Budget Outlook
description
Transcript of Budget Outlook
BudgetOutlook
Glen Crawford
P5 Meeting
Sep 24 2007
24 Sep 2007 HEP Budget FY08 Update for P5 2
DOE FY2008 Budget + Outyears
FY2008 brief review Outyears Inputs for P5
Revised DOE out-year budget scenarios Revised facility ops out-year projections Revised new project profiles (actual+ my guesses)
24 Sep 2007 HEP Budget FY08 Update for P5 3
FY2008: Status HEP FY 2008 Request is 4% above FY 2007 Appropriation
($782M vs $751M) House mark at President’s Request Senate mark at President’s Request +7M Both have interesting language on JDEM
Expect Continuing Resolution…for how long?
Out-year projections ambiguous (more on this later)
24 Sep 2007 HEP Budget FY08 Update for P5 4
HEP Long-term Trend20 yr. HEP Funding in FY08 Dollars (w/OMB Inflators)
0
1
2
3
4
5
6
7
8
9
10
90 95 00 05 08*
Fiscal Year
Fu
nd
ing
($10
0M)
Operating Equipment Construction/AIP, GPP
*President's Request
24 Sep 2007 HEP Budget FY08 Update for P5 5
HEP program in FY 2008
Overall HEP priorities in FY 2008: Tevatron and B-factory supported to run
Last year of B-factory Ops LHC support (Ops and Computing) up 9% as data
taking begins Core research program at the universities (+3%)
and laboratories (+2%) maintained New initiatives for the future of HEP (see next slide)
24 Sep 2007 HEP Budget FY08 Update for P5 6
Initiatives in FY08
Initiatives for the future of HEP: ILC R&D ($42M $60M)
SCRF infrastructure development continues More new neutrino experiments
Main Injector Neutrino Exp’t v-A (MINERvA) Tokai-to-Kamioka near detector (T2K)
Stage III Dark Energy experiment (DES) Investment in long-term accelerator R&D
increased +$5M
24 Sep 2007 HEP Budget FY08 Update for P5 7
HEP Trends FY2008
Growth continues in R&D and new initiatives Addresses highest priority future facility (ILC) as
well as long-term R&D (accelerator science) Also targeted at high-impact physics areas in the
nearer term that have relatively well-defined “roadmaps”: Neutrinos Dark Energy
The challenge is that HEP budgets only growing at approximately cost-of-living…hard to grow new efforts
24 Sep 2007 HEP Budget FY08 Update for P5 8
Revised Input for P5 Advice inconsistent with likely budget scenarios does not help
But boundary conditions have changed, particularly ILC We would also like to know priorities independent of budget
Out-year overall budget envelope has changed since last time Was: Growing at few to several % per year Now: ??
Facilities Operations envelopes : Now have better idea of B-factory ramp-down trajectory (at
least 1st phase). FY2010 Tevatron running?
Project profiles Revised profiles: actual plans for actual projects; my guesses
for others. Did not iterate with NSF. New proposals beginning to surface
24 Sep 2007 HEP Budget FY08 Update for P5 9
Suggested out-year scenarios$ in Millions FY05 FY06 FY07 FY08 FY09 FY10 FY11
HEP Budget out-years, FY07 Pres Req 740 717 775 785 810 890 975
Alternative HEP out-years (~FY08 Req) 740 717 751 782 837 895 957
Actual 740 717 751 782
“Alternative” assumes 7% annual increase (a la ACI), see following slide
24 Sep 2007 HEP Budget FY08 Update for P5 10
Outyear HEP Profile DOE HEP FY2007 out-year profile is a component of an Office of
Science proposal developed with FY2007 Pres. Req. and sent to Congress March 2006 Grows 1-3% (9-10%) per yr in 2008-9 (2010-11) Actual bottoms-up integration of projects
FY2008 “profile” is nominal 7% per yr pro rata Compromise forced by lack of agreement between OMB and
Congress on outyear planning Mechanical increase of each SC program by fixed rate Because it is based on FY08 Req., integral funding is less than in
comparable FY07 exercise.
24 Sep 2007 HEP Budget FY08 Update for P5 11
Facilities Ramp-down Profiles
These are our rough estimates We concur with FNAL estimates of ~$25M (M&S only) incremental
to run Collider for one year. Assume:
LCLS covers most of SLAC linac ops (2008+). HEP Ops staff at SLAC transition to other activities.
FNAL operations for NuMI will continue thru NOvA (2018?)
Est. annual savings in $M Year 1 Year 2 Year 3Tevatron 30 20 10
$215M $185M $165M $155M
B-factory 35 35 5
$90M $55M $20M $15M
24 Sep 2007 HEP Budget FY08 Update for P5 12
Project Profiles : Caveats
All numbers are rounded, “planning level”, per experiment (may want >1)
Start and end dates flexible; does not include operations
Unless otherwise noted these are NOT actual project profiles
All $ in Millions and could include contributions from both US funding agencies
24 Sep 2007 HEP Budget FY08 Update for P5 13
Nominal Project Profiles I
“Small” projects (Total Project Cost [TPC] <$50M)
Project Year 1 Year 2 Year 3 Year 4 Year 5Nominal
TPC
DES (CD-1) 1 6 9 7 2 25
Daya Bay (CD-1) 1 5 9 11 8 34
Small Dark Matter Expt 8 10 7 25
g-29 11 7 -- 27
24 Sep 2007 HEP Budget FY08 Update for P5 14
Nominal Project Profiles II “Medium” projects ($400M>TPC>$50M):
Project Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
TPC
($M)
Ground-based DE Telescope 20 50 60 50 20 -- 200
Large DM Expt 10 20 40 20 10 -- 100
Double Beta Decay Expt 10 20 40 20 10 -- 100
NOvA (CD-2) 8 36 65 73 46 32 260
LHC Detector Upgrades 10 40 80 70 50 20 270
Next Gen Nu Expt 20 30 50 30 20 -- 150
DUSEL Phase I 40 70 90 70 30 -- 300
24 Sep 2007 HEP Budget FY08 Update for P5 15
Nominal Project Profiles III Large new facilities ($1B > TPC > $400M)
ProjectYear
1Year
2Year
3 Year 4 Year
5Year
6 TPC
Space-based Dark Energy Telescope 20 30 70 90 100 70 400
Megaton-scale Nu Detector 40 90 110 120 110 30 500
ILC Pre-construction R&D (US share) 30 60 75 90 105 120 540
ILC US site studies + industrialization 0 10 30 75 95 150 390
24 Sep 2007 HEP Budget FY08 Update for P5 16
Nominal Project Profiles IV Ultra-scale new facilities (TPC > $1B)
ProjectYear
1Year
2Year
3Year
4 Year
5Year
6Out-Year TPC
ILC construction (US Share, FY07$) 225 435 695 760 780 705 1675 5275
Neutrino Factory TBD
Muon Collider TBD
24 Sep 2007 HEP Budget FY08 Update for P5 17
What’s Not Included
“Super” NuMI Upgrade (0.71.2MW) Needs revised profile from lab. TPC $50-100M?
LHC Accelerator Upgrade Needs definition of what it is (CERN) Needs definition of US scope
Project X No cost estimate yet
24 Sep 2007 HEP Budget FY08 Update for P5 18
Summary Budget outlook (FY08+) is uncertain
May clear up in 6 months…or not So are boundary conditions
ILC is the elephant in the room Does that change priorities?
Particularly, if ILC is delayed or stretched out P5 advice will be most useful in
Determining optimal balance of existing research program vs. future opportunities
What are the budget implications of different physics scenarios?