Bridge Report Summary
-
Upload
jayaramrddy -
Category
Documents
-
view
229 -
download
0
Transcript of Bridge Report Summary
-
7/26/2019 Bridge Report Summary
1/13
i
CVEN 754
Advanced structural Design Studio
A report on
DESIGN OF A PRESTRESSED CONCRETE BRIDGE
by
Alla, Jaya Ram Reddy, (UIN: 224002461)
Spring 2015
-
7/26/2019 Bridge Report Summary
2/13
CVEN754BridgeProject
pg. ii
Table of Contents
Author: ....................................................................................................................... i
Table of Contents: ..................................................................................................... ii
1 Scope of the Project .............................................................................................3
2 Construction Methods & Drawings .....................................................................4
3 Typical Design Notes ..........................................................................................9
4 Summary of the Bill of Quantity for 5 design options ......................................10
5 Summary of the Cost estimation for 5 design options ...................................... 11
6 Reply to the Peer Review of the design.. ..........................................................12
-
7/26/2019 Bridge Report Summary
3/13
CVEN754BridgeProject
pg. 3
1.
Scope of the Project
This Project is about the design and construction of 900 ft span bridge. The design of the new
river bridges items must be consistent with the requirements of TXDoT. The scope of this Contract is
to design and prepare 5 separate Bridge Plans, special provisions, quantity estimates, and compare the
merits of all the designs.
In response to your current need regarding the design of a 900ft bridge, the following five
designs have been prepared. In detail, we are gonna discuss about the summary of design by Er. Jaya
Ram Reddy Alla. The design has external post tensioning and the construction mthod assumed is big
lift.
SNo. EngineerSpan
ConfigurationGirder
Construction
MethodRemarks
1JAYA RAM REDDY
ALLA
140-190-240-
190-140TX 84 Big Lift
External Post
Tensioning
2KAITHA SHIVA
PRASAD
140-190-240-
190-140TX 70 Haunched
3SANTIAGO SERRANO
APONTE
140-190-240-
190-140TX 84 Shored
4AKESH VARMA
KOTHAPALLI
100-100-150-
200-150-100-
100
TX 70 ShoredWidened
Web
5NIKITHA REDDY
PONAKA
100-100-150-
200-150-100-
100
TX 70Big Lift
Unshored
Internal Post
Tensioning
-
7/26/2019 Bridge Report Summary
4/13
CVEN754BridgeProject
pg. 4
2.
Construction Methods and Design Drawings
Engineer Name : JAYA RAM REDDY, ALLA
Construction Method : Big Lift (External Post Tension)
Span Configuration : 140-190-240-190-140
Construction Equipment : Crawler cranes (at Casting yard, site), trailor, pre-stressing
jacks
Construction Method:
Using formwork, the substructure (Pier and Pier cap) are constructed.
For transportation purpose, smaller spans are cast at yard and are transported to site and post
tensioned. (190 ft will be 70+120 and 240 will be 70+100+70).
Pre Tension:o For transportation purposes, pretension is designed for the dead load of the individual
segments.
o On the casting bed, before concreting the tendons are tensioned.
o These individual segments are transported to site on a trailor.
Post Tension:
o At site, individual segments are spliced together and post tensioning is done.
o The post tensioning is designed for the dead load of the girder, slab and weathering
course and railings.
o Once the post tensioning is done, the crawler cranes lift the 190 span in tandem and
place the girder on the pier caps.
o Likewise 240 span and the other 190 span is also erected.
o The deck slab is poured on the girders using sacrificial shutter/ formwork.
Local Post Tension:
o Once the deck is poured, the system acts as a continuous span. So before the railing and
weathering loads, local post tension using dywidag bars will be done over the pier,
nullifying the negative moments over the continuous support.
-
7/26/2019 Bridge Report Summary
5/13
CVEN754BridgeProject
pg. 5
o
Simply Supported (only Pretensioning) Harped Solution
-
7/26/2019 Bridge Report Summary
6/13
CVEN754BridgeProject
pg. 6
Longitudinal Section of Simply Supported (only Pretensioning) Harped Solution
-
7/26/2019 Bridge Report Summary
7/13
CVEN754BridgeProject
pg. 7
Simply Supported Cross Sectional and Longitudinal Section (Pre-Tension + Post-Ten
-
7/26/2019 Bridge Report Summary
8/13
CVEN754BridgeProject
pg. 8
Longitudinal Section for 620ft Span
-
7/26/2019 Bridge Report Summary
9/13
CVEN754BridgeProject
pg. 9
3.
Typical Design Notes:
Eccentricities are not subjected to change without the notice and approval of the Engineer in
Charge.
Post-tension and pre-tension are to be done under the supervision of a trained Site Engineer. Rebar required for helical reinforcement in the pier has to be done according to the diameter and
spacing provisions provided in the drawings.
Any changes in the drawings are to be taken to the notice of Engineer and should proceed only if
they are approved.
The segments are subjected to lift only after the approval from the client. Equipment is to be
checked thoroughly before lifting.
Diameter of the tendons strands and rebar are not subjected to change without the approval of
Engineer in Charge.
Stirrups for the pier caps are to be bent as per the provisions mentioned in the design drawings.
Splicing and anchoring is to be done under the supervision of site engineer.
-
7/26/2019 Bridge Report Summary
10/13
CVEN754BridgeProject
pg. 10
4.
Summary of the Bill of Quantity for 5 design options:
COMPARISION OF QUANTIY FOR 5 DIFFERENT BRIDGE DESIGN P
S.No Engineer Jaya Ram Reddy, A Shiva, K Akesh Varma,K San
1 Span Configuration 140-190-240-190-140 140-190-240-190-140
100-100-150-200-150-100-100
140190
2 Girder TX-84 TX-70 TX-70 TX
3Construction
Method
Big Lift(External Post
Tension)
Haunchedshored
Construction
Shored
Construction Co
4 Concrete Quantity 76043 Cu.Ft 72530 Cu.Ft 72422 Cu.Ft 8
5 Pre-Tension strands 92000 Ft 166089 Ft 136800 Ft
6Post TensionStrands
318200 Ft 355680 Ft 328320 Ft
Legend:
Least Quantity
Highest Quantity
-
7/26/2019 Bridge Report Summary
11/13
CVEN754BridgeProject
pg. 11
5.
Summary of the Cost Estimation for 5 design options :
MATERIALS AND EQUIPMENT COST
ENGINEER Concrete Pre-Tension strands Post Tension Strands Crane Sho
Jaya Ram Reddy, A $350,644.92 $202,400.00 $700,040.00
$189,000.00
Shiva, K $334,442.56 $365,396.28 $782,496.00 $189,000.00
Akesh Varma,K $333,944.28 $300,960.00 $722,304.00
$189,000.00
Santiago, S $381,714.51 $222,024.00 $990,399.83
$189,000.00
Nikitha,P $333,944.28 $300,960.00 $722,304.00 $189,000.00
Notes:
Crane
price
is
based
on
$10,500
weekly
(40
Hours)
ShoreSystempriceisbasedon$1.2perSQFTperday(AccordingtoDoka)
DESIGN RANKING BASED ON
PRICE
RANKING ENGINEER
1
Jaya Ram Reddy, A
2 Nikitha,P
3 Shiva, K
4 Akesh Varma,K
5 Santiago, S
-
7/26/2019 Bridge Report Summary
12/13
CVEN754BridgeProject
pg. 12
6. Reply to the Peer Review of the design:
Designer: Er. Jaya Ram Reddy Alla
Peer Reviewer: Er. Kelly Ha
The reply to the questions posed by the peer reviewer are addressed herewith.
Design Option 1-A:
1. Does the harping actually balance the end-moments?
a. I have tried to balance the maximum of the end moments. Care was taken that the
maximum possible tendons have been harped (Extra tendons couln't fit because of
the web thickness)
Design Option 1-B:
1.
If you want to use Post tensioning, need to use a modified Tx-84 in order for the ducts to
properly fit in the web. This is going to make your girder heavier and slighly change
sectional properties.
a. I have used 19 no' of 0.5" conduits which has a dia of 3.5" which gives me an clear
of 2.25" on either side in a web. So, I dont have to use a modified section.
2. 0.6" dia strands called out, used wrong area calculation in tendon force.
a. Noted (a typo), the tendon force calculated is correct, I had used 0.5" dia strands.
3. Note sure where ept1 came from?
a. Back calculation was done. The Ept1 required for 3 ducts was calculated and found.
4.
Why does f1e1=f2e2 ?a. Ofcourse, to balance the end moments, 1st post tension was balanced with pre
tension.
5. Was the sheer check and ultimate check conducted?
a. Noted, these checks were calculated and included in the design. Deflection was also
included.
Design of Pier Cap:
1. Have #6, #7 called out for the design.
a. No., only # 7 bars are to be used, please refer drawing. On pg 3.3.
2.
Did the moment for bent caps design come from the seismic forces or localized soft soil.
a. The moment has come from localized soft soil.
3. Need to add harsoil soil design & soft soil?
a. The critical moment was from localized soil, hence the cap was designed for
localized soft soil condition.
-
7/26/2019 Bridge Report Summary
13/13
CVEN754BridgeProject
pg. 13
Design of Pier:
1. Need to add hard soil design.
a. The over turning moments were calculated in pg: 4.6, please refer.
2. Longitudinal Rft is large and may pose problems
a.
#14 no' bars were used, no where we need to bend these bars so less problem whileconstruction.
3. Transverse Rft is large and may pose problems
a. #4, #5 no' bars were used as shear reinforcement. There wont be any problem in
bending the bars.
Design of Continuous span:
1. Maybe want to think about splitting up tendons so that can be partially unstressed when
replacing the deck.Maybe want to think about splitting up tendons so that can be partially
unstressed when replacing the deck.a. For the reason, an extra conduit duct (no tendons) for future purpose can be
provided, just incase of maintenaince.
2. Add stress checks at mid span of end spans
a. The stress checks for 190' and 240' spans at Mid span were already included, please
refer Pg: 27.
3. For live load checks, not sure if moments were found correctly.
a. Moment distribution method was adopted to find the live load moments. The lane
load and truck loads were included in the moment calculation. (Refer Pg: 25)
4. Cross section ends, need to show anchors will fit; will be especially large with using 37
strands.a. "VSL" specifies that for strands of 55 needs 6.3" from center for anchorage, for the
240' span, I have provided 6" for 37 strands, which should be enough.