Bristol BF 021-1(33)Regional Concerns MeetingVT Route 116 – Bridge #12 over Baldwin CreekApril 27, 2015
![Page 2: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/2.jpg)
Introductions
Jennifer Fitch, P.E.VTrans Project Manager
Laura Stone, P.E.VTrans Scoping Engineer
Carolyn Carlson, P.E.VTrans Senior Project Manager
![Page 3: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/3.jpg)
Purpose of Meeting
Provide an understanding of our approach to the project
Provide an overview of project constraints Discuss alternatives that were considered Provide an opportunity to ask questions and
voice concerns Foster support for the recommended
alternative
![Page 4: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/4.jpg)
Location Map
![Page 5: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/5.jpg)
Bridge 12Project Location
![Page 6: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/6.jpg)
Meeting Overview
VTrans Project Development Process Project Overview
– Existing Conditions– Alternatives Considered– Selected Alternative
Maintenance of Traffic Schedule Questions
![Page 7: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/7.jpg)
VTrans Project Development Process
Project Definition
Project Design Construction
Project
Funded
Project
Defined
Contract
Award
Quantify areas of impact
Environmental permits
Develop plans, estimate and specifications
Right-of-Way Process (if needed)
Initiated
Identify resources & constraints
Evaluate alternatives Public participation Build Consensus
![Page 8: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/8.jpg)
Who are you representing?
A. Municipal Official
B. Resident
C. Emergency Services
D. Local Business
E. Independent Organization
F. Other
A. B. C. D. E. F.
44%
25%
31%
0%0%0%
![Page 9: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/9.jpg)
How often do you use this segment of VT Route 116?
A. Daily
B. Weekly
C. Monthly
D. Rarely
E. Never
Daily
Wee
kly
Month
ly
Rarel
y
Never
13%
31%
0%
31%
25%
![Page 10: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/10.jpg)
How often do you walk over the bridge?
A. Daily
B. Weekly
C. Monthly
D. Rarely
E. Never
Daily
Wee
kly
Month
ly
Rarel
y
Never
0%6%
69%
25%
0%
![Page 11: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/11.jpg)
How often do you bike over the bridge?
A. Daily
B. Weekly
C. Monthly
D. Rarely
E. Never
Daily
Wee
kly
Month
ly
Rarel
y
Never
0% 0%
56%
31%
13%
![Page 12: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/12.jpg)
What is your reason for attending this meeting?
A. Specific concern
B. General Interest
C. Live in close vicinity
D. Other
0%
94%
6%0%
![Page 13: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/13.jpg)
Project Overview
Existing Conditions
Alternatives Considered
Recommended Alternative
![Page 14: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/14.jpg)
Description of Terms Used
Beams (Superstructure)
Deck
Abutment (Substructure)
Bridge Rail
Cross Section of Bridge
![Page 15: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/15.jpg)
Existing Conditions – Bridge #12
Roadway Classification – Minor Rural Arterial Superstructure – 89’ long Steel Beam Bridge Substructure – Skeletal Abutments Constructed in 1955 Ownership – State of Vermont
![Page 16: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/16.jpg)
Existing Conditions – Bridge #12
The existing concrete deck is in poor condition. There have been pop-outs in the past, and future deck pop-outs are possible at any time.
Deck geometry is substandard.
The roadway is not banked sufficiently for the horizontal curve present.
Bridge railing is substandard.
![Page 17: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/17.jpg)
Existing Conditions - Bridge #12
Deck Rating 4 (Poor) Superstructure Rating 7 (Good) Substructure Rating 6
(Satisfactory) Channel Rating 7 (Good)
Continual deck deterioration with large delaminations and exposed rebar
![Page 18: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/18.jpg)
Existing Conditions - Bridge #12
Bridge Railing– Not Crash tested– Deteriorated posts, Exposed Reinforcing
Steel
Bridge Railing
![Page 19: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/19.jpg)
Looking South Over Bridge
Existing Conditions - Bridge #12
Substandard Horizontal Curve Substandard Deck Geometry
– Existing: 11’/4’– Standard: 11’/5’
![Page 20: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/20.jpg)
Existing Conditions
![Page 21: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/21.jpg)
ADT of 2,800 DHV of 320 % Trucks: 15.7 Design Speed of 50 mph Archaeological resources in 3 quadrants
Design Criteria and Considerations
![Page 22: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/22.jpg)
No Action– Additional maintenance required within 10 years
Rehabilitation – Deck Patching– Deck and substructure patching with anodes– Shortest design life– Substandard width and railing
Rehabilitation – Deck Replacement– Longer lifespan compared to patching– Substructure patching with anodes– Width and railing brought up to standard
Full Bridge Replacement– Longest design life– Meets all geometric criteria
Alternatives Considered – Bridge #12
![Page 23: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/23.jpg)
Selected Alternative - Bridge #12
Replace existing deck – Bridge widened by 1 foot on each side to meet
standard– New approach railing and bridge railing– New joints– Meets all geometric criteria– 40 year design life– Utility relocation will be needed– No ROW needed
![Page 24: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/24.jpg)
Proposed Typical Sections Proposed Bridge Rail to Rail = 32’ (Existing is 30’)
![Page 25: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/25.jpg)
Proposed Layout
![Page 26: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/26.jpg)
Maintenance of Traffic Options Considered
Road Closure with Offsite Detour– Signed by State, regional detour route: 61.3 miles end-to-end
Phased Construction– Minimal impacts to adjacent properties, wetlands, and wooded
areas– Longer construction duration– No ROW needed
Temporary Bridge– One-way with signals, downstream– Biggest impacts to ROW, adjacent properties, and archaeological
resources
![Page 27: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/27.jpg)
Phased Construction One lane, alternating, with a traffic
signal Existing is wide enough to complete
deck replacement with 2 phases No ROW needed
(Picture from US Route 7 Bridge 184 in Highgate)
Selected Maintenance of Traffic
![Page 28: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/28.jpg)
Phase 1 Layout
![Page 29: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/29.jpg)
Phase 2 Layout
![Page 30: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/30.jpg)
Which would you be most concerned about?
A. Construction delays on VT Route 116
B. Bridge Aesthetics
C. Environmental Impacts
D. Recreational Impacts
E. Other
F. Not really concerned
A. B. C. D. E. F.
31%
0%
46%
0%0%
23%
![Page 31: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/31.jpg)
Which design aspect is the most important to you?
A. Shoulder width/bicycle accommodations
B. Aesthetics - Bridge Railing
C. Construction year
D. Construction Duration
E. Cost
F. Other
A. B. C. D. E. F.
45%
18%
0%
18%18%
0%
![Page 32: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/32.jpg)
Preliminary Project Schedule
Construction – Summer 2017 or 2018
![Page 33: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/33.jpg)
Project Summary
Replace deck:– Phased construction
• 2 Phases
– Bearing replacement as necessary– Substructure concrete patching as necessary– Utility relocation will be needed– No ROW needed
![Page 34: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/34.jpg)
Did you find this presentation to be?
A. Too technical in nature
B. Too simplified
C. Just about right
D. Not much use at all
Too te
chni
cal i
n nat
ure
Too si
mplif
ied
Just
about
right
Not m
uch u
se a
t all
0% 0%
100%
0%
![Page 35: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/35.jpg)
Do you find the recommended scope of work satisfactory?
A. Yes
B. No
Yes No
0%
100%
![Page 36: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/36.jpg)
Bristol BF 021-1(33)Questions and CommentsVT Route 116 – Bridge #12 over Baldwin Creek
April 27, 2015
For more information: https://outside.vermont.gov/agency/vtrans/external/Projects/
Structures/13B256
![Page 37: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/37.jpg)
Bristol BF 021-1(33)
Alt 1 Alt 2 Alt 3
Deck Patching Deck Replacement Full Bridge Replacement
Short Term Lane Closures a. Offsite Detour b. Phasing a. Offsite Detour b. Phasing c. Temporary
Bridge
Total Project Costs (including Engineering and Contingencies)
$631,750 $1,077,450 $1,432,000 $2,805,000 $3,219,000 $3,120,040
Project Development Duration 2 years 2 years 2 years 2 years 2 years 4 years
Construction Duration 3 months 3 months 8 months 6 months 9 months 18 months
Closure Duration (If Applicable) N/A 10 days N/A 4 weeks N/A N/A
Geometric Design Criteria Substandard width Meets Criteria Meets Criteria Meets Criteria Meets Criteria Meets Criteria
Alignment Change No No No No No No
Utilities No Change Possible Relocation
Possible Relocation Relocation Relocation Relocation
ROW No No No No No Yes
Design Life 15 Years 40 years 40 years 80 years 80 Years 80 Years
Alternatives Matrix
![Page 38: Bristol BF 021-1(33) Regional Concerns Meeting VT Route 116 – Bridge #12 over Baldwin Creek April 27, 2015.](https://reader036.fdocuments.us/reader036/viewer/2022062517/56649f355503460f94c52725/html5/thumbnails/38.jpg)
Additional Considerations
None for this project