BUILDING CONSTRUCTION 1 CONSTRUCTION ACTIVITY AND PROCESS MR. BRUCE LEE XIA SHENG EVELYN PAUL 0311619

description

This assignment was done using Revit. This is a report of possible construction process in constructing a 3 storey house.

Transcript of Building Construction 1 - Final Project

  • 1. BUILDING CONSTRUCTION 1 CONSTRUCTION ACTIVITY AND PROCESS MR. BRUCE LEE XIA SHENG EVELYN PAUL 0311619

2. Week 1 Construction Activity 1: SETTING OUT DURATION: 8 Days EQUIPMENTS: 1. Backhoe 2. Bulldozer 3. Excavator SKILLED WORKERS: 1. 2 Construction Supervisors 2. 3 Equipment Operators 3. 1 Excavation Foreman 4. 1 Ground Leveling Staff 5. 3 Contractors 6. 1 Plumber 7. 1 Electrician 8. 1 Carpenter TECHNICAL INFORMATION: Before earthworks, the planned building is set out. Building profiles and the use of string lines to mark the outside perimeters of the construction and any other critical measurements. One of the most important things in setting out is position and accuracy in which the hurdles are placed . Excavations will proceed and plumbers will be able to install the underground plumbing. Electricians will be able to install the meter box and any pre-wires necessary. Carpenters may also use these set out lines to begin framing on the construction. Levels have to be set out based on benchmarks in the surroundings. Geometric surveying measures the difference in height of a horizontally set up level from a benchmark with levelling staff held vertically. 3. Week 2 Construction Activity 1: Earthwork DURATION: 2 Days EQUIPMENTS: 1. Backhoe 2. Bulldozer 3. Excavator SKILLED WORKERS: 1. 3 Heavy Equipment Operator 2. 2 Construction Supervisor 3. 1 Excavation Foreman 4. 3 General Workers TECHNICAL INFORMATION: The earth may be moved to another location and formed into a desired shape for a purpose. Much of earthworks involves machine excavation and fill or backfill. Preservation of topsoil, slope protection, soil formation, soil loosening and soil improvement take part of the earthwork. Preparing holes for the piles. 4. Week 3 Construction Activity 1: Piling DURATION: 4 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements EQUIPMENTS: 1. 1 Hydraulic hammer 2. 1 Concrete vibrator 3. 1 Bar bending machine SKILLED WORKERS: 1. 1 Pile Driver Operator 2. 2 Carpenters 3. 2 Bar Benders 4. 3 Construction Workers TECHNICAL INFORMATION: According to the location of the piles in the ground reinforced concrete piles are driven to transfer the load-bearing from the building through the weak ground to the load bearing ground below. 5. Week 3 Construction Activity 2: Pile Cap DUARTION: 4 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber formwork EQUIPMENT: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKER: 1. 2 Carpenters 2. 2 Bar Benders 3. 5 Construction workers TECHNICAL INFORMATION: After driving piles, reinforced concrete pile caps joins the head of the cluster of the piles in order to distribute the load from a column among the piles. The framework is installed and reinforced cage is also installed in the framework. The mold is filled with the concrete. The framework is removed after. 6. Week 7 Construction Activity 1: Stump DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcement 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 1 Bar Bender 3. 3 Construction Workers TECHNICAL INFORMATION: The stumps are installed between the pile cap and column. The framework is installed and rebar is also installed in the framework. The mold is filled with the concrete. The framework is removed after. 7. Week 9 Construction Activity 1: Ground Beam DURATION: 7 Days MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Bar Bending Machine 2. 1 Concrete Vibrator SKILLED WORKERS: 1. 2 Bar Benders 2. 3 Carpenters 3. 4 Construction Workers TECHNICAL INFORMATION: Ground beams are mostly formed and placed along with the slab they support and to distribute the tension forces. 8. Week 9 Construction Activity 2: Ground Floor Columns DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Bar Bending Machines 2. 1 Concrete Vibrator 3. Hammers 4. Nails SKILLED WORKERS: 1. 2 Bar Benders 2. 3 Carpenters 3. 4 Construction Workers TECHNICAL INFORMATION: According to the location of the column plans, reinforced concrete fills the plywood formwork placed. 9. Week 10 Construction Activity 1: Ground Floor Columns DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine 3. Hammers 4. Nails SKILLED WORKERS: 1. 2 Carpenters 2. 3 Construction Workers 3. 1 Bar Bender TECHNICAL INFORMATION: According to the location of the column plans, reinforced concrete fills the plywood formwork placed. 10. Week 11 Construction Activity 1:First Floor Beam DURATION: 7 Days MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 3 Construction Workers TECHNICAL INFORMATION: The beams are mostly formed and placed along with the slabs they support to distribute the tension forces. 11. Week 11 Construction Activity 1:First Floor Slab DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 4 Construction Workers TECHNICAL INFORMATION: Concrete slab is a plate structure reinforced to span either a structural bay. 12. Week 13 Construction Activity 1: First Floor Columns DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 1 Bar Bender 3. 4 Construction Workers TECHNICAL INFORMATION: According to the location of the column plans, reinforced concrete fills the plywood formwork placed. 13. Week 14 Construction Activity 1: First Floor Columns DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 1 Bar Bender 3. 3 Construction Workers TECHNICAL INFORMATION: According to the location of the column plans, reinforced concrete fills the plywood formwork placed. 14. Week 15 Construction Activity 1: Second Floor Beam DURATION: 7 Days MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 4 Construction Workers TECHNICAL INFORMATION: The beams are mostly formed and placed along with the slab they support and to distribute the tension forces throughout the building. 15. Week 15 Construction Activity 2: Second Floor Slab DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar benders 3. 4 Construction Workers TECHNICAL INFORMATION: Concrete slab is a plate structure reinforced to span either a structural bay. 16. Week 17 Construction Activity 1: Ground Floor Slab DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 4 Construction Workers TECHNICAL INFORMATION: Concrete slab is a plate structure reinforced to span either a structural bay. 17. Week 19 Construction Activity 1: First Floor Columns DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenter 2. 1 Bar Bender 3. 3 Construction Workers TECHNICAL INFORMATION: According to the location of the column plans, reinforced concrete fills the plywood formwork placed. 18. Week 21 Construction Activity 1: Ground Floor Staircase DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 1 Bar Bender 3. 3 Construction Workers TECHNICAL INFORMATION: After the formwork is installed, the reinforced bars join the starter bars then the concrete is poured to fill up the formwork which will be removed after the concrete is cured. 19. Week 22 Construction Activity 1: First Floor Staircase DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 1 Bar Bender 3. 3 Construction Worker TECHNICAL INFORMATION: After the formwork is installed, the reinforced bars join the starter bars then the concrete is poured to fill up the formwork which will be removed after the concrete is cured. 20. Week 23 Construction Activity 1: Roof Beam DURATION: 7 Days MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending Machine SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 3 Construction Workers TECHNICAL INFORMATION: The beams are mostly formed and placed along with the slab they support and to distribute the tension forces. 21. Week 24 Construction Activity 1: Roof Slab DURATION: 2 Weeks MATERIALS: 1. Concrete Grade 30 2. Reinforcements 3. Timber Formwork EQUIPMENTS: 1. 1 Concrete Vibrator 2. 1 Bar Bending SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 4 Construction Workers TECHNICAL INFORMATION: Concrete slab is a plate structure reinforced to span either a structural bay. The structure of a flat roof may consist of reinforced concrete slabs, timber or steel beams decking and wood or steel joints and sheathing. The roof slabs may be supported by reinforced concrete columns, reinforced concrete frames or bearing walls of reinforced concrete. 22. Week 26 Construction Activity 1: Ground Floor Exterior Brickwork DURATION: 3 Weeks MATERIALS: 1. Common Clay Bricks 2. Mortar 3. Brickwork Reinforcement Mesh (Ex-Mesh) EQUIPMENTS: 1. Brick Trowels 2. Leveling Instruments 3. Bucket SKILLED WORKERS: 1. 1 Carpenter 2. 4 Construction Workers TECHNICAL INFORMATION: Except for the spaces for the curtain walls, windows and doors, exterior brick walls are constructed. Ex-meshes are placed on every fifth brick joint to strengthen. 23. Week 27 Construction Activity 1: First Floor Exterior Brickwork DURATION: 3 Weeks MATERIALS: 1. Common Clay Brick 2. Mortar 3. Brickwork Reinforcement Mesh (Ex-Mesh) EQUIPMENTS: 1. Brick Trowels 2. Leveling Instrument 3. Bucket SKILLED WORKERS: 1. 1 Carpenter 2. 4 General Workers TECHNICAL INFORMATION: Except for the spaces for the curtain walls, windows and doors, exterior brick walls are constructed. Ex-meshes are placed on every fifth brick joint to strengthen. 24. Week 28 Construction Activity 1: Second Floor Exterior Brickwork DURATION: 3 Weeks MATERIALS: 1. Common Clay Brick 2. Mortar 3. Brickwork Reinforcements Mesh (Ex-Mesh) EQUIPMENTS: 1. Brick Trowels 2. Leveling Instruments 3. Bucket SKILLED WORKERS: 1. 1 Carpenter 2. 4 Construction Workers TECHNICAL INFORMATION: Except for the spaces for the curtain walls, windows and doors, exterior brick walls are constructed. Ex-meshes are placed on every fifth brick joint to strengthen. 25. Week 29 Construction Activity 1: Interior Brickwork DURATION: 3 Weeks MATERIALS: 1. Common Clay Brick 2. Mortar 3. Brickwork Reinforcement Mesh (Ex- Mesh) EQUIPMENTS: 1. Brick Trowels 2. Leveling Instruments 3. Bucket SKILLED WORKERS: 1. 1 Carpenter 2. 4 General Workers TECHNICAL INFORMATION: Except for the spaces for the curtain walls, windows and doors, exterior brick walls are constructed. Ex-meshes are placed on every fifth brick joint to strengthen. GROUND FLOOR 26. FIRST FLOOR SECOND FLOOR 27. Week 32 Construction Activity 1: Roof Tiling DURATION: 3 Days MATERIALS: 1. 1 Concrete Grade 30 2. Roof Tiles EQUIPMENTS: 1. Mortar 2. Trowel 3. Mesh Tape 4. Sealer SKILLED WORKERS: 1. 2 Carpenters 2. 2 Bar Benders 3. 4 Construction Workers TECHNICAL INFORMATION: Concrete slab is a plate structure reinforced to span either a structural bay. The structure of a flat roof may consist of reinforced concrete slabs, timber or steel beams decking and wood or steel joints and sheathing. The roof slabs may be supported by reinforced concrete columns, reinforced concrete frames or bearing walls of reinforced concrete. 28. Week 33 Construction Activity 1: Installation of the windows and doors frame DURATION: 11 Days MATERIALS: 1. Aluminum 2. Timber EQUIPMENTS: 1. Hammers 2. Nails 3. Leveling Instruments SKILLED WORKERS: 1. 3 Construction Workers TECHNICAL INFORMATION: The frames of windows and doors are installed o the space prepared after the brickwork. Week 35 Construction Activity 1: Plumbing and electrical DURATION: 4 Weeks MATERIALS: 1. Pipes 2. Wires EQUIPMENTS: 1. Pliers 2. Cutters 3. Sealers SKILLED WORKERS: 1. 1 Plumber 2. 1 Electrical Engineer 3. 2 Carpenters 4. 3 Construction Workers TECHNICAL INFORMATION: The pipes and wires are installed for the water and electricity supply system. 29. Week 49 Construction Activity 1: Exterior and Interior walls finishing DURATION: 6 Weeks MATERIALS: 1. Primer 2. Paint 3. Wall Plaster EQUIPMENTS: 1. Paint Brushes 2. Rollers 3. Ladders 4. Steel Wool SKILLED WORKERS: 1. 2 Carpenters 2. 4 Construction Workers TECHNICAL INFORMATION: Painting on the exterior and interior for both the protection and aesthetic purpose. 30. Week 45 Construction Activity 1: Installation of Door panels DURATION: 7 Days MATERIALS: 1. Wooden Door Panels 2. Hinge EQUIPMENTS: 1. Screw Drivers 2. Sealers SKILLED WORKERS: 1. 4 Construction Workers TECHNICAL INFORMATION: The wooden door panels are installed on the prepared space with the frame. Week 46 Construction Activity 1: Installation of Curtain walls and glass panel DURATION: 2 Weeks MATERIALS: 1. Steel Mullions 2. Sealant 3. Screws EQUIPMENTS: 1. Screw Drivers 2. Sealers SKILLED WORKERS: 1. 4 Construction Workers TECHNICAL INFORMATION: Curtain wall panel and glass panel are installed on the prepared space with the frame. The mullions are installed on the curtain walls after. 31. Week 47 Construction Activity 1: Installation of glass sliding doors DURATION: 2 Weeks MATERIALS: 1. Glass panels 2. Sealant EQUIPMENTS: 1. Sealer SKILLED WORKERS: 1. 3 Construction Workers TECHNICAL INFORMATION: Glass panels are installed on the prepared space with the frame. Week 59 Construction Activity 1: Installation of staircase railing DURATION: 3 Days MATERIALS: 1. Glass Panels 2. Sealant 3. Steel Rail 4. Screws EQUIPMENTS: 1. Sealer 2. Screw Driver SKILLED WORKERS: 1. 2 Construction Workers TECHNICAL INFORMATION: The steel railing and glass panels are installed on the staircase. 32. Week 50 Construction Activity 1: Floor tile and wooden finishing DURATION: 2 Weeks MATERIALS: 1. Ceramic Tiles 2. Solid Timber Flooring 3. Porcelain Tiles EQUIPMENTS: 5. Mortar 6. Trowel 7. Mesh Tape 8. Sealer SKILLED WORKERS: 1. 2 Construction Workers TECHNICAL INFORMATION: The tile finishing for the living room, kitchen, balcony and bathroom and wooden finishing for the rooms are installed. 33. Week 52 Construction Activity 1: Installation of Window Panels DURATION: 7 Days MATERIALS: 3. Wooden window 4. Hinge EQUIPMENTS: 3. Screw Drivers 4. Sealers SKILLED WORKERS: 2. 4 Construction Workers TECHNICAL INFORMATION: The wooden window panels are installed on the prepared space with the frame. 34. Week 53 Construction Activity 1: Installation of fixed furniture and utilities DURATION: 2 Weeks MATERIALS: 1. Medium and Soft Woods 2. Varnish 3. Glue 4. Water Heater 5. Paint 6. Light Bulbs 7. Fixed Electrical Appliances EQUIPMENTS: 1. Hammers 2. Nails 3. Cutters 4. Table Saw SKILLED WORKERS: 1. 2 Construction Workers 2. 1 Electrician TECHNICAL INFORMATION: The fixed furniture such as lighting , telephone, door bell, fan, bath tub, basin, toilet bowl, cabinet and etc are installed at the end.