BOYA OVAL WESTERN LIBRARY CONCEPT DESIGN PROJECT COSTINGS CURRENT BUDGET $M 8.10 BRAUDE & ASSOC ESTIMATE $M 7.95 COMPLETE PROJECT AS DESIGNED: Quantity Surveyor costing $M10.42 Shire allowance for contingencies $M .30 Total $M10.72 STAGED PROJECT: Stage one – Library/Community buildings/oval and undercroft carpark :- Quantity Surveyor costing $M 7.90 Shire allowance for contingencies $M .30 Sub Total $M 8.20 Stage two _ Sports Clubrooms/changerooms and remaining parking :- Quantity Surveyor costing $M 2.65 Shire allowance for contingencies $M .10 Sub Total $M 2.75 Combined Total For Staged Project $M10.95
Transcript of BOYA OVAL WESTERN LIBRARY CONCEPT DESIGN PROJECT …
BOYA OVAL WESTERN LIBRARY CONCEPT DESIGN PROJECT COSTINGS
CURRENT BUDGET $M 8.10
BRAUDE & ASSOC ESTIMATE $M 7.95
COMPLETE PROJECT AS DESIGNED:
Quantity Surveyor costing $M10.42
Shire allowance for contingencies $M .30
Total $M10.72
STAGED PROJECT:
Stage one – Library/Community buildings/oval and undercroft carpark :-
Quantity Surveyor costing $M 7.90
Shire allowance for contingencies $M .30
Sub Total $M 8.20
Stage two _ Sports Clubrooms/changerooms and remaining parking :-
Quantity Surveyor costing $M 2.65
Shire allowance for contingencies $M .10
Sub Total $M 2.75
Combined Total For Staged Project $M10.95