Book 1
-
Upload
murali-krishna -
Category
Documents
-
view
103 -
download
4
Transcript of Book 1
IRR-CCDW
222
CHAPTER-IV
CANAL CROSS DRAINAGE WORKS
(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)
FOR THE YEAR :2011-12Index- code
IRR-CCDW CANAL CROSS DRAINAGE WORKS - DATA RATES
IRR-CCDW-1 EXCAVATION & FOUNDATION TREATMENT WORKS :
IRR-CCDW-1-1
50 m and initial lift upto 3 m.
DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 NIL 0.00 0.00 0.000.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 NIL 0.00 0.00 0.00
0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 work inspector Day 0.25 275.00 68.752 mazdoor Day 6.00 215.00 1290.00
Total cost of Labour Rs: 1358.75labour component/unit qty 135.90Add contractor's profit and overhead charges 0.14 19.00labour component/unit qty (including contractor's profit) 154.90
ABSTRACT:A. Cost of Materials Rs: 0.00B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1358.75
Total Rs: 1358.75D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 190.23Total cost for 10.00 cum Rs: 1548.98Rate per cum (A+B+C+D)/10.0 Rs. 154.90
IRR-CCDW-1-2 Excavation for Structures- Mechanical Means ( Data adopted from MORTH)
including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.Depth upto 3 m
Unit = cumDATA: Taking output = 240 cum 240.00 cum
a) LabourSl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 work inspector day 0.32 275.00 88.00 2 Mazdoor day 8.00 215.00 1720.00
Total in Rs. 1808.00
b)Machinery
Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundations of canalcross drainage and other appurtenant structures and placing the excavated stuff neatly inspecified dump area or disposing off the same as directed etc., complete with initial lead upto
Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification,
IRR-CCDW
223
Sl No Description Unit Quantity Rate Amountin Rs. in Rs.
1 Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1180.70 7084.20 Fuel/ Energy charges hour 6.00 680.60 4083.60 crew for excavator hour 6.00 148.20 889.20 Total in Rs. 12057.00
labour component/unit qty 50.20Add contractor's profit and overhead charges 0.14 7.00labour component/unit qty (including contractor's profit) 57.20
Abstracta) Labour Rs 1808.00 b) Machinery Rs 12057.00 c) Material Rs 0.00 Total Rs 13865.00
D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1941.1Total cost for 240.00 cum Rs: 15806.1Rate per cum (A+B+C+D)/240.0 Rs. 65.90
IRR-CCDW-1-3
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 NIL 0.00 0.00 0.000.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 NIL 0.00 0.00 0.00
0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crowbarman Day 1.25 260.00 325.002 Stone breaker Day 1.25 260.00 325.003 work inspector Day 0.25 275.00 68.754 mazdoor Day 6.00 215.00 1290.00
Total cost of Labour Rs: 2008.75labour component/unit qty 200.90Add contractor's profit and overhead charges 0.14 28.10labour component/unit qty (including contractor's profit) 229.00
ABSTRACT:A. Cost of Materials Rs: 0.00B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 2008.75
Total Rs: 2008.75D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 281.23Total cost for 10.00 cum Rs: 2289.98Rate per cum (A+B+C+D)/10.0 Rs. 229.00
IRR-CCDW-1-4and other appurtenant structures and placing the excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial
( Data adopted from MORTH) Mechanical MeansUnit = cum
DATA: Taking output = 180 cum 180.00 cuma) Labour
Excavation in ordnary rock (including HDR) without blasting including boulders above 0.3 m upto 0.60 m dia.for foundations of canal cross drainage and other appurtenant structures and placing the
complete with initial lead upto 50 m and initial lift upto 3 m.
Excavation in ordnary rock without blasting for foundations of canal cross drainage
lead upto 50 m and initial lift upto 3 m.
IRR-CCDW
224
Sl No Description Unit Quantity Rate Amountin Rs. in Rs.
1 work inspector day 0.24 275.00 66.00 2 Mazdoor day 6.00 215.00 1290.00
Total in Rs. 1356.00
b) MachinerySl No Description Unit Quantity Rate Amount
in Rs. in Rs.1.0 Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1180.70 7084.20
Fuel/ Energy charges hour 6.00 680.60 4083.60 crew for excavator hour 6.00 148.20 889.20 Total in Rs. 12057.00
labour component/unit qty 67.00Add contractor's profit and overhead charges 0.14 9.40labour component/unit qty (including contractor's profit) 76.40
Abstract a) Labour Rs 1356.00 b) Machinery Rs 12057.00 c) Material Rs 0.00
Total Rs 13413.00
D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1877.82Total cost for 180.00 cum Rs: 15290.82Rate per cum (A+B+C+D)/180.0 Rs. 84.90
IRR-CCDW-1-5
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
DATA:RATE ANALYSIS UNIT : 100 cum
A. MATERIALS:Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.1 Use rate of drill rod 1.6 m length Rm 43.50 16.50 717.75
Reconditioning charges @ 10% 71.782 Use rate of air hose 2 Nos. Hour 6.00 0.16 0.983 Explosive small dia ( Kelvex-220 ) kg 20.00 54 1080.004 Electric detonators Nos 29.00 11 319.005 Detonating fuse coil Rm 70.00 8 560.006 Sundries LS 0.50 33 16.50
Total cost of Materials Rs: 2766.00
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Air compressor 8.5 cmm ( diesel ) Hour 3.00 210.40 631.20
Fuel / Energy charges Hour 3.00 696.10 2088.302 Jack hammers 2 Nos. Hour 6.00 13.50 81.00
Fuel / Energy charges Hour 6.00 0.00 0.00Total hire charges of Machinery Rs: 2800.50
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Air compressor Hour 3.00 136.00 408.002 Crew for Jack hammer Hour 6.00 212.60 1275.603 work inspector Day 1.00 275.00 275.004 Blaster Day 0.50 310.00 155.005 Helper blaster Day 0.50 260.00 130.006 Crowbarman Day 6.00 260.00 1560.007 Stone breaker Day 3.00 260.00 780.008 mazdoor Day 51.00 215.00 10965.00
Total cost of Labour Rs: 15548.60labour component/unit qty 155.50Add contractor's profit and overhead charges 0.14 21.80labour component/unit qty (including contractor's profit) 177.30
Excavation in hard rock requiring blasting including boulders above 0.6 m upto 1.2 m dia. forfoundations of canal cross drainage and other appurtenant structures and placing the
complete with initial lead upto 50 m and initial lift upto 3 m.
IRR-CCDW
225
ABSTRACT:A. Cost of Materials Rs: 2766.00B. Hire charges of Machinery Rs: 2800.50C. Cost of Labour Rs: 15548.60
Total Rs: 21115.10D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2956.11Total cost for 100.00 cum Rs: 24071.21Rate per cum (A+B+C+D)/100.0 Rs. 240.70
IRR-CCDW-1-6
excavated rock neatly in specified dump area or stack yard as directed etc., complete with
DATA:
RATE ANALYSIS UNIT : 100.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Explosive small dia ( Kelvex-220 ) kg 32.00 54 1728.002 Ordinary detonator No. 8.00 6 48.003 Electric detonator No. 104.00 11 1144.004 Detonating fuse coil Rm 150.00 8 1200.005 Use rate of air hose 2 Nos. Hour 16.00 8.13 130.006 Use rate of drill rod Rm 98.30 22.00 2162.60
Reconditioning charges @ 10% 216.26Total cost of Materials Rs: 6628.86
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Air compressor 8.5 cmm ( diesel ) Hour 8.00 210.40 1683.20
Fuel / Energy charges Hour 8.00 696.10 5568.802 Jack hammer 2 Nos Hour 16.00 13.50 216.00
Fuel / Energy charges Hour 16.00 0.00 0.00Total hire charges of Machinery Rs: 7468.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Air compressor Hour 8.00 136.00 1088.002 Crew for Jack hammer Hour 16.00 212.60 3401.603 Blaster licensed Day 1.00 310.00 310.004 Helper blasting Day 1.00 260.00 260.005 work inspector Day 1.00 275.00 275.006 Crowbarman Day 6.00 260.00 1560.007 Stone breaker Day 6.00 260.00 1560.008 mazdoor Day 51.00 215.00 10965.00
Total cost of Labour Rs: 19419.60labour component/unit qty 194.20Add contractor's profit and overhead charges 0.14 27.20labour component/unit qty (including contractor's profit) 221.40
ABSTRACT:A. Cost of Materials Rs: 6628.86B. Hire charges of Machinery Rs: 7468.00C. Cost of Labour Rs: 19419.60
Total Rs: 33516.46D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 4692.3Total cost for 100.00 cum Rs: 38208.76Rate per cum (A+B+C+D)/100.0 Rs. 382.10
IRR-CCDW-1-7and other appurtenant structures and placing the excavated rock neatly in
initial lift upto 3 m.Hard Rock ( blasting prohibited ) ( Data adopted from MORTH) Unit = cum
DATA: Taking output = 10 cumMechanical Means 10.00 cum
Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. forfoundations of canal cross drainage and other appurtenant structures and placing the
initial lead upto 50 m and initial lift upto 3 m.
Excavation in hard rock with blasting prohibited for foundations of canal cross drainage
or stack yard as directed etc., complete with specified dump area initial lead upto 50 m and
IRR-CCDW
226
a) LabourSl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 work inspector day 0.20 275.00 55.00 2 Mazdoor day 5.00 215.00 1075.00
Total in Rs. 1130.00
b) MachinerySl No Description Unit Quantity Rate Amount
in Rs. in Rs.1.0 hour 6.00 178.50 1071.00
Fuel/ Energy charges hour 6.00 556.90 3341.40 crew for compressor hour 6.00 136.00 816.00 Total in Rs. 5228.40
labour component/unit qty 522.80Add contractor's profit and overhead charges 0.14 73.20labour component/unit qty (including contractor's profit) 596.00
Abstracta) Labour Rs 1130.00 b) Machinery Rs 5228.40 c) Material Rs 0.00
Total Rs 6358.40
D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 890.18Total cost for 10.00 cum Rs: 7248.58Rate per cum (A+B+C+D)/10.0 Rs. 724.90
IRR-CCDW-1-81.25 m length driven into 32 mm dia hole drilled in bed rock and remaining length embedded inconcrete / masonry including cost of all materials, machinery, labour, drilling and cleaning
upto 50 m and all lifts.DATA:
RATE ANALYSIS UNIT : 10.00 Nos.A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for grouting kg 5.00 5.50 27.502 25 mm dia steel kg 101.00 41.00 4141.003 Use rate of 32 mm dia drill rod Rm 12.50 22.00 275.00
Reconditioning charges @ 10% 27.504 Use rate of air hose Hour 2.00 8.13 16.25
Total cost of Materials Rs: 4487.25
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Air compressor 8.5 cmm ( diesel ) Hour 1.00 210.40 210.40
Fuel / Energy charges Hour 1.00 696.10 696.102 Jack hammer 2 Nos Hour 2.00 13.50 27.00
Fuel / Energy charges Hour 2.00 0.00 0.00Total hire charges of Machinery Rs: 933.50
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Air compressor Hour 1.00 136.00 136.002 Crew for Jack hammer Hour 2.00 212.60 425.203 Mason Class-II Day 0.50 260.00 130.004 Bar bender Day 0.50 300.00 150.005 work inspector Day 0.50 275.00 137.506 mazdoor Day 1.00 215.00 215.00
Total cost of Labour Rs: 1193.70labour component/unit qty 119.40Add contractor's profit and overhead charges 0.14 16.70labour component/unit qty (including contractor's profit) 136.10
Air Compressor 250 cft with 2 leads of pneumatic breaker
Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel anchor rods with
hole, driving anchor rod, grouting hole with thick cement slurry etc., complete with initial lead
IRR-CCDW
227
ABSTRACT:A. Cost of Materials Rs: 4487.25B. Hire charges of Machinery Rs: 933.50C. Cost of Labour Rs: 1193.70
Total Rs: 6614.45
IRR-CCDW
228
D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 926.02Total cost for 10.00 Nos. Rs: 7540.47Rate per each (A+B+C+D)/10.0 Rs. 754.00
IRR-CCDW-2 STEEL AND CEMENT CONCRETE WORKS :
IRR-CCDW-2-1cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,
DATA:
RATE ANALYSIS UNIT : 1000.00 kgA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Rein.Steel with 5 % wastage kg 1050.00 41.00 43050.002 Binding wire 1.25 mm dia kg 8.00 55 440.003 Sundries ( chairs / spacers etc ) LS 3.00 33 99.00
Total cost of Materials Rs: 43589.00
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nil 0.00 0.00 0.00
0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 work inspector Day 1.00 275.00 275.002 Bar bender Day 6.00 300.00 1800.003 mazdoor Day 11.00 215.00 2365.00
Total cost of Labour Rs: 4440.00labour component/unit qty 4.40Add contractor's profit and overhead charges 0.14 0.60labour component/unit qty (including contractor's profit) 5.00
ABSTRACT:A. Cost of Materials Rs: 43589.00B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 4440.00
Total Rs: 48029.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 6724.06Total cost for 1000.00 kg Rs: 54753.06Rate per kg (A+B+C+D)/1000.0 Rs. 54.80
IRR-CCDW-2-2100 x 10 mm angle and 250 x 12 mm plate for sinking for sinking 4.50 m outer diameter foundation wells foundation wells including cost of all materials, machinery, labour, bending, welding, providing anchors etc., complete with initial lead upto 50 m and all lifts.
DETAILS OF FOUNDATION WELL CUTTING EDGE
DATA: RATE ANALYSIS UNIT : 615.00 kgA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Str.Steel angle with 2.5 % wastage kg 216.10 40.00 8644.00
Providing, fabricating and placing in position reinforcement steel bars for RCC works including
complete with initial lead upto 50 and all lifts.
Providing, fabricating and fixing in position structural steel cutting edge consisting of 100 x
IRR-CCDW
229
2 Str.Steel plate with 2.5 % wastage kg 342.30 43.00 14718.903 Steel for anchors kg 56.60 41.00 2320.604 Acetyline gas cum 0.50 275 137.505 Oxygen gas cum 1.50 40 60.006 Welding electrodes Nos 300.00 9.00 2700.007 Sundries LS 5.00 33 165.00
Total cost of Materials Rs: 28746.00
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Bending machine Hour 8.00 14.50 116.00
Fuel / Energy charges Hour 8.00 60.40 483.202 Welding set Hour 30.00 12.90 387.00
Fuel / Energy charges Hour 30.00 48.30 1449.003 Sundries LS 10.00 33 330.00
Total hire charges of Machinery Rs: 2765.20
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Str. Steel fabricator Day 2.00 310.00 620.002 Welder / Gas cutter Day 5.00 285.00 1425.003 work inspector Day 1.00 275.00 275.004 mazdoor Day 5.00 215.00 1075.00
Total cost of Labour Rs: 3395.00labour component/unit qty 5.50Add contractor's profit and overhead charges 0.14 0.80labour component/unit qty (including contractor's profit) 6.30
ABSTRACT:A. Cost of Materials Rs: 28746.00B. Hire charges of Machinery Rs: 2765.20C. Cost of Labour Rs: 3395.00
Total Rs: 34906.20D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 4886.87Total cost for 615.00 kg Rs: 39793.07Rate per kg (A+B+C+D)/615.0 Rs. 64.70
IRR-CCDW-2-3
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Data RATE ANALYSIS UNIT : 15.38 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 3998.80 5.50 21993.40Cement for incidentals @ 3 kg / cum kg 46.14 5.50 253.77
2 Coarse aggregate 40-20 mm cum 6.92 975.00 6747.98Coarse aggregate 20-10 mm cum 4.15 1025.00 4256.42Coarse aggregate 10 mm below cum 2.77 750.00 2076.30
3 Fine aggregate cum 6.15 425 2614.604 Super Plasticizer kg 16.00 54 863.745 Use rate of shuttering for 40 uses sqm 15.38 197.64 3039.75
Scaffolding @ of shuttering 10% 303.976 Sundries LS 0.50 33 16.50
Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00
Total cost of Materials Rs: 42166.42
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,
complete with initial lead upto 50 m and all lifts.
IRR-CCDW
230
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Needle vibrator Hour 8.00 102.00 816.005 work inspector Day 1.00 275.00 275.006 Mason Class-I Day 1.00 285.00 285.007 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 15.38 215.00 3306.70for cleaning/ washing/ curing Day 1.00 215.00 215.00
8 Labour cost for shuttering sqm 15.38 55.65 855.90Labour cost for scaffolding @ 10% 85.59
Total cost of Labour Rs: 10984.64labour component/unit qty 714.20Add contractor's profit and overhead charges 0.14 100.00labour component/unit qty (including contractor's profit) 814.20
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 42166.42B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 10984.64
Total Rs: 54706.71D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 7658.94Total cost for 15.38 cum Rs: 62365.65Rate per cum (A+B+C+D)/15.38 Rs. 4055.00
IRR-CCDW-2-4
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
DATA:
RATE ANALYSIS UNIT : 14.40 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 3600.00 5.50 19800.00Cement for incidentals @ 3 kg / cum kg 43.20 5.50 237.60
2 Coarse aggregate 80-40 mm cum 4.94 560.00 2765.95Coarse aggregate 40-20 mm cum 4.23 975.00 4127.76Coarse aggregate 20-10 mm cum 2.82 1025.00 2892.96Coarse aggregate 10 mm below cum 2.12 750.00 1587.60
3 Fine aggregate cum 5.04 425 2142.004 Super Plasticizer kg 14.40 54 777.605 Use rate of shuttering for 40 uses sqm 14.40 197.64 2846.06
Scaffolding @ of shuttering 10% 284.616 Sundries LS 0.50 33 16.50
Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00
Total cost of Materials Rs: 37478.63
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,
complete with initial lead upto 50 m and all lifts.
IRR-CCDW
231
in Rs. in Rs.1 Concrete mixer 600/400 ltr ( diesel) Hour 8.00 77.00 616.00
Fuel / Energy charges Hour 8.00 123.80 990.402 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 60 mm dia ( petrol) Hour 8.00 6.20 49.60
Fuel / Energy charges Hour 8.00 18.60 148.80Total hire charges of Machinery Rs: 2359.65
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Needle vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 14.40 215.00 3096.00for cleaning/ washing/ curing Day 1.00 215.00 215.00
8 Labour cost for shuttering sqm 14.40 55.65 801.36Labour cost for scaffolding @ 10% 80.14
Total cost of Labour Rs: 10713.95labour component/unit qty 744.00Add contractor's profit and overhead charges 0.14 104.20labour component/unit qty (including contractor's profit) 848.20
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 37478.63B. Hire charges of Machinery Rs: 2359.65C. Cost of Labour Rs: 10713.95
Total Rs: 50552.23D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 7077.31Total cost for 14.40 cum Rs: 57629.5406331Rate per cum (A+B+C+D)/14.40 Rs. 4002.10
IRR-CCDW-2-5
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSIS UNIT : 16.36 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 3599.20 5.50 19795.60Cement for incidentals @ 3 kg / cum kg 49.08 5.50 269.94
2 Coarse aggregate 40-20 mm cum 7.36 975.00 7177.95Coarse aggregate 20-10 mm cum 4.42 1025.00 4527.63Coarse aggregate 10 mm below cum 2.94 750.00 2208.60
3 Fine aggregate cum 6.54 425 2781.204 Super Plasticizer kg 14.40 54 777.435 Use rate of shuttering for 40 uses sqm 16.36 197.64 3233.44
Scaffolding @ of shuttering 10% 323.346 Sundries LS 0.50 33 16.50
Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00
Total cost of Materials Rs: 41111.63
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,
complete with initial lead upto 50 m and all lifts.
IRR-CCDW
232
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 16.36 215.00 3517.40
8 for cleaning/ washing/ curing Day 1.00 215.00 215.009 Labour cost for shuttering sqm 16.36 55.65 910.43
Total cost of Labour Rs: 11164.28labour component/unit qty 682.40Add contractor's profit and overhead charges 0.14 95.50labour component/unit qty (including contractor's profit) 777.90
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 41111.63B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 11164.28
Total Rs: 53831.56D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 7536.42Total cost for 16.36 cum Rs: 61367.9818026Rate per cum (A+B+C+D)/16.36 Rs. 3751.10
IRR-CCDW-2-6
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
DATA: RATE ANALYSIS UNIT : 14.55 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 3201.00 5.50 17605.50Cement for incidentals @ 3 kg / cum kg 43.65 5.50 240.08
2 Coarse aggregate 80-40 mm cum 4.99 560.00 2794.76Coarse aggregate 40-20 mm cum 4.28 975.00 4170.76Coarse aggregate 20-10 mm cum 2.85 1025.00 2923.10Coarse aggregate 10 mm below cum 2.14 750.00 1604.14
3 Fine aggregate cum 5.09 425 2164.314 Super Plasticizer kg 12.80 54 691.425 Use rate of shuttering for 40 uses sqm 14.55 197.64 2875.70
Scaffolding @ of shuttering 10% 287.576 Sundries LS 0.50 33 16.50
Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00
Total cost of Materials Rs: 35373.83
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,
complete with initial lead upto 50 m and all lifts.
IRR-CCDW
233
in Rs. in Rs.1 Concrete mixer 600/400 ltr ( diesel ) Hour 8.00 77.00 616.00
Fuel / Energy charges Hour 8.00 123.80 990.402 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 6.20 49.60
Fuel / Energy charges Hour 8.00 18.60 148.80Total hire charges of Machinery Rs: 2359.65
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 14.55 215.00 3128.25for cleaning/ washing/ curing Day 1.00 215.00 215.00
8 Labour cost for shuttering sqm 14.55 55.65 809.71Labour cost for scaffolding @ 10% 80.97
Total cost of Labour Rs: 10755.38labour component/unit qty 739.20Add contractor's profit and overhead charges 0.14 103.50labour component/unit qty (including contractor's profit) 842.70
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 35373.83B. Hire charges of Machinery Rs: 2359.65C. Cost of Labour Rs: 10755.38
Total Rs: 48488.86D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 6788.44Total cost for 14.55 cum Rs: 55277.2994522Rate per cum (A+B+C+D)/14.55 Rs. 3799.10
IRR-CCDW-2-7
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 310 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSIS UNIT : 14.19 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 4398.90 5.50 24193.95Cement for incidentals @ 3 kg / cum kg 42.57 5.50 234.14
2 Coarse aggregate 40-20 mm cum 6.39 975.00 6225.86Coarse aggregate 20-10 mm cum 3.83 1025.00 3927.08Coarse aggregate 10 mm below cum 2.55 750.00 1915.65
3 Fine aggregate cum 5.68 425 2412.304 Super Plasticizer kg 17.60 54 950.165 Use rate of shuttering for 40 uses sqm 14.19 197.64 2804.55
Scaffolding @ of shuttering 10% 280.466 Sundries LS 0.50 33 16.50
Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00
Total cost of Materials Rs: 42960.65
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,
complete with initial lead upto 50 m and all lifts. ( Cement content : 220 kg / cum )
IRR-CCDW
234
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 14.19 215.00 3050.85for cleaning/ washing/ curing Day 1.00 215.00 215.00
8 Labour cost for shuttering sqm 14.19 55.65 789.67Labour cost for scaffolding @ 10% 78.97
Total cost of Labour Rs: 10655.94labour component/unit qty 750.90Add contractor's profit and overhead charges 0.14 105.10labour component/unit qty (including contractor's profit) 856.00
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 42960.65B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 10655.94
Total Rs: 55172.24D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 7724.11Total cost for 14.19 cum Rs: 62896.35Rate per cum (A+B+C+D)/14.19 Rs. 4432.40
IRR-CCDW-2-8
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSIS UNIT : 15.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 4800.00 5.50 26400.00Cement for incidentals @ 5 kg / cum kg 75.00 5.50 412.50
2 Coarse aggregate 40-20 mm cum 6.75 975.00 6581.25Coarse aggregate 20-10 mm cum 4.05 1025.00 4151.25Coarse aggregate 10 mm below cum 2.70 750.00 2025.00
3 Fine aggregate cum 6.00 425 2550.004 Super Plasticizer kg 19.20 54 1036.805 Use rate of shuttering sqm 30.00 197.64 5929.29
Scaffolding @ of shuttering 25% 1482.326 Sundries LS 0.50 33 16.50
Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00
Total cost of Materials Rs: 50584.91
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
IRR-CCDW
235
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65
IRR-CCDW
236
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying including lifting Day 4.00 215.00 860.00for conveying concrete Day 15.00 215.00 3225.00for cleaning/ washing/ curing Day 1.00 215.00 215.00
8 Labour cost for shuttering sqm 15.00 55.65 834.75Labour cost for scaffolding @ 25% 208.69
Total cost of Labour Rs: 11219.89labour component/unit qty 748.00Add contractor's profit and overhead charges 0.14 104.70labour component/unit qty (including contractor's profit) 852.70
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 50584.91B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 11219.89
Total Rs: 63360.44D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8870.46Total cost for 15.00 cum Rs: 72230.90Rate per cum (A+B+C+D)/15.0 Rs. 4815.40
IRR-CCDW-2-9
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSIS UNIT : 15.76 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 5200.80 5.50 28604.40Cement for incidentals @ 5 kg / cum kg 78.80 5.50 433.40
2 Coarse aggregate 20-10 mm cum 8.20 1025.00 8400.08Coarse aggregate 10 mm below cum 4.41 750.00 3309.60
3 Fine aggregate cum 7.09 425 3014.104 Super Plasticizer kg 20.80 54 1123.375 Use rate of shuttering sqm 31.52 197.64 6229.70
Scaffolding @ of shuttering 25% 1557.436 Sundries LS 0.50 33 16.50
Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00
Total cost of Materials Rs: 52688.58
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
IRR-CCDW
237
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 4.00 215.00 860.00for conveying concrete Day 15.76 215.00 3388.40for cleaning/ washing/ curing Day 1.00 215.00 215.00
8 Labour cost for shuttering sqm 31.52 55.65 1754.09Labour cost for scaffolding @ 25% 438.52
Total cost of Labour Rs: 12532.46labour component/unit qty 795.20Add contractor's profit and overhead charges 0.14 111.30labour component/unit qty (including contractor's profit) 906.50
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 52688.58B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 12532.46
Total Rs: 66776.69D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 9348.74Total cost for 15.76 cum Rs: 76125.4308142Rate per cum (A+B+C+D)/15.76 Rs. 4830.30
IRR-CCDW-2-10
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSIS UNIT : 15.71 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 4398.80 5.50 24193.40Cement for incidentals @ 5 kg / cum kg 78.55 5.50 432.03
2 Coarse aggregate 20-10 mm cum 8.17 1025.00 8373.43Coarse aggregate 10 mm below cum 4.40 750.00 3299.10
3 Fine aggregate cum 7.07 425 3004.544 Super Plasticizer kg 17.60 54 950.145 Use rate of shuttering for 40 uses sqm 31.42 197.64 6209.94
Scaffolding @ of shuttering 25% 1552.486 Sundries LS 0.50 33 16.50Add seignorage charges on CA @ (included in material rate) Rs: 0.00
Add seignorage charges on FA @ (included in material rate) Rs: 0.00Total cost of Materials Rs: 48031.56
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
IRR-CCDW
238
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 4.00 215.00 860.00for conveying concrete Day 15.71 215.00 3377.65for cleaning/ washing/ curing Day 1.00 215.00 215.00
8 Labour cost for shuttering sqm 31.42 55.65 1748.52Labour cost for scaffolding @ 25% 437.13
Total cost of Labour Rs: 12514.75labour component/unit qty 796.60Add contractor's profit and overhead charges 0.14 111.50labour component/unit qty (including contractor's profit) 908.10
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 48031.56B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 12514.75
Total Rs: 62101.96D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8694.27Total cost for 15.71 cum Rs: 70796.2297088Rate per cum (A+B+C+D)/15.71 Rs. 4506.40
IRR-CCDW-2-11
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSIS UNIT : 18.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 3960.00 5.50 21780.00Cement for incidentals @ 5 kg / cum kg 90.00 5.50 495.00
2 Coarse aggregate 20-10 mm cum 9.36 1025.00 9594.00Coarse aggregate 10 mm below cum 5.04 750.00 3780.00
3 Fine aggregate cum 8.10 425 3442.504 Super Plasticizer kg 15.84 54 855.365 Use rate of shuttering for 40 uses sqm 36.00 197.64 7115.14
Scaffolding @ of shuttering 25% 1778.796 Sundries LS 0.50 33 16.50
Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00
Total cost of Materials Rs: 48857.29
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
IRR-CCDW
239
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 4.00 215.00 860.00for conveying concrete Day 18.00 215.00 3870.00for cleaning/ washing/ curing Day 1.00 215.00 215.00
8 Labour cost for shuttering sqm 36.00 55.65 2003.40Labour cost for scaffolding @ 25% 500.85
Total cost of Labour Rs: 13325.70labour component/unit qty 740.30Add contractor's profit and overhead charges 0.14 103.60labour component/unit qty (including contractor's profit) 843.90
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 48857.29B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 13325.70
Total Rs: 63738.64D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8923.41Total cost for 18.00 cum Rs: 72662.047935Rate per cum (A+B+C+D)/18.0 Rs. 4036.80
IRR-CCDW-2-12
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. 7500(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSIS UNIT : 15.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 5250.00 5.50 28875.002 Coarse aggregate 20-10 mm cum 7.80 1025.00 7995.00
Coarse aggregate 10 mm below cum 4.20 750.00 3150.003 Fine aggregate cum 6.75 425 2868.754 Super Plasticizer kg 21.00 54 1134.005 Use rate of curved shutter (40 uses) sqm 82.50 217.41 17936.096 Sundries LS 0.50 33 16.50
Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00
Total cost of Materials Rs: 61975.34
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for well kerb including cost of all materials, machinery, labour, formwork,
etc., complete with initial lead upto 50 m and all lifts.
IRR-CCDW
240
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 15.00 215.00 3225.00for cleaning/ washing/ curing Day 1.00 215.00 215.00
7 Labour cost for shuttering sqm 82.50 55.65 4591.13Total cost of Labour Rs: 14446.28
labour component/unit qty 963.10Add contractor's profit and overhead charges 0.14 134.80labour component/unit qty (including contractor's profit) 1097.90
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 61975.34B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 14446.28
Total Rs: 77457.56D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 10844.06Total cost for 15.00 cum Rs: 88301.6230023Rate per cum (A+B+C+D)/15.0 Rs. 5886.80
IRR-CCDW-2-13
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSIS UNIT : 15.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 4800.00 5.50 26400.00Cement for incidentals @ 2 kg / cum kg 30.00 5.50 165.00
2 Coarse aggregate 40-20 mm cum 6.75 975.00 6581.25Coarse aggregate 20-10 mm cum 4.05 1025.00 4151.25Coarse aggregate 10 mm below cum 2.70 750.00 2025.00
3 Fine aggregate cum 6.00 425 2550.004 Super Plasticizer kg 19.20 54 1036.805 Use rate of curved shutter (40 uses) sqm 60.00 217.41 13044.436 Sundries LS 0.50 33 16.50
Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00
Total cost of Materials Rs: 55970.23
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.55
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for well steining including cost of all materials, machinery, labour, formwork,
etc., complete with initial lead upto 50 m and all lifts.
IRR-CCDW
241
3 Crew for Vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 15.00 215.00 3225.00for cleaning/ washing/ curing Day 1.00 215.00 215.00
IRR-CCDW
242
7 Labour cost for shuttering sqm 60.00 55.65 3339.00Total cost of Labour Rs: 13194.15
labour component/unit qty 879.60Add contractor's profit and overhead charges 0.14 123.10labour component/unit qty (including contractor's profit) 1002.70
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 55970.23B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 13194.15
Total Rs: 70200.33D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 9828.05Total cost for 15.00 cum Rs: 80028.377638Rate per cum (A+B+C+D)/15.0 Rs. 5335.20
IRR-CCDW-2-14
machinery, labour, batching, mixing, placing in position as per detailed specifications etc.,
(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSIS UNIT : 14.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 4900.00 5.50 26950.002 Coarse aggregate 20-10 mm cum 7.28 1025.00 7462.00
Coarse aggregate 10 mm below cum 3.92 750.00 2940.003 Fine aggregate cum 6.30 425 2677.504 Super Plasticizer kg 19.60 54 1058.40
TOTAL Rs: 41087.90Add for tremie arrangement @ 1% Rs: 410.88Add seignorage charges on CA @ (Included in material ra Rs:Add seignorage charges on FA @ (Included in material ra Rs:
Total cost of Materials Rs: 41498.78
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Sundries( Hopper etc. ) LS 5.00 33 165.00
Total hire charges of Machinery Rs: 1053.75
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Fitter shuttering Day 1.00 260.00 260.004 work inspector Day 1.00 275.00 275.005 mazdoor
for erecting/ dismantling tremie Day 4.00 215.00 860.00for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for feeding tremie hopper Day 2.00 215.00 430.00for conveying concrete Day 16.00 215.00 3440.00
Total cost of Labour Rs: 9659.15labour component/unit qty 689.90Add contractor's profit and overhead charges 0.14 96.60labour component/unit qty (including contractor's profit) 786.50
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 41498.78B. Hire charges of Machinery Rs: 1053.75
Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N / sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for well bottom plug by tremie or skip box method including cost of all materials,
complete with initial lead upto 50 m and all lifts. ( Cement content : 350 kg / cum )
IRR-CCDW
243
C. Cost of Labour Rs: 9659.15Total Rs: 52211.68
IRR-CCDW
244
D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 7309.64Total cost for 14.00 cum Rs: 59521.319Rate per cum (A+B+C+D)/14.0 Rs. 4251.50
IRR-CCDW-2-15
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSIS UNIT : 14.29 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 4001.20 5.50 22006.602 Coarse aggregate 40-20 mm cum 6.43 975.00 6269.74
Coarse aggregate 20-10 mm cum 3.86 1025.00 3954.76Coarse aggregate 10 mm below cum 2.57 750.00 1929.15
3 Fine aggregate cum 5.72 425 2429.304 Super Plasticizer kg 16.00 54 864.26
Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 37453.80
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 14.29 215.00 3072.35for cleaning/ washing/ curing Day 1.00 215.00 215.00
Total cost of Labour Rs: 9702.50labour component/unit qty 679.00Add contractor's profit and overhead charges 0.14 95.10labour component/unit qty (including contractor's profit) 774.10
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 37453.80B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 9702.50
Total Rs: 48192.25D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 6746.92Total cost for 14.29 cum Rs: 54939.17Rate per cum (A+B+C+D)/14.29 Rs. 3844.60
IRR-CCDW-2-16
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for well top plug including cost of all materials, machinery, labour, cleaning,
initial lead upto 50 m and all lifts.
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
IRR-CCDW
245
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curingaggregates for well cap including cost of all materials, machinery, labour, formwork,
IRR-CCDW
246
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSIS UNIT : 15.76 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 5200.80 5.50 28604.40Cement for incidentals @ 5 kg / cum kg 78.80 5.50 433.40
2 Coarse aggregate 20-10 mm cum 8.20 1025.00 8400.08Coarse aggregate 10 mm below cum 4.41 750.00 3309.60
3 Fine aggregate cum 7.09 425 3014.104 Super Plasticizer kg 20.80 54 1123.375 Use rate of curved shutter (40 uses) sqm 15.76 197.64 3114.856 Sundries LS 0.50 33 16.50
Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 48016.30
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 15.76 215.00 3388.40for cleaning/ washing/ curing Day 1.00 215.00 215.00
7 Labour cost for shuttering sqm 15.76 55.65 877.04Total cost of Labour Rs: 10895.59
labour component/unit qty 691.30Add contractor's profit and overhead charges 0.14 96.80labour component/unit qty (including contractor's profit) 788.10
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 48016.30B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 10895.59
Total Rs: 59947.85D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8392.7Total cost for 15.76 cum Rs: 68340.5480057Rate per cum (A+B+C+D)/15.76 Rs. 4336.30
IRR-CCDW-2-17
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curingetc., complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
etc., complete with initial lead upto 50 m and all lifts.
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for piers and abutments including cost of all materials, labour, machinery,
IRR-CCDW
247
DATA: RATE ANALYSIS UNIT : 14.40 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 3600.00 5.50 19800.00Cement for incidentals @ 5 kg / cum kg 72.00 5.50 396.00
2 Coarse aggregate 80-40 mm cum 4.94 560.00 2765.95Coarse aggregate 40-20 mm cum 4.23 975.00 4127.76Coarse aggregate 20-10 mm cum 2.82 1025.00 2892.96Coarse aggregate 10 mm below cum 2.12 750.00 1587.60
3 Fine aggregate cum 5.04 425 2142.004 Super Plasticizer kg 14.40 54 777.605 Use rate of shuttering for 40 uses sqm 39.60 207.52 8217.996 Scaffolding @ of shuttering 30% 2465.40
Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 45173.26
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 600/400 ltr ( diesel ) Hour 8.00 77.00 616.00
Fuel / Energy charges Hour 8.00 123.80 990.402 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 6.20 49.60
Fuel / Energy charges Hour 8.00 18.60 148.80Total hire charges of Machinery Rs: 1839.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 6.00 215.00 1290.00for conveying concrete Day 14.40 215.00 3096.00for cleaning/ washing/ curing Day 1.00 215.00 215.00
7 Labour cost for shuttering sqm 39.60 55.65 2203.74Labour cost for scaffolding @ 30% 661.12
Total cost of Labour Rs: 13236.01labour component/unit qty 919.20Add contractor's profit and overhead charges 0.14 128.70labour component/unit qty (including contractor's profit) 1047.90
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 45173.26B. Hire charges of Machinery Rs: 1839.95C. Cost of Labour Rs: 13236.01
Total Rs: 60249.22D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8434.89Total cost for 14.40 cum Rs: 68684.1102355Rate per cum (A+B+C+D)/14.40 Rs. 4769.70
IRR-CCDW-2-18
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for piers and abutments including cost of all materials, labour, machinery,
etc., complete with initial lead upto 50 m and all lifts.
IRR-CCDW
248
DATA: RATE ANALYSIS UNIT : 14.55 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 3201.00 5.50 17605.50Cement for incidentals @ 5 kg / cum kg 72.75 5.50 400.13
2 Coarse aggregate 80-40 mm cum 4.99 560.00 2794.76Coarse aggregate 40-20 mm cum 4.28 975.00 4170.76Coarse aggregate 20-10 mm cum 2.85 1025.00 2923.10Coarse aggregate 10 mm below cum 2.14 750.00 1604.14
3 Fine aggregate cum 5.09 425 2164.314 Super Plasticizer kg 12.80 54 691.425 Use rate ofshuttering for 40 uses sqm 40.01 207.52 8303.596 Scaffolding @ of shuttering 30% 2491.08
Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 43148.78
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 600/400 ltr ( diesel ) Hour 8.00 77.00 616.00
Fuel / Energy charges Hour 8.00 123.80 990.402 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 6.20 49.60
Fuel / Energy charges Hour 8.00 18.60 148.80Total hire charges of Machinery Rs: 1839.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 6.00 215.00 1290.00for conveying concrete Day 14.55 215.00 3128.25for cleaning/ washing/ curing Day 1.00 215.00 215.00
7 Labour cost for shuttering sqm 40.01 55.65 2226.70Labour cost for scaffolding @ 30% 668.01
Total cost of Labour Rs: 13298.10labour component/unit qty 914.00Add contractor's profit and overhead charges 0.14 128.00labour component/unit qty (including contractor's profit) 1042.00
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 43148.78B. Hire charges of Machinery Rs: 1839.95C. Cost of Labour Rs: 13298.10
Total Rs: 58286.83D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8160.16Total cost for 14.55 cum Rs: 66446.9933213Rate per cum (A+B+C+D)/14.55 Rs. 4566.80
IRR-CCDW-2-19
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSIS UNIT : 16.36 cum
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for piers and abutments including cost of all materials, labour, machinery,
etc., complete with initial lead upto 50 m and all lifts.
IRR-CCDW
249
A. MATERIALS:Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.1 Cement for mix kg 3599.20 5.50 19795.60
Cement for incidentals @ 5 kg / cum kg 81.80 5.50 449.902 Coarse aggregate 40-20 mm cum 7.36 975.00 7177.95
IRR-CCDW
250
Coarse aggregate 20-10 mm cum 4.42 1025.00 4527.63Coarse aggregate 10 mm below cum 2.94 750.00 2208.60
3 Fine aggregate cum 6.54 425 2781.204 Super Plasticizer kg 14.40 54 777.435 Use rate of shuttering for 40 uses sqm 44.99 207.52 9336.556 Scaffolding @ of shuttering 30% 2800.96
Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 49855.82
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 5.00 215.00 1075.00for conveying concrete Day 16.36 215.00 3517.40for cleaning/ washing/ curing Day 1.00 215.00 215.00
7 Labour cost for shuttering sqm 44.99 55.65 2503.69Labour cost for scaffolding @ 30% 751.11
Total cost of Labour Rs: 13832.35labour component/unit qty 845.50Add contractor's profit and overhead charges 0.14 118.40labour component/unit qty (including contractor's profit) 963.90
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 49855.82B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 13832.35
Total Rs: 64724.12D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 9061.38Total cost for 16.36 cum Rs: 73785.5025565Rate per cum (A+B+C+D)/16.36 Rs. 4510.10
IRR-CCDW-2-20
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
DATA: RATE ANALYSIS UNIT : 16.25 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 5200.00 5.50 28600.00Cement for incidentals @ 5 kg / cum kg 81.25 5.50 446.88
2 Coarse aggregate 40-20 mm cum 7.31 975.00 7129.69Coarse aggregate 20-10 mm cum 4.39 1025.00 4497.19
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for cantiliver / counterfort retaining walls including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
IRR-CCDW
251
Coarse aggregate 10 mm below cum 2.93 750.00 2193.753 Fine aggregate cum 6.50 425 2762.504 Super Plasticizer kg 20.80 54 1123.205 Use rate of shuttering for 40 uses sqm 52.81 197.64 10438.01
Scaffolding @ of shuttering 25% 2609.506 Sundries LS 0.50 33 16.50
Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 59817.22
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 5.00 215.00 1075.00for conveying concrete Day 16.25 215.00 3493.75for cleaning/ washing/ curing Day 1.00 215.00 215.00
7 Labour cost for shuttering sqm 52.81 55.65 2939.02Labour cost for scaffolding @ 25% 734.75
Total cost of Labour Rs: 14227.67labour component/unit qty 875.50Add contractor's profit and overhead charges 0.14 122.60labour component/unit qty (including contractor's profit) 998.10
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 59817.22B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 14227.67
Total Rs: 75080.84D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 10511.32Total cost for 16.25 cum Rs: 85592.1553387Rate per cum (A+B+C+D)/16.25 Rs. 5267.20
IRR-CCDW-2-21
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum, plums of size 150 to 80 mm : 0.25cum ) 2.82
DATA: RATE ANALYSIS UNIT : 18.09 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 4703.40 5.50 25868.70Cement for incidentals @ 4 kg / cum kg 72.36 5.50 397.98
2 Coarse aggregate 40-20 mm cum 6.92 975.00 6746.44
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates with placing and sinking plums of size 150 to 80 mm upto 15 percent for gravitytype retaining walls / piers / abutments etc., including cost of all materials, machinery,
finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
IRR-CCDW
252
Coarse aggregate 20-10 mm cum 4.15 1025.00 4255.45Coarse aggregate 10 mm below cum 2.77 750.00 2075.83
3 Plums of size 150 to 80 mm cum 4.52 310 1401.984 Fine aggregate cum 6.15 425 2614.015 Super Plasticizer kg 18.81 54 1015.93
Use rate of shuttering for 40 uses sqm 49.75 197.64 9832.246 Scaffolding @ of shuttering 30% 2949.67
Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 57158.22
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 6.20 49.60
Fuel / Energy charges Hour 8.00 18.60 148.80Total hire charges of Machinery Rs: 1087.15
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 5.00 215.00 1075.00for placing plums Day 2.00 215.00 430.00for conveying concrete Day 15.38 215.00 3306.70for conveying plums Day 2.00 215.00 430.00for cleaning/ washing/ curing Day 1.00 215.00 215.00
7 Labour for shuttering sqm 49.75 55.65 2768.45Labour for scaffolding @ 30% 830.53
Total cost of Labour Rs: 14825.83labour component/unit qty 819.60Add contractor's profit and overhead charges 0.14 114.70labour component/unit qty (including contractor's profit) 934.30
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 57158.22B. Hire charges of Machinery Rs: 1087.15C. Cost of Labour Rs: 14825.83
Total Rs: 73071.20D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 10229.97Total cost for 18.09 cum Rs: 83301.17Rate per cum (A+B+C+D)/18.09 Rs. 4604.80
IRR-CCDW-2-22
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSIS UNIT : 15.38 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 3998.80 5.50 21993.40
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,gradedaggregates for cast in-situ pipes including cost of all materials, machinery, labour, cleaning,
initial lead upto 50 m and all lifts.
IRR-CCDW
253
Cement for incidentals @ 5 kg / cum kg 76.90 5.50 422.952 Coarse aggregate 40-20 mm cum 6.92 975.00 6747.98
Coarse aggregate 20-10 mm cum 4.15 1025.00 4256.42Coarse aggregate 10 mm below cum 2.77 750.00 2076.30
3 Fine aggregate cum 6.15 425 2614.604 Super Plasticizer kg 16.00 54 863.745 Use rate of shuttering for 40 uses sqm 30.76 207.52 6383.47
Scaffolding @ of shuttering 15% 957.526 Sundries LS 0.50 33 16.50
Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 46332.87
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 15.38 215.00 3306.70for cleaning/ washing/ curing Day 1.00 215.00 215.00
7 Labour for shuttering sqm 30.76 55.65 1711.79Labour for scaffolding @ 15% 256.77
Total cost of Labour Rs: 11905.41labour component/unit qty 774.10Add contractor's profit and overhead charges 0.14 108.40labour component/unit qty (including contractor's profit) 882.50
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 46332.87B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 11905.41
Total Rs: 59274.23D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8298.39Total cost for 15.38 cum Rs: 67572.6227247Rate per cum (A+B+C+D)/15.38 Rs. 4393.50
IRR-CCDW-2-23
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
DATA: RATE ANALYSIS UNIT : 14.40 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 3600.00 5.50 19800.00Cement for incidentals @ 5 kg / cum kg 72.00 5.50 396.00
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for cast in-situ pipes including cost of all materials, labour, machinery, formwork,
complete with initial lead upto 50 m and all lifts.
IRR-CCDW
254
2 Coarse aggregate 80-40 mm cum 4.94 560.00 2765.95Coarse aggregate 40-20 mm cum 4.23 975.00 4127.76Coarse aggregate 20-10 mm cum 2.82 1025.00 2892.96Coarse aggregate 10 mm below cum 2.12 750.00 1587.60
3 Fine aggregate cum 5.04 425 2142.004 Super Plasticizer kg 14.40 54 777.605 Use rate of shuttering for 40 uses sqm 28.80 207.52 5976.726 Scaffolding @ of shuttering 15% 896.51
Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 41363.10
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 600/400 ltr ( diesel ) Hour 8.00 77.00 616.00
Fuel / Energy charges Hour 8.00 123.80 990.402 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 6.20 49.60
Fuel / Energy charges Hour 8.00 18.60 148.80Total hire charges of Machinery Rs: 1839.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 14.40 215.00 3096.00for cleaning/ washing/ curing Day 1.00 215.00 215.00
7 Labour cost for shuttering sqm 28.80 55.65 1602.72Labour cost for scaffolding @ 15% 240.41
Total cost of Labour Rs: 11569.28labour component/unit qty 803.40Add contractor's profit and overhead charges 0.14 112.50labour component/unit qty (including contractor's profit) 915.90
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 41363.10B. Hire charges of Machinery Rs: 1839.95C. Cost of Labour Rs: 11569.28
Total Rs: 54772.33D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 7668.13Total cost for 14.40 cum Rs: 62440.46Rate per cum (A+B+C+D)/14.40 Rs. 4336.10
IRR-CCDW-2-24
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSIS UNIT : 15.76 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 5200.80 5.50 28604.40Cement for incidentals @ 5 kg / cum kg 78.80 5.50 433.40
2 Coarse aggregate 20-10 mm cum 8.20 1025.00 8400.08
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for deck slab & kerb including cost of all materials,machinery, labour, formwork,
etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 300 kg / cum )
IRR-CCDW
255
Coarse aggregate 10 mm below cum 4.41 750.00 3309.603 Fine aggregate cum 7.09 425 3014.104 Super Plasticizer kg 20.80 54 1123.375 Use rate of shuttering for 30 uses sqm 39.40 242.86 9568.57
Scaffolding @ of shuttering 250% 23921.436 Sundries LS 1.00 33 33.00
Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 78407.95
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 2.00 285.00 570.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 4.00 215.00 860.00for conveying concrete Day 15.76 215.00 3388.40for cleaning/ washing/ curing Day 1.00 215.00 215.00
7 Labour cost for shuttering sqm 39.40 55.65 2192.61Labour cost for scaffolding @ 250% 5481.53
Total cost of Labour Rs: 18192.68labour component/unit qty 1154.40Add contractor's profit and overhead charges 0.14 161.60labour component/unit qty (including contractor's profit) 1316.00
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 78407.95B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 18192.68
Total Rs: 97636.59D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 13669.12Total cost for 15.76 cum Rs: 111305.71Rate per cum (A+B+C+D)/15.76 Rs. 7062.50
IRR-CCDW-2-25
formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
kg / cum )Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSIS UNIT : 15.76 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 5200.80 5.50 28604.40Cement for incidentals @ 5 kg / cum kg 78.80 5.50 433.40
2 Coarse aggregate 20-10 mm cum 8.20 1025.00 8400.08Coarse aggregate 10 mm below cum 4.41 750.00 3309.60
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for columns and beams including cost of all materials, labour, machinery,
finishing, curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content : 300
IRR-CCDW
256
3 Fine aggregate cum 7.09 425 3014.104 Super Plasticizer kg 20.80 54 1123.375 Use rate of shuttering sqm 78.80 197.64 15574.26
Scaffolding @ of shuttering 50% 7787.136 Sundries LS 1.00 33 33.00
Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 68279.34
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 15.76 215.00 3388.40for cleaning/ washing/ curing Day 1.00 215.00 215.00
7 Labour cost for shuttering sqm 78.80 55.65 4385.22Labour cost for scaffolding @ 50% 2192.61
Total cost of Labour Rs: 16596.38labour component/unit qty 1053.10Add contractor's profit and overhead charges 0.14 147.40labour component/unit qty (including contractor's profit) 1200.50
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 68279.34B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 16596.38
Total Rs: 85911.67D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 12027.63Total cost for 15.76 cum Rs: 97939.30Rate per cum (A+B+C+D)/15.76 Rs. 6214.40
IRR-CCDW-2-26
cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSIS UNIT : 15.76 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 5200.80 5.50 28604.40Cement for incidentals @ 5 kg / cum kg 78.80 5.50 433.40
2 Coarse aggregate 20-10 mm cum 8.20 1025.00 8400.08Coarse aggregate 10 mm below cum 4.41 750.00 3309.60
3 Fine aggregate cum 7.09 425 3014.10
Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for wearing coat including cost of all materials, machinery, labour, formwork,
finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 mand all lifts. ( Cement content : 300 kg / cum )
IRR-CCDW
257
4 Super Plasticizer kg 20.80 54 1123.375 Use rate of shuttering sqm 7.88 197.64 1557.436 Sundries ( asphalt mortar etc ) LS 5.00 33 165.00
Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 46607.38
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 2.00 285.00 570.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 4.00 215.00 860.00for conveying concrete Day 15.76 215.00 3388.40for cleaning/ washing/ curing Day 2.00 215.00 430.00
7 Labour cost for shuttering sqm 7.88 55.65 438.52Total cost of Labour Rs: 11172.07
labour component/unit qty 708.90Add contractor's profit and overhead charges 0.14 99.20labour component/unit qty (including contractor's profit) 808.10
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 46607.38B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 11172.07
Total Rs: 58815.40D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8234.16Total cost for 15.76 cum Rs: 67049.56Rate per cum (A+B+C+D)/15.76 Rs. 4254.40
IRR-CCDW-2-27 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSIS UNIT : 15.76 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 5200.80 5.50 28604.40Cement for incidentals @ 5 kg / cum kg 78.80 5.50 433.40
2 Coarse aggregate 20-10 mm cum 8.20 1025.00 8400.08Coarse aggregate 10 mm below cum 4.41 750.00 3309.60
3 Fine aggregate cum 7.09 425 3014.104 Super Plasticizer kg 20.80 54 1123.375 Use rate of shuttering for 40 uses sqm 70.92 197.64 14016.83
Scaffolding @ of shuttering 25% 3504.216 Sundries LS 0.50 33 16.50
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for troughs including cost of all materials, machinery, labour, formwork,
etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 300 kg / cum )
IRR-CCDW
258
Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 62422.49
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( diesel ) Hour 8.00 6.00 48.00
Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 5.00 215.00 1075.00for conveying concrete Day 15.76 215.00 3388.40for cleaning/ washing/ curing Day 1.00 215.00 215.00
7 Labour cost for shuttering sqm 70.92 55.65 3946.70Labour cost for scaffolding @ 25% 986.67
Total cost of Labour Rs: 15381.92labour component/unit qty 976.00Add contractor's profit and overhead charges 0.14 136.60labour component/unit qty (including contractor's profit) 1112.60
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 62422.49B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 15381.92
Total Rs: 78840.36D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 11037.65Total cost for 15.76 cum Rs: 89878.0133319Rate per cum (A+B+C+D)/15.76 Rs. 5702.90
IRR-CCDW-3 FOUNDATION WELL SINKING WORKS :
IRR-CCDW-3-1DATA: Unit = Running meter
Taking output = 1mdiameter of well = 6.00m
(i) Depth below bed level upto 3.0mRate of sinking = 0.50 m /hour
a) Labour0.12 Mate (Mason Cl- ll ) 260.00 day 31.201.00 Sinker ( skilled) 285.00 day 285.002.00 Sinking helper ( Semi skilled) 215.00 day 430.00
sub total (a) 746.20b) Machinery
2.00 Hire & running charges of crane with grab 422.30 hour 844.60 bucket of 0.75 cum capacity and accessories.Fuel Charges 233.90 hour 467.80Crew Charges 106.30 hour 212.60Consumables in sinking @ 10% of machinery charges 152.50
sub total (b) 1677.50sub total (a+b) 2423.70
14.00% 339.32
Sinking RCC wells vertically for foundation of piers and abutments in all kinds of soil, sand and soft rock by approved well sinking method including cost of all materials, machinery, labour, kent - ledge arrangements, disposal of excavated material as directed etc., complete with lead upto 50 m for disposal of excavated material.(diameter of well 6.00m)
c) Add for Contractor's profit and overhead charges on (A+B)
IRR-CCDW
259
Rate per metre = (a+b+c)/1.0 2763.02or say ( Rate upto 3.0m for 6.0 m well sinking ) 2763.00labour component/unit qty 898.70Contractor's profit and overhead charges 14.00% 125.80labour component/unit qty(including contractor's profit) 1024.50
(ii) Beyond 3m and upto 10m depthRate of sinking = 0.33 m per hour.
a) Labour0.15 Mate (Mason Cl- ll ) 260.00 day 39.001.25 Sinker ( skilled) 285.00 day 356.252.50 Sinking helper ( Semi skilled) 215.00 day 537.50
sub total (a) 932.75b) Machinery
3.00 Hire & running charges of crane with grab 422.30 hour 1266.90 bucket of 0.75 cum capacity and accessories.Fuel Charges 233.90 hour 701.70Crew Charges 106.30 hour 318.90Consumables in sinking @ 10% of machinery charges 228.75
sub total (b) 2516.25sub total (a+b) 3449.00
14.00% 482.86
Rate per metre = (a+b+c) 3931.86or say ( Rate for 3.0m to 10m well sinking ) 3931.90
labour component/unit qty 1161.50Contractor's profit and overhead charges 0.14 162.60labour component/unit qty(including contractor's profit) 1324.10
IRR-CCDW-3-2ramming as directed including cost of all materials, machinery, labour etc., complete with
DATA: RATE ANALYSIS UNIT : 15.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Sand unscreened cum 15.75 325 5118.750.00 0.00
Add seignorage charges on Sand @ Rs: (Included in material ra Rs: 0.00Total cost of Materials Rs: 5118.75
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nill 0.00 0.00 0.00
0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 work inspector Day 0.25 275.00 68.752 mazdoor Day 4.00 215.00 860.00
Total cost of Labour Rs: 928.75labour component/unit qty 61.90Add contractor's profit and overhead charges 0.14 8.70labour component/unit qty (including contractor's profit) 70.60
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 5118.75B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 928.75
Total Rs: 6047.50D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 846.65Total cost for 15.00 cum Rs: 6894.15
c) Add for Contractor's profit and overhead charges on (A+B)
Filling foundation wells with sand in layers of 25 to 30 cm and compacting by watering,
initial lead upto 50 m and all lifts.
IRR-CCDW
260
Rate per cum (A+B+C+D)/15.0 Rs. 459.60
IRR-CCDW-4 MASONRY WORKS :
IRR-CCDW-4-1
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,Stone Chips : 0.15 cum)
DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 1430.00 5.50 7865.002 Rubble stones cum 8.50 265 2252.503 Stone chips cum 1.50 310 465.004 Sand screened cum 4.00 425 1700.00
Add seignorage charges on Stone@ Rs(Included in material ra Rs: 0.00Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00
Total cost of Materials Rs: 12282.50
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.902 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.95Total hire charges of Machinery Rs: 554.85
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Water tanker Hour 1.00 106.30 106.302 Crew for Pump Hour 0.50 71.10 35.553 work inspector Day 1.00 275.00 275.004 Mason Class-I Day 1.00 285.00 285.005 Mason Class-II Day 2.00 260.00 520.006 mazdoor
for conveying rubble stones Day 4.00 215.00 860.00for preparing mortar Day 2.00 215.00 430.00for loading mortar pans Day 1.00 215.00 215.00for laying & packing mortar Day 3.00 215.00 645.00for washing rubble / finishing / curing Day 1.00 215.00 215.00for conveying mortar / chips Day 4.00 215.00 860.00
Total cost of Labour Rs: 4446.85labour component/unit qty 444.70Add contractor's profit and overhead charges 0.14 62.30labour component/unit qty (including contractor's profit) 507.00
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 12282.50B. Hire charges of Machinery Rs: 554.85C. Cost of Labour Rs: 4446.85
Total Rs: 17284.20D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2419.79Total cost for 10.00 cum Rs: 19703.99Rate per cum (A+B+C+D)/10.0 Rs. 1970.40
IRR-CCDW-4-2
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,Stone Chips : 0.15 cum)
Providing and constructing un-coursed rubble stone masonry with approved stones inCM 1 : 4 proportion for sub-structure portions of return walls / abutments etc., including
stone chips, curing etc., complete with initial lead upto 50 m and all lifts.
Providing and constructing un-coursed rubble stone masonry with approved stones inCM 1 : 4 proportion for super-structure portions of return walls / abutments etc., including
stone chips, curing etc., complete with initial lead upto 50 m and all lifts.
IRR-CCDW
261
DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 1430.00 5.50 7865.002 Rubble stones cum 8.50 265 2252.503 Stone chips cum 1.50 310 465.004 Sand screened cum 4.00 425 1700.00
TOTAL Rs: 12282.50Add for scaffolding @ 2.5% Rs: 307.06Add seignorage charges on Stone@ Rs(Included in material ra Rs:Add seignorage charges on Sand @ Rs(Included in material ra Rs:
Total cost of Materials Rs: 12589.56
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.902 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.95Total hire charges of Machinery Rs: 554.85
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Water tanker Hour 1.00 106.30 106.302 Crew for Pump Hour 0.50 71.10 35.553 work inspector Day 1.00 275.00 275.004 Mason Class-I Day 1.00 285.00 285.005 Mason Class-II Day 2.00 260.00 520.006 mazdoor
for conveying rubble stones Day 4.00 215.00 860.00for preparing mortar Day 2.00 215.00 430.00for loading mortar pans Day 1.00 215.00 215.00for laying & packing mortar Day 3.00 215.00 645.00for washing rubble / finishing / curing Day 1.00 215.00 215.00for conveying mortar / chips Day 4.00 215.00 860.00
TOTAL Rs: 4446.85Add for labour for scaffolding @ 2.5% Rs: 111.17
Total cost of Labour Rs: 4558.02labour component/unit qty 455.80Add contractor's profit and overhead charges 0.14 63.80labour component/unit qty (including contractor's profit) 519.60
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 12589.56B. Hire charges of Machinery Rs: 554.85C. Cost of Labour Rs: 4558.02
Total Rs: 17702.43D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2478.34Total cost for 10.00 cum Rs: 20180.77375Rate per cum (A+B+C+D)/10.0 Rs. 2018.10
IRR-CCDW-4-3stones from approved source including cost of all materials, machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with
(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones 25 x 25x 45 cm : 60 Nos)
DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 1330.00 5.50 7315.002 Header stones 25x25x45 cm Nos 60.00 32 1920.003 Khandki stones 25x25x30 cm Nos 180.00 12 2160.004 Rubble stones cum 4.50 265 1192.50
Providing and constructing coursed rubble masonry second sort in CM 1:4 proportion with
initial lead upto 50 m and initial lift upto 3m.
IRR-CCDW
262
5 Stone chips cum 1.50 310 465.006 Sand screened cum 3.50 425 1487.50
TOTAL Rs: 14540.00Add for scaffolding materials @ 2.5% Rs: 363.50Add seignorage charges on Stone@ Rs(Included in material ra Rs:Add seignorage charges on Sand @ Rs(Included in material ra Rs:
Total cost of Materials Rs: 14903.50
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.902 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.95Total hire charges of Machinery Rs: 554.85
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Water tanker Hour 1.00 106.30 106.302 Crew for Pump Hour 0.50 71.10 35.553 work inspector Day 1.00 275.00 275.004 Stone chiseller Cl -II Day 3.00 260.00 780.005 Mason Class-I Day 1.00 285.00 285.006 Mason Class-II Day 2.00 260.00 520.007 mazdoor
for conveying stones / rubble Day 4.00 215.00 860.00for preparation of mortar Day 3.00 215.00 645.00for loading mortar pans Day 1.00 215.00 215.00for laying & packing mortar Day 3.00 215.00 645.00for washing rubble / finishing / curing Day 1.00 215.00 215.00for conveying mortar / chips Day 2.00 215.00 430.00
TOTAL Rs: 5011.85Add for labour for scaffolding @ 2.5% Rs: 125.30
Total cost of Labour Rs: 5137.15labour component/unit qty 513.70Add contractor's profit and overhead charges 0.14 71.90labour component/unit qty (including contractor's profit) 585.60
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 14903.50B. Hire charges of Machinery Rs: 554.85C. Cost of Labour Rs: 5137.15
Total Rs: 20595.50D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2883.37Total cost for 10.00 cum Rs: 23478.86625Rate per cum (A+B+C+D)/10.0 Rs. 2347.90
IRR-CCDW-4-4 Providing and constructing coursed rubble masonry first sort in CM 1:4 proportion withstones from approved source including cost of all materials, machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete withinitial lead upto 50 m and initial lift upto 3 m.(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones 25 x 25x 45 cm : 60 Nos)
DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 1330.00 5.50 7315.002 Header stones 25x25x45 cm Nos 60.00 32 1920.003 Khandki stones 25x25x30 cm Nos 180.00 12 2160.004 Rubble stones cum 4.50 265 1192.505 Stone chips cum 1.50 310 465.006 Sand screened cum 3.50 425 1487.50
TOTAL Rs: 14540.00Add for scaffolding materials @ 2.5% Rs: 363.50Add seignorage charges on Stone@ Rs(Included in material ra Rs:Add seignorage charges on Sand @ Rs(Included in material ra Rs:
IRR-CCDW
263
Total cost of Materials Rs: 14903.50
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.902 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.95Total hire charges of Machinery Rs: 554.85
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Water tanker Hour 1.00 106.30 106.302 Crew for Pump Hour 0.50 71.10 35.553 work inspector Day 1.00 275.00 275.004 Stone chiseller Cl -II Day 6.00 260.00 1560.005 Mason Class-I Day 1.00 285.00 285.006 Mason Class-II Day 2.00 260.00 520.007 mazdoor8 for conveying rubble/ stones Day 4.00 215.00 860.00
for preparation of mortar Day 3.00 215.00 645.00for loading mortar pans Day 1.00 215.00 215.00for laying & packing mortar Day 3.00 215.00 645.00for washing rubble / finishing / curing Day 1.00 215.00 215.00for conveying mortar / chips Day 2.00 215.00 430.00
TOTAL Rs: 5791.85Add for labour for scaffolding @ 2.5% Rs: 144.80
Total cost of Labour Rs: 5936.65labour component/unit qty 593.70Add contractor's profit and overhead charges 0.14 83.10labour component/unit qty (including contractor's profit) 676.80
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 14903.50B. Hire charges of Machinery Rs: 554.85C. Cost of Labour Rs: 5936.65
Total Rs: 21395.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2995.3Total cost for 10.00 cum Rs: 24390.29625Rate per cum (A+B+C+D)/10.0 Rs. 2439.00
IRR-CCDW-4-5proportion by volume including raking and cleaning joints for 50 mm depth, pressing cementmortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
DATA: RATE ANALYSIS UNIT : 100.00 sqmA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 456.00 5.50 2508.002 Sand screened cum 0.75 425 318.75
TOTAL Rs: 2826.75Add for scaffolding / ramps etc @ 2.5% Rs: 70.67Add seignorage charges on Sand @ Rs(Included in material ra Rs:
Total cost of Materials Rs: 2897.42
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 2
initial lead upto 50 m and all lifts.
IRR-CCDW
264
1 Mason Cl- I Day 10.00 285.00 2850.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 10.00 215.00 2150.00
Total cost of Labour Rs: 5275.00labour component/unit qty 52.80Add contractor's profit and overhead charges 0.14 7.40labour component/unit qty (including contractor's profit) 60.20
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2897.42B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 5275.00
Total Rs: 8172.42D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1144.14Total cost for 100.00 sqm Rs: 9316.55875Rate per sqm (A+B+C+D)/100.0 Rs. 93.20
IRR-CCDW-4-6proportion by volume including raking and cleaning joints for 50 mm depth, pressing cementmortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
DATA: RATE ANALYSIS UNIT : 100.00 sqmA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 322.00 5.50 1771.002 Sand screened cum 0.75 425 318.75
TOTAL Rs: 2089.75Add for scaffolding / ramps etc @ 2.5% Rs: 52.24Add seignorage charges on Sand @ Rs(Included in material ra Rs:
Total cost of Materials Rs: 2141.99
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- I Day 10.00 285.00 2850.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 10.00 215.00 2150.00
Total cost of Labour Rs: 5275.00labour component/unit qty 52.80Add contractor's profit and overhead charges 0.14 7.40labour component/unit qty (including contractor's profit) 60.20
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2141.99B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 5275.00
Total Rs: 7416.99D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1038.38Total cost for 100.00 sqm Rs: 8455.37375Rate per sqm (A+B+C+D)/100.0 Rs. 84.60
IRR-CCDW-4-7of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
DATA: RATE ANALYSIS UNIT : 100.00 sqmA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 629.00 5.50 3459.50
Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 3
initial lead upto 50 m and all lifts.
Providing 12 mm thick plastering in cement mortar 1:3 proportion by volume including cost
complete with initial lead upto 50 m and all lifts.
IRR-CCDW
265
2 Sand screened cum 1.32 425 561.00TOTAL Rs: 4020.50
Add for scaffolding / ramps etc @ 2.5% Rs: 100.51Add seignorage charges on Sand @ Rs(Included in material ra Rs:
Total cost of Materials Rs: 4121.01
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- I Day 10.00 285.00 2850.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 20.00 215.00 4300.00
Total cost of Labour Rs: 7425.00labour component/unit qty 74.30Add contractor's profit and overhead charges 0.14 10.40labour component/unit qty (including contractor's profit) 84.70
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 4121.01B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 7425.00
Total Rs: 11546.01D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1616.44Total cost for 100.00 sqm Rs: 13162.4525Rate per sqm (A+B+C+D)/100.0 Rs. 131.60
IRR-CCDW-4-8of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
DATA: RATE ANALYSIS UNIT : 100.00 sqmA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 472.00 5.50 2596.002 Sand screened cum 1.32 425 561.00
TOTAL Rs: 3157.00Add for scaffolding / ramps etc @ 2.5% Rs: 78.93Add seignorage charges on Sand @ Rs(Included in material ra Rs:
Total cost of Materials Rs: 3235.93
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- I Day 10.00 285.00 2850.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 20.00 215.00 4300.00
Total cost of Labour Rs: 7425.00labour component/unit qty 74.30Add contractor's profit and overhead charges 0.14 10.40labour component/unit qty (including contractor's profit) 84.70
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 3235.93B. Hire charges of Machinery Rs: 0.00
Providing 12 mm thick plastering in cement mortar 1:4 proportion by volume including cost
complete with initial lead upto 50 m and all lifts.
IRR-CCDW
266
C. Cost of Labour Rs: 7425.00Total Rs: 10660.93
D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1492.53Total cost for 100.00 sqm Rs: 12153.455Rate per sqm (A+B+C+D)/100.0 Rs. 121.50
IRR-CCDW-4-9of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
DATA: RATE ANALYSIS UNIT : 100.00 sqmA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 1050.00 5.50 5775.002 Sand screened cum 2.20 425 935.00
TOTAL Rs: 6710.00Add for scaffolding / ramps etc @ 2.5% Rs: 167.75Add seignorage charges on Sand @ Rs(Included in material ra Rs:
Total cost of Materials Rs: 6877.75
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- I Day 15.00 285.00 4275.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 25.00 215.00 5375.00
Total cost of Labour Rs: 9925.00labour component/unit qty 99.30Add contractor's profit and overhead charges 0.14 13.90labour component/unit qty (including contractor's profit) 113.20
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 6877.75B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 9925.00
Total Rs: 16802.75D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2352.39Total cost for 100.00 sqm Rs: 19155.14Rate per sqm (A+B+C+D)/100.0 Rs. 191.60
IRR-CCDW-4-10of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
DATA: RATE ANALYSIS UNIT : 100.00 sqmA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 788.00 5.50 4334.002 Sand screened cum 2.20 425 935.00
TOTAL Rs: 5269.00Add for scaffolding / ramps etc @ 2.5% Rs: 131.73Add seignorage charges on Sand @ Rs(Included in material ra Rs:
Total cost of Materials Rs: 5400.73
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nil 0.00 0.00 0.00
Providing 20 mm thick plastering in cement mortar 1:3 proportion by volume including cost
complete with initial lead upto 50 m and all lifts.
Providing 20 mm thick plastering in cement mortar 1:4 proportion by volume including cost
complete with initial lead upto 50 m and all lifts.
IRR-CCDW
267
( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- I Day 15.00 285.00 4275.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 25.00 215.00 5375.00
Total cost of Labour Rs: 9925.00labour component/unit qty 99.30Add contractor's profit and overhead charges 0.14 13.90labour component/unit qty (including contractor's profit) 113.20
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 5400.73B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 9925.00
Total Rs: 15325.73D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2145.6Total cost for 100.00 sqm Rs: 17471.325Rate per sqm (A+B+C+D)/100.0 Rs. 174.70
IRR-CCDW-5 COPING & RAILING WORKS :
IRR-CCDW-5-1
50 m and all lifts.(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
DATA: RATE ANALYSIS UNIT : 10.00 sqmA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 75.00 5.50 412.502 Sand screened cum 0.30 425 127.503 Burnt stone slab 10 cm thick sqm 10.50 227 2383.50
Add seignorage charges on Stone @ Rs(Included in material ra Rs: 0.00Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00
Total cost of Materials Rs: 2923.50
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- II Day 1.00 260.00 260.002 Stone chiseller Cl- II Day 1.00 260.00 260.003 work inspector Day 0.50 275.00 137.504 mazdoor Day 2.00 215.00 430.00
Total cost of Labour Rs: 1087.50labour component/unit qty 108.80Add contractor's profit and overhead charges 0.14 15.20labour component/unit qty (including contractor's profit) 124.00
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2923.50B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1087.50
Total Rs: 4011.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 561.54Total cost for 10.00 sqm Rs: 4572.54Rate per sqm (A+B+C+D)/10.0 Rs. 457.30
Providing and fixing 10 cm thick roughly dressed burnt stone slabs for coping set inCM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume includingcost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
IRR-CCDW
268
IRR-CCDW-5-2CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
50 m and all lifts.(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
DATA: RATE ANALYSIS UNIT : 10.00 sqmA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 75.00 5.50 412.502 Sand screened cum 0.30 425 127.503 Burnt stone slab 10 cm thick sqm 10.50 227 2383.50
Add seignorage charges on Stone @ Rs(Included in material ra Rs: 0.00Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00
Total cost of Materials Rs: 2923.50
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- II Day 1.00 260.00 260.002 Stone chiseller Cl- I Day 4.00 285.00 1140.003 work inspector Day 0.50 275.00 137.504 mazdoor Day 2.00 215.00 430.00
Total cost of Labour Rs: 1967.50labour component/unit qty 196.80Add contractor's profit and overhead charges 0.14 27.60labour component/unit qty (including contractor's profit) 224.40
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2923.50B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1967.50
Total Rs: 4891.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 684.74Total cost for 10.00 sqm Rs: 5575.74Rate per sqm (A+B+C+D)/10.0 Rs. 557.60
IRR-CCDW-5-3
50 m and all lifts.(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
DATA: RATE ANALYSIS UNIT : 10.00 sqmA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 75.00 5.50 412.502 Sand screened cum 0.30 425 127.503 Burnt stone slab 10 cm thick sqm 10.50 227 2383.50
Add seignorage charges on Stone @ Rs(Included in material ra Rs: 0.00Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00
Total cost of Materials Rs: 2923.50
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nil 0.00 0.00 0.00
( Manual mixing) 0.00 0.00 0.00
Providing and fixing 10 cm thick one line dressed burnt stone slabs for coping set in
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
Providing and fixing 10 cm thick two line dressed burnt stone slabs for coping set inCM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume includingcost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
IRR-CCDW
269
Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- II Day 1.00 260.00 260.002 Stone chiseller Cl-I Day 8.00 285.00 2280.003 work inspector Day 0.50 275.00 137.504 mazdoor Day 2.00 215.00 430.00
Total cost of Labour Rs: 3107.50labour component/unit qty 310.80Add contractor's profit and overhead charges 0.14 43.50labour component/unit qty (including contractor's profit) 354.30
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2923.50B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 3107.50
Total Rs: 6031.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 844.34Total cost for 10.00 sqm Rs: 6875.34Rate per sqm (A+B+C+D)/10.0 Rs. 687.50
IRR-CCDW-5-4
cleaning surface, batching, mixing, placing in position, levelling, compacting, finishing, curing
(Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSIS UNIT : 14.67 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement for mix kg 4401.00 5.50 24205.50Cement for incidentals @ 5 kg / cum kg 73.35 5.50 403.42
2 Coarse aggregate 20-10 mm cum 7.63 1025.00 7819.11Coarse aggregate 10 mm below cum 4.11 750.00 3080.70
3 Fine aggregate cum 6.60 425 2805.644 Super Plasticizer kg 17.60 54 950.625 Use rate of shuttering sqm 80.69 197.64 15946.816 Sundries sqm 1.00 33 33.00
Add seignorage charges on Stone @(Included in material rate) Rs: 0.00Add seignorage charges on Sand @ (Included in material rate) Rs: 0.00
Total cost of Materials Rs: 55244.80
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40
Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20
Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80
Fuel / Energy charges Hour 1.00 233.90 233.90Total hire charges of Machinery Rs: 1408.45
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor
for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00
Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N /sqmm ) grade cement concrete using 20 mm down size approved clean, hard, gradedaggregates for coping slab including cost of all materials, machinery, labour, formwork,
etc., complete with initial lead upto 50 m and initial lift upto 3 m.
IRR-CCDW
270
for laying and tamping Day 3.00 215.00 645.00for conveying concrete Day 14.67 215.00 3154.05for cleaning/ washing/ curing Day 1.00 215.00 215.00
7 Labour cost for shuttering/scaffolding sqm 80.69 55.65 4490.12Total cost of Labour Rs: 13564.62
labour component/unit qty 924.70Add contractor's profit and overhead charges 0.14 129.50labour component/unit qty (including contractor's profit) 1054.20
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 55244.80B. Hire charges of Machinery Rs: 1408.45C. Cost of Labour Rs: 13564.62
Total Rs: 70217.87D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 9830.5Total cost for 14.67 cum Rs: 80048.37Rate per cum (A+B+C+D)/14.67 Rs. 5456.60
IRR-CCDW-5-5 Providing and constructing protective railing consisting of in-situ railing posts of size 15 x15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre to centre in M-20 gradeconcrete using 20 mm down size graded aggregates and with each post reinforced by 4 Nos.of 8 mm dia main bars embedded in kerb concrete for a depth of 40 cm and 5 Nos. of 6 mmdia. stirrups including fixing 3 rows of 40 mm dia. GI pipes with one coat of red oxide primerand two coats of synthetic enamel paint, cost of all materials, machinery, labour, formwork,finishing, curing etc., complete with lead upto 50 m and all lifts.
DATA: RATE ANALYSIS UNIT : 10.00 RmA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 30.00 5.50 165.002 20-10 mm coarse aggregate cum 0.04 1025.00 41.003 10-4.75 mm coarse aggregate cum 0.02 750.00 15.004 Fine aggregate cum 0.04 425 17.005 Reinforcement steel kg 16.39 41.00 671.996 40 mm dia GI pipes B class Rm 30.00 189 5670.007 Use rate of shuttering sqm 3.00 197.64 592.938 Sundries ( paints/ binding wire etc ) LS 4.00 33 132.00
Add seignorage charges on Stone @ (Included in material rate) Rs: 0.00Add seignorage charges on Sand @(Included in material rate) Rs: 0.00
Total cost of Materials Rs: 7304.92
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nill 0.00 0.00 0.00
0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Class I Day 0.50 285.00 142.502 Bar bender Day 0.50 300.00 150.003 work inspector Day 0.50 275.00 137.504 mazdoor Day 1.50 215.00 322.505 Painter Cl- II Day 0.50 260.00 130.006 Fitter shuttering Day 0.50 260.00 130.00
Total cost of Labour Rs: 1012.50labour component/unit qty 101.30Add contractor's profit and overhead charges 0.14 14.20labour component/unit qty (including contractor's profit) 115.50
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 7304.92B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1012.50
Total Rs: 8317.42D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1164.44
IRR-CCDW
271
Total cost for 10.00 Rm Rs: 9481.858529Rate per Rm (A+B+C+D)/10.0 Rs. 948.20
IRR-CCDW-6 HUME PIPE LAYING & JOINTING WORKS :
IRR-CCDW-6-1proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)
DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 99.00 5.50 544.502 Sand screened cum 0.10 425 42.503 Hemp yarn kg 0.91 60 54.60
Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 641.60
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- II Day 2.00 260.00 520.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 3.00 215.00 645.00
Total cost of Labour Rs: 1440.00labour component/unit qty 144.00Add contractor's profit and overhead charges 0.14 20.20labour component/unit qty (including contractor's profit) 164.20
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 641.60B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1440.00
Total Rs: 2081.60D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 291.42Total cost for 10.00 Joints Rs: 2373.02Rate per joint (A+B+C+D)/10.0 Rs. 237.30
Note:
IRR-CCDW-6-2proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)
DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 174.00 5.50 957.002 Sand screened cum 0.22 425 93.503 Hemp yarn kg 1.27 60 76.20
Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 1126.70
B. MACHINERY:
Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
IRR-CCDW
272
Sl No Description Unit Quantity Rate Amountin Rs. in Rs.
1 Nill 0.00 0.00 0.00( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- II Day 2.00 260.00 520.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 3.00 215.00 645.00
Total cost of Labour Rs: 1440.00labour component/unit qty 144.00Add contractor's profit and overhead charges 0.14 20.20labour component/unit qty (including contractor's profit) 164.20
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 1126.70B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1440.00
Total Rs: 2566.70D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 359.34Total cost for 10.00 Joints Rs: 2926.04Rate per joint (A+B+C+D)/10.0 Rs. 292.60
Note:
IRR-CCDW-6-3proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
IRR-CCDW
273
DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 248.00 5.50 1364.002 Sand screened cum 0.25 425 106.253 Hemp yarn kg 2.20 60 132.00
Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 1602.25
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- II Day 2.50 260.00 650.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 4.00 215.00 860.00
Total cost of Labour Rs: 1785.00labour component/unit qty 178.50Add contractor's profit and overhead charges 0.14 25.00labour component/unit qty (including contractor's profit) 203.50
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 1602.25B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1785.00
Total Rs: 3387.25D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 474.22Total cost for 10.00 Joints Rs: 3861.47Rate per joint (A+B+C+D)/10.0 Rs. 386.10
Note:
IRR-CCDW-6-4proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint)
DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 321.00 5.50 1765.502 Sand screened cum 0.31 425 131.753 Hemp yarn kg 2.50 60 150.00
Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 2047.25
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- II Day 2.50 260.00 650.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 4.00 215.00 860.00
Total cost of Labour Rs: 1785.00
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 700 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
IRR-CCDW
274
labour component/unit qty 178.50Add contractor's profit and overhead charges 0.14 25.00labour component/unit qty (including contractor's profit) 203.50
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2047.25B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1785.00
Total Rs: 3832.25D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 536.52Total cost for 10.00 Joints Rs: 4368.77Rate per joint (A+B+C+D)/10.0 Rs. 436.90
Note:
IRR-CCDW-6-5proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)
DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 396.00 5.50 2178.002 Sand screened cum 0.39 425 165.753 Hemp yarn kg 3.10 60 186.00
Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 2529.75
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- II Day 3.00 260.00 780.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 5.00 215.00 1075.00
Total cost of Labour Rs: 2130.00labour component/unit qty 213.00Add contractor's profit and overhead charges 0.14 29.80labour component/unit qty (including contractor's profit) 242.80
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2529.75B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 2130.00
Total Rs: 4659.75D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 652.37Total cost for 10.00 Joints Rs: 5312.12Rate per joint (A+B+C+D)/10.0 Rs. 531.20
Note:
IRR-CCDW-6-6proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)
DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 900 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
IRR-CCDW
275
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 446.00 5.50 2453.002 Sand screened cum 0.45 425 191.253 Hemp yarn kg 3.40 60 204.00
Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 2848.25
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- II Day 3.00 260.00 780.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 5.00 215.00 1075.00
Total cost of Labour Rs: 2130.00labour component/unit qty 213.00Add contractor's profit and overhead charges 0.14 29.80labour component/unit qty (including contractor's profit) 242.80
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2848.25B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 2130.00
Total Rs: 4978.25D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 696.96Total cost for 10.00 Joints Rs: 5675.21Rate per joint (A+B+C+D)/10.0 Rs. 567.50
Note:
IRR-CCDW-6-7proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)
DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 495.00 5.50 2722.502 Sand screened cum 0.50 425 212.503 Hemp yarn kg 3.77 60 226.20
Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 3161.20
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- II Day 3.00 260.00 780.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 6.00 215.00 1290.00
Total cost of Labour Rs: 2345.00labour component/unit qty 234.50Add contractor's profit and overhead charges 0.14 32.80
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 1000 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
IRR-CCDW
276
labour component/unit qty (including contractor's profit) 267.30
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 3161.20B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 2345.00
Total Rs: 5506.20D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 770.87Total cost for 10.00 Joints Rs: 6277.07Rate per joint (A+B+C+D)/10.0 Rs. 627.70
Note:
IRR-CCDW-6-8proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto50 m and all lifts.(Cement content: 56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)
DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Cement kg 569.00 5.50 3129.502 Sand screened cum 0.58 425 246.503 Hemp yarn kg 4.15 60 249.00
Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 3625.00
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- II Day 3.00 260.00 780.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 6.00 215.00 1290.00
Total cost of Labour Rs: 2345.00labour component/unit qty 234.50Add contractor's profit and overhead charges 0.14 32.80labour component/unit qty (including contractor's profit) 267.30
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 3625.00B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 2345.00
Total Rs: 5970.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 835.8Total cost for 10.00 Joints Rs: 6805.8Rate per joint (A+B+C+D)/10.0 Rs. 680.60
Note:
IRR-CCDW-6-9proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)
DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amount
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 1100 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 1200 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
IRR-CCDW
277
in Rs. in Rs.1 Cement kg 668.00 5.50 3674.002 Sand screened cum 0.69 425 293.253 Hemp yarn kg 4.53 60 271.80
Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 4239.05
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- II Day 4.00 260.00 1040.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 7.00 215.00 1505.00
Total cost of Labour Rs: 2820.00labour component/unit qty 282.00Add contractor's profit and overhead charges 0.14 39.50labour component/unit qty (including contractor's profit) 321.50
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 4239.05B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 2820.00
Total Rs: 7059.05D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 988.27Total cost for 10.00 Joints Rs: 8047.32Rate per joint (A+B+C+D)/10.0 Rs. 804.70
Note:
IRR-CCDW-7 BACK FILLING & OTHER WORKS :
IRR-CCDW-7-1including cost of all materials, machinery, labour, watering, ramming etc., complete with initiallead upto 50 m and initial lift upto 3 m.
DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Rubble / Boulder cum 10.00 265 2650.002 Sand unscreened cum 4.00 325 1300.00
Add seignorage charges on Stone@ Rs(Included in material ra Rs: 0.00Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00
Total cost of Materials Rs: 3950.00
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nill 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 work inspector Day 0.50 275.00 137.502 Mason Cl II Day 1.00 260.00 260.003 mazdoor Day 4.00 215.00 860.00
Total cost of Labour Rs: 1257.50labour component/unit qty 125.80Add contractor's profit and overhead charges 0.14 17.60labour component/unit qty (including contractor's profit) 143.40
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Providing rubble / boulder and sand filling behind abutment and return walls in layers
IRR-CCDW
278
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 3950.00B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1257.50
Total Rs: 5207.50D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 729.05Total cost for 10.00 cum Rs: 5936.55Rate per cum (A+B+C+D)/10.0 Rs. 593.70
IRR-CCDW-7-2including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by earth
upto 50 m and all lifts.
DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Murum cum 12.00 80 960.000.00 0.00 0.00
Add seignorage charges on Soil @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 960.00
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Nill 0.00 0.00 0.00
0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Cartman with double bullock cart Day 0.50 305.00 152.502 work inspector Day 0.50 275.00 137.503 mazdoor Day 6.00 215.00 1290.00
Total cost of Labour Rs: 1580.00labour component/unit qty 158.00Add contractor's profit and overhead charges 0.14 22.10labour component/unit qty (including contractor's profit) 180.10
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 960.00B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1580.00
Total Rs: 2540.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 355.6Total cost for 10.00 cum Rs: 2895.6Rate per cum (A+B+C+D)/10.0 Rs. 289.60
IRR-CCDW-7-3including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by power
50 m and all lifts.
DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 Murum cum 12.00 80 960.000.00 0.00 0.00
Add seignorage charges on Soil @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 960.00
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
Providing and filling murrum / gravely soil ( CNS soil ) for foundation or around pipes
masters to achieve density control of not less than 95 percent etc., complete with lead
Providing and filling murum / gravely soil ( CNS soil ) for foundation or above pipes
roller to achieve density control of not less than 98 percent etc., complete with lead upto
IRR-CCDW
279
in Rs. in Rs.1 Diesel road roller 8-10 tonne Hour 0.17 151.50 25.85
Fuel / Energy charges Hour 0.17 556.90 95.03Total hire charges of Machinery Rs: 120.89
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Operator road roller Hour 0.17 136.00 23.212 Cartman with double bullock cart Day 0.50 305.00 152.50
IRR-CCDW
280
3 work inspector Day 0.50 275.00 137.504 mazdoor Day 1.50 215.00 322.50
Total cost of Labour Rs: 635.71labour component/unit qty 63.60Add contractor's profit and overhead charges 0.14 8.90labour component/unit qty (including contractor's profit) 72.50
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 960.00B. Hire charges of Machinery Rs: 120.89C. Cost of Labour Rs: 635.71
Total Rs: 1716.60D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 240.32Total cost for 10.00 cum Rs: 1956.91556314Rate per cum (A+B+C+D)/10.0 Rs. 195.70
IRR-CCDW-7-4
size 70x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats syntheticenamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
DATA: RATE ANALYSIS UNIT : 4 Nos.A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 One line dressed Km stone No. 4.00 340 1360.002 40-20 mm coarse aggregate cum 0.20 975.00 195.003 20-10 mm coarse aggregate cum 0.15 1025.00 153.754 10-4.75 mm coarse aggregate cum 0.10 750.00 75.005 Sand screened cum 0.20 425 85.006 Cement kg 100.00 5.50 550.007 Synthetic enamel paint I st quality ltr 1.00 184.00 184.008 Sundries ( brush / oil etc ) LS 4.00 33 132.00
Add seignorage charges on Stone @ (Included in material ra Rs: 0.00Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 2734.75
B. MACHINERY:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 NIL 0.00 0.00 0.00
( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00
C. LABOUR:Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.1 Mason Cl- II Day 1.00 260.00 260.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 1.00 215.00 215.004 Painter Cl- I Day 1.00 300.00 300.00
Total cost of Labour Rs: 1050.00labour component/unit qty 262.50Add contractor's profit and overhead charges 0.14 36.80labour component/unit qty (including contractor's profit) 299.30
ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2734.75B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1050.00
Total Rs: 3784.75D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 529.87Total cost for 4.00 Nos. Rs: 4314.62Rate per No. (A+B+C+D)/4.0 Rs. 1078.70
IRR-CCDW-7-5
size 50x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats syntheticenamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
Providing and fixing one line dressed 111x35x25 cm thick IRC standard kilometre stone incement concrete M-10 grade with 40 mm down size aggregates including excavating pit of
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Providing and fixing one line dressed 65x15x10 cm thick IRC standard hectometre stone incement concrete M-10 grade with 40 mm down size aggregates including excavating pit of
IRR-CCDW
281
DATA: RATE ANALYSIS UNIT : 4 Nos.A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.
1 One line dressed hectometre stone No. 4.00 180 720.002 40-20 mm coarse aggregate cum 0.20 975.00 195.003 20-10 mm coarse aggregate cum 0.15 1025.00 153.754 10-4.75 mm coarse aggregate cum 0.10 750.00 75.005 Sand screened cum 0.20 425 85.006 Cement kg 100.00 5.50 550.007 Synthetic enamel paint I st quality ltr 0.40 184.00 73.608 Sundries ( brush / oil etc ) LS 1.00 33 33.00
Add seignorage charges on Stone @ (Included in material ra Rs: 0.00Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00
Total cost of Materials Rs: 1885.35B. MACHINERY:
Sl No Description Unit Quantity Rate Amountin Rs. in Rs.
1 NIL 0.00 0.00 0.00( Manual mixing ) 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00C. LABOUR:
Sl No Description Unit Quantity Rate Amountin Rs. in Rs.
1 Mason Cl- II Day 1.00 260.00 260.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 1.00 215.00 215.004 Painter Cl- I Day 0.50 300.00 150.00
Total cost of Labour Rs: 900.00labour component/unit qty 225.00Add contractor's profit and overhead charges 0.14 31.50labour component/unit qty (including contractor's profit) 256.50ABSTRACT:A. Cost of Materials including seignorage charges Rs: 1885.35B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 900.00
Total Rs: 2785.35D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 389.95Total cost for 4.00 Nos. Rs: 3175.3Rate per No. (A+B+C+D)/4.0 Rs. 793.80
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
CHAPTER-IV
CANAL CROSS DRAINAGE WORKS
(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)
FOR THE YEAR :2011-12Index- code
IRR-CCDW CANAL CROSS DRAINAGE WORKS - DATA RATES
IRR-CCDW-1 EXCAVATION & FOUNDATION TREATMENT WORKS :
IRR-CCDW-1-1
50 m and initial lift upto 3 m.
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 NIL
Total cost of Materials
B. MACHINERY:Sl No Description
1 NIL
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 work inspector2 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials
Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundations of canalcross drainage and other appurtenant structures and placing the excavated stuff neatly inspecified dump area or disposing off the same as directed etc., complete with initial lead upto
B. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-1-2 Excavation for Structures- Mechanical Means
including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.Depth upto 3 m
Unit = cumDATA: Taking output = 240 cum
a) LabourSl No Description
1 work inspector2 Mazdoor
Total in Rs.
b)MachinerySl No Description
1 Hydraulic excavator 1.0 cum bucket capacity Fuel/ Energy chargescrew for excavatorTotal in Rs.
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
Abstracta) Labourb) Machineryc) MaterialTotal
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-1-3
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification,
Excavation in ordnary rock (including HDR) without blasting including boulders above 0.3 m upto 0.60 m dia.for foundations of canal cross drainage and other appurtenant structures and placing the
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 NIL
Total cost of Materials
B. MACHINERY:Sl No Description
1 NIL
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crowbarman2 Stone breaker3 work inspector4 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of MaterialsB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-1-4and other appurtenant structures and placing the excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial
( Data adopted from MORTH) Mechanical MeansUnit = cum
DATA: Taking output = 180 cuma) Labour
complete with initial lead upto 50 m and initial lift upto 3 m.
Excavation in ordnary rock without blasting for foundations of canal cross drainage
lead upto 50 m and initial lift upto 3 m.
Sl No Description
1 work inspector2 Mazdoor
Total in Rs.
b) MachinerySl No Description
1.0 Hydraulic excavator 1.0 cum bucket capacity Fuel/ Energy chargescrew for excavatorTotal in Rs.
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
Abstract a) Labour b) Machinery c) Material
Total D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-1-5
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
DATA:RATE ANALYSIS
A. MATERIALS:Sl No Particulars
1 Use rate of drill rod 1.6 m lengthReconditioning charges @
2 Use rate of air hose 2 Nos.3 Explosive small dia ( Kelvex-220 )4 Electric detonators5 Detonating fuse coil6 Sundries
Total cost of Materials
B. MACHINERY:Sl No Description
Excavation in hard rock requiring blasting including boulders above 0.6 m upto 1.2 m dia. forfoundations of canal cross drainage and other appurtenant structures and placing the
complete with initial lead upto 50 m and initial lift upto 3 m.
1 Air compressor 8.5 cmm ( diesel )Fuel / Energy charges
2 Jack hammers 2 Nos.Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Air compressor2 Crew for Jack hammer3 work inspector4 Blaster5 Helper blaster6 Crowbarman7 Stone breaker8 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of MaterialsB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-1-6
excavated rock neatly in specified dump area or stack yard as directed etc., complete with
DATA:
RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Explosive small dia ( Kelvex-220 )2 Ordinary detonator3 Electric detonator4 Detonating fuse coil5 Use rate of air hose 2 Nos.
Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. forfoundations of canal cross drainage and other appurtenant structures and placing the
initial lead upto 50 m and initial lift upto 3 m.
6 Use rate of drill rodReconditioning charges @
Total cost of Materials
B. MACHINERY:Sl No Description
1 Air compressor 8.5 cmm ( diesel )Fuel / Energy charges
2 Jack hammer 2 NosFuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Air compressor2 Crew for Jack hammer3 Blaster licensed4 Helper blasting5 work inspector6 Crowbarman7 Stone breaker8 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of MaterialsB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-1-7and other appurtenant structures and placing the excavated rock neatly in
initial lift upto 3 m.Hard Rock ( blasting prohibited )Unit = cum
DATA: Taking output = 10 cumMechanical Meansa) Labour
Excavation in hard rock with blasting prohibited for foundations of canal cross drainage
or stack yard as directed etc., complete with specified dump area initial lead upto 50 m and
Sl No Description
1 work inspector2 Mazdoor
Total in Rs.
b) MachinerySl No Description
1.0
Fuel/ Energy chargescrew for compressorTotal in Rs.
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
Abstracta) Labourb) Machineryc) Material
Total D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-1-81.25 m length driven into 32 mm dia hole drilled in bed rock and remaining length embedded inconcrete / masonry including cost of all materials, machinery, labour, drilling and cleaning
upto 50 m and all lifts.DATA:
RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for grouting2 25 mm dia steel3 Use rate of 32 mm dia drill rod
Reconditioning charges @ 4 Use rate of air hose
Total cost of Materials
B. MACHINERY:
Air Compressor 250 cft with 2 leads of pneumatic breaker
Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel anchor rods with
hole, driving anchor rod, grouting hole with thick cement slurry etc., complete with initial lead
Sl No Description
1 Air compressor 8.5 cmm ( diesel )Fuel / Energy charges
2 Jack hammer 2 NosFuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Air compressor2 Crew for Jack hammer3 Mason Class-II4 Bar bender5 work inspector6 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of MaterialsB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per each
IRR-CCDW-2 STEEL AND CEMENT CONCRETE WORKS :
IRR-CCDW-2-1cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,
DATA:
RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Rein.Steel with 5 % wastage2 Binding wire 1.25 mm dia3 Sundries ( chairs / spacers etc )
Total cost of Materials
Providing, fabricating and placing in position reinforcement steel bars for RCC works including
complete with initial lead upto 50 and all lifts.
B. MACHINERY:Sl No Description
1 Nil
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 work inspector2 Bar bender3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of MaterialsB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per kg
IRR-CCDW-2-2100 x 10 mm angle and 250 x 12 mm plate for sinking for sinking 4.50 m outer diameter foundation wells foundation wells including cost of all materials, machinery, labour, bending, welding, providing anchors etc., complete with initial lead upto 50 m and all lifts.
DETAILS OF FOUNDATION WELL CUTTING EDGE
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Str.Steel angle with 2.5 % wastage2 Str.Steel plate with 2.5 % wastage3 Steel for anchors4 Acetyline gas5 Oxygen gas6 Welding electrodes7 Sundries
Providing, fabricating and fixing in position structural steel cutting edge consisting of 100 x
Total cost of Materials
B. MACHINERY:Sl No Description
1 Bending machineFuel / Energy charges
2 Welding setFuel / Energy charges
3 SundriesTotal hire charges of Machinery
C. LABOUR:Sl No Description
1 Str. Steel fabricator2 Welder / Gas cutter3 work inspector4 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of MaterialsB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per kg
IRR-CCDW-2-3
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Data RATE ANALYSISA. MATERIALS:
Sl No Particulars
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,
complete with initial lead upto 50 m and all lifts.
1 Cement for mixCement for incidentals @ 3 kg / cum
2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses
Scaffolding @ of shuttering6 Sundries
Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Water tanker 8000 ltrFuel / Energy charges
4 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Needle vibrator5 work inspector6 Mason Class-I7 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
8 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-4
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
DATA:
RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 3 kg / cum
2 Coarse aggregate 80-40 mmCoarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses
Scaffolding @ of shuttering6 Sundries
Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 600/400 ltr ( diesel)Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Water tanker 8000 ltrFuel / Energy charges
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,
complete with initial lead upto 50 m and all lifts.
4 Needle vibrator 60 mm dia ( petrol)Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Needle vibrator5 Mason Class-I6 work inspector7 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
8 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-5
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSISA. MATERIALS:
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,
complete with initial lead upto 50 m and all lifts.
Sl No Particulars
1 Cement for mixCement for incidentals @ 3 kg / cum
2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses
Scaffolding @ of shuttering6 Sundries
Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Water tanker 8000 ltrFuel / Energy charges
4 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concrete
8 for cleaning/ washing/ curing9 Labour cost for shuttering
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-6
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 3 kg / cum
2 Coarse aggregate 80-40 mmCoarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses
Scaffolding @ of shuttering6 Sundries
Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 600/400 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Water tanker 8000 ltr
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,
complete with initial lead upto 50 m and all lifts.
Fuel / Energy charges4 Needle vibrator 60 mm dia ( petrol )
Fuel / Energy chargesTotal hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
8 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-7
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 310 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSIS
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,
complete with initial lead upto 50 m and all lifts. ( Cement content : 220 kg / cum )
A. MATERIALS:Sl No Particulars
1 Cement for mixCement for incidentals @ 3 kg / cum
2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses
Scaffolding @ of shuttering6 Sundries
Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Water tanker 8000 ltrFuel / Energy charges
4 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
8 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labour
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-8
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering
Scaffolding @ of shuttering6 Sundries
Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Fuel / Energy charges3 Water tanker 8000 ltr
Fuel / Energy charges4 Needle vibrator 40 mm dia ( petrol )
Fuel / Energy chargesTotal hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor
for batching materialsfor loading mortar pansfor laying including liftingfor conveying concretefor cleaning/ washing/ curing
8 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-9
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering
Scaffolding @ of shuttering6 Sundries
Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Water tanker 8000 ltrFuel / Energy charges
4 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
8 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labour
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-10
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses
Scaffolding @ of shuttering6 SundriesAdd seignorage charges on CA @ (included in material rate)
Add seignorage charges on FA @ (included in material rate) Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
3 Water tanker 8000 ltrFuel / Energy charges
4 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
8 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-11
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses
Scaffolding @ of shuttering6 Sundries
Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Water tanker 8000 ltrFuel / Energy charges
4 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
8 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labour
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-12
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mix2 Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below3 Fine aggregate4 Super Plasticizer5 Use rate of curved shutter (40 uses)6 Sundries
Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for well kerb including cost of all materials, machinery, labour, formwork,
etc., complete with initial lead upto 50 m and all lifts.
3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
7 Labour cost for shutteringTotal cost of Labour
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
ra20hcux1/ctl 2011
IRR-CCDW-2-13
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for well steining including cost of all materials, machinery, labour, formwork,
etc., complete with initial lead upto 50 m and all lifts.
1 Cement for mixCement for incidentals @ 2 kg / cum
2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of curved shutter (40 uses)6 Sundries
Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
7 Labour cost for shutteringTotal cost of Labour
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-14
machinery, labour, batching, mixing, placing in position as per detailed specifications etc.,
(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mix2 Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below3 Fine aggregate4 Super Plasticizer
Add for tremie arrangement @Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Sundries( Hopper etc. )Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Fitter shuttering4 work inspector
Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N / sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for well bottom plug by tremie or skip box method including cost of all materials,
complete with initial lead upto 50 m and all lifts. ( Cement content : 350 kg / cum )
5 mazdoorfor erecting/ dismantling tremiefor batching materialsfor loading mortar pansfor feeding tremie hopperfor conveying concrete
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-15
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mix2 Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer
Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for well top plug including cost of all materials, machinery, labour, cleaning,
initial lead upto 50 m and all lifts.
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-16
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for well cap including cost of all materials, machinery, labour, formwork,
etc., complete with initial lead upto 50 m and all lifts.
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of curved shutter (40 uses)6 Sundries
Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
7 Labour cost for shutteringTotal cost of Labour
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-17
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curingetc., complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 80-40 mmCoarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses6 Scaffolding @ of shuttering
Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 600/400 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 60 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for piers and abutments including cost of all materials, labour, machinery,
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
7 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-18
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mix
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for piers and abutments including cost of all materials, labour, machinery,
etc., complete with initial lead upto 50 m and all lifts.
Cement for incidentals @ 5 kg / cum2 Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate ofshuttering for 40 uses6 Scaffolding @ of shuttering
Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 600/400 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 60 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
7 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-19
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses6 Scaffolding @ of shuttering
Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for piers and abutments including cost of all materials, labour, machinery,
etc., complete with initial lead upto 50 m and all lifts.
2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
7 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-20
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for cantiliver / counterfort retaining walls including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses
Scaffolding @ of shuttering6 Sundries
Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
7 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost for
Rate per cum
IRR-CCDW-2-21
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum, plums of size 150 to 80 mm : 0.25cum )
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 4 kg / cum
2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Plums of size 150 to 80 mm4 Fine aggregate5 Super Plasticizer
Use rate of shuttering for 40 uses6 Scaffolding @ of shuttering
Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 60 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates with placing and sinking plums of size 150 to 80 mm upto 15 percent for gravitytype retaining walls / piers / abutments etc., including cost of all materials, machinery,
finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor placing plumsfor conveying concretefor conveying plumsfor cleaning/ washing/ curing
7 Labour for shutteringLabour for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-22
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 40-20 mm
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,gradedaggregates for cast in-situ pipes including cost of all materials, machinery, labour, cleaning,
initial lead upto 50 m and all lifts.
Coarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses
Scaffolding @ of shuttering6 Sundries
Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
7 Labour for shutteringLabour for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-23
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 80-40 mmCoarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses6 Scaffolding @ of shuttering
Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 600/400 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 60 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for cast in-situ pipes including cost of all materials, labour, machinery, formwork,
complete with initial lead upto 50 m and all lifts.
2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
7 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-24
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for deck slab & kerb including cost of all materials,machinery, labour, formwork,
etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 300 kg / cum )
5 Use rate of shuttering for 30 usesScaffolding @ of shuttering
6 SundriesAdd seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
7 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-25
formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
kg / cum )Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering
Scaffolding @ of shuttering6 Sundries
Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for columns and beams including cost of all materials, labour, machinery,
finishing, curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content : 300
6 mazdoorfor batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
7 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-26
cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering6 Sundries ( asphalt mortar etc )
Add seignorage charges on CA @
Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for wearing coat including cost of all materials, machinery, labour, formwork,
finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 mand all lifts. ( Cement content : 300 kg / cum )
Add seignorage charges on FA @ Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
7 Labour cost for shutteringTotal cost of Labour
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-2-27 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for troughs including cost of all materials, machinery, labour, formwork,
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses
Scaffolding @ of shuttering6 Sundries
Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Needle vibrator 40 mm dia ( diesel )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing
etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 300 kg / cum )
7 Labour cost for shutteringLabour cost for scaffolding @
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-3 FOUNDATION WELL SINKING WORKS :
IRR-CCDW-3-1DATA: Unit = Running meter
Taking output = 1mdiameter of well = 6.00m
(i) Depth below bed level upto 3.0mRate of sinking = 0.50 m /hour
a) Labour0.12 Mate (Mason Cl- ll )1.00 Sinker ( skilled)2.00 Sinking helper ( Semi skilled)
sub total (a)b) Machinery
2.00 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.Fuel Charges Crew ChargesConsumables in sinking @ 10% of machinery charges
sub total (b)sub total (a+b)
Rate per metre = (a+b+c)/1.0or say ( Rate upto 3.0m for 6.0 m well sinking )labour component/unit qtyContractor's profit and overhead charges
Sinking RCC wells vertically for foundation of piers and abutments in all kinds of soil, sand and soft rock by approved well sinking method including cost of all materials, machinery, labour, kent - ledge arrangements, disposal of excavated material as directed etc., complete with lead upto 50 m for disposal of excavated material.(diameter of well 6.00m)
c) Add for Contractor's profit and overhead charges on (A+B)
labour component/unit qty(including contractor's profit)
(ii) Beyond 3m and upto 10m depthRate of sinking = 0.33 m per hour.
a) Labour0.15 Mate (Mason Cl- ll )1.25 Sinker ( skilled)2.50 Sinking helper ( Semi skilled)
sub total (a)b) Machinery
3.00 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.Fuel Charges Crew ChargesConsumables in sinking @ 10% of machinery charges
sub total (b)sub total (a+b)
Rate per metre = (a+b+c)or say ( Rate for 3.0m to 10m well sinking )
labour component/unit qtyContractor's profit and overhead chargeslabour component/unit qty(including contractor's profit)
IRR-CCDW-3-2ramming as directed including cost of all materials, machinery, labour etc., complete with
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Sand unscreened
Add seignorage charges on Sand @ Rs:Total cost of Materials
B. MACHINERY:Sl No Description
1 Nill
c) Add for Contractor's profit and overhead charges on (A+B)
Filling foundation wells with sand in layers of 25 to 30 cm and compacting by watering,
initial lead upto 50 m and all lifts.
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 work inspector2 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-4 MASONRY WORKS :
IRR-CCDW-4-1
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,Stone Chips : 0.15 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Rubble stones3 Stone chips4 Sand screened
Add seignorage charges on Stone@ RsAdd seignorage charges on Sand @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Water tanker 8000 ltr
Providing and constructing un-coursed rubble stone masonry with approved stones inCM 1 : 4 proportion for sub-structure portions of return walls / abutments etc., including
stone chips, curing etc., complete with initial lead upto 50 m and all lifts.
Fuel / Energy charges2 5 hp pump ( diesel )
Fuel / Energy chargesTotal hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Water tanker2 Crew for Pump3 work inspector4 Mason Class-I5 Mason Class-II6 mazdoor
for conveying rubble stonesfor preparing mortarfor loading mortar pansfor laying & packing mortarfor washing rubble / finishing / curingfor conveying mortar / chips
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-4-2
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,Stone Chips : 0.15 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
Providing and constructing un-coursed rubble stone masonry with approved stones inCM 1 : 4 proportion for super-structure portions of return walls / abutments etc., including
stone chips, curing etc., complete with initial lead upto 50 m and all lifts.
1 Cement2 Rubble stones3 Stone chips4 Sand screened
Add for scaffolding @Add seignorage charges on Stone@ RsAdd seignorage charges on Sand @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Water tanker 8000 ltrFuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Water tanker2 Crew for Pump3 work inspector4 Mason Class-I5 Mason Class-II6 mazdoor
for conveying rubble stonesfor preparing mortarfor loading mortar pansfor laying & packing mortarfor washing rubble / finishing / curingfor conveying mortar / chips
Add for labour for scaffolding @Total cost of Labour
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost for
Rate per cum
IRR-CCDW-4-3stones from approved source including cost of all materials, machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with
(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones 25 x 25x 45 cm : 60 Nos)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Header stones 25x25x45 cm3 Khandki stones 25x25x30 cm4 Rubble stones5 Stone chips6 Sand screened
Add for scaffolding materials @Add seignorage charges on Stone@ RsAdd seignorage charges on Sand @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Water tanker 8000 ltrFuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Water tanker2 Crew for Pump3 work inspector4 Stone chiseller Cl -II5 Mason Class-I6 Mason Class-II7 mazdoor
for conveying stones / rubblefor preparation of mortar
Providing and constructing coursed rubble masonry second sort in CM 1:4 proportion with
initial lead upto 50 m and initial lift upto 3m.
for loading mortar pansfor laying & packing mortarfor washing rubble / finishing / curingfor conveying mortar / chips
Add for labour for scaffolding @Total cost of Labour
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-4-4 Providing and constructing coursed rubble masonry first sort in CM 1:4 proportion withstones from approved source including cost of all materials, machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete withinitial lead upto 50 m and initial lift upto 3 m.(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones 25 x 25x 45 cm : 60 Nos)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Header stones 25x25x45 cm3 Khandki stones 25x25x30 cm4 Rubble stones5 Stone chips6 Sand screened
Add for scaffolding materials @Add seignorage charges on Stone@ RsAdd seignorage charges on Sand @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Water tanker 8000 ltrFuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Water tanker2 Crew for Pump3 work inspector4 Stone chiseller Cl -II5 Mason Class-I6 Mason Class-II7 mazdoor8 for conveying rubble/ stones
for preparation of mortarfor loading mortar pansfor laying & packing mortarfor washing rubble / finishing / curingfor conveying mortar / chips
Add for labour for scaffolding @Total cost of Labour
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-4-5proportion by volume including raking and cleaning joints for 50 mm depth, pressing cementmortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
DATA: RATE ANALYSISA. MATERIALS:
Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 2
initial lead upto 50 m and all lifts.
Sl No Particulars
1 Cement2 Sand screened
Add for scaffolding / ramps etc @Add seignorage charges on Sand @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Nil( Manual mixing)
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- I2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm
IRR-CCDW-4-6proportion by volume including raking and cleaning joints for 50 mm depth, pressing cementmortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement
Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 3
initial lead upto 50 m and all lifts.
2 Sand screened
Add for scaffolding / ramps etc @Add seignorage charges on Sand @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Nil( Manual mixing)
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- I2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm
IRR-CCDW-4-7of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened
Add for scaffolding / ramps etc @Add seignorage charges on Sand @ Rs
Providing 12 mm thick plastering in cement mortar 1:3 proportion by volume including cost
complete with initial lead upto 50 m and all lifts.
Total cost of Materials
B. MACHINERY:Sl No Description
1 Nil( Manual mixing)
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- I2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm
IRR-CCDW-4-8of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened
Add for scaffolding / ramps etc @Add seignorage charges on Sand @ Rs
Total cost of Materials
B. MACHINERY:
Providing 12 mm thick plastering in cement mortar 1:4 proportion by volume including cost
complete with initial lead upto 50 m and all lifts.
Sl No Description
1 Nil( Manual mixing)
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- I2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm
IRR-CCDW-4-9of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened
Add for scaffolding / ramps etc @Add seignorage charges on Sand @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Nil
Providing 20 mm thick plastering in cement mortar 1:3 proportion by volume including cost
complete with initial lead upto 50 m and all lifts.
( Manual mixing)Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- I2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm
IRR-CCDW-4-10of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened
Add for scaffolding / ramps etc @Add seignorage charges on Sand @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Nil( Manual mixing)
Total hire charges of Machinery
Providing 20 mm thick plastering in cement mortar 1:4 proportion by volume including cost
complete with initial lead upto 50 m and all lifts.
C. LABOUR:Sl No Description
1 Mason Cl- I2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm
IRR-CCDW-5 COPING & RAILING WORKS :
IRR-CCDW-5-1
50 m and all lifts.(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened3 Burnt stone slab 10 cm thick
Add seignorage charges on Stone @ RsAdd seignorage charges on Sand @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Nil( Manual mixing)
Total hire charges of Machinery
Providing and fixing 10 cm thick roughly dressed burnt stone slabs for coping set inCM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume includingcost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
C. LABOUR:Sl No Description
1 Mason Cl- II2 Stone chiseller Cl- II3 work inspector4 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm
IRR-CCDW-5-2CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
50 m and all lifts.(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened3 Burnt stone slab 10 cm thick
Add seignorage charges on Stone @ RsAdd seignorage charges on Sand @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Nil( Manual mixing)
Total hire charges of Machinery
Providing and fixing 10 cm thick one line dressed burnt stone slabs for coping set in
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
C. LABOUR:Sl No Description
1 Mason Cl- II2 Stone chiseller Cl- I3 work inspector4 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm
IRR-CCDW-5-3
50 m and all lifts.(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened3 Burnt stone slab 10 cm thick
Add seignorage charges on Stone @ RsAdd seignorage charges on Sand @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Nil( Manual mixing)
Total hire charges of Machinery
Providing and fixing 10 cm thick two line dressed burnt stone slabs for coping set inCM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume includingcost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
C. LABOUR:Sl No Description
1 Mason Cl- II2 Stone chiseller Cl-I3 work inspector4 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm
IRR-CCDW-5-4
cleaning surface, batching, mixing, placing in position, levelling, compacting, finishing, curing
(Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement for mixCement for incidentals @ 5 kg / cum
2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below
3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering6 Sundries
Add seignorage charges on Stone @(Included in material rate) Add seignorage charges on Sand @ (Included in material rate)
Total cost of Materials
Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N /sqmm ) grade cement concrete using 20 mm down size approved clean, hard, gradedaggregates for coping slab including cost of all materials, machinery, labour, formwork,
etc., complete with initial lead upto 50 m and initial lift upto 3 m.
B. MACHINERY:Sl No Description
1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges
2 5 hp pump ( diesel )Fuel / Energy charges
3 Water tanker 8000 ltrFuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Mason Class-I5 work inspector6 mazdoor
for batching materialsfor loading mortar pansfor laying and tampingfor conveying concretefor cleaning/ washing/ curing
7 Labour cost for shuttering/scaffoldingTotal cost of Labour
labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-5-5 Providing and constructing protective railing consisting of in-situ railing posts of size 15 x15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre to centre in M-20 gradeconcrete using 20 mm down size graded aggregates and with each post reinforced by 4 Nos.of 8 mm dia main bars embedded in kerb concrete for a depth of 40 cm and 5 Nos. of 6 mmdia. stirrups including fixing 3 rows of 40 mm dia. GI pipes with one coat of red oxide primerand two coats of synthetic enamel paint, cost of all materials, machinery, labour, formwork,
finishing, curing etc., complete with lead upto 50 m and all lifts.
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 20-10 mm coarse aggregate3 10-4.75 mm coarse aggregate4 Fine aggregate5 Reinforcement steel6 40 mm dia GI pipes B class7 Use rate of shuttering8 Sundries ( paints/ binding wire etc )
Add seignorage charges on Stone @ (Included in material rate) Add seignorage charges on Sand @(Included in material rate)
Total cost of Materials
B. MACHINERY:Sl No Description
1 Nill
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Class I2 Bar bender3 work inspector4 mazdoor5 Painter Cl- II6 Fitter shuttering
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per Rm
IRR-CCDW-6 HUME PIPE LAYING & JOINTING WORKS :
IRR-CCDW-6-1proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened3 Hemp yarn
Add seignorage charges on Sand @ RsTotal cost of Materials
B. MACHINERY:Sl No Description
1 Nill( Manual mixing )
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- II2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint
Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
Note:
IRR-CCDW-6-2proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened3 Hemp yarn
Add seignorage charges on Sand @ RsTotal cost of Materials
B. MACHINERY:Sl No Description
1 Nill( Manual mixing )
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- II2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
Note:
IRR-CCDW-6-3proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened3 Hemp yarn
Add seignorage charges on Sand @ RsTotal cost of Materials
B. MACHINERY:Sl No Description
1 Nill( Manual mixing )
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- II2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
Note:
IRR-CCDW-6-4proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened3 Hemp yarn
Add seignorage charges on Sand @ RsTotal cost of Materials
B. MACHINERY:Sl No Description
1 Nill( Manual mixing )
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- II2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 700 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
Note:
IRR-CCDW-6-5proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened3 Hemp yarn
Add seignorage charges on Sand @ RsTotal cost of Materials
B. MACHINERY:Sl No Description
1 Nill( Manual mixing )
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- II2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
Note:
IRR-CCDW-6-6proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened3 Hemp yarn
Add seignorage charges on Sand @ RsTotal cost of Materials
B. MACHINERY:Sl No Description
1 Nill( Manual mixing )
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- II2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 900 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
Note:
IRR-CCDW-6-7proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened3 Hemp yarn
Add seignorage charges on Sand @ RsTotal cost of Materials
B. MACHINERY:Sl No Description
1 Nill( Manual mixing )
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- II2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 1000 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
Note:
IRR-CCDW-6-8proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto50 m and all lifts.(Cement content: 56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened3 Hemp yarn
Add seignorage charges on Sand @ RsTotal cost of Materials
B. MACHINERY:Sl No Description
1 Nill( Manual mixing )
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- II2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 1100 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
Note:
IRR-CCDW-6-9proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
50 m and all lifts.(Cement content: 66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Cement2 Sand screened3 Hemp yarn
Add seignorage charges on Sand @ RsTotal cost of Materials
B. MACHINERY:Sl No Description
1 Nill( Manual mixing )
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Mason Cl- II2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Laying and jointing 1200 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
Note:
IRR-CCDW-7 BACK FILLING & OTHER WORKS :
IRR-CCDW-7-1including cost of all materials, machinery, labour, watering, ramming etc., complete with initiallead upto 50 m and initial lift upto 3 m.
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Rubble / Boulder2 Sand unscreened
Add seignorage charges on Stone@ RsAdd seignorage charges on Sand @ Rs
Total cost of Materials
B. MACHINERY:Sl No Description
1 Nill( Manual mixing )
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 work inspector2 Mason Cl II3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class
Providing rubble / boulder and sand filling behind abutment and return walls in layers
IRR-CCDW-7-2including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by earth
upto 50 m and all lifts.
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Murum
Add seignorage charges on Soil @ RsTotal cost of Materials
B. MACHINERY:Sl No Description
1 Nill
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Cartman with double bullock cart2 work inspector3 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-7-3including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by power
Providing and filling murrum / gravely soil ( CNS soil ) for foundation or around pipes
masters to achieve density control of not less than 95 percent etc., complete with lead
Providing and filling murum / gravely soil ( CNS soil ) for foundation or above pipes
roller to achieve density control of not less than 98 percent etc., complete with lead upto
50 m and all lifts.
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 Murum
Add seignorage charges on Soil @ RsTotal cost of Materials
B. MACHINERY:Sl No Description
1 Diesel road roller 8-10 tonneFuel / Energy charges
Total hire charges of Machinery
C. LABOUR:Sl No Description
1 Operator road roller2 Cartman with double bullock cart3 work inspector4 mazdoor
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum
IRR-CCDW-7-4
size 70x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats syntheticenamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
Providing and fixing one line dressed 111x35x25 cm thick IRC standard kilometre stone incement concrete M-10 grade with 40 mm down size aggregates including excavating pit of
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 One line dressed Km stone2 40-20 mm coarse aggregate3 20-10 mm coarse aggregate4 10-4.75 mm coarse aggregate5 Sand screened6 Cement7 Synthetic enamel paint I st quality8 Sundries ( brush / oil etc )
Add seignorage charges on Stone @ Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of Materials
B. MACHINERY:Sl No Description
1 NIL( Manual mixing )
Total hire charges of MachineryC. LABOUR:
Sl No Description
1 Mason Cl- II2 work inspector3 mazdoor4 Painter Cl- I
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)
ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per No.
IRR-CCDW-7-5
size 50x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic
Providing and fixing one line dressed 65x15x10 cm thick IRC standard hectometre stone incement concrete M-10 grade with 40 mm down size aggregates including excavating pit of
enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
DATA: RATE ANALYSISA. MATERIALS:
Sl No Particulars
1 One line dressed hectometre stone2 40-20 mm coarse aggregate3 20-10 mm coarse aggregate4 10-4.75 mm coarse aggregate5 Sand screened6 Cement7 Synthetic enamel paint I st quality8 Sundries ( brush / oil etc )
Add seignorage charges on Stone @ Add seignorage charges on CA @ Add seignorage charges on FA @
Total cost of MaterialsB. MACHINERY:
Sl No Description
1 NIL( Manual mixing )
Total hire charges of MachineryC. LABOUR:
Sl No Description
1 Mason Cl- II2 work inspector3 mazdoor4 Painter Cl- I
Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per No.
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
CANAL CROSS DRAINAGE WORKS
(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)
CANAL CROSS DRAINAGE WORKS - DATA RATES
UNIT : 10.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 0.25 275.00 68.75Day 6.00 215.00 1290.00
Rs: 1358.75135.90
0.14 19.00154.90
Rs: 0.00
including boulders upto 0.30 m dia. for foundations of canal and other appurtenant structures and placing the excavated stuff neatly in
specified dump area or disposing off the same as directed etc., complete with initial lead upto
Rs: 0.00Rs: 1358.75
Total Rs: 1358.7514.00% Rs: 190.23
10.00 cum Rs: 1548.98(A+B+C+D)/10.0 Rs. 154.90
( Data adopted from MORTH)
including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing
240.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
day 0.32 275.00 88.00 day 8.00 215.00 1720.00
1808.00
Unit Quantity Rate Amountin Rs. in Rs.
hour 6.00 1180.70 7084.20 hour 6.00 680.60 4083.60 hour 6.00 148.20 889.20
12057.00 50.20
0.14 7.0057.20
Rs 1808.00 Rs 12057.00 Rs 0.00 Rs 13865.00
14.00% Rs: 1941.1240.00 cum Rs: 15806.1
(A+B+C+D)/240.0 Rs. 65.90
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
of foundation of structures as per drawing and technical specification,
HDR) without blasting including boulders above 0.3 m upto 0.60 m dia. of canal cross drainage and other appurtenant structures and placing the
UNIT : 10.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 1.25 260.00 325.00Day 1.25 260.00 325.00Day 0.25 275.00 68.75Day 6.00 215.00 1290.00
Rs: 2008.75200.90
0.14 28.10229.00
Rs: 0.00Rs: 0.00Rs: 2008.75
Total Rs: 2008.7514.00% Rs: 281.23
10.00 cum Rs: 2289.98(A+B+C+D)/10.0 Rs. 229.00
and other appurtenant structures and placing the excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial
180.00 cum
for foundations of canal cross drainage
Unit Quantity Rate Amountin Rs. in Rs.
day 0.24 275.00 66.00 day 6.00 215.00 1290.00
1356.00
Unit Quantity Rate Amountin Rs. in Rs.
hour 6.00 1180.70 7084.20 hour 6.00 680.60 4083.60 hour 6.00 148.20 889.20
12057.00 67.00
0.14 9.4076.40
Rs 1356.00 Rs 12057.00 Rs 0.00 Rs 13413.00
14.00% Rs: 1877.82180.00 cum Rs: 15290.82
(A+B+C+D)/180.0 Rs. 84.90
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
UNIT : 100 cum
Unit Quantity Rate Amountin Rs. in Rs.
Rm 43.50 16.50 717.7510% 71.78Hour 6.00 0.16 0.98
kg 20.00 54 1080.00Nos 29.00 11 319.00Rm 70.00 8 560.00LS 0.50 33 16.50
Rs: 2766.00
Unit Quantity Rate Amount
including boulders above 0.6 m upto 1.2 m dia. for of canal cross drainage and other appurtenant structures and placing the
in Rs. in Rs.Hour 3.00 210.40 631.20Hour 3.00 696.10 2088.30Hour 6.00 13.50 81.00Hour 6.00 0.00 0.00
Rs: 2800.50
Unit Quantity Rate Amountin Rs. in Rs.
Hour 3.00 136.00 408.00Hour 6.00 212.60 1275.60Day 1.00 275.00 275.00Day 0.50 310.00 155.00Day 0.50 260.00 130.00Day 6.00 260.00 1560.00Day 3.00 260.00 780.00Day 51.00 215.00 10965.00
Rs: 15548.60155.50
0.14 21.80177.30
Rs: 2766.00Rs: 2800.50Rs: 15548.60
Total Rs: 21115.1014.00% Rs: 2956.11
100.00 cum Rs: 24071.21(A+B+C+D)/100.0 Rs. 240.70
excavated rock neatly in specified dump area or stack yard as directed etc., complete with
UNIT : 100.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 32.00 54 1728.00No. 8.00 6 48.00No. 104.00 11 1144.00Rm 150.00 8 1200.00
Hour 16.00 8.13 130.00
of all toughness by blasting including boulders above 1.2 m dia. for of canal cross drainage and other appurtenant structures and placing the
Rm 98.30 22.00 2162.6010% 216.26
Rs: 6628.86
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 210.40 1683.20Hour 8.00 696.10 5568.80Hour 16.00 13.50 216.00Hour 16.00 0.00 0.00
Rs: 7468.00
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 136.00 1088.00Hour 16.00 212.60 3401.60Day 1.00 310.00 310.00Day 1.00 260.00 260.00Day 1.00 275.00 275.00Day 6.00 260.00 1560.00Day 6.00 260.00 1560.00Day 51.00 215.00 10965.00
Rs: 19419.60194.20
0.14 27.20221.40
Rs: 6628.86Rs: 7468.00Rs: 19419.60
Total Rs: 33516.4614.00% Rs: 4692.3
100.00 cum Rs: 38208.76(A+B+C+D)/100.0 Rs. 382.10
and other appurtenant structures and placing the excavated rock neatly in
( Data adopted from MORTH)
10.00 cum
for foundations of canal cross drainage
or stack yard as directed etc., complete with specified dump area initial lead upto 50 m and
Unit Quantity Rate Amountin Rs. in Rs.
day 0.20 275.00 55.00 day 5.00 215.00 1075.00
1130.00
Unit Quantity Rate Amountin Rs. in Rs.
hour 6.00 178.50 1071.00
hour 6.00 556.90 3341.40 hour 6.00 136.00 816.00
5228.40 522.80
0.14 73.20596.00
Rs 1130.00 Rs 5228.40 Rs 0.00 Rs 6358.40
14.00% Rs: 890.1810.00 cum Rs: 7248.58
(A+B+C+D)/10.0 Rs. 724.90
1.25 m length driven into 32 mm dia hole drilled in bed rock and remaining length embedded inconcrete / masonry including cost of all materials, machinery, labour, drilling and cleaning
UNIT : 10.00 Nos.
Unit Quantity Rate Amountin Rs. in Rs.
kg 5.00 5.50 27.50kg 101.00 41.00 4141.00Rm 12.50 22.00 275.0010% 27.50Hour 2.00 8.13 16.25
Rs: 4487.25
25 mm dia 2.50 m long cold twisted deformed steel anchor rods with
hole, driving anchor rod, grouting hole with thick cement slurry etc., complete with initial lead
Unit Quantity Rate Amountin Rs. in Rs.
Hour 1.00 210.40 210.40Hour 1.00 696.10 696.10Hour 2.00 13.50 27.00Hour 2.00 0.00 0.00
Rs: 933.50
Unit Quantity Rate Amountin Rs. in Rs.
Hour 1.00 136.00 136.00Hour 2.00 212.60 425.20Day 0.50 260.00 130.00Day 0.50 300.00 150.00Day 0.50 275.00 137.50Day 1.00 215.00 215.00
Rs: 1193.70119.40
0.14 16.70136.10
Rs: 4487.25Rs: 933.50Rs: 1193.70
Total Rs: 6614.4514.00% Rs: 926.02
10.00 Nos. Rs: 7540.47(A+B+C+D)/10.0 Rs. 754.00
cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,
UNIT : 1000.00 kg
Unit Quantity Rate Amountin Rs. in Rs.
kg 1050.00 41.00 43050.00kg 8.00 55 440.00LS 3.00 33 99.00
Rs: 43589.00
reinforcement steel bars for RCC works including
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 1.00 275.00 275.00Day 6.00 300.00 1800.00Day 11.00 215.00 2365.00
Rs: 4440.004.40
0.14 0.605.00
Rs: 43589.00Rs: 0.00Rs: 4440.00
Total Rs: 48029.0014.00% Rs: 6724.06
1000.00 kg Rs: 54753.06(A+B+C+D)/1000.0 Rs. 54.80
100 x 10 mm angle and 250 x 12 mm plate for sinking for sinking 4.50 m outer diameter foundation wells foundation wells including cost of all materials, machinery, labour, bending, welding, providing anchors etc., complete with initial lead upto 50 m and all lifts.
DETAILS OF FOUNDATION WELL CUTTING EDGE
UNIT : 615.00 kg
Unit Quantity Rate Amountin Rs. in Rs.
kg 216.10 40.00 8644.00kg 342.30 43.00 14718.90kg 56.60 41.00 2320.60
cum 0.50 275 137.50cum 1.50 40 60.00Nos 300.00 9.00 2700.00LS 5.00 33 165.00
structural steel cutting edge consisting of 100 x
Rs: 28746.00
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 14.50 116.00Hour 8.00 60.40 483.20Hour 30.00 12.90 387.00Hour 30.00 48.30 1449.00LS 10.00 33 330.00
Rs: 2765.20
Unit Quantity Rate Amountin Rs. in Rs.
Day 2.00 310.00 620.00Day 5.00 285.00 1425.00Day 1.00 275.00 275.00Day 5.00 215.00 1075.00
Rs: 3395.005.50
0.14 0.806.30
Rs: 28746.00Rs: 2765.20Rs: 3395.00
Total Rs: 34906.2014.00% Rs: 4886.87
615.00 kg Rs: 39793.07(A+B+C+D)/615.0 Rs. 64.70
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
UNIT : 15.38 cum
Unit Quantity Rate Amountin Rs. in Rs.
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
including cost of all materials, machinery, labour, formwork,
kg 3998.80 5.50 21993.40kg 46.14 5.50 253.77
cum 6.92 975.00 6747.98cum 4.15 1025.00 4256.42cum 2.77 750.00 2076.30cum 6.15 425 2614.60kg 16.00 54 863.74
sqm 15.38 197.64 3039.7510% 303.97LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 42166.42
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1555.65
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 275.00 275.00Day 1.00 285.00 285.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 15.38 215.00 3306.70Day 1.00 215.00 215.00sqm 15.38 55.65 855.9010% 85.59
Rs: 10984.64714.20
0.14 100.00814.20
Rs: 42166.42Rs: 1555.65Rs: 10984.64
Total Rs: 54706.7114.00% Rs: 7658.94
15.38 cum Rs: 62365.65(A+B+C+D)/15.38 Rs. 4055.00
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
UNIT : 14.40 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 3600.00 5.50 19800.00kg 43.20 5.50 237.60
cum 4.94 560.00 2765.95cum 4.23 975.00 4127.76cum 2.82 1025.00 2892.96cum 2.12 750.00 1587.60cum 5.04 425 2142.00kg 14.40 54 777.60
sqm 14.40 197.64 2846.0610% 284.61LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 37478.63
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 77.00 616.00Hour 8.00 123.80 990.40Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
including cost of all materials, machinery, labour, formwork,
Hour 8.00 6.20 49.60Hour 8.00 18.60 148.80
Rs: 2359.65
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 14.40 215.00 3096.00Day 1.00 215.00 215.00sqm 14.40 55.65 801.3610% 80.14
Rs: 10713.95744.00
0.14 104.20848.20
Rs: 37478.63Rs: 2359.65Rs: 10713.95
Total Rs: 50552.2314.00% Rs: 7077.31
14.40 cum Rs: 57629.5406331(A+B+C+D)/14.40 Rs. 4002.10
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
UNIT : 16.36 cum
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
including cost of all materials, machinery, labour, formwork,
Unit Quantity Rate Amountin Rs. in Rs.
kg 3599.20 5.50 19795.60kg 49.08 5.50 269.94
cum 7.36 975.00 7177.95cum 4.42 1025.00 4527.63cum 2.94 750.00 2208.60cum 6.54 425 2781.20kg 14.40 54 777.43
sqm 16.36 197.64 3233.4410% 323.34LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 41111.63
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1555.65
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 16.36 215.00 3517.40Day 1.00 215.00 215.00sqm 16.36 55.65 910.43
Rs: 11164.28682.40
0.14 95.50
777.90
Rs: 41111.63Rs: 1555.65Rs: 11164.28
Total Rs: 53831.5614.00% Rs: 7536.42
16.36 cum Rs: 61367.9818026(A+B+C+D)/16.36 Rs. 3751.10
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
UNIT : 14.55 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 3201.00 5.50 17605.50kg 43.65 5.50 240.08
cum 4.99 560.00 2794.76cum 4.28 975.00 4170.76cum 2.85 1025.00 2923.10cum 2.14 750.00 1604.14cum 5.09 425 2164.31kg 12.80 54 691.42
sqm 14.55 197.64 2875.7010% 287.57LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 35373.83
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 77.00 616.00Hour 8.00 123.80 990.40Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
including cost of all materials, machinery, labour, formwork,
Hour 1.00 233.90 233.90Hour 8.00 6.20 49.60Hour 8.00 18.60 148.80
Rs: 2359.65
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 14.55 215.00 3128.25Day 1.00 215.00 215.00sqm 14.55 55.65 809.7110% 80.97
Rs: 10755.38739.20
0.14 103.50842.70
Rs: 35373.83Rs: 2359.65Rs: 10755.38
Total Rs: 48488.8614.00% Rs: 6788.44
14.55 cum Rs: 55277.2994522(A+B+C+D)/14.55 Rs. 3799.10
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
(Cement content: 310 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
UNIT : 14.19 cum
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
including cost of all materials, machinery, labour, formwork,
( Cement content : 220 kg / cum )
Unit Quantity Rate Amountin Rs. in Rs.
kg 4398.90 5.50 24193.95kg 42.57 5.50 234.14
cum 6.39 975.00 6225.86cum 3.83 1025.00 3927.08cum 2.55 750.00 1915.65cum 5.68 425 2412.30kg 17.60 54 950.16
sqm 14.19 197.64 2804.5510% 280.46LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 42960.65
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1555.65
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 14.19 215.00 3050.85Day 1.00 215.00 215.00sqm 14.19 55.65 789.6710% 78.97
Rs: 10655.94
750.900.14 105.10
856.00
Rs: 42960.65Rs: 1555.65Rs: 10655.94
Total Rs: 55172.2414.00% Rs: 7724.11
14.19 cum Rs: 62896.35(A+B+C+D)/14.19 Rs. 4432.40
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
UNIT : 15.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 4800.00 5.50 26400.00kg 75.00 5.50 412.50
cum 6.75 975.00 6581.25cum 4.05 1025.00 4151.25cum 2.70 750.00 2025.00cum 6.00 425 2550.00kg 19.20 54 1036.80
sqm 30.00 197.64 5929.2925% 1482.32LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 50584.91
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
works including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1555.65
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 4.00 215.00 860.00Day 15.00 215.00 3225.00Day 1.00 215.00 215.00sqm 15.00 55.65 834.7525% 208.69
Rs: 11219.89748.00
0.14 104.70852.70
Rs: 50584.91Rs: 1555.65Rs: 11219.89
Total Rs: 63360.4414.00% Rs: 8870.46
15.00 cum Rs: 72230.90(A+B+C+D)/15.0 Rs. 4815.40
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
works including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
UNIT : 15.76 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 5200.80 5.50 28604.40kg 78.80 5.50 433.40
cum 8.20 1025.00 8400.08cum 4.41 750.00 3309.60cum 7.09 425 3014.10kg 20.80 54 1123.37
sqm 31.52 197.64 6229.7025% 1557.43LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 52688.58
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1555.65
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 4.00 215.00 860.00Day 15.76 215.00 3388.40Day 1.00 215.00 215.00sqm 31.52 55.65 1754.0925% 438.52
Rs: 12532.46
795.200.14 111.30
906.50
Rs: 52688.58Rs: 1555.65Rs: 12532.46
Total Rs: 66776.6914.00% Rs: 9348.74
15.76 cum Rs: 76125.4308142(A+B+C+D)/15.76 Rs. 4830.30
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),
UNIT : 15.71 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 4398.80 5.50 24193.40kg 78.55 5.50 432.03
cum 8.17 1025.00 8373.43cum 4.40 750.00 3299.10cum 7.07 425 3004.54kg 17.60 54 950.14
sqm 31.42 197.64 6209.9425% 1552.48LS 0.50 33 16.50
Add seignorage charges on CA @ (included in material rate) Rs: 0.00Add seignorage charges on FA @ (included in material rate) Rs: 0.00
Rs: 48031.56
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
works including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1555.65
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 4.00 215.00 860.00Day 15.71 215.00 3377.65Day 1.00 215.00 215.00sqm 31.42 55.65 1748.5225% 437.13
Rs: 12514.75796.60
0.14 111.50908.10
Rs: 48031.56Rs: 1555.65Rs: 12514.75
Total Rs: 62101.9614.00% Rs: 8694.27
15.71 cum Rs: 70796.2297088(A+B+C+D)/15.71 Rs. 4506.40
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
works including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
UNIT : 18.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 3960.00 5.50 21780.00kg 90.00 5.50 495.00
cum 9.36 1025.00 9594.00cum 5.04 750.00 3780.00cum 8.10 425 3442.50kg 15.84 54 855.36
sqm 36.00 197.64 7115.1425% 1778.79LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 48857.29
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1555.65
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 4.00 215.00 860.00Day 18.00 215.00 3870.00Day 1.00 215.00 215.00sqm 36.00 55.65 2003.4025% 500.85
Rs: 13325.70
740.300.14 103.60
843.90
Rs: 48857.29Rs: 1555.65Rs: 13325.70
Total Rs: 63738.6414.00% Rs: 8923.41
18.00 cum Rs: 72662.047935(A+B+C+D)/18.0 Rs. 4036.80
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
If water is to be brought from other place add only lead charges @ 500 ltr / cum. 7500(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),
UNIT : 15.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 5250.00 5.50 28875.00cum 7.80 1025.00 7995.00cum 4.20 750.00 3150.00cum 6.75 425 2868.75kg 21.00 54 1134.00
sqm 82.50 217.41 17936.09LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 61975.34
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
including cost of all materials, machinery, labour, formwork,
Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1035.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 15.00 215.00 3225.00Day 1.00 215.00 215.00sqm 82.50 55.65 4591.13
Rs: 14446.28963.10
0.14 134.801097.90
Rs: 61975.34Rs: 1035.95Rs: 14446.28
Total Rs: 77457.5614.00% Rs: 10844.06
15.00 cum Rs: 88301.6230023(A+B+C+D)/15.0 Rs. 5886.80
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
UNIT : 15.00 cum
Unit Quantity Rate Amount
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
including cost of all materials, machinery, labour, formwork,
in Rs. in Rs.kg 4800.00 5.50 26400.00kg 30.00 5.50 165.00
cum 6.75 975.00 6581.25cum 4.05 1025.00 4151.25cum 2.70 750.00 2025.00cum 6.00 425 2550.00kg 19.20 54 1036.80
sqm 60.00 217.41 13044.43LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 55970.23
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1035.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 15.00 215.00 3225.00Day 1.00 215.00 215.00sqm 60.00 55.65 3339.00
Rs: 13194.15879.60
0.14 123.101002.70
Rs: 55970.23Rs: 1035.95
Rs: 13194.15Total Rs: 70200.33
14.00% Rs: 9828.0515.00 cum Rs: 80028.377638
(A+B+C+D)/15.0 Rs. 5335.20
machinery, labour, batching, mixing, placing in position as per detailed specifications etc.,
(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),
UNIT : 14.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 4900.00 5.50 26950.00cum 7.28 1025.00 7462.00cum 3.92 750.00 2940.00cum 6.30 425 2677.50kg 19.60 54 1058.40
TOTAL Rs: 41087.901% Rs: 410.88
(Included in material ra Rs:(Included in material ra Rs:
Rs: 41498.78
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95LS 5.00 33 165.00
Rs: 1053.75
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Day 1.00 260.00 260.00Day 1.00 275.00 275.00
( 28 days cube compressive strength not less than 15 N / sq down size approved, clean, hard, graded
by tremie or skip box method including cost of all materials,
. ( Cement content : 350 kg / cum )
Day 4.00 215.00 860.00Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 2.00 215.00 430.00Day 16.00 215.00 3440.00
Rs: 9659.15689.90
0.14 96.60786.50
Rs: 41498.78Rs: 1053.75Rs: 9659.15
Total Rs: 52211.6814.00% Rs: 7309.64
14.00 cum Rs: 59521.319(A+B+C+D)/14.0 Rs. 4251.50
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with
If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
UNIT : 14.29 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 4001.20 5.50 22006.60cum 6.43 975.00 6269.74cum 3.86 1025.00 3954.76cum 2.57 750.00 1929.15cum 5.72 425 2429.30kg 16.00 54 864.26
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 37453.80
Unit Quantity Rate Amount
( 28 days cube compressive strength not less thandown size approved, clean, hard, graded
including cost of all materials, machinery, labour, cleaning,
in Rs. in Rs.Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1035.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 14.29 215.00 3072.35Day 1.00 215.00 215.00
Rs: 9702.50679.00
0.14 95.10774.10
Rs: 37453.80Rs: 1035.95Rs: 9702.50
Total Rs: 48192.2514.00% Rs: 6746.92
14.29 cum Rs: 54939.17(A+B+C+D)/14.29 Rs. 3844.60
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
28 days cube compressive strength not less than down size approved, clean, hard, graded
including cost of all materials, machinery, labour, formwork,
UNIT : 15.76 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 5200.80 5.50 28604.40kg 78.80 5.50 433.40
cum 8.20 1025.00 8400.08cum 4.41 750.00 3309.60cum 7.09 425 3014.10kg 20.80 54 1123.37
sqm 15.76 197.64 3114.85LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 48016.30
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1035.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 15.76 215.00 3388.40Day 1.00 215.00 215.00sqm 15.76 55.65 877.04
Rs: 10895.59691.30
0.14 96.80788.10
Rs: 48016.30Rs: 1035.95Rs: 10895.59
Total Rs: 59947.8514.00% Rs: 8392.7
15.76 cum Rs: 68340.5480057(A+B+C+D)/15.76 Rs. 4336.30
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
UNIT : 14.40 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 3600.00 5.50 19800.00kg 72.00 5.50 396.00
cum 4.94 560.00 2765.95cum 4.23 975.00 4127.76cum 2.82 1025.00 2892.96cum 2.12 750.00 1587.60cum 5.04 425 2142.00kg 14.40 54 777.60
sqm 39.60 207.52 8217.9930% 2465.40
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 45173.26
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 77.00 616.00Hour 8.00 123.80 990.40Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.20 49.60Hour 8.00 18.60 148.80
Rs: 1839.95
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
including cost of all materials, labour, machinery,
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 6.00 215.00 1290.00Day 14.40 215.00 3096.00Day 1.00 215.00 215.00sqm 39.60 55.65 2203.7430% 661.12
Rs: 13236.01919.20
0.14 128.701047.90
Rs: 45173.26Rs: 1839.95Rs: 13236.01
Total Rs: 60249.2214.00% Rs: 8434.89
14.40 cum Rs: 68684.1102355(A+B+C+D)/14.40 Rs. 4769.70
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
UNIT : 14.55 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 3201.00 5.50 17605.50
( 28 days cube compressive strength not less thandown size approved, clean, hard, graded
including cost of all materials, labour, machinery,
kg 72.75 5.50 400.13cum 4.99 560.00 2794.76cum 4.28 975.00 4170.76cum 2.85 1025.00 2923.10cum 2.14 750.00 1604.14cum 5.09 425 2164.31kg 12.80 54 691.42
sqm 40.01 207.52 8303.5930% 2491.08
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 43148.78
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 77.00 616.00Hour 8.00 123.80 990.40Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.20 49.60Hour 8.00 18.60 148.80
Rs: 1839.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 6.00 215.00 1290.00Day 14.55 215.00 3128.25Day 1.00 215.00 215.00sqm 40.01 55.65 2226.7030% 668.01
Rs: 13298.10914.00
0.14 128.001042.00
Rs: 43148.78Rs: 1839.95
Rs: 13298.10Total Rs: 58286.83
14.00% Rs: 8160.1614.55 cum Rs: 66446.9933213
(A+B+C+D)/14.55 Rs. 4566.80
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
UNIT : 16.36 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 3599.20 5.50 19795.60kg 81.80 5.50 449.90
cum 7.36 975.00 7177.95cum 4.42 1025.00 4527.63cum 2.94 750.00 2208.60cum 6.54 425 2781.20kg 14.40 54 777.43
sqm 44.99 207.52 9336.5530% 2800.96
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 49855.82
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1035.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
including cost of all materials, labour, machinery,
Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 5.00 215.00 1075.00Day 16.36 215.00 3517.40Day 1.00 215.00 215.00sqm 44.99 55.65 2503.6930% 751.11
Rs: 13832.35845.50
0.14 118.40963.90
Rs: 49855.82Rs: 1035.95Rs: 13832.35
Total Rs: 64724.1214.00% Rs: 9061.38
16.36 cum Rs: 73785.5025565(A+B+C+D)/16.36 Rs. 4510.10
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
UNIT : 16.25 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 5200.00 5.50 28600.00kg 81.25 5.50 446.88
cum 7.31 975.00 7129.69cum 4.39 1025.00 4497.19cum 2.93 750.00 2193.75
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
aggregates for cantiliver / counterfort retaining walls including cost of all materials,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
cum 6.50 425 2762.50kg 20.80 54 1123.20
sqm 52.81 197.64 10438.0125% 2609.50LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 59817.22
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1035.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 5.00 215.00 1075.00Day 16.25 215.00 3493.75Day 1.00 215.00 215.00sqm 52.81 55.65 2939.0225% 734.75
Rs: 14227.67875.50
0.14 122.60998.10
Rs: 59817.22Rs: 1035.95Rs: 14227.67
Total Rs: 75080.8414.00% Rs: 10511.32
16.25 cum Rs: 85592.1553387
(A+B+C+D)/16.25 Rs. 5267.20
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum,
2.82
UNIT : 18.09 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 4703.40 5.50 25868.70kg 72.36 5.50 397.98
cum 6.92 975.00 6746.44cum 4.15 1025.00 4255.45cum 2.77 750.00 2075.83cum 4.52 310 1401.98cum 6.15 425 2614.01kg 18.81 54 1015.93
sqm 49.75 197.64 9832.2430% 2949.67
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 57158.22
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.20 49.60Hour 8.00 18.60 148.80
Rs: 1087.15
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
placing and sinking plums of size 150 to 80 mm upto 15 percent for gravity etc., including cost of all materials, machinery,
lead upto 50 m and all lifts.
Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 5.00 215.00 1075.00Day 2.00 215.00 430.00Day 15.38 215.00 3306.70Day 2.00 215.00 430.00Day 1.00 215.00 215.00sqm 49.75 55.65 2768.4530% 830.53
Rs: 14825.83819.60
0.14 114.70934.30
Rs: 57158.22Rs: 1087.15Rs: 14825.83
Total Rs: 73071.2014.00% Rs: 10229.97
18.09 cum Rs: 83301.17(A+B+C+D)/18.09 Rs. 4604.80
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with
If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
UNIT : 15.38 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 3998.80 5.50 21993.40kg 76.90 5.50 422.95
cum 6.92 975.00 6747.98
( 28 days cube compressive strength not less than down size approved, clean, hard,graded
including cost of all materials, machinery, labour, cleaning,
cum 4.15 1025.00 4256.42cum 2.77 750.00 2076.30cum 6.15 425 2614.60kg 16.00 54 863.74
sqm 30.76 207.52 6383.4715% 957.52LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 46332.87
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1035.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 15.38 215.00 3306.70Day 1.00 215.00 215.00sqm 30.76 55.65 1711.7915% 256.77
Rs: 11905.41774.10
0.14 108.40882.50
Rs: 46332.87Rs: 1035.95Rs: 11905.41
Total Rs: 59274.23
14.00% Rs: 8298.3915.38 cum Rs: 67572.6227247
(A+B+C+D)/15.38 Rs. 4393.50
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
If water is to be brought from other place add only lead charges @ 500 ltr / cum.(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
UNIT : 14.40 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 3600.00 5.50 19800.00kg 72.00 5.50 396.00
cum 4.94 560.00 2765.95cum 4.23 975.00 4127.76cum 2.82 1025.00 2892.96cum 2.12 750.00 1587.60cum 5.04 425 2142.00kg 14.40 54 777.60
sqm 28.80 207.52 5976.7215% 896.51
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 41363.10
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 77.00 616.00Hour 8.00 123.80 990.40Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.20 49.60Hour 8.00 18.60 148.80
Rs: 1839.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
including cost of all materials, labour, machinery, formwork,
Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 14.40 215.00 3096.00Day 1.00 215.00 215.00sqm 28.80 55.65 1602.7215% 240.41
Rs: 11569.28803.40
0.14 112.50915.90
Rs: 41363.10Rs: 1839.95Rs: 11569.28
Total Rs: 54772.3314.00% Rs: 7668.13
14.40 cum Rs: 62440.46(A+B+C+D)/14.40 Rs. 4336.10
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
UNIT : 15.76 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 5200.80 5.50 28604.40kg 78.80 5.50 433.40
cum 8.20 1025.00 8400.08cum 4.41 750.00 3309.60cum 7.09 425 3014.10kg 20.80 54 1123.37
( 28 days cube compressive strength not less than down size approved, clean, hard, graded
including cost of all materials,machinery, labour, formwork,
( Cement content : 300 kg / cum )
sqm 39.40 242.86 9568.57250% 23921.43
LS 1.00 33 33.00(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 78407.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1035.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 2.00 285.00 570.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 4.00 215.00 860.00Day 15.76 215.00 3388.40Day 1.00 215.00 215.00sqm 39.40 55.65 2192.61
250% 5481.53Rs: 18192.68
1154.400.14 161.60
1316.00
Rs: 78407.95Rs: 1035.95Rs: 18192.68
Total Rs: 97636.5914.00% Rs: 13669.12
15.76 cum Rs: 111305.71(A+B+C+D)/15.76 Rs. 7062.50
formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
If water is to be brought from other place add only lead charges @ 500 ltr / cum.(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
UNIT : 15.76 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 5200.80 5.50 28604.40kg 78.80 5.50 433.40
cum 8.20 1025.00 8400.08cum 4.41 750.00 3309.60cum 7.09 425 3014.10kg 20.80 54 1123.37
sqm 78.80 197.64 15574.2650% 7787.13LS 1.00 33 33.00
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 68279.34
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1035.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
( 28 days cube compressive strength not less thandown size approved, clean, hard, graded
including cost of all materials, labour, machinery,
initial lead upto 50 m and all lifts. ( Cement content : 300
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 15.76 215.00 3388.40Day 1.00 215.00 215.00sqm 78.80 55.65 4385.2250% 2192.61
Rs: 16596.381053.10
0.14 147.401200.50
Rs: 68279.34Rs: 1035.95Rs: 16596.38
Total Rs: 85911.6714.00% Rs: 12027.63
15.76 cum Rs: 97939.30(A+B+C+D)/15.76 Rs. 6214.40
cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,
If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
UNIT : 15.76 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 5200.80 5.50 28604.40kg 78.80 5.50 433.40
cum 8.20 1025.00 8400.08cum 4.41 750.00 3309.60cum 7.09 425 3014.10kg 20.80 54 1123.37
sqm 7.88 197.64 1557.43LS 5.00 33 165.00
(Included in material ra Rs: 0.00
( 28 days cube compressive strength not less than 20 N / down size approved, clean, hard, graded
including cost of all materials, machinery, labour, formwork,
finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 m
(Included in material ra Rs: 0.00Rs: 46607.38
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1035.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 2.00 285.00 570.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 4.00 215.00 860.00Day 15.76 215.00 3388.40Day 2.00 215.00 430.00sqm 7.88 55.65 438.52
Rs: 11172.07708.90
0.14 99.20808.10
Rs: 46607.38Rs: 1035.95Rs: 11172.07
Total Rs: 58815.4014.00% Rs: 8234.16
15.76 cum Rs: 67049.56(A+B+C+D)/15.76 Rs. 4254.40
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing
down size approved, clean, hard, graded including cost of all materials, machinery, labour, formwork,
If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
UNIT : 15.76 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 5200.80 5.50 28604.40kg 78.80 5.50 433.40
cum 8.20 1025.00 8400.08cum 4.41 750.00 3309.60cum 7.09 425 3014.10kg 20.80 54 1123.37
sqm 70.92 197.64 14016.8325% 3504.21LS 0.50 33 16.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 62422.49
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20
Rs: 1035.95
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 5.00 215.00 1075.00Day 15.76 215.00 3388.40Day 1.00 215.00 215.00
. ( Cement content : 300 kg / cum )
sqm 70.92 55.65 3946.7025% 986.67
Rs: 15381.92976.00
0.14 136.601112.60
Rs: 62422.49Rs: 1035.95Rs: 15381.92
Total Rs: 78840.3614.00% Rs: 11037.65
15.76 cum Rs: 89878.0133319(A+B+C+D)/15.76 Rs. 5702.90
260.00 day 31.20285.00 day 285.00215.00 day 430.00
746.20
422.30 hour 844.60
233.90 hour 467.80106.30 hour 212.60
Consumables in sinking @ 10% of machinery charges 152.501677.502423.70
14.00% 339.32
2763.02or say ( Rate upto 3.0m for 6.0 m well sinking ) 2763.00
898.7014.00% 125.80
Sinking RCC wells vertically for foundation of piers and abutments in all kinds of soil, sand and soft rock by approved well sinking method including cost of all materials, machinery, labour, kent - ledge arrangements, disposal of excavated material as directed etc., complete with lead upto 50 m for disposal of excavated material.(diameter of well 6.00m)
labour component/unit qty(including contractor's profit) 1024.50
260.00 day 39.00285.00 day 356.25215.00 day 537.50
932.75
422.30 hour 1266.90
233.90 hour 701.70106.30 hour 318.90
Consumables in sinking @ 10% of machinery charges 228.752516.253449.00
14.00% 482.86
3931.863931.90
1161.500.14 162.60
labour component/unit qty(including contractor's profit) 1324.10
ramming as directed including cost of all materials, machinery, labour etc., complete with
UNIT : 15.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
cum 15.75 325 5118.750.00 0.00
(Included in material ra Rs: 0.00Rs: 5118.75
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
in layers of 25 to 30 cm and compacting by watering,
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 0.25 275.00 68.75Day 4.00 215.00 860.00
Rs: 928.7561.90
0.14 8.7070.60
Rs: 5118.75Rs: 0.00Rs: 928.75
Total Rs: 6047.5014.00% Rs: 846.65
15.00 cum Rs: 6894.15(A+B+C+D)/15.0 Rs. 459.60
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,
UNIT : 10.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 1430.00 5.50 7865.00cum 8.50 265 2252.50cum 1.50 310 465.00cum 4.00 425 1700.00
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 12282.50
Unit Quantity Rate Amountin Rs. in Rs.
Hour 1.00 285.80 285.80
un-coursed rubble stone masonry with approved stones infor sub-structure portions of return walls / abutments etc., including
lead upto 50 m and all lifts.
Hour 1.00 233.90 233.90Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95
Rs: 554.85
Unit Quantity Rate Amountin Rs. in Rs.
Hour 1.00 106.30 106.30Hour 0.50 71.10 35.55Day 1.00 275.00 275.00Day 1.00 285.00 285.00Day 2.00 260.00 520.00
Day 4.00 215.00 860.00Day 2.00 215.00 430.00Day 1.00 215.00 215.00Day 3.00 215.00 645.00Day 1.00 215.00 215.00Day 4.00 215.00 860.00
Rs: 4446.85444.70
0.14 62.30507.00
Rs: 12282.50Rs: 554.85Rs: 4446.85
Total Rs: 17284.2014.00% Rs: 2419.79
10.00 cum Rs: 19703.99(A+B+C+D)/10.0 Rs. 1970.40
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,
UNIT : 10.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
un-coursed rubble stone masonry with approved stones infor super-structure portions of return walls / abutments etc., including
lead upto 50 m and all lifts.
kg 1430.00 5.50 7865.00cum 8.50 265 2252.50cum 1.50 310 465.00cum 4.00 425 1700.00
TOTAL Rs: 12282.502.5% Rs: 307.06
(Included in material ra Rs:(Included in material ra Rs:
Rs: 12589.56
Unit Quantity Rate Amountin Rs. in Rs.
Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95
Rs: 554.85
Unit Quantity Rate Amountin Rs. in Rs.
Hour 1.00 106.30 106.30Hour 0.50 71.10 35.55Day 1.00 275.00 275.00Day 1.00 285.00 285.00Day 2.00 260.00 520.00
Day 4.00 215.00 860.00Day 2.00 215.00 430.00Day 1.00 215.00 215.00Day 3.00 215.00 645.00Day 1.00 215.00 215.00Day 4.00 215.00 860.00
TOTAL Rs: 4446.852.5% Rs: 111.17
Rs: 4558.02455.80
0.14 63.80519.60
Rs: 12589.56Rs: 554.85Rs: 4558.02
Total Rs: 17702.4314.00% Rs: 2478.34
10.00 cum Rs: 20180.77375
(A+B+C+D)/10.0 Rs. 2018.10
stones from approved source including cost of all materials, machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with
(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones
UNIT : 10.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 1330.00 5.50 7315.00Nos 60.00 32 1920.00Nos 180.00 12 2160.00cum 4.50 265 1192.50cum 1.50 310 465.00cum 3.50 425 1487.50
TOTAL Rs: 14540.002.5% Rs: 363.50
(Included in material ra Rs:(Included in material ra Rs:
Rs: 14903.50
Unit Quantity Rate Amountin Rs. in Rs.
Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95
Rs: 554.85
Unit Quantity Rate Amountin Rs. in Rs.
Hour 1.00 106.30 106.30Hour 0.50 71.10 35.55Day 1.00 275.00 275.00Day 3.00 260.00 780.00Day 1.00 285.00 285.00Day 2.00 260.00 520.00
Day 4.00 215.00 860.00Day 3.00 215.00 645.00
coursed rubble masonry second sort in CM 1:4 proportion with
Day 1.00 215.00 215.00Day 3.00 215.00 645.00Day 1.00 215.00 215.00Day 2.00 215.00 430.00
TOTAL Rs: 5011.852.5% Rs: 125.30
Rs: 5137.15513.70
0.14 71.90585.60
Rs: 14903.50Rs: 554.85Rs: 5137.15
Total Rs: 20595.5014.00% Rs: 2883.37
10.00 cum Rs: 23478.86625(A+B+C+D)/10.0 Rs. 2347.90
Providing and constructing coursed rubble masonry first sort in CM 1:4 proportion withstones from approved source including cost of all materials, machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with
(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones
UNIT : 10.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 1330.00 5.50 7315.00Nos 60.00 32 1920.00Nos 180.00 12 2160.00cum 4.50 265 1192.50cum 1.50 310 465.00cum 3.50 425 1487.50
TOTAL Rs: 14540.002.5% Rs: 363.50
(Included in material ra Rs:(Included in material ra Rs:
Rs: 14903.50
Unit Quantity Rate Amount
in Rs. in Rs.Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95
Rs: 554.85
Unit Quantity Rate Amountin Rs. in Rs.
Hour 1.00 106.30 106.30Hour 0.50 71.10 35.55Day 1.00 275.00 275.00Day 6.00 260.00 1560.00Day 1.00 285.00 285.00Day 2.00 260.00 520.00
Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 1.00 215.00 215.00Day 3.00 215.00 645.00Day 1.00 215.00 215.00Day 2.00 215.00 430.00
TOTAL Rs: 5791.852.5% Rs: 144.80
Rs: 5936.65593.70
0.14 83.10676.80
Rs: 14903.50Rs: 554.85Rs: 5936.65
Total Rs: 21395.0014.00% Rs: 2995.3
10.00 cum Rs: 24390.29625(A+B+C+D)/10.0 Rs. 2439.00
proportion by volume including raking and cleaning joints for 50 mm depth, pressing cementmortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
UNIT : 100.00 sqm
to coursed rubble face stone masonry in CM 1 : 2
Unit Quantity Rate Amountin Rs. in Rs.
kg 456.00 5.50 2508.00cum 0.75 425 318.75
TOTAL Rs: 2826.752.5% Rs: 70.67
(Included in material ra Rs:Rs: 2897.42
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 10.00 285.00 2850.00Day 1.00 275.00 275.00Day 10.00 215.00 2150.00
Rs: 5275.0052.80
0.14 7.4060.20
Rs: 2897.42Rs: 0.00Rs: 5275.00
Total Rs: 8172.4214.00% Rs: 1144.14
100.00 sqm Rs: 9316.55875(A+B+C+D)/100.0 Rs. 93.20
proportion by volume including raking and cleaning joints for 50 mm depth, pressing cementmortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
UNIT : 100.00 sqm
Unit Quantity Rate Amountin Rs. in Rs.
kg 322.00 5.50 1771.00
to coursed rubble face stone masonry in CM 1 : 3
cum 0.75 425 318.75TOTAL Rs: 2089.75
2.5% Rs: 52.24(Included in material ra Rs:
Rs: 2141.99
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 10.00 285.00 2850.00Day 1.00 275.00 275.00Day 10.00 215.00 2150.00
Rs: 5275.0052.80
0.14 7.4060.20
Rs: 2141.99Rs: 0.00Rs: 5275.00
Total Rs: 7416.9914.00% Rs: 1038.38
100.00 sqm Rs: 8455.37375(A+B+C+D)/100.0 Rs. 84.60
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
UNIT : 100.00 sqm
Unit Quantity Rate Amountin Rs. in Rs.
kg 629.00 5.50 3459.50cum 1.32 425 561.00
TOTAL Rs: 4020.502.5% Rs: 100.51
(Included in material ra Rs:
12 mm thick plastering in cement mortar 1:3 proportion by volume including cost
Rs: 4121.01
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 10.00 285.00 2850.00Day 1.00 275.00 275.00Day 20.00 215.00 4300.00
Rs: 7425.0074.30
0.14 10.4084.70
Rs: 4121.01Rs: 0.00Rs: 7425.00
Total Rs: 11546.0114.00% Rs: 1616.44
100.00 sqm Rs: 13162.4525(A+B+C+D)/100.0 Rs. 131.60
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
UNIT : 100.00 sqm
Unit Quantity Rate Amountin Rs. in Rs.
kg 472.00 5.50 2596.00cum 1.32 425 561.00
TOTAL Rs: 3157.002.5% Rs: 78.93
(Included in material ra Rs:Rs: 3235.93
12 mm thick plastering in cement mortar 1:4 proportion by volume including cost
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 10.00 285.00 2850.00Day 1.00 275.00 275.00Day 20.00 215.00 4300.00
Rs: 7425.0074.30
0.14 10.4084.70
Rs: 3235.93Rs: 0.00Rs: 7425.00
Total Rs: 10660.9314.00% Rs: 1492.53
100.00 sqm Rs: 12153.455(A+B+C+D)/100.0 Rs. 121.50
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
UNIT : 100.00 sqm
Unit Quantity Rate Amountin Rs. in Rs.
kg 1050.00 5.50 5775.00cum 2.20 425 935.00
TOTAL Rs: 6710.002.5% Rs: 167.75
(Included in material ra Rs:Rs: 6877.75
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.00
20 mm thick plastering in cement mortar 1:3 proportion by volume including cost
0.00 0.00 0.00Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 15.00 285.00 4275.00Day 1.00 275.00 275.00Day 25.00 215.00 5375.00
Rs: 9925.0099.30
0.14 13.90113.20
Rs: 6877.75Rs: 0.00Rs: 9925.00
Total Rs: 16802.7514.00% Rs: 2352.39
100.00 sqm Rs: 19155.14(A+B+C+D)/100.0 Rs. 191.60
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
UNIT : 100.00 sqm
Unit Quantity Rate Amountin Rs. in Rs.
kg 788.00 5.50 4334.00cum 2.20 425 935.00
TOTAL Rs: 5269.002.5% Rs: 131.73
(Included in material ra Rs:Rs: 5400.73
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
20 mm thick plastering in cement mortar 1:4 proportion by volume including cost
Unit Quantity Rate Amountin Rs. in Rs.
Day 15.00 285.00 4275.00Day 1.00 275.00 275.00Day 25.00 215.00 5375.00
Rs: 9925.0099.30
0.14 13.90113.20
Rs: 5400.73Rs: 0.00Rs: 9925.00
Total Rs: 15325.7314.00% Rs: 2145.6
100.00 sqm Rs: 17471.325(A+B+C+D)/100.0 Rs. 174.70
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
UNIT : 10.00 sqm
Unit Quantity Rate Amountin Rs. in Rs.
kg 75.00 5.50 412.50cum 0.30 425 127.50sqm 10.50 227 2383.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 2923.50
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
roughly dressed burnt stone slabs for coping set in proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
Unit Quantity Rate Amountin Rs. in Rs.
Day 1.00 260.00 260.00Day 1.00 260.00 260.00Day 0.50 275.00 137.50Day 2.00 215.00 430.00
Rs: 1087.50108.80
0.14 15.20124.00
Rs: 2923.50Rs: 0.00Rs: 1087.50
Total Rs: 4011.0014.00% Rs: 561.54
10.00 sqm Rs: 4572.54(A+B+C+D)/10.0 Rs. 457.30
CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm
UNIT : 10.00 sqm
Unit Quantity Rate Amountin Rs. in Rs.
kg 75.00 5.50 412.50cum 0.30 425 127.50sqm 10.50 227 2383.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 2923.50
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
one line dressed burnt stone slabs for coping set in
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
Unit Quantity Rate Amountin Rs. in Rs.
Day 1.00 260.00 260.00Day 4.00 285.00 1140.00Day 0.50 275.00 137.50Day 2.00 215.00 430.00
Rs: 1967.50196.80
0.14 27.60224.40
Rs: 2923.50Rs: 0.00Rs: 1967.50
Total Rs: 4891.0014.00% Rs: 684.74
10.00 sqm Rs: 5575.74(A+B+C+D)/10.0 Rs. 557.60
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm
UNIT : 10.00 sqm
Unit Quantity Rate Amountin Rs. in Rs.
kg 75.00 5.50 412.50cum 0.30 425 127.50sqm 10.50 227 2383.50
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 2923.50
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
two line dressed burnt stone slabs for coping set in proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
Unit Quantity Rate Amountin Rs. in Rs.
Day 1.00 260.00 260.00Day 8.00 285.00 2280.00Day 0.50 275.00 137.50Day 2.00 215.00 430.00
Rs: 3107.50310.80
0.14 43.50354.30
Rs: 2923.50Rs: 0.00Rs: 3107.50
Total Rs: 6031.0014.00% Rs: 844.34
10.00 sqm Rs: 6875.34(A+B+C+D)/10.0 Rs. 687.50
cleaning surface, batching, mixing, placing in position, levelling, compacting, finishing, curing
(Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement),
UNIT : 14.67 cum
Unit Quantity Rate Amountin Rs. in Rs.
kg 4401.00 5.50 24205.50kg 73.35 5.50 403.42
cum 7.63 1025.00 7819.11cum 4.11 750.00 3080.70cum 6.60 425 2805.64kg 17.60 54 950.62
sqm 80.69 197.64 15946.81sqm 1.00 33 33.00
Add seignorage charges on Stone @(Included in material rate) Rs: 0.00Add seignorage charges on Sand @ (Included in material rate) Rs: 0.00
Rs: 55244.80
( 28 days cube compressive strength not less than 15 N / down size approved clean, hard, graded
including cost of all materials, machinery, labour, formwork,
lead upto 50 m and initial lift upto 3 m.
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90
Rs: 1408.45
Unit Quantity Rate Amountin Rs. in Rs.
Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Day 1.00 285.00 285.00Day 1.00 275.00 275.00
Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 14.67 215.00 3154.05Day 1.00 215.00 215.00sqm 80.69 55.65 4490.12
Rs: 13564.62924.70
0.14 129.501054.20
Rs: 55244.80Rs: 1408.45Rs: 13564.62
Total Rs: 70217.8714.00% Rs: 9830.5
14.67 cum Rs: 80048.37(A+B+C+D)/14.67 Rs. 5456.60
Providing and constructing protective railing consisting of in-situ railing posts of size 15 x15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre to centre in M-20 gradeconcrete using 20 mm down size graded aggregates and with each post reinforced by 4 Nos.of 8 mm dia main bars embedded in kerb concrete for a depth of 40 cm and 5 Nos. of 6 mmdia. stirrups including fixing 3 rows of 40 mm dia. GI pipes with one coat of red oxide primerand two coats of synthetic enamel paint, cost of all materials, machinery, labour, formwork,
UNIT : 10.00 Rm
Unit Quantity Rate Amountin Rs. in Rs.
kg 30.00 5.50 165.00cum 0.04 1025.00 41.00cum 0.02 750.00 15.00cum 0.04 425 17.00kg 16.39 41.00 671.99Rm 30.00 189 5670.00sqm 3.00 197.64 592.93LS 4.00 33 132.00
Add seignorage charges on Stone @ (Included in material rate) Rs: 0.00Add seignorage charges on Sand @(Included in material rate) Rs: 0.00
Rs: 7304.92
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 0.50 285.00 142.50Day 0.50 300.00 150.00Day 0.50 275.00 137.50Day 1.50 215.00 322.50Day 0.50 260.00 130.00Day 0.50 260.00 130.00
Rs: 1012.50101.30
0.14 14.20115.50
Rs: 7304.92Rs: 0.00Rs: 1012.50
Total Rs: 8317.4214.00% Rs: 1164.44
10.00 Rm Rs: 9481.858529(A+B+C+D)/10.0 Rs. 948.20
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
(Cement content: 9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)
UNIT : 10.00 Joints
Unit Quantity Rate Amountin Rs. in Rs.
kg 99.00 5.50 544.50cum 0.10 425 42.50kg 0.91 60 54.60
(Included in material ra Rs: 0.00Rs: 641.60
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 2.00 260.00 520.00Day 1.00 275.00 275.00Day 3.00 215.00 645.00
Rs: 1440.00144.00
0.14 20.20164.20
Rs: 641.60Rs: 0.00Rs: 1440.00
Total Rs: 2081.6014.00% Rs: 291.42
10.00 Joints Rs: 2373.02(A+B+C+D)/10.0 Rs. 237.30
NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
(Cement content: 17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)
UNIT : 10.00 Joints
Unit Quantity Rate Amountin Rs. in Rs.
kg 174.00 5.50 957.00cum 0.22 425 93.50kg 1.27 60 76.20
(Included in material ra Rs: 0.00Rs: 1126.70
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 2.00 260.00 520.00Day 1.00 275.00 275.00Day 3.00 215.00 645.00
Rs: 1440.00144.00
0.14 20.20164.20
Rs: 1126.70Rs: 0.00Rs: 1440.00
Total Rs: 2566.7014.00% Rs: 359.34
10.00 Joints Rs: 2926.04(A+B+C+D)/10.0 Rs. 292.60
NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
(Cement content: 24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)
UNIT : 10.00 Joints
Unit Quantity Rate Amountin Rs. in Rs.
kg 248.00 5.50 1364.00cum 0.25 425 106.25kg 2.20 60 132.00
(Included in material ra Rs: 0.00Rs: 1602.25
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 2.50 260.00 650.00Day 1.00 275.00 275.00Day 4.00 215.00 860.00
Rs: 1785.00178.50
0.14 25.00203.50
Rs: 1602.25Rs: 0.00Rs: 1785.00
Total Rs: 3387.2514.00% Rs: 474.22
10.00 Joints Rs: 3861.47(A+B+C+D)/10.0 Rs. 386.10
NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
(Cement content: 32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint)
UNIT : 10.00 Joints
Unit Quantity Rate Amountin Rs. in Rs.
kg 321.00 5.50 1765.50cum 0.31 425 131.75kg 2.50 60 150.00
(Included in material ra Rs: 0.00Rs: 2047.25
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 2.50 260.00 650.00Day 1.00 275.00 275.00Day 4.00 215.00 860.00
Rs: 1785.00178.50
0.14 25.00203.50
Rs: 2047.25Rs: 0.00Rs: 1785.00
Total Rs: 3832.2514.00% Rs: 536.52
10.00 Joints Rs: 4368.77(A+B+C+D)/10.0 Rs. 436.90
NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
(Cement content: 39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)
UNIT : 10.00 Joints
Unit Quantity Rate Amountin Rs. in Rs.
kg 396.00 5.50 2178.00cum 0.39 425 165.75kg 3.10 60 186.00
(Included in material ra Rs: 0.00Rs: 2529.75
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 3.00 260.00 780.00Day 1.00 275.00 275.00Day 5.00 215.00 1075.00
Rs: 2130.00213.00
0.14 29.80242.80
Rs: 2529.75Rs: 0.00Rs: 2130.00
Total Rs: 4659.7514.00% Rs: 652.37
10.00 Joints Rs: 5312.12(A+B+C+D)/10.0 Rs. 531.20
NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
(Cement content: 44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)
UNIT : 10.00 Joints
Unit Quantity Rate Amountin Rs. in Rs.
kg 446.00 5.50 2453.00cum 0.45 425 191.25kg 3.40 60 204.00
(Included in material ra Rs: 0.00Rs: 2848.25
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 3.00 260.00 780.00Day 1.00 275.00 275.00Day 5.00 215.00 1075.00
Rs: 2130.00213.00
0.14 29.80242.80
Rs: 2848.25Rs: 0.00Rs: 2130.00
Total Rs: 4978.2514.00% Rs: 696.96
10.00 Joints Rs: 5675.21(A+B+C+D)/10.0 Rs. 567.50
NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
(Cement content: 49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)
UNIT : 10.00 Joints
Unit Quantity Rate Amountin Rs. in Rs.
kg 495.00 5.50 2722.50cum 0.50 425 212.50kg 3.77 60 226.20
(Included in material ra Rs: 0.00Rs: 3161.20
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 3.00 260.00 780.00Day 1.00 275.00 275.00Day 6.00 215.00 1290.00
Rs: 2345.00234.50
0.14 32.80267.30
Rs: 3161.20Rs: 0.00Rs: 2345.00
Total Rs: 5506.2014.00% Rs: 770.87
10.00 Joints Rs: 6277.07(A+B+C+D)/10.0 Rs. 627.70
NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
(Cement content: 56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)
UNIT : 10.00 Joints
Unit Quantity Rate Amountin Rs. in Rs.
kg 569.00 5.50 3129.50cum 0.58 425 246.50kg 4.15 60 249.00
(Included in material ra Rs: 0.00Rs: 3625.00
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 3.00 260.00 780.00Day 1.00 275.00 275.00Day 6.00 215.00 1290.00
Rs: 2345.00234.50
0.14 32.80267.30
Rs: 3625.00Rs: 0.00Rs: 2345.00
Total Rs: 5970.0014.00% Rs: 835.8
10.00 Joints Rs: 6805.8(A+B+C+D)/10.0 Rs. 680.60
class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
(Cement content: 66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)
UNIT : 10.00 Joints
Unit Quantity Rate Amountin Rs. in Rs.
kg 668.00 5.50 3674.00cum 0.69 425 293.25kg 4.53 60 271.80
(Included in material ra Rs: 0.00Rs: 4239.05
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 4.00 260.00 1040.00Day 1.00 275.00 275.00Day 7.00 215.00 1505.00
Rs: 2820.00282.00
0.14 39.50321.50
Rs: 4239.05Rs: 0.00Rs: 2820.00
Total Rs: 7059.0514.00% Rs: 988.27
10.00 Joints Rs: 8047.32(A+B+C+D)/10.0 Rs. 804.70
NP- 2 class or IRC standard hume pipes in CM 1 : 2
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
including cost of all materials, machinery, labour, watering, ramming etc., complete with initial
UNIT : 10.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
cum 10.00 265 2650.00cum 4.00 325 1300.00
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 3950.00
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 0.50 275.00 137.50Day 1.00 260.00 260.00Day 4.00 215.00 860.00
Rs: 1257.50125.80
0.14 17.60143.40
Rs: 3950.00Rs: 0.00Rs: 1257.50
Total Rs: 5207.5014.00% Rs: 729.05
10.00 cum Rs: 5936.55(A+B+C+D)/10.0 Rs. 593.70
behind abutment and return walls in layers
including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by earth
UNIT : 10.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
cum 12.00 80 960.000.00 0.00 0.00
(Included in material ra Rs: 0.00Rs: 960.00
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 0.50 305.00 152.50Day 0.50 275.00 137.50Day 6.00 215.00 1290.00
Rs: 1580.00158.00
0.14 22.10180.10
Rs: 960.00Rs: 0.00Rs: 1580.00
Total Rs: 2540.0014.00% Rs: 355.6
10.00 cum Rs: 2895.6(A+B+C+D)/10.0 Rs. 289.60
including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by power
( CNS soil ) for foundation or around pipes
density control of not less than 95 percent etc., complete with lead
( CNS soil ) for foundation or above pipes
density control of not less than 98 percent etc., complete with lead upto
UNIT : 10.00 cum
Unit Quantity Rate Amountin Rs. in Rs.
cum 12.00 80 960.000.00 0.00 0.00
(Included in material ra Rs: 0.00Rs: 960.00
Unit Quantity Rate Amountin Rs. in Rs.
Hour 0.17 151.50 25.85Hour 0.17 556.90 95.03
Rs: 120.89
Unit Quantity Rate Amountin Rs. in Rs.
Hour 0.17 136.00 23.21Day 0.50 305.00 152.50Day 0.50 275.00 137.50Day 1.50 215.00 322.50
Rs: 635.7163.60
0.14 8.9072.50
Rs: 960.00Rs: 120.89Rs: 635.71
Total Rs: 1716.6014.00% Rs: 240.32
10.00 cum Rs: 1956.91556314(A+B+C+D)/10.0 Rs. 195.70
size 70x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats syntheticenamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
111x35x25 cm thick IRC standard kilometre stone in down size aggregates including excavating pit of
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
UNIT : 4 Nos.
Unit Quantity Rate Amountin Rs. in Rs.
No. 4.00 340 1360.00cum 0.20 975.00 195.00cum 0.15 1025.00 153.75cum 0.10 750.00 75.00cum 0.20 425 85.00kg 100.00 5.50 550.00ltr 1.00 184.00 184.00LS 4.00 33 132.00
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 2734.75
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 1.00 260.00 260.00Day 1.00 275.00 275.00Day 1.00 215.00 215.00Day 1.00 300.00 300.00
Rs: 1050.00262.50
0.14 36.80299.30
Rs: 2734.75Rs: 0.00Rs: 1050.00
Total Rs: 3784.7514.00% Rs: 529.87
4.00 Nos. Rs: 4314.62(A+B+C+D)/4.0 Rs. 1078.70
size 50x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic
65x15x10 cm thick IRC standard hectometre stone in down size aggregates including excavating pit of
enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
UNIT : 4 Nos.
Unit Quantity Rate Amountin Rs. in Rs.
No. 4.00 180 720.00cum 0.20 975.00 195.00cum 0.15 1025.00 153.75cum 0.10 750.00 75.00cum 0.20 425 85.00kg 100.00 5.50 550.00ltr 0.40 184.00 73.60LS 1.00 33 33.00
(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00
Rs: 1885.35
Unit Quantity Rate Amountin Rs. in Rs.
0.00 0.00 0.000.00 0.00 0.00
Rs: 0.00
Unit Quantity Rate Amountin Rs. in Rs.
Day 1.00 260.00 260.00Day 1.00 275.00 275.00Day 1.00 215.00 215.00Day 0.50 300.00 150.00
Rs: 900.00225.00
0.14 31.50256.50
Rs: 1885.35Rs: 0.00Rs: 900.00
Total Rs: 2785.3514.00% Rs: 389.95
4.00 Nos. Rs: 3175.3(A+B+C+D)/4.0 Rs. 793.80
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.