Bill of Quantity
CONSTRUCTUIN OF UNDP
PARKING AREA
-
7/31/2019 Boq Gaza Park Boq
2/13
1/1
Demolishing of the existing store 120 m2 area according to
the approved method statement and including transfer the
rubble to approved dump yard according to the UNDPengineer instructions.
L.S 1
1/2
Relocation and replanting of the existing trees. The work
includes importing all required materials; such as
agricultural soil, fertilizer, concrete basins, etc. and making
good all according to drawings, specifications and
instructions of the Engineer.
L.S 1
1/3
Clean, excavate, cut and fill the parking area and Ramp
with clean dune sand to the bottom of the sub-base layer
design level including watering, compaction not less than
98% & CBR not less than 15% ,all according to drawing
and technical specifications .
m2 1,050.0
1/4
Supply and lay approved sub-base material ( Kurkar) of 20
cm thickness for the parking area in one layer with CBR.>
30%, watering and compaction up to 98% maximum drydensity according to modified proctor test. all according to
drawing and technical specifications .
m2 1,000.0
1/5
Supplying ,spreading ,leveling , damping and compacting
(M.D.D 100%) of 15cm base coarse material with CBR80
up to required` levels, according to drawing specifications
and under supervision .
m2 1,000.0
1/6
Supply, spread, install approved colored interlock tiles 8
cm thick including 5 cm clean sand bed, compacting and
tiles testing all according to drawings, specifications and
instructions by the Engineer.
m2 1,000.0
Total (US $)
Total
AmountUS $
QuantityUnitUnit Rate
US $(letters)
Item
No.Description
Unit Rate
US $(Numbers)
Bill No. 1
Excavation and Interlock Work
2
-
7/31/2019 Boq Gaza Park Boq
3/13
Rates of Concrete Works shall include:-
1. All form works and shuttering (new lumber for shuttering)
in any form, shape and size . Making chamfered and curved
edges, allowing for and making grooves and sleeves and
using Tie Rods (Batant) for concrete walls ; removal of
forms and cleaning of all exposed tie wires and rods. Steel
forms must be used in shuttering the external decorations.
2. Supplying, Casting, vibrating and curing as per
specifications.
3. Approved additives and admixtures.
5. Supplying reinforcement of any grade, size and length as
detailed in the drawings, storing on site including cutting,
bending and fixing in position and providing all tying wires,
spacers, shop drawings, testing and bar bending schedules
6. Painting of exposed surfaces of underground reinforced
concrete elements with two coats of hot bituminous paint(75/25) after primer layer , the strokes of each layer to be
opposite to each other.
7. Compaction and testing under the foundation, ground
beams, and ground slabs, the compaction must exceed 97%
of MDD.
8. All works according to specifications , drawings and
supervisor engineer instructions
2/1
Supply and cast ready mix reinforced concrete B(250)
kg/cm2
for the footings and ground beams for bounadary
beams around the parking area, edge beam. The work shall
include polythene sheets under the footings and beams,
excavation, compaction and backfilling ,all according to
drawings and technical specifications .
M3 16
2/2Ditto but for middle and copping beam as per specifications,
drawings and supervisor engineer's instructions.M
3 8
2/3
Supply and cast ready mix reinforced concrete B (300)
kg/cm2 for columns, footing, ground beams and lintels for
guard room . Then price include the cost of used materials
equipments, and workmanship for all necessary protections
and safety measures for the excavated area, in addition to the
protection of the neighbouring foundations if any.
M3 6
2/4
Supply and cast ready mix reinforced concrete B (300)
kg/cm2 for retaining walls (footing, stem) stairs and retaining
beams. The price includes the cost of used materials,
equipments and workmanship for all necessary protections
and safety measures for the excavated area, in addition to the
protection of the neighbouring foundations if any. all works
should be according to Drawings, Specifications and
instructions of the Engineer.
M3 24
Bill No. 2
Concrete Works.Unit Rate
US $
(letters)
Unit Rate
US $
(Numbers)
Total
Amount
US $
Item
No.Description Unit Quantity
3
-
7/31/2019 Boq Gaza Park Boq
4/13
Unit Rate
US $
(letters)
Unit Rate
US $
(Numbers)
Total
Amount
US $
Item
No.Description Unit Quantity
2/5
Supply and cast ready mix concrete B250 for Ribbed Slabs
of 25cm thickness including reinforced steel, hollow block
(25x40x17cm), drop beams and electrical conduits and all
other materials according to Drawings, Specifications and
instructions of the Engineer.
M2 40
2/6
Supply and cast reinforced concrete (B-250) concrete lining
for Ground Slab, ramp and Abutment for retaining wall of
10cm. thickness including steel reinforcement ( 8 mm
diameter every 20 cm in both directions), reinforced edge
beam and polythene sheet , the rate shall include applying
well trowelled surface, all in according to drawings,
specifications and engineer's instructions.
M2 40
2/7Ditto but 15 cm thick with 10 mm diameter of reinforcement
steel every 20 cm in both directions for cars' ramp.M
2 60
Total (US $)
4
-
7/31/2019 Boq Gaza Park Boq
5/13
The price include:
1- supplying hollow or solid cement block from goodand approved factory in perfect dimension and build it
in good manner with a compressive strength 35 kg/cm2
for hollow block and 60 kg/cm2
for solid block. This
item will include cement mortars, reinforced concrete
infill (B250) between columns & block walls (10-20 cm
wide) with 28mm/40cm horizontally and 210mm
vertically according to drawings, pipes encasement, and
bituminous paper between block work and drop beams
& all requirements needed to finish the works according
to the drawings, specification and to the supervision
engineer instructions.
2- Providing samples for approval and all the required
tests.
3/1
Supply and build hollow cement block 40x20x20cm for
external walls according to the drawings, specification
and to the supervision engineer instructions.M
2 400
3/2
Supply and build solid cement block 40x20x20 cm,
under ground beams, and external boundary for building
including painting the buried parts with one coat of
primer and two coats of hot bitumen according to the
drawings, specification and to the supervision engineer
instructions.
M2 50
Bill No. 3
Building Works.
Total (US $)
Unit Rate
US $
(letters)
Unit Rate
US $
(Numbers)
Total
Amount
US $
Item
No.Description Unit Quantity
5
-
7/31/2019 Boq Gaza Park Boq
6/13
All works must be according to drawings, specification and engineer
instructions. Rates shall include :
Supply of all needed materials, including galvanized angles for the
corners as well as the use of galvanized wire mesh between
concrete and block work.
Preparation works by covering all conduits of electricity, water
supplies , etc, with a galvanized wire mesh at least 20cm width
coated by mortar (1:1) cement : sand and the work includes removal
of wires and nails and cleaning of surfaces to be ready for
plastering.
Contractor shall take into consideration that all direct and indirect
works and expenses required for the completion of the coming items
are included in the unit price.
Trimming of concrete chippings, removing the wires and etc. and
cleaning of existing surfaces to be ready for plastering.
This should be done prior to commencement of plastering and after
obtaining a written approval from the supervision engineer.
Curing with water for at least three days for each coat.
4/1
Supply and make internal plastering 13 mm thick for ceiling, walls
and soffits. The work includes rough primer nail rendering to form a
key with (mix 1:1) cement sand, second layer 13mm: Base-Coat
"Rendering" with (1:3:0.25) cement: sand: lime and third layer:
Finishing Coat with (1:4:0.50) cement: sand: lime . Works include
all materials needed to finish the works according to specifications ,
drawings and supervisor engineer's instructions.
M2 120
4/2
Supply and make external plastering 20mm thick to walls with four
faces : the first is the rough nail rendering (mix 1:1) cement sand;
the second is 5mm thick mortar (mix 1: 2) cement: sand, the third is
the undercoat 13mm (mix 1: 3 :0.25) cement:sand:lime, the forth is
two coats of Tyrolean finish ( mix 1: 3) white cement to fineaggregate (Quartiz) and all is according to specifications , drawings
and supervisor engineer's instructions.
M2 600
Bill No. 4
Plaster Works.
Total (US $)
ItemNo.
Description Unit Quantity
Unit Rate
US $(letters)
Unit Rate
US $(Numbers)
Total
AmountUS $
6
-
7/31/2019 Boq Gaza Park Boq
7/13
5/1
Supply and install terrazzo floor tiles (grade A) size
25cm x 25cm x 2.5cm laid on 2cm mortar bed and 5
cm sand bed and terrazzo skirting 25cm x 7cm x1cm
including all materials and testing as per
specifications and drawings
M2 35
5/2Supply and Paint the ceiling with one coat of Pendroleprimer and at least two coats of emulsion paint
(Polyside) as per specification and drawingsM2 40
5/3
Supply and Paint, internal walls with one coat of
Pendrole primer and at least two coats of emulsion
paint (Supercryle) as per specification and drawingsM2 120
5/4
Supply and Paint, external road mark painting for the
roof of guard room, for the cars parking and tracks
arrows with one prime coat and two finishing coats of
approved brand name painting material or equal
approved as specification and drawings
M2 100
5/5
Supplying & fix (W1) (1.2X1.6 m) colored aluminum
window section 7000 with two rails, with min. wallthick 1.5mm, glass 4 mm thick, ironmongery ,
accessories and hard ware as per specification and
drawings.
No. 2
5/6
Supply and fix colored aluminum window W2 hinged
type section 4500 type , overall s ize 70 x100 cm,
complete with frame, two hinges at the mid (Jack
type), glass 4mm thick, ironmongery and hardware
and as per specifications and drawings.The work shall
include applying Shatter Resistance Film to the glass.
No. 1
5/7
Supply & fix Wooden Door D1 (80X220X4.5 cm)
made of wood grade A including frame cover
mould, architrave and at least two coats of oil paint,
hard ware locked type Walley switch or equivalent
and brass hinges 10cm height and all other fitting
according to specification and drawings.
No. 1
5/8
Supply and install white glazed wall tiles (grade A)
size 20 cm x 20cm x 6mm thick laid on mortar
backing up to lintel level including limefree cement
plaster coat (1:3) as specified in the drawing and
approved by representative engineer.
M2 20
5/9
Supply and install best quality non slipping ceramic
floor tiles (grade A) size 20 cm x 20cm x 6mm thick
as specification and drawings.M2
5
5/10
Supply and install roof water proofing course
consisting of polypit sheets (4.0mm thick) and base
coat of bitumen and making good all according to
specifications and instructions by the Engineer.Therate include verticals parts skirting as per specificat
M2 40
Total (US $)
Unit Rate
US $
(Numbers)
Total
Amount
US $
Bill No. 5
Finishing work
Item
No.Description Unit Quantity
Unit
Rate
US $
7
-
7/31/2019 Boq Gaza Park Boq
8/13
.6/1 Supplying , fixing and erecting 3" hot galvanize steel Pipe
3 m hight, with 3 mm thick hot galvanized sheet base
plate, 2020 cm . The item shall include 43/4" Galv.
Steel bolts. The item shall also include outdoor street
light fixture 250 Watt lamp Gaash type or equevelent with
1.5" hot galvanized arm 2 m, ignitor, choke coil, starter,
capacitor,junction box , 32.5 sq. mm NYY cable from
junction box to the outdoor street light fixture 250 Wattlamp, and all other materials and accessories required to
complete the job according to Drawings, Specifications
and instructions of the Engineer.
No. 7
.6/2 Supplying ,fixing and erecting wall outdoor mounted
projector . The item shall include 23/4" Galv. Steel
bolts , 250 Watt lamp,junction box, ignitor, choke coil,
starter, capacitor, 32.5 sq. mm NYY cable from junction
box to the outdoor street light fixture 250 Watt lamp , and
all other materials and accessories required to complete
the job according to Drawings, Specifications and
instructions of the Engineer.No. 3
.6/3 Supplying and erecting 510mm2 XLPE cable to connect
the MDB with the source. The item shall include
excavation ,backfilling, 3" flexible conduits and warningtape and all other materials and accessories required to
complete the job according to Drawings, Specifications
and instructions of the Engineer.Mr 80
.6/4 Supplying and erecting 56mm2 XLPE cable, connecting
the MDB with each junction box of the external light
Projectors. The item shall include cable channel
,excavation, backfilling, 3" flexible conduits , warning tape
and all other materials and accessories required to
complete the job according to Drawings, Specifications
and instructions of the Engineer.
Mr 120
.6/5 Supplying and installing MDB box (60x40) cm (Type is
MOELLER or equivalent). including all circuit breakers,
busbars, accessories, and all other materials and
accessories required to complete the job according to
Drawings, Specifications and instructions of the Engineer.
LS 1
.6/6 Supplying and erecting TV socket outlet including wiring
co axial cable 75 ohms and all other materials and
accessories required to complete the job according to
Drawings, Specifications and instructions of the Engineer.
No. 1
.6/7 Supplying and erecting telephone socket outlet including
wiring 2 pair cable from themain tel. box including sleeves
and all other materials and accessories required to
complete the job according to Drawings, Specifications
and instructions of the Engineer.
No. 2
.6/8 Suppling and erecting flurescent light fixture 220 V, 1X36
W, 120 cm long discharge lamp, dayligh, electronic
starter, wires, conduits, bolts & clamps. Type Gaash orequivelent and all other materials and accessories
required to complete the job according to Drawings,
Specifications and instructions of the Engineer.
No. 5
Unit Rate
US $
(Numbers)
Total
Amount
US $
Bill No. 6
ELECTRICAL WORKS
Item
No.Description Unit Quantity
Unit Rate
US $
(letters)
8
-
7/31/2019 Boq Gaza Park Boq
9/13
Unit Rate
US $
(Numbers)
Total
Amount
US $
Item
No.Description Unit Quantity
Unit Rate
US $
(letters)
.6/9 Supplying and erecting circular wall and ceiling mounted
polycarbonate light with 60 W lamp waterproof type IP54
including wires, conduits and all other materials and
accessories required to complete the job according to
Drawings, Specifications and instructions of the Engineer.
No. 2
.6/10 Supplying and erecting double pole switch Type Gewiss
or approved equal including wires, conduits and all other
materials and accessories required to complete the job
according to Drawings, Specifications and instructions ofthe Engineer.No. 3
.6/11 Supplying and erecting single phase, 220V, 16 A socket
outlet including wires, conduits and all other materials
and accessories required to complete the job according
to Drawings, Specifications and instructions of the
Engineer.No. 5
.6/12 Supplying and erecting Oz-On A/C regulator including
wires, conduits and all other materials and accessories
required to complete the job according to Drawings,
Specifications and instructions of the Engineer.
No. 1
.6/13 Supplying and erecting security lighting control panel
including one 10 A photocell, 1 three poles 3 Kw
contactor, with the needed auxiliary contacts, one toggle
switch (0,1,2), one 110 A MCB, 316 A MCB, and one24 hour timer and all other materials and accessories
according to Drawings, Specifications and instructions of
the Engineer.LS 1
.6/14 Supply, install UPVC 4" pipes for electrical cable as per
drawings , the work include Excavation ,backfilling on
layers 20 cm thick with compacting to 97% of MDD. and
all required accessories required to complete the job, all
according to drawings, specifications and instructions of
the Engineer.
Mr 100
.6/15 Supply and install 3" flexible PVC conduit with a rope
inside it for futuer ducts, the work include Excavation
,backfilling on layers 20 cm thick with compacting to 98 %
,and all required accessories required to complete the
job, all according to drawings, specifications andinstructions of the Engineer.
Mr 200
.6/16 Supply and install 60 cm internal diameter precast
circular reinforced concrete electrical manholes, complete
with B300 cast in place reinforced concrete base or
(approved precast), cast iron cover (25ton Capacity),
Frame, ring's inside , excavation in any type of soil up to
1.5 mdepth , backfilling with clean sand and compaction,
and all required accessories required to complete the job,
all according to drawings, specifications and instructions
of the Engineer.
No. 3
Total (US $)
9
-
7/31/2019 Boq Gaza Park Boq
10/13
All Plumbing works include the required units and
its accessories as described in the items and the
rates include:
1- All the plumbing units should be from the best
quality and has trade mark.
2- Submitting shopdrawing for water supply and
waste water networks for approval prior to
commencement of the work.
3-Submitting samples for all required material with
catalogue indicating its specifications.
4-All required tests , pressure for water net work ,
hydraulic test for sewage lines
5- Cleaning and desinficting all water pipes.
6- Insulation of all galvanized water pipes and
wraping it with bitumen's sheets and protect pipes
located under tiles with cement morter. In addition
to the insulation materials against heat loss for hot
water pipes.
7- All hot and cold water pipes for the points of
fixtures to the nearest distribution board.
8-All plumbing works ( wash basin, kitchen sink,
gully traps,etc) include the connection to the
nearest trap, WC to the nearest vertical sewage
header in the typical floors and WC in the GF to the
nearest manhole and include all accessories
including PVC S and caps for all the ends of pipes
7/1 Supply and fix white glazed fireclay Oriental W.C.
suite (Vitra type - grade A ), or equivalent complete
with 9 liter plastic double action flushing cistern,
and fixed chromium plated tap 1/2 Tibesa type or
equivelent, including all water supply pipes16mm(Golany) to the nearest dist. box (DB),
flushing hose sprayer, angle valves, UPVC drainage
pipe connecting to the nearest manhole or sewage
header as per specifications , drawings and
supervisor engineer instructions.No. 1
7/2 Supply and fix white glazed fire clay hand wash
basin size 55cm x45cm (Vitra type - grade A ) or
equivalent, complete with all water supply pipes
16mm (Golany) to the nearest distribution box (DB),
waste fitting, trap, plug and chain, chromium water
mixer ( Tebisa ,jack, wall mounted type or
equivalent), glazed fire clay soap holder, and the
drainage line 2 to the nearest floor trap. No. 1
7/3 Supply and install white glazed steel shower tray
size 70x70x7cm with shower mixer (Tebisa jack
type) including sprayer, hose, stand, glazed fire clay
soap holder, including all needed fittings, pipes, and
connections to water network to reach the
distribution box.including cold and hot water supply
lines EPDM 16 mm to the distribution box dia.,
waste fitting, trap, plug with chain and drainage
connection to the nearest manholes.No. 1
Total
Amount
US $
Bill No. 7
Plumbing WORKS
Item
No.Description Unit Quantity
Unit Rate
US $
(letters)
Unit Rate
US $
(Numbers)
10
-
7/31/2019 Boq Gaza Park Boq
11/13
Total
Amount
US $
Item
No.Description Unit Quantity
Unit Rate
US $
(letters)
Unit Rate
US $
(Numbers)
7/4 Supply and fix floor trap 4inch diameter, complete
with heavy duty brass grating and 4& 2 PVC
drainage pipe to the nearest manhole and including
S trap if needed as specification and drawings. No. 1
7/5 Supply and install 3" P.V.C drainage pipes
including all necessary bends connections and
making good all according to specifications and
instructions by the Engineer.
MR 97/6 Supply, paint, fix and disinfect cold water storage
plastic tank 1500 liter capacity , approved type, float
valve, overflow pipe (1diam) and drip tray, with all
connections to the rising main and distribution pipe
work and stop valves 1, and painted steel
foundation from welded angles 45x45x4.5mm
50cm high , 5cm new hard wood on the complete
area under the tanks, with all accessories as
specification and drawings. the rate includes
painting of the water tank.No. 3
7/7 Supply and install concrete manhole of internal
diameter 60 cm ,and (50-100) cm depth according to
the required level, 12cm thick plain concrete forwalls and base, slab, with cast iron cover with frame
50cm opening, 8 ton bearing capacity, including
excavation, backfilling, hunching and making good
according to specification ,drawing, and the
engineer instructions.
No. 2
7/8Supply and install water distribution box
(60x65x15) cm with Golani Pipes all needed
accessories .All lines to have Sagiv valves and Air
valves with aluminum cover as per drawings and
engineers instructions. No. 2
7/9 Supply and install PE pipe 20mm to connect the
main feeder galv. steel pipe 1" to the DB in thegaurd room with all reguired fittings and
accessories. The item includes fixing to the walls
using galvanized brakets and connecting it to theMR 70
7/10 Supply and install Galvanized steel pipe1" from the
water tanks on the UNDP buildin roof to the car
bark. The item includes fixing to the walls using
galvanized brakets and connecting it to the water
tank with all reguired fittings and accessories. MR 25
7/11 Supply and install UPVC pipes 200mm, SN8 for
outlet drain, with sockets ,work includes
excavating of trenches (depth 0.75-1.5m), bedding,
compacted backfilling with clean sand, connecting
to the existing manholes and hydraulic test
according to the specifications and the engineersMR 30
7/12 Supply and construct storm water collection gullies
of length 3.0 m as detailed in drawings constructed
of reinforced concrete B300 , including cast iron
grills, cast iron curb stone , benching, excavation
and backfilling with clean sand and compaction,
remove the surplus soil to the tip as shown in the
drawings and according to the specifications and the
engineers instructions. No. 3
Total (US $)
11
-
7/31/2019 Boq Gaza Park Boq
12/13
8/1
Supply and install steel door 2.20x0.9m (type SD1). The
price should include oil painting two coats, primer coat, and
Walley switch type lock, hinges and iron mongery all
according to drawings, specifications and instructions by
the Engineer.
No. 1
8/2
Supply and install steel door 2.20x1.0m (type SD2). The
price should include oil painting two coats, primer coat, and
Walley switch type lock, hinges and iron mongery all
according to drawings, specifications and instructions by
the Engineer.
No. 1
8/3
Supply and install steel sliding gate 2.55.0 m to be
mounted at the UNDP parking entrance .the unit rate shall
include painted one primer coat and two oil coats at least,
the unit rate shall include supplying ,installing and erecting
an approved complete electrical motorreducer ''DELMA
ROY 6 or equivalent''with electrical power capable to
operate the sliding gate ,complete with control panel ,
remote control, latches, and all needed electrical cables
,wires ,and conduits and all needed parts, fittings and
accessories .The unit rate shall include all needworkmanship ,equipment , concrete to fix the gate with the
existing walls and requirement to complete the job .The
work shall be done all as per drawings, specifications
,manufacture instructions and instructions by the Engineer.
No. 1
8/4
Supply and install steel sliding gate 2.55.0 m to be
mounted at the UNDP emergency parking exit .the unit rate
shall include painted one primer coat and two oil coats at
least, Walley switch type lock, hinges , iron mongery and
all needed parts, fittings and accessories, suspended
parbed wires .The unit rate shall include all need
workmanship ,equipment, concrete to fix the gate with the
existing walls and requirement to complete the job .The
work shall be done all as per drawings, specifications
,manufacture instructions and instructions by the Engineer.
No. 1
8/5
Supply and install fence 1.5 m height including supply and
fixing steel tri - angles edge (Type ST-37 total length 2.5m)
and fixing at least 1 m from the total length in concrete
columan, 40*40*4mm Wire Mesh 1.5m height , three rows
of 4mm Tension Wire,and Barbed wire 0.45m height, all
according to drawings and engineers instructions.
MR 120
Unit Rate
US $
(Numbers)
Total
Amount
US $
Total (US $)
Bill No. 8
Metal WORKS
Item
No.Description Unit Quantity
Unit Rate
US $
(letters)
12
-
7/31/2019 Boq Gaza Park Boq
13/13
1
2
3
4
5
6
7
8
Summary
Item Total (Us $)
Metal works
Description
Excavation and Intrlock works
Concrete Works
Plumbing works
Plastering works
Total in letters ..............................................................................
Building works
Total in numbers .........................................................................
Finishing works
Electrical works
VAT(0%)
TOTAL (US $)
Name of the contractor ......
Mobile .
Authorized signature ......
Signature and Sealing.
Title ...
Telephone.
Fax .
13