BOYA OVAL WESTERN LIBRARY CONCEPT DESIGN PROJECT …

4
BOYA OVAL WESTERN LIBRARY CONCEPT DESIGN PROJECT COSTINGS CURRENT BUDGET $M 8.10 BRAUDE & ASSOC ESTIMATE $M 7.95 COMPLETE PROJECT AS DESIGNED: Quantity Surveyor costing $M10.42 Shire allowance for contingencies $M .30 Total $M10.72 STAGED PROJECT: Stage one – Library/Community buildings/oval and undercroft carpark :- Quantity Surveyor costing $M 7.90 Shire allowance for contingencies $M .30 Sub Total $M 8.20 Stage two _ Sports Clubrooms/changerooms and remaining parking :- Quantity Surveyor costing $M 2.65 Shire allowance for contingencies $M .10 Sub Total $M 2.75 Combined Total For Staged Project $M10.95

Transcript of BOYA OVAL WESTERN LIBRARY CONCEPT DESIGN PROJECT …

Page 1: BOYA OVAL WESTERN LIBRARY CONCEPT DESIGN PROJECT …

BOYA OVAL WESTERN LIBRARY CONCEPT DESIGN PROJECT COSTINGS

CURRENT BUDGET $M 8.10

BRAUDE & ASSOC ESTIMATE $M 7.95

COMPLETE PROJECT AS DESIGNED:

Quantity Surveyor costing $M10.42

Shire allowance for contingencies $M .30

Total $M10.72

STAGED PROJECT:

Stage one – Library/Community buildings/oval and undercroft carpark :-

Quantity Surveyor costing $M 7.90

Shire allowance for contingencies $M .30

Sub Total $M 8.20

Stage two _ Sports Clubrooms/changerooms and remaining parking :-

Quantity Surveyor costing $M 2.65

Shire allowance for contingencies $M .10

Sub Total $M 2.75

Combined Total For Staged Project $M10.95