BQE Hicks Street Wall Repair

13
BQE Hicks Street Wall Repair September 24, 2020

Transcript of BQE Hicks Street Wall Repair

Page 1: BQE Hicks Street Wall Repair

BQE Hicks Street Wall RepairSeptember 24, 2020

Page 2: BQE Hicks Street Wall Repair

Meeting Protocols

• All attendees will be placed on mute at the beginning of the presentation.

• Attendees will view the presentation through screen sharing but participant cameras will not be accessible.

• Please enter questions or comments in the Q&A panel.

2

Page 3: BQE Hicks Street Wall Repair

Hicks Street Wall Repair3

Page 4: BQE Hicks Street Wall Repair

Work Location

Hicks Street Wall

Queens-bound BQE to Cadman Plaza West (Exit

28A)

4

Page 5: BQE Hicks Street Wall Repair

Planned Work

• Remove loose/deteriorated concrete

• Replace deteriorated rebar

• Repair brackets supporting granite capstone

• Replace concrete

• Replace sidewalk per NYSDOT standard

5

Page 6: BQE Hicks Street Wall Repair

Equipment

• Air compressors

• Scissor lifts

• Telehandler

• Chipping guns

6

Page 7: BQE Hicks Street Wall Repair

Full Closure – Fall 2020

7

Partial Closure – Spring 2021

Closures

Top of BQE Ramp to Hicks Street Hicks Street to Old Fulton Street

Page 8: BQE Hicks Street Wall Repair

MPT

• VMS Board before Atlantic Avenue alerting drivers to ramp closure and detour

8

Example VMS signage

Page 9: BQE Hicks Street Wall Repair

MPT

Hicks Street Ramp ClosureSignage before Hicks Street

Motorists who miss signage at Atlantic Ave will be directed to take Tillary Street Exit

9

Page 10: BQE Hicks Street Wall Repair

Full Ramp Closure – Queens-bound BQE to Cadman Plaza West (Exit 28A)Motorists should exit the BQE at Atlantic Avenue (Exit 27)

Ramp Closed

MPT

Page 11: BQE Hicks Street Wall Repair

Queens-Bound Detour to Old Fulton

Street

1. Take Exit 27 to Atlantic Ave and turn left

2. Continue on Atlantic Ave and turn right

on Furman Street

3. Proceed north on Furman Street

4. Turn right on Old Fulton Street

Detours to Old Fulton Street

Page 12: BQE Hicks Street Wall Repair

Project Schedule

• Phase 1: Week of October 5th, 2020 to mid-December 2020 (end date weather permitting)

• Demobilization & Ramp opened: December 2020 to March 2021

• Phase 2: April 2021 to September 2021

• Work hours: Monday to Friday: 7 a.m. to 6 p.m.

Intermittent Saturdays: Rain dates as required

No night time work anticipated

Page 13: BQE Hicks Street Wall Repair

Community Outreach

• Stakeholder coordination

• Elected Officials

• Community Boards

• Residents

• PS 8

• Coordination with Essential City Services

• First responders and emergency services

• Regular project updates

• LiaisonCommunity Liaison:

Anita Navalurkar

[email protected]