Btl Uprvunlpresent i

download Btl Uprvunlpresent i

of 65

Transcript of Btl Uprvunlpresent i

  • 7/29/2019 Btl Uprvunlpresent i

    1/65

  • 7/29/2019 Btl Uprvunlpresent i

    2/65

    BOILER TUBE FAILUREESTIMATED OVER 1500-2000 BTF

    TAKE PLACE EVERY YEAR ININDIAN POWER INDUSTRY.

    BTL IS RESPOSIBLE FOR ABOUT8% OF LOSS IN AVAILABILITY

    ANTICIPATED ANNUAL LOSS 8000 MW

  • 7/29/2019 Btl Uprvunlpresent i

    3/65

  • 7/29/2019 Btl Uprvunlpresent i

    4/65

    UPRVUNL-PIE STATIONSBTF LOSSES AV. ONE BTF EVERY 1.5 DAY

    EST. GENERATION LOSS: 6.25 MU PER DAY

    AV. DAILY AVAILABILITY LOSS: 14.65%

    EST. REVENUE LOSS: Rs 1.25 Cr per day@Rs 2/- per Kwh

    EST. LOSS IN PROFIT: Rs 12.5 Lakhs per day@ 10%

  • 7/29/2019 Btl Uprvunlpresent i

    5/65

    BOILER TUBE FAILURE

    WATER TOUCHED TUBES e.g. WATER WALL, ECONOMISER etc.

    IF OPERATED TO DESIGN REGIME SHALL

    HAVE INFINITE LIFE EXCEPT FOR NORMAL

    WEAR

    STEAM TOUCHED TUBES e.g. SH/RH etc.

    DUE TO HIGH PRESSURE & TEMPERATURE

    STEAM CONDITION ARE SUBJECTED TOCREEP INITIATED PHENOMENON.

    LIFE OF SUCH TUBES IS LIMITED TO 200 000

    Hrs.

  • 7/29/2019 Btl Uprvunlpresent i

    6/65

  • 7/29/2019 Btl Uprvunlpresent i

    7/65

    3.0 OVERHEATING & CREEP Short Term Overheating due to Starvation (Blockage)

    Long Term Overheating Creep

    Graphitization

    4.0 POOR WATER CHEMISTRY Hydrogen Damage/ Embrittlement Caustic Gouging Pitting Chemical Cleaning/ Excursion Damage

    BTL CAUSE

  • 7/29/2019 Btl Uprvunlpresent i

    8/65

    5.0 POOR MAINTENECE Material Mix-up

    Weld Defect

    Improper Inspection Non Availability of Material Mechanical Rubbing/Attrition or Fretting due to inadequate fix up/ support6.0 OTHERS Ageing of DMW Joints

    Ageing of Shop Weld Joints with allowable defects

    BTL CAUSE

  • 7/29/2019 Btl Uprvunlpresent i

    9/65

    BTL CAUSE IMPACT ANALYSIS

    1.0 EROSION: 40% Ash Erosion: 28% Steam Erosion: 8% PF/Coal Erosion: 4%

    2.0 CORROSION & PITTING: 3%3.0 OVERHEATING: 7%

    4.0 POOR MAINTENANCE: 48%

    Attachment Weld Failure: 18%

    Site Weld Failure: 16% Stub joint/DMW Failure: 6% Material Mix-up: 3% Mech. Rubbing/Attrition: 5%

    5.0 OTHERS: 2%

  • 7/29/2019 Btl Uprvunlpresent i

    10/65

    MAJOR AREA OF CONCERNIN

    PRESSURE PARTS

    1.0 WATER WALLS: 35%

    2.0 SECOND PASS (ECO/LTSH/SCW): 43%

    3.0 SUPERHEATERS: 11%

    4.0 REHEATERS: 11%

  • 7/29/2019 Btl Uprvunlpresent i

    11/65

    BTF MANAGEMENT

    UNDERSTANDING

    &PREVENTION

  • 7/29/2019 Btl Uprvunlpresent i

    12/65

    EROSION

    Flue Gas erosion is caused by the abrasive particles mainly alphaquartz and pyrites in ash and is dependant on the amount and

    velocity of ash particles. Alpha quartz in ash in Indian conditions

    varies from 10-20%.

    FG erosion causes polishing of the tubes. This form of erosionoccurs mainly in Economizer and LTSH.

    Erosion by steam is severe if it is wet e.g. by soot blowers.

    Falling slag results in abrasion of the tube surface.

    Coal particle erosion results from damaged coal burners.

  • 7/29/2019 Btl Uprvunlpresent i

    13/65

    EXTREME END COILS ON BOTH LHS AND RHS OF ECONOMIZER & LTSH ASWELL AS OTHER COILS TO BE LIFTED/LOWERED FOR A THORUGH INSPECTION AND

    THICKNESS SURVEY.

    TUBES IN EROSION PRONE AREAS TO BE INSPECTED FOR HEALTHINESS AT

    EVERY OPPORTUNITY & SHIELDED OR SHIELDS RESTORED.

    COIL BANKS BENDS TO BE PROTECTED BY CASSETTE BAFFLES & INSPECTEDAT EACH OPPORTUNITY.

    VISUAL INSPECTION AND THICKNESS SURVEY TO BE CARRIED OUT AT EVERY

    UNIT OVERHAUL AS WELL AS EVERY AVAILABLE OPORTUNITY. TUBE THICKNESS IN

    EROSION PRONE AREAS TO BE MEASURED AND RECORDED.

    TUBES WITH 15 -20 % LOSS IN THICKNESS ARE TO BE REPLACED.

    INSTALLATION OF VELOCITY DEFLECTORS/ EROSION CONTROL DEVICES TO

    REDUCE HIGH FLUE GAS VELOCITIES AND INEQUITABLE FLOW DISTRIBUTION

    COILS TO BE INSPECTED TO ENSURE THEIR ALIGNMENT AND PITCH. HANGERS

    & HOLDING CLAMPS AREA TO BE INSPECTED FOR EROSION AROUND THE AREA

    APPLICATION OF REFRACTORY IN HIGHLY EROSION PRONE AREAS

    EROSION MANAGEMENT

  • 7/29/2019 Btl Uprvunlpresent i

    14/65

    OVERHAULING OF WALL DESLAGGERS. ENSURE PROPER NOZZLEALIGNMENT IN EVERY UNIT OVERHAUL TO AVOID STEAM IMPINGEMENT

    STEAM BLOWING PRESSURE TO BE MONITORED AND SET AT THE WALLBLOWERS THE SET PRESSURE TO BE CHECKED QUARTERLY FOR ANYDEVIATIONS AND CORELATED WITH THE EROSION RATE IN SUBSEQUENTSHUTDOWNS

    COAL COMPARTMENT ASSEMBLIES TO BE REPLACED AT THE END OFTHEIR LIFE OR DURING UNIT OVERHAUL, AS REQUIRED

    COAL BURNERS AND NOZZLE TIPS TO BE INSPECTED AT EVERYOPPORTUNITY AND DAMAGED BUFFER PLATES AND TOP PLATES ARE

    REPLACED

    PLATES WITH WEAR RESISTANT COATING CAN BE USED TO ENHANCECOAL NOZZLE TIP LIFE AND REDUCE PF EROSION

    COAL COMPARTMENT CAN BE HARD FACED AT EROSION PRONE AREASTO REDUCE THE RATE OF EROSION

    EROSION MANAGEMENT

  • 7/29/2019 Btl Uprvunlpresent i

    15/65

    INSPECTION AND REPAIR /REPLACEMENT OF AIR NOZZLES AND

    TIPS IN EVERY CAPITAL OVERHAUL TO ENSURE ADEQUATE AIRFLOW

    BURNER TRANSITION TUBES AND CORNER TUBES TO BE

    INSPECTED DURING OVERHAULS THOROUGHLY

    WEAR BARS CAN BE WELDED ON CORNER TUBES OF S-PANEL

    REFRACTORY CAN BE APPLIED AT UPPER AND LOWERTRANSITION TUBE BENDS TO REDUCE EROSION

    THE INTERFACE OF S-PANEL TUBES WITH SIDE WATER WALLS TOBE SEALED WITH REFRACTORY

    THICKNESS SURVEY OF S-PANEL ZONE TO BE DONE DURING EACH

    AVAILABLE OPPORTUNITY

    EROSION MANAGEMENT

  • 7/29/2019 Btl Uprvunlpresent i

    16/65

    OVERHEATING

    Operation of tubes at temperatures higher than the design temperatures causesreduction in tube material strength. Overheating results in deterioration inmicrostructure of tube material and enhanced oxidation occurs.

    Short term overheating failures are characterized by fish mouth bursts withvery thin burst lips which display a partially or fully hardened structuredepending on the temperature.

    Such failures are caused by loss of circulation either because of choking orbecause of loss of water level in the drum, flame impingement on tubes, andsecondary combustion. These failures are common in high heat flux areas likewater walls.

    Choking may be caused by foreign materials or pre boiler deposits due toimproper water treatment or condenser leakage which get deposited at highheat flux areas or bends. High dissolved gases in feed water, condenser leakageall give rise to pre boiler deposits.

    Flame impingements are caused by damage to the burner system.

  • 7/29/2019 Btl Uprvunlpresent i

    17/65

  • 7/29/2019 Btl Uprvunlpresent i

    18/65

    When deposits are suspected diameter measurement of other tubes at the sameelevation as failed tubes should be taken for indications of bulging & swelling.Bends in the tube circuit also need to be examined.

    Chemical examination of the deposits to carried out to determine their source.

    Boiler water chemistry to be monitored strictly to prevent long term

    overheating. Maintenance procedures to be followed to prevent tools, cutting debris and

    weld spatter from entering tube circuits & blockage.

    Operating procedures should limit tube metal temperatures to design values. Ifthis is not possible then possibilities to upgrade tube material can be explored.

    Metallographic examination of tube samples in high heat flux zones gives agood indication.

    Avoid slagging and wall fouling by proper operation of soot blowers,combustion controls through proper burner & SADC management & avoidingoperation of the unit at low or high operational regime.

    OVERHEATING MANAGEMENT

  • 7/29/2019 Btl Uprvunlpresent i

    19/65

    CORROSION

    Corrosion accounts for about 15-30% of tube failures. Useful life of tube steels is affected by a number of internal corrosion

    mechanisms that are controlled by the chemistry of water. Dosants andcontaminants in water have a major influence on corrosion.

    Under normal operating conditions there is a protective magnetic oxide scale

    on the inside surface of the boiler tubes. This protective magnetite has low solubility in water under slightly alkaline

    conditions.This solubility increases rapidly at pH values below 5 and above 12causing risk of corrosion. If this protective layer is disturbed the tubes corrodeat a faster rate causing tube failures.

    On load corrosion (H2 damage and caustic gouging) is caused by concentrationof impurities in water.

    Caustic corrosion develops from deposition of feed water corrosion productswherein NaOH can concentrate to high pH levels. At high pH the protectivelayer becomes soluble leading to rapid corrosion, irregular wall thinning or

    gouging on the water side of the tube .

  • 7/29/2019 Btl Uprvunlpresent i

    20/65

    Hydrogen damage results from fouled heat transfer surfaces and acidic

    condition of boiler water e.g. where sea water is used in condensers. Hydrogencombines with carbon to form methane at grain boundaries. Large methanegas molecules become trapped between the grain boundaries and cause anetwork of discontinuous internal cracks.

    Pitting is caused by attack of dissolved oxygen in boiler water on tube internalsurface.

    Stress corrosion cracking (SCC) results from a combination of tensile stress,corrosive environment and susceptible material like austenitic stainless steels.

    The problem is common with stainless steel cold bends when heat treatmentsare not done or are not proper.

    For austenitic stainless steels chlorides are mainly responsible for SSC. AsChromium provides the corrosion resistance, formation of ChromiumCarbide makes the tube susceptible to SCC. Hence stabilized grades of SS

    which have alloy elements like Titanium and Columbium, that are strongcarbide formers are preferred.

    CORROSION

  • 7/29/2019 Btl Uprvunlpresent i

    21/65

    Monitoring and control of boiler water chemistry to prevent high caustic/acidic levelsand restoration to design values.

    Maintenance of condensers & feed water heaters and chemical treatment andmonitoring to be carried out without deviations.

    Pitting can be controlled by rigorous monitoring, identification and control ofcondenser leaks and others causing air ingress. During boiler operation pH of boiler

    water should be maintained between 9.5-10.5. Residual dissolved oxygen should be lessthan 0.005ppm. During boiler shutdown boiler circuit should be completely filled withDM water at a pH of 9.5 and containing minimum 200ppm hydrazine. The hydrazinecontent should be checked everyday and extra quantity should be added if the valuefalls below 50ppm. Alternatively in dry preservation the boiler circuit is filled with drynitrogen and maintained at a positive pressure.

    Corrosion damage can be reduced by minimizing ingress of feed water corrosion and

    condenser tube leakage.

    Periodic Tube samples to be taken to verify the amount of deposition in the tube. As itresults in wall thinning extent of damage can be estimated by NDE methods.

    Carry out periodic inspection of water wall tubes in high heat flux areas for internaldeposits and analyzing the need for chemical cleaning.

    Sophisticated UT techniques can identify locations where H2 damage has embrittled the

    steel.

    CORROSION MANAGEMENT

  • 7/29/2019 Btl Uprvunlpresent i

    22/65

    Cyclical stresses or strains imposed on boiler tube lead to fatiguefailures. Fatigue failures are mainly caused by the restraintoffered to free expansion of tubes at attachment welds or wheretubes are fixed to a drum, header, wall, seal or support

    attachment.

    They can also occur at butt welds if they are not made properlyi.e. incomplete penetration.

    Fatigue cracks occur at stress concentration regions such as rootof notch or locations near sudden change of cross section.

    Fatigue Failures are easily identified as they have relativelysmooth fracture surface and the cracks appear straight with a

    blunt edge.

    FATIGUE

  • 7/29/2019 Btl Uprvunlpresent i

    23/65

  • 7/29/2019 Btl Uprvunlpresent i

    24/65

    DIS-SIMILAR METAL WELD FAILURE

    OCCURANCE

    It occurs in steam cooled tubing at the joint of ferritic and austenitic steel.

    Degradation in DMW joint is related to service time, operating temperature,temperature cycling and system stress.

    DMW failure results in circumferential fracture in the joint which is parallel tothe weld fusion line.

    ACTION PLAN

    Sample selected DMW joint for visual and metallurgical analysis.

    Using Ni based filler metal welds instead of SS based gives a service life of 3-4times.

    Scaffolding load should not fall on the DMW joint areas. Similarly DMW jointshould be positioned as far as possible from the fixed loads.

    QUALITY IN MAINTENANCE

  • 7/29/2019 Btl Uprvunlpresent i

    25/65

    WELD DEFECTSOCCURANCE

    Statistical data shows that about 5% of tube failures are attributed to weld andmaterial defects. These failures occur particularly during the initial periods ofoperation.

    Weld defects occur due to lack of quality control over the essential weldingvariables. Defects in the welds occur due to inadequate stress relief, incompletefusion, lack of penetration, inclusions, porosity etc.

    ACTION PLAN

    Quality control procedures like qualification of welder, carrying out welder test

    are essential. This minimizes chances of common welding process defects likeLP, porosity, excess penetration, incomplete fusion, undercuts, etc.

    Testing of weld joints by radiography methods. 100% of joints to be radiographed. .

    Gas cutting to be avoided especially in vertical tube sections. At unavoidableconditions it must be done in presence of competent boiler maintenance

    engineer. A plan can be made for NDT of old weld joints in a phased manner.

    QUALITY IN MAINTENANCE

  • 7/29/2019 Btl Uprvunlpresent i

    26/65

    BTL FAILURES

    PATTERN & EXAMPLES

  • 7/29/2019 Btl Uprvunlpresent i

    27/65

  • 7/29/2019 Btl Uprvunlpresent i

    28/65

  • 7/29/2019 Btl Uprvunlpresent i

    29/65

  • 7/29/2019 Btl Uprvunlpresent i

    30/65

  • 7/29/2019 Btl Uprvunlpresent i

    31/65

  • 7/29/2019 Btl Uprvunlpresent i

    32/65

  • 7/29/2019 Btl Uprvunlpresent i

    33/65

    steam errosion platten SH tube-1

  • 7/29/2019 Btl Uprvunlpresent i

    34/65

  • 7/29/2019 Btl Uprvunlpresent i

    35/65

  • 7/29/2019 Btl Uprvunlpresent i

    36/65

  • 7/29/2019 Btl Uprvunlpresent i

    37/65

  • 7/29/2019 Btl Uprvunlpresent i

    38/65

  • 7/29/2019 Btl Uprvunlpresent i

    39/65

    corrosion fatigue of the cold

    bend of SH tubes

  • 7/29/2019 Btl Uprvunlpresent i

    40/65

  • 7/29/2019 Btl Uprvunlpresent i

    41/65

    fire side corrosion on ww tubes

  • 7/29/2019 Btl Uprvunlpresent i

    42/65

    oil ash corrosion of furnace ww tubes

  • 7/29/2019 Btl Uprvunlpresent i

    43/65

    stress corrosion cracking

  • 7/29/2019 Btl Uprvunlpresent i

    44/65

    Water wall tube overheating due tointernal oxide layer deposition

  • 7/29/2019 Btl Uprvunlpresent i

    45/65

  • 7/29/2019 Btl Uprvunlpresent i

    46/65

  • 7/29/2019 Btl Uprvunlpresent i

    47/65

  • 7/29/2019 Btl Uprvunlpresent i

    48/65

  • 7/29/2019 Btl Uprvunlpresent i

    49/65

    hydrogen damagethick wall longitudinal burst

  • 7/29/2019 Btl Uprvunlpresent i

    50/65

    Hydrogen damage-blow out of tube

  • 7/29/2019 Btl Uprvunlpresent i

    51/65

  • 7/29/2019 Btl Uprvunlpresent i

    52/65

  • 7/29/2019 Btl Uprvunlpresent i

    53/65

  • 7/29/2019 Btl Uprvunlpresent i

    54/65

    hydrogen embrittlement-window failure

  • 7/29/2019 Btl Uprvunlpresent i

    55/65

  • 7/29/2019 Btl Uprvunlpresent i

    56/65

  • 7/29/2019 Btl Uprvunlpresent i

    57/65

    over heating failureof down comer tubes

  • 7/29/2019 Btl Uprvunlpresent i

    58/65

  • 7/29/2019 Btl Uprvunlpresent i

    59/65

  • 7/29/2019 Btl Uprvunlpresent i

    60/65

  • 7/29/2019 Btl Uprvunlpresent i

    61/65

  • 7/29/2019 Btl Uprvunlpresent i

    62/65

  • 7/29/2019 Btl Uprvunlpresent i

    63/65

  • 7/29/2019 Btl Uprvunlpresent i

    64/65

  • 7/29/2019 Btl Uprvunlpresent i

    65/65