BUILDING ELECTRICAL SERVICES DESIGN FOR...
Transcript of BUILDING ELECTRICAL SERVICES DESIGN FOR...
BUILDING ELECTRICALSERVICES DESIGN FOR HOSTEL
ALONG NYERERE ROAD
Presented By : OELE O. COLLINS ERICKRegistration Number : F17/1999/2005Supervisor: Dr. N. AbunguExaminer: Mr. Dharmadhikary
PROJECT INDEX: PRJ 095
Objectives
• Lighting design• Power points layout design• Cables sizing• Power back-up system• Protection systems design• Power factor correction
Lighting Design
• Lighting design was done using the lumenmethod.
• For the lounge area within one hostel room :
Illuminance, E = 150 luxArea, A = (5.8m * 2.821m) = 16.36 m2
Flux of one light fitting, F = 2800 lumensUtility Factor, UF = 0.39Maintenance Factor, MF = 0.80
Power Points
It consisted of :
• Twin socket power outlets- rated 13 A- connected in a ring circuit- three pins for line, neutral and earth cables
• Kitchen Unit
• Three phase isolators
- Lifts
Design Analysis
Using a worst case scenario of :
• 100 Watts for a single light fitting
• 1,000 Watts for a twin socket power outlet
Floor Total
load(Watts)
20% future load growth
factored in total load(Watts)
Lower 21,100 25,320
Upper ground 52,200 62,640
First 52,200 62,640
Second 52,200 62,640
Third 52,200 62,640
Attic 12,700 15,240
TOTAL 242,600 291,120
Summary for All Single-Phase Loads
Floor Total Current
drawn(Amps)
No. of CUs
Lower 105.5 2
Upper ground 261.0 3
First 261.0 3
Second 261.0 3
Third 261.0 3
Attic 63.5 1
TOTAL No. of Consumer units 15 CUs
Summary for All Total Currents Drawn
Consumer Unit Way Assignment• Circuit and way on CU
= UGF 1.1• Total load(watts)
= 900• Total current (amps)
= (900W/240V) = 3.75• MCB size
= 6A• Cable size(mm2 )
= 1.5
Load BalancingPhase Red Yellow Blue
Total Single-Phase Loads
(Watts)
81,933.36 80,033.36 80,633.36
Total Three-Phase Loads
(Watts)
66,000.00 66,000.00 66,000.00
TotalBalanced
Loads (Watts)
147,933.36 146,033.36 146,633.36
Current(Amps)
456.169 448.252 450.752
Sample Distribution Board, DB ‘B’ CableSizing
• Length of cable connecting DB ‘B’ at the atticfloor to the switchboard = 20m
• Current used for sizing the cable = 180 Amps.• Allowing for a maximum of 1.5% design
voltage drop on this cable• 0.3643% voltage drop is less than 1.5%• The 95mm2 cable is appropriate.
Power Back-Up Generator Size• Total hostel load = 308,600.08 Watts
• Applying 15 % future load growth= 308,600.08 * 1.15 = 354.89 Kilowatts
• Total hostel load in kVA with future load growthfactored in:
= 443.6125 kVA
• A 450 kVA, 50 Hz VOLVO generator size is chosen
Sample Discrimination Between CU UGF 1 and DB ‘A’
• Consumer unit= UGF1
• Distribution board feeding the CU= DB ‘A’
• Cable current capacity (Amps)= 79
• Cable current (Amps)= 70.98
• Rating of largest MCB in CU (Amps)= 20
• Fault current (Amps)= 769.29
• Rating of G FRAME MCCB Upstream in DB (Amps)= 100
Power Factor Correction
Cos-1 0.65 = 49.46˚
Cos-1 0.9 = 25.84˚
Apparent power (S)=327.89 kVA
Actual (REAL) power load consumption = kVA× cos ∅=327.89×0.65 = 213.1285 kW
Reactive power aftercorrection=213.1285 tan 25.84`=103.21 kVAR
kVAR before power factorcorrection=327.89×sin49.46 = 249.18 kVAR
Capacitor bank = 249.18
-103.21 =145.97 kVAR
Conclusions
• An appropriate lighting scheme anddistribution system layout was achieved.
• Various sizing of cables were discussed• Overload and short circuit protections were
provided for.• Power back-up generator was put in place
and its capacity determined.
Recommendations and Future Work
• Software for building electrical servicesdesigns.
-Computer programs and macrosfor mathematical computations
• A bill of quantities to estimate the cost• Earth Faults analysis