Brunswick Terminal Station - planning.vic.gov.au€¦ · Planning and Environment Act 1987 Advisory...

81
Planning and Environment Act 1987 Advisory Committee Report Brunswick Terminal Station 21 August 2015

Transcript of Brunswick Terminal Station - planning.vic.gov.au€¦ · Planning and Environment Act 1987 Advisory...

  •  

    Planning and Environment Act 1987 

    Advisory Committee Report 

     

     Brunswick Terminal Station  

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

    21 August 2015     

  •  

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

    Planning and Environment Act 1987 

    Advisory Committee Report pursuant to Section 151 of the Act 

    Brunswick Terminal Station 

     

    221 August 2015 

     

     

       Nick Wimbush, Chair   Robin Crocker, Member 

     

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

     

     

    Contents   Page 

    Summary and response to Terms of Reference ..................................................................... i 

    1  Introduction and background...................................................................................... 1 1.1  The role of the Advisory Committee ....................................................................... 1 1.2  Appointment and Terms of Reference .................................................................... 1 1.3  Submissions ............................................................................................................. 2 1.4  Hearings ................................................................................................................... 2 1.5  Inspections .............................................................................................................. 3 1.6  Structure of this Report ........................................................................................... 3 

    2  Overview of the site and surrounds ............................................................................ 4 2.1  The subject site and surrounds ............................................................................... 4 2.2  Background to the proposal .................................................................................... 8 

    3  Review of the planning approvals ............................................................................. 10 3.1  Planning permit application MPS/2009/776 ......................................................... 10 3.2  Planning permit application MPS/2011/420 ......................................................... 11 3.3  Moreland Planning Scheme Amendment C140 .................................................... 13 3.4  Post ‐ Moreland Planning Scheme Amendment C140 .......................................... 15 3.5  Planning permit application MPS/2014/87 ........................................................... 15 3.6  Submissions on planning approvals process ......................................................... 16 3.7  Discussion and conclusions ................................................................................... 19 3.8  Findings and recommendations ............................................................................ 21 

    4  Consultation ............................................................................................................. 22 4.1  Overview of processes .......................................................................................... 22 4.2  Pre‐Moreland C140 processes .............................................................................. 22 4.3  Moreland C140 process ......................................................................................... 30 4.4  Post Moreland Amendment C140 processes ........................................................ 31 4.5  Impact consultation had on design outcomes ...................................................... 31 4.6  Overall discussion and conclusions ....................................................................... 32 4.7  Findings and recommendations ............................................................................ 36 

    5  Amenity impacts and landscaping ............................................................................. 38 5.1  The issue ................................................................................................................ 38 5.2  Submissions ........................................................................................................... 45 5.3  Discussion and conclusions ................................................................................... 45 5.4  Findings and recommendations ............................................................................ 46 

    6  Future planning assessment and consultation .......................................................... 47 6.1  Overview of existing models and processes ......................................................... 47 6.2  Submissions ........................................................................................................... 49 6.3  Discussion and conclusions ................................................................................... 51 6.4  Findings and recommendations ............................................................................ 52 

    7  Other matters ........................................................................................................... 54 7.1  Network regulatory approval process ................................................................... 54 7.2  Review of the existing planning instruments ........................................................ 56 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

     

     

    8  Health and safety impacts ......................................................................................... 59 8.1  Background ............................................................................................................ 59 8.2  Electro‐magnetic radiation .................................................................................... 59 8.3  Fire and emergency response ............................................................................... 65 

     

    Appendix A  Terms of Reference 

     List of Tables 

      Page 

    Table 1  Parties to the Committee Hearings ......................................................................... 2 

    Table 2  Summary of BTS consultation activities and outcomes: from 2010 ..................... 23 

    Table 3  Public participation: Application of IAP2 core values at the BTS .......................... 34  

    List of Figures   Page 

    Figure 1  BTS site location ...................................................................................................... 4 

    Figure 2  Aerial photograph of BTS site .................................................................................. 5 

    Figure 3  Merri Creek environs east of BTS site ..................................................................... 6 

    Figure 4  Views  of  BTS  site  from  (top  to  bottom):  north,  south,  east  and west ......................................................................................................................... 7 

    Figure 5  Zoning of BTS site and surrounding area ................................................................ 8 

    Figure 6  2013 Landscape Concept Plan (revised), Urban Initiatives ................................... 40 

    Figure 7  New  66kV  building  under  construction,  adjacent  to Merri  Creek parklands, April 2015 ............................................................................................. 42 

    Figure 8  2014 Landscape Plan 01, Urbis .............................................................................. 43 

    Figure 9  2014 Landscape Plan 02, Urbis .............................................................................. 44 

        

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

     

     

    List of Abbreviations  

    AEMO  Australian Energy Market Operator 

    ARPANSA  Australian Radiation Protection and Nuclear Safety Agency 

    AusNet Services  AusNet Transmission Group Pty Ltd; SP AusNet 

    BTS  Brunswick Terminal Station 

    BTSCRG  Brunswick Terminal Station Community Reference Group 

    BTSCWG  Brunswick Terminal Station Community Working Group 

    CBD  Central Business District 

    CMP  Construction Management Plan 

    Council  Moreland City Council 

    DELWP  Department  of  Environment,  Land,  Water  and  Planning, previously DPCD and DTPLI 

    DPCD  Department  of  Planning  and  Community  Development (former) 

    DTPLI  Department of Transport, Planning and Local Infrastructure (former) 

    EES  Environment Effects Statement 

    EMF  Electro‐magnetic Field 

    EMR  Electro‐magnetic Radiation 

    ENRC  Inquiry  into  the Environment Effects Statement Process  in Victoria 

    EPA  Environment Protection Authority 

    ESO  Environmental Significance Overlay 

    ESV  Energy Safe Victoria 

    FOMC  Friends of Merri Creek 

    Former Minister for Planning  Hon. Matthew Guy (then) MLC 

    GRZ  General Residential Zone 

    IAP2  International Association for Public Participation 

    LPPF  Local Planning Policy Framework 

    MCMC  Merri Creek Management Committee 

    MCRG  Merri Creek Residents Group 

    Minister for Planning  Hon. Richard Wynne MP 

    MSS  Municipal Strategic Statement 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

     

     

    NER  National Electricity Rules 

    NHMRC  National Health and Medical Research Council 

    NRZ  Neighbourhood Residential Zone 

    Proponents  AusNet Services, CitiPower, AEMO.  Referred to generically.  Where necessary a specific company may be  identified as the ‘proponent’. 

    R1Z  Residential 1 Zone 

    RIT  Regulatory Impact Test 

    SBO  Special Building Overlay 

    SPPF  State Planning Policy Framework 

    SUZ  Special Use Zone 

    the Act  Planning and Environment Act 1987 

    VAGO  Victorian Auditor‐General’s Office 

    VCAT  Victorian Civil and Administrative Tribunal 

    VPP  Victoria Planning Provisions 

     

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

     

    Page i 

     

    Summary and response to Terms of Reference (i) Summary The Brunswick Terminal Station Advisory Committee (the Committee) was appointed by the Minister for Planning on 20 March 2015 under section 151 of the Planning and Environment Act 1987. 

    The Committee’s Terms of Reference (attached at Appendix A) state at paragraphs 3 and 4 that the Advisory Committee has the following purpose: …to review the planning approvals process,  including  community  consultation,  for  the  upgrade  of  the  Brunswick  Terminal Station and report on its findings.  The Advisory Committee should provide advice to assist in the  planning  assessment  and  consultation  process  for  future  regional  or  state  significant infrastructure proposals. 

    The Committee wrote to affected parties on 13 April 2015 inviting them to provide a written submission  and  appear  before  the  Committee.    These  affected  parties were  identified  in clause  11  of  the  Terms  of  Reference  and were Moreland  City  Council,  AusNet  Services, CitiPower, the Australian Energy Market Operator, and Merri Creek Residents Group Inc.  In addition, the Committee wrote to Yarra City Council and Darebin City Council  inviting them to  provide  a  submission  on  the  basis  of  their  status  as  nearby  and  involved  Councils.   A request  to make  a  submission was made  and  acceded  to by  the Committee by Professor Carolyn Whitzman, an Urban Planning specialist and local resident. 

    The Hearings took place on 16 and 17 June, and 16 July 2015 at Planning Panels Victoria. 

    Key issues raised in submissions and at the Hearing included:  The  planning  approvals  process  –  both  submissions  in  support  for  this  process  and 

    submissions opposing the process that took place  The community consultation process  Amenity impacts and landscaping  Proposed future planning assessment and consultation  Appropriateness of Ministerial Amendment process and section 20(4)  Appropriateness of regulatory tests and approval process  Health and safety impacts. 

    Having considered the  issues and submissions  in detail, the Committee has concluded that there were no apparent  fundamental  flaws  in the planning permit application process and consideration  of  the  permit  applications  by  Moreland  City  Council.    In  hindsight,  the justification for the use of the s20(4) process to approve Moreland Amendment C140 on the material before  the Committee does not  appear  strong.    That being  said,  the Committee accepts that the Proponent had genuine concerns as to the urgency and necessity of supply protection; but is not convinced that the pathway taken ended up being any more efficient. 

    The Committee considers that the use of section 20(4) of the Planning and Environment Act 1987  is  legitimate  in  some  circumstances;  but  other  than  for  minor  amendments  with limited  third  party  impacts,  should  be  used  judiciously  and  in  consultation  with  the responsible authority. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

     

    Page ii 

     

    Further,  the  Committee  considers  that  a  review  of  terminal  station  and  other  critical electrical  infrastructure  in  planning  schemes  could  be  considered,  to  improve  their recognition in the SPPF and apply appropriate land use controls and zoning where necessary. 

    (ii) Findings and recommendations The Committee makes  the  following  findings  and  recommendations  against  the  reporting requirements in the Terms of Reference which are primarily contained in clauses 20 and 22. 

    20(a) A  review of  the planning approvals process,  including  community  consultation,  for the upgrade of Brunswick Terminal Station. 

    20(b) Advice on the impact that the consultation undertaken had on the design outcome. 

    The planning approvals process is addressed in Chapter 3 of this report. 

    Findings: 

    In relation to the planning approvals process, the Committee finds: 

    There were  no  apparent  fundamental  flaws  in  the  planning  permit  application process  and  consideration  of  the  permit  applications  by  the  Moreland  City Council. 

    In  hindsight,  the  justification  for  the  use  of  the  s20(4)  provisions  to  approve Moreland C140 on the material before the Panel does not appear strong; and it is not clear to the Committee why a s20(4) planning scheme amendment was used as opposed to the former Minister for Planning calling in the planning permit from the Victorian Civil and Administrative Tribunal. 

    Whether or not  it was  ‘the right decision’ of the former Minister for Planning to use s20(4) rather than allowing the matter to take its course through the Victorian Civil and Administrative Tribunal is a rather moot point, as the decision was made and has not been legally challenged by any party. 

    The planning instruments developed and implemented through Amendment C140 appear to have been poorly drafted, and to some extent reversed the efficiencies gained through the use of s20(4). 

    It is arguable that if the second planning permit application had been allowed to run  its  course, possibly  through  the Victorian Civil  and Administrative  Tribunal, that  the end outcome would have been achieved  in a similar  timeframe  to  that which  resulted, with more  transparency  for  the community; but  the Committee accepts  that at  the  time  the Proponent had genuine concerns as  to  the urgency and necessity of supply protection. 

    Recommendations: 

    In  relation  to  the  planning  approvals  process  the  Committee  does  not make  any  specific recommendations.   Recommendations  for  future planning processes  are  included  later  in this Executive Summary and report. 

    Community consultation and the impact on design is addressed in Chapter 4 of this report.    

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

     

    Page iii 

     

    Findings: 

    In relation to community consultation, the Committee finds: 

    Community  consultation  and  participation  for  the  Brunswick  Terminal  Station upgrade started late and did not include any community input into the decision to substantially increase the capacity at the site. 

    Consultation undertaken from 2010 met some good practice principles  identified by  the  Victorian  Auditor General’s Office  and  the  International  Association  for Public  Participation,  but  tended  to  focus  on  providing  information  and  seeking support for proposed on‐site works. 

    Consultation  largely  targeted  local  residents,  with  limited  involvement  of community groups and no significant involvement by the State government. 

    Consultation  related  to  planning  permit  applications  generally  met  statutory requirements but did not  fully address some community concerns  regarding  the Brunswick Terminal Station upgrade. 

    The  design  of  the  project,  but  not  the  location, was  fundamentally  altered  in response  to  community  consultation undertaken  through  the  land use planning process. This resulted, in the Committee’s view, in a much improved project, but at substantially increased cost. 

    Recommendations: 

    In relation to community consultation the Committee recommends: 

    1. The  relevant  agency  formally  adopt  the  International  Association  for  Public Participation  and Victorian Auditor General’s Office  community  consultation  and participation  principles  and  processes  in  future  infrastructure  projects  at  the scoping  stage.    This  should  include preparation of  a  comprehensive  consultation plan,  consultation  at  an  early  stage,  and  the  use  of  independent  facilitators  for consultation and participation activities. 

    2. Identify key agency  responsibilities  for projects of  state and  regional  significance and ensure appropriate involvement in the planning and consultation process. 

    20(c) Advice to Government on how existing amenity impacts could be mitigated through any  changes  to  the Draft  Landscape  Concept  Plans  under  the  Brunswick  Terminal Station Incorporated Document 2012. 

    Amenity and landscaping plans are addressed in Chapter 5 of this report. 

    Findings: 

    In relation to the amenity and landscape plans the Committee finds: 

    The  2014  Landscape  Plan  by  Urbis  is  based  on  sound  principles  and  includes extensive  planting  of mostly  indigenous  species.   No  significant  changes  to  the plan  were  put  forward  in  submissions  and  the  Advisory  Committee  did  not identify changes that would further mitigate visual impacts. 

    Effective  implementation  of  the  plan  and  ongoing maintenance  works,  to  the satisfaction of the responsible authority, will provide a substantial  improvement 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

     

    Page iv 

     

    in visual amenity in residential streets adjacent to the Brunswick Terminal Station and along the Merri Creek parklands. 

    Earlier  landscape  planning  for  the  site  was  of  variable  quality,  in  some  cases lacking  adequate  assessment  of  site  values,  articulation  of  landscape  principles and involvement of the community. 

    Recommendations: 

    The Committee makes no  specific  recommendations on  improvements  to  landscaping and amenity beyond implementation of the existing approved landscape plans. 

    20(d) Advice on the options to Government for the planning assessment and consultation process of future regional or state significant infrastructure. 

    Future planning and assessment of infrastructure are addressed in Chapter 6 of this report.  This focuses on land use planning.  The Committee addresses network planning in Chapter 7. 

    Findings: 

    In  relation  to  future  land  use  planning  and  assessment  of  infrastructure  the  Committee finds: 

    The planning process,  including, as  relevant, assessment under  the Environment Effects Act  1978,  and  the  Planning  and  Environment Act  1987  via  environment effects  statements,  planning  scheme  amendments  and  planning  permit applications  are  fundamentally  robust  processes  for  considering  regional  and state significant infrastructure. 

    The Victorian Parliament  Inquiry  into the Environment Effects Statement Process (2011)  suggested  significant  changes  to  the  Environment  Effects  Statement process which would, if implemented, likely provide for more nuanced pathways for  environmental  assessment  of  significant  projects  and  improved  strategic assessment. 

    The use of section 20(4) of the Planning and Environment Act 1987 is legitimate in some  circumstances;  but  other  than  for minor  amendments with  limited  third party impacts, should be used judiciously and in consultation with the responsible authority. 

    A review of terminal station and other critical electrical infrastructure in planning schemes could be considered, to  improve their recognition  in the State Planning Policy  Framework  and  apply  appropriate  land  use  controls  and  zoning  where necessary. 

    Recommendations: 

    In relation to future planning and assessment of infrastructure the Committee recommends: 

    3. Consider  the  recommendations  of  the  Inquiry  into  the  Environment  Effects Statement Process  (2011) with a view  to  revising  the environmental assessment process  and  the Ministerial  guidelines  for  assessment of environmental effects, including greater use of strategic environmental assessment. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

     

    Page v 

     

    4. Consider  revising  the  Planning  and  Environment  Act  1987  to  reintroduce  a requirement  for  the  Minister  for  Planning  to  consult  with  the  responsible authority when utilising s20(4) of the Act. 

    5. Consider  reviewing  the  practice  note  Ministerial  Powers  of  Intervention  in Planning and Heritage Matters to ensure it is relevant to contemporary planning objectives and expectations. 

    6. Consider undertaking a review of the treatment of critical electrical infrastructure in  the  State  Planning  Policy  Framework  (Clause  19)  and  an  analysis  of  specific infrastructure  sites  to  facilitate  appropriate  underlying  zoning  and  land  use controls. 

    20(e) Any other relevant matters raised in the course of the Advisory Committee hearing. 

    Other matters are addressed  in Chapter 7 of this report.   These other matters  include  links to  the  electricity  regulatory  approval  process  and  the  improvement  of  the  approved planning instruments. 

    Findings: 

    In relation to regulatory approvals for electricity networks the Committee finds: 

    There  is  no  clear  link  between  the  regulatory  approval  process  for  electricity infrastructure  in  Victoria,  and  the  approval  processes  under  the  Planning  and Environment Act 1987. 

    Earlier  engagement  by  the  Proponent(s)  in  the  land  use  planning  process  as opposed  to  the  network  regulatory  process would  very  likely  have  produced  a similar or better outcome in a more timely manner. 

    Recommendations: 

    In relation to regulatory approvals for electricity networks the Committee recommends: 

    7. The Minister for Planning consult with the Minister for Energy and Resources with the aim of  improving  integration between  land use planning processes and  the electricity network regulatory process, including community consultation. 

    Findings: 

    In  relation  to  improving  the approved planning  regime  for  the Brunswick Terminal Station the Committee finds: 

    A more thorough process of preparation and expert peer review of the planning instruments contained  in Amendment C140 would  likely have resulted  in a more robust and effective set of planning controls that may have reduced the need for additional planning permits and delay. 

    Recommendations: 

    The Committee makes no specific recommendations  in relation to  improving the approved planning regime for the Brunswick Terminal Station. 

    22  Submissions regarding health and safety  impacts will be considered by the Advisory Committee and referred to the appropriate authority when the issue falls outside the jurisdiction of the Minister for Planning. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

     

    Page vi 

     

    Health and safety impacts are addressed in Chapter 8 of this report. 

    Findings: 

    In relation to health and safety (EMR and EMF) the Committee finds: 

    Subject  to  the  finding below, based on  the Committee’s  review of  the available material, AusNet Services and CitiPower’s approach to electro‐magnetic radiation appears reasonable. 

    The  Committee  is  not  an  expert  committee  in  relation  to  non‐ionising  electro‐magnetic  radiation  and  considers  this  issue  requires  ongoing  review  and monitoring to ensure regulation maintains pace with relevant research. 

    In relation to other health and safety matters the Committee finds: 

    Based on the Committee’s review of the available material, AusNet Services and CitiPower’s approach to emergency planning and response appears reasonable. 

    Recommendations: 

    In relation to health and safety (EMR and EMF) the Committee recommends: 

    8. The Minister for Planning refer this report to the Victorian Department of Health and Human  Services, Radiation  Safety,  for  further  consideration  and  discussion with relevant Commonwealth Department counterparts. 

     

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 1 of 66 

    1 Introduction and background 1.1 The role of the Advisory Committee The Advisory Committee’s (the Committee) Terms of Reference (TOR) (attached at Appendix A) state at paragraphs 3 and 4 that the Committee has the following purpose:1 

    …  to  review  the  planning  approvals  process,  including  community consultation, for the upgrade of the Brunswick Terminal Station and report on its  findings.    The Advisory Committee  should provide advice  to assist  in  the planning  assessment  and  consultation  process  for  future  regional  or  state significant infrastructure proposals. 

    1.2 Appointment and Terms of Reference Mr Nick Wimbush  (Chair) and Mr Robin Crocker were appointed as  the Committee by  the Minister for Planning on 20 March 2015 under section 151 of the Planning and Environment Act 1987. 

    The Terms of Reference set the scope and role of the Committee  in advising the Minister, and at clause 20 outline the reporting requirements as follows: 

    The Advisory Committee must produce a written  report  for  the Minister  for Planning providing specific advice on the following issues:  A  review  of  the  planning  approvals  process,  including  community 

    consultation, for the upgrade of Brunswick Terminal Station  Advice on  the  impact  that  the consultation undertaken had on  the design 

    outcome  Advice to Government on how existing amenity impacts could be enhanced 

    through  any  changes  to  the  Draft  Landscape  Concept  Plans  under  the Brunswick Terminal Station Incorporated Document 2012 

    Advice  on  the  options  to  Government  for  the  planning  assessment  and consultation process of future regional or state significant infrastructure 

    Any other relevant matters raised in the course of the Advisory Committee hearing 

    A list of persons consulted or heard. 

    The TOR also noted that the Committee is not to review decisions of the Victorian Civil and Administrative Tribunal (VCAT) and that, at clause 20: 

    Submissions  regarding  health  and  safety  impacts will  be  considered  by  the Advisory Committee and referred to the appropriate authority when the issue falls outside the jurisdiction of the Minister for Planning. 

                                                           1  The Committee  requested  the Minister  for Planning vary  the Terms of Reference  to expand  the Hearing 

    timeframe  to  accommodate  the Merri  Creek  Residents  Group  availability.    The  Terms  of  Reference  in Appendix A reflect this change. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 2 of 66 

    1.3 Submissions Under  clause  11  of  the  TOR,  the  Committee wrote  to  affected  parties  inviting  them  to provide a written submission and appear before the Committee.  The invited parties were:  Moreland City Council (Council)  AusNet Services  CitiPower  Australian Energy Market Operator (AEMO)  Merri Creek Residents Group Inc (MCRG). 

    In  addition  to  the  parties  listed  above,  the  Committee  wrote  to  the  following  Councils inviting  them  to provide a  submission on  the basis of  their  status as nearby and  involved Councils:  Yarra City Council  Darebin City Council. 

    The  City  of  Yarra made  a  submission  and  appeared  at  the  Hearing  in  response  to  the invitation. 

    Professor  Carolyn  Whitzman,  a  local  resident  and  expert  in  community  consultation, approached  the  Committee  requesting  to  make  a  submission;  a  request  to  which  the Committee acceded. 

    1.4 Hearings A Directions Hearing was held on 19 May 2015 at Planning Panels Victoria.   The Hearings were held on 16 and 17 June and 16 July 2015 at Planning Panels Victoria.  The Committee heard the parties listed at Table 1. 

    Table 1  Parties to the Committee Hearings 

    Submitter  Represented by 

    Department of Environment, Land, Water and Planning (DELWP) 

    Taren Brockhouse and Sharon Stewart 

    Moreland City Council  John Rantino of Maddocks Lawyers assisted by Darren Camilleri of Moreland City Council.  Briana Eastaugh for Maddocks Lawyers appeared for the closing 

    AusNet Transmission Group Pty Ltd (AusNet Services) 

    Ian Pitt QC of Best Hooper assisted by Dennis McRohan and Alistair Parker 

    CitiPower Pty Ltd  Neil Watt 

    Australian Energy Market Operator (AEMO) Marita Foley of Counsel assisted by Nicola Falcon and Natalie O’Connor  

    Yarra City Council  Sherry Hopkins 

    Professor Carolyn Whitzman   

    Merri Creek Residents Group  Nick Tweedie SC and Jon Gottschall of Counsel 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 3 of 66 

    assisted by Ramon Collodetti and Chris Black2 

    1.5 Inspections The  Committee  visited  the  subject  site  and  surrounds  on  an  unaccompanied  basis  on  15 April 2015  including neighbouring streets,  the Merri Creek environment and Sumner Park.  On  4  June  2015,  the  Committee,  with  representatives  from  AusNet  Services,  CitiPower, Council and the MCRG, inspected the construction works within the BTS. 

    1.6 Structure of this Report The  report  is  structured generally around  the key  reporting  requirements  in  the Terms of Reference as follows:  Overview of the site and surrounds  Review of the planning approvals  Consultation  Amenity impacts and landscaping  Future planning assessment and consultation  Other matters 

    - Network regulatory approval process - Review of the existing planning instruments 

    Health and safety impacts. 

                                                           2  Other members including Mr John Langer and Mr Colin Abbott also made comment at the Hearings.  Other 

    members were present at different times. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 4 of 66 

    2 Overview of the site and surrounds 2.1 The subject site and surrounds The  Brunswick  Terminal  Station  (BTS)  site  is  located  about  3km  northeast  of  central Melbourne  in Brunswick  East  (Figures  1  and  2).    The  site  is  bounded  by  the Merri Creek parklands  to  the  east  and  residential  areas  to  the  south  (Alister  Street)  and west  (King Street). 

     Figure 1  BTS site location3 

                                                           3  Source: DELWP, 2015. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 5 of 66 

     Figure 2  Aerial photograph of BTS site4 

    The Merri  Creek  corridor  is  a  regionally  important  open  space  asset,  providing  wildlife habitat and attracting large numbers of users to the bicycle/pedestrian trail and to sporting facilities  including a  soccer  field and  clubhouse at Sumner Park.   The  creek environs have significant natural and  landscape values, enhanced by active management overseen by the Merri Creek Management Committee (MCMC) since its establishment in 1989 (Figure 3).  A bicycle/pedestrian bridge over Merri Creek adjacent to the BTS provides convenient access across the creek. 

                                                           4  Source: Urbis 2015. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 6 of 66 

     Figure 3  Merri Creek environs east of BTS site5 

    Alister and King streets have a range of mostly low‐set dwelling styles built from the 1930s, on original size allotments.  Views into the BTS from these residential streets, and the Merri Creek parklands, are relatively open with various infrastructure elements visible (Figure 4). 

    The BTS has an area of 4.06ha.  It was rezoned from Residential 1 Zone (R1Z) to Special Use Zone  Schedule 3  (SUZ3)  in Moreland Planning  Scheme Amendment C140  (Figure 5).   This zoning provides  for  continued use  and development of  the  site  as  a utility  installation  ‘… while minimising the impact on the amenity of the surrounding area’.6 

    Three overlays affect the site: the Environmental Significance Overlay (ESO1), Land Subject to Inundation Overlay (LSIO1), and Special Building Overlay (SBO).  Permits are required for certain works under these overlays. 

    The site has been highly altered due to its establishment as a utility installation.  Natural and landscape  values  are  low  with  existing  vegetation  of  varying  quality  and  health.    All established species are introduced and none are of local significance.7    

                                                           5  Unless otherwise indicated, images were taken by the Committee in April 2015. 6  BTS Planning Permit Application February 2014, Urbis. 7  BTS Planning Permit Application, SP AusNet/Urbis, February 2014 (Binder 2, Tab 62). 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 7 of 66 

            

           

            

         

     

     

    Figure 4  Views of BTS site from (top to bottom): north, south, east and west 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 8 of 66 

     Figure 5  Zoning of BTS site and surrounding area8 

    2.2 Background to the proposal The  BTS  is  one  of  three  terminal  stations  supplying  electricity  to  the  inner  Melbourne metropolitan area (and one of 49 terminal stations owned by AusNet Services).  The stations convert electricity from high voltage to lower voltage for domestic and commercial use. 

    The BTS site has operated as a terminal station since 1939.  The site contains transformers, a switchyard and associated  facilities.   High voltage powerlines at 220kV enter  the site  from the north and east along the Merri Creek valley, and a series of lower voltage lines leave the site at various points at 66kV and 22kV. 

                                                           8  From Moreland Planning Scheme. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 9 of 66 

    Electricity  from the terminal station  is supplied to about 73,000 customers  in Melbourne’s inner northern suburbs and the north eastern corner of the Central Business District (CBD). 

    The need to upgrade supply security, and predictions of increased demand for electricity in the supply area, led CitiPower to propose an upgrade to the BTS in 2004.  Upgrades are also proposed for the terminal stations at Richmond and West Melbourne. 

    Proposed  upgrading  of  the BTS  includes  a  switchgear  building  near  King  Street,  two  new 220kV and 66kV buildings located towards the eastern boundary, and removal of redundant structures.    Extensive  retaining walls,  security  fencing  and  landscaping  are  also  proposed (Figure 8).   The upgrade will  increase the output of the BTS from 225 Megavolt Ampere to 900 Megavolt Ampere, a 400% increase. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 10 of 66 

    3 Review of the planning approvals This section focuses on the  land use planning system and the series of permit applications, planning  scheme  amendment  and  VCAT  decision  that  occurred  from  2008  to  now.    The electricity network regulatory framework decisions pre‐2009 are discussed in Chapter 7. 

    3.1 Planning permit application MPS/2009/776 3.1.1 Lodgement and application The planning permit application was  lodged on 7 December 2009  for buildings and works summarised as:9 

    Install 7 x 220kV circuit breakers  Install 2 x 220/66kV busses  Install 2 x 220/66kV transformers (225 mva each)  Line entry connections for Thomastown line  Demolish some existing buildings and 66kV switch yard  Install one new 66kV switch room  New electric fence within the compound, for public safety purposes. 

    3.1.2 Planning controls The  application  provided  an  assessment  of  the  relevant  planning  controls  including identifying  the  following objective  in  the Planning and Environment Act 1987  (the Act), at s4(e): 

    To protect public utilities and  other assets and  enable  the  orderly provision and  coordination of public utilities and other  facilities  for  the benefit of  the community. 

    The application also drew attention to the following State Planning Policy Framework (SPPF) clauses as relevant and provided commentary on their applicability:  Clause 12.04 – A more prosperous city  Clause 14.01 – Planning for urban settlement  Clause 15 – Environment  Clause 18 – Infrastructure  Clause 19.03 – Design and built form. 

    An assessment against the Local Planning Policy Framework (LPPF) was also undertaken and identified the following clauses as relevant:  Clause 21.05‐5 – Urban design urban character and street landscapes  Clause 21.05‐6 – Open space and outdoor recreation  Clause 21.05‐10 – Infrastructure  Clause 22.01 – Discretionary uses in residential areas.    

                                                           9  Aurecon Development Application, 12 November 2009, page 12. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 11 of 66 

    The  following  zone  and  overlay  controls  were  identified  and  their  purposes  and  permit trigger requirements considered:10 

    The subject site is located in the Residential 1 Zone (R1Z) and is affected by an Environmental Significance Overlay – Schedule 1  (ESO1).   A  small portion of the  site  (along  the eastern boundary)  is also  included  in  the Land Subject  to Inundation Overlay (LSIO) and the south‐eastern corner of the site  is covered by a Special Building Overlay (SBO). 

    3.1.3 Council decision Following a number of requests  for  further  information,  the application was considered at the Moreland City Council Urban Planning Committee meeting on 23 June 2010.  The officer report  assessed  the  application  against  the  planning  scheme  and  recommended  that  a permit be granted with extensive conditions. 

    The officer recommendation conclusion noted that the BTS had been in existence for over 50 years; there was no activity proposed beyond the existing use rights; and changes suggested through  the  report and conditions ensure  the proposal  is acceptable having  regard  to  the provisions of the Moreland Planning Scheme and local objections. 

    Council voted to refuse the permit and a notice of refusal was issued on 30 June 2010.  The reasons for refusal, included inconsistency with the SPPF and LPPF, particularly in relation to responsiveness  to  the  Merri  Creek  and  residential  context  including  siting,  design  and landscape and issues with the existing use rights under clause 63.05. 

    The applicant did not exercise a right of appeal to VCAT on the refusal. 

    3.2 Planning permit application MPS/2011/420 3.2.1 Lodgement and application Following  the  refusal of  the  initial planning permit, an expanded consultation process was undertaken as outlined in Chapter 4. 

    The  second  planning  permit  application was  lodged  on  25 August  2011  for  buildings  and works for the proposal summarised as:11 

    Retention of 22kV switchgear building at the northern end of the site  Retention  of  220/22kV  enclosed  transformers at  the  northern  end  of  the 

    site  Replacement of  the  line  termination  rack at  the northern end of  the  site.  

    The new rack will be more tubular in appearance  Replacement of the existing outdoor 220kV switchyard with new indoor Gas 

    Insulated Switchgear  (GIS).   The building will be  located near  the eastern site  boundary  and  will  be  approximately  26  metres  x  27  metres  and approximately 10 metre (sic) high 

                                                           10  Aurecon Development Application, 12 November 2009, page 16. 11  Beca Permit Application, 25 August 2011, page 14. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 12 of 66 

    Establishment  of  a  control  room  abutting  the  220kV  room  that  is approximately 27m x 16m and approximately 6 metres in height 

    Establishment of a 66kV building towards the southern end of the site.  This building will  house  the  66kV GIS,  transformers  and  the  capacitor  banks.  The building will be approximately 57 metre x 50 metre.   This building will be divided roughly into thirds with each third incrementally stepping up and away  from  Alister  Street  –  approximately  7  metres,  9  metres,  then  10 metres in height.  This building will be designed to allow a future expansion to install an additional transformer and associated switchgear 

    Relocation of the existing perimeter and security fences.  The security fence is  to  be  set  back  as  far  as  practicable  and  the  permitter  fence  will  be replaced with a  fence made of a  combination of palisade and  chain‐wire mesh  and  set‐back  along  the  frontages  closest  to  the  King  and  Alister Streets intersection 

    Removal of the redundant 66kV switchyard  located  in the eastern area of the BTS site 

    Removal of the existing compressor room  Removal  of  the workshop  buildings  and  sheds  located  in  the  south  east 

    corner of the site  Removal of  redundant buildings along King Street  (Maintenance Building, 

    Cooling Tower and Machine Room)  Removal of the tower on the King Street side of the site  Complete removal of the dis‐used access‐point mid‐way along King Street. 

    The application was notable  in  that as well as being a  substantially  re‐designed project  it included  a  considerable  number  of  additional  specialist  studies  compared  to  the  first application  including a contamination assessment, geotechnical assessment, Aboriginal and other heritage assessments, an assessment of electromagnetic fields and others. 

    3.2.2 Planning controls The  planning  controls  applying  to  the  site  at  the  time  of  the  second  planning  permit application were as described in 3.1.2 above and the consultants for the applicant undertook a similar analysis in support of the application. 

    The second application provided a more thorough assessment of clause 63 – Existing uses, and  noted  that  the  applicant  had  obtained  a  Certificate  of  Compliance  from  Council confirming that the established facility had existing use rights. 

    3.2.3 Council decision The application was considered at the Urban Planning Committee Meeting on 23 November 2011.   The Council officers  supported  the application and  recommended  that a permit be issued concluding that: 

    The Brunswick Terminal Station has existed  in this  location for 80 years.   The proposed  building  and  works  are  considered  to  respond  to  their  context, ensure the sensitive  interfaces and environments are protected and enhances liveability and amenity. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 13 of 66 

    The design of the buildings and the landscaping is considered to be responsive to  the  preferred  future  character  for  the  area  as  it  reinforces  the  positive landscape  element  of  the  existing  character  and  improves  the landscape/green character. 

    Lastly, the proposal meets the objectives and requirements of Council’s Human Exposure  to  Electromagnetic  Radiation  Policy  and  Relocation  of  Overhead Cables  Strategy  Policy.    In  particular,  a  number  of  measures  have  been introduced into the design to reduce fields, particularly magnetic fields.12 

    Council voted to refuse the application and a notice of refusal was  issued on 29 November 2011.   The  reasons  for  refusal  included  inconsistency of  the building and works scale with the  Residential  1  Zone,  the  inability  of  the  project  to  satisfactorily  demonstrate  that  it addressed  health  impacts  (from  Electro‐magnetic  Fields  (EMF)),  that  it  was  contrary  to Council’s policy on Electro‐magnetic Radiation (EMR) and that there were still issues related to clause 63 and existing use rights. 

    The  Proponent,  AusNet  Services,  lodged  an  application  for  review  at  VCAT  in  December 2011;  this was withdrawn  in  February  2012  following  the  approval  of  Amendment  C140 (discussed below).13 

    3.3 Moreland Planning Scheme Amendment C140 3.3.1 Background In October 2011 a briefing prepared by AEMO, the then SP AusNet, CitiPower and Powercor was  provided  to  senior  officers  from DPCD  and DPI.14  This  briefing  outlined  the  planning process undertaken including consultation, and stressed that planning delays were at risk of prolonging a period of reduced security of electricity supply and increasing the likelihood of supply constraints for new development. 

    On 7 November 2011, a letter signed by AEMO, CitiPower and Powercor to the Minister for Planning requested that the planning permit be called in prior to it being considered by the City of Moreland.15 The letter indicated that the matter would be likely to proceed to VCAT. 

    The letter outlined the planning history and consultation process and identified the reasons for the call‐in as security of supply, the extent of consultation undertaken and the potential impact  of  delays  on  customers  and  communities.    The  request  was  supported  on  15 November 2011 by  the  former Minister  for Energy and Resources  in writing  to  the  former Minister for Planning.16 

                                                           12  In  relation  to  the  last point Council  also  commissioned  a peer  review of  the  EMF  issue which  generally 

    supported the application.  This is discussed further in Chapter 8. 13  Moreland original submission, para 54. 14  Document 15 in the Hearing. 15  A  copy  of  this  letter was  provided  to  the  Committee  as  part  of  the  request  for  information  from  the 

    Committee to DELWP (the ‘RFI package’). 16  Ibid. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 14 of 66 

    DPCD prepared documentation for the former Minister for Planning to enable the call‐in to take place.  They advised the Committee that: 17 

    Advice was subsequently received by DPCD from the Minister’s office that the preferred  course  of  action  was  a  planning  scheme  amendment  to  apply planning  controls  to  reflect  the  use  of  the  land  as  a  utility  installation  and enable the upgrade through an incorporated document. 

    The Department then provided a briefing to the former Minister which included a summary of  the  process  to  date  and  key  issues  and  three  options;  being  a  planning  scheme amendment under s20(4) of the Act, calling in the permit as requested, and no action.  The first option was presented as the preferred option.18 

    The  call‐in was  not  supported  in  the  briefing  on  the  basis  that  it would  not  address  the inappropriateness of the underlying planning controls for the site, particularly the residential zoning. 

    Amendment C140 to the Moreland Planning Scheme was approved by the former Minister for Planning on 3 February 2012 under section 20(4) of the Act and gazetted on 17 February 2015.19 The reasons given by the former Minister were:20 

    I consider that – 

    Compliance with any of the requirements of sections 17, 18 and 19 of the Act and the regulations is not warranted because:  The Amendment rezones the land to facilitate the development of the land 

    for the upgrade of the Brunswick Terminal Station.   This development has been the subject of a planning permit application that was fully advertised and that third parties were given an opportunity to comment on. 

    The  interests  of  Victoria  or  any  part  of  Victoria  make  such  an  exemption appropriate because:  The Amendment rezones the land to facilitate the upgrade of the Brunswick 

    Terminal Station which  is part of the Victorian transmission network.   The upgrade  is urgent to ensure the maintenance of a secure electricity supply to the Melbourne CBD and inner suburbs. 

    3.3.2 What the Amendment did The Amendment made the following changes to the Moreland Planning Scheme: 21 

    Rezoning 46 King Street, Brunswick East from Residential 1 Zone to Special Use Zone; 

                                                           17  DELWP Submission, Hearing Document 2.  The Committee questioned Ms Brockhouse of the nature of this 

    advice from the former Minister’s office and she advised that it was verbal advice. 18  A copy of the briefing was provided by DELWP to the Committee in the RFI package. 19  S20(4) of the Planning and Environment Act 1987 enables the Minister to prepare, adopt and approve an 

    Amendment without notice.  This is discussed further in Chapter 6. 20  Reasons  for  Decision  to  Exercise  Power  of  Intervention  Under  Section  20(4)  of  the  Planning  and 

    Environment Act 1987 Moreland Planning Scheme Amendment C140. 21  Moreland C140 Explanatory Report. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 15 of 66 

    Inserting Schedule 3 to the Special Use Zone;  Amending Schedule 1 to Clause 42.01 to introduce exemptions for buildings 

    and works carried out  in accordance with  the Brunswick Terminal Station Incorporated Document 2012; 

    Including  the Brunswick Terminal Station  Incorporated Document, 2012  in the Schedule to Clause 81.01. 

    The Explanatory Report described the need for the Amendment as follows: 

    To respond to the projected growth in electricity demand in Melbourne’s inner suburbs and CBD ‐ CitiPower, the Australian Energy Market Operator (AEMO) and  SP  AusNet  (together  are  referred  to  as  ‘the  proponent’)  propose  to upgrade the Brunswick Terminal Station to increase its capacity.  The upgrade is  required  by  summer  2014/2015  and  is  critical  to  providing  capacity  and security  of  supply  (sufficient  backup  arrangements  to  prevent  power disruptions) to the CBD network.  If the Brunswick Terminal Station upgrade is not  complete  by  summer  2014/2015,  the  proponent  has  advised  that  it  is almost inevitable that power interruptions will occur during periods of summer loading affecting one or more suburbs at a time. 

    The Incorporated Document included in Amendment C140 states that no permit is required to use and develop  the BTS  site  for a utility  installation, provided  that  it  is  carried out  in accordance with the conditions of the  Incorporated Document.   This  is further discussed  in Chapter 7. 

    3.4 Post ‐ Moreland Planning Scheme Amendment C140 Throughout early 2013, there was a significant amount of correspondence between Council, the Proponent  and  the MCRG  in  relation  to  tree  removal,  site management,  consultation and other issues.22 

    It became apparent during this time that a number of works required for the BTS were not covered by  the exemptions provided by  the  Incorporated Document and on 17  July 2013 AusNet Services requested that the former Minister undertake another Amendment to the Moreland Planning Scheme to allow a number of works that had already occurred.23 

    The then DTPLI sought Council’s view on such an Amendment, and Council advised in a letter dated 9 January 2014 that it did not support the requested Amendment.  Council advised the Committee that  it has never heard of the outcome of this request24, and a planning permit application was lodged by the Proponent soon after. 

    3.5 Planning permit application MPS/2014/87 The Committee is not reviewing the VCAT decision in accordance with its TOR.  The following information is provided for completeness. 

                                                           22  See Folder 2 provided by Council. 23  Council original submission, paragraph 63 onwards. 24   Ibid, paragraph 67. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 16 of 66 

    A  planning  permit  application  (MPS/2014/87)  was  lodged  by  AusNet  Services  (then  SP AusNet) for the following:25 

    Removal  of  vegetation,  construction  of  fences,  excavation works  at  depths greater  than  1  metre,  2  lot  subdivision  and  minor  alterations  for  the development  of  the  land  not  generally  in  accordance  with  the  Brunswick Terminal Station Incorporated Document 2012. 

    The application was considered by Council on 11 June 2014, who resolved to issue a permit with conditions; notice of  the decision  to grant a planning permit being  issued on 17  June 2014. 

    On 3 July 2014 the MCRG lodged an application for review with VCAT.  The matter was heard in August 2014 and VCAT ordered that a permit be  issued  in their decision of 4 September 2014.26 The permit was issued on 10 September 2014 and plans endorsed on 22 September 2014. 

    As  noted  by  Council  in  their  original  submission  to  the  Committee,  the  plans  endorsed through  the  2014  permit  process  depart  in  some  cases  from  those  included  in  the Incorporated Document.  Particularly relevant plans include:27  The Vegetation Removal Plan  Landscape Plan  Planting schedules. 

    3.6 Submissions on planning approvals process There were a range of views expressed  in submissions to the Committee  in relation to the planning approvals process.   These generally  fell  into  two major positions: support  for  the process as it occurred and particularly the s20(4) amendment from the electrical supply and distributions companies and regulator; and opposition to the Ministerial intervention on the basis that the planning process should have run its course from Council and the MCRG. 

    Some of the detailed  issues are outlined  in the process summary earlier  in this chapter but the two positions can be summarised briefly as follows. 

    Support for the process eventually followed based on the several avenues and opportunities of consultation undertaken; the redesign of the project to respond to community concerns; and the urgency of decision‐making given the stated threat to supply security. 

    Opposition  to  the  planning  process  as  it  evolved  was  grounded  in  opposition  to  the expansion of  the BTS  itself, but was particularly  focused on  the Ministerial  s20(4) process when the planning decision was taken away from the responsible authority.  Mr Rantino for Council restated this fundamental opposition:28 

                                                           25  There  were  a  number  of  other  minor  relatively  uncontroversial  permit  applications  including 

    MPS/2013/868, to retrospectively consider drainage works.  26  Merri Creek Residents Group Inc v Moreland CC [2014] VCAT 1099. 27  Council original submission, paragraph 82. 28  Moreland City Council original submission, paragraph 85. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 17 of 66 

    It would be a misunderstanding of Council’s decision to grant the 2014 permit or to endorse the plans to think that Council supported the expansion of the site.  Council did not and does not support the expansion of the site. 

    He submitted that as Council was not permitted to consult  in relation to Amendment C140 before  it  was  approved,  in  particular  in  relation  to  the  new  planning  controls  and  the Incorporated Document, Council considers that this resulted in the following:29 

    Planning  controls  that  were  not  clear  in  relation  to  planning  permit exemptions 

    The inclusion of a Construction Management Plan and associated planning enforcement  responsibilities  that  go  well  beyond  the  expertise  and resources of Council 

    The  inability  for  Council  to  defend  its  concerns  in  relation  to  the  health impacts  of  the  infrastructure  and  uphold  Council’s  Human  Exposure  to Electromagnetic Radiation Policy, February 2000 

    The  removal  of  the  requirement  for  the  project  to  satisfactorily demonstrate how  the buildings and works will  satisfy a policy of prudent avoidance  to  eliminate  any  health  effects  associated  with  exposure  to electromagnetic energy fields 

    A  landscape  plan  approved  in  the  Incorporated  Document  that  lacked detail,  was  ambiguous,  unclear  and  left  the  community  and  officers uncertain as to setbacks, trees to be retained and vegetation. 

    Council  further  stated  that  as  the  Construction  Management  Plan  (CMP)  has  been  the subject of numerous iterations and debate over the meaning of certain aspects, the Minister should be responsible for its enforcement. 

    The MCRG submitted similarly that the approval process was flawed for a number of reasons including:30  The process was unsatisfactory and led to a poor planning outcome  Consultation was poor and this contributed to the poor outcome  The former Minister’s intervention was unnecessary and unjustified  The process excluded the Group’s usual rights in the planning process and the ‘urgency’ 

    reason was an unsubstantiated assertion  The resulting amendment (C140) was flawed and has resulted in a planning control that 

    is inadequate, unclear, unfair, inflexible and (in some respects) unlawful  In approving the Amendment the former Minister failed to give adequate consideration 

    to environmental and health matters including EMF.31 

                                                           29  Council original submission, pages 26‐27 30  MCRG original submission paragraph 10. 31  Submissions were made on the extent to which planning decisions should consider environmental, health 

    and  amenity  issues,  for  example  see  the  Council  Hearing  submission  paragraph  18  onwards.    The Committee does not consider this was a contested issue and there is broad acceptance of considering such issues in planning.  The extent of consideration of course may be at issue in particular decisions. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 18 of 66 

    The  planning  process  through  the  initial  two  permit  applications  appears  to  have  been operating  as  it  should  under  the  Act,  albeit  with  apparently  growing  concern  from  the Proponents in relation to timing. 

    A key  issue  in submissions  in relation to the planning process was that of urgency.   AusNet Services  and  CitiPower  submitted  that  the  request  for  the  planning  permit  call  in, which resulted in the s20(4) amendment, was that the upgrade had become urgent and security of electricity supply was threatened (see 3.3.1 above). 

    The MCRG submitted that this substantial exaggeration of the true position was not borne out:32 

    As  far as  the group  is aware,  there were no  significant power  interruptions that occurred  in  the  summer of 2014/2015 within  inner Melbourne.   This  is despite  the  fact  that  the  BTS  Project  has,  as  a  result  of  the  actions  of  the operator  of  the  BTS,  still  not  been  completed  (and  indeed  had  barely  even been commenced in the summer of 2014/2015. 

    CitiPower submitted that the primary reason that the predictions of supply interruption and degraded supply security did not come to pass was because of the ‘work arounds’ that were undertaken when the planning process delays became apparent. 

    These,  it was  submitted, were  undertaken  jointly  by  CitiPower,  AusNet  Services,  Jemena Electricity Networks and United Energy, and included:33  Temporary 66kV powerlines in Kew and Malvern  A temporary additional 220kV transformer at Richmond Terminal Station  Operational switching on high demand days. 

    Mr Watt for CitiPower submitted that the first two ‘works arounds’ cost approximately $19 million, are temporary, and do not provide for a long term supply solution. 

    Mr Pitt for AusNet Services tabled in the Hearing Transmission Connection Planning Reports for 2011 and 2014. The Committee was  taken  through  the  relevant parts of  these  reports relating  to  the  BTS,  Richmond  Terminal  Station  and West Melbourne  Terminal  Station  in some detail by the Proponents and the MCRG to demonstrate their respective points of view about the necessity and timing of works. 

    Another  issue  raised  by  the MCRG  in  relation  to  the  planning  process  was  that  of  the transmission  lines  from  the BTS being upgraded due  to  the BTS expansion, but not being included in the BTS assessment itself.  A powerline under 220kV is defined as a ‘minor utility installation’ at clause 74 in the planning scheme and does not require a permit for use in the residential zones. 

    Mr Tweedie for MCRG submitted that there is a long history in planning and environmental assessment  of  including  the whole  of  a  project  in  the  assessment.    In  response Mr  Pitt submitted  that  as  the  sub‐transmission  lines  do  not  require  a  permit  under  the  planning scheme, then a permit is not required. 

                                                           32  MCRG original submission, paragraph 27. 33  CitiPower Hearing submission, paragraphs 19‐23. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 19 of 66 

    3.7 Discussion and conclusions One of the striking elements of the whole matter is how much work was undertaken on the network  regulatory  assessment  process  by  the  Proponent(s)  prior  to  a  planning  permit application  being  considered.    This  issue  is  discussed  in more  detail  in  Chapter  7  but  in essence  the Proponents had undertaken  several  years worth of  regulatory  approval work and  appeared,  in  the  early  stages  of  the  land  use  planning  process,  to  have  expected  a ‘rubber stamp’ on the initial planning permit application. 

    Whatever the relationship with the regulatory approval process, the Panel considers that the planning permit application processes with Council as  the  responsible authority appear  to have run as they should under the Act. 

    The  Committee  considers  that  the  planning  process,  and  the  public  scrutiny  of  the  BTS expansion  through  those  permit  processes,  has  demonstrably  resulted  in  a  better,  albeit considerably  more  expensive,  project  for  the  local  community  than  that  originally proposed.34 

    The Committee notes  that  two permit applications were  refused by Council  in  the  face of officer support, and despite the efforts at consultation by the Proponents.   Nothing can be read  in to this other than the normal Council process running  its course; no one sought to argue before the Committee that Council was not entitled to make the two refusal decisions. 

    However, in light of the first refusal, and the likelihood of the second refusal, the Committee also accepts and understands  the concerns of  the Proponents  in exploring other approval avenues; that is directly approaching the former Minister for Planning, to try and expedite a positive decision‐making outcome. 

    The Committee can see no  intent  in the Proponent’s request to the  former Minister other than  to  expedite  the  outcome  of  improving  security  of  supply  and  to  prevent  supply disruptions; both genuinely held concerns in the Committee’s view. 

    The question of need and urgency was subject to considerable submissions  in the Hearing.  The Committee was taken in great detail through network planning reports that were said to demonstrate, or not, whether the BTS upgrade was needed at all and whether it was needed in such a hurry. 

    While the Committee does not need to provide an answer to this specific question,  it does make the following observations:  Network planning and the supply of such critical  infrastructure has  long  lead times and 

    decisions on major asset upgrade and equipment are relatively inflexible35  The risks  in  ‘under‐servicing’ demand are apparent; over‐servicing has cost  implications 

    for  the  consumer  but  under‐servicing may  impose  critical  limitations  on  an  essential service 

    That there were no supply disruptions in the summer of 2014/2015 would appear to be plausibly  explained  by  ‘work  arounds’,  demand management,  and  to  some  extent,  a milder summer. 

                                                           34  The improvements are articulated in Chapter 4. 35  Mr Watt from CitiPower talked of the difficulty of delivery and lead times for transformers for example. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 20 of 66 

    In relation to the course of action taken by the former Minister for Planning in preparing and approving Moreland C140,  it  is  important  to  note  that  there  is  no  suggestion  before  the Committee  that  the  former Minister his  legal powers  in making  the  s20(4) decision.    If he had,  the  proper  place  to  challenge  this would  have  been  before  the  courts  and  no  such challenge has been made. 

    Why  the  former  Minister  chose  the  s20(4)  pathway  rather  than  calling  in  the  second planning  permit  from  VCAT  is  less  clear.    DELWP  in  their  submission  and  in  answering questions could not shed any light on the matter other than to say it was verbally requested from the former Minister’s office. 

    The  end  result,  and  it may  be  the  reason  for  the  s20(4)  approach,  although  this  is  pure speculation, was that any further consultation was excluded.36 If a permit is called in under s58 of Schedule 1 of  the Victorian Civil and Administrative Tribunal Act 1998, an Advisory Committee  under  s151  of  the  Planning  and  Environment  Act  is  usually  formed  with  an opportunity for public input to advise the former Minister on the permit application.37 

    Alternatively,  the route  taken via Amendment C140 can be seen as a  longer  term solution which provides  a  fundamentally more  appropriate  zoning  for  the  land  given  the BTS use.  However, as the post Amendment C140 permit applications and VCAT decision attest, it has still not been as efficient a process as the Proponents might have hoped. 

    Overall, and with the helpful benefit of hindsight, the decision of the former Minister to use s20(4)  of  the  Act  to  prepare  and  approve  Amendment  C140  appears  to  have  not  been particularly supportive of project delivery as it:  Approved planning  instruments  that were  flawed  to  some extent  (discussed  further  in 

    Chapter 7)  (Partly because of the above point) did not achieve the efficiency benefits desired by the 

    Proponents  in  the planning process as additional permit applications and eventually a VCAT hearing were still required 

    Led  to  significant  community  concern  due  to  the  lack  of  engagement  in  the  process compared to if the project as a whole had been argued in front of VCAT. 

    It is difficult not to conclude, although the Committee cannot be certain, that if following the refusal of the second permit application the matter had run its course through VCAT, that a similar  outcome might  have  been  achieved  in  a  shorter  timeframe  than  has  eventuated.  This of course is assuming that in the circumstances, VCAT had decided that a permit should be issued. 

    If  VCAT  had  refused  to  issue  a  permit,  the  use  of  s20(4)  as  a  ‘last  resort’  to  approve Amendment C140 or  a  similar Amendment would  still have been  available  to  the  former Minister. 

                                                           36  Mr Pitt at para 2.29 of the AusNet submission rightly noted that exclusion of consultation is not limited to 

    s20(4) in the Act. 37  This  is  the  same head of power  for  this Committee.   A number of  similar VCAT  call‐ins with  associated 

    Advisory Committees have been undertaken recently, for example for the Mt Buller‐Mt Stirling Link Road.  It  should  be  noted  that  such  an  Advisory  Committee  is  not  required  by  the  VCAT  Act  but  is  usually undertaken as a matter of convention. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 21 of 66 

    In relation to the  issue of whether sub‐transmission  lines, which are  ‘as of right’  in most  if not  all  zones,  should  have  been  included  in  the  application  and  assessment  process,  the Committee  notes  this  did  not  appear  to  be  an  issue  in  the  planning  permit  applications before Council  and  it was not  addressed  specifically  in  the Ministerial Amendment C140.  However the Committee is aware that there a body of law on this type of issue going back to at least the Pioneer Principle and it may require consideration in future.38 

    The difficulty  in describing what  the project actually  includes may be problematic  in both spatial and temporal terms given the timing of works and extent of the electricity grid. 

    3.8 Findings and recommendations Findings: 

    In relation to the planning approvals process, the Committee finds: 

    There were  no  apparent  fundamental  flaws  in  the  planning  permit  application process  and  consideration  of  the  permit  applications  by  the  Moreland  City Council. 

    In  hindsight,  the  justification  for  the  use  of  the  s20(4)  provisions  to  approve Moreland C140 on the material before the Panel does not appear strong; and it is not clear to the Committee why a s20(4) planning scheme amendment was used as opposed to the former Minister for Planning calling in the planning permit from the Victorian Civil and Administrative Tribunal. 

    Whether or not  it was  ‘the right decision’ of the former Minister for Planning to use s20(4) rather than allowing the matter to take its course through the Victorian Civil and Administrative Tribunal is a rather moot point, as the decision was made and has not been legally challenged by any party. 

    The planning instruments developed and implemented through Amendment C140 appear to have been poorly drafted, and to some extent reversed the efficiencies gained through the use of s20(4). 

    It is arguable that if the second planning permit application had been allowed to run  its  course, possibly  through  the Victorian Civil  and Administrative  Tribunal, that  the end outcome would have been achieved  in a similar  timeframe  to  that which  resulted, with more  transparency  for  the community; but  the Committee accepts  that at  the  time  the Proponent had genuine concerns as  to  the urgency and necessity of supply protection. 

    Recommendations: 

    In  relation  to  the  planning  approvals  process  the  Committee  does  not make  any  specific recommendations.   Recommendations  for  future planning processes  are  included  later  in this report. 

                                                           38  The Committee notes that the planning provisions around wind energy facilities have been changed in 2015 

    to  explicitly  include  the  transmission  lines  to  the  grid  from  a wind  farm  in  the  project  assessment  to acknowledge their potential impact. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 22 of 66 

    4 Consultation 4.1 Overview of processes Extensive  documentation  on  consultation  activities  undertaken  on  the  BTS  upgrade was provided to the Committee by Council (Folders 1 and 2), and  in other written submissions.  This  included  accounts  of  the  processes  undertaken  by  the  Council,  AusNet  Services, CitiPower  and  AEMO,  and  stakeholder  responses.    Professor  Whitzman  submitted  an assessment of  the adequacy and appropriateness of  the  consultation process and offered comments on alternative approaches.   Several members of the MCRG also made  individual submissions. 

    The Committee reviewed all submissions and also considered some recent policy documents relevant to the BTS upgrade.  Most of these were tabled or cited at the Hearing. 

    A summary of the main consultation activities and impacts on design outcomes is shown in Table 2.  This provides an overview of community consultation and participation since 2010. 

    Submissions  are  discussed  in  detail  in  sections  4.2  to  4.5  and  an  overall  discussion  and recommendations are included in sections 4.6 and 4.7. 

    4.2 Pre‐Moreland C140 processes Relevant activities prior to community consultation commencing in 2010 were noted:  Following a decision by the Essential Services Commission to approve the upgrade of the 

    BTS  in 2008,  two written  submissions were  received, both  from power  companies.   A related 2008 CitiPower  report  recommending upgrade of  the BTS was available  to  the public.39 

    SP  AusNet wrote  to  the  Council  on  6  August  2009  regarding  proposals  to  construct fencing  and  undertaken  landscape  works.    Consultation  was  not  discussed.    The upcoming planning permit application for the upgrade was also not discussed. 

    SP AusNet c/‐ Aurecon lodged a planning permit application for a $58 million upgrade of the BTS on 7 December 2009.  No consultation was documented in the application or in the associated Aurecon Development Application of 12 November 2009.   The proposal included a series of additional towers and overhead wires. 

    The  Council wrote  to Aurecon  on  4 March  2010  indicating  that  any  requirements  for advertising would be advised.  

                                                           39  CitiPower submission 15 May 2015, p6. 

  • Brunswick Terminal Station  Advisory Committee Report  21 August 2015 

    Page 23 of 66 

    Table 2  Summary of BTS consultation activities and outcomes: from 2010 

    Date/ C140 stage 

    Community stakeholders involved  

    Consultation Stat/Non Stat * 

    Proposal/ issues  Community inputs  Impact on design outcomes 

    Source 

    Pre C140             

    Mar‐Jun 2010 

    Adjacent owners/ occupiers, 3 stakeholder organisations (including MCMC). 

    Stat: Notices at site, in media, sent to stakeholder organisations, one community meeting (31/5/10). 

    Dec 2009 application for planning permit: proposed $58m upgrade including 12 new 26 m pylons. Issues: Alternative options, impacts on visual amenity, noise, landscaping, nature of works, health. 

    16 initial objections and 26 more after 31 May meeting.  No consensus at meeting.  Subsequently a total of over 200 objections. 

    Proponent committed�