3

= beam size (main beam type 2) X concrete density

= (0.5m X 0.2m) X 24kN/m3 = 2.40kN/m

II. (GF) H/1-2, F-H/2 (1F) H/1-2, F-H/2 (RF) H/1-2, F-H/2

= beam size (sub beam type 1) X concrete density

= (0.4m X 0.2m) X 24kN/m3 = 1.92kN/m

Slab weight

= thickness X concrete density

=0.15m X 24kN/m3 = 3.6kN/m

2

Column self weight

= beam size X height X concrete density

= 0.3m X 0.4m X 3m X 24kN/m3 = 8.64kN

Page 96: Building Structure Project 2 report

Building Structure 96 Project 2

Dead load acting on column H2

Roof

level

Slabs (Flat

roof)

11.55m2 (ttl slab area) X 3.6kN/m

2 41.58kN

Roof beams (2.25m X 2.4kN/m) + (4.45m X

1.92kN/m)

13.94kN

1st floor Wall self

weight

6.7m (ttl wall length) X 8.55kN/m 57.28kN

Slabs 11.55 m2 (ttl slab area) X 3.6kN/m

2 41.58kN

Beams (2.25m X 2.4kN/m) + (4.45m X

1.92kN/m)

13.94kN

Column - 8.64kN

Grd

floor Wall self

weight

5.5m (ttl wall length) X 8.55kN/m 47.03kN

Slabs 11.55m2 (ttl slab area) X 3.6kN/m

2 41.58kN

Beams (2.25m X 2.4kN/m) + (4.45m X

1.92kN/m)

13.94kN

Column - 8.64kN

Total dead load 288.16kN

Apply 1.4 dead load factor 403.42kN

Live load acting on column H2

1st floor Residential 11.55m

2 (ttl slab area) X 1.5kN/m

2 17.32kN

Grd

floor Residential 11.55m2 (ttl slab area) X 1.5kN/m

2 17.32kN

Total live load 34.64kN

Apply 1.6 Live load factor 55.44kN

Ultimate load on column H2 = 458.86kN

Page 97: Building Structure Project 2 report

Building Structure 97 Project 2

Tributary area method load analysis on column H3

Height of floors = 3m

Brick wall weight

=height X thickness X brick density

=3.0m X 0.15m X 19kN/m3 = 8.55kN/m

Beam self weight

I. (GF) H/2-3, E-H/3 (1F) H/2-3, E-H/3 (RF) H/2-3, E-H/3

= beam size (main beam type 2) X concrete density

= (0.5m X 0.2m) X 24kN/m3 = 2.40kN/m

II. (GF) H/3-4 (1F) H/3-4 (RF) H/3-4

= beam size (sub beam type 1) X concrete density

= (0.4m X 0.2m) X 24kN/m3 = 1.92kN/m

III. (GF) G/3-4 (1F) G/2-3

= beam size (sub beam type 2) X concrete density

= (0.3m X 0.2m) X 24kN/m3 = 1.44kN/m

Slab weight

= thickness X concrete density

=0.15m X 24kN/m3 = 3.6kN/m

2

Column self weight

= beam size X height X concrete density

= 0.3m X 0.4m X 3m X 24kN/m3 = 8.64kN

Page 98: Building Structure Project 2 report

Building Structure 98 Project 2

Dead load acting on column H3

Roof

level

Slabs (Flat

roof)

19.125m2 (ttl slab area) X 3.6kN/m

2 68.85kN

Roof beams (6.6m X 2.4kN/m) + (2m X

1.92kN/m)

19.68kN

1st floor Wall self

weight

9.5m (ttl wall length) X 8.55kN/m 81.22kN

Slabs 19.125m2 (ttl slab area) X 3.6kN/m

2 68.85kN

Beams (6.6m X 2.4kN/m) + (2m X

1.92kN/m) + (2.25m X 1.44kN/m)

22.92kN

Column - 8.64kN

Grd

floor Wall self

weight

8.6m (ttl wall length) X 8.55kN/m 73.53kN

Slabs 19.125m2 (ttl slab area) X 3.6kN/m

2 68.85kN

Beams (6.6m X 2.4kN/m) + (2m X

1.92kN/m) + (2m X 1.44KN/m)

22.56kN

Column - 8.64kN

Total dead load 443.74kN

Apply 1.4 dead load factor 621.24kN

Live load acting on column H3

1st floor Residential 19.125m

2 (ttl slab area) X 1.5kN/m

2 28.69kN

Grd

floor Residential 19.125m2 (ttl slab area) X 1.5kN/m

2 28.69kN

Total live load 57.37kN

Apply 1.6 Live load factor 91.8kN

Ultimate load on column H3 = 713.04kN

Page 99: Building Structure Project 2 report

Building Structure 99 Project 2

Efficiency of column N = 0.4fcuAc + 0.8 fyAsc

N = capacity of concrete

Fcu = concrete strength (N/mm2) = 30N/mm2

Ac = cross section of concrete column

fy = yield strength of steel (N/mm2) = 460N/mm2

Asc = steel content in a column

Ac = 300 x 400 = 120,000

Asc

= 2 % x 120,000 = 2,400

N = 0.4fcu

Ac + 0.8 f

yA

sc

= 0.4(30)(120000) + 0.8(460)(2400)

= 1440,000 + 883,200

= 2323200 N = 2323.2kN

300mm

400mm

For column C3 = 617.74kN (sustainable load) For column H2 = 458.86kN (sustainable load) For column H3 = 713.04kN (sustainable load)