Building presentation 10-8-12

66
Trends In Education – Buildings and Facilities Patrick Shannon Dean College of Business and Economics Boise State University October 9, 2012

Transcript of Building presentation 10-8-12

Page 1: Building presentation   10-8-12

Trends In Education – Buildings and Facilities

Patrick ShannonDean

College of Business and EconomicsBoise State University

October 9, 2012

Page 2: Building presentation   10-8-12

Reasons To Build New Facilities

• To Increase Capacity• To Modernize • To Increase Enrollment• To Attract New Faculty• To Support and Enhance Brand

112 AACSB Members Schools have completed or have new buildings or expansions in progress since 2010

Page 3: Building presentation   10-8-12

A Facility Can Impact Brand Image

Page 4: Building presentation   10-8-12

Some Dreams Do Come True

From Here

To Here

Page 5: Building presentation   10-8-12

65,000 sq feet (we used 45,000)Little student spaceHVAC ProblemsInadequate Classrooms (capacity, technology and layout)Centers spread around campus

Our Old Building

Page 6: Building presentation   10-8-12

Significant Milestones

2005 – New Building Location Boise State University

Master Plan

Linking the University and Idaho’s Business Community

Page 7: Building presentation   10-8-12

Building site

Western Gateway to Campus

Page 8: Building presentation   10-8-12

The previous western gateway to Boise State University.

Page 9: Building presentation   10-8-12

Significant Milestones 2006 – Project Budget Raised from $10 million to $35.5 million

2007 – Micron Technology Foundation – Lead Gift - $12.5 million$5 million match requirement by December 31, 2009

2008 – President Kustra Okays Bond Financing for $16 million

2008 – COBE Building Team Formed: Faculty – Staff – University Architect – Center Director – Students – DPW

2008 - AC Martin Company Hired to “Program the Building”

Programming:What - How Many - How Big - Constraints

Page 10: Building presentation   10-8-12

Top Level Programming Results from AC Martin

Our Own Analysis

Page 11: Building presentation   10-8-12

Programming Results – Blocking

Page 12: Building presentation   10-8-12

Programming Results – Lecture Hall

Page 13: Building presentation   10-8-12

Programming Results – Classroom lab

Page 14: Building presentation   10-8-12

Significant Milestones 2009 – Architect Selected

Hummel – Boise, Lead ArchitectsAnderson-Mason-Dale, DenverIntegrated Structures, Berkely

Page 15: Building presentation   10-8-12

The Design Process Fall 2009 – Fall 2011

Meetings – Meetings and more Meetings!Building Team Faculty, Staff, Advisory Board,

Student Advisory Council, University Administration ……..

Pattern Language Approach

Visited Other Buildings: U of Montana, U of Colorado, Denver U, Northern Arizona, U of Arizona, U of Oregon, U of Idaho

Page 16: Building presentation   10-8-12

42 Patterns Emerged

- Gateway Anchor- Family of Entrances

- Beautiful Light- A Place to Call Home

- Faculty Collaboration- …….

Page 17: Building presentation   10-8-12

Pattern 12 - Beautiful Light

Light affects us deeply. It can alter our moods, affect our productivity and energy levels but when inappropriate to task, either too bright or too dim or the wrong color, it can make the environment uncomfortable.

- Use natural light whenever possible to light interior spaces.- Nighttime illumination should be pleasing and useful.- Have flexible task lighting that can be adjusted by the user.

Page 18: Building presentation   10-8-12

Some “Beautiful Light” Outcomes

Page 19: Building presentation   10-8-12

The Design – An Early Sketch

Page 20: Building presentation   10-8-12
Page 21: Building presentation   10-8-12
Page 22: Building presentation   10-8-12
Page 23: Building presentation   10-8-12
Page 24: Building presentation   10-8-12
Page 25: Building presentation   10-8-12
Page 26: Building presentation   10-8-12
Page 27: Building presentation   10-8-12
Page 28: Building presentation   10-8-12

The Design – Later Renderings

Page 29: Building presentation   10-8-12

The Design – Later Renderings

Page 30: Building presentation   10-8-12

Significant Milestones Fall 2010 – Construction Company Selected - ESI

$28.5 million October 2010 – Groundbreaking

18 Month Build Schedule

May 1, 2012 - Finish

Page 31: Building presentation   10-8-12

November, 2010

Page 32: Building presentation   10-8-12
Page 33: Building presentation   10-8-12
Page 34: Building presentation   10-8-12
Page 35: Building presentation   10-8-12
Page 36: Building presentation   10-8-12
Page 37: Building presentation   10-8-12
Page 38: Building presentation   10-8-12
Page 39: Building presentation   10-8-12
Page 40: Building presentation   10-8-12
Page 41: Building presentation   10-8-12
Page 42: Building presentation   10-8-12
Page 43: Building presentation   10-8-12
Page 44: Building presentation   10-8-12
Page 45: Building presentation   10-8-12
Page 46: Building presentation   10-8-12

April, 2012

Page 47: Building presentation   10-8-12

August, 2012

Page 48: Building presentation   10-8-12
Page 49: Building presentation   10-8-12

26 Team Rooms

Page 50: Building presentation   10-8-12

Green Roof

Page 51: Building presentation   10-8-12
Page 52: Building presentation   10-8-12

Skaggs Hall of Learning250 Seats

Page 53: Building presentation   10-8-12

Ten Case Style Classroom(50 and 60 seat)

Page 54: Building presentation   10-8-12

Flexible Style Classrooms40 Seat

Page 55: Building presentation   10-8-12

Technology Classroom

Page 56: Building presentation   10-8-12

Boardroom Terrace

Executive Education Terrace

Page 57: Building presentation   10-8-12

8 Conference/Seminar Rooms

Page 58: Building presentation   10-8-12

Board Room

Page 59: Building presentation   10-8-12

Home Base

Page 60: Building presentation   10-8-12
Page 61: Building presentation   10-8-12

Financial Trading Room

Page 62: Building presentation   10-8-12

Cafe

Page 63: Building presentation   10-8-12

Commons

Page 64: Building presentation   10-8-12
Page 65: Building presentation   10-8-12

Summary Information

119,000 square feet - Geothermal Heating - Green RoofTotal Project - $35.5 million (construction, technology,

furnishings, architects, etc.)1,023 Donors – $20.3 million ($15.2 million bonded)3,400 students75 full-time faculty - 6 Centers16 classrooms - 26 team rooms - 3 Interview Rooms3x Wireless CoverageImagination Lab - Technology Lab – Financial Trading RoomFaculty Collaboration AreasGA and Adjunct faculty offices

Page 66: Building presentation   10-8-12

Our Dream Came True!