BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San...

18
BUENA VISTA CORRIDOR (Frio Street to Santa Rosa Street) * PROJECT UPDATE * MARCH 2020 Dolorosa (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure repairs along Dolorosa (San Saba to Santa Rosa) through March 31, 2020. The right and partial left, eastbound lanes will be closed. To facilitate traffic, three lanes of traffic will remain open for motorists. These projects are being constructed in conjunction with the Buena Vista Street Corridor, a $2.5 million 2012 Bond Project. Additionally, pedestrian access will be maintained as necessary for key events. For ease of reference, a map is provided below.

Transcript of BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San...

Page 1: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

BUENA VISTA CORRIDOR (Frio Street to Santa Rosa Street) * PROJECT UPDATE * MARCH 2020

Dolorosa (San Saba to Santa Rosa) Sidewalk & Lane Closures

The contractor continues sidewalk infrastructure repairs along Dolorosa (San Saba to Santa Rosa) through March 31, 2020. The right and partial left, eastbound lanes will be closed. To facilitate traffic, three lanes of traffic will remain open for motorists. These projects are being constructed in conjunction with the Buena Vista Street Corridor, a $2.5 million 2012 Bond Project. Additionally, pedestrian access will be maintained as necessary for key events. For ease of reference, a map is provided below.

Page 2: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

Buena Vista (Pecos Street to Farmers Market Driveway)

Night Time Lane Closures On Monday March 30-31, 2020, Buena Vista (Pecos Street to Farmers Market Driveway), intermittent lane closures will occur overnight to allow for the complete milling and overlaying of the street under Interstate Highway 35.

Page 3: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

___________________________________

MARCH 2020 ACTIVITIES: • Northside Buena Vista (S. Leona to N. Pecos): The Hawk signal

is now operational for the public. • Northside Dolorosa (San Saba to Santa Rosa): Preparing for

final landscaping and tree installation. • Southside Dolorosa (San Saba to Santa Rosa): Electrical

conduit for lighting installed. Irrigation lines installed for trees. Concrete pier footings for pedestrian lighting completed. Pedestrian lighting installed. Formed and poured concrete sidewalks. Formed tree planter sections. Excavation of bus pad at street. Started forming concrete sidewalk ramp at San Saba & Dolorosa.

Page 4: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

PLANNED ACTIVITIES FOR THE NEXT 3+ WEEKS:

• Northside Buena Vista (S. Leona to N. Pecos): Clean up work. • Northside Dolorosa (San Saba to Santa Rosa): Preparing for

final landscaping and tree installation. • Southside Dolorosa (San Saba to Santa Rosa): Form and pour

concrete sidewalks. Form tree planter sections. Continue excavating bus pad at street and form and pour with concrete finish. Continue to form and pour concrete sidewalk and wheelchair ramp at San Saba & Dolorosa. Start forming pedestrian crossing island at S. Concho St.

• Please note: Crews will have traffic control devices adjacent to areas they will be working at. Please slow down at these areas while work is underway, thank you.

PROJECT SCOPE:

• Improve pedestrian connectivity on Buena Vista between Frio and Santa Rosa. Aesthetic and lighting enhancements will be added as appropriate and within available funding.

• Install HAWK signal at Buena Vista & S. Leona St.

Thank you San Antonio for your patience as we

improve your community!

Page 5: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

Forming sidewalk and tree planters on Southside Dolorosa

Page 6: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

Pouring concrete sidewalk on Southside Dolorosa

Page 7: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

New sidewalk on Southside Dolorosa

Page 8: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

New sidewalk and pedestrian lights on Southside Dolorosa

Page 9: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

Excavating for new bus pad on Southside Dolorosa

Page 10: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

Brick pavers, curb and pedestrian lighting on Northside

Dolorosa by La Margartia

Page 11: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

Brick pavers, curb and pedestrian lighting on Northside

Dolorosa by La Margartia

Page 12: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

Pedestrian crossing island on Northside Dolorosa

by La Margarita

Page 13: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

Pedestrian lights, brick pavers and curb

on Northside under IH-35

Page 14: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

New HAWK signal installed at Buena Vista & S. Leona

Page 15: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

New HAWK signal installed at Buena Vista & S. Leona

Page 16: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

Pedestrian lighting at Buena Vista by the UTSA parking lot

Page 17: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

New curb, sidewalk and wheel chair ramps at

Buena Vista & S. Leona northwest intersection

Page 18: BUENA VISTA CORRIDOR - UTSA Facilitiesfacilities.utsa.edu/wp-content/uploads/2020/03/... · (San Saba to Santa Rosa) Sidewalk & Lane Closures The contractor continues sidewalk infrastructure

New sidewalk on Buena Vista connecting to S. Frio

**PLEASE NOTE: ALL WORK IS SUBJECT TO FAVORABLE WEATHER CONDITIONS**

THANK YOU FOR YOUR PATIENCE AS WE IMPROVE YOUR COMMUNITY.

If you have questions about the project, please contact:

Joey Doctor

Capital Projects Officer | TCI - City of San Antonio 210.207.8415 | [email protected]

or www.sanantonio.gov/tci

Transportation & Capital Improvements (TCI) PO Box 839966

San Antonio, Texas 78283-3966 210-207-8022