Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM...
Transcript of Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM...
![Page 1: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/1.jpg)
12/25/06 EVM Introduction 1
12/25/06 EVM Introduction 1
Brief Introduction toEarned Value Management (EVM)
![Page 2: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/2.jpg)
12/25/06 EVM Introduction 2
12/25/06 EVM Introduction 2
Outline
• Introduction to the basic rationale and elements of EVM
• Issues of actually implementing an EVM tracking scheme
• Background materials
![Page 3: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/3.jpg)
12/25/06 EVM Introduction 3
12/25/06 EVM Introduction 3
The Problem
• A successful program manager says: “We completed the project we promised to deliver in the time we promised and with the budget we asked for.”
• The standard source of information about the status of the project is the status of the budget, which only tells you how quickly and how completely you are spending the money you have.
• What you really want to track is how quickly and how completely you are accomplishing the work you promised to do.
• The coupling of money spent to work done or schedule consumed is loose and nonlinear.
• Also, the expenditure track is a one-dimensional projection of a two-dimensional problem.
ScheduleVariance
BudgetVariance
(under)
(over)
(ahead)(behind)
![Page 4: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/4.jpg)
12/25/06 EVM Introduction 4
12/25/06 EVM Introduction 4
Why You Need to Know BothCost and Schedule Variances
• Project A is in good shape, under budget and ahead of schedule.• Project B is over budget, but if we realize
it is ahead of schedule, we canslow the effort to save money.
• Project D’s cost variance looks better than A’s, but if we realize it is behind schedule, we can spend more to catch up.
• Project C looks just like B if we only look at the cost variance, but we can’t slow down to save money.And it looks just like D if we only look at schedule, but we can’t spend more to catch up. It’s time to rescope!
ScheduleVariance
BudgetVariance(under)
(over)
(ahead)(behind)
A
BC
D
![Page 5: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/5.jpg)
12/25/06 EVM Introduction 5
12/25/06 EVM Introduction 5
1. DEFINE THE WORK AND ORGANIZE TEAMS
100
4060
1525
3030
2. SCHEDULE THE WORK
3. ALLOCATE BUDGETS
$
CONTRACT BUDGET BASE
TIMEBASELIN
E
So What Do We Have to Work With?
MANAGEMENT RESERVE (MR)
Each chunk of work corresponds to a chunk of budget and a chunk of schedule.
![Page 6: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/6.jpg)
12/25/06 EVM Introduction 6
12/25/06 EVM Introduction 6
• For each chunk of work, define its ‘value’ as the budget assigned to it.
• When you complete that chunk of work, you have ‘earned’ its value.
• The total earned value to date gives you a point on the ($,time)graph – the Budgeted Cost of Work Performed (BCWP).
• You could compare this to the actual amount of work that you were supposed to have completed by this point in the schedule, as measured by its budgeted cost – the Budgeted Cost of Work Scheduled (BCWS), another point on the ($,time) graph.
• You could also compare it to the actual amount spent to complete the chunks of work done to date – the Actual Cost of Work Performed (ACWP), a third point on the ($,time) graph.
• Look at what information these comparisons give about the status of the project.
The Basic Idea
![Page 7: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/7.jpg)
12/25/06 EVM Introduction 7
12/25/06 EVM Introduction 7
Budgeted Cost of Work Scheduled(BCWS)
Total Budget = $5,000to be spent over 5 monthsWe plan to deploy 1 standeach month at an estimated cost of $1,000.BCWS each month = $1,000Month 1
BCWS = $1,000
Month 4BCWS = $1,000
Month 3BCWS = $1,000
Month 5BCWS = $1,000
Month 2BCWS = $1,000
Each dollar of BCWS represents a specific dollar of work scope. BCWS is aggregated and summed as the performance measurement baseline.
Each dollar of BCWS represents a specific dollar of work scope. BCWS is aggregated and summed as the performance measurement baseline.
![Page 8: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/8.jpg)
12/25/06 EVM Introduction 8
12/25/06 EVM Introduction 8
Budgeted Cost of Work Performed(BCWP)
We’re at the end of thesecond month, but only1 stand is complete. Value of work performed = $1,000
You earn value the same wayas it was budgeted in the baseline.
You earn value the same wayas it was budgeted in the baseline.
![Page 9: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/9.jpg)
12/25/06 EVM Introduction 9
12/25/06 EVM Introduction 9
Schedule Variance(SV)
BC WSBC WP
Of the work we scheduled to have done,how much did we budget for it to cost?
Of the work we actually performed,how much did we budget for it to cost?
SCHEDULE VARIANCE is the difference between work scheduled and work performed (expressed in terms of budget dollars)
formula: SV $ = BCWP - BCWS
example: SV = BCWP - BCWS = $1,000 - $2,000 SV= -$1,000 (negative = behind schedule)
SCHEDULE VARIANCE is the difference between work scheduled and work performed (expressed in terms of budget dollars)
formula: SV $ = BCWP - BCWS
example: SV = BCWP - BCWS = $1,000 - $2,000 SV= -$1,000 (negative = behind schedule)
BU
DG
ET B
ASE
D
![Page 10: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/10.jpg)
12/25/06 EVM Introduction 10
12/25/06 EVM Introduction 10
Schedule Variance(SV)
$
5 months
BCWS“the baseline”
BCWP“earned value”
TIME
5,000
sv
![Page 11: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/11.jpg)
12/25/06 EVM Introduction 11
12/25/06 EVM Introduction 11
Actual Cost of Work Performed(ACWP)
Labor came to $1,300,and materials cost$1,100. That first standcost $2,400!
actual expenditures vs. budgetactual expenditures vs. budget
![Page 12: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/12.jpg)
12/25/06 EVM Introduction 12
12/25/06 EVM Introduction 12
Cost Variance(CV)
BC WPAC WP
Of the work we actually performed,how much did we budget for it to cost?
Of the work we actually performed,how much did it actually cost?
COST VARIANCE is the difference between budgeted costand actual cost
formula: CV $ = BCWP - ACWP
example: CV = BCWP - ACWP = $1,000 - $2,400 CV= -$1,400 (negative = cost overrun)
COST VARIANCE is the difference between budgeted costand actual cost
formula: CV $ = BCWP - ACWP
example: CV = BCWP - ACWP = $1,000 - $2,400 CV= -$1,400 (negative = cost overrun)
PER
FOR
MA
NC
E B
ASE
D
![Page 13: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/13.jpg)
12/25/06 EVM Introduction 13
12/25/06 EVM Introduction 13
Cost Variance(CV)
$
TIME 5 months
BCWP“earned value”
ACWP“actual cost”
5,000
cv
![Page 14: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/14.jpg)
12/25/06 EVM Introduction 14
12/25/06 EVM Introduction 14
Note That We Can IsolateSchedule and Cost Variances
schedule variance = BCWP - BCWS = negative numbercost variance = BCWP - ACWP = negative number
behind schedule,over cost
behind schedule,over cost
5 months
BCWS
BCWP
ACWP
TIME
5,000
svcv
$
![Page 15: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/15.jpg)
12/25/06 EVM Introduction 15
12/25/06 EVM Introduction 15
Where are the significant problems?
WBS DESCRIPTION Proj Ofcr %Comp %Spent CPI CV CV CV % VAC VAC
1 3600 PCC Zepka 28.99 34.09 0.850 ↑ -296.2 -17.62 ↔ -187.2
2 3200 COMMUNICATIONS Tideman 34.63 41.03 0.844 ↓ -130.8 -18.49 ↔ -87.0
3 G&A GEN & ADMIN 33.67 36.11 0.932 ↓ -45.2 -7.26 ↔ -36.8
4 2200 SYS ENGINEERING Price 85.04 94.35 0.901 ↓ -26.4 -10.95 ↔ 0.0
5 3800 I & A Troop 35.40 37.08 0.955 ↓ -24.2 -4.75 ↔ -24.8
6 2100 PROJ MANAGEMENT Brown 45.70 48.51 0.942 ↔ -17.4 -6.16 ↔ -3.2
7 2300 FUNC INTEGRA Price 71.62 75.23 0.952 ↓ -17.4 -5.03 ↔ -30.8
8 5200 MANAGEMENT DATA Simmons 84.18 98.10 0.858 ↓ -13.2 -16.54 ↑ -16.0
9 3100 SENSORS Smith 20.87 21.49 0.971 ↓ -10.6 -2.94 ↔ -21.6
10 4000 SPARES Blair 17.87 18.90 0.945 ↑ -7.8 -5.78 ↔ -6.2
11 6200 SYSTEM TEST Hall 60.82 61.66 0.986 ↑ -5.6 -1.38 ↔ -2.0
12 5100 ENG DATA Novak 38.51 52.80 0.729 ↓ -4.6 -37.10 ↔ 0.0
13 MR MGT RESERVE 0.00 0.00 0.0 ↔ 439.2
14 UB UNDIST BUDGET 0.0 0.0
15 COM COST OF MONEY 0.0 0.0
16 3700 DATA DISPLAY Troop 41.13 41.13 1.000 ↔ 0.0 0.00 ↔ 0.0
17 OV OVERHEAD 0.0 0.0
18 6100 TEST FACILITIES Smart 100.00 98.02 1.020 ↔ 2.0 1.98 ↔ 0.0
19 3500 COMP PROGRAMS Pino 46.46 44.66 1.040 ↓ 3.4 3.87 ↔ -1.4
20 6300 PCC TEST Bond 23.13 22.64 1.021 ↓ 4.2 2.10 ↔ 0.0
21 3400 ADPE Zepka 41.89 39.79 1.053 ↓ 12.6 5.02 ↔ 4.6
22 3300 AUX EQUIP Tideman 27.57 24.33 1.133 ↓ 78.2 11.73 ↓ 8.4
sorted by CV ($)By tracking and sorting on variances, we can isolate the troublesome WBS elements.
![Page 16: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/16.jpg)
12/25/06 EVM Introduction 16
12/25/06 EVM Introduction 16
COST PERF INDEX (CPI) = BCWPACWP
SCHED PERF INDEX (SPI) = BCWPBCWS
COST PERF INDEX (CPI) = BCWPACWP
SCHED PERF INDEX (SPI) = BCWPBCWS
1.0
.9
1.1
“GO
OD
”“B
AD
”
1.2
.8
CPI
SPI
TIME
Performance Indices
We can also get a sense of the overall performance of the project by tracking performance indices.
![Page 17: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/17.jpg)
12/25/06 EVM Introduction 17
12/25/06 EVM Introduction 17
Budget at Completion(BAC)
$
time
BACsum of all BCWS =
$
$
$$
$
$
$
When all work has been phased, the cumulative BCWS = BACe.g., $5,000 = $5,000
When all work has been phased, the cumulative BCWS = BACe.g., $5,000 = $5,000
$5,000$5,000
The most important markers of the overall performance of the project look at predictions of the variances at the end. These require several quantities, the first being the Budget at Completion.
![Page 18: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/18.jpg)
12/25/06 EVM Introduction 18
12/25/06 EVM Introduction 18
• Estimate at Completion (EAC)
– defined as actual cost to date + estimated cost of work remaining– usually develop comprehensive EAC at least annually
• reported by WBS in cost performance report
– should examine on monthly basis– consider the following in EAC generation:
• performance to date• impact of approved corrective action plans• known/anticipated downstream problems• best estimate of the cost to complete remaining work
– also called latest revised estimate (LRE), indicated final cost, etc.
What will be the final cost?
ACWP + ETC = EAC
![Page 19: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/19.jpg)
12/25/06 EVM Introduction 19
12/25/06 EVM Introduction 19
Getting the Estimate at Completion
Just a few little glitches…. We should be able to do the complete job….ack…
let’s see, for about $7,500
![Page 20: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/20.jpg)
12/25/06 EVM Introduction 20
12/25/06 EVM Introduction 20
• Common EAC Formulae:
EAC = BAC/CPI
= ACWPcum + Budgeted Cost of Work RemainingCPI3
= ACWPcum + Budgeted Cost of Work Remaining.8(CPI) +.2(SPI)
= ACWPcum + Budgeted Cost of Work RemainingCPI * SPI
Determining EAC via Statistics
![Page 21: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/21.jpg)
12/25/06 EVM Introduction 21
12/25/06 EVM Introduction 21
Other methods of EAC calculation
• “Grass Roots” or formal EAC
– detailed build-up from the lowest level detail– hours, rates, bill of material, etc.
• Average of statistical formulae
• Show range of EACs (optimistic, most probable, pessimistic)
• Complete schedule risk analysis for remaining work, estimate work remaining
![Page 22: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/22.jpg)
12/25/06 EVM Introduction 22
12/25/06 EVM Introduction 22
Variance at Completion(VAC)
VARIANCE AT COMPLETION is the difference between what the total job is supposed to cost and what the total job is now expected to cost.
FORMULA: VAC = BAC - EAC
Example: VAC = $5,000 - $7,500VAC = - $2,500 (negative = overrun)
VARIANCE AT COMPLETION is the difference between what the total job is supposed to cost and what the total job is now expected to cost.
FORMULA: VAC = BAC - EAC
Example: VAC = $5,000 - $7,500VAC = - $2,500 (negative = overrun)
B AC
E AC
what the total job is supposedto cost
what the total job is expectedto cost
![Page 23: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/23.jpg)
12/25/06 EVM Introduction 23
12/25/06 EVM Introduction 23
Variance at Completion(VAC)
VAC = Budget at Completion - Estimate at Completion= BAC - EAC
$
BAC
EACVAC
TIME
![Page 24: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/24.jpg)
12/25/06 EVM Introduction 24
12/25/06 EVM Introduction 24
• Variance at Completion vs. Contractor Loss– Positive VAC:
• EAC < BAC underrun contractor gain
– Negative VAC:• EAC > BAC share area contractor partial loss• EAC > ceiling overrun contractor loss (100%)
• Government develops top level EAC for comparison– Government will limit progress payments if EAC is greater than
ceiling– Government needs forecast of fund requirements
• May still have time to change the final outcome
VAC is Particularly Importantfor Government Contracts
![Page 25: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/25.jpg)
12/25/06 EVM Introduction 25
12/25/06 EVM Introduction 25
• A survey of over 800 military programs showed that no program ever improved performance better than the following EAC calculation:
EAC = BAC/CPI,
at the 15%-complete point in the program.
• Thus, there is strong empirical evidence that EVM translates early information into essential guidance for program re-baselining.
Probably the BiggestSelling Point for EVM
![Page 26: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/26.jpg)
12/25/06 EVM Introduction 26
12/25/06 EVM Introduction 26
EVM Analyses
PCUM
Term Formula
Percent Complete
Cost Performance Indexor Performance Factor
Checklist ActionsRatio of work accomplished in terms of the total amount of work to do.
Symbol% Done
CPI or PF
TCPI or VF
BCWPBAC
Average PerformanceBCWPcum
Duration (wks or mos) Since ACWP Began
BCWPcumDuration (wks or mos)
From Time Now to Manager's Stated Completion Date
SC or S/CSchedule Correlation
BCWPACWP
Ratio of work accomplished against money spent (an efficiency rating: Work Done for Resources Expended)
To CompletePerformance Index
or Verification Factor
BAC - BCWPEAC - ACWP
Ratio of work remaining against money remaining (Efficiency which must be achieved to complete the remaining work with the expected remaining money)
Schedule Performance Index SPI Ratio of work accomplished against what should have been done (Efficiency Rating: Work done as compared to what should have been done)
BCWPBCWS
SV
Ratio of Schedule Variance (SV) in terms of average amount of work accomplished (in weeks or months). It indicates a correlation to program true schedule condition
IEACIndependent EstimateAt Completion
BACPF
Calculation of a projected Estimate At Completion to compare with the CAM's Estimate At Completion:1) Ration of total work to be done against experienced cost efficiency2) Sunk costs added to a ratio of remaining work against weighted cost and schedule efficiencies
1)
2)BAC - BCWP.8CPI + .2SPI
ACWP +
Average Expected Performance To Finish
Average rate at which work has been accomplished since work began
Average rate at which work must be accomplished in the future to finish on the date the CAM has forecasted for completion of the work.PTO GO
PCUM
There are a wide variety of indicators to play with in EVM.
![Page 27: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/27.jpg)
12/25/06 EVM Introduction 27
12/25/06 EVM Introduction 27
EVM Analyses
• Sort on significant variances– eliminate almost complete, just starting, etc.
• Graph and analyze trends• Look at comparative data
– e.g. cumulative performance vs. projected performance• Examine written analysis by contractor
– does it answer why?– adequacy of corrective action plans
• Analysis of schedule trends, critical path• Analysis of EAC realism
what are the drivers?what can we do about them?what are the drivers?what can we do about them?
There are a wide variety of analytic techniques to play with in EVM.
![Page 28: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/28.jpg)
12/25/06 EVM Introduction 28
12/25/06 EVM Introduction 28
Graphical EVM Analyses
Dollars In M
illions
Estimates at Completion MEGA HERZ ELEC & VEN F04695-86-C-0050 RDPR FPI
Element: 3600 Name: PCC
BACLRECUM CPI
1992APR MAY JUN JUL AUG SEP OCT NOV DEC
1993JAN
5.0
6.0
7.0
8.0
5.1 5.4 5.1
5.1 5.4 5.7
5.1 5.4 5.9
5.1 5.4 6.0
5.1 5.5 6.3
5.1 5.5 5.8
5.1 5.5 6.5
5.5 5.7 7.6
5.5 5.7 6.8
5.8 6.0 6.8
MEGA HERZ ELEC & VEN Cost/Schedule VarianceF04695-86-C-0050 MOH-2 RDPR FPI POP: 01 MAR 1992 - 15 SEP 1993
Percent of D
ollars
COST VARIANCESCHEDULE VARIANCE
1992MAY JUN JUL AUG SEP OCT NOV DEC
1993JAN
-30.0
-20.0
-10.0
0.0
10.0
20.0
30.0
Cost Drivers, Cause
Dollars In MillionsBCWSBCWPACWP
CVSV
0.3 0.2 0.2 0.0 -0.1
0.6 0.5 0.5 -0.0 -0.1
1.0 0.9 0.9 -0.0 -0.1
1.4 1.4 1.5 -0.1 -0.0
2.2 2.2 2.2 0.0 -0.0
2.5 2.7 3.0 -0.3 0.2
4.2 3.8 4.2 -0.5 -0.4
5.6 5.3 5.6 -0.3 -0.3
7.3 6.9 7.3 -0.5 -0.4
At CompletionKTR PO
20.8 20.8
20.8 20.8 20.8 23.0 0.0 -2.2
PMB: 20.4 % COMP: 32.9 MR: 0.4 KTR MR LRE: 0.0 PO MR LRE: 0.0CURRENT FUNDING: 10.0
PO EPC: 24.0PROJ FUNDING: 23.0
AS OF: JAN 93OPR: MR B. TECH
PROGRAM: Mohawk Vehicle
0%
-11%-7%-6%
Overall cost and schedule trend
EAC realism
graphs show overall trend...are you getting better,
or worse?
graphs show overall trend...are you getting better,
or worse?
![Page 29: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/29.jpg)
12/25/06 EVM Introduction 29
12/25/06 EVM Introduction 29
Will the contractor come in on budget?
COST PERFORMANCE INDEX:
CPI = cost efficiency for work performed to date(The value of work accomplished for each dollar spent)
$1000= = = $2400 = .42
Compare the CPI to the TCPI-BAC:
TCPI(BAC) = Efficiency necessary to complete on budget
= = = $5000 - $1000$5000 - $2400
Example: Using Performance Efficiencies (1)
BCWPACWP
WORKACCOMPLISHED
ACTUALS
BAC-BCWPBAC-ACWP
WORKREMAINING
BUDGETREMAINING
= $4000$2600 = 1.54
HISTORY
FUTURE
![Page 30: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/30.jpg)
12/25/06 EVM Introduction 30
12/25/06 EVM Introduction 30
Example: Using Performance Efficiencies (2)
SCHEDULE PERFORMANCE INDEX:
SPI = schedule efficiency with which work has been accomplished(The rate at which work is being accomplished)
WORK= BCWP = ACCOMPLISHED = $1000 = .50
BCWS WORK $2000 SCHEDULED
![Page 31: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/31.jpg)
12/25/06 EVM Introduction 31
12/25/06 EVM Introduction 31
IS THE CONTRACTOR'S EAC (LRE) REASONABLE?Compare the CPI to the TCPI-LRE
TCPI(LRE) = Efficiency necessary to complete at the contractor’s estimate
WORKBAC-BCWP REMAINING $5000 - $1000 $4000 1.00LRE-ACWP ESTIMATE $6400 - $2400 $4000
REMAINING
Cumulative performance to date (CPI) = .42
Contractor has been performing at 42% efficiency, but expects tocomplete remaining work at 100% efficiency!
Example: Using Performance Efficiencies (3)
reasonable?
= == = =
![Page 32: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/32.jpg)
12/25/06 EVM Introduction 32
12/25/06 EVM Introduction 32
Outline
• Introduction to the basic rationale and elements of EVM
• Issues of actually implementing an EVM tracking scheme
• Background materials
![Page 33: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/33.jpg)
12/25/06 EVM Introduction 33
12/25/06 EVM Introduction 33
Control Account
Software Engineering
Getting at the Value
WorkPackages
PlanningPackages
OBS DATA SUMMARIZATION
SOFTWAREINTEGRATION
PROGRAM
Product Development
Master Planning
AdaProducts
Software Tools Standards
CPCI #1MOS
CPCI #2MOLE
CPCI #3MAC
AdaStudy
AdaConversion
AdaApproach
AdaApplications
Secure Systems
LAN Applications
Marketing
BCWSBCWPACWPBACEAC
FUNCTIONALORGANIZATION
CWBSEXTENSION
SELECTEDREPORTINGELEMENTS
SELECTEDPSWBS
ELEMENTS
Hardware Engineering
Engineering
Operations
WBS
DATA
SUMMARIZATION
VP/GM
Control Account
Control Account
Control Account
Control Account
Control Account
Control Account
Responsibility Matrix
![Page 34: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/34.jpg)
12/25/06 EVM Introduction 34
12/25/06 EVM Introduction 34
Control Account Elements
Work PackagesDetailed, short-span tasks, or
material items, required to
accomplish the CA objectives,
typically in the near term
Task 1Task 2
Task 4Task 5
Task 3Work Packages
Planning Packages
Planning PackagesFuture work that has not been
detail planned as work packages.
They are always scheduled to
occur in the future.
Work Packages have budgets
and schedules.
![Page 35: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/35.jpg)
12/25/06 EVM Introduction 35
12/25/06 EVM Introduction 35
• Development of Control Account Plans– MAY break down the control account budget into smaller work
packages
• Work Package• subset of control account• reasonably short in duration• single element of cost (e.g., labor)• single technique for earning value• consistent with detail schedules• has same characteristics as control account
– scope of work– milestone completion criteria– single performing organization– start and end dates
CONTROL ACCOUNT PLAN
Work Pkg #1
Work Pkg #2
Work Pkg #3
$$
$ $
$
$
$
$$
Work Packages
![Page 36: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/36.jpg)
12/25/06 EVM Introduction 36
12/25/06 EVM Introduction 36
• Work packages are discrete and measurable.
• Work packages yield products or accomplishments, such as
– design drawing package– conduct design review– install stand
• Often done in rolling wave
– detailed plans made for near term work packages– planning packages are for future work and are not detailed– CAMs periodically plan another increment of work packages
Work Package Characteristics
![Page 37: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/37.jpg)
12/25/06 EVM Introduction 37
12/25/06 EVM Introduction 37
• Should be a quantitative and discrete way to measure the work– Discrete
• physical, tangible end product
– Apportioned• discrete, dependent on another discrete work package• example: quality assurance• planned as historical estimating factor (e.g., 7%)
– Level of Effort• no tangible end product• basis of measurement: time• when clock starts ticking, you automatically accumulate earned value• no schedule variance• example: management personnel
• May tie in with success criteria or technical measure• e.g., successful completion of a specific test, reliability growth curve
Ways of Earning Value
![Page 38: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/38.jpg)
12/25/06 EVM Introduction 38
12/25/06 EVM Introduction 38
Method How Value is Earned
0/100 no EV at opening, 100% EV at close of WP
50/50 50% EV at opening, 50% EV at close of WP
Units Completed same budget value for identical units
Equivalent Units planned unit standards, allows partial credit
Weighted Milestone each milestone weighted based on planned resources
ideal to have a milestone each month
Percent Complete subjective (least desirable)
Methods for Assigning Earned Value
![Page 39: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/39.jpg)
12/25/06 EVM Introduction 39
12/25/06 EVM Introduction 39
Suggested for LWA
• 0/50/100 measurement• Typical work package length is 80 hours.• Work package status is reported at status meetings, held every
two weeks.– May just be that 50% of work packages are reported at weekly
status meetings.• EV is 0% (of budget for work package) if it has not yet been
started, or is only now starting.• EV is 50% if work is underway.• EV is 100% if work is complete.• If work package is at 50% two status meetings in a row, it is
flagged as a potential issue.• Avoids subjectivity of “% done”; compromises on granularity of
tracking, frequency of reporting• Puts the onus on doing the WPs right, up front.
![Page 40: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/40.jpg)
12/25/06 EVM Introduction 40
12/25/06 EVM Introduction 40
Outline
• Introduction to the basic rationale and elements of EVM
• Issues of actually implementing an EVM tracking scheme
• Background materials
![Page 41: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/41.jpg)
12/25/06 EVM Introduction 41
12/25/06 EVM Introduction 41
A Spectrum of Implementation
Where
When
Core EV PrinciplesANSI/EIA-748-1998
(32 criteria)Tailored Applications
Small Companies Larger Companies
Major Defense
Contractors
as desired
Government Organic
Reports
Foreign Countries
streamlined, no paper?
corporate policy,
“enterprise wide”
DoD Non-Major Contracts (>12 months)
<$6M* >$6M
DoD Major Contracts
>$70M RDT&E
>$300M Prod
tailored to needs C/SSR CPR
*with judgment
FFP contracts?
Commercial or Defense
![Page 42: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/42.jpg)
12/25/06 EVM Introduction 42
12/25/06 EVM Introduction 42
Earned Value Management:History
• 1959 PERT and PERT/Cost— Milestone Charts And Rate-of-Expenditure
Curves— Dollars Spent Vs Estimates Of Percent
Complete (DD 1097)• 1963 Earned Value Concept (MINUTEMAN)• 1964 Cost Accomplishment Concept (TITAN III)• 1966 AF—Cost/schedule Planning And Control
Specification (C/SPCS)• 1967 DOD—Cost/Schedule Control Systems
Criteria (C/SCSC) (DODI 7000.2)• 1972 DOD—-Revised DODI 7000.2 and Issued the
Joint Implementation Guide (JIG)• 1972 NASA Marshall Space Flight Center—C/SPC• 1975 DOE—Performance Measurement System
(PMS)• 1976 DOD—Revised the C/SCSC JIG• 1980 DOD—Revised the C/SCSC JIG• 1982 National Security Agency—Earned Value• 1983 NASA—Goddard Space Flight Center—PMS• 1984 FAA & NASA Lewis Research Center—PMS
• 1985 NASA Johnson Space Flight Center—PMS• 1987 DOD—Revised DOD C/SCSC JIG• 1988 NASA Marshall SFC—Revised PMS
(MMI 8020.7C, 44 Criteria)• 1989 Australian DOD—DODI 7000.2• 1990 Canadian DOD—PMS• 1991 DODI 5000.2 replaces DODI 7000.2• 1992 National Oceanic And Atmospheric
Administration (NOAA)—PMS• 1993 Swedish FMV—C/SCSC• 1994 Internal Revenue Service (IRS)—C/SCSC• 1994 Federal Bureau Of Investigation (FBI)
—C/SCSC• 1996 DODR 5000.2-R replaces DODI 5000.2
C/SCSC revised from 35 to 32 criteria• 1996 Revised JIG—Renamed Earned Value
Management Implementation Guide (EVMIG)• 1997 EVMIG Revised• 1998 MIL-STD 881B replaced by MIL HDBK 881
![Page 43: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM](https://reader034.fdocuments.us/reader034/viewer/2022042300/5ecb72570746fe0230439d5e/html5/thumbnails/43.jpg)
12/25/06 EVM Introduction 43
12/25/06 EVM Introduction 43
EVM Resources
• BooksEarned ValueQuentin W. Fleming & Joel M. KopplemanCost/Schedule Control Systems CriteriaQuentin W. FlemingProject Performance MeasurementRobert R. KempsVisualizing Project ManagementKevin Forsberg, Ph.D., Hal Mooz and Howard Cotterman
• SoftwareArtemis ViewsArtemis Management SystemsContact: Patrick Perugini (303) 581-3102Web: http://www.artemispm.comCobraWelcom SoftwareContact: Diana Melton (281) 558-0514Web: http://www.wst.com
• Software [continued]Dekker TRAKKERDekker Ltd.Contact: Ron Barry (909) 384-9000Web: http://www.dtrakker.comMicroFrame Project Manager (MPM)MicroFrame Technologies, Inc.Contact: Carl Amacker (415) 616-4000Web: http://www.microframe.com
• InternetProject Management Institutehttp://www.pmi.org
US DoD Earned Valuehttp://www.acq.osd.mil/pm
Earned Value Bibliographyhttp://www.uwf.edu/~dchriste/ev-bib.html