BUILDING DESIGN BDC MEETING #7

Airport Heights Elementary School March 6, 2014

BUILDING DESIGN BDC MEETING #7

Airport Heights Elementary School March 6, 2014

McCool Carlson GreenArchitects

AnchorageSchool District

Page 2: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

INTRODUCTIONS• ASD Management• Design Team• Building Design

Committee (BDC)

Page 3: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

AGENDA• Process Overview• Master Plan Review

• Building Assessment• Educational Specification• Learning Signature• Site Analysis• Site Plan• Building Plan• Massing/Section Concepts

• Next Steps

Page 4: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

DESIGN PROCESS• Schematic Design

• Master Plan Confirmation• Space Development• Massing/Section Concepts• Exterior Design• Interior Design• Engineering Systems

• Design Development• Construction Documents• Bidding• Construction

Page 5: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

PROJECT SCHEDULE• March 6: BDC #7 Restart• March 18: BDC #8• March 27&28: Focus Groups (pending)• April 1: Bonds Pass! (if not, project is on hold)• April 8: BDC #9• April 22: BDC #10• June 1: Schematic Design Submittal• June 16: School Board Approval• September 1: Design Development Submittal• December 31: Construction Documents Submittal• January 2015: Bidding• May 2015 – July 2016: Construction• August 2016: Your in the new school! (Provided Bonds Pass)

Page 6: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

PROJECT GOALS & OBJECTIVES• Support Great

Teaching & Learning• Community Oriented• Sustainable• Flexible• Highly Functional• Safe & Secure• Fit School Culture• Maximize Value

Page 7: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

LEARNING SIGNATURE

Page 8: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

FACILITY ASSESSMENT

• Building envelope is under‐insulated • Accessibility code violations • Worn interior finishes and furniture• Structural systems deficiencies• Aging Sprinkler, Domestic Water and Plumbing• Inefficient Heating and ventilation• Kitchen ventilation and food service equipment replacement• Comprehensive electrical systems upgrades • Outdated AV & IT systems / learning technology• Asbestos‐containing materials abatement

Page 9: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

PROGRAM AREA DEFICIENCIES

• Administration• Multipurpose Room• Food Service and Receiving• Music• Art• Kindergarten• Special Programs

Page 10: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

EXISTING SITE

Page 11: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

SITE MASTER PLAN

Page 12: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

EXISTING FLOOR PLAN

Page 13: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

BUILDING MASTER PLAN

Page 14: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

BUILDING MASTER PLAN

Page 15: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

MASSING / SECTION CONCEPTS

Page 16: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

MASSING / SECTION CONCEPTS

Page 17: BUILDING DESIGN BDC MEETING #7 - mcgalaska.commcgalaska.com/wp-content/uploads/2015/02/BDC7... · • Building envelope is under‐insulated • Accessibility code violations •

Airport Heights ES | Schematic Design | McCool Carlson GreenArchitects

NEXT STEPS

• Site Plan Refinement• Exterior Design• Space Development