    S NO DESCRIPTION UNIT NO L B QUANTITY REMARKS

    1

    AREA OF EACH

    FLOOR SFT 1 139.375 69.375 9669.1406

    DEDUCT OPENINGS SFT -1 17.625 10.0416 -176.9832

    LIFT SFT -1 6.25 5.75 -35.9375

    LIFT SFT -2 6.25 7.375 -92.1875

    9364.03

    FOR 6 SLABS SFT 56184.00

    56184

    AREA STATEMENT FOR THE GANGAVRAM PORT ADMIN BUILDING

  • 7/29/2019 B.O.Q for Gangavaram Structural

    2/25

    MATERIAL RATES

    AS PER RMC

    M-25 CUM 4125

    M-35 CUM 4750

    Co-Eff Description Unit Rate Amount Remarks

    1.02 Cost of the concrete- M25 grade Cum 4125.00 4207.50 2% wastage

    1.00 Labour charges for laying Cum 1000.00 1000.00

    1.00 Curing Cum 30.00 30.00

    1.00 Vibration charges Cum 50.00 50.00

    Sub - Total 5287.50

    Add 2% for Tools and Tackles 5287.50 2% 105.75Sub - Total 5393.25

    water & Electricity 5393.25 3.00% 161.80

    5555.05

    Co-Eff Description Unit Rate Amount Remarks

    1.02 Cost of the concrete- M35 grade Cum 4750.00 4845.00 2% wastage

    1.00 Labour charges for laying Cum 1000.00 1000.00

    1.00 Vibration charges Cum 50.00 50.00

    1.00 Curing Cum 30.00 30.00

    Sub - Total 5925.00

    Add 2% for Tools and Tackles 5925.00 2% 118.50

    Sub - Total 6043.50

    water & Electricity 6043.50 3.00% 181.31

    6224.81

    12 to 24 ft level 6274.81

    24 to 36 ft level 6324.81

    36 to 48 ft level 6374.81

    48 to 60 ft level 6424.81

    60 to 72 ft level 6474.81

    5% Extra on labour

    charges for each floor

    ITEM-1.2 C & E Slabs

    lafarge quotation

    lafarge quotation

    ITEM-1- BEAMS TO SUPPORT FLOATING COLUMNS

    ITEM-1.2 A,B, D & F pt beams, drops Beams, RCC beams & columns

  • 7/29/2019 B.O.Q for Gangavaram Structural

    3/25

    Co-Eff Description Unit Rate Amount Remarks

    1.02 Cost of the concrete- M35 grade Cum 4750.00 4845.00 2% wastage

    1.00 Labour charges for laying Cum 800.00 800.00

    1.00 Vibration charges Cum 50.00 50.00

    1.00 Curing Cum 30.00 30.00

    Sub - Total 5725.00

    Add 2% for Tools and Tackles 5725.00 2% 114.50

    Sub - Total 5839.50

    water & Electricity 5839.50 3.00% 175.19

    6014.69

    Co-Eff Description Unit Rate Amount Remarks

    1.02 Cost of the concrete- M25 grade Cum 4125.00 4207.50 2% wastage

    1.00 Labour charges for laying Cum 1200.00 1200.00

    1.00 Vibration charges Cum 50.00 50.00

    1.00 Curing Cum 30.00 30.00

    Sub - Total 5487.50

    Add 2% for Tools and Tackles 5487.50 2% 109.75

    Sub - Total 5597.25

    water & Electricity 5597.25 3.00% 167.925765.17

    12 to 24 ft level 5825.17

    24 to 36 ft level 5885.17

    36 to 48 ft level 5945.17

    48 to 60 ft level 6005.17

    60 to 72 ft level 6065.17

    Co-Eff Description Unit Rate Amount Remarks

    1.05 Cost of steel MT 55000.00 57750.00 Including 5% wastage

    1.00 Transportation - considering 5km MT 500.00 500.00

    10.00 Binding Wire Kg 70.00 700.00

    ITEM-1.2 G Staircase

    5% Extra on labour

    charges for each floor

    ITEM-2 REINFORCEMENT

  • 7/29/2019 B.O.Q for Gangavaram Structural

    4/25

    1.00

    Labour Charges bending, binding

    & fixing MT 4000.00 4000.00

    Sub - Total 62950.00

    Add 2% for Tools and Tackles 62950.00 2% 1259.00

    Sub - Total 64209.00

    water & Electricity 64209.00 3.00% 1926.27

    66135.27

    12 to 24 ft level 66185.27

    24 to 36 ft level 66235.27

    36 to 48 ft level 66285.27

    48 to 60 ft level 66335.27

    60 to 72 ft level 66385.27

    Co-Eff Description Unit Rate Amount Remarks

    1.00 L/C beam shuttering Sqm 150.00 150.00

    1.00 Material Charges Sqm 150.00 150.00

    1.00 Consumables Sqm 20.00 20.00

    1.00 Plant & machinery Sqm 10.00 10.00

    Sub - Total 330.00

    Add 2% for Tools and Tackles 330.00 2% 6.60

    Sub - Total 336.60

    water & Electricity 336.60 3.00% 10.10

    346.70

    Co-Eff Description Unit Rate Amount Remarks

    1.00 L/C for shuttering Sqm 150.00 150.00

    1.00 Material Charges Sqm 130.00 130.00

    1.00 Material for Staging Sqm 50.00 50.00

    1.00 Consumables Sqm 20.00 20.00

    1.00 Plant & machinery Sqm 5.00 5.00

    Sub - Total 355.00

    Add 2% for Tools and Tackles 355.00 2% 7.10

    Sub - Total 362.10

    water & Electricity 362.10 3.00% 10.86

    Extra Rs.50/MT for each

    floor for lifting charges

    ITEM-3 SHUTTERING - BEAMS SUPPORTING FLOATING COLUMNS

    ITEM-3 SHUTTERING FOR OTHERS

  • 7/29/2019 B.O.Q for Gangavaram Structural

    5/25

    372.96

    12 to 24 ft level 422.96

    24 to 36 ft level 472.96

    36 to 48 ft level 522.96

    48 to 60 ft level 572.96

    60 to 72 ft level 622.96

    Co-Eff Description Unit Rate Amount Remarks

    1.00 Post tensioning works Sqm 500.00 500.00

    ( Utracon Quote

    425+taxes)

    1.00 Cement for grouting Sqm 100.00 100.00

    1.00 Material for Staging Sqm 50.00 50.00Sub - Total 650.00

    Add 2% for Tools and Tackles 650.00 2% 13.00

    Sub - Total 663.00

    water & Electricity 663.00 3.00% 19.89

    682.89

    Extra Rs.50 for each floor

    for lifting charges

    POST TENSIONING

  • 7/29/2019 B.O.Q for Gangavaram Structural

    6/25

    SL.NO DESCRIPTION UNIT QTY RATE AMOUNT

    1

    Laying reinforced cement concrete of grade

    M25 / M35 / M40 (Design mix) with 20mm

    graded machine crushed blue coarse ordinary

    Portland cement, for all types of works below

    basement floor slab. All depths as per

    specification and as directed by the

    Engg.in.charge but excluding the cost of

    reinforcement steel. All other works up toplinth lvl

    a) Beams to support floating columns(M25) Cum 55.00 5,555.05 305528

    1.1

    Laying reinforced cement concrete of grade

    M25 / M35 / M40(Design mix) with 20mm

    graded machine crushed blue coarse ordinary

    Portland cement, for all types of works above

    basement floor . All depths as per specification

    and as directed by the Engg.in.charge but

    excluding the cost of reinforcement steel. All

    other works above + 0' to 12'0' lvl. 0

    a)Pt beam(M35) Cum 1.50 6,224.81 9337

    b)Drops (M35) Cum 22.00 6,224.81 136946c)Pt Slab (M35) Cum 169.00 6,014.69 1016483

    d)RCCbeams (M35) Cum 32.00 6,224.81 199194

    e)RCC Slab (M35) Cum 3.80 6,014.69 22856

    f) Columns (M35) Cum 38.50 6,224.81 239655

    g)Staircase (M25) Cum 4.6 5,765.17 26520

    1.2

    Laying reinforced cement concrete of grade

    M25 / M35 / M40(Design mix) with 20mm

    graded machine crushed blue coarse ordinary

    Portland cement, for all types of works above

    plinth. All depths as per specification and as

    directed by the Engg.in.charge but excluding

    the cost of reinforcement steel. All other works

    above 12'0"' to +24'0" lvl 0

    a)Pt beam(M35) Cum 1.50 6,274.81 9412

    b)Drops (M35) Cum 22.00 6,274.81 138046

    c)Pt Slab (M35) Cum 169.00 6,014.69 1016483

    d)RCCbeams (M35) Cum 32.00 6,274.81 200794

    e)RCC Slab (M35) Cum 3.80 6,014.69 22856

    f) Columns (M35) Cum 38.50 6,274.81 241580

    g)Staircase (M25) Cum 4.6 5,825.17 26796

    1.3

    Laying reinforced cement concrete of grade

    M25 / M35 / M40 for P.T. Slabs & R.C.C

    beams (Design mix) with 20mm graded

    machine crushed blue coarse ordinary Portland

    cement, for all types of works above plinth

    (double ht). All depths as per specification and

    as directed by the Engg.in.charge but excluding

    the cost of reinforcement steel. All other works

    from 24' 0" to +36'0" lvl 0

    a)Pt beam(M35) Cum 1.50 6,324.81 9487

    b)Drops (M35) Cum 22.00 6,324.81 139146

    c)Pt Slab (M35) Cum 169.00 6,014.69 1016483

    d)RCCbeams (M35) Cum 32.00 6,324.81 202394

    e)RCC Slab (M35) Cum 3.80 6,014.69 22856

    f) Columns (M35) Cum 38.50 6,324.81 243505

    QUANTITIES FOR DEVELOPEMNT OF PORT FACILITIES AT PORT

  • 7/29/2019 B.O.Q for Gangavaram Structural

    7/25

    SL.NO DESCRIPTION UNIT QTY RATE AMOUNT

    g)Staircase (M25) Cum 4.6 5,885.17 27072

    1.4

    Laying reinforced cement concrete of grade

    M25 / M35 / M40 for P.T. Slabs & R.C.C

    beams (Design mix) with 20mm graded

    machine crushed blue coarse ordinary Portland

    cement, for all types of works above plinth . All

    depths as per specification and as directed by

    the Engg.in.charge but excluding the cost of

    reinforcement steel. All other works from 36'

    0" to +48'0" lvl 0

    a)Pt beam(M35) Cum 1.50 6,374.81 9562

    b)Drops (M35) Cum 22.00 6,374.81 140246

    c)Pt Slab (M35) Cum 169.00 6,014.69 1016483

    d)RCCbeams (M35) Cum 32.00 6,374.81 203994

    e)RCC Slab (M35) Cum 3.80 6,014.69 22856

    f) Columns (M35) Cum 38.50 6,374.81 245430

    g)Staircase (M25) Cum 4.6 5,945.17 27348

    1.5

    Laying reinforced cement concrete of grade

    M25 / M35 / M40 (Design mix) with 20mm

    graded machine crushed blue coarse ordinary

    Portland cement, for all types of works all

    depths as per specification and as directed by

    the Engg.in.charge but excluding the cost of

    reinforcement steel. All other works from

    +48'0" to 60'0" lvl 0

    a)Pt beam(M35) Cum 1.50 6,424.81 9637

    b)Drops (M35) Cum 22.00 6,424.81 141346

    c)Pt Slab (M35) Cum 169.00 6,014.69 1016483

    d)RCCbeams (M35) Cum 32.00 6,424.81 205594

    e)RCC Slab (M35) Cum 3.80 6,014.69 22856

    f) Columns (M35) Cum 38.50 6,424.81 247355

    g)Staircase (M25) Cum 4.6 6,005.17 27624

    1.6

    Laying reinforced cement concrete of grade

    M25 / M35 / M40 (Design mix) with 20mm

    graded machine crushed blue coarse ordinary

    Portland cement, for all types of works all

    depths as per specification and as directed by

    the Engg.in.charge but excluding the cost of

    reinforcement steel. All other works from

    +60'0" to 72'0" lvl0

    a)Pt beam(M35) Cum 1.50 6,474.81 9712

    b)Drops (M35) Cum 22.00 6,474.81 142446

    c)Pt Slab (M35) Cum 169.00 6,014.69 1016483

    d)RCCbeams (M35) Cum 32.00 6,474.81 207194

    e)RCC Slab (M35) Cum 3.80 6,014.69 22856f) Columns (M35) Cum 38.50 6,474.81 249280

    g)Staircase (M25) Cum 4.6 6,065.17 27900

    h)Lmr&Hrm Cum 18.00 6,474.81 116547

    i)O.H.T Cum 45.00 6,474.81 291366

  • 7/29/2019 B.O.Q for Gangavaram Structural

    8/25

    SL.NO DESCRIPTION UNIT QTY RATE AMOUNT

    2

    Fixing in position following reinforcement steel

    of all diameters, for RCC including the same

    from Owner's stores to site of work,

    straightening, cleaning, cutting, bending to

    shapes and length as per details, binding with

    black soft anneled binding wire, providing

    cover blocks to steel supports and spacers bars

    etc., complete for all depths and heights as per

    specifications up to plinthlvl0a) Beams to support floating columns M.T 9.7 66,135.27 641512

    2.1

    Fixing in position following reinforcement steel

    of all diameters, for RCC including the same

    from Owner's stores to site of work,

    straightening, cleaning, cutting, bending to

    shapes and length as per details, binding with

    black soft anneled binding wire, providing

    cover blocks to steel supports and spacers bars

    etc., complete for all depths and heights as per

    specifications.+0'0" to 12'0"0

    a)Ptslabs & Drops,tiebeam M.T 17 66,135.27 1124300

    b)RCCbeams M.T 10.00 66,135.27 661353

    c)RCC Slab M.T 0.30 66,135.27 19841

    d) Columns M.T 9.80 66,135.27 648126

    e)Staircase M.T 0.5 66,135.27 33068

    2.2

    Fixing in position following reinforcement steel

    of all diameters, for RCC including the same

    from Owner's stores to site of work,

    straightening, cleaning, cutting, bending to

    shapes and length as per details, binding with

    black soft anneled binding wire, providing

    cover blocks to steel supports and spacers bars

    etc., complete for all depths and heights as per

    specifications.+12'0" to 24'0" lvl 0

    a)Ptslabs & Drops,tiebeam M.T 17 66,185.27 1125150

    b)RCCbeams M.T 10.00 66,185.27 661853

    c)RCC Slab M.T 0.30 66,185.27 19856

    d) Columns M.T 9.80 66,185.27 648616

    e)Staircase M.T 0.5 66,185.27 33093

    2.3

    Fixing in position following reinforcement steel

    of all diameters, for RCC including the same

    from Owner's stores to site of work,

    straightening, cleaning, cutting, bending to

    shapes and length as per details, binding with

    black soft anneled binding wire, providing

    cover blocks to steel supports and spacers bars

    etc., complete for all depths and heights as per

    specifications.+24'0" to 36'0" lvl 0

    a)Ptslabs & Drops,tiebeam M.T 17 66,235.27 1126000

    b)RCCbeams M.T 10.00 66,235.27 662353

    c)RCC Slab M.T 0.30 66,235.27 19871

    d)Columns M.T 9.80 66,235.27 649106

    e)Staircase M.T 0.5 66,235.27 33118

  • 7/29/2019 B.O.Q for Gangavaram Structural

    9/25

    SL.NO DESCRIPTION UNIT QTY RATE AMOUNT

    2.4

    Fixing in position following reinforcement steel

    of all diameters, for RCC including the same

    from Owner's stores to site of work,

    straightening, cleaning, cutting, bending to

    shapes and length as per details, binding with

    black soft anneled binding wire, providing

    cover blocks to steel supports and spacers bars

    etc., complete for all depths and heights as per

    specifications.+36'0" to 48'0" lvl0

  • 7/29/2019 B.O.Q for Gangavaram Structural

    10/25

    SL.NO DESCRIPTION UNIT QTY RATE AMOUNT

    a)Ptslabs & Drops,tiebeam M.T 17 66,285.27 1126850

    b)RCCbeams M.T 10.00 66,285.27 662853

    c)RCC Slab M.T 0.30 66,285.27 19886

    d)Columns M.T 9.80 66,285.27 649596

    e)Staircase M.T 0.5 66,285.27 33143

    2.5

    Fixing in position following reinforcement steel

    of all diameters, for RCC including the same

    from Owner's stores to site of work,

    straightening, cleaning, cutting, bending to

    shapes and length as per details, binding with

    black soft anneled binding wire, providing

    cover blocks to steel supports and spacers bars

    etc., complete for all depths and heights as per

    specifications.+48'0" to 60'0"lvl 0

    a)Ptslabs & Drops,tiebeam M.T 17 66,335.27 1127700

    b)RCCbeams M.T 10.00 66,335.27 663353

    c)RCC Slab M.T 0.30 66,335.27 19901

    d)Columns M.T 9.80 66,335.27 650086

    e)Staircase M.T 0.5 66,335.27 33168

    2.6

    Fixing in position following reinforcement steel

    of all diameters, for RCC including the same

    from Owner's stores to site of work,

    straightening, cleaning, cutting, bending to

    shapes and length as per details, binding with

    black soft anneled binding wire, providing

    cover blocks to steel supports and spacers bars

    etc., complete for all depths and heights as per

    specifications.+60'0" to 72'0"lvl 0

    a)Ptslabs & Drops,tiebeam M.T 17 66,385.27 1128550

    b)RCCbeams M.T 10.00 66,385.27 663853

    c)RCC Slab M.T 0.30 66,385.27 19916

    d)Columns M.T 9.80 66,385.27 650576

    e)Staircase M.T 0.5 66,385.27 33193

    h)Lmr&Hrm M.T 2 66,385.27 132771

    i)O.H.T M.T 4 66,385.27 232348

    3.0

    Installing, dismantling and removing after

    specific period the following form work (of

    approved quality to give a fair and smooth

    exposed concrete finish including scaffolding,

    centering, bracing, providing openings, cutouts,

    pockets etc., complete in all types of cast-in-

    situ concrete works) as per specifications,

    drawings and as directed by the Engineer-in-

    charge. up to plinth lvl. 0

    a) Beams to support floating columns Sqm 135.00 346.70 46805

    3.1

    Installing, dismantling and removing after

    specific period the following form work (of

    approved quality to give a fair and smooth

    exposed concrete finish including scaffolding,

    centering, bracing, providing openings, cutouts,

    pockets etc., complete in all types of cast-in-

    situ concrete works) as per specifications,

    drawings and as directed by the Engineer-in-

    charge. +0' to 12"0" 0

  • 7/29/2019 B.O.Q for Gangavaram Structural

    11/25

    SL.NO DESCRIPTION UNIT QTY RATE AMOUNT

    a)Pt beam Sqm 2.50 372.96 932

    b)Drops Sqm 37.00 372.96 13800

    c)Pt Slab Sqm 825.00 372.96 307692

    d)RCCbeams Sqm 203 372.96 75711

    e)RCC Slab Sqm 21.50 372.96 8019

    f) Columns Sqm 332.00 372.96 123823

    g)Staircase Sqm 29 372.96 10816

    3.2

    Installing, dismantling and removing after

    specific period the following form work (of

    approved quality to give a fair and smooth

    exposed concrete finish including scaffolding,

    centering, bracing, providing openings, cutouts,

    pockets etc., complete in all types of cast-in-

    situ concrete works) as per specifications,

    drawings and as directed by the Engineer-in-

    charge. +12'0" to +24'0" lvl 0

    a)Pt beam Sqm 2.50 422.96 1057

    b)Drops Sqm 37.00 422.96 15650

    c)Pt Slab Sqm 825.00 422.96 348942

    d)RCCbeams Sqm 203 422.96 85861

    e)RCC Slab Sqm 21.5 422.96 9094

    f) Columns Sqm 332.00 422.96 140423

    g)Staircase Sqm 29 422.96 12266

    3.3

    Installing, dismantling and removing after

    specific period the following form work (of

    approved quality to give a fair and smooth

    exposed concrete finish including scaffolding,

    centering, bracing, providing openings, cutouts,

    pockets etc., complete in all types of cast-in-

    situ concrete works) as per specifications,

    drawings and as directed by the Engineer-in-

    charge. +24'0" to 36'0" lvl 0

    a)Pt beam Sqm 2.50 472.96 1182

    b)Drops Sqm 37.00 472.96 17500

    c)Pt Slab Sqm 825.00 472.96 390192

    d)RCCbeams Sqm 203 472.96 96011

    e)RCC Slab Sqm 21.5 472.96 10169

    f) Columns Sqm 332.00 472.96 157023

    g)Staircase Sqm 29 472.96 13716

    3.4

    Installing, dismantling and removing after

    specific period the following form work (of

    approved quality to give a fair and smooth

    exposed concrete finish including scaffolding,

    centering, bracing, providing openings, cutouts,

    pockets etc., complete in all types of cast-in-

    situ concrete works) as per specifications,

    drawings and as directed by the Engineer-in-

    charge. +36'0" to 48'0" lvl

  • 7/29/2019 B.O.Q for Gangavaram Structural

    12/25

    SL.NO DESCRIPTION UNIT QTY RATE AMOUNT

    a)Pt beam Sqm 2.50 522.96 1307

    b)Drops Sqm 37.00 522.96 19350

    c)Pt Slab Sqm 825.00 522.96 431442

    d)RCCbeams Sqm 203 522.96 106161

    e)RCC Slab Sqm 21.5 522.96 11244

    f) Columns Sqm 332.00 522.96 173623

    g)Staircase Sqm 29 522.96 15166

    3.5

    Installing, dismantling and removing after

    specific period the following form work (of

    approved quality to give a fair and smooth

    exposed concrete finish including scaffolding,

    centering, bracing, providing openings, cutouts,

    pockets etc., complete in all types of cast-in-

    situ concrete works) as per specifications,

    drawings and as directed by the Engineer-in-

    charge. +48'0" to 60'0" lvl 0

    a)Pt beam Sqm 2.50 572.96 1432

    b)Drops Sqm 37.00 572.96 21200

    c)Pt Slab Sqm 825.00 572.96 472692

    d)RCCbeams Sqm 203 572.96 116311

    e)RCC Slab Sqm 21.5 572.96 12319

    f) Columns Sqm 332.00 572.96 190223

    g)Staircase Sqm 29 572.96 16616

    3.6

    Installing, dismantling and removing after

    specific period the following form work (of

    approved quality to give a fair and smooth

    exposed concrete finish including scaffolding,

    centering, bracing, providing openings, cutouts,

    pockets etc., complete in all types of cast-in-

    situ concrete works) as per specifications,

    drawings and as directed by the Engineer-in-

    charge. +60'0" to 72'0" lvl 0

    a)Pt beam Sqm 2.50 622.96 1557

    b)Drops Sqm 37.00 622.96 23050

    c)Pt Slab Sqm 825.00 622.96 513942

    d)RCCbeams Sqm 203 622.96 126461

    e)RCC Slab Sqm 21.5 622.96 13394

    f) Columns Sqm 332.00 622.96 206823

    g)Staircase Sqm 29 622.96 18066

    h)Lmr&Hrm Sqm 140.00 622.96 87214

    i)O.H.T Sqm 325.00 622.96 202462

    4 Post tensioning works: Supply and installation

    of post-tensioning materials, including strand,

    anchorages and sheathing.Stressing of tendons,

    including the supply of stressing

    equipment.Grouting of tendons, including the

    supply of grouting equipment. Preparation of

    post-tensioning shop drawings 0

    First floor(+12'0"lvl) sqm 825.00 682.89 563384

    Second floor(+24'0"lvl) sqm 825.00 682.89 563384

    Third floor(+36'0"lvl) sqm 825.00 682.89 563384

    Fourth floor(+48'0"lvl) sqm 825.00 682.89 563384

    Fifth floor(+60'0"lvl) sqm 825.00 682.89 563384

    Sixth floor(+72'0"lvl) sqm 825.00 682.89 563384

    -

  • 7/29/2019 B.O.Q for Gangavaram Structural

    13/25

    SL.NO DESCRIPTION UNIT QTY RATE AMOUNT

    5 Existing concrete breaking for

    suspendedslab,columns and lifpits. Remove the

    debries from construction site deposted in

    location directed by the Engineer Incharge. L.S L.S L.S

    -

    6 Construction of newpiles and pile caps are as

    per drawings. L.S L.S L.S

    -

    Note:

    TOTAL AMOUNT Rs 34,698,009

    1)PT quote is taken from PT vendor quote attcahed

    2)Sump is not consider

    3)Quantities of structural works are calculated with 10% wastage.

  • 7/29/2019 B.O.Q for Gangavaram Structural

    14/25

    Offer for Construction of Buidling for Gangavaram Port Ltd

    Bill of Quantities

    Item No. Description Unit Qty. Rate(Rs.) Amount(Rs.)

    1

    Construction of RCC superstructure(frame work only) for a ground

    plus five floor building inclusive of all materials,excluding the design

    and cost of foundation ,brickwork,flooring, engineering -services and

    interior works etc. Sft 56184 618 34698009

    NOTE:

    1 VAT & Service Tax extra, if applicable.

    2 Rate is only for skeleton RCC Structure.

    3 No Brick walls, no plastering and no flooring.

    4 Total building floor area will be of 56184 Sft

    5 Floor to floor Height considered as 12fts only

    6

    The above price based on the Quantities given by you , any revision in

    the quantities/drawings extra price will be charged for additional

    scope of work

    7 Rate excluding glazing works8 Space for labour,material storage shall be provided by client

  • 7/29/2019 B.O.Q for Gangavaram Structural

    15/25

  • 7/29/2019 B.O.Q for Gangavaram Structural

    16/25

  • 7/29/2019 B.O.Q for Gangavaram Structural

    17/25

  • 7/29/2019 B.O.Q for Gangavaram Structural

    18/25

  • 7/29/2019 B.O.Q for Gangavaram Structural

    19/25

  • 7/29/2019 B.O.Q for Gangavaram Structural

    20/25

  • 7/29/2019 B.O.Q for Gangavaram Structural

    21/25

    56184 SFT

    COST PER SFT OF ALL THE ITEMS

    N DESCRIPTION UNIT

    TOTAL

    QUANTITY

    SANTHOS

    H SYAM

    TOTAL BUILT UP AREA

    TOTAL AMOUNT

  • 7/29/2019 B.O.Q for Gangavaram Structural

    22/25

    1 CONCRETE CUM 1746.40 10694021 12204306

    2 STEEL MT 240.80 15954947 18719792

    3 SHUTTERING SQM 9300 4668733 5208000

    TOTAL

    4 POST TENSINOING SQM 4950 3380304