MEMORANDUM TO: Finance and Administration Committee FROM: Kathy Fisher, Budget Manager (612-726-8158) SUBJECT: BUDGET VARIANCE REPORT APRIL 2018 DATE: May 25, 2018 Actual revenue and expenses have been compared to the budgeted amounts for April 2018. Below is a summary of the year-to-date activity and larger variances. Details are explained within the report. Operating Revenues are over budget $1,491,379 or 1.2%. Greater than Budget Concessions Strong Passenger Spending Passenger Services New Agreement Auto Rental CFCs Higher Number of Transactions Lower than Budget Parking Fewer Transactions Operating Expenses are over budget $2,134,513 or 3.8%. Greater than Budget Personnel Overtime/Double-time for Snow Events and Super Bowl Maintenance Snow Events Non-Operating Revenue and Expenses are under budget $2,135,000. Lower than Budget Other Non-Operating Revenue Interest Income Net Revenues Available for Designation total $61,034,142. F&A 6/4/2018 ITEM II A1 Page 1 of 5

Transcript of BUDGET VARIANCE REPORT APRIL 2018 - Granicus

Page 1: BUDGET VARIANCE REPORT APRIL 2018 - Granicus

MEMORANDUM

TO: Finance and Administration Committee

FROM: Kathy Fisher, Budget Manager (612-726-8158)

SUBJECT: BUDGET VARIANCE REPORT – APRIL 2018

DATE: May 25, 2018

Actual revenue and expenses have been compared to the budgeted amounts for April 2018. Below is a summary of the year-to-date activity and larger variances. Details are explained within the report. Operating Revenues are over budget $1,491,379 or 1.2%.

Greater than Budget

Concessions – Strong Passenger Spending

Passenger Services – New Agreement

Auto Rental CFCs – Higher Number of Transactions

Lower than Budget

Parking – Fewer Transactions Operating Expenses are over budget $2,134,513 or 3.8%. Greater than Budget

Personnel – Overtime/Double-time for Snow Events and Super Bowl

Maintenance – Snow Events Non-Operating Revenue and Expenses are under budget $2,135,000. Lower than Budget

Other Non-Operating Revenue – Interest Income Net Revenues Available for Designation total $61,034,142.

F&A 6/4/2018 ITEM II A1

Page 1 of 5

Page 2: BUDGET VARIANCE REPORT APRIL 2018 - Granicus

Metropolitan Airports Commission

April 2018 Budget Variance Analysis

Operating Revenue

($=000) 2017 Total

Year to Date Dollar % 2018

Actual Actual Budget Variance Variance Budget

OPERATING REVENUES

Airline Rates & Charges

Airline Agreement

Landing Fees 20,012$ 20,590$ 20,726$ (135)$ -0.7% 67,138$

Ramp Fees 2,469 2,447 2,495 (49) -2.0% 7,489

Airline R & R 1,502 1,556 1,557 (1) -0.1% 4,674

Terminal 1-Lindbergh - Rentals 12,405 13,309 13,186 123 0.9% 39,567

Terminal 1-Lindbergh - Other Rentals 2,108 1,968 1,839 129 7.0% 6,131

Concessions Rebate - - - - (17,367)

Total Airline Agreement 38,495 39,870 39,803 67 0.2% 107,632

Terminal 2-Humphrey Lobby Fees 5,633 5,651 5,740 (89) 0.0% 10,358

Terminal 2-Humphrey Other/Passenger Fees 1,371 1,343 1,444 (101) -7.0% 3,320

Total Airline Rates & Charges 45,499 46,864 46,987 (123) -0.3% 121,311

Concessions

Terminal/Other

Food & Beverage 6,683 7,418 6,749 669 9.9% 24,023

News 1,300 1,320 1,298 22 1.7% 4,879

Retail Stores 1,614 1,962 1,708 254 14.9% 5,407

Passenger Services 2,153 3,027 2,157 870 40.3% 6,431

Total Terminal/Other 11,751 13,728 11,912 1,816 15.2% 40,740

Parking/Ground Transportation

Parking 37,779 36,917 37,267 (350) -0.9% 101,628

Ground Transportation Fees 2,904 3,566 3,606 (40) -1.1% 11,477

Auto Rental-On Airport 5,863 5,858 5,960 (102) -1.7% 19,490

Total Parking/Ground Transportation 46,546 46,340 46,833 (493) -1.1% 132,595

Other Concessions 671 739 688 51 7.4% 2,160

Total Concessions 58,968 60,807 59,433 1,374 2.3% 175,495

Rentals/Fees

Buildings & Facilities 3,296 3,400 3,523 (122) -3.5% 11,072

Auto Rental CFCs 3,872 4,179 3,917 261 6.7% 21,850

Ground Rentals 3,601 3,655 3,612 43 1.2% 10,869

Reliever Airports 1,926 2,283 2,324 (41) -1.7% 8,035

Total Rentals/Fees 12,697 13,517 13,376 141 1.1% 51,826

Utilities and Other Revenue

Utilities 1,295 1,340 1,263 77 6.1% 4,867

GA/Airside Fees 1,095 1,367 1,304 63 4.8% 4,229

Maintenance, Cleaning, Distribution Fees 889 967 1,000 (33) -3.3% 4,122

Other Revenues 560 302 357 (54) -15.2% 1,824

Reimbursed Expense 305 768 721 47 6.5% 2,173

Total Utilities and Other Revenue 4,143 4,744 4,645 99 2.1% 17,214

Total Operating Revenue 121,307$ 125,933$ 124,442$ 1,491$ 1.2% 365,846$

Brackets ( ) Represent Revenue Items under Budget and Expense Items over Budget

2018

Year To Date

F&A 6/4/2018 ITEM II A1

Page 2 of 5

Page 3: BUDGET VARIANCE REPORT APRIL 2018 - Granicus

April 2018 Budget Variance Analysis

Operating Expenses

Non-Operating Revenues & Expenses

($=000) 2017 Total

Year to Date Dollar % 2018

Actual Actual Budget Variance Variance Budget

Total Operating Revenue 121,307$ 125,933$ 124,442$ 1,491$ 1.2% 365,846$

OPERATING EXPENSES

Personnel 24,190$ 28,508$ 26,948$ (1,560)$ -5.8% 88,222$

Administrative 765 760 784 24 3.1% 2,066

Professional Services 1,325 1,389 1,453 63 4.4% 7,050

Utilities 4,830 5,283 5,462 179 3.3% 19,696

Operating Services 5,103 7,926 8,187 261 3.2% 28,955

Maintenance 12,593 12,805 11,648 (1,156) -9.9% 38,514

Other 1,439 1,331 1,385 54 3.9% 4,494

Total Operating Expenses 50,245$ 58,002$ 55,868$ (2,135)$ -3.8% 188,997$

(excludes depreciation and noise amortization)

Net Operating Revenues 71,062$ 67,931$ 68,574$ (643)$ -0.9% 176,849$

NON-OPERATING REVENUE (EXPENSES)

($=000) 2017 Total

Year to Date Dollar % 2018

Actual Actual Budget Variance Variance Budget

Other Non-Operating Revenue

Interest Income 2,015$ -$ 2,145$ (2,145)$ -100.0% 6,436$

Self-Liquidating Income 1,551 1,631 1,631 - 0.0% 4,902

3,566 1,631 3,776 (2,145) 11,338

Debt Service

Short Term Financing (79) (254) (254) - 0.0% (2,426)

Bond Prinipal/Int-Operating Fund Transfer 0 - 0.0% (103,100)

Equip Financing Principal/Int Payments (2,031) (1,771) (1,771) - 0.0% (4,382)

(2,110) (2,025) (2,025) - (109,908)

Equipment

Capital Expenditures (352) (343) (353) 10 -2.8% (1,112)

Equipment Purchases (886) (2,099) (2,099) - 0.0% (10,088)

Equipment Financing 3,779 - - - 0.0% 3,465

2,541 (2,442) (2,452) 10 (7,735)

Other

Six Month Reserve Transfer (3,522) (4,113) (4,113) - 0.0% (4,113)

Interstate Settlement/Medicare D 57 52 52 - 0.0% 130

Gain (Loss) on Equipment & Other - - - - 0.0% -

(3,465) (4,061) (4,061) - (3,983)

Total Non-Operating Revenues (Expenses) 532$ (6,897)$ (4,762)$ (2,135)$ 44.8% (110,288)$

Net Revenues Available for Designation 71,594$ 61,034$ 63,812$ (2,778)$ -4.35% 66,561$

Brackets ( ) Represent Revenue Items under Budget and Expense Items over Budget

Year To Date

2018

Year To Date

2018

F&A 6/4/2018 ITEM II A1

Page 3 of 5

Page 4: BUDGET VARIANCE REPORT APRIL 2018 - Granicus

OPERATING REVENUE Operating Revenue for April year-to-date is $1,491,379 or 1.2% over budget. The greatest variances exist in the following categories: CONCESSIONS As shown in the following chart comparing year-over-year, Total Concessions in 2018 exceeds Total Concessions in previous years due to the new concession stores and additional passenger services. Total Concessions revenue for 2018 year-to-date is $60,806,953 which is $1,839,265 higher than 2017 year-to-date Concessions revenue.

$0

$3,000,000

$6,000,000

$9,000,000

$12,000,000

$15,000,000

$18,000,000

$21,000,000

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Total Concessions 2015

2016

2017

2018

Concessions year-to-date revenue is $1,373,883 or 2.3% higher than budget as shown in the below table.

Variance % Variance $

Passengers as of March

(includes non revenue -

year over year)

0.83% n/a

Food & Beverage 9.9% 669,418$

News 1.7% 21,774$

Retail Stores 14.9% 254,442$

Passenger Services 40.3% 870,100$

Parking -0.9% (350,308)$

Ground Transportation -1.1% (40,258)$

Auto Rental -1.7% (102,211)$

Other Concessions 7.4% 50,926$

Total Variance 2.3% 1,373,883$

April 2018 Year-to-Date

Concessio

ns

Food & Beverage and Retail Stores Food & Beverage is over budget $669,418 or 9.9% and Retail Stores is over budget $254,442 or 14.9% due to strong passenger spending in the new concessions, especially around Super Bowl LII.

F&A 6/4/2018 ITEM II A1

Page 4 of 5

Page 5: BUDGET VARIANCE REPORT APRIL 2018 - Granicus

Passenger Services Passenger Services is over budget $870,100 or 40.3%. The Distributed Antenna System (DAS) was upgraded by a wireless service provider to improve cell phone coverage throughout the MAC campus. The agreement was signed late in 2017 and was not included in the 2018 budget. Parking Parking is under budget $350,308 or 0.9% as long-term parking transactions are less than anticipated in the budget. RENTALS AND FEES Auto Rental CFCs Auto Rental CFCs is over budget 261,196 or 6.7% as this revenue source has a higher number of transactions than the budget anticipated.

OPERATING EXPENSES Operating expenses are over budget $2,134,513 or 3.8%. The greatest variances exist in the following areas: PERSONNEL Personnel is over budget $1,559,722 or 5.8% due to overtime and double-time exceeding the budget by $2,165,969 but is offset by staff vacancies. Snow events that occurred leading up to and during the Super Bowl and snow events through April resulted in a large amount of overtime/double-time to be used. Because of a higher than normal snowfall amount and timing of the snow events, the total 2018 snow removal overtime/double-time budget has been spent. The likely result will be an increase in airline rates and charges at year-end. Also contributing to the variance in overtime is a larger police presence needed before, during and after the Super Bowl. MAINTENANCE Maintenance is over budget $1,156,201 or 9.9%. Additional snow removal materials and equipment were needed for the snow events that occurred during the first part of the year.

NON-OPERATING REVENUE AND EXPENSES OTHER NON-OPERATING REVENUE Other Non-Operating Revenue is under budget $2,135,000 or 44.8%. A rise in interest rates causes the market value of MAC’s portfolio to drop which in turn lowers the interest earning on investments. With the recent rise in interest rates, the expected interest earnings have not occurred.

COMMITTEE ACTION REQUESTED: RECOMMEND TO THE FULL COMMISSION APPROVAL OF THE BUDGET VARIANCE REPORT AND AUTHORIZE EXPENDITURES IN THESE CATEGORIES UP TO THE BUDGETED OR FORECASTED BUDGET AMOUNTS.

F&A 6/4/2018 ITEM II A1

Page 5 of 5