Brock Environmental Center - Presentation from July 16, 2013 Open House

4
Primary Construction Route Park Access Park Access Public Parking Secondary Construction Route www.houriganconstruction.com www.cbf.org Park Access

description

Presentation by Hourigan Construction on construction plans for the Chesapeake Bay Foundation's Brock Environmental Center at Pleasure House Point 7/16/13

Transcript of Brock Environmental Center - Presentation from July 16, 2013 Open House

Page 1: Brock Environmental Center - Presentation from July 16, 2013 Open House

Primary Construction

Route

Park Access

Park Access

PublicParking

Secondary Construction

Route

www.houriganconstruction.com www.cbf.org

Park Access

Page 2: Brock Environmental Center - Presentation from July 16, 2013 Open House

CONSTRUCTION ENTRANCE AND DELIVERY SIGN & PROJECT RENDERING

SAFETY RULES SIGN

& SECURITY GATE

SECURITY CAMERA

CONSTRUCTION PARKING

HOURIGAN & CBF PROJECT TRAILERS

SECURED STORAGE

CONSTRUCTION-USE SOLAR ARRAY

RECYCLE/LOADING AREA SECURITY LIGHTING

DIRECTION OF CONSTRUCTION

SECURITY LIGHTING

SECURITY LIGHTING

EROSION AND SEDIMENT FENCE

TEMPORARY POWER/SANITARY FACILITIES

BROCK ENVIRONMENTAL CENTER SITE UTILIZATION PLAN

EXISTING SWING-GATE TO REMAIN DURING CONSTRUCTION

STRUCTURAL ERECTION ROAD -

8’ STONE WITH GEO TEXTILE FABRIC

www.houriganconstruction.com www.cbf.org

Page 3: Brock Environmental Center - Presentation from July 16, 2013 Open House

Construction Means and Methods

www.houriganconstruction.com www.cbf.org

Noise Reduction•Activitiesproducinghigherlevelsofnoisewillbeperformedbetweenthehoursof9:00amand3:30pmMondaythroughFriday

Green Construction Processes Utilized to Reduce Carbon Footprint•Onsitewatermanagement•Noonsiteconstructionparking•Solarpanelarrayfortemporaryconstructionpower•Waterwellfortemporaryconstructionwater•Pollutionreductionmethodsutilizedonequipment•Containmentareasaroundtemporarytoilets•Minimizeuseoffossilfuelequipment

Public Parking and Access to Park•ParkingattheCitypumphouseorMarlinBayDrive•Accesstoparkidentifiedviasignage

Construction Traffic•Primaryconstructionroute:ShoreDr.toE.Stratford•Constructionhours:MondaythroughFriday6:30am–5:00pm•ConstructionparkingattheCitypumphouse•Dustcontrolmethods

Safety & Security•6’tallsecurityfence•Motionsensorlighting•Webbasedsecuritycamera

Page 4: Brock Environmental Center - Presentation from July 16, 2013 Open House

Construction Schedule (as of July 16, 2013)

Brock Environmental Center

Construction Activity Start Date Completion DateTotal Construction 08/05/13 07/30/14

Fencing & Gates 08/05/13 08/16/13Construction Trailers 08/12/13 08/16/13Clearing & Construction Roads 08/19/13 08/30/13Concrete Structure 08/28/13 10/18/13Site Utilities 09/02/13 10/25/13Steel Structure 10/28/13 11/29/13Interior Construction 12/30/13 04/04/14Pier 01/01/14 05/01/14Site Work 02/17/14 04/11/14Chesterfield Road Waterline 04/07/14 04/18/14Marlin Bay Path 05/01/14 08/01/14Complete Construction 07/30/14 07/30/14

CBF Occupancy Late Summer Early Fall