BTW 2012 Network Changes – 3 month rolling plan
description
Transcript of BTW 2012 Network Changes – 3 month rolling plan
1
The information contained in this Presentation is confidential information as per your terms and conditions with British Telecommunications plc (BT).
Please treat it accordingly and do not forward, republish or permit unauthorized access.
BT reserves the right to make changes to the information in this Presentation at any time without further notice.
BTW Planned Engineering Works 90 day overview July 2013 to September 2013These dates are indicative dates only and not to be used for any forecasting purposes as they are all subject to change. Please ensure that you wait for formal notifications from IRAMS.
2
BTW 2012 Network Changes – 3 month rolling plan
• Whilst BTW has continually worked to enhance its network, we are currently undergoing an exceptional level of change driven by four main drivers:-
– Stability – to improve the reliability of the network, BTW is targeting certain network elements with hardware and software improvements.
– Capacity – the need for additional capacity is driven by an increase in the number of broadband users on the 21C network (through migration from 20C and growth) and also by the ever-increasing bandwidth demands of those users.
– Resilience –to improve the resilience of the network , BTW is actively removing single points of failure from the network – New Functionality – to meet the needs of the market BTW needs to enhance its network to deliver the services its
customers require.
• This presentation outlines the key upgrade programmes, their drivers, customer impact and the number of upgrades per programme per week.
• BTW is keen to deliver all the required improvements as quickly as possible whilst actively managing the risk to customers. For this reason a range of run-rates against each programme has been outlined. The actual run-rates achieved will be determined by this ongoing live analysis of risk.
• Customer outage times for the PEWs start between 00:01 and 02:00 with the aim of completing customer impacting work by 06:00. This allows 2 hours for roll-back should the PEW be unsuccessful.
• Business as usual capacity upgrades and upgrades to resilient structures have not been listed here.
3
Customer Service / BTID Network Change - Executive Summary
21c BRAS Upgrades Programme No 37
SE800 11.1.2.5p8 Software upgrade - status update• The following dashboard provides overall status of the upgrade program with projected completion
22nd July:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16Birmingham 30-Apr-13 01-May-13 01-May-13 01-May-13 30-Apr-13 30-Apr-13 30-Apr-13 01-May-13 03-May-13 03-May-13 01-May-13 30-Apr-13Bristol 25-Apr-13 25-Apr-13 25-Apr-13 26-Apr-13 29-Apr-13 29-Apr-13 26-Apr-13 26-Apr-13 26-Apr-13 25-Apr-13 25-Apr-13 26-Apr-13 26-Jun-13Cardiff 24-Apr-13 24-Apr-13 24-Apr-13 19-Jun-13 19-Jun-13 19-Jun-13 19-Jun-13 24-Apr-13 24-Apr-13 30-Apr-13Colindale 21-Mar-13 22-Mar-13 22-Mar-13 19-Jun-13 27-Mar-13 27-Mar-13 26-Mar-13 26-Mar-13 27-Mar-13 27-Mar-13 03-May-13 26-Mar-13 26-Mar-13 03-May-13 21-Mar-13 01-Jul-13Derby 14-May-13 03-Apr-13 08-Apr-13 08-Apr-13 03-Apr-13 03-Apr-13 03-Apr-13 03-Apr-13 05-Jul-13Falkirk 28-Jun-13 23-May-13 28-Jun-13 24-May-13 24-May-13 23-May-13 28-Jun-13 04-Jul-13Faraday 29-May-13 31-May-13 29-May-13 29-May-13 29-May-13 30-May-13 30-May-13 29-May-13 30-May-13 30-May-13 31-May-13 31-May-13 31-May-13 31-May-13 New BuildGlasgow 24-Jun-13 24-Jun-13 27-Jun-13 25-Jun-13 25-Jun-13 25-Jun-13 25-Jun-13 26-Jun-13 26-Jun-13 26-Jun-13 26-Jun-13 26-Jun-13 27-Jun-13 25-Jun-13 27-Jun-13 27-Jun-13Guildford 16-Apr-13 16-Apr-13 15-Apr-13 17-Apr-13 15-Apr-13 16-Apr-13 15-Apr-13 17-Apr-13 16-Apr-13 17-Apr-13 17-Apr-13 15-Apr-13 17-Apr-13 New Build New BuildLeeds 04-Jul-13 04-Jul-13 19-Jul-13 05-Apr-13 05-Apr-13 05-Apr-13 04-Jul-13 05-Apr-13 05-Apr-13 04-Jul-13 11-Jul-13Manchester 12-Apr-13 12-Apr-13 12-Apr-13 12-Apr-13 11-Apr-13 11-Apr-13 11-Apr-13 11-Apr-13 11-Apr-13 10-Apr-13 12-Apr-13 10-Apr-13 10-Apr-13Milton Keynes 20-Jun-13 20-Jun-13 20-Jun-13 20-Jun-13 21-Jun-13 21-Jun-13 10-May-13 10-May-13 09-May-13 21-Jun-13 10-May-13 10-May-13 20-Jun-13 15-May-13Newcastle 12-Mar-13 12-Mar-13 13-Mar-13 19-Mar-13 19-Mar-13 29-Apr-13 14-Mar-13 13-Mar-13 12-Mar-13 04-Jul-13Peterborough 30-Jan-13 16-Jan-13 30-Jan-13 31-Jan-13 31-Jan-13 22-Jan-13 01-Feb-13 08-Mar-13 26-Nov-12 29-Jan-13 29-Jan-13 15-Jul-13 New BuildPreston 18-Apr-13 18-Apr-13 10-Jul-13 10-Jul-13 10-Jul-13 10-Jul-13 08-Jul-13 08-Jul-13 18-Apr-13 18-Apr-13 22-Jul-13 18-Apr-13 New BuildSheffield 11-Jun-13 11-Jun-13 11-Jun-13 10-Jun-13 10-Jun-13 10-Jun-13 11-Jun-13 10-Jun-13Slough 22-Feb-13 22-Feb-13 26-Feb-13 28-Feb-13 01-Mar-13 05-Mar-13 06-Mar-13 08-Mar-13 27-Feb-13 27-Feb-13 28-Feb-13 01-Mar-13 05-Mar-13 26-Feb-13 06-Mar-13 29-Apr-13Southbank 16-May-13 16-May-13 14-May-13 14-May-13 15-May-13 15-May-13 17-May-13 14-May-13 14-May-13 15-May-13 17-May-13 17-May-13 15-May-13 16-May-13 17-May-13 11-Jul-13Stepney Green 03-Jun-13 03-Jun-13 04-Jun-13 05-Jun-13 07-Jun-13 04-Jun-13 04-Jun-13 05-Jun-13 05-Jun-13 05-Jun-13 07-Jun-13 07-Jun-13 07-Jun-13 04-Jun-13 05-Jun-13 04-Jun-13Wolverhampton 22-Jul-13 23-Nov-12 09-Jul-13 09-Jul-13 05-Jul-13 05-Jul-13 05-Jul-13 09-Jul-13 05-Jul-13 09-Jul-13 18-Jun-13
CompleteOn planNew build = New BRAS installations planned to address growth as required. Theses will be installed with latest 11.1.2.5p8 SEOS softwareRe-planned = Postponed, e.g. where pre-checks I have identified technical issue requiring resolution before upgrade. Specified date is the revised date.
POSI SiteBRAS Number
4
Customer Service / BTID Network Change - Executive Summary
New Deployments May – July 2013
Prog
No:
Upgrade Key Drivers Total Upgrades
Average EU Impact per upgrade
Affected Products
Average EU outage (Mins)
Upgrades per week
Target Months Targat End
June
July
Aug
Sep
500G IEA chassis upgrade
Scaling 4 port 10G line-card
TBC TBC TBC TBC TBC TBA
21c EES, EEA, IEA, MSE Upgrade
Vendor support, Functionality
Approx 2500. 6000 HE, WBMC, WBC
20 75 Dec 13
40
45
21C UpgradesProg No:
Upgrade Key Drivers Upgrades Complete / Total
EUs per upgrade
Upgrades per PEW
Affected Products
Av. End user outage (Mins)
Upgrades per week
Progress Planne
d EndM
ayJun
July
Aug
SVLAN moves
Capacity,Stability
Ongoing Av 800Min 0
Max 1000
9 WBC 35 Up to 75 Ongoing
BRAS 11.1.2.5 P8 Upgrade
Functionality (IPv6), stability.
243/243 BB EU’s per BRAS
Av 35000Max 45000
6 WBC / WBMC
45 Up to 24
Jul 13
2nd Vendor MSPE Software Upgrades
Functionality(LAG Support)
21/67 Non Service Impacting
0 None 0 4
Nov 13
7750 R10 Upgrade
Features (Ipv6), Vendor Support
2/2500 Variable 1 HE, WBC, WBMC
15 80May
14
High ThroughputBEA-VS
Capacity 11/20 Av 120K 1 WBC / WCC
45 mins 1 Jun-14
6
SVLAN moves - these moves offload SVLAN’s (bundles of Broadband traffic) from one BRAS to another. This is carried out to alleviate capacity issues mplet
37 21C BRAS upgrades to support IPv6 and improve stability
38Supports LAG functionality and also improved resilience performance.
39Required to support IPv6 and due to current software going end of support
22
6
Ongoing 20C Upgrades Cont’d
Prog No:
Upgrade Key Drivers Upgrades Complete / Total
EUs per upgrade
Upgrades per PEW
Affected Products
Av. End user outage (Mins)
Upgrades per week
Progress Planne
d End
May
June
July
Aug
ERX BRAS12.3
EoL 23/225 Av 11000Min 3000
Max 18000
2 IPSC 20 8 Jul 14
DSLAM SDH Bypass (MSIP Closure)
MSIP Platform Closure
242/4620 700 15 IPSC 10 60Sep 14
49
46
7
Completed 20C Upgrades
1
14
2
10k BRAS SB11 Stability 122/122 Av 11000Min 3000
Max 18000
6 IPSC Up to 18 Apr 1336
8
Completed 21C Upgrades
Progr No:
Upgrade Key Drivers
Upgrades Complete / Total
BB EUs and/or Ethernet Circuits per upgrade
Upgrades per PEW
Affected Products
Av. End user outage (Mins)
Upgrades per week
Date Ende
d
Copper MSAN Upgrade
Functionality
5594/5594 Non-Customer Impacting
Up to 120
None 0 Up to 480 Dec 11
EAD Chassis Code Upgrade
Stability 6950/6950 Up to 15 Ethernet Circuits
Up to 200
Ethernet,Mobile
Ethernet
<1 Up to 1000
Feb 12
21C BRAS Core Migration
Capacity 151/151 Non Customer Impacting
Up to 12 WBC 0 16-30 Feb 12
BEA VS Card Upgrade
Capacity 20/20 – Complete
Non-Customer Impacting
1 None 0 Up to 4 Mar 12
DDR Hardware replacement
Stability 200/200 Non Customer impacting
10 None 0 50 May 12
15
16
3
17
28
9
Completed 21C Upgrades
Progr No:
Upgrade Key Drivers
Upgrades Complete / Total
BB EUs and/or Ethernet Circuits per upgrade
Upgrades per PEW
Affected Products
Av. End user outage (Mins)
Upgrades per wee
Date Ende
d
EAD Chassis Code Upgrade
Stability 6950/6950 Up to 15 Ethernet Circuits
Up to 200 Ethernet,Mobile
Ethernet
<1 Up to 1000
Feb 12
21C BRAS Core Migration
Capacity 151/151 Non Customer Impacting
Up to 12 WBC 0 16-30 Feb 12
BEA VS Card Upgrade
Capacity 20/20 – Complete
Non-Customer Impacting
1 None 0 Up to 4 Mar 12
DDR Hardware replacement
Stability 200/200 Non Customer impacting
10 None 0 50 May 12
MPLS Core Router Upgrades
Code Update 109/109
Av 20000Min 0
Max 100000
1 WBMC180
(240 Max)
1-4 Jun12
16
3
17
28
11
10
Completed 21C Upgrades
Progr No:
Upgrade Key Drivers
Upgrades Complete / Total
BB EUs and/or Ethernet Circuits per upgrade
Upgrades per PEW
Affected Products
Av. End user outage (Mins)
Upgrades per week
Date Ende
d
High ThroughputBEA-VS
Capacity 5/5 Av 120K 1 WBC / WCC
45 mins 1 Jun 12
BRAS software Upgrade
Stability 193/193 Av 17000Max 32000
1 WBC / WBMC/
WCC
45 mins Up to 50 Jul 12
Copper MSANSoftware Upgrade
Stability / Capacity
5844/5844 Average 700
120 WBC /WBMC
30 mins 480 May 12
2nd vendor MSAN Upgrade
Stability 702/702 Average 700
40-50 WBC / WBMC/WCC
40 mins 200 - 250 Jul 12
2nd Vendor MSPE
Stability 51/51 Av 20k 1 WBC / WCC /
Ethernet
30 secs – 2 mins
2 Jan 13
22
26
27
30
23
Broadband Services on 21CN
12
46
9
11
14
20 22
23
2628
29
31
3227
3834
40 3435
36
3739
44
4545
45
45
46
47 48
1150
4946
39
39