BRIDGE # MUN 154 over N CHANNEL MISS RIVERMUN 154 over N CHANNEL MISS RIVER Minnesota Structure...
Transcript of BRIDGE # MUN 154 over N CHANNEL MISS RIVERMUN 154 over N CHANNEL MISS RIVER Minnesota Structure...
2016 UNDERWATER
BRIDGE INSPECTION REPORT
BRIDGE #
DISTRICT: COUNTY: CITY/TOWNSHIP:
Date of Inspection:
Equipment Used:
Inspected By:
Report Written By:
Report Reviewed By:
Final Report Date:
4260
MUN 154 over N CHANNEL MISS RIVER
District 6 Winona WINONA
11/30/2016
Forsyth, Roy
Roy Forsyth
City or Municipal Highway AgencyOwner:
MinnesotaSTATE:
UNDERWATER SUMMARY 3
UNDERWATER INSPECTION 4
UNDERWATER INSPECTION PROCEDURES 6
APPENDIX A: STRUCTURE INVENTORY 7
ELEMENTS 8
PICTURES 13
DRAWINGS 21
TABLE OF CONTENTS
PAGE NUMBER
Contractor:
RECOMMENDATIONS:(A) Prior placement of riprap at the piers has substantially improved structural integrity of the bridge. Therefore, monitor footing exposure during future inspections and reinspect the submerged substructure units at the normal maximum recommended (NBIS) interval of sixty (60) months.
Collins Engineers
9687Contractor Job Number:
RECOMMENDATIONS
REPORT SUMMARY
UNDERWATER INSPECTION
The substructure units inspected at Bridge No. 4260, Piers 1 through 13, were found to be in satisfactory condition. The submerged concrete was typically in satisfactory to fair condition with moderate scaling from 1 foot above to 1 foot below the waterline and random widespread hairline cracking throughout most pier shafts. The structure had extensive riprap with sand infilling present around all of the piers to address any past footing undermining. The riprap typically extended to top of footing or to no lower than 3 feet below top of footing. The concrete footings typically exhibited rough surfaces with up to 3 inch maximum penetration.
INSPECTION FINDINGS:(A) The channel bottom at Pier 13 consisted of silt with small stones and no riprap. Stone and rubble was observed at the upstream and downstream ends.(B) The channel bottom of Piers 1 through 12 consisted of riprap typically 1 to 2 feet in diameter with a maximum diameter of up to 3 feet. It was observed around the entire perimeter of all piers typically extending to top of footing or to no lower than 3 feet below top of footing. The concrete footing typically exhibited rough surfaces with up to 3 inch maximum penetration.(C) The submerged concrete was typically in satisfactory condition with moderate scaling from 1 foot above the waterline to 1 feet below the waterline with typical penetrations of 1 inch and maximum penetrations of up to 6 inch. Random vertical and horizontal hairline cracks were also observed on the concrete shaft surfaces widespread throughout all piers. Cracking often has efflorescence associated with it. (D) Pier 9 exhibited an area of section loss on the downstream south corner from 6 inches above to 2 foot below the waterline with up to 6 inches of penetration and no exposed steel.(E) The upstream nose and west face of Pier 3 had moderate timber debris from channel bottom up to 4 feet above waterline, consisting of 2 foot diameter and smaller logs. (F) There was a 2 foot diameter by 30 foot long log at the west face of Pier 1 extending from the channel bottom up 2 feet.
INSPECTION FINDINGS
Page 3 of 25
12.1Maximum Water Depth at Substructure(s) Inspected (feet):
Oblong rectangular shafts with rounded corners which sit on rectangular footings that are founded on timber piles.
Water Level Reference:
WATERLINE DATUM4.
General Shape:
3.
1.5Waterway Velocity (ft/sec):
Piers 1 through 13.Substructure(s) Inspected:
SUBSTRUCTURE INSPECTION DATA
Springline at the downstream end of Pier 1.
5Code:Item 60: Substructure:
8Code:Item 61: Channel and Channel Protection:
(Minnesota specific codes are used for 92B and 113)
Description:
Waterline Elevation (feet):
NBIS CODING INFORMATION5.
District:
MUN 154Facility Carried:
085 - WinonaCounty:
District 6
N CHANNEL MISS RIVER
BRIDGE DATA1.
UNDERWATER INSPECTION
Feature Intersected:
4260Bridge #:
Bridge Description:
Weather Conditions:
11/30/2016Date of Underwater Inspection:
None/NegligibleUnderwater Visibility (feet):
Cloudy, 30 °F
INSPECTION DATA2.
The superstructure consists of twenty-four spans of reinforcedconcrete arches or beams. The main spans across the channel areopen spandrel reinforced concrete arches. The bridge is supported byreinforced concrete piers which are founded on timber piles. Thechannel piers are numbered 1 through 13 starting with Pier 1 on theeast shore.
Inspection Diver:
Roy ForsythProfessional Engineer/Team Leader:
Page 4 of 25
885 1EAScour 1
50275
EA 1212220 Reinforced Concrete Footing
LF
No (Mark your selection with an X)XYes
6. STRUCTURAL ELEMENT CONDITION RATING
Item 92B: Underwater Inspection: Code:
Item 62: Culvert: Code:
P
Bridge is scour critical because abutment or pier foundation is rated as unstable due to observed scour at bridge site.
Code:
Y 48 11/2016
Item 113: Scour Critical Bridge:
CS2 CS3CS1Quantity Unit
Reinforced Concrete Pier Wall 325210
CS4
Conditions
ELEM # Element Description
Page 5 of 25
The routine underwater inspection of Bridge 4260 (City Route 154 over the North Channel of the Mississippi River) was completed on November, 30, 2016. The underwater inspection was conducted from a 20 foot boat. The inspection was conducted by a team consisting of a PE-Diver with a valid MnDOT Team leader certification, a backup diver and a dive tender. The inspection utilized commercial dive equipment and techniques (SSA and/or SCUBA) in accordance with OSHA regulations. Profiles were taken along the upstream and downstream faces of the bridge and around the periphery of substructure units to determine the presence, location and area of scour.
The bridge elements inspected consisted of 13 piers and 12 concrete footings. According to the bridge inventory or design drawings, Piers 1 through 13 were founded on timber pile footings. Inspection procedures followed FHWA guidance and the MnDOT Bridge and Structure Inspection Program Manual with channel bottom probing to search for bottom of foundations. The routine underwater inspection frequency is recommended to remain at 60 months based on those findings and risk factors. Also, inspection procedures should continue to follow the above approach and standard guidance with 100% Level I and 10% Level II intensity efforts.
INSPECTION PROCEDURES
UNDERWATER INSPECTION
Page 6 of 25
Spec. Feat.Pier Foundation (Material/Type)
1 - CONCCantilever ID
+ W A T E R W A Y +Number of Spans Historic Status
3 - FTG PILE
Underwater 60Culvert Type 3 - FTG PILE
Pinned Asbly.
11/30/2016
Barrel Length
1220.0 ft. Navigation Control
Waterway Opening (sf.) 99999Structure Length
ft. Year Painted
0 - No nav. control on waterwayDeck Width (Out-to-Out) 24.5
+ P A I N T +
APPR: 11 TOTAL:5 - Not eligible
MAIN: 13
Main Span Length 72.0 ft.Drainage Area (sq. mi.)
B R I D G E D A T A +Main Span Detail
N - NOT REQUIRED+ M I S C.
Appr. Span Type 1 - Concrete Structure Flared
V - OPEN SPANDREL ARCH GR Termini N - NOT REQUIRED
Appr. Guardrail
Main Span Type 2 - Concrete Continuous Median Width On Bridge
ft. Bridge Railing 0 - SUBSTANDARD
N - NOT REQUIRED
Main Span Design 12 - Arch
ft. GR Transition
Skew 0
Y/N Freq Date
Abutment Foundation (Material/Type)
1 - CONC Frac. Critical
D E P T H I N S P. +Appr. Span Design
0 - No flare+ I N
Appr. Span Detail Field Conn. ID
06 - Deck Girder Parallel Structure N - No parallel structure
Pier Protection
0 - Not Required
Rating Date 12/15/200621345 sq. ft. Traffic
ft. 50B. Rt 5.00Sidewalk Width 50A. Lt 0.00
Roadway Area (Curb-to-Curb)
Posted Load 1 - Vehicle Only (Type R12-1A)
PostingStructure Area (Out-to-Out) 29890 sq. ft.
DBL:VEH: 4 SEMI:
Rt 02 ARail Type Lt 02 C N - N/AN - N/A B N - N/A
N - Not Applicable Overweight Permit CodesCurb Height Lt
ft. Horizontal 0 - Not Required
0.00 ft. Vertical0.00 ft. Rt
Wear Surf Install Year
sq. ft. Nav. Vert. Lift Bridge Clear. (ft.)
P - STBL - PROT INPL
Year 2016Primer Type MN Scour Code
Painted Area
Unsound Paint % Nav. Clr. (ft.)Deck Material 1 - Concrete Cast-in-Place 0.0Wear Surf Type 4 - Low Slump Concrete
Vert. 0.0 Horiz.
S I G N S +Operating Rating 2 - HS TRUCK
0 - None + B R I D G E
Inventory Rating 2 - HS TRUCK 1.3
2.2Deck Rebars Install Year
Deck Rebars
Finish TypeWear Course/Fill Depth 0.00 ft.
0 - None
Design Load 0 - Other/Unknown
+ C A P A C I T Y R A T I N G S +Deck Membrane
44 ° 3
Inspector Name Forsyth, Roy
Latitude Control Section (TH Only) Status' 35.11 ''
3 - One lane bridge for 2-way traffic
Routine Inspection Frequency 12
Sect., Twp., Range
AT E COUNTY LINE Level of Service 1 - MAINLINE
- 07W Roadway Type23 - 107N
Detour Length 99.0 mi.R A T I N G S +
Custodian 04 - City or Municipal Highway Agency
Owner 04 - City or Municipal Highway Agency
Deck 5 Unsound Deck %
C O N D I T I O N° 37 '
P - Posted for Load
Longitude 91 000+00.147 + N B I 55.74 '' Reference Point
Crew
+ I N S P E C T I O N +
Agency Br. No. 214
District 06
Bridge Match ID (TIS) 0 Userkey
MUN 154 over N CHANNEL MISS RIVER
Minnesota Structure Inventory Report
Bridge ID: 4260
+ G E N E R A L + + R O A D W A Y +
Date: 12/23/2016
Sufficiency Rating 26.6Roadway Name or Description
154
City WINONA
Routine Inspection Date 04/21/2016
Desc. Loc.
Township MUN 154
Number
NRoadway O/U Key Route On StructureMaint. Area Structurally Deficient
YRoute Sys 10 - MUNCounty 085 - Winona Functionally Obsolete
Lanes
Waterway Adequacy 8Max. Vert. Clear.
ft.Legislative District 31Aft.Potential ABC 2 - N/A ft.
ft.On - Off System Roadway Width 17.50 ft.
Vertical Clearance ft.0 - OFF
Underclearances N
Service On 5 - Highway-pedestrian Appr. Surface Width+ S A F E T Y F E A T U R E S +
5 - Waterway Bridge Roadway Width 17.5
24.0 ft.
Service Under
ft.
17.4 ft. Approach Alignment 6Horizontal Clear.
ft.
ft.+ S T R U C T U R E + Lateral Clearance
HCADT ADTT5
Year Built 1916
MN Year Reconstructed 1947 Functional Class
%Channel 8
Substructure
0Superstructure 5
ON 1 UNDER
40 YEAR 1989BMU Agreement ADT
Structure Evaluation 3If Divided
D I M E N S I O N S +Bridge Plan Location 0 - NO PLAN
Deck Geometry 3NB-EB SB-WBDate Opened to Traffic
+ R D W Y
FHWA Year Reconstructed 2003
MN Temporary Status
19 - Urban - LocalCulvert N
A P P R A I S A L R A T I N G S ++ N B I
Page 7 of 25
County:
City:
Township:
Township:Section: Range:
Span Type:
NBI Deck: Super: Sub: Chan: Culv:
Appraisal Ratings - Approach: Waterway:
Required Bridge Signs - Load Posting:
Horizntal:
Traffic:
Vertical:
MN Scour Code:
Open, Posted, Closed:
Location:
Route:
Control Section:
Local Agency Bridge Nbr.:
Ref. Pt.:
Maint. Area:
Length:
Deck Width:
Rdwy. Area/ Pct. Unsnd:
Paint Area/ Pct. Unsnd:
Culvert:
Winona
WINONA
107N23 07W
2 - Concrete Continuous 11 - Arch -Deck
5 5 5 8 N
6 8
1 - Vehicle Only (TypeR12-1A)
0 - Not Required
0 - Not Required
N - Not Applicable
P - STBL - PROT INPL
AT E COUNTY LINE
10 - MUN 154 000+00.147
1220.0
24.5
21345 sq. ft. / %
sq. ft. / %
N/A
P - Posted for Load
ft.
ft.
Postings: 4List:
MINNESOTA BRIDGE INSPECTION REPORT
01/30/2017
BRIDGE 4260 MUN 154 OVER N CHANNEL MISS RIVER
Unofficial Structurally Deficient N
YUnofficial Functionally Obsolete
Unofficial Sufficiency Rating 26.6
ELEMNBR ELEMENT NAME INSP. DATE QUANTITY
QTYCS 1
QTYCS 2
QTYCS 3
QTYCS 4REPORT TYPE
Reinforced Concrete Deck 12/23/2016 29890 SF 8880 21000 10 012 Underwater
04/21/2016 29890 SF 8880 21000 10 0Routine
Notes: All of the deck sections have cracks with efflorescence and water staining.[2014 - 2016] - no change
510 - Wearing Surfaces 21345 SF 21122 220 3 0
Notes: Low Slump Overlay with Uncoated Rebar Notes: The deck was repaired and overlaid in 2003 with low slump concrete overlay. There isdelaminated concrete at both joints adjacent to the curb in the 6th and 7th deck sections from the west end.[2014] - no change [2015 -2016] - unsound area <0.1%
Underwater 12/23/2016
21345 SF 21122 220 3 0Routine 04/21/2016
Reinforced Concrete OpenGirder/Beam
12/23/2016 600 LF 540 50 10 0110 Underwater
04/21/2016 600 LF 540 50 10 0Routine
Notes: The concrete deck girders are located in Spans 1 through 9 and span 24. There are two concrete deck girders per span and are ofvarying depths.There are scattered areas of minor vertical cracks with some minor concrete scaling and some exposed vertical rebars.2013 - There are some areas of spalling concrete with exposed rebar near open joints.[2014 - 2016] - no change
Reinforced Concrete Arch 12/23/2016 1840 LF 887 603 350 0144 Underwater
04/21/2016 1840 LF 887 603 350 0Routine
Notes: 2013 - Most patches have minor hairline cracks with some spall and delamination around the edge of the patch.
Refer to the snooper report for this element.
[2014] - no change [2015 - 2016] - some spalls have exposed rebar.
Arch Spandrel Column Notes: Starting at span 10 there are eight spandrel columns per span.
Refer to the snooper report for this element.
2013 - All spandrels have random cracking.[2014] - no change [2015 -2016] - some patches and delaminations
Page 8 of 25
Reinforced Concrete Floor Beam 12/23/2016 2352 LF 1802 500 50 0155 Underwater
04/21/2016 2352 LF 1802 500 50 0Routine
Notes: There are seven 16' floorbeams per span. There are numerous patched areas along the concrete floorbeams with some having randomcracks and delaminated areas. There are several exposed vertical and horizontal rebar.
Refer to the snooper report for this element.
2013 - Several concrete floor beams have cracking, rust staining, delaminations, and section loss on exposed rebars near open joints. There is65' of deterioration on spans 1-9. The remainder is over the water.[2014 - 2016] - no change
Reinforced Concrete Column 12/23/2016 44 EA 15 27 2 0205 Underwater
04/21/2016 44 EA 15 27 2 0Routine
Notes: There are total of 22 Piers with two columns per pier for a total of forty four (44) columns. There are columns that have random crackswith delaminated areas.
Refer to the snooper report for this element.
2013 - Pier 11-both columns have random cracks and spalls/delamination, Pier 13-both columns have random cracks and spalls/delamination,Pier 16-both columns have random cracks and spalls/delamination[2014] - no change[2015-2016] - some new patches have delaminations.
Reinforced Concrete Pier Wall 12/23/2016 528 LF 300 224 4 0210 Underwater
04/21/2016 528 LF 300 224 4 0Routine
Notes: [2015-2016] - spans 10-22 have pier walls in the water. refer to the snooper report for pier wall notes. pier wall element shall have thesame quantity as pier cap.
Reinforced Concrete Abutment 12/23/2016 75 LF 0 65 10 0215 Underwater
04/21/2016 75 LF 0 65 10 0Routine
Notes: There is no abutment on the west end of the bridge.East Abutment - there is an open full height vertical crack in the center of the abutment. The crack opening varies from 1/4" + and becomeswider at the bottom. There are spalls and delaminated concrete along the SE and NE edges of the abutment. [2014 -,2015] - no change.[2016] East abutment wall has a full width leaching horizontal crack, located approx. half way up the wall.
Wingwall notes: The wingwalls are located only on the east end of the bridge.SE Wingwall - there are several full height vertical cracks in the wingwall.NE Wingwall - there is a diagonal crack in the wingwall.[2014] - no change [2015] - the front corner of the NE wingwall next to the abutment has spalls and delaminations and cracking patches.[2016] Each wingwall has a full length cold joint (horizontal crack)
Reinforced Concrete Pile Cap/Footing 12/23/2016 12 LF 0 12 0 0220 Underwater
Notes: [2016 Underwater Inspection] - Pier footings are exposed at Piers 1 through 12.
Reinforced Concrete Pier Cap 12/23/2016 528 LF 264 254 10 0234 Underwater
04/21/2016 528 LF 264 254 10 0Routine
Notes: Starting at pier 10 each pier has 16' long caps. Refer to the snooper report for this element.2013 - As noted in the snooper report. [2014-2016 ] - no change
Open Expansion Joint 12/23/2016 349 LF 349 0 0 0304 Underwater
04/21/2016 349 LF 349 0 0 0Routine
Notes: The open joints have new steel edge plates. At the time of this inspection no deterioration was noted.[2014 - 2016] - no change
Reinforced Concrete Approach Slab 12/23/2016 370 SF 0 0 370 0321 Underwater
04/21/2016 370 SF 0 0 370 0Routine
Notes: The concrete approach is on the east end of the bridge. The concrete is broken up at the joint with the deck and has settled up to 3" ormore. Attempts have been made to patch the approach with bituminous.[2014, 2015] - no change [2016] Same plus moderate scaling concrete and settlement, full width . Use CS 3
ELEMNBR ELEMENT NAME INSP. DATE QUANTITY
QTYCS 1
QTYCS 2
QTYCS 3
QTYCS 4
BRIDGE 4260 MUN 154 OVER N CHANNEL MISS RIVER
REPORT TYPE
Page 9 of 25
Reinforced Concrete Bridge Railing 12/23/2016 2440 LF 2342 90 8 0331 Underwater
04/21/2016 2440 LF 2342 90 8 0Routine
Notes: All rail sections were repaired in 2003. The south side rail at joint 12 has a diagonal crack with a 8" x 12" delaminated area of concrete.2012 - there is a 1' x 1' delamination located between the 6th and 7th joint on the front face of the north rail.[2014] - no change [2015 - 2016] - several rail sections on each side with moderate patching have leaching random cracks.
Critical Deficiencies or Safety Hazards 12/23/2016 1 EA 1 0 0 0800 Underwater
04/21/2016 1 EA 1 0 0 0Routine
Notes: [2014 - 2016] - No critical findings were observed at the time of inspection.
Concrete Decks - Cracking & Sealing 12/23/2016 2200 LF 400 1800 0 0810 Underwater
04/21/2016 2200 LF 400 1800 0 0Routine
Notes: There are numerous unsealed transverse and longitudinal cracks across the entire deck surface. There is over 90 linear feet of cracksin each deck section.[2014 - 2016] - no change
Bituminous Approach Roadway 12/23/2016 1 EA 0 1 0 0822 Underwater
04/21/2016 1 EA 0 1 0 0Routine
Notes: The bituminous approach is on the west end of the bridge. The approach is 6" lower than the deck. A 2' wide concrete slope ramp waspoured at the end of the deck to level the gap between the bituminous approach and the deck. The concrete ramp has unsealed cracks and isdelaminated.[2014 - 2016] - no change
Secondary Members (Superstructure) 12/23/2016 29 EA 28 1 0 0855 Underwater
04/21/2016 29 EA 28 1 0 0Routine
Notes: The secondary elements are the struts between the columns on piers 4 to 10.The strut at pier 8 has an area of poorly consolidated concrete and a delamination on the bottom.2013 - quantity changed due to the fact that there are 2 struts on spans 10-22[2014 - 2016] - no change
Concrete Shear Cracking 12/23/2016 1 EA 1 0 0 0883 Underwater
04/21/2016 1 EA 1 0 0 0Routine
Notes: [2016] No shear cracks found at concrete elements.
Scour 12/23/2016 1 EA 1 0 0 0885 Underwater
04/21/2016 1 EA 1 0 0 0Routine
Notes: An underwater inspection on the bridge was completed by Ayres Associates in October of 2004. No corrective actions wererecommended. The Ayres report stated that rip rap has been placed around the pier footings and that the concrete below the water is in faircondition.[2014 - 2016] - no change
Load Posting or Vertical ClearanceSigning
12/23/2016 1 EA 1 0 0 0890 Underwater
04/21/2016 1 EA 1 0 0 0Routine
Notes: [2016] correct load posting sign (4T) is posted at each end.
Other Bridge Signing 12/23/2016 1 EA 1 0 0 0891 Underwater
04/21/2016 1 EA 1 0 0 0Routine
Notes: Load posting, speed limit, and danger signs are posted on both ends of the deck.[2014 - 2016] - no change
Slopes & Slope Protection 12/23/2016 1 EA 0 1 0 0892 Underwater
04/21/2016 1 EA 0 1 0 0Routine
Notes: There is erosion of the slope along the SE wingwall.[2014 - 2016] - no change
ELEMNBR ELEMENT NAME INSP. DATE QUANTITY
QTYCS 1
QTYCS 2
QTYCS 3
QTYCS 4
BRIDGE 4260 MUN 154 OVER N CHANNEL MISS RIVER
REPORT TYPE
Page 10 of 25
Deck & Approach Drainage 12/23/2016 1 EA 1 0 0 0894 Underwater
04/21/2016 1 EA 1 0 0 0Routine
Notes: All deck drains were open.[2014 - 2016] - no change
Sidewalk, Curb, & Median 12/23/2016 1 EA 0 1 0 0895 Underwater
04/21/2016 1 EA 0 1 0 0Routine
Notes: The curbs were repaired under the deck contract in 2003.There is a spall in the curbing in the NE end of the 4th deck section from the west end of the bridge. There are unsealed cracks in both curbs.[2014 - 2016] - no change
Miscellaneous Items 12/23/2016 1 EA 0 1 0 0899 Underwater
04/21/2016 1 EA 0 1 0 0Routine
Notes: The sidewalk on the NE end of the deck is broken up. There is a 2' gap between the sidewalk and the end of the bridge. The railingalong the sidewalk is rusted through and needs to be replaced. The NE railing is inadequate for pedestrian protection and should be replaced.THIS RAILING IS DANGEROUS. The SE side rail is new and in good condition.2012 - NE Railing has been replaced. Replacement railing is a new square tube welded railing.2013 - The sidewalk on the NE end of the deck is broken up. There is a 12' gap along the curb near the end of the bridge at the SE corner.[2014 - 2016] - no change
Protected Species 12/23/2016 1 EA 0 1 0 0900 Underwater
04/21/2016 1 EA 0 1 0 0Routine
Notes: [2016] There are swallow nests on the bridge.
General Notes: BRIDGE WAS CLOSED 11/1/96 AS ORDERED BY MN/DOT
The City of Winona contracted for the repair of the deck and railing in 2003. After repair of the deck, all pourable joints wereremoved. After the repairs in 2003 were completed, Mn/DOT personnel started inspecting this structure. A separate contractwas issued in 2004 to repair the pier scour. Scour was repaired by adding rip rap around the piers. The bridge was re-openedafter the scour repair was completed. An underwater inspection was completed on the bridge by Ayres Associates in Octoberof 2004. Ayres report stated that no corrective actions will be needed.
Mn/DOT inspection personnel used a boat to inspect the bridge in 2005.Mn/DOT inspection personnel used a snooper to inspect the bridge in 2008.[2011] - inspected by Gary Waletzki.[2012] - inspected by Steve Miller.[2013] - inspected by Gary Waletzki, Aaron Forthun, and Robert Pyfferoen. Mn/DOT inspection personnel used a snooper toinspect the bridge.[2014 & 2016] - inspected by Robert Pyfferoen. Limited access to River Spans. Visual assistance with binoculars was used.The arch span elements 144, 155, 385, 380, 205, and 234 were not closely inspected at this time due to the limited access.[2015] - inspected by Robert Pyfferoen, Tony Bale, Aaron Forthun, and Gary Waletzki. Mn/DOT inspection personnel used aboat to inspect the bridge.
NBI code change for deck from 7 to 5 (RCP- 2016), due to under deck cracking, staining and deterioration.
58. Deck NBI:
36A. Brdg Railings NBI:
36B. Transitions NBI:
36C. Appr Guardrail NBI:
36D. Appr GuardrailTerminal NBI:
59. Superstructure NBI:
60. Substructure NBI:
61. Channel NBI:
62. Culvert NBI:
71. Waterway Adeq NBI:
72. Appr RoadwayAlignment NBI:
[2016] - moderate under deck cracking, staining & deterioration with some delamination
[2014] - cracking, delam. and spalling with exposed reinforcement
[2016] - moderate cracking, staining & isolated structural cracking
[2014] - The banks are in stable condition.
[2016] deck above floodwater elevations
[2015] - very minor speed reduction required
ELEMNBR ELEMENT NAME INSP. DATE QUANTITY
QTYCS 1
QTYCS 2
QTYCS 3
QTYCS 4
BRIDGE 4260 MUN 154 OVER N CHANNEL MISS RIVER
REPORT TYPE
Page 11 of 25
ELEMNBR ELEMENT NAME INSP. DATE QUANTITY
QTYCS 1
QTYCS 2
QTYCS 3
QTYCS 4
BRIDGE 4260 MUN 154 OVER N CHANNEL MISS RIVER
REPORT TYPE
Inspector's Signature Reviewer's Signature
Page 12 of 25
Photo 1 - Overall looking south.
Photo 2 - East Abutment looking northeast.
Pictures
Page 13 of 25
Pictures
Photo 3 - Pier 1 looking east.
Photo 4 - Pier 2 looking east.
Page 14 of 25
Pictures
Photo 5 - Pier 3 looking east.
Photo 6 - Pier 4 looking east.
Page 15 of 25
Pictures
Photo 7 - Pier 5 looking east.
Photo 8 - Pier 6 looking east.
Page 16 of 25
Pictures
Photo 9 - Pier 7 looking east.
Photo 10 - Pier 8 looking east.
Page 17 of 25
Pictures
Photo 11 - Pier 9 looking east.
Photo 12 - Pier 10 looking east.
Page 18 of 25
Pictures
Photo 13 - Pier 11 looking east.
Photo 14 - Pier 12 looking west.
Page 19 of 25
Pictures
Photo 15 - Pier 13 looking west.
Page 20 of 25
Page 21 of 25
UNDERWATER BRIDGE INSPECTION
DEPARTMENT OF TRANSPORTATION
MINNESOTA
Checked By: Scale:
Drawn By: Date:
www.collinsengr.com
(651) 646-8502
St. Paul, MN. 55104
Suite 206
1599 Selby Ave.
Project:
N
SOUNDING PLAN
Pier 9 Pier 8 Pier 7 Pier 6
(See Figure 1)
MA
TC
H
LIN
E
A
(See Figure 3)
MA
TC
H
LIN
E
B
Flo
w
Mississip
pi
River
North Channel
4
2 2 2 2
3 3 3 3
-9.7 -8.2 -8.8-11.6-8.7 -9.7 -9.7 -8.0-12.5 -11.0 -9.7
-5.6
-5.2
-5.8 -5.8
-5.5
-5.7 -7.4
-7.2
-7.4 -8.5
-7.4
-8.7 -6.8
-6.3
-6.9 -7.3
-6.5
-7.2 -7.5
-6.4
-7.1 -8.5
-8.2
-8.1
-13.8-16.6-14.7 -13.7 -8.0-18.5 -13.9 -16.0 -13.1-8.6 -9.5 -8.5-6.0-7.0-13.6
-8.6
-11.5
-15.9
-10.3
-14.4 -17.8 -13.5 -15.8 -11.8 -15.5 -11.2 -17.2
-6.3
-6.3
-6.7 -6.0
-7.2
-7.2 -8.7
-8.9
-7.4
-7.2
-8.2
-9.8
-7.8
-7.7 -8.4
-8.6
-9.2 -8.3
-9.7
-7.9 -9.5 -9.6 -9.5
Legend
Timber Debris
-2.0
-5.2 Sounding Depth from Waterline (08/16/12)
Refer to Figure 1 for General Notes.
Note:
INSPECTION AND SOUNDING PLAN
DISTRICT 6, WINONA COUNTY
OVER THE NORTH CHANNEL OF THE MISSISSIPPI RIVER
STRUCTURE NO. 4260
MJS
RAF
9687
11/30/2016
1"=50'
Figure No.:2
-10.7 -10.8 -10.7 -10.2 -10.9 -10.6
-10.8 -10.5
-9.4 -11.3 -11.9 -10.1 -10.2 -12.2 -10.7 -13.7 -10.7 -11.1 -10.9
-11.2
-10.1
-10.2
-10.7
-14.1 -13.3 -13.9 -14.2 -14.1 -13.6 -14.2 -13.8
-0.5 VFE-2.0 VFE
-1.0 VFE
-4.5 VFE
-2.5 VFE
-1.5 VFE
-3.0 VFE
-1.0 VFE
-1.0 VFE
-2.0 VFE-2.5 VFE
-0.5 VFE
and no exposed steel.
6 inches above to 2 foot below the waterline with up to 6 inches of penetration
Pier 9 exhibited an area of section loss on the downstream south corner from 4
with it.
widespread throughout all piers. Cracking often has efflorescence associated
and horizontal hairline cracks were also observed on the concrete shaft surfaces
penetrations of 1 inch and maximum penetrations of up to 6 inch. Random vertical
scaling from 1 foot above the waterline to 1 feet below the waterline with typical
3 The submerged concrete was typically in satisfactory condition with moderate
footing typically exhibited rough surfaces with up to 3 inch maximum penetration.
to top of footing or to no lower than 3 feet below top of footing. The concrete
It was observed around the entire perimeter of all piers typically extending
typically 1 to 2 feet in diameter with a maximum diameter of up to 3 feet.
2 The channel bottom of Piers 1 through 12 consisted of riprap
INSPECTION NOTES:
Sounding Depth from Waterline (11/30/16)
Page 22 of 25
Page 23 of 25
UNDERWATER BRIDGE INSPECTION
DEPARTMENT OF TRANSPORTATION
MINNESOTA
Checked By: Scale:
Drawn By: Date:
www.collinsengr.com
(651) 646-8502
St. Paul, MN. 55104
Suite 206
1599 Selby Ave.
Project:
UPSTREAM FASCIA PROFILE
DOWNSTREAM FASCIA PROFILE
(See Figure 5)
MA
TC
H
LIN
E
C
Shoreline
~ Pier 12 ~ Pier 11 ~ Pier 10 ~ Pier 9 ~ Pier 8
~ Pier 7
Reference 100.0
@ Springline Pier 1
(See Figure 5)
MA
TC
H
LIN
E
C
~ Pier 12 ~ Pier 11 ~ Pier 10 ~ Pier 9 ~ Pier 8
~ Pier 7
Reference 100.0
@ Springline Pier 1
120.0
80.0
60.0
40.0
120.0
80.0
60.0
40.0
Vertical Scale: 1" = 50'-0"
~ Pier 13
~ Pier 13
W.L. El. 94.1
on 08/16/12
Channel Bottom
on 08/16/12
Channel Bottom
Refer to Figure 1 for General Notes.
Note:
Vertical Scale: 1" = 50'-0"
UPSTREAM AND DOWNSTREAMFASCIA PROFILES
DISTRICT 6, WINONA COUNTY
OVER THE NORTH CHANNEL OF THE MISSISSIPPI RIVER
STRUCTURE NO. 4260
MJS
RAF
9687
11/30/2016
1"=50'
Figure No.:4
Legend
Channel Bottom per 2012 Inspection
Channel Bottom per 2016 Inspection
Shoreline
W.L. El. 94.1
on 11/30/16
Channel Bottom
on 11/30/16
Channel Bottom
Page 24 of 25
UNDERWATER BRIDGE INSPECTION
DEPARTMENT OF TRANSPORTATION
MINNESOTA
Checked By: Scale:
Drawn By: Date:
www.collinsengr.com
(651) 646-8502
St. Paul, MN. 55104
Suite 206
1599 Selby Ave.
Project:
UPSTREAM FASCIA PROFILE
DOWNSTREAM FASCIA PROFILE
(See Figure 4)
MA
TC
H
LIN
E
C
~ Pier 7
~ Pier 6 ~ Pier 5 ~ Pier 4 ~ Pier 3 ~ Pier 2
Shoreline
Reference 100.0
@ Springline Pier 1
(See Figure 4)
MA
TC
H
LIN
E
C
~ Pier 7
~ Pier 6 ~ Pier 5 ~ Pier 4 ~ Pier 3 ~ Pier 2
@ Springline Pier 1
Reference 100.0
120.0
80.0
60.0
40.0
80.0
60.0
40.0
120.0
Vertical Scale: 1" = 50'-0"
Vertical Scale: 1" = 50'-0"
~ Pier 1
~ Pier 1
W.L. El. 94.1
on 08/16/12
Channel Bottom
on 0816/12
Channel Bottom
Refer to Figure 1 for General Notes.
Note:
Refer to Figure 1 for General Notes.
Note:
UPSTREAM AND DOWNSTREAMFASCIA PROFILES
DISTRICT 6, WINONA COUNTY
OVER THE NORTH CHANNEL OF THE MISSISSIPPI RIVER
STRUCTURE NO. 4260
UPSTREAM AND DOWNSTREAMFASCIA PROFILES
MJS
RAF
9687
11/30/2016
1"=50'
Figure No.:5
Shoreline
W.L. El. 94.1
on 11/30/16
Channel Bottom
on 11/30/16
Channel Bottom
Page 25 of 25