Building Commissioning
Ron Major
Resource Conservation Manager
![Page 2: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/2.jpg)
What will be covered?
Definitions of commissioning, retro-commissioning and re-commissioning
New building commissioning
Retro-Commissioning
![Page 3: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/3.jpg)
What will be covered?
Commissioning and LEED
Commissioning and the Washington Sustainable Schools Protocol
![Page 4: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/4.jpg)
What is building commissioning?
ASHRAE definition; Commissioning is the process of ensuring that systems are designed, installed, functionally tested, and capable of being operated and maintained to perform in conformity with the design intent.
![Page 5: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/5.jpg)
What is building commissioning?
Washington State Department of General Administration’s definition; Building Commissioning is a systematic and documented process of ensuring that the owner’s operational needs are met, building systems perform efficiently, and building operators are properly trained.
![Page 6: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/6.jpg)
Definitions
Building commissioning typically involves four distinct “phases” for new construction.
Pre-designDesignConstruction Warranty
![Page 7: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/7.jpg)
Definitions
Re-commissioning; is applied to an existing building that was originally commissioned.
Retro-commissioning; is applied to an existing building that was never commissioned.
![Page 8: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/8.jpg)
What is the goal of building commissioning?
To deliver a facility that operates as it was intended.
To provide a facility that meets the needs of the building owner and occupants.
To provide appropriate training for facility operators on the operation and maintenance of the building systems.
![Page 9: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/9.jpg)
When should the building commissioning process start?
Building commissioning can be started near the end of construction. (good)
Building commissioning can be started at the start of construction. (better)
Building commissioning can be started during schematic design. (best)
![Page 10: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/10.jpg)
When should the building commissioning process start?
Benefits of early involvement – Design review. Better building commissioning
specifications. Clear building commissioning
expectations. Better bids.
![Page 11: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/11.jpg)
When should the building commissioning process start?
Early involvement by the commissioning agent may not carry a cost premium. It will reduce project design problems and will introduce building commissioning expectations early.
![Page 12: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/12.jpg)
Develop building commissioning scope of work
Before meeting with the commissioning agent develop a draft commissioning scope of work.
Start by asking the facility owner and operators what problems they encountered on previous construction projects.
![Page 13: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/13.jpg)
Develop building commissioning scope of work
Do not limit your commissioning to just HVAC and controls. Envelope, lighting controls, security, lab spaces, medical gas systems, and other complex systems should be considered.
![Page 14: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/14.jpg)
Develop building commissioning scope of work
Then use the Commissioning Guidelines for systems to be commissioned.HVAC systemsAir distribution systemsPlumbing and piping systemsHeating and cooling plant equipmentControl systemsElectrical systemsMetering strategy and equipment
![Page 15: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/15.jpg)
What should be budgeted for building commissioning?
The following rules of thumb can help a client budget for building commissioning services.
$1.00 to $2.00 per square foot depending on the complexity, size and location of the building.
1.0 to 2.5% of the total construction cost.
![Page 16: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/16.jpg)
Cost savings for building commissioning
8% - 20% reduction in operating costs for a building that is commissioned.
1.5 – 5.5 year simple payback on commissioning. Based on:fewer change orders. lower energy usage.reduced operational problems.
![Page 17: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/17.jpg)
What does building commissioning involve?
Verifying and documenting building systems’ performance through all phases of a project from concept to occupancy.
Testing HVAC systems’ performance to ensure that they meet the needs of the building throughout the full range of operating parameters that may be encountered.
![Page 18: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/18.jpg)
Expected Deliverables
1. Commissioning plan and schedule detailing each step of the commissioning process and each team member’s role and responsibilities.
2. A diagnostic and functional test plan detailing how each test will be accomplished and noting expected performance parameters.
![Page 19: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/19.jpg)
Expected Deliverables
3. A list of findings and potential improvements identified by the commissioning provider for design phase and construction phase activities
4. A training plan recommending specific topics and training schedules
![Page 20: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/20.jpg)
Expected Deliverables
5. At the completion of the project, a final commissioning report detailing all of the commissioning provider’s findings and recommendations including copies of all functional performance testing data.
![Page 21: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/21.jpg)
Expected Deliverables
6. A systems concepts and operations manual which gives a description of each system with specific information about how to optimally operate and control the system during all modes of operation such as during fire, power outage, shutdown, etc., including special instructions for energy efficient operation and re-commissioning.
![Page 22: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/22.jpg)
Expected Deliverables
7. Energy savings and implementation cost estimates for recommendations developed in the process are also deliverables for retro-commissioning projects.
![Page 23: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/23.jpg)
Retro-commissioning
Is a systematic, documented process that identifies low cost O&M improvements in an existing building and brings that building up to the design intentions of its current usage.
![Page 24: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/24.jpg)
What are the goals of retro-commissioning?
To identify and fix existing problems, such as indoor air quality.
To improve the energy efficiency of the building.
To provide a facility that meets the current needs of the building owner and occupants.
To provide training for facility operators on the operation and maintenance of the existing building systems.
![Page 25: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/25.jpg)
What is the cost of retro-commissioning?
$0.40 to $1.20 per square foot depending on the complexity, size, and location of the building. This includes the first phase and the second phase after corrections are
made.
General housekeeping done before commissioning is started can help reduce costs.
Assigning maintenance staff to assist the commissioning agent can also help reduce the cost while providing a good training opportunity.
![Page 26: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/26.jpg)
What does retro-commissioning involve?
Verifying and documenting the existing building systems’ performance.
Testing HVAC systems’ performance to ensure that they meet the current needs.
Identifying and recommending solutions to existing building problems.
![Page 27: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/27.jpg)
When to retro-commission
If the building has never been commissioned.
If the original usage of the building has changed.
If the building is experiencing:occupant comfort complaints. indoor air quality problems.higher energy costs.numerous operation and maintenance problems.
![Page 28: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/28.jpg)
Why use retro-commissioning?
Low first cost for the building owner. The cost for the first phase is typically in the $0.25 to $0.75 per square foot range.
The commissioning agent fully tests all of the systems.
Simple repairs can be done during the retro-commissioning investigation.
![Page 29: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/29.jpg)
Why use retro-commissioning?
To make sure the equipment is operating correctly.
To improve indoor air quality.
To reduce occupant complaints.
To increase occupant comfort.
To reduce energy and demand costs.
![Page 30: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/30.jpg)
Why use retro-commissioning?
The commissioning agent can subcontract and oversee the repairs.
The commissioning agent commissions the repairs after the work is completed to make sure the systems are working correctly.
The retro-commissioning process is fully documented.
![Page 31: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/31.jpg)
Developing the retro-commissioning scope of work
Ask the facility owner and operator what problems they are encountering.
Interview building staff to find out what problems they are experiencing.
Based upon what was learned, draft the retro-commissioning scope of work before meeting with the commissioning agent.
![Page 32: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/32.jpg)
Cost savings for retro-commissioning
5% - 20% reduction in annual operating costs.
1.5 – 7.5 year simple payback is typical.
This is based on:lower energy usage.reduced operational problems.improved occupant comfort.
![Page 33: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/33.jpg)
Selecting theright commissioning agent
It is important to select a commissioning agent that has hands on experience with controls and HVAC systems.
It is important to select a commissioning agent that has good troubleshooting and problem solving skills.
![Page 34: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/34.jpg)
How Does Commissioning fit into the LEED Version 2.2 Process?
There are two levels of building commissioning for the LEED process.The first is what is called Fundamental
Commissioning and it is a pre-requisite requirement for all LEED projects.
The second is Enhanced Commissioning and provides one point under energy and atmosphere credit number 3.
![Page 35: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/35.jpg)
LEED V2.2 Pre-Requisite Commissioning Requirements:
REQUIRED SYSTEMS: HVAC & controls, lighting controls, domestic water heating and any renewable energy systems
The project team must designate a specific individual as the commissioning authority (CA). This individual must be qualified. Projects larger than 50K SF project must be commissioned by a third party
![Page 36: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/36.jpg)
LEED V2.2 Pre-Requisite Commissioning Requirements:
The owner shall develop and CA shall review owner’s project requirements (OPR) document.
The A/E shall develop and CA shall review the basis of design (BOD) documents for the commissioned systems
![Page 37: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/37.jpg)
LEED V2.2 Pre-Requisite Commissioning Requirements:
The project documents must include the commissioning requirements (Specs)
A commissioning plan must be developed and implemented
The CA must verify the installation and functional performance of all commissioned systems
![Page 38: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/38.jpg)
LEED V2.2 Pre-Requisite Commissioning Requirements:
The CA must complete a final summary commissioning report
![Page 39: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/39.jpg)
LEED Enhanced Commissioning Requirements (EA Credit #3)
The CA must complete a review of the construction documents at approximately the 50% complete stage
The CA must complete a review of the contractors standard submittals related to commissioned systems
![Page 40: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/40.jpg)
LEED Enhanced Commissioning Requirements (EA Credit #3)
The CA must verify all specified training
The CA must develop a systems manual for all commissioned systems
The CA must review operation and performance of commissioned systems with the owner within 10 months after substantial completion
![Page 41: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/41.jpg)
Additional (Highly) Recommended Commissioning Scope
The CA meets with the project team to present preliminary Cx plan & discuss Cx contract scope of work and Cx related responsibilities of the entire project team
The CA conducts a control systems integration meeting
![Page 42: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/42.jpg)
Additional (Highly) Recommended Commissioning Scope
The CA conducts a pre-construction commissioning coordination meeting with the contractors
The CA makes periodic site visits during construction to review installation and witness contractor start-up routines
The CA conducts a “Lessons Learned” meeting after all Cx is complete
![Page 43: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/43.jpg)
Often Misunderstood LEED Commissioning Requirements
Owners Project Requirement (OPR) & Basis of Design (BOD)BOD based on OPRPrior to submittals for Fundamental
Commissioning Prior to design submittal for Enhanced
CommissioningDeveloping project onset maximizes
value
![Page 44: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/44.jpg)
Often Misunderstood LEED Commissioning Requirements
Design review intent and timingReview as early as possible after
the design is fully developed and documented, such that issues may be resolved as early as possible before the construction documents are finalized.
![Page 45: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/45.jpg)
Often Misunderstood LEED Commissioning Requirements
Enhanced Commissioning Credit Independent 3rd party requirement# 2, Design Review# 3, Contractor submittal review# 6, Post Cx review
All other Enhanced & Prerequisite requirements may be provided by an individual employed by design or CM firm, but not otherwise working on the project.
![Page 46: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/46.jpg)
Commissioning and the Washington Sustainable Schools Protocol
E4.0: Fundamental Commissioning: Required The design team and the school district shall comply with
completion requirements outlined in Section 1416 of Washington’s NREC and WAC 180-27-080 regarding:
Drawings Manuals System balancing Systems commissioning And in conformance with ESSB 5509, commissioning
shall be performed for projects over 5,000 s.f.
![Page 47: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/47.jpg)
Commissioning and the Washington Sustainable Schools Protocol
E4.1: Additional Commissioning Conduct a commissioning design review of the Owner’s Project
Requirements (OPR), Basis of Design (BOD), and design documents prior to mid-construction documents phase and back-check the review comments in the subsequent design submission.
Review contractor submittals applicable to systems being commissioned for compliance with OPR and BOD. This review shall be concurrent with A/E reviews and submitted to the design team and the owner.
Prepare a final commissioning report following the WSEC 2004 – Building Commissioning Final Report Guidelines available from NEEC and review with the school district, verifying that systems are operational to the OPR and BOD and work is completed.
![Page 48: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/48.jpg)
Commissioning and the Washington Sustainable Schools Protocol
Verify functional and maintenance training of O&M Staff, and verify that such training is completed in the Final Commissioning Report.
Verify that training of building occupants regarding optimal operation of commissioned systems they interface with has been completed.
Assure through contractual arrangements involvement by the CxA in reviewing building operation after one academic year of building use with O&M staff and occupants. Include a plan for resolving outstanding commissioning-related issues.
![Page 49: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/49.jpg)
A properly commissioned facility can result in
Fewer change orders during the construction process Fewer call-backs for warranty work Long-term tenant satisfaction Lower energy bills Avoided equipment replacement costs Improved profit margin for building owners Properly trained operational staff Operations and Maintenance manuals are compiled
correctly
![Page 50: Building Commissioning Ron Major Resource Conservation Manager.](https://reader035.fdocuments.us/reader035/viewer/2022062421/56649d205503460f949f5472/html5/thumbnails/50.jpg)
Building commissioning resources
GA’s Building Commissioning Program: www.ga.wa.gov/eas/bcx