Bridge Report Summary

download Bridge Report Summary

of 13

Transcript of Bridge Report Summary

  • 7/26/2019 Bridge Report Summary

    1/13

    i

    CVEN 754

    Advanced structural Design Studio

    A report on

    DESIGN OF A PRESTRESSED CONCRETE BRIDGE

    by

    Alla, Jaya Ram Reddy, (UIN: 224002461)

    Spring 2015

  • 7/26/2019 Bridge Report Summary

    2/13

    CVEN754BridgeProject

    pg. ii

    Table of Contents

    Author: ....................................................................................................................... i

    Table of Contents: ..................................................................................................... ii

    1 Scope of the Project .............................................................................................3

    2 Construction Methods & Drawings .....................................................................4

    3 Typical Design Notes ..........................................................................................9

    4 Summary of the Bill of Quantity for 5 design options ......................................10

    5 Summary of the Cost estimation for 5 design options ...................................... 11

    6 Reply to the Peer Review of the design.. ..........................................................12

  • 7/26/2019 Bridge Report Summary

    3/13

    CVEN754BridgeProject

    pg. 3

    1.

    Scope of the Project

    This Project is about the design and construction of 900 ft span bridge. The design of the new

    river bridges items must be consistent with the requirements of TXDoT. The scope of this Contract is

    to design and prepare 5 separate Bridge Plans, special provisions, quantity estimates, and compare the

    merits of all the designs.

    In response to your current need regarding the design of a 900ft bridge, the following five

    designs have been prepared. In detail, we are gonna discuss about the summary of design by Er. Jaya

    Ram Reddy Alla. The design has external post tensioning and the construction mthod assumed is big

    lift.

    SNo. EngineerSpan

    ConfigurationGirder

    Construction

    MethodRemarks

    1JAYA RAM REDDY

    ALLA

    140-190-240-

    190-140TX 84 Big Lift

    External Post

    Tensioning

    2KAITHA SHIVA

    PRASAD

    140-190-240-

    190-140TX 70 Haunched

    3SANTIAGO SERRANO

    APONTE

    140-190-240-

    190-140TX 84 Shored

    4AKESH VARMA

    KOTHAPALLI

    100-100-150-

    200-150-100-

    100

    TX 70 ShoredWidened

    Web

    5NIKITHA REDDY

    PONAKA

    100-100-150-

    200-150-100-

    100

    TX 70Big Lift

    Unshored

    Internal Post

    Tensioning

  • 7/26/2019 Bridge Report Summary

    4/13

    CVEN754BridgeProject

    pg. 4

    2.

    Construction Methods and Design Drawings

    Engineer Name : JAYA RAM REDDY, ALLA

    Construction Method : Big Lift (External Post Tension)

    Span Configuration : 140-190-240-190-140

    Construction Equipment : Crawler cranes (at Casting yard, site), trailor, pre-stressing

    jacks

    Construction Method:

    Using formwork, the substructure (Pier and Pier cap) are constructed.

    For transportation purpose, smaller spans are cast at yard and are transported to site and post

    tensioned. (190 ft will be 70+120 and 240 will be 70+100+70).

    Pre Tension:o For transportation purposes, pretension is designed for the dead load of the individual

    segments.

    o On the casting bed, before concreting the tendons are tensioned.

    o These individual segments are transported to site on a trailor.

    Post Tension:

    o At site, individual segments are spliced together and post tensioning is done.

    o The post tensioning is designed for the dead load of the girder, slab and weathering

    course and railings.

    o Once the post tensioning is done, the crawler cranes lift the 190 span in tandem and

    place the girder on the pier caps.

    o Likewise 240 span and the other 190 span is also erected.

    o The deck slab is poured on the girders using sacrificial shutter/ formwork.

    Local Post Tension:

    o Once the deck is poured, the system acts as a continuous span. So before the railing and

    weathering loads, local post tension using dywidag bars will be done over the pier,

    nullifying the negative moments over the continuous support.

  • 7/26/2019 Bridge Report Summary

    5/13

    CVEN754BridgeProject

    pg. 5

    o

    Simply Supported (only Pretensioning) Harped Solution

  • 7/26/2019 Bridge Report Summary

    6/13

    CVEN754BridgeProject

    pg. 6

    Longitudinal Section of Simply Supported (only Pretensioning) Harped Solution

  • 7/26/2019 Bridge Report Summary

    7/13

    CVEN754BridgeProject

    pg. 7

    Simply Supported Cross Sectional and Longitudinal Section (Pre-Tension + Post-Ten

  • 7/26/2019 Bridge Report Summary

    8/13

    CVEN754BridgeProject

    pg. 8

    Longitudinal Section for 620ft Span

  • 7/26/2019 Bridge Report Summary

    9/13

    CVEN754BridgeProject

    pg. 9

    3.

    Typical Design Notes:

    Eccentricities are not subjected to change without the notice and approval of the Engineer in

    Charge.

    Post-tension and pre-tension are to be done under the supervision of a trained Site Engineer. Rebar required for helical reinforcement in the pier has to be done according to the diameter and

    spacing provisions provided in the drawings.

    Any changes in the drawings are to be taken to the notice of Engineer and should proceed only if

    they are approved.

    The segments are subjected to lift only after the approval from the client. Equipment is to be

    checked thoroughly before lifting.

    Diameter of the tendons strands and rebar are not subjected to change without the approval of

    Engineer in Charge.

    Stirrups for the pier caps are to be bent as per the provisions mentioned in the design drawings.

    Splicing and anchoring is to be done under the supervision of site engineer.

  • 7/26/2019 Bridge Report Summary

    10/13

    CVEN754BridgeProject

    pg. 10

    4.

    Summary of the Bill of Quantity for 5 design options:

    COMPARISION OF QUANTIY FOR 5 DIFFERENT BRIDGE DESIGN P

    S.No Engineer Jaya Ram Reddy, A Shiva, K Akesh Varma,K San

    1 Span Configuration 140-190-240-190-140 140-190-240-190-140

    100-100-150-200-150-100-100

    140190

    2 Girder TX-84 TX-70 TX-70 TX

    3Construction

    Method

    Big Lift(External Post

    Tension)

    Haunchedshored

    Construction

    Shored

    Construction Co

    4 Concrete Quantity 76043 Cu.Ft 72530 Cu.Ft 72422 Cu.Ft 8

    5 Pre-Tension strands 92000 Ft 166089 Ft 136800 Ft

    6Post TensionStrands

    318200 Ft 355680 Ft 328320 Ft

    Legend:

    Least Quantity

    Highest Quantity

  • 7/26/2019 Bridge Report Summary

    11/13

    CVEN754BridgeProject

    pg. 11

    5.

    Summary of the Cost Estimation for 5 design options :

    MATERIALS AND EQUIPMENT COST

    ENGINEER Concrete Pre-Tension strands Post Tension Strands Crane Sho

    Jaya Ram Reddy, A $350,644.92 $202,400.00 $700,040.00

    $189,000.00

    Shiva, K $334,442.56 $365,396.28 $782,496.00 $189,000.00

    Akesh Varma,K $333,944.28 $300,960.00 $722,304.00

    $189,000.00

    Santiago, S $381,714.51 $222,024.00 $990,399.83

    $189,000.00

    Nikitha,P $333,944.28 $300,960.00 $722,304.00 $189,000.00

    Notes:

    Crane

    price

    is

    based

    on

    $10,500

    weekly

    (40

    Hours)

    ShoreSystempriceisbasedon$1.2perSQFTperday(AccordingtoDoka)

    DESIGN RANKING BASED ON

    PRICE

    RANKING ENGINEER

    1

    Jaya Ram Reddy, A

    2 Nikitha,P

    3 Shiva, K

    4 Akesh Varma,K

    5 Santiago, S

  • 7/26/2019 Bridge Report Summary

    12/13

    CVEN754BridgeProject

    pg. 12

    6. Reply to the Peer Review of the design:

    Designer: Er. Jaya Ram Reddy Alla

    Peer Reviewer: Er. Kelly Ha

    The reply to the questions posed by the peer reviewer are addressed herewith.

    Design Option 1-A:

    1. Does the harping actually balance the end-moments?

    a. I have tried to balance the maximum of the end moments. Care was taken that the

    maximum possible tendons have been harped (Extra tendons couln't fit because of

    the web thickness)

    Design Option 1-B:

    1.

    If you want to use Post tensioning, need to use a modified Tx-84 in order for the ducts to

    properly fit in the web. This is going to make your girder heavier and slighly change

    sectional properties.

    a. I have used 19 no' of 0.5" conduits which has a dia of 3.5" which gives me an clear

    of 2.25" on either side in a web. So, I dont have to use a modified section.

    2. 0.6" dia strands called out, used wrong area calculation in tendon force.

    a. Noted (a typo), the tendon force calculated is correct, I had used 0.5" dia strands.

    3. Note sure where ept1 came from?

    a. Back calculation was done. The Ept1 required for 3 ducts was calculated and found.

    4.

    Why does f1e1=f2e2 ?a. Ofcourse, to balance the end moments, 1st post tension was balanced with pre

    tension.

    5. Was the sheer check and ultimate check conducted?

    a. Noted, these checks were calculated and included in the design. Deflection was also

    included.

    Design of Pier Cap:

    1. Have #6, #7 called out for the design.

    a. No., only # 7 bars are to be used, please refer drawing. On pg 3.3.

    2.

    Did the moment for bent caps design come from the seismic forces or localized soft soil.

    a. The moment has come from localized soft soil.

    3. Need to add harsoil soil design & soft soil?

    a. The critical moment was from localized soil, hence the cap was designed for

    localized soft soil condition.

  • 7/26/2019 Bridge Report Summary

    13/13

    CVEN754BridgeProject

    pg. 13

    Design of Pier:

    1. Need to add hard soil design.

    a. The over turning moments were calculated in pg: 4.6, please refer.

    2. Longitudinal Rft is large and may pose problems

    a.

    #14 no' bars were used, no where we need to bend these bars so less problem whileconstruction.

    3. Transverse Rft is large and may pose problems

    a. #4, #5 no' bars were used as shear reinforcement. There wont be any problem in

    bending the bars.

    Design of Continuous span:

    1. Maybe want to think about splitting up tendons so that can be partially unstressed when

    replacing the deck.Maybe want to think about splitting up tendons so that can be partially

    unstressed when replacing the deck.a. For the reason, an extra conduit duct (no tendons) for future purpose can be

    provided, just incase of maintenaince.

    2. Add stress checks at mid span of end spans

    a. The stress checks for 190' and 240' spans at Mid span were already included, please

    refer Pg: 27.

    3. For live load checks, not sure if moments were found correctly.

    a. Moment distribution method was adopted to find the live load moments. The lane

    load and truck loads were included in the moment calculation. (Refer Pg: 25)

    4. Cross section ends, need to show anchors will fit; will be especially large with using 37

    strands.a. "VSL" specifies that for strands of 55 needs 6.3" from center for anchorage, for the

    240' span, I have provided 6" for 37 strands, which should be enough.