Book 1

291
IRR-CCDW 222 CHAPTER-IV CANAL CROSS DRAINAGE WORKS (WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED) FOR THE YE Index- code IRR-CCDW CANAL CROSS DRAINAGE WORKS - DATA RATES IRR-CCDW-1 EXCAVATION & FOUNDATION TREATMENT WORKS : IRR-CCDW-1-1 50 m and initial lift upto 3 m. DATA: RATE ANALYSIS UNIT : 10.00 A. MATERIALS: Sl No Particulars Unit Quantity Rate in Rs. 1 NIL 0.00 0.00 0.00 0.00 Total cost of Materials Rs: B. MACHINERY: Sl No Description Unit Quantity Rate in Rs. 1 NIL 0.00 0.00 0.00 0.00 Total hire charges of Machinery Rs: C. LABOUR: Sl No Description Unit Quantity Rate in Rs. 1 work inspector Day 0.25 275.00 2 mazdoor Day 6.00 215.00 Total cost of Labour Rs: labour component/unit qty 135.90 Add contractor's profit and overhead charges 0.14 19.00 labour component/unit qty (including contractor's profit) 154.90 ABSTRACT: A. Cost of Materials Rs: B. Hire charges of Machinery Rs: C. Cost of Labour Rs: Total Rs: D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: Total cost for 10.00 cum Rs: Rate per cum (A+B+C+D)/10.0 Rs. IRR-CCDW-1-2 Excavation for Structures- Mechanical Means ( Data adopted from MORTH) including setting out, construction of shoring and bracing, removal of stumps Unit = cum DATA: Taking output = 240 cum 240.00 cum a) Labour Sl No Description Unit Quantity Rate in Rs. 1 work inspector day 0.32 275.00 2 Mazdoor day 8.00 215.00 Total in Rs. b)Machinery Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundati cross drainage and other appurtenant structures and placing the excavated stuff specified dump area or disposing off the same as directed etc., complete with in Earth work in excavation in all kinds of soils of foundation of structures as of sides and bottom and backfilling with approved Depth upto 3 m

Transcript of Book 1

Page 1: Book 1

IRR-CCDW

222

CHAPTER-IV

CANAL CROSS DRAINAGE WORKS

(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)

FOR THE YEAR :2011-12Index- code

IRR-CCDW CANAL CROSS DRAINAGE WORKS - DATA RATES

IRR-CCDW-1 EXCAVATION & FOUNDATION TREATMENT WORKS :

IRR-CCDW-1-1

50 m and initial lift upto 3 m.

DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 NIL 0.00 0.00 0.000.00 0.00 0.00

Total cost of Materials Rs: 0.00

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 NIL 0.00 0.00 0.00

0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 work inspector Day 0.25 275.00 68.752 mazdoor Day 6.00 215.00 1290.00

Total cost of Labour Rs: 1358.75labour component/unit qty 135.90Add contractor's profit and overhead charges 0.14 19.00labour component/unit qty (including contractor's profit) 154.90

ABSTRACT:A. Cost of Materials Rs: 0.00B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1358.75

Total Rs: 1358.75D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 190.23Total cost for 10.00 cum Rs: 1548.98Rate per cum (A+B+C+D)/10.0 Rs. 154.90

IRR-CCDW-1-2 Excavation for Structures- Mechanical Means ( Data adopted from MORTH)

including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.Depth upto 3 m

Unit = cumDATA: Taking output = 240 cum 240.00 cum

a) LabourSl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 work inspector day 0.32 275.00 88.00 2 Mazdoor day 8.00 215.00 1720.00

Total in Rs. 1808.00

b)Machinery

Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundations of canalcross drainage and other appurtenant structures and placing the excavated stuff neatly inspecified dump area or disposing off the same as directed etc., complete with initial lead upto

Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification,

Page 2: Book 1

IRR-CCDW

223

Sl No Description Unit Quantity Rate Amountin Rs. in Rs.

1 Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1180.70 7084.20 Fuel/ Energy charges hour 6.00 680.60 4083.60 crew for excavator hour 6.00 148.20 889.20 Total in Rs. 12057.00

labour component/unit qty 50.20Add contractor's profit and overhead charges 0.14 7.00labour component/unit qty (including contractor's profit) 57.20

Abstracta) Labour Rs 1808.00 b) Machinery Rs 12057.00 c) Material Rs 0.00 Total Rs 13865.00

D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1941.1Total cost for 240.00 cum Rs: 15806.1Rate per cum (A+B+C+D)/240.0 Rs. 65.90

IRR-CCDW-1-3

excavated stuff neatly in specified dump area or disposing off the same as directed etc.,

DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 NIL 0.00 0.00 0.000.00 0.00 0.00

Total cost of Materials Rs: 0.00

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 NIL 0.00 0.00 0.00

0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crowbarman Day 1.25 260.00 325.002 Stone breaker Day 1.25 260.00 325.003 work inspector Day 0.25 275.00 68.754 mazdoor Day 6.00 215.00 1290.00

Total cost of Labour Rs: 2008.75labour component/unit qty 200.90Add contractor's profit and overhead charges 0.14 28.10labour component/unit qty (including contractor's profit) 229.00

ABSTRACT:A. Cost of Materials Rs: 0.00B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 2008.75

Total Rs: 2008.75D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 281.23Total cost for 10.00 cum Rs: 2289.98Rate per cum (A+B+C+D)/10.0 Rs. 229.00

IRR-CCDW-1-4and other appurtenant structures and placing the excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial

( Data adopted from MORTH) Mechanical MeansUnit = cum

DATA: Taking output = 180 cum 180.00 cuma) Labour

Excavation in ordnary rock (including HDR) without blasting including boulders above 0.3 m upto 0.60 m dia.for foundations of canal cross drainage and other appurtenant structures and placing the

complete with initial lead upto 50 m and initial lift upto 3 m.

Excavation in ordnary rock without blasting for foundations of canal cross drainage

lead upto 50 m and initial lift upto 3 m.

Page 3: Book 1

IRR-CCDW

224

Sl No Description Unit Quantity Rate Amountin Rs. in Rs.

1 work inspector day 0.24 275.00 66.00 2 Mazdoor day 6.00 215.00 1290.00

Total in Rs. 1356.00

b) MachinerySl No Description Unit Quantity Rate Amount

in Rs. in Rs.1.0 Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1180.70 7084.20

Fuel/ Energy charges hour 6.00 680.60 4083.60 crew for excavator hour 6.00 148.20 889.20 Total in Rs. 12057.00

labour component/unit qty 67.00Add contractor's profit and overhead charges 0.14 9.40labour component/unit qty (including contractor's profit) 76.40

Abstract a) Labour Rs 1356.00 b) Machinery Rs 12057.00 c) Material Rs 0.00

Total Rs 13413.00

D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1877.82Total cost for 180.00 cum Rs: 15290.82Rate per cum (A+B+C+D)/180.0 Rs. 84.90

IRR-CCDW-1-5

excavated stuff neatly in specified dump area or disposing off the same as directed etc.,

DATA:RATE ANALYSIS UNIT : 100 cum

A. MATERIALS:Sl No Particulars Unit Quantity Rate Amount

in Rs. in Rs.1 Use rate of drill rod 1.6 m length Rm 43.50 16.50 717.75

Reconditioning charges @ 10% 71.782 Use rate of air hose 2 Nos. Hour 6.00 0.16 0.983 Explosive small dia ( Kelvex-220 ) kg 20.00 54 1080.004 Electric detonators Nos 29.00 11 319.005 Detonating fuse coil Rm 70.00 8 560.006 Sundries LS 0.50 33 16.50

Total cost of Materials Rs: 2766.00

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Air compressor 8.5 cmm ( diesel ) Hour 3.00 210.40 631.20

Fuel / Energy charges Hour 3.00 696.10 2088.302 Jack hammers 2 Nos. Hour 6.00 13.50 81.00

Fuel / Energy charges Hour 6.00 0.00 0.00Total hire charges of Machinery Rs: 2800.50

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Air compressor Hour 3.00 136.00 408.002 Crew for Jack hammer Hour 6.00 212.60 1275.603 work inspector Day 1.00 275.00 275.004 Blaster Day 0.50 310.00 155.005 Helper blaster Day 0.50 260.00 130.006 Crowbarman Day 6.00 260.00 1560.007 Stone breaker Day 3.00 260.00 780.008 mazdoor Day 51.00 215.00 10965.00

Total cost of Labour Rs: 15548.60labour component/unit qty 155.50Add contractor's profit and overhead charges 0.14 21.80labour component/unit qty (including contractor's profit) 177.30

Excavation in hard rock requiring blasting including boulders above 0.6 m upto 1.2 m dia. forfoundations of canal cross drainage and other appurtenant structures and placing the

complete with initial lead upto 50 m and initial lift upto 3 m.

Page 4: Book 1

IRR-CCDW

225

ABSTRACT:A. Cost of Materials Rs: 2766.00B. Hire charges of Machinery Rs: 2800.50C. Cost of Labour Rs: 15548.60

Total Rs: 21115.10D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2956.11Total cost for 100.00 cum Rs: 24071.21Rate per cum (A+B+C+D)/100.0 Rs. 240.70

IRR-CCDW-1-6

excavated rock neatly in specified dump area or stack yard as directed etc., complete with

DATA:

RATE ANALYSIS UNIT : 100.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Explosive small dia ( Kelvex-220 ) kg 32.00 54 1728.002 Ordinary detonator No. 8.00 6 48.003 Electric detonator No. 104.00 11 1144.004 Detonating fuse coil Rm 150.00 8 1200.005 Use rate of air hose 2 Nos. Hour 16.00 8.13 130.006 Use rate of drill rod Rm 98.30 22.00 2162.60

Reconditioning charges @ 10% 216.26Total cost of Materials Rs: 6628.86

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Air compressor 8.5 cmm ( diesel ) Hour 8.00 210.40 1683.20

Fuel / Energy charges Hour 8.00 696.10 5568.802 Jack hammer 2 Nos Hour 16.00 13.50 216.00

Fuel / Energy charges Hour 16.00 0.00 0.00Total hire charges of Machinery Rs: 7468.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Air compressor Hour 8.00 136.00 1088.002 Crew for Jack hammer Hour 16.00 212.60 3401.603 Blaster licensed Day 1.00 310.00 310.004 Helper blasting Day 1.00 260.00 260.005 work inspector Day 1.00 275.00 275.006 Crowbarman Day 6.00 260.00 1560.007 Stone breaker Day 6.00 260.00 1560.008 mazdoor Day 51.00 215.00 10965.00

Total cost of Labour Rs: 19419.60labour component/unit qty 194.20Add contractor's profit and overhead charges 0.14 27.20labour component/unit qty (including contractor's profit) 221.40

ABSTRACT:A. Cost of Materials Rs: 6628.86B. Hire charges of Machinery Rs: 7468.00C. Cost of Labour Rs: 19419.60

Total Rs: 33516.46D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 4692.3Total cost for 100.00 cum Rs: 38208.76Rate per cum (A+B+C+D)/100.0 Rs. 382.10

IRR-CCDW-1-7and other appurtenant structures and placing the excavated rock neatly in

initial lift upto 3 m.Hard Rock ( blasting prohibited ) ( Data adopted from MORTH) Unit = cum

DATA: Taking output = 10 cumMechanical Means 10.00 cum

Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. forfoundations of canal cross drainage and other appurtenant structures and placing the

initial lead upto 50 m and initial lift upto 3 m.

Excavation in hard rock with blasting prohibited for foundations of canal cross drainage

or stack yard as directed etc., complete with specified dump area initial lead upto 50 m and

Page 5: Book 1

IRR-CCDW

226

a) LabourSl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 work inspector day 0.20 275.00 55.00 2 Mazdoor day 5.00 215.00 1075.00

Total in Rs. 1130.00

b) MachinerySl No Description Unit Quantity Rate Amount

in Rs. in Rs.1.0 hour 6.00 178.50 1071.00

Fuel/ Energy charges hour 6.00 556.90 3341.40 crew for compressor hour 6.00 136.00 816.00 Total in Rs. 5228.40

labour component/unit qty 522.80Add contractor's profit and overhead charges 0.14 73.20labour component/unit qty (including contractor's profit) 596.00

Abstracta) Labour Rs 1130.00 b) Machinery Rs 5228.40 c) Material Rs 0.00

Total Rs 6358.40

D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 890.18Total cost for 10.00 cum Rs: 7248.58Rate per cum (A+B+C+D)/10.0 Rs. 724.90

IRR-CCDW-1-81.25 m length driven into 32 mm dia hole drilled in bed rock and remaining length embedded inconcrete / masonry including cost of all materials, machinery, labour, drilling and cleaning

upto 50 m and all lifts.DATA:

RATE ANALYSIS UNIT : 10.00 Nos.A. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for grouting kg 5.00 5.50 27.502 25 mm dia steel kg 101.00 41.00 4141.003 Use rate of 32 mm dia drill rod Rm 12.50 22.00 275.00

Reconditioning charges @ 10% 27.504 Use rate of air hose Hour 2.00 8.13 16.25

Total cost of Materials Rs: 4487.25

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Air compressor 8.5 cmm ( diesel ) Hour 1.00 210.40 210.40

Fuel / Energy charges Hour 1.00 696.10 696.102 Jack hammer 2 Nos Hour 2.00 13.50 27.00

Fuel / Energy charges Hour 2.00 0.00 0.00Total hire charges of Machinery Rs: 933.50

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Air compressor Hour 1.00 136.00 136.002 Crew for Jack hammer Hour 2.00 212.60 425.203 Mason Class-II Day 0.50 260.00 130.004 Bar bender Day 0.50 300.00 150.005 work inspector Day 0.50 275.00 137.506 mazdoor Day 1.00 215.00 215.00

Total cost of Labour Rs: 1193.70labour component/unit qty 119.40Add contractor's profit and overhead charges 0.14 16.70labour component/unit qty (including contractor's profit) 136.10

Air Compressor 250 cft with 2 leads of pneumatic breaker

Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel anchor rods with

hole, driving anchor rod, grouting hole with thick cement slurry etc., complete with initial lead

Page 6: Book 1

IRR-CCDW

227

ABSTRACT:A. Cost of Materials Rs: 4487.25B. Hire charges of Machinery Rs: 933.50C. Cost of Labour Rs: 1193.70

Total Rs: 6614.45

Page 7: Book 1

IRR-CCDW

228

D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 926.02Total cost for 10.00 Nos. Rs: 7540.47Rate per each (A+B+C+D)/10.0 Rs. 754.00

IRR-CCDW-2 STEEL AND CEMENT CONCRETE WORKS :

IRR-CCDW-2-1cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,

DATA:

RATE ANALYSIS UNIT : 1000.00 kgA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Rein.Steel with 5 % wastage kg 1050.00 41.00 43050.002 Binding wire 1.25 mm dia kg 8.00 55 440.003 Sundries ( chairs / spacers etc ) LS 3.00 33 99.00

Total cost of Materials Rs: 43589.00

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nil 0.00 0.00 0.00

0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 work inspector Day 1.00 275.00 275.002 Bar bender Day 6.00 300.00 1800.003 mazdoor Day 11.00 215.00 2365.00

Total cost of Labour Rs: 4440.00labour component/unit qty 4.40Add contractor's profit and overhead charges 0.14 0.60labour component/unit qty (including contractor's profit) 5.00

ABSTRACT:A. Cost of Materials Rs: 43589.00B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 4440.00

Total Rs: 48029.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 6724.06Total cost for 1000.00 kg Rs: 54753.06Rate per kg (A+B+C+D)/1000.0 Rs. 54.80

IRR-CCDW-2-2100 x 10 mm angle and 250 x 12 mm plate for sinking for sinking 4.50 m outer diameter foundation wells foundation wells including cost of all materials, machinery, labour, bending, welding, providing anchors etc., complete with initial lead upto 50 m and all lifts.

DETAILS OF FOUNDATION WELL CUTTING EDGE

DATA: RATE ANALYSIS UNIT : 615.00 kgA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Str.Steel angle with 2.5 % wastage kg 216.10 40.00 8644.00

Providing, fabricating and placing in position reinforcement steel bars for RCC works including

complete with initial lead upto 50 and all lifts.

Providing, fabricating and fixing in position structural steel cutting edge consisting of 100 x

Page 8: Book 1

IRR-CCDW

229

2 Str.Steel plate with 2.5 % wastage kg 342.30 43.00 14718.903 Steel for anchors kg 56.60 41.00 2320.604 Acetyline gas cum 0.50 275 137.505 Oxygen gas cum 1.50 40 60.006 Welding electrodes Nos 300.00 9.00 2700.007 Sundries LS 5.00 33 165.00

Total cost of Materials Rs: 28746.00

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Bending machine Hour 8.00 14.50 116.00

Fuel / Energy charges Hour 8.00 60.40 483.202 Welding set Hour 30.00 12.90 387.00

Fuel / Energy charges Hour 30.00 48.30 1449.003 Sundries LS 10.00 33 330.00

Total hire charges of Machinery Rs: 2765.20

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Str. Steel fabricator Day 2.00 310.00 620.002 Welder / Gas cutter Day 5.00 285.00 1425.003 work inspector Day 1.00 275.00 275.004 mazdoor Day 5.00 215.00 1075.00

Total cost of Labour Rs: 3395.00labour component/unit qty 5.50Add contractor's profit and overhead charges 0.14 0.80labour component/unit qty (including contractor's profit) 6.30

ABSTRACT:A. Cost of Materials Rs: 28746.00B. Hire charges of Machinery Rs: 2765.20C. Cost of Labour Rs: 3395.00

Total Rs: 34906.20D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 4886.87Total cost for 615.00 kg Rs: 39793.07Rate per kg (A+B+C+D)/615.0 Rs. 64.70

IRR-CCDW-2-3

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

Data RATE ANALYSIS UNIT : 15.38 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 3998.80 5.50 21993.40Cement for incidentals @ 3 kg / cum kg 46.14 5.50 253.77

2 Coarse aggregate 40-20 mm cum 6.92 975.00 6747.98Coarse aggregate 20-10 mm cum 4.15 1025.00 4256.42Coarse aggregate 10 mm below cum 2.77 750.00 2076.30

3 Fine aggregate cum 6.15 425 2614.604 Super Plasticizer kg 16.00 54 863.745 Use rate of shuttering for 40 uses sqm 15.38 197.64 3039.75

Scaffolding @ of shuttering 10% 303.976 Sundries LS 0.50 33 16.50

Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00

Total cost of Materials Rs: 42166.42

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,

complete with initial lead upto 50 m and all lifts.

Page 9: Book 1

IRR-CCDW

230

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Needle vibrator Hour 8.00 102.00 816.005 work inspector Day 1.00 275.00 275.006 Mason Class-I Day 1.00 285.00 285.007 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 15.38 215.00 3306.70for cleaning/ washing/ curing Day 1.00 215.00 215.00

8 Labour cost for shuttering sqm 15.38 55.65 855.90Labour cost for scaffolding @ 10% 85.59

Total cost of Labour Rs: 10984.64labour component/unit qty 714.20Add contractor's profit and overhead charges 0.14 100.00labour component/unit qty (including contractor's profit) 814.20

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 42166.42B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 10984.64

Total Rs: 54706.71D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 7658.94Total cost for 15.38 cum Rs: 62365.65Rate per cum (A+B+C+D)/15.38 Rs. 4055.00

IRR-CCDW-2-4

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA:

RATE ANALYSIS UNIT : 14.40 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 3600.00 5.50 19800.00Cement for incidentals @ 3 kg / cum kg 43.20 5.50 237.60

2 Coarse aggregate 80-40 mm cum 4.94 560.00 2765.95Coarse aggregate 40-20 mm cum 4.23 975.00 4127.76Coarse aggregate 20-10 mm cum 2.82 1025.00 2892.96Coarse aggregate 10 mm below cum 2.12 750.00 1587.60

3 Fine aggregate cum 5.04 425 2142.004 Super Plasticizer kg 14.40 54 777.605 Use rate of shuttering for 40 uses sqm 14.40 197.64 2846.06

Scaffolding @ of shuttering 10% 284.616 Sundries LS 0.50 33 16.50

Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00

Total cost of Materials Rs: 37478.63

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,

complete with initial lead upto 50 m and all lifts.

Page 10: Book 1

IRR-CCDW

231

in Rs. in Rs.1 Concrete mixer 600/400 ltr ( diesel) Hour 8.00 77.00 616.00

Fuel / Energy charges Hour 8.00 123.80 990.402 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 60 mm dia ( petrol) Hour 8.00 6.20 49.60

Fuel / Energy charges Hour 8.00 18.60 148.80Total hire charges of Machinery Rs: 2359.65

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Needle vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 14.40 215.00 3096.00for cleaning/ washing/ curing Day 1.00 215.00 215.00

8 Labour cost for shuttering sqm 14.40 55.65 801.36Labour cost for scaffolding @ 10% 80.14

Total cost of Labour Rs: 10713.95labour component/unit qty 744.00Add contractor's profit and overhead charges 0.14 104.20labour component/unit qty (including contractor's profit) 848.20

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 37478.63B. Hire charges of Machinery Rs: 2359.65C. Cost of Labour Rs: 10713.95

Total Rs: 50552.23D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 7077.31Total cost for 14.40 cum Rs: 57629.5406331Rate per cum (A+B+C+D)/14.40 Rs. 4002.10

IRR-CCDW-2-5

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSIS UNIT : 16.36 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 3599.20 5.50 19795.60Cement for incidentals @ 3 kg / cum kg 49.08 5.50 269.94

2 Coarse aggregate 40-20 mm cum 7.36 975.00 7177.95Coarse aggregate 20-10 mm cum 4.42 1025.00 4527.63Coarse aggregate 10 mm below cum 2.94 750.00 2208.60

3 Fine aggregate cum 6.54 425 2781.204 Super Plasticizer kg 14.40 54 777.435 Use rate of shuttering for 40 uses sqm 16.36 197.64 3233.44

Scaffolding @ of shuttering 10% 323.346 Sundries LS 0.50 33 16.50

Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00

Total cost of Materials Rs: 41111.63

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,

complete with initial lead upto 50 m and all lifts.

Page 11: Book 1

IRR-CCDW

232

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 16.36 215.00 3517.40

8 for cleaning/ washing/ curing Day 1.00 215.00 215.009 Labour cost for shuttering sqm 16.36 55.65 910.43

Total cost of Labour Rs: 11164.28labour component/unit qty 682.40Add contractor's profit and overhead charges 0.14 95.50labour component/unit qty (including contractor's profit) 777.90

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 41111.63B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 11164.28

Total Rs: 53831.56D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 7536.42Total cost for 16.36 cum Rs: 61367.9818026Rate per cum (A+B+C+D)/16.36 Rs. 3751.10

IRR-CCDW-2-6

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA: RATE ANALYSIS UNIT : 14.55 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 3201.00 5.50 17605.50Cement for incidentals @ 3 kg / cum kg 43.65 5.50 240.08

2 Coarse aggregate 80-40 mm cum 4.99 560.00 2794.76Coarse aggregate 40-20 mm cum 4.28 975.00 4170.76Coarse aggregate 20-10 mm cum 2.85 1025.00 2923.10Coarse aggregate 10 mm below cum 2.14 750.00 1604.14

3 Fine aggregate cum 5.09 425 2164.314 Super Plasticizer kg 12.80 54 691.425 Use rate of shuttering for 40 uses sqm 14.55 197.64 2875.70

Scaffolding @ of shuttering 10% 287.576 Sundries LS 0.50 33 16.50

Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00

Total cost of Materials Rs: 35373.83

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,

complete with initial lead upto 50 m and all lifts.

Page 12: Book 1

IRR-CCDW

233

in Rs. in Rs.1 Concrete mixer 600/400 ltr ( diesel ) Hour 8.00 77.00 616.00

Fuel / Energy charges Hour 8.00 123.80 990.402 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 6.20 49.60

Fuel / Energy charges Hour 8.00 18.60 148.80Total hire charges of Machinery Rs: 2359.65

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 14.55 215.00 3128.25for cleaning/ washing/ curing Day 1.00 215.00 215.00

8 Labour cost for shuttering sqm 14.55 55.65 809.71Labour cost for scaffolding @ 10% 80.97

Total cost of Labour Rs: 10755.38labour component/unit qty 739.20Add contractor's profit and overhead charges 0.14 103.50labour component/unit qty (including contractor's profit) 842.70

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 35373.83B. Hire charges of Machinery Rs: 2359.65C. Cost of Labour Rs: 10755.38

Total Rs: 48488.86D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 6788.44Total cost for 14.55 cum Rs: 55277.2994522Rate per cum (A+B+C+D)/14.55 Rs. 3799.10

IRR-CCDW-2-7

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 310 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSIS UNIT : 14.19 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 4398.90 5.50 24193.95Cement for incidentals @ 3 kg / cum kg 42.57 5.50 234.14

2 Coarse aggregate 40-20 mm cum 6.39 975.00 6225.86Coarse aggregate 20-10 mm cum 3.83 1025.00 3927.08Coarse aggregate 10 mm below cum 2.55 750.00 1915.65

3 Fine aggregate cum 5.68 425 2412.304 Super Plasticizer kg 17.60 54 950.165 Use rate of shuttering for 40 uses sqm 14.19 197.64 2804.55

Scaffolding @ of shuttering 10% 280.466 Sundries LS 0.50 33 16.50

Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00

Total cost of Materials Rs: 42960.65

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,

complete with initial lead upto 50 m and all lifts. ( Cement content : 220 kg / cum )

Page 13: Book 1

IRR-CCDW

234

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 14.19 215.00 3050.85for cleaning/ washing/ curing Day 1.00 215.00 215.00

8 Labour cost for shuttering sqm 14.19 55.65 789.67Labour cost for scaffolding @ 10% 78.97

Total cost of Labour Rs: 10655.94labour component/unit qty 750.90Add contractor's profit and overhead charges 0.14 105.10labour component/unit qty (including contractor's profit) 856.00

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 42960.65B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 10655.94

Total Rs: 55172.24D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 7724.11Total cost for 14.19 cum Rs: 62896.35Rate per cum (A+B+C+D)/14.19 Rs. 4432.40

IRR-CCDW-2-8

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSIS UNIT : 15.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 4800.00 5.50 26400.00Cement for incidentals @ 5 kg / cum kg 75.00 5.50 412.50

2 Coarse aggregate 40-20 mm cum 6.75 975.00 6581.25Coarse aggregate 20-10 mm cum 4.05 1025.00 4151.25Coarse aggregate 10 mm below cum 2.70 750.00 2025.00

3 Fine aggregate cum 6.00 425 2550.004 Super Plasticizer kg 19.20 54 1036.805 Use rate of shuttering sqm 30.00 197.64 5929.29

Scaffolding @ of shuttering 25% 1482.326 Sundries LS 0.50 33 16.50

Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00

Total cost of Materials Rs: 50584.91

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 14: Book 1

IRR-CCDW

235

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65

Page 15: Book 1

IRR-CCDW

236

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying including lifting Day 4.00 215.00 860.00for conveying concrete Day 15.00 215.00 3225.00for cleaning/ washing/ curing Day 1.00 215.00 215.00

8 Labour cost for shuttering sqm 15.00 55.65 834.75Labour cost for scaffolding @ 25% 208.69

Total cost of Labour Rs: 11219.89labour component/unit qty 748.00Add contractor's profit and overhead charges 0.14 104.70labour component/unit qty (including contractor's profit) 852.70

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 50584.91B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 11219.89

Total Rs: 63360.44D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8870.46Total cost for 15.00 cum Rs: 72230.90Rate per cum (A+B+C+D)/15.0 Rs. 4815.40

IRR-CCDW-2-9

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS UNIT : 15.76 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 5200.80 5.50 28604.40Cement for incidentals @ 5 kg / cum kg 78.80 5.50 433.40

2 Coarse aggregate 20-10 mm cum 8.20 1025.00 8400.08Coarse aggregate 10 mm below cum 4.41 750.00 3309.60

3 Fine aggregate cum 7.09 425 3014.104 Super Plasticizer kg 20.80 54 1123.375 Use rate of shuttering sqm 31.52 197.64 6229.70

Scaffolding @ of shuttering 25% 1557.436 Sundries LS 0.50 33 16.50

Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00

Total cost of Materials Rs: 52688.58

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 16: Book 1

IRR-CCDW

237

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 4.00 215.00 860.00for conveying concrete Day 15.76 215.00 3388.40for cleaning/ washing/ curing Day 1.00 215.00 215.00

8 Labour cost for shuttering sqm 31.52 55.65 1754.09Labour cost for scaffolding @ 25% 438.52

Total cost of Labour Rs: 12532.46labour component/unit qty 795.20Add contractor's profit and overhead charges 0.14 111.30labour component/unit qty (including contractor's profit) 906.50

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 52688.58B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 12532.46

Total Rs: 66776.69D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 9348.74Total cost for 15.76 cum Rs: 76125.4308142Rate per cum (A+B+C+D)/15.76 Rs. 4830.30

IRR-CCDW-2-10

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS UNIT : 15.71 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 4398.80 5.50 24193.40Cement for incidentals @ 5 kg / cum kg 78.55 5.50 432.03

2 Coarse aggregate 20-10 mm cum 8.17 1025.00 8373.43Coarse aggregate 10 mm below cum 4.40 750.00 3299.10

3 Fine aggregate cum 7.07 425 3004.544 Super Plasticizer kg 17.60 54 950.145 Use rate of shuttering for 40 uses sqm 31.42 197.64 6209.94

Scaffolding @ of shuttering 25% 1552.486 Sundries LS 0.50 33 16.50Add seignorage charges on CA @ (included in material rate) Rs: 0.00

Add seignorage charges on FA @ (included in material rate) Rs: 0.00Total cost of Materials Rs: 48031.56

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 17: Book 1

IRR-CCDW

238

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 4.00 215.00 860.00for conveying concrete Day 15.71 215.00 3377.65for cleaning/ washing/ curing Day 1.00 215.00 215.00

8 Labour cost for shuttering sqm 31.42 55.65 1748.52Labour cost for scaffolding @ 25% 437.13

Total cost of Labour Rs: 12514.75labour component/unit qty 796.60Add contractor's profit and overhead charges 0.14 111.50labour component/unit qty (including contractor's profit) 908.10

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 48031.56B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 12514.75

Total Rs: 62101.96D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8694.27Total cost for 15.71 cum Rs: 70796.2297088Rate per cum (A+B+C+D)/15.71 Rs. 4506.40

IRR-CCDW-2-11

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS UNIT : 18.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 3960.00 5.50 21780.00Cement for incidentals @ 5 kg / cum kg 90.00 5.50 495.00

2 Coarse aggregate 20-10 mm cum 9.36 1025.00 9594.00Coarse aggregate 10 mm below cum 5.04 750.00 3780.00

3 Fine aggregate cum 8.10 425 3442.504 Super Plasticizer kg 15.84 54 855.365 Use rate of shuttering for 40 uses sqm 36.00 197.64 7115.14

Scaffolding @ of shuttering 25% 1778.796 Sundries LS 0.50 33 16.50

Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00

Total cost of Materials Rs: 48857.29

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.904 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1555.65

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 18: Book 1

IRR-CCDW

239

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Crew for Vibrator Hour 8.00 102.00 816.005 Mason Class-I Day 1.00 285.00 285.006 work inspector Day 1.00 275.00 275.007 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 4.00 215.00 860.00for conveying concrete Day 18.00 215.00 3870.00for cleaning/ washing/ curing Day 1.00 215.00 215.00

8 Labour cost for shuttering sqm 36.00 55.65 2003.40Labour cost for scaffolding @ 25% 500.85

Total cost of Labour Rs: 13325.70labour component/unit qty 740.30Add contractor's profit and overhead charges 0.14 103.60labour component/unit qty (including contractor's profit) 843.90

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 48857.29B. Hire charges of Machinery Rs: 1555.65C. Cost of Labour Rs: 13325.70

Total Rs: 63738.64D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8923.41Total cost for 18.00 cum Rs: 72662.047935Rate per cum (A+B+C+D)/18.0 Rs. 4036.80

IRR-CCDW-2-12

scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. 7500(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS UNIT : 15.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 5250.00 5.50 28875.002 Coarse aggregate 20-10 mm cum 7.80 1025.00 7995.00

Coarse aggregate 10 mm below cum 4.20 750.00 3150.003 Fine aggregate cum 6.75 425 2868.754 Super Plasticizer kg 21.00 54 1134.005 Use rate of curved shutter (40 uses) sqm 82.50 217.41 17936.096 Sundries LS 0.50 33 16.50

Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00

Total cost of Materials Rs: 61975.34

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for well kerb including cost of all materials, machinery, labour, formwork,

etc., complete with initial lead upto 50 m and all lifts.

Page 19: Book 1

IRR-CCDW

240

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 15.00 215.00 3225.00for cleaning/ washing/ curing Day 1.00 215.00 215.00

7 Labour cost for shuttering sqm 82.50 55.65 4591.13Total cost of Labour Rs: 14446.28

labour component/unit qty 963.10Add contractor's profit and overhead charges 0.14 134.80labour component/unit qty (including contractor's profit) 1097.90

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 61975.34B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 14446.28

Total Rs: 77457.56D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 10844.06Total cost for 15.00 cum Rs: 88301.6230023Rate per cum (A+B+C+D)/15.0 Rs. 5886.80

IRR-CCDW-2-13

scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSIS UNIT : 15.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 4800.00 5.50 26400.00Cement for incidentals @ 2 kg / cum kg 30.00 5.50 165.00

2 Coarse aggregate 40-20 mm cum 6.75 975.00 6581.25Coarse aggregate 20-10 mm cum 4.05 1025.00 4151.25Coarse aggregate 10 mm below cum 2.70 750.00 2025.00

3 Fine aggregate cum 6.00 425 2550.004 Super Plasticizer kg 19.20 54 1036.805 Use rate of curved shutter (40 uses) sqm 60.00 217.41 13044.436 Sundries LS 0.50 33 16.50

Add seignorage charges on CA @ R(Included in material ra Rs: 0.00Add seignorage charges on FA @ R(Included in material ra Rs: 0.00

Total cost of Materials Rs: 55970.23

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.55

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for well steining including cost of all materials, machinery, labour, formwork,

etc., complete with initial lead upto 50 m and all lifts.

Page 20: Book 1

IRR-CCDW

241

3 Crew for Vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 15.00 215.00 3225.00for cleaning/ washing/ curing Day 1.00 215.00 215.00

Page 21: Book 1

IRR-CCDW

242

7 Labour cost for shuttering sqm 60.00 55.65 3339.00Total cost of Labour Rs: 13194.15

labour component/unit qty 879.60Add contractor's profit and overhead charges 0.14 123.10labour component/unit qty (including contractor's profit) 1002.70

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 55970.23B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 13194.15

Total Rs: 70200.33D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 9828.05Total cost for 15.00 cum Rs: 80028.377638Rate per cum (A+B+C+D)/15.0 Rs. 5335.20

IRR-CCDW-2-14

machinery, labour, batching, mixing, placing in position as per detailed specifications etc.,

(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS UNIT : 14.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 4900.00 5.50 26950.002 Coarse aggregate 20-10 mm cum 7.28 1025.00 7462.00

Coarse aggregate 10 mm below cum 3.92 750.00 2940.003 Fine aggregate cum 6.30 425 2677.504 Super Plasticizer kg 19.60 54 1058.40

TOTAL Rs: 41087.90Add for tremie arrangement @ 1% Rs: 410.88Add seignorage charges on CA @ (Included in material ra Rs:Add seignorage charges on FA @ (Included in material ra Rs:

Total cost of Materials Rs: 41498.78

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Sundries( Hopper etc. ) LS 5.00 33 165.00

Total hire charges of Machinery Rs: 1053.75

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Fitter shuttering Day 1.00 260.00 260.004 work inspector Day 1.00 275.00 275.005 mazdoor

for erecting/ dismantling tremie Day 4.00 215.00 860.00for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for feeding tremie hopper Day 2.00 215.00 430.00for conveying concrete Day 16.00 215.00 3440.00

Total cost of Labour Rs: 9659.15labour component/unit qty 689.90Add contractor's profit and overhead charges 0.14 96.60labour component/unit qty (including contractor's profit) 786.50

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 41498.78B. Hire charges of Machinery Rs: 1053.75

Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N / sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for well bottom plug by tremie or skip box method including cost of all materials,

complete with initial lead upto 50 m and all lifts. ( Cement content : 350 kg / cum )

Page 22: Book 1

IRR-CCDW

243

C. Cost of Labour Rs: 9659.15Total Rs: 52211.68

Page 23: Book 1

IRR-CCDW

244

D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 7309.64Total cost for 14.00 cum Rs: 59521.319Rate per cum (A+B+C+D)/14.0 Rs. 4251.50

IRR-CCDW-2-15

batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSIS UNIT : 14.29 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 4001.20 5.50 22006.602 Coarse aggregate 40-20 mm cum 6.43 975.00 6269.74

Coarse aggregate 20-10 mm cum 3.86 1025.00 3954.76Coarse aggregate 10 mm below cum 2.57 750.00 1929.15

3 Fine aggregate cum 5.72 425 2429.304 Super Plasticizer kg 16.00 54 864.26

Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 37453.80

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 14.29 215.00 3072.35for cleaning/ washing/ curing Day 1.00 215.00 215.00

Total cost of Labour Rs: 9702.50labour component/unit qty 679.00Add contractor's profit and overhead charges 0.14 95.10labour component/unit qty (including contractor's profit) 774.10

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 37453.80B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 9702.50

Total Rs: 48192.25D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 6746.92Total cost for 14.29 cum Rs: 54939.17Rate per cum (A+B+C+D)/14.29 Rs. 3844.60

IRR-CCDW-2-16

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for well top plug including cost of all materials, machinery, labour, cleaning,

initial lead upto 50 m and all lifts.

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded

Page 24: Book 1

IRR-CCDW

245

scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curingaggregates for well cap including cost of all materials, machinery, labour, formwork,

Page 25: Book 1

IRR-CCDW

246

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS UNIT : 15.76 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 5200.80 5.50 28604.40Cement for incidentals @ 5 kg / cum kg 78.80 5.50 433.40

2 Coarse aggregate 20-10 mm cum 8.20 1025.00 8400.08Coarse aggregate 10 mm below cum 4.41 750.00 3309.60

3 Fine aggregate cum 7.09 425 3014.104 Super Plasticizer kg 20.80 54 1123.375 Use rate of curved shutter (40 uses) sqm 15.76 197.64 3114.856 Sundries LS 0.50 33 16.50

Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 48016.30

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 15.76 215.00 3388.40for cleaning/ washing/ curing Day 1.00 215.00 215.00

7 Labour cost for shuttering sqm 15.76 55.65 877.04Total cost of Labour Rs: 10895.59

labour component/unit qty 691.30Add contractor's profit and overhead charges 0.14 96.80labour component/unit qty (including contractor's profit) 788.10

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 48016.30B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 10895.59

Total Rs: 59947.85D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8392.7Total cost for 15.76 cum Rs: 68340.5480057Rate per cum (A+B+C+D)/15.76 Rs. 4336.30

IRR-CCDW-2-17

formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curingetc., complete with initial lead upto 50 m and all lifts.

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

etc., complete with initial lead upto 50 m and all lifts.

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for piers and abutments including cost of all materials, labour, machinery,

Page 26: Book 1

IRR-CCDW

247

DATA: RATE ANALYSIS UNIT : 14.40 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 3600.00 5.50 19800.00Cement for incidentals @ 5 kg / cum kg 72.00 5.50 396.00

2 Coarse aggregate 80-40 mm cum 4.94 560.00 2765.95Coarse aggregate 40-20 mm cum 4.23 975.00 4127.76Coarse aggregate 20-10 mm cum 2.82 1025.00 2892.96Coarse aggregate 10 mm below cum 2.12 750.00 1587.60

3 Fine aggregate cum 5.04 425 2142.004 Super Plasticizer kg 14.40 54 777.605 Use rate of shuttering for 40 uses sqm 39.60 207.52 8217.996 Scaffolding @ of shuttering 30% 2465.40

Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 45173.26

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 600/400 ltr ( diesel ) Hour 8.00 77.00 616.00

Fuel / Energy charges Hour 8.00 123.80 990.402 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 6.20 49.60

Fuel / Energy charges Hour 8.00 18.60 148.80Total hire charges of Machinery Rs: 1839.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 6.00 215.00 1290.00for conveying concrete Day 14.40 215.00 3096.00for cleaning/ washing/ curing Day 1.00 215.00 215.00

7 Labour cost for shuttering sqm 39.60 55.65 2203.74Labour cost for scaffolding @ 30% 661.12

Total cost of Labour Rs: 13236.01labour component/unit qty 919.20Add contractor's profit and overhead charges 0.14 128.70labour component/unit qty (including contractor's profit) 1047.90

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 45173.26B. Hire charges of Machinery Rs: 1839.95C. Cost of Labour Rs: 13236.01

Total Rs: 60249.22D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8434.89Total cost for 14.40 cum Rs: 68684.1102355Rate per cum (A+B+C+D)/14.40 Rs. 4769.70

IRR-CCDW-2-18

formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for piers and abutments including cost of all materials, labour, machinery,

etc., complete with initial lead upto 50 m and all lifts.

Page 27: Book 1

IRR-CCDW

248

DATA: RATE ANALYSIS UNIT : 14.55 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 3201.00 5.50 17605.50Cement for incidentals @ 5 kg / cum kg 72.75 5.50 400.13

2 Coarse aggregate 80-40 mm cum 4.99 560.00 2794.76Coarse aggregate 40-20 mm cum 4.28 975.00 4170.76Coarse aggregate 20-10 mm cum 2.85 1025.00 2923.10Coarse aggregate 10 mm below cum 2.14 750.00 1604.14

3 Fine aggregate cum 5.09 425 2164.314 Super Plasticizer kg 12.80 54 691.425 Use rate ofshuttering for 40 uses sqm 40.01 207.52 8303.596 Scaffolding @ of shuttering 30% 2491.08

Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 43148.78

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 600/400 ltr ( diesel ) Hour 8.00 77.00 616.00

Fuel / Energy charges Hour 8.00 123.80 990.402 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 6.20 49.60

Fuel / Energy charges Hour 8.00 18.60 148.80Total hire charges of Machinery Rs: 1839.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 6.00 215.00 1290.00for conveying concrete Day 14.55 215.00 3128.25for cleaning/ washing/ curing Day 1.00 215.00 215.00

7 Labour cost for shuttering sqm 40.01 55.65 2226.70Labour cost for scaffolding @ 30% 668.01

Total cost of Labour Rs: 13298.10labour component/unit qty 914.00Add contractor's profit and overhead charges 0.14 128.00labour component/unit qty (including contractor's profit) 1042.00

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 43148.78B. Hire charges of Machinery Rs: 1839.95C. Cost of Labour Rs: 13298.10

Total Rs: 58286.83D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8160.16Total cost for 14.55 cum Rs: 66446.9933213Rate per cum (A+B+C+D)/14.55 Rs. 4566.80

IRR-CCDW-2-19

formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSIS UNIT : 16.36 cum

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for piers and abutments including cost of all materials, labour, machinery,

etc., complete with initial lead upto 50 m and all lifts.

Page 28: Book 1

IRR-CCDW

249

A. MATERIALS:Sl No Particulars Unit Quantity Rate Amount

in Rs. in Rs.1 Cement for mix kg 3599.20 5.50 19795.60

Cement for incidentals @ 5 kg / cum kg 81.80 5.50 449.902 Coarse aggregate 40-20 mm cum 7.36 975.00 7177.95

Page 29: Book 1

IRR-CCDW

250

Coarse aggregate 20-10 mm cum 4.42 1025.00 4527.63Coarse aggregate 10 mm below cum 2.94 750.00 2208.60

3 Fine aggregate cum 6.54 425 2781.204 Super Plasticizer kg 14.40 54 777.435 Use rate of shuttering for 40 uses sqm 44.99 207.52 9336.556 Scaffolding @ of shuttering 30% 2800.96

Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 49855.82

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 5.00 215.00 1075.00for conveying concrete Day 16.36 215.00 3517.40for cleaning/ washing/ curing Day 1.00 215.00 215.00

7 Labour cost for shuttering sqm 44.99 55.65 2503.69Labour cost for scaffolding @ 30% 751.11

Total cost of Labour Rs: 13832.35labour component/unit qty 845.50Add contractor's profit and overhead charges 0.14 118.40labour component/unit qty (including contractor's profit) 963.90

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 49855.82B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 13832.35

Total Rs: 64724.12D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 9061.38Total cost for 16.36 cum Rs: 73785.5025565Rate per cum (A+B+C+D)/16.36 Rs. 4510.10

IRR-CCDW-2-20

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.

DATA: RATE ANALYSIS UNIT : 16.25 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 5200.00 5.50 28600.00Cement for incidentals @ 5 kg / cum kg 81.25 5.50 446.88

2 Coarse aggregate 40-20 mm cum 7.31 975.00 7129.69Coarse aggregate 20-10 mm cum 4.39 1025.00 4497.19

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for cantiliver / counterfort retaining walls including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 30: Book 1

IRR-CCDW

251

Coarse aggregate 10 mm below cum 2.93 750.00 2193.753 Fine aggregate cum 6.50 425 2762.504 Super Plasticizer kg 20.80 54 1123.205 Use rate of shuttering for 40 uses sqm 52.81 197.64 10438.01

Scaffolding @ of shuttering 25% 2609.506 Sundries LS 0.50 33 16.50

Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 59817.22

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 5.00 215.00 1075.00for conveying concrete Day 16.25 215.00 3493.75for cleaning/ washing/ curing Day 1.00 215.00 215.00

7 Labour cost for shuttering sqm 52.81 55.65 2939.02Labour cost for scaffolding @ 25% 734.75

Total cost of Labour Rs: 14227.67labour component/unit qty 875.50Add contractor's profit and overhead charges 0.14 122.60labour component/unit qty (including contractor's profit) 998.10

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 59817.22B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 14227.67

Total Rs: 75080.84D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 10511.32Total cost for 16.25 cum Rs: 85592.1553387Rate per cum (A+B+C+D)/16.25 Rs. 5267.20

IRR-CCDW-2-21

labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum, plums of size 150 to 80 mm : 0.25cum ) 2.82

DATA: RATE ANALYSIS UNIT : 18.09 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 4703.40 5.50 25868.70Cement for incidentals @ 4 kg / cum kg 72.36 5.50 397.98

2 Coarse aggregate 40-20 mm cum 6.92 975.00 6746.44

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates with placing and sinking plums of size 150 to 80 mm upto 15 percent for gravitytype retaining walls / piers / abutments etc., including cost of all materials, machinery,

finishing, curing etc.,complete with initial lead upto 50 m and all lifts.

Page 31: Book 1

IRR-CCDW

252

Coarse aggregate 20-10 mm cum 4.15 1025.00 4255.45Coarse aggregate 10 mm below cum 2.77 750.00 2075.83

3 Plums of size 150 to 80 mm cum 4.52 310 1401.984 Fine aggregate cum 6.15 425 2614.015 Super Plasticizer kg 18.81 54 1015.93

Use rate of shuttering for 40 uses sqm 49.75 197.64 9832.246 Scaffolding @ of shuttering 30% 2949.67

Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 57158.22

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 6.20 49.60

Fuel / Energy charges Hour 8.00 18.60 148.80Total hire charges of Machinery Rs: 1087.15

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 5.00 215.00 1075.00for placing plums Day 2.00 215.00 430.00for conveying concrete Day 15.38 215.00 3306.70for conveying plums Day 2.00 215.00 430.00for cleaning/ washing/ curing Day 1.00 215.00 215.00

7 Labour for shuttering sqm 49.75 55.65 2768.45Labour for scaffolding @ 30% 830.53

Total cost of Labour Rs: 14825.83labour component/unit qty 819.60Add contractor's profit and overhead charges 0.14 114.70labour component/unit qty (including contractor's profit) 934.30

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 57158.22B. Hire charges of Machinery Rs: 1087.15C. Cost of Labour Rs: 14825.83

Total Rs: 73071.20D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 10229.97Total cost for 18.09 cum Rs: 83301.17Rate per cum (A+B+C+D)/18.09 Rs. 4604.80

IRR-CCDW-2-22

batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSIS UNIT : 15.38 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 3998.80 5.50 21993.40

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,gradedaggregates for cast in-situ pipes including cost of all materials, machinery, labour, cleaning,

initial lead upto 50 m and all lifts.

Page 32: Book 1

IRR-CCDW

253

Cement for incidentals @ 5 kg / cum kg 76.90 5.50 422.952 Coarse aggregate 40-20 mm cum 6.92 975.00 6747.98

Coarse aggregate 20-10 mm cum 4.15 1025.00 4256.42Coarse aggregate 10 mm below cum 2.77 750.00 2076.30

3 Fine aggregate cum 6.15 425 2614.604 Super Plasticizer kg 16.00 54 863.745 Use rate of shuttering for 40 uses sqm 30.76 207.52 6383.47

Scaffolding @ of shuttering 15% 957.526 Sundries LS 0.50 33 16.50

Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 46332.87

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 15.38 215.00 3306.70for cleaning/ washing/ curing Day 1.00 215.00 215.00

7 Labour for shuttering sqm 30.76 55.65 1711.79Labour for scaffolding @ 15% 256.77

Total cost of Labour Rs: 11905.41labour component/unit qty 774.10Add contractor's profit and overhead charges 0.14 108.40labour component/unit qty (including contractor's profit) 882.50

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 46332.87B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 11905.41

Total Rs: 59274.23D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8298.39Total cost for 15.38 cum Rs: 67572.6227247Rate per cum (A+B+C+D)/15.38 Rs. 4393.50

IRR-CCDW-2-23

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA: RATE ANALYSIS UNIT : 14.40 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 3600.00 5.50 19800.00Cement for incidentals @ 5 kg / cum kg 72.00 5.50 396.00

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for cast in-situ pipes including cost of all materials, labour, machinery, formwork,

complete with initial lead upto 50 m and all lifts.

Page 33: Book 1

IRR-CCDW

254

2 Coarse aggregate 80-40 mm cum 4.94 560.00 2765.95Coarse aggregate 40-20 mm cum 4.23 975.00 4127.76Coarse aggregate 20-10 mm cum 2.82 1025.00 2892.96Coarse aggregate 10 mm below cum 2.12 750.00 1587.60

3 Fine aggregate cum 5.04 425 2142.004 Super Plasticizer kg 14.40 54 777.605 Use rate of shuttering for 40 uses sqm 28.80 207.52 5976.726 Scaffolding @ of shuttering 15% 896.51

Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 41363.10

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 600/400 ltr ( diesel ) Hour 8.00 77.00 616.00

Fuel / Energy charges Hour 8.00 123.80 990.402 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 6.20 49.60

Fuel / Energy charges Hour 8.00 18.60 148.80Total hire charges of Machinery Rs: 1839.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 14.40 215.00 3096.00for cleaning/ washing/ curing Day 1.00 215.00 215.00

7 Labour cost for shuttering sqm 28.80 55.65 1602.72Labour cost for scaffolding @ 15% 240.41

Total cost of Labour Rs: 11569.28labour component/unit qty 803.40Add contractor's profit and overhead charges 0.14 112.50labour component/unit qty (including contractor's profit) 915.90

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 41363.10B. Hire charges of Machinery Rs: 1839.95C. Cost of Labour Rs: 11569.28

Total Rs: 54772.33D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 7668.13Total cost for 14.40 cum Rs: 62440.46Rate per cum (A+B+C+D)/14.40 Rs. 4336.10

IRR-CCDW-2-24

scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS UNIT : 15.76 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 5200.80 5.50 28604.40Cement for incidentals @ 5 kg / cum kg 78.80 5.50 433.40

2 Coarse aggregate 20-10 mm cum 8.20 1025.00 8400.08

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for deck slab & kerb including cost of all materials,machinery, labour, formwork,

etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 300 kg / cum )

Page 34: Book 1

IRR-CCDW

255

Coarse aggregate 10 mm below cum 4.41 750.00 3309.603 Fine aggregate cum 7.09 425 3014.104 Super Plasticizer kg 20.80 54 1123.375 Use rate of shuttering for 30 uses sqm 39.40 242.86 9568.57

Scaffolding @ of shuttering 250% 23921.436 Sundries LS 1.00 33 33.00

Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 78407.95

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 2.00 285.00 570.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 4.00 215.00 860.00for conveying concrete Day 15.76 215.00 3388.40for cleaning/ washing/ curing Day 1.00 215.00 215.00

7 Labour cost for shuttering sqm 39.40 55.65 2192.61Labour cost for scaffolding @ 250% 5481.53

Total cost of Labour Rs: 18192.68labour component/unit qty 1154.40Add contractor's profit and overhead charges 0.14 161.60labour component/unit qty (including contractor's profit) 1316.00

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 78407.95B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 18192.68

Total Rs: 97636.59D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 13669.12Total cost for 15.76 cum Rs: 111305.71Rate per cum (A+B+C+D)/15.76 Rs. 7062.50

IRR-CCDW-2-25

formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,

kg / cum )Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.

(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS UNIT : 15.76 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 5200.80 5.50 28604.40Cement for incidentals @ 5 kg / cum kg 78.80 5.50 433.40

2 Coarse aggregate 20-10 mm cum 8.20 1025.00 8400.08Coarse aggregate 10 mm below cum 4.41 750.00 3309.60

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for columns and beams including cost of all materials, labour, machinery,

finishing, curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content : 300

Page 35: Book 1

IRR-CCDW

256

3 Fine aggregate cum 7.09 425 3014.104 Super Plasticizer kg 20.80 54 1123.375 Use rate of shuttering sqm 78.80 197.64 15574.26

Scaffolding @ of shuttering 50% 7787.136 Sundries LS 1.00 33 33.00

Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 68279.34

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 3.00 215.00 645.00for conveying concrete Day 15.76 215.00 3388.40for cleaning/ washing/ curing Day 1.00 215.00 215.00

7 Labour cost for shuttering sqm 78.80 55.65 4385.22Labour cost for scaffolding @ 50% 2192.61

Total cost of Labour Rs: 16596.38labour component/unit qty 1053.10Add contractor's profit and overhead charges 0.14 147.40labour component/unit qty (including contractor's profit) 1200.50

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 68279.34B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 16596.38

Total Rs: 85911.67D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 12027.63Total cost for 15.76 cum Rs: 97939.30Rate per cum (A+B+C+D)/15.76 Rs. 6214.40

IRR-CCDW-2-26

cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS UNIT : 15.76 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 5200.80 5.50 28604.40Cement for incidentals @ 5 kg / cum kg 78.80 5.50 433.40

2 Coarse aggregate 20-10 mm cum 8.20 1025.00 8400.08Coarse aggregate 10 mm below cum 4.41 750.00 3309.60

3 Fine aggregate cum 7.09 425 3014.10

Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for wearing coat including cost of all materials, machinery, labour, formwork,

finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 mand all lifts. ( Cement content : 300 kg / cum )

Page 36: Book 1

IRR-CCDW

257

4 Super Plasticizer kg 20.80 54 1123.375 Use rate of shuttering sqm 7.88 197.64 1557.436 Sundries ( asphalt mortar etc ) LS 5.00 33 165.00

Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 46607.38

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 2.00 285.00 570.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 4.00 215.00 860.00for conveying concrete Day 15.76 215.00 3388.40for cleaning/ washing/ curing Day 2.00 215.00 430.00

7 Labour cost for shuttering sqm 7.88 55.65 438.52Total cost of Labour Rs: 11172.07

labour component/unit qty 708.90Add contractor's profit and overhead charges 0.14 99.20labour component/unit qty (including contractor's profit) 808.10

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 46607.38B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 11172.07

Total Rs: 58815.40D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 8234.16Total cost for 15.76 cum Rs: 67049.56Rate per cum (A+B+C+D)/15.76 Rs. 4254.40

IRR-CCDW-2-27 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than

scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS UNIT : 15.76 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 5200.80 5.50 28604.40Cement for incidentals @ 5 kg / cum kg 78.80 5.50 433.40

2 Coarse aggregate 20-10 mm cum 8.20 1025.00 8400.08Coarse aggregate 10 mm below cum 4.41 750.00 3309.60

3 Fine aggregate cum 7.09 425 3014.104 Super Plasticizer kg 20.80 54 1123.375 Use rate of shuttering for 40 uses sqm 70.92 197.64 14016.83

Scaffolding @ of shuttering 25% 3504.216 Sundries LS 0.50 33 16.50

20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for troughs including cost of all materials, machinery, labour, formwork,

etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 300 kg / cum )

Page 37: Book 1

IRR-CCDW

258

Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 62422.49

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Needle vibrator 40 mm dia ( diesel ) Hour 8.00 6.00 48.00

Fuel / Energy charges Hour 8.00 12.40 99.20Total hire charges of Machinery Rs: 1035.95

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Needle vibrator Hour 8.00 102.00 816.004 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00for laying Day 5.00 215.00 1075.00for conveying concrete Day 15.76 215.00 3388.40for cleaning/ washing/ curing Day 1.00 215.00 215.00

7 Labour cost for shuttering sqm 70.92 55.65 3946.70Labour cost for scaffolding @ 25% 986.67

Total cost of Labour Rs: 15381.92labour component/unit qty 976.00Add contractor's profit and overhead charges 0.14 136.60labour component/unit qty (including contractor's profit) 1112.60

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 62422.49B. Hire charges of Machinery Rs: 1035.95C. Cost of Labour Rs: 15381.92

Total Rs: 78840.36D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 11037.65Total cost for 15.76 cum Rs: 89878.0133319Rate per cum (A+B+C+D)/15.76 Rs. 5702.90

IRR-CCDW-3 FOUNDATION WELL SINKING WORKS :

IRR-CCDW-3-1DATA: Unit = Running meter

Taking output = 1mdiameter of well = 6.00m

(i) Depth below bed level upto 3.0mRate of sinking = 0.50 m /hour

a) Labour0.12 Mate (Mason Cl- ll ) 260.00 day 31.201.00 Sinker ( skilled) 285.00 day 285.002.00 Sinking helper ( Semi skilled) 215.00 day 430.00

sub total (a) 746.20b) Machinery

2.00 Hire & running charges of crane with grab 422.30 hour 844.60 bucket of 0.75 cum capacity and accessories.Fuel Charges 233.90 hour 467.80Crew Charges 106.30 hour 212.60Consumables in sinking @ 10% of machinery charges 152.50

sub total (b) 1677.50sub total (a+b) 2423.70

14.00% 339.32

Sinking RCC wells vertically for foundation of piers and abutments in all kinds of soil, sand and soft rock by approved well sinking method including cost of all materials, machinery, labour, kent - ledge arrangements, disposal of excavated material as directed etc., complete with lead upto 50 m for disposal of excavated material.(diameter of well 6.00m)

c) Add for Contractor's profit and overhead charges on (A+B)

Page 38: Book 1

IRR-CCDW

259

Rate per metre = (a+b+c)/1.0 2763.02or say ( Rate upto 3.0m for 6.0 m well sinking ) 2763.00labour component/unit qty 898.70Contractor's profit and overhead charges 14.00% 125.80labour component/unit qty(including contractor's profit) 1024.50

(ii) Beyond 3m and upto 10m depthRate of sinking = 0.33 m per hour.

a) Labour0.15 Mate (Mason Cl- ll ) 260.00 day 39.001.25 Sinker ( skilled) 285.00 day 356.252.50 Sinking helper ( Semi skilled) 215.00 day 537.50

sub total (a) 932.75b) Machinery

3.00 Hire & running charges of crane with grab 422.30 hour 1266.90 bucket of 0.75 cum capacity and accessories.Fuel Charges 233.90 hour 701.70Crew Charges 106.30 hour 318.90Consumables in sinking @ 10% of machinery charges 228.75

sub total (b) 2516.25sub total (a+b) 3449.00

14.00% 482.86

Rate per metre = (a+b+c) 3931.86or say ( Rate for 3.0m to 10m well sinking ) 3931.90

labour component/unit qty 1161.50Contractor's profit and overhead charges 0.14 162.60labour component/unit qty(including contractor's profit) 1324.10

IRR-CCDW-3-2ramming as directed including cost of all materials, machinery, labour etc., complete with

DATA: RATE ANALYSIS UNIT : 15.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Sand unscreened cum 15.75 325 5118.750.00 0.00

Add seignorage charges on Sand @ Rs: (Included in material ra Rs: 0.00Total cost of Materials Rs: 5118.75

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nill 0.00 0.00 0.00

0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 work inspector Day 0.25 275.00 68.752 mazdoor Day 4.00 215.00 860.00

Total cost of Labour Rs: 928.75labour component/unit qty 61.90Add contractor's profit and overhead charges 0.14 8.70labour component/unit qty (including contractor's profit) 70.60

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 5118.75B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 928.75

Total Rs: 6047.50D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 846.65Total cost for 15.00 cum Rs: 6894.15

c) Add for Contractor's profit and overhead charges on (A+B)

Filling foundation wells with sand in layers of 25 to 30 cm and compacting by watering,

initial lead upto 50 m and all lifts.

Page 39: Book 1

IRR-CCDW

260

Rate per cum (A+B+C+D)/15.0 Rs. 459.60

IRR-CCDW-4 MASONRY WORKS :

IRR-CCDW-4-1

cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging

(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,Stone Chips : 0.15 cum)

DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 1430.00 5.50 7865.002 Rubble stones cum 8.50 265 2252.503 Stone chips cum 1.50 310 465.004 Sand screened cum 4.00 425 1700.00

Add seignorage charges on Stone@ Rs(Included in material ra Rs: 0.00Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00

Total cost of Materials Rs: 12282.50

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.902 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.95Total hire charges of Machinery Rs: 554.85

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Water tanker Hour 1.00 106.30 106.302 Crew for Pump Hour 0.50 71.10 35.553 work inspector Day 1.00 275.00 275.004 Mason Class-I Day 1.00 285.00 285.005 Mason Class-II Day 2.00 260.00 520.006 mazdoor

for conveying rubble stones Day 4.00 215.00 860.00for preparing mortar Day 2.00 215.00 430.00for loading mortar pans Day 1.00 215.00 215.00for laying & packing mortar Day 3.00 215.00 645.00for washing rubble / finishing / curing Day 1.00 215.00 215.00for conveying mortar / chips Day 4.00 215.00 860.00

Total cost of Labour Rs: 4446.85labour component/unit qty 444.70Add contractor's profit and overhead charges 0.14 62.30labour component/unit qty (including contractor's profit) 507.00

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 12282.50B. Hire charges of Machinery Rs: 554.85C. Cost of Labour Rs: 4446.85

Total Rs: 17284.20D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2419.79Total cost for 10.00 cum Rs: 19703.99Rate per cum (A+B+C+D)/10.0 Rs. 1970.40

IRR-CCDW-4-2

cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging

(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,Stone Chips : 0.15 cum)

Providing and constructing un-coursed rubble stone masonry with approved stones inCM 1 : 4 proportion for sub-structure portions of return walls / abutments etc., including

stone chips, curing etc., complete with initial lead upto 50 m and all lifts.

Providing and constructing un-coursed rubble stone masonry with approved stones inCM 1 : 4 proportion for super-structure portions of return walls / abutments etc., including

stone chips, curing etc., complete with initial lead upto 50 m and all lifts.

Page 40: Book 1

IRR-CCDW

261

DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 1430.00 5.50 7865.002 Rubble stones cum 8.50 265 2252.503 Stone chips cum 1.50 310 465.004 Sand screened cum 4.00 425 1700.00

TOTAL Rs: 12282.50Add for scaffolding @ 2.5% Rs: 307.06Add seignorage charges on Stone@ Rs(Included in material ra Rs:Add seignorage charges on Sand @ Rs(Included in material ra Rs:

Total cost of Materials Rs: 12589.56

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.902 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.95Total hire charges of Machinery Rs: 554.85

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Water tanker Hour 1.00 106.30 106.302 Crew for Pump Hour 0.50 71.10 35.553 work inspector Day 1.00 275.00 275.004 Mason Class-I Day 1.00 285.00 285.005 Mason Class-II Day 2.00 260.00 520.006 mazdoor

for conveying rubble stones Day 4.00 215.00 860.00for preparing mortar Day 2.00 215.00 430.00for loading mortar pans Day 1.00 215.00 215.00for laying & packing mortar Day 3.00 215.00 645.00for washing rubble / finishing / curing Day 1.00 215.00 215.00for conveying mortar / chips Day 4.00 215.00 860.00

TOTAL Rs: 4446.85Add for labour for scaffolding @ 2.5% Rs: 111.17

Total cost of Labour Rs: 4558.02labour component/unit qty 455.80Add contractor's profit and overhead charges 0.14 63.80labour component/unit qty (including contractor's profit) 519.60

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 12589.56B. Hire charges of Machinery Rs: 554.85C. Cost of Labour Rs: 4558.02

Total Rs: 17702.43D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2478.34Total cost for 10.00 cum Rs: 20180.77375Rate per cum (A+B+C+D)/10.0 Rs. 2018.10

IRR-CCDW-4-3stones from approved source including cost of all materials, machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with

(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones 25 x 25x 45 cm : 60 Nos)

DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 1330.00 5.50 7315.002 Header stones 25x25x45 cm Nos 60.00 32 1920.003 Khandki stones 25x25x30 cm Nos 180.00 12 2160.004 Rubble stones cum 4.50 265 1192.50

Providing and constructing coursed rubble masonry second sort in CM 1:4 proportion with

initial lead upto 50 m and initial lift upto 3m.

Page 41: Book 1

IRR-CCDW

262

5 Stone chips cum 1.50 310 465.006 Sand screened cum 3.50 425 1487.50

TOTAL Rs: 14540.00Add for scaffolding materials @ 2.5% Rs: 363.50Add seignorage charges on Stone@ Rs(Included in material ra Rs:Add seignorage charges on Sand @ Rs(Included in material ra Rs:

Total cost of Materials Rs: 14903.50

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.902 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.95Total hire charges of Machinery Rs: 554.85

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Water tanker Hour 1.00 106.30 106.302 Crew for Pump Hour 0.50 71.10 35.553 work inspector Day 1.00 275.00 275.004 Stone chiseller Cl -II Day 3.00 260.00 780.005 Mason Class-I Day 1.00 285.00 285.006 Mason Class-II Day 2.00 260.00 520.007 mazdoor

for conveying stones / rubble Day 4.00 215.00 860.00for preparation of mortar Day 3.00 215.00 645.00for loading mortar pans Day 1.00 215.00 215.00for laying & packing mortar Day 3.00 215.00 645.00for washing rubble / finishing / curing Day 1.00 215.00 215.00for conveying mortar / chips Day 2.00 215.00 430.00

TOTAL Rs: 5011.85Add for labour for scaffolding @ 2.5% Rs: 125.30

Total cost of Labour Rs: 5137.15labour component/unit qty 513.70Add contractor's profit and overhead charges 0.14 71.90labour component/unit qty (including contractor's profit) 585.60

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 14903.50B. Hire charges of Machinery Rs: 554.85C. Cost of Labour Rs: 5137.15

Total Rs: 20595.50D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2883.37Total cost for 10.00 cum Rs: 23478.86625Rate per cum (A+B+C+D)/10.0 Rs. 2347.90

IRR-CCDW-4-4 Providing and constructing coursed rubble masonry first sort in CM 1:4 proportion withstones from approved source including cost of all materials, machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete withinitial lead upto 50 m and initial lift upto 3 m.(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones 25 x 25x 45 cm : 60 Nos)

DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 1330.00 5.50 7315.002 Header stones 25x25x45 cm Nos 60.00 32 1920.003 Khandki stones 25x25x30 cm Nos 180.00 12 2160.004 Rubble stones cum 4.50 265 1192.505 Stone chips cum 1.50 310 465.006 Sand screened cum 3.50 425 1487.50

TOTAL Rs: 14540.00Add for scaffolding materials @ 2.5% Rs: 363.50Add seignorage charges on Stone@ Rs(Included in material ra Rs:Add seignorage charges on Sand @ Rs(Included in material ra Rs:

Page 42: Book 1

IRR-CCDW

263

Total cost of Materials Rs: 14903.50

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.902 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.95Total hire charges of Machinery Rs: 554.85

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Water tanker Hour 1.00 106.30 106.302 Crew for Pump Hour 0.50 71.10 35.553 work inspector Day 1.00 275.00 275.004 Stone chiseller Cl -II Day 6.00 260.00 1560.005 Mason Class-I Day 1.00 285.00 285.006 Mason Class-II Day 2.00 260.00 520.007 mazdoor8 for conveying rubble/ stones Day 4.00 215.00 860.00

for preparation of mortar Day 3.00 215.00 645.00for loading mortar pans Day 1.00 215.00 215.00for laying & packing mortar Day 3.00 215.00 645.00for washing rubble / finishing / curing Day 1.00 215.00 215.00for conveying mortar / chips Day 2.00 215.00 430.00

TOTAL Rs: 5791.85Add for labour for scaffolding @ 2.5% Rs: 144.80

Total cost of Labour Rs: 5936.65labour component/unit qty 593.70Add contractor's profit and overhead charges 0.14 83.10labour component/unit qty (including contractor's profit) 676.80

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 14903.50B. Hire charges of Machinery Rs: 554.85C. Cost of Labour Rs: 5936.65

Total Rs: 21395.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2995.3Total cost for 10.00 cum Rs: 24390.29625Rate per cum (A+B+C+D)/10.0 Rs. 2439.00

IRR-CCDW-4-5proportion by volume including raking and cleaning joints for 50 mm depth, pressing cementmortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with

DATA: RATE ANALYSIS UNIT : 100.00 sqmA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 456.00 5.50 2508.002 Sand screened cum 0.75 425 318.75

TOTAL Rs: 2826.75Add for scaffolding / ramps etc @ 2.5% Rs: 70.67Add seignorage charges on Sand @ Rs(Included in material ra Rs:

Total cost of Materials Rs: 2897.42

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nil 0.00 0.00 0.00

( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.

Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 2

initial lead upto 50 m and all lifts.

Page 43: Book 1

IRR-CCDW

264

1 Mason Cl- I Day 10.00 285.00 2850.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 10.00 215.00 2150.00

Total cost of Labour Rs: 5275.00labour component/unit qty 52.80Add contractor's profit and overhead charges 0.14 7.40labour component/unit qty (including contractor's profit) 60.20

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2897.42B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 5275.00

Total Rs: 8172.42D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1144.14Total cost for 100.00 sqm Rs: 9316.55875Rate per sqm (A+B+C+D)/100.0 Rs. 93.20

IRR-CCDW-4-6proportion by volume including raking and cleaning joints for 50 mm depth, pressing cementmortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with

DATA: RATE ANALYSIS UNIT : 100.00 sqmA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 322.00 5.50 1771.002 Sand screened cum 0.75 425 318.75

TOTAL Rs: 2089.75Add for scaffolding / ramps etc @ 2.5% Rs: 52.24Add seignorage charges on Sand @ Rs(Included in material ra Rs:

Total cost of Materials Rs: 2141.99

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nil 0.00 0.00 0.00

( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- I Day 10.00 285.00 2850.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 10.00 215.00 2150.00

Total cost of Labour Rs: 5275.00labour component/unit qty 52.80Add contractor's profit and overhead charges 0.14 7.40labour component/unit qty (including contractor's profit) 60.20

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2141.99B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 5275.00

Total Rs: 7416.99D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1038.38Total cost for 100.00 sqm Rs: 8455.37375Rate per sqm (A+B+C+D)/100.0 Rs. 84.60

IRR-CCDW-4-7of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,

DATA: RATE ANALYSIS UNIT : 100.00 sqmA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 629.00 5.50 3459.50

Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 3

initial lead upto 50 m and all lifts.

Providing 12 mm thick plastering in cement mortar 1:3 proportion by volume including cost

complete with initial lead upto 50 m and all lifts.

Page 44: Book 1

IRR-CCDW

265

2 Sand screened cum 1.32 425 561.00TOTAL Rs: 4020.50

Add for scaffolding / ramps etc @ 2.5% Rs: 100.51Add seignorage charges on Sand @ Rs(Included in material ra Rs:

Total cost of Materials Rs: 4121.01

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nil 0.00 0.00 0.00

( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- I Day 10.00 285.00 2850.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 20.00 215.00 4300.00

Total cost of Labour Rs: 7425.00labour component/unit qty 74.30Add contractor's profit and overhead charges 0.14 10.40labour component/unit qty (including contractor's profit) 84.70

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 4121.01B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 7425.00

Total Rs: 11546.01D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1616.44Total cost for 100.00 sqm Rs: 13162.4525Rate per sqm (A+B+C+D)/100.0 Rs. 131.60

IRR-CCDW-4-8of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,

DATA: RATE ANALYSIS UNIT : 100.00 sqmA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 472.00 5.50 2596.002 Sand screened cum 1.32 425 561.00

TOTAL Rs: 3157.00Add for scaffolding / ramps etc @ 2.5% Rs: 78.93Add seignorage charges on Sand @ Rs(Included in material ra Rs:

Total cost of Materials Rs: 3235.93

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nil 0.00 0.00 0.00

( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- I Day 10.00 285.00 2850.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 20.00 215.00 4300.00

Total cost of Labour Rs: 7425.00labour component/unit qty 74.30Add contractor's profit and overhead charges 0.14 10.40labour component/unit qty (including contractor's profit) 84.70

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 3235.93B. Hire charges of Machinery Rs: 0.00

Providing 12 mm thick plastering in cement mortar 1:4 proportion by volume including cost

complete with initial lead upto 50 m and all lifts.

Page 45: Book 1

IRR-CCDW

266

C. Cost of Labour Rs: 7425.00Total Rs: 10660.93

D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1492.53Total cost for 100.00 sqm Rs: 12153.455Rate per sqm (A+B+C+D)/100.0 Rs. 121.50

IRR-CCDW-4-9of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,

DATA: RATE ANALYSIS UNIT : 100.00 sqmA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 1050.00 5.50 5775.002 Sand screened cum 2.20 425 935.00

TOTAL Rs: 6710.00Add for scaffolding / ramps etc @ 2.5% Rs: 167.75Add seignorage charges on Sand @ Rs(Included in material ra Rs:

Total cost of Materials Rs: 6877.75

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nil 0.00 0.00 0.00

( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- I Day 15.00 285.00 4275.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 25.00 215.00 5375.00

Total cost of Labour Rs: 9925.00labour component/unit qty 99.30Add contractor's profit and overhead charges 0.14 13.90labour component/unit qty (including contractor's profit) 113.20

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 6877.75B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 9925.00

Total Rs: 16802.75D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2352.39Total cost for 100.00 sqm Rs: 19155.14Rate per sqm (A+B+C+D)/100.0 Rs. 191.60

IRR-CCDW-4-10of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,

DATA: RATE ANALYSIS UNIT : 100.00 sqmA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 788.00 5.50 4334.002 Sand screened cum 2.20 425 935.00

TOTAL Rs: 5269.00Add for scaffolding / ramps etc @ 2.5% Rs: 131.73Add seignorage charges on Sand @ Rs(Included in material ra Rs:

Total cost of Materials Rs: 5400.73

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nil 0.00 0.00 0.00

Providing 20 mm thick plastering in cement mortar 1:3 proportion by volume including cost

complete with initial lead upto 50 m and all lifts.

Providing 20 mm thick plastering in cement mortar 1:4 proportion by volume including cost

complete with initial lead upto 50 m and all lifts.

Page 46: Book 1

IRR-CCDW

267

( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- I Day 15.00 285.00 4275.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 25.00 215.00 5375.00

Total cost of Labour Rs: 9925.00labour component/unit qty 99.30Add contractor's profit and overhead charges 0.14 13.90labour component/unit qty (including contractor's profit) 113.20

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 5400.73B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 9925.00

Total Rs: 15325.73D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 2145.6Total cost for 100.00 sqm Rs: 17471.325Rate per sqm (A+B+C+D)/100.0 Rs. 174.70

IRR-CCDW-5 COPING & RAILING WORKS :

IRR-CCDW-5-1

50 m and all lifts.(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)

DATA: RATE ANALYSIS UNIT : 10.00 sqmA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 75.00 5.50 412.502 Sand screened cum 0.30 425 127.503 Burnt stone slab 10 cm thick sqm 10.50 227 2383.50

Add seignorage charges on Stone @ Rs(Included in material ra Rs: 0.00Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00

Total cost of Materials Rs: 2923.50

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nil 0.00 0.00 0.00

( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- II Day 1.00 260.00 260.002 Stone chiseller Cl- II Day 1.00 260.00 260.003 work inspector Day 0.50 275.00 137.504 mazdoor Day 2.00 215.00 430.00

Total cost of Labour Rs: 1087.50labour component/unit qty 108.80Add contractor's profit and overhead charges 0.14 15.20labour component/unit qty (including contractor's profit) 124.00

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2923.50B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1087.50

Total Rs: 4011.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 561.54Total cost for 10.00 sqm Rs: 4572.54Rate per sqm (A+B+C+D)/10.0 Rs. 457.30

Providing and fixing 10 cm thick roughly dressed burnt stone slabs for coping set inCM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume includingcost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto

Page 47: Book 1

IRR-CCDW

268

IRR-CCDW-5-2CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including

50 m and all lifts.(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)

DATA: RATE ANALYSIS UNIT : 10.00 sqmA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 75.00 5.50 412.502 Sand screened cum 0.30 425 127.503 Burnt stone slab 10 cm thick sqm 10.50 227 2383.50

Add seignorage charges on Stone @ Rs(Included in material ra Rs: 0.00Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00

Total cost of Materials Rs: 2923.50

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nil 0.00 0.00 0.00

( Manual mixing) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- II Day 1.00 260.00 260.002 Stone chiseller Cl- I Day 4.00 285.00 1140.003 work inspector Day 0.50 275.00 137.504 mazdoor Day 2.00 215.00 430.00

Total cost of Labour Rs: 1967.50labour component/unit qty 196.80Add contractor's profit and overhead charges 0.14 27.60labour component/unit qty (including contractor's profit) 224.40

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2923.50B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1967.50

Total Rs: 4891.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 684.74Total cost for 10.00 sqm Rs: 5575.74Rate per sqm (A+B+C+D)/10.0 Rs. 557.60

IRR-CCDW-5-3

50 m and all lifts.(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)

DATA: RATE ANALYSIS UNIT : 10.00 sqmA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 75.00 5.50 412.502 Sand screened cum 0.30 425 127.503 Burnt stone slab 10 cm thick sqm 10.50 227 2383.50

Add seignorage charges on Stone @ Rs(Included in material ra Rs: 0.00Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00

Total cost of Materials Rs: 2923.50

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nil 0.00 0.00 0.00

( Manual mixing) 0.00 0.00 0.00

Providing and fixing 10 cm thick one line dressed burnt stone slabs for coping set in

cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto

Providing and fixing 10 cm thick two line dressed burnt stone slabs for coping set inCM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume includingcost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto

Page 48: Book 1

IRR-CCDW

269

Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- II Day 1.00 260.00 260.002 Stone chiseller Cl-I Day 8.00 285.00 2280.003 work inspector Day 0.50 275.00 137.504 mazdoor Day 2.00 215.00 430.00

Total cost of Labour Rs: 3107.50labour component/unit qty 310.80Add contractor's profit and overhead charges 0.14 43.50labour component/unit qty (including contractor's profit) 354.30

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2923.50B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 3107.50

Total Rs: 6031.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 844.34Total cost for 10.00 sqm Rs: 6875.34Rate per sqm (A+B+C+D)/10.0 Rs. 687.50

IRR-CCDW-5-4

cleaning surface, batching, mixing, placing in position, levelling, compacting, finishing, curing

(Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSIS UNIT : 14.67 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement for mix kg 4401.00 5.50 24205.50Cement for incidentals @ 5 kg / cum kg 73.35 5.50 403.42

2 Coarse aggregate 20-10 mm cum 7.63 1025.00 7819.11Coarse aggregate 10 mm below cum 4.11 750.00 3080.70

3 Fine aggregate cum 6.60 425 2805.644 Super Plasticizer kg 17.60 54 950.625 Use rate of shuttering sqm 80.69 197.64 15946.816 Sundries sqm 1.00 33 33.00

Add seignorage charges on Stone @(Included in material rate) Rs: 0.00Add seignorage charges on Sand @ (Included in material rate) Rs: 0.00

Total cost of Materials Rs: 55244.80

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 44.80 358.40

Fuel / Energy charges Hour 8.00 61.90 495.202 5 hp pump ( diesel ) Hour 0.50 8.40 4.20

Fuel / Energy charges Hour 0.50 61.90 30.953 Water tanker 8000 ltr Hour 1.00 285.80 285.80

Fuel / Energy charges Hour 1.00 233.90 233.90Total hire charges of Machinery Rs: 1408.45

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Crew for Concrete mixer Hour 8.00 141.70 1133.602 Crew for Pump Hour 0.50 71.10 35.553 Crew for Water tanker Hour 1.00 106.30 106.304 Mason Class-I Day 1.00 285.00 285.005 work inspector Day 1.00 275.00 275.006 mazdoor

for batching materials Day 11.00 215.00 2365.00for loading mortar pans Day 4.00 215.00 860.00

Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N /sqmm ) grade cement concrete using 20 mm down size approved clean, hard, gradedaggregates for coping slab including cost of all materials, machinery, labour, formwork,

etc., complete with initial lead upto 50 m and initial lift upto 3 m.

Page 49: Book 1

IRR-CCDW

270

for laying and tamping Day 3.00 215.00 645.00for conveying concrete Day 14.67 215.00 3154.05for cleaning/ washing/ curing Day 1.00 215.00 215.00

7 Labour cost for shuttering/scaffolding sqm 80.69 55.65 4490.12Total cost of Labour Rs: 13564.62

labour component/unit qty 924.70Add contractor's profit and overhead charges 0.14 129.50labour component/unit qty (including contractor's profit) 1054.20

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 55244.80B. Hire charges of Machinery Rs: 1408.45C. Cost of Labour Rs: 13564.62

Total Rs: 70217.87D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 9830.5Total cost for 14.67 cum Rs: 80048.37Rate per cum (A+B+C+D)/14.67 Rs. 5456.60

IRR-CCDW-5-5 Providing and constructing protective railing consisting of in-situ railing posts of size 15 x15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre to centre in M-20 gradeconcrete using 20 mm down size graded aggregates and with each post reinforced by 4 Nos.of 8 mm dia main bars embedded in kerb concrete for a depth of 40 cm and 5 Nos. of 6 mmdia. stirrups including fixing 3 rows of 40 mm dia. GI pipes with one coat of red oxide primerand two coats of synthetic enamel paint, cost of all materials, machinery, labour, formwork,finishing, curing etc., complete with lead upto 50 m and all lifts.

DATA: RATE ANALYSIS UNIT : 10.00 RmA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 30.00 5.50 165.002 20-10 mm coarse aggregate cum 0.04 1025.00 41.003 10-4.75 mm coarse aggregate cum 0.02 750.00 15.004 Fine aggregate cum 0.04 425 17.005 Reinforcement steel kg 16.39 41.00 671.996 40 mm dia GI pipes B class Rm 30.00 189 5670.007 Use rate of shuttering sqm 3.00 197.64 592.938 Sundries ( paints/ binding wire etc ) LS 4.00 33 132.00

Add seignorage charges on Stone @ (Included in material rate) Rs: 0.00Add seignorage charges on Sand @(Included in material rate) Rs: 0.00

Total cost of Materials Rs: 7304.92

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nill 0.00 0.00 0.00

0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Class I Day 0.50 285.00 142.502 Bar bender Day 0.50 300.00 150.003 work inspector Day 0.50 275.00 137.504 mazdoor Day 1.50 215.00 322.505 Painter Cl- II Day 0.50 260.00 130.006 Fitter shuttering Day 0.50 260.00 130.00

Total cost of Labour Rs: 1012.50labour component/unit qty 101.30Add contractor's profit and overhead charges 0.14 14.20labour component/unit qty (including contractor's profit) 115.50

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 7304.92B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1012.50

Total Rs: 8317.42D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 1164.44

Page 50: Book 1

IRR-CCDW

271

Total cost for 10.00 Rm Rs: 9481.858529Rate per Rm (A+B+C+D)/10.0 Rs. 948.20

IRR-CCDW-6 HUME PIPE LAYING & JOINTING WORKS :

IRR-CCDW-6-1proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)

DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 99.00 5.50 544.502 Sand screened cum 0.10 425 42.503 Hemp yarn kg 0.91 60 54.60

Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 641.60

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nill 0.00 0.00 0.00

( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- II Day 2.00 260.00 520.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 3.00 215.00 645.00

Total cost of Labour Rs: 1440.00labour component/unit qty 144.00Add contractor's profit and overhead charges 0.14 20.20labour component/unit qty (including contractor's profit) 164.20

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 641.60B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1440.00

Total Rs: 2081.60D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 291.42Total cost for 10.00 Joints Rs: 2373.02Rate per joint (A+B+C+D)/10.0 Rs. 237.30

Note:

IRR-CCDW-6-2proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)

DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 174.00 5.50 957.002 Sand screened cum 0.22 425 93.503 Hemp yarn kg 1.27 60 76.20

Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 1126.70

B. MACHINERY:

Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 51: Book 1

IRR-CCDW

272

Sl No Description Unit Quantity Rate Amountin Rs. in Rs.

1 Nill 0.00 0.00 0.00( Manual mixing ) 0.00 0.00 0.00

Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- II Day 2.00 260.00 520.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 3.00 215.00 645.00

Total cost of Labour Rs: 1440.00labour component/unit qty 144.00Add contractor's profit and overhead charges 0.14 20.20labour component/unit qty (including contractor's profit) 164.20

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 1126.70B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1440.00

Total Rs: 2566.70D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 359.34Total cost for 10.00 Joints Rs: 2926.04Rate per joint (A+B+C+D)/10.0 Rs. 292.60

Note:

IRR-CCDW-6-3proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 52: Book 1

IRR-CCDW

273

DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 248.00 5.50 1364.002 Sand screened cum 0.25 425 106.253 Hemp yarn kg 2.20 60 132.00

Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 1602.25

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nill 0.00 0.00 0.00

( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- II Day 2.50 260.00 650.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 4.00 215.00 860.00

Total cost of Labour Rs: 1785.00labour component/unit qty 178.50Add contractor's profit and overhead charges 0.14 25.00labour component/unit qty (including contractor's profit) 203.50

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 1602.25B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1785.00

Total Rs: 3387.25D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 474.22Total cost for 10.00 Joints Rs: 3861.47Rate per joint (A+B+C+D)/10.0 Rs. 386.10

Note:

IRR-CCDW-6-4proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint)

DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 321.00 5.50 1765.502 Sand screened cum 0.31 425 131.753 Hemp yarn kg 2.50 60 150.00

Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 2047.25

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nill 0.00 0.00 0.00

( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- II Day 2.50 260.00 650.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 4.00 215.00 860.00

Total cost of Labour Rs: 1785.00

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 700 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 53: Book 1

IRR-CCDW

274

labour component/unit qty 178.50Add contractor's profit and overhead charges 0.14 25.00labour component/unit qty (including contractor's profit) 203.50

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2047.25B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1785.00

Total Rs: 3832.25D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 536.52Total cost for 10.00 Joints Rs: 4368.77Rate per joint (A+B+C+D)/10.0 Rs. 436.90

Note:

IRR-CCDW-6-5proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)

DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 396.00 5.50 2178.002 Sand screened cum 0.39 425 165.753 Hemp yarn kg 3.10 60 186.00

Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 2529.75

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nill 0.00 0.00 0.00

( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- II Day 3.00 260.00 780.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 5.00 215.00 1075.00

Total cost of Labour Rs: 2130.00labour component/unit qty 213.00Add contractor's profit and overhead charges 0.14 29.80labour component/unit qty (including contractor's profit) 242.80

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2529.75B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 2130.00

Total Rs: 4659.75D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 652.37Total cost for 10.00 Joints Rs: 5312.12Rate per joint (A+B+C+D)/10.0 Rs. 531.20

Note:

IRR-CCDW-6-6proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)

DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 900 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 54: Book 1

IRR-CCDW

275

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 446.00 5.50 2453.002 Sand screened cum 0.45 425 191.253 Hemp yarn kg 3.40 60 204.00

Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 2848.25

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nill 0.00 0.00 0.00

( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- II Day 3.00 260.00 780.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 5.00 215.00 1075.00

Total cost of Labour Rs: 2130.00labour component/unit qty 213.00Add contractor's profit and overhead charges 0.14 29.80labour component/unit qty (including contractor's profit) 242.80

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2848.25B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 2130.00

Total Rs: 4978.25D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 696.96Total cost for 10.00 Joints Rs: 5675.21Rate per joint (A+B+C+D)/10.0 Rs. 567.50

Note:

IRR-CCDW-6-7proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)

DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 495.00 5.50 2722.502 Sand screened cum 0.50 425 212.503 Hemp yarn kg 3.77 60 226.20

Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 3161.20

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nill 0.00 0.00 0.00

( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- II Day 3.00 260.00 780.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 6.00 215.00 1290.00

Total cost of Labour Rs: 2345.00labour component/unit qty 234.50Add contractor's profit and overhead charges 0.14 32.80

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 1000 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 55: Book 1

IRR-CCDW

276

labour component/unit qty (including contractor's profit) 267.30

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 3161.20B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 2345.00

Total Rs: 5506.20D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 770.87Total cost for 10.00 Joints Rs: 6277.07Rate per joint (A+B+C+D)/10.0 Rs. 627.70

Note:

IRR-CCDW-6-8proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto50 m and all lifts.(Cement content: 56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)

DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Cement kg 569.00 5.50 3129.502 Sand screened cum 0.58 425 246.503 Hemp yarn kg 4.15 60 249.00

Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 3625.00

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nill 0.00 0.00 0.00

( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- II Day 3.00 260.00 780.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 6.00 215.00 1290.00

Total cost of Labour Rs: 2345.00labour component/unit qty 234.50Add contractor's profit and overhead charges 0.14 32.80labour component/unit qty (including contractor's profit) 267.30

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 3625.00B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 2345.00

Total Rs: 5970.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 835.8Total cost for 10.00 Joints Rs: 6805.8Rate per joint (A+B+C+D)/10.0 Rs. 680.60

Note:

IRR-CCDW-6-9proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)

DATA: RATE ANALYSIS UNIT : 10.00 JointsA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amount

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 1100 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 1200 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 56: Book 1

IRR-CCDW

277

in Rs. in Rs.1 Cement kg 668.00 5.50 3674.002 Sand screened cum 0.69 425 293.253 Hemp yarn kg 4.53 60 271.80

Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 4239.05

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nill 0.00 0.00 0.00

( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- II Day 4.00 260.00 1040.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 7.00 215.00 1505.00

Total cost of Labour Rs: 2820.00labour component/unit qty 282.00Add contractor's profit and overhead charges 0.14 39.50labour component/unit qty (including contractor's profit) 321.50

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 4239.05B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 2820.00

Total Rs: 7059.05D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 988.27Total cost for 10.00 Joints Rs: 8047.32Rate per joint (A+B+C+D)/10.0 Rs. 804.70

Note:

IRR-CCDW-7 BACK FILLING & OTHER WORKS :

IRR-CCDW-7-1including cost of all materials, machinery, labour, watering, ramming etc., complete with initiallead upto 50 m and initial lift upto 3 m.

DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Rubble / Boulder cum 10.00 265 2650.002 Sand unscreened cum 4.00 325 1300.00

Add seignorage charges on Stone@ Rs(Included in material ra Rs: 0.00Add seignorage charges on Sand @ Rs(Included in material ra Rs: 0.00

Total cost of Materials Rs: 3950.00

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nill 0.00 0.00 0.00

( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 work inspector Day 0.50 275.00 137.502 Mason Cl II Day 1.00 260.00 260.003 mazdoor Day 4.00 215.00 860.00

Total cost of Labour Rs: 1257.50labour component/unit qty 125.80Add contractor's profit and overhead charges 0.14 17.60labour component/unit qty (including contractor's profit) 143.40

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Providing rubble / boulder and sand filling behind abutment and return walls in layers

Page 57: Book 1

IRR-CCDW

278

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 3950.00B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1257.50

Total Rs: 5207.50D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 729.05Total cost for 10.00 cum Rs: 5936.55Rate per cum (A+B+C+D)/10.0 Rs. 593.70

IRR-CCDW-7-2including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by earth

upto 50 m and all lifts.

DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Murum cum 12.00 80 960.000.00 0.00 0.00

Add seignorage charges on Soil @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 960.00

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Nill 0.00 0.00 0.00

0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Cartman with double bullock cart Day 0.50 305.00 152.502 work inspector Day 0.50 275.00 137.503 mazdoor Day 6.00 215.00 1290.00

Total cost of Labour Rs: 1580.00labour component/unit qty 158.00Add contractor's profit and overhead charges 0.14 22.10labour component/unit qty (including contractor's profit) 180.10

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 960.00B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1580.00

Total Rs: 2540.00D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 355.6Total cost for 10.00 cum Rs: 2895.6Rate per cum (A+B+C+D)/10.0 Rs. 289.60

IRR-CCDW-7-3including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by power

50 m and all lifts.

DATA: RATE ANALYSIS UNIT : 10.00 cumA. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 Murum cum 12.00 80 960.000.00 0.00 0.00

Add seignorage charges on Soil @ Rs(Included in material ra Rs: 0.00Total cost of Materials Rs: 960.00

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

Providing and filling murrum / gravely soil ( CNS soil ) for foundation or around pipes

masters to achieve density control of not less than 95 percent etc., complete with lead

Providing and filling murum / gravely soil ( CNS soil ) for foundation or above pipes

roller to achieve density control of not less than 98 percent etc., complete with lead upto

Page 58: Book 1

IRR-CCDW

279

in Rs. in Rs.1 Diesel road roller 8-10 tonne Hour 0.17 151.50 25.85

Fuel / Energy charges Hour 0.17 556.90 95.03Total hire charges of Machinery Rs: 120.89

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Operator road roller Hour 0.17 136.00 23.212 Cartman with double bullock cart Day 0.50 305.00 152.50

Page 59: Book 1

IRR-CCDW

280

3 work inspector Day 0.50 275.00 137.504 mazdoor Day 1.50 215.00 322.50

Total cost of Labour Rs: 635.71labour component/unit qty 63.60Add contractor's profit and overhead charges 0.14 8.90labour component/unit qty (including contractor's profit) 72.50

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 960.00B. Hire charges of Machinery Rs: 120.89C. Cost of Labour Rs: 635.71

Total Rs: 1716.60D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 240.32Total cost for 10.00 cum Rs: 1956.91556314Rate per cum (A+B+C+D)/10.0 Rs. 195.70

IRR-CCDW-7-4

size 70x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats syntheticenamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost

DATA: RATE ANALYSIS UNIT : 4 Nos.A. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 One line dressed Km stone No. 4.00 340 1360.002 40-20 mm coarse aggregate cum 0.20 975.00 195.003 20-10 mm coarse aggregate cum 0.15 1025.00 153.754 10-4.75 mm coarse aggregate cum 0.10 750.00 75.005 Sand screened cum 0.20 425 85.006 Cement kg 100.00 5.50 550.007 Synthetic enamel paint I st quality ltr 1.00 184.00 184.008 Sundries ( brush / oil etc ) LS 4.00 33 132.00

Add seignorage charges on Stone @ (Included in material ra Rs: 0.00Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 2734.75

B. MACHINERY:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 NIL 0.00 0.00 0.00

( Manual mixing ) 0.00 0.00 0.00Total hire charges of Machinery Rs: 0.00

C. LABOUR:Sl No Description Unit Quantity Rate Amount

in Rs. in Rs.1 Mason Cl- II Day 1.00 260.00 260.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 1.00 215.00 215.004 Painter Cl- I Day 1.00 300.00 300.00

Total cost of Labour Rs: 1050.00labour component/unit qty 262.50Add contractor's profit and overhead charges 0.14 36.80labour component/unit qty (including contractor's profit) 299.30

ABSTRACT:A. Cost of Materials including seignorage charges Rs: 2734.75B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 1050.00

Total Rs: 3784.75D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 529.87Total cost for 4.00 Nos. Rs: 4314.62Rate per No. (A+B+C+D)/4.0 Rs. 1078.70

IRR-CCDW-7-5

size 50x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats syntheticenamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost

Providing and fixing one line dressed 111x35x25 cm thick IRC standard kilometre stone incement concrete M-10 grade with 40 mm down size aggregates including excavating pit of

of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Providing and fixing one line dressed 65x15x10 cm thick IRC standard hectometre stone incement concrete M-10 grade with 40 mm down size aggregates including excavating pit of

Page 60: Book 1

IRR-CCDW

281

DATA: RATE ANALYSIS UNIT : 4 Nos.A. MATERIALS:

Sl No Particulars Unit Quantity Rate Amountin Rs. in Rs.

1 One line dressed hectometre stone No. 4.00 180 720.002 40-20 mm coarse aggregate cum 0.20 975.00 195.003 20-10 mm coarse aggregate cum 0.15 1025.00 153.754 10-4.75 mm coarse aggregate cum 0.10 750.00 75.005 Sand screened cum 0.20 425 85.006 Cement kg 100.00 5.50 550.007 Synthetic enamel paint I st quality ltr 0.40 184.00 73.608 Sundries ( brush / oil etc ) LS 1.00 33 33.00

Add seignorage charges on Stone @ (Included in material ra Rs: 0.00Add seignorage charges on CA @ (Included in material ra Rs: 0.00Add seignorage charges on FA @ (Included in material ra Rs: 0.00

Total cost of Materials Rs: 1885.35B. MACHINERY:

Sl No Description Unit Quantity Rate Amountin Rs. in Rs.

1 NIL 0.00 0.00 0.00( Manual mixing ) 0.00 0.00 0.00

Total hire charges of Machinery Rs: 0.00C. LABOUR:

Sl No Description Unit Quantity Rate Amountin Rs. in Rs.

1 Mason Cl- II Day 1.00 260.00 260.002 work inspector Day 1.00 275.00 275.003 mazdoor Day 1.00 215.00 215.004 Painter Cl- I Day 0.50 300.00 150.00

Total cost of Labour Rs: 900.00labour component/unit qty 225.00Add contractor's profit and overhead charges 0.14 31.50labour component/unit qty (including contractor's profit) 256.50ABSTRACT:A. Cost of Materials including seignorage charges Rs: 1885.35B. Hire charges of Machinery Rs: 0.00C. Cost of Labour Rs: 900.00

Total Rs: 2785.35D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: 389.95Total cost for 4.00 Nos. Rs: 3175.3Rate per No. (A+B+C+D)/4.0 Rs. 793.80

of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 61: Book 1

CHAPTER-IV

CANAL CROSS DRAINAGE WORKS

(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)

FOR THE YEAR :2011-12Index- code

IRR-CCDW CANAL CROSS DRAINAGE WORKS - DATA RATES

IRR-CCDW-1 EXCAVATION & FOUNDATION TREATMENT WORKS :

IRR-CCDW-1-1

50 m and initial lift upto 3 m.

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 NIL

Total cost of Materials

B. MACHINERY:Sl No Description

1 NIL

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 work inspector2 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials

Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundations of canalcross drainage and other appurtenant structures and placing the excavated stuff neatly inspecified dump area or disposing off the same as directed etc., complete with initial lead upto

Page 62: Book 1

B. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-1-2 Excavation for Structures- Mechanical Means

including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.Depth upto 3 m

Unit = cumDATA: Taking output = 240 cum

a) LabourSl No Description

1 work inspector2 Mazdoor

Total in Rs.

b)MachinerySl No Description

1 Hydraulic excavator 1.0 cum bucket capacity Fuel/ Energy chargescrew for excavatorTotal in Rs.

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

Abstracta) Labourb) Machineryc) MaterialTotal

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-1-3

excavated stuff neatly in specified dump area or disposing off the same as directed etc.,

Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification,

Excavation in ordnary rock (including HDR) without blasting including boulders above 0.3 m upto 0.60 m dia.for foundations of canal cross drainage and other appurtenant structures and placing the

Page 63: Book 1

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 NIL

Total cost of Materials

B. MACHINERY:Sl No Description

1 NIL

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crowbarman2 Stone breaker3 work inspector4 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of MaterialsB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-1-4and other appurtenant structures and placing the excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial

( Data adopted from MORTH) Mechanical MeansUnit = cum

DATA: Taking output = 180 cuma) Labour

complete with initial lead upto 50 m and initial lift upto 3 m.

Excavation in ordnary rock without blasting for foundations of canal cross drainage

lead upto 50 m and initial lift upto 3 m.

Page 64: Book 1

Sl No Description

1 work inspector2 Mazdoor

Total in Rs.

b) MachinerySl No Description

1.0 Hydraulic excavator 1.0 cum bucket capacity Fuel/ Energy chargescrew for excavatorTotal in Rs.

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

Abstract a) Labour b) Machinery c) Material

Total D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-1-5

excavated stuff neatly in specified dump area or disposing off the same as directed etc.,

DATA:RATE ANALYSIS

A. MATERIALS:Sl No Particulars

1 Use rate of drill rod 1.6 m lengthReconditioning charges @

2 Use rate of air hose 2 Nos.3 Explosive small dia ( Kelvex-220 )4 Electric detonators5 Detonating fuse coil6 Sundries

Total cost of Materials

B. MACHINERY:Sl No Description

Excavation in hard rock requiring blasting including boulders above 0.6 m upto 1.2 m dia. forfoundations of canal cross drainage and other appurtenant structures and placing the

complete with initial lead upto 50 m and initial lift upto 3 m.

Page 65: Book 1

1 Air compressor 8.5 cmm ( diesel )Fuel / Energy charges

2 Jack hammers 2 Nos.Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Air compressor2 Crew for Jack hammer3 work inspector4 Blaster5 Helper blaster6 Crowbarman7 Stone breaker8 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of MaterialsB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-1-6

excavated rock neatly in specified dump area or stack yard as directed etc., complete with

DATA:

RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Explosive small dia ( Kelvex-220 )2 Ordinary detonator3 Electric detonator4 Detonating fuse coil5 Use rate of air hose 2 Nos.

Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. forfoundations of canal cross drainage and other appurtenant structures and placing the

initial lead upto 50 m and initial lift upto 3 m.

Page 66: Book 1

6 Use rate of drill rodReconditioning charges @

Total cost of Materials

B. MACHINERY:Sl No Description

1 Air compressor 8.5 cmm ( diesel )Fuel / Energy charges

2 Jack hammer 2 NosFuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Air compressor2 Crew for Jack hammer3 Blaster licensed4 Helper blasting5 work inspector6 Crowbarman7 Stone breaker8 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of MaterialsB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-1-7and other appurtenant structures and placing the excavated rock neatly in

initial lift upto 3 m.Hard Rock ( blasting prohibited )Unit = cum

DATA: Taking output = 10 cumMechanical Meansa) Labour

Excavation in hard rock with blasting prohibited for foundations of canal cross drainage

or stack yard as directed etc., complete with specified dump area initial lead upto 50 m and

Page 67: Book 1

Sl No Description

1 work inspector2 Mazdoor

Total in Rs.

b) MachinerySl No Description

1.0

Fuel/ Energy chargescrew for compressorTotal in Rs.

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

Abstracta) Labourb) Machineryc) Material

Total D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-1-81.25 m length driven into 32 mm dia hole drilled in bed rock and remaining length embedded inconcrete / masonry including cost of all materials, machinery, labour, drilling and cleaning

upto 50 m and all lifts.DATA:

RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for grouting2 25 mm dia steel3 Use rate of 32 mm dia drill rod

Reconditioning charges @ 4 Use rate of air hose

Total cost of Materials

B. MACHINERY:

Air Compressor 250 cft with 2 leads of pneumatic breaker

Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel anchor rods with

hole, driving anchor rod, grouting hole with thick cement slurry etc., complete with initial lead

Page 68: Book 1

Sl No Description

1 Air compressor 8.5 cmm ( diesel )Fuel / Energy charges

2 Jack hammer 2 NosFuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Air compressor2 Crew for Jack hammer3 Mason Class-II4 Bar bender5 work inspector6 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of MaterialsB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per each

IRR-CCDW-2 STEEL AND CEMENT CONCRETE WORKS :

IRR-CCDW-2-1cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,

DATA:

RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Rein.Steel with 5 % wastage2 Binding wire 1.25 mm dia3 Sundries ( chairs / spacers etc )

Total cost of Materials

Providing, fabricating and placing in position reinforcement steel bars for RCC works including

complete with initial lead upto 50 and all lifts.

Page 69: Book 1

B. MACHINERY:Sl No Description

1 Nil

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 work inspector2 Bar bender3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of MaterialsB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per kg

IRR-CCDW-2-2100 x 10 mm angle and 250 x 12 mm plate for sinking for sinking 4.50 m outer diameter foundation wells foundation wells including cost of all materials, machinery, labour, bending, welding, providing anchors etc., complete with initial lead upto 50 m and all lifts.

DETAILS OF FOUNDATION WELL CUTTING EDGE

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Str.Steel angle with 2.5 % wastage2 Str.Steel plate with 2.5 % wastage3 Steel for anchors4 Acetyline gas5 Oxygen gas6 Welding electrodes7 Sundries

Providing, fabricating and fixing in position structural steel cutting edge consisting of 100 x

Page 70: Book 1

Total cost of Materials

B. MACHINERY:Sl No Description

1 Bending machineFuel / Energy charges

2 Welding setFuel / Energy charges

3 SundriesTotal hire charges of Machinery

C. LABOUR:Sl No Description

1 Str. Steel fabricator2 Welder / Gas cutter3 work inspector4 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of MaterialsB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per kg

IRR-CCDW-2-3

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

Data RATE ANALYSISA. MATERIALS:

Sl No Particulars

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,

complete with initial lead upto 50 m and all lifts.

Page 71: Book 1

1 Cement for mixCement for incidentals @ 3 kg / cum

2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses

Scaffolding @ of shuttering6 Sundries

Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Water tanker 8000 ltrFuel / Energy charges

4 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Needle vibrator5 work inspector6 Mason Class-I7 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

8 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

Page 72: Book 1

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-4

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA:

RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 3 kg / cum

2 Coarse aggregate 80-40 mmCoarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses

Scaffolding @ of shuttering6 Sundries

Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 600/400 ltr ( diesel)Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Water tanker 8000 ltrFuel / Energy charges

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,

complete with initial lead upto 50 m and all lifts.

Page 73: Book 1

4 Needle vibrator 60 mm dia ( petrol)Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Needle vibrator5 Mason Class-I6 work inspector7 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

8 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-5

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSISA. MATERIALS:

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,

complete with initial lead upto 50 m and all lifts.

Page 74: Book 1

Sl No Particulars

1 Cement for mixCement for incidentals @ 3 kg / cum

2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses

Scaffolding @ of shuttering6 Sundries

Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Water tanker 8000 ltrFuel / Energy charges

4 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concrete

8 for cleaning/ washing/ curing9 Labour cost for shuttering

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead charges

Page 75: Book 1

labour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-6

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 3 kg / cum

2 Coarse aggregate 80-40 mmCoarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses

Scaffolding @ of shuttering6 Sundries

Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 600/400 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Water tanker 8000 ltr

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,

complete with initial lead upto 50 m and all lifts.

Page 76: Book 1

Fuel / Energy charges4 Needle vibrator 60 mm dia ( petrol )

Fuel / Energy chargesTotal hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

8 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-7

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 310 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSIS

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for foundation filling including cost of all materials, machinery, labour, formwork,

complete with initial lead upto 50 m and all lifts. ( Cement content : 220 kg / cum )

Page 77: Book 1

A. MATERIALS:Sl No Particulars

1 Cement for mixCement for incidentals @ 3 kg / cum

2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses

Scaffolding @ of shuttering6 Sundries

Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Water tanker 8000 ltrFuel / Energy charges

4 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

8 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labour

Page 78: Book 1

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-8

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering

Scaffolding @ of shuttering6 Sundries

Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 79: Book 1

Fuel / Energy charges3 Water tanker 8000 ltr

Fuel / Energy charges4 Needle vibrator 40 mm dia ( petrol )

Fuel / Energy chargesTotal hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor

for batching materialsfor loading mortar pansfor laying including liftingfor conveying concretefor cleaning/ washing/ curing

8 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-9

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 80: Book 1

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering

Scaffolding @ of shuttering6 Sundries

Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Water tanker 8000 ltrFuel / Energy charges

4 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

8 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labour

Page 81: Book 1

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-10

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses

Scaffolding @ of shuttering6 SundriesAdd seignorage charges on CA @ (included in material rate)

Add seignorage charges on FA @ (included in material rate) Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 82: Book 1

3 Water tanker 8000 ltrFuel / Energy charges

4 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

8 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-11

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for sub-structure / super- structure works including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 83: Book 1

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses

Scaffolding @ of shuttering6 Sundries

Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Water tanker 8000 ltrFuel / Energy charges

4 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Crew for Vibrator5 Mason Class-I6 work inspector7 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

8 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labour

Page 84: Book 1

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-12

scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mix2 Coarse aggregate 20-10 mm

Coarse aggregate 10 mm below3 Fine aggregate4 Super Plasticizer5 Use rate of curved shutter (40 uses)6 Sundries

Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for well kerb including cost of all materials, machinery, labour, formwork,

etc., complete with initial lead upto 50 m and all lifts.

Page 85: Book 1

3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

7 Labour cost for shutteringTotal cost of Labour

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

ra20hcux1/ctl 2011

IRR-CCDW-2-13

scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for well steining including cost of all materials, machinery, labour, formwork,

etc., complete with initial lead upto 50 m and all lifts.

Page 86: Book 1

1 Cement for mixCement for incidentals @ 2 kg / cum

2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of curved shutter (40 uses)6 Sundries

Add seignorage charges on CA @ RAdd seignorage charges on FA @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

7 Labour cost for shutteringTotal cost of Labour

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of Machinery

Page 87: Book 1

C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-14

machinery, labour, batching, mixing, placing in position as per detailed specifications etc.,

(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mix2 Coarse aggregate 20-10 mm

Coarse aggregate 10 mm below3 Fine aggregate4 Super Plasticizer

Add for tremie arrangement @Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Sundries( Hopper etc. )Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Fitter shuttering4 work inspector

Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N / sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for well bottom plug by tremie or skip box method including cost of all materials,

complete with initial lead upto 50 m and all lifts. ( Cement content : 350 kg / cum )

Page 88: Book 1

5 mazdoorfor erecting/ dismantling tremiefor batching materialsfor loading mortar pansfor feeding tremie hopperfor conveying concrete

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-15

batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mix2 Coarse aggregate 40-20 mm

Coarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer

Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for well top plug including cost of all materials, machinery, labour, cleaning,

initial lead upto 50 m and all lifts.

Page 89: Book 1

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-16

scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for well cap including cost of all materials, machinery, labour, formwork,

etc., complete with initial lead upto 50 m and all lifts.

Page 90: Book 1

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of curved shutter (40 uses)6 Sundries

Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

7 Labour cost for shutteringTotal cost of Labour

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:

Page 91: Book 1

A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-17

formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curingetc., complete with initial lead upto 50 m and all lifts.

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 80-40 mmCoarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses6 Scaffolding @ of shuttering

Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 600/400 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 60 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for piers and abutments including cost of all materials, labour, machinery,

Page 92: Book 1

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

7 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-18

formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mix

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for piers and abutments including cost of all materials, labour, machinery,

etc., complete with initial lead upto 50 m and all lifts.

Page 93: Book 1

Cement for incidentals @ 5 kg / cum2 Coarse aggregate 80-40 mm

Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate ofshuttering for 40 uses6 Scaffolding @ of shuttering

Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 600/400 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 60 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

7 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of Machinery

Page 94: Book 1

C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-19

formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses6 Scaffolding @ of shuttering

Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for piers and abutments including cost of all materials, labour, machinery,

etc., complete with initial lead upto 50 m and all lifts.

Page 95: Book 1

2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

7 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-20

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates for cantiliver / counterfort retaining walls including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 96: Book 1

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses

Scaffolding @ of shuttering6 Sundries

Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

7 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost for

Page 97: Book 1

Rate per cum

IRR-CCDW-2-21

labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum, plums of size 150 to 80 mm : 0.25cum )

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 4 kg / cum

2 Coarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Plums of size 150 to 80 mm4 Fine aggregate5 Super Plasticizer

Use rate of shuttering for 40 uses6 Scaffolding @ of shuttering

Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 60 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, gradedaggregates with placing and sinking plums of size 150 to 80 mm upto 15 percent for gravitytype retaining walls / piers / abutments etc., including cost of all materials, machinery,

finishing, curing etc.,complete with initial lead upto 50 m and all lifts.

Page 98: Book 1

2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor placing plumsfor conveying concretefor conveying plumsfor cleaning/ washing/ curing

7 Labour for shutteringLabour for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-22

batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 40-20 mm

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,gradedaggregates for cast in-situ pipes including cost of all materials, machinery, labour, cleaning,

initial lead upto 50 m and all lifts.

Page 99: Book 1

Coarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses

Scaffolding @ of shuttering6 Sundries

Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

7 Labour for shutteringLabour for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

Page 100: Book 1

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-23

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 80-40 mmCoarse aggregate 40-20 mmCoarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses6 Scaffolding @ of shuttering

Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 600/400 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 60 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, gradedaggregates for cast in-situ pipes including cost of all materials, labour, machinery, formwork,

complete with initial lead upto 50 m and all lifts.

Page 101: Book 1

2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

7 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-24

scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for deck slab & kerb including cost of all materials,machinery, labour, formwork,

etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 300 kg / cum )

Page 102: Book 1

5 Use rate of shuttering for 30 usesScaffolding @ of shuttering

6 SundriesAdd seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

7 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

Page 103: Book 1

IRR-CCDW-2-25

formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,

kg / cum )Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.

(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering

Scaffolding @ of shuttering6 Sundries

Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for columns and beams including cost of all materials, labour, machinery,

finishing, curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content : 300

Page 104: Book 1

6 mazdoorfor batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

7 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-26

cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering6 Sundries ( asphalt mortar etc )

Add seignorage charges on CA @

Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for wearing coat including cost of all materials, machinery, labour, formwork,

finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 mand all lifts. ( Cement content : 300 kg / cum )

Page 105: Book 1

Add seignorage charges on FA @ Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 40 mm dia ( petrol )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

7 Labour cost for shutteringTotal cost of Labour

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-2-27 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than

scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing

20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for troughs including cost of all materials, machinery, labour, formwork,

Page 106: Book 1

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering for 40 uses

Scaffolding @ of shuttering6 Sundries

Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Needle vibrator 40 mm dia ( diesel )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Needle vibrator4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor layingfor conveying concretefor cleaning/ washing/ curing

etc., complete with initial lead upto 50 m and all lifts. ( Cement content : 300 kg / cum )

Page 107: Book 1

7 Labour cost for shutteringLabour cost for scaffolding @

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-3 FOUNDATION WELL SINKING WORKS :

IRR-CCDW-3-1DATA: Unit = Running meter

Taking output = 1mdiameter of well = 6.00m

(i) Depth below bed level upto 3.0mRate of sinking = 0.50 m /hour

a) Labour0.12 Mate (Mason Cl- ll )1.00 Sinker ( skilled)2.00 Sinking helper ( Semi skilled)

sub total (a)b) Machinery

2.00 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.Fuel Charges Crew ChargesConsumables in sinking @ 10% of machinery charges

sub total (b)sub total (a+b)

Rate per metre = (a+b+c)/1.0or say ( Rate upto 3.0m for 6.0 m well sinking )labour component/unit qtyContractor's profit and overhead charges

Sinking RCC wells vertically for foundation of piers and abutments in all kinds of soil, sand and soft rock by approved well sinking method including cost of all materials, machinery, labour, kent - ledge arrangements, disposal of excavated material as directed etc., complete with lead upto 50 m for disposal of excavated material.(diameter of well 6.00m)

c) Add for Contractor's profit and overhead charges on (A+B)

Page 108: Book 1

labour component/unit qty(including contractor's profit)

(ii) Beyond 3m and upto 10m depthRate of sinking = 0.33 m per hour.

a) Labour0.15 Mate (Mason Cl- ll )1.25 Sinker ( skilled)2.50 Sinking helper ( Semi skilled)

sub total (a)b) Machinery

3.00 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.Fuel Charges Crew ChargesConsumables in sinking @ 10% of machinery charges

sub total (b)sub total (a+b)

Rate per metre = (a+b+c)or say ( Rate for 3.0m to 10m well sinking )

labour component/unit qtyContractor's profit and overhead chargeslabour component/unit qty(including contractor's profit)

IRR-CCDW-3-2ramming as directed including cost of all materials, machinery, labour etc., complete with

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Sand unscreened

Add seignorage charges on Sand @ Rs:Total cost of Materials

B. MACHINERY:Sl No Description

1 Nill

c) Add for Contractor's profit and overhead charges on (A+B)

Filling foundation wells with sand in layers of 25 to 30 cm and compacting by watering,

initial lead upto 50 m and all lifts.

Page 109: Book 1

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 work inspector2 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-4 MASONRY WORKS :

IRR-CCDW-4-1

cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging

(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,Stone Chips : 0.15 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Rubble stones3 Stone chips4 Sand screened

Add seignorage charges on Stone@ RsAdd seignorage charges on Sand @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Water tanker 8000 ltr

Providing and constructing un-coursed rubble stone masonry with approved stones inCM 1 : 4 proportion for sub-structure portions of return walls / abutments etc., including

stone chips, curing etc., complete with initial lead upto 50 m and all lifts.

Page 110: Book 1

Fuel / Energy charges2 5 hp pump ( diesel )

Fuel / Energy chargesTotal hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Water tanker2 Crew for Pump3 work inspector4 Mason Class-I5 Mason Class-II6 mazdoor

for conveying rubble stonesfor preparing mortarfor loading mortar pansfor laying & packing mortarfor washing rubble / finishing / curingfor conveying mortar / chips

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-4-2

cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging

(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,Stone Chips : 0.15 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

Providing and constructing un-coursed rubble stone masonry with approved stones inCM 1 : 4 proportion for super-structure portions of return walls / abutments etc., including

stone chips, curing etc., complete with initial lead upto 50 m and all lifts.

Page 111: Book 1

1 Cement2 Rubble stones3 Stone chips4 Sand screened

Add for scaffolding @Add seignorage charges on Stone@ RsAdd seignorage charges on Sand @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Water tanker 8000 ltrFuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Water tanker2 Crew for Pump3 work inspector4 Mason Class-I5 Mason Class-II6 mazdoor

for conveying rubble stonesfor preparing mortarfor loading mortar pansfor laying & packing mortarfor washing rubble / finishing / curingfor conveying mortar / chips

Add for labour for scaffolding @Total cost of Labour

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost for

Page 112: Book 1

Rate per cum

IRR-CCDW-4-3stones from approved source including cost of all materials, machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with

(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones 25 x 25x 45 cm : 60 Nos)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Header stones 25x25x45 cm3 Khandki stones 25x25x30 cm4 Rubble stones5 Stone chips6 Sand screened

Add for scaffolding materials @Add seignorage charges on Stone@ RsAdd seignorage charges on Sand @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Water tanker 8000 ltrFuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Water tanker2 Crew for Pump3 work inspector4 Stone chiseller Cl -II5 Mason Class-I6 Mason Class-II7 mazdoor

for conveying stones / rubblefor preparation of mortar

Providing and constructing coursed rubble masonry second sort in CM 1:4 proportion with

initial lead upto 50 m and initial lift upto 3m.

Page 113: Book 1

for loading mortar pansfor laying & packing mortarfor washing rubble / finishing / curingfor conveying mortar / chips

Add for labour for scaffolding @Total cost of Labour

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-4-4 Providing and constructing coursed rubble masonry first sort in CM 1:4 proportion withstones from approved source including cost of all materials, machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete withinitial lead upto 50 m and initial lift upto 3 m.(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones 25 x 25x 45 cm : 60 Nos)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Header stones 25x25x45 cm3 Khandki stones 25x25x30 cm4 Rubble stones5 Stone chips6 Sand screened

Add for scaffolding materials @Add seignorage charges on Stone@ RsAdd seignorage charges on Sand @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

Page 114: Book 1

1 Water tanker 8000 ltrFuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Water tanker2 Crew for Pump3 work inspector4 Stone chiseller Cl -II5 Mason Class-I6 Mason Class-II7 mazdoor8 for conveying rubble/ stones

for preparation of mortarfor loading mortar pansfor laying & packing mortarfor washing rubble / finishing / curingfor conveying mortar / chips

Add for labour for scaffolding @Total cost of Labour

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-4-5proportion by volume including raking and cleaning joints for 50 mm depth, pressing cementmortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with

DATA: RATE ANALYSISA. MATERIALS:

Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 2

initial lead upto 50 m and all lifts.

Page 115: Book 1

Sl No Particulars

1 Cement2 Sand screened

Add for scaffolding / ramps etc @Add seignorage charges on Sand @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Nil( Manual mixing)

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- I2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm

IRR-CCDW-4-6proportion by volume including raking and cleaning joints for 50 mm depth, pressing cementmortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement

Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 3

initial lead upto 50 m and all lifts.

Page 116: Book 1

2 Sand screened

Add for scaffolding / ramps etc @Add seignorage charges on Sand @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Nil( Manual mixing)

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- I2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm

IRR-CCDW-4-7of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened

Add for scaffolding / ramps etc @Add seignorage charges on Sand @ Rs

Providing 12 mm thick plastering in cement mortar 1:3 proportion by volume including cost

complete with initial lead upto 50 m and all lifts.

Page 117: Book 1

Total cost of Materials

B. MACHINERY:Sl No Description

1 Nil( Manual mixing)

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- I2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm

IRR-CCDW-4-8of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened

Add for scaffolding / ramps etc @Add seignorage charges on Sand @ Rs

Total cost of Materials

B. MACHINERY:

Providing 12 mm thick plastering in cement mortar 1:4 proportion by volume including cost

complete with initial lead upto 50 m and all lifts.

Page 118: Book 1

Sl No Description

1 Nil( Manual mixing)

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- I2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm

IRR-CCDW-4-9of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened

Add for scaffolding / ramps etc @Add seignorage charges on Sand @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Nil

Providing 20 mm thick plastering in cement mortar 1:3 proportion by volume including cost

complete with initial lead upto 50 m and all lifts.

Page 119: Book 1

( Manual mixing)Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- I2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm

IRR-CCDW-4-10of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened

Add for scaffolding / ramps etc @Add seignorage charges on Sand @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Nil( Manual mixing)

Total hire charges of Machinery

Providing 20 mm thick plastering in cement mortar 1:4 proportion by volume including cost

complete with initial lead upto 50 m and all lifts.

Page 120: Book 1

C. LABOUR:Sl No Description

1 Mason Cl- I2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm

IRR-CCDW-5 COPING & RAILING WORKS :

IRR-CCDW-5-1

50 m and all lifts.(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened3 Burnt stone slab 10 cm thick

Add seignorage charges on Stone @ RsAdd seignorage charges on Sand @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Nil( Manual mixing)

Total hire charges of Machinery

Providing and fixing 10 cm thick roughly dressed burnt stone slabs for coping set inCM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume includingcost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto

Page 121: Book 1

C. LABOUR:Sl No Description

1 Mason Cl- II2 Stone chiseller Cl- II3 work inspector4 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm

IRR-CCDW-5-2CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including

50 m and all lifts.(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened3 Burnt stone slab 10 cm thick

Add seignorage charges on Stone @ RsAdd seignorage charges on Sand @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Nil( Manual mixing)

Total hire charges of Machinery

Providing and fixing 10 cm thick one line dressed burnt stone slabs for coping set in

cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto

Page 122: Book 1

C. LABOUR:Sl No Description

1 Mason Cl- II2 Stone chiseller Cl- I3 work inspector4 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm

IRR-CCDW-5-3

50 m and all lifts.(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened3 Burnt stone slab 10 cm thick

Add seignorage charges on Stone @ RsAdd seignorage charges on Sand @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Nil( Manual mixing)

Total hire charges of Machinery

Providing and fixing 10 cm thick two line dressed burnt stone slabs for coping set inCM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume includingcost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto

Page 123: Book 1

C. LABOUR:Sl No Description

1 Mason Cl- II2 Stone chiseller Cl-I3 work inspector4 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per sqm

IRR-CCDW-5-4

cleaning surface, batching, mixing, placing in position, levelling, compacting, finishing, curing

(Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement for mixCement for incidentals @ 5 kg / cum

2 Coarse aggregate 20-10 mmCoarse aggregate 10 mm below

3 Fine aggregate4 Super Plasticizer5 Use rate of shuttering6 Sundries

Add seignorage charges on Stone @(Included in material rate) Add seignorage charges on Sand @ (Included in material rate)

Total cost of Materials

Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N /sqmm ) grade cement concrete using 20 mm down size approved clean, hard, gradedaggregates for coping slab including cost of all materials, machinery, labour, formwork,

etc., complete with initial lead upto 50 m and initial lift upto 3 m.

Page 124: Book 1

B. MACHINERY:Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )Fuel / Energy charges

2 5 hp pump ( diesel )Fuel / Energy charges

3 Water tanker 8000 ltrFuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Crew for Concrete mixer2 Crew for Pump3 Crew for Water tanker4 Mason Class-I5 work inspector6 mazdoor

for batching materialsfor loading mortar pansfor laying and tampingfor conveying concretefor cleaning/ washing/ curing

7 Labour cost for shuttering/scaffoldingTotal cost of Labour

labour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-5-5 Providing and constructing protective railing consisting of in-situ railing posts of size 15 x15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre to centre in M-20 gradeconcrete using 20 mm down size graded aggregates and with each post reinforced by 4 Nos.of 8 mm dia main bars embedded in kerb concrete for a depth of 40 cm and 5 Nos. of 6 mmdia. stirrups including fixing 3 rows of 40 mm dia. GI pipes with one coat of red oxide primerand two coats of synthetic enamel paint, cost of all materials, machinery, labour, formwork,

Page 125: Book 1

finishing, curing etc., complete with lead upto 50 m and all lifts.

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 20-10 mm coarse aggregate3 10-4.75 mm coarse aggregate4 Fine aggregate5 Reinforcement steel6 40 mm dia GI pipes B class7 Use rate of shuttering8 Sundries ( paints/ binding wire etc )

Add seignorage charges on Stone @ (Included in material rate) Add seignorage charges on Sand @(Included in material rate)

Total cost of Materials

B. MACHINERY:Sl No Description

1 Nill

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Class I2 Bar bender3 work inspector4 mazdoor5 Painter Cl- II6 Fitter shuttering

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per Rm

Page 126: Book 1

IRR-CCDW-6 HUME PIPE LAYING & JOINTING WORKS :

IRR-CCDW-6-1proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened3 Hemp yarn

Add seignorage charges on Sand @ RsTotal cost of Materials

B. MACHINERY:Sl No Description

1 Nill( Manual mixing )

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- II2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint

Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 127: Book 1

Note:

IRR-CCDW-6-2proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened3 Hemp yarn

Add seignorage charges on Sand @ RsTotal cost of Materials

B. MACHINERY:Sl No Description

1 Nill( Manual mixing )

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- II2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 128: Book 1

Note:

IRR-CCDW-6-3proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened3 Hemp yarn

Add seignorage charges on Sand @ RsTotal cost of Materials

B. MACHINERY:Sl No Description

1 Nill( Manual mixing )

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- II2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 129: Book 1

Note:

IRR-CCDW-6-4proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened3 Hemp yarn

Add seignorage charges on Sand @ RsTotal cost of Materials

B. MACHINERY:Sl No Description

1 Nill( Manual mixing )

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- II2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 700 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 130: Book 1

Note:

IRR-CCDW-6-5proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened3 Hemp yarn

Add seignorage charges on Sand @ RsTotal cost of Materials

B. MACHINERY:Sl No Description

1 Nill( Manual mixing )

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- II2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 131: Book 1

Note:

IRR-CCDW-6-6proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened3 Hemp yarn

Add seignorage charges on Sand @ RsTotal cost of Materials

B. MACHINERY:Sl No Description

1 Nill( Manual mixing )

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- II2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 900 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 132: Book 1

Note:

IRR-CCDW-6-7proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened3 Hemp yarn

Add seignorage charges on Sand @ RsTotal cost of Materials

B. MACHINERY:Sl No Description

1 Nill( Manual mixing )

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- II2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 1000 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 133: Book 1

Note:

IRR-CCDW-6-8proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto50 m and all lifts.(Cement content: 56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened3 Hemp yarn

Add seignorage charges on Sand @ RsTotal cost of Materials

B. MACHINERY:Sl No Description

1 Nill( Manual mixing )

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- II2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 1100 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

Page 134: Book 1

Note:

IRR-CCDW-6-9proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

50 m and all lifts.(Cement content: 66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Cement2 Sand screened3 Hemp yarn

Add seignorage charges on Sand @ RsTotal cost of Materials

B. MACHINERY:Sl No Description

1 Nill( Manual mixing )

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Mason Cl- II2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per joint

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Laying and jointing 1200 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 135: Book 1

Note:

IRR-CCDW-7 BACK FILLING & OTHER WORKS :

IRR-CCDW-7-1including cost of all materials, machinery, labour, watering, ramming etc., complete with initiallead upto 50 m and initial lift upto 3 m.

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Rubble / Boulder2 Sand unscreened

Add seignorage charges on Stone@ RsAdd seignorage charges on Sand @ Rs

Total cost of Materials

B. MACHINERY:Sl No Description

1 Nill( Manual mixing )

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 work inspector2 Mason Cl II3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

(1) For NP3 Class - 10% extra over the rates of NP2 Class(2) For NP4 Class - 20% extra over the rates of NP2 Class

Providing rubble / boulder and sand filling behind abutment and return walls in layers

Page 136: Book 1

IRR-CCDW-7-2including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by earth

upto 50 m and all lifts.

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Murum

Add seignorage charges on Soil @ RsTotal cost of Materials

B. MACHINERY:Sl No Description

1 Nill

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Cartman with double bullock cart2 work inspector3 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-7-3including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by power

Providing and filling murrum / gravely soil ( CNS soil ) for foundation or around pipes

masters to achieve density control of not less than 95 percent etc., complete with lead

Providing and filling murum / gravely soil ( CNS soil ) for foundation or above pipes

roller to achieve density control of not less than 98 percent etc., complete with lead upto

Page 137: Book 1

50 m and all lifts.

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 Murum

Add seignorage charges on Soil @ RsTotal cost of Materials

B. MACHINERY:Sl No Description

1 Diesel road roller 8-10 tonneFuel / Energy charges

Total hire charges of Machinery

C. LABOUR:Sl No Description

1 Operator road roller2 Cartman with double bullock cart3 work inspector4 mazdoor

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per cum

IRR-CCDW-7-4

size 70x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats syntheticenamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost

Providing and fixing one line dressed 111x35x25 cm thick IRC standard kilometre stone incement concrete M-10 grade with 40 mm down size aggregates including excavating pit of

of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 138: Book 1

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 One line dressed Km stone2 40-20 mm coarse aggregate3 20-10 mm coarse aggregate4 10-4.75 mm coarse aggregate5 Sand screened6 Cement7 Synthetic enamel paint I st quality8 Sundries ( brush / oil etc )

Add seignorage charges on Stone @ Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of Materials

B. MACHINERY:Sl No Description

1 NIL( Manual mixing )

Total hire charges of MachineryC. LABOUR:

Sl No Description

1 Mason Cl- II2 work inspector3 mazdoor4 Painter Cl- I

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)

ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per No.

IRR-CCDW-7-5

size 50x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic

Providing and fixing one line dressed 65x15x10 cm thick IRC standard hectometre stone incement concrete M-10 grade with 40 mm down size aggregates including excavating pit of

Page 139: Book 1

enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost

DATA: RATE ANALYSISA. MATERIALS:

Sl No Particulars

1 One line dressed hectometre stone2 40-20 mm coarse aggregate3 20-10 mm coarse aggregate4 10-4.75 mm coarse aggregate5 Sand screened6 Cement7 Synthetic enamel paint I st quality8 Sundries ( brush / oil etc )

Add seignorage charges on Stone @ Add seignorage charges on CA @ Add seignorage charges on FA @

Total cost of MaterialsB. MACHINERY:

Sl No Description

1 NIL( Manual mixing )

Total hire charges of MachineryC. LABOUR:

Sl No Description

1 Mason Cl- II2 work inspector3 mazdoor4 Painter Cl- I

Total cost of Labourlabour component/unit qtyAdd contractor's profit and overhead chargeslabour component/unit qty (including contractor's profit)ABSTRACT:A. Cost of Materials including seignorage chargesB. Hire charges of MachineryC. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)Total cost forRate per No.

of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 140: Book 1

CANAL CROSS DRAINAGE WORKS

(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)

CANAL CROSS DRAINAGE WORKS - DATA RATES

UNIT : 10.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 0.25 275.00 68.75Day 6.00 215.00 1290.00

Rs: 1358.75135.90

0.14 19.00154.90

Rs: 0.00

including boulders upto 0.30 m dia. for foundations of canal and other appurtenant structures and placing the excavated stuff neatly in

specified dump area or disposing off the same as directed etc., complete with initial lead upto

Page 141: Book 1

Rs: 0.00Rs: 1358.75

Total Rs: 1358.7514.00% Rs: 190.23

10.00 cum Rs: 1548.98(A+B+C+D)/10.0 Rs. 154.90

( Data adopted from MORTH)

including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing

240.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

day 0.32 275.00 88.00 day 8.00 215.00 1720.00

1808.00

Unit Quantity Rate Amountin Rs. in Rs.

hour 6.00 1180.70 7084.20 hour 6.00 680.60 4083.60 hour 6.00 148.20 889.20

12057.00 50.20

0.14 7.0057.20

Rs 1808.00 Rs 12057.00 Rs 0.00 Rs 13865.00

14.00% Rs: 1941.1240.00 cum Rs: 15806.1

(A+B+C+D)/240.0 Rs. 65.90

excavated stuff neatly in specified dump area or disposing off the same as directed etc.,

of foundation of structures as per drawing and technical specification,

HDR) without blasting including boulders above 0.3 m upto 0.60 m dia. of canal cross drainage and other appurtenant structures and placing the

Page 142: Book 1

UNIT : 10.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 1.25 260.00 325.00Day 1.25 260.00 325.00Day 0.25 275.00 68.75Day 6.00 215.00 1290.00

Rs: 2008.75200.90

0.14 28.10229.00

Rs: 0.00Rs: 0.00Rs: 2008.75

Total Rs: 2008.7514.00% Rs: 281.23

10.00 cum Rs: 2289.98(A+B+C+D)/10.0 Rs. 229.00

and other appurtenant structures and placing the excavated stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial

180.00 cum

for foundations of canal cross drainage

Page 143: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

day 0.24 275.00 66.00 day 6.00 215.00 1290.00

1356.00

Unit Quantity Rate Amountin Rs. in Rs.

hour 6.00 1180.70 7084.20 hour 6.00 680.60 4083.60 hour 6.00 148.20 889.20

12057.00 67.00

0.14 9.4076.40

Rs 1356.00 Rs 12057.00 Rs 0.00 Rs 13413.00

14.00% Rs: 1877.82180.00 cum Rs: 15290.82

(A+B+C+D)/180.0 Rs. 84.90

excavated stuff neatly in specified dump area or disposing off the same as directed etc.,

UNIT : 100 cum

Unit Quantity Rate Amountin Rs. in Rs.

Rm 43.50 16.50 717.7510% 71.78Hour 6.00 0.16 0.98

kg 20.00 54 1080.00Nos 29.00 11 319.00Rm 70.00 8 560.00LS 0.50 33 16.50

Rs: 2766.00

Unit Quantity Rate Amount

including boulders above 0.6 m upto 1.2 m dia. for of canal cross drainage and other appurtenant structures and placing the

Page 144: Book 1

in Rs. in Rs.Hour 3.00 210.40 631.20Hour 3.00 696.10 2088.30Hour 6.00 13.50 81.00Hour 6.00 0.00 0.00

Rs: 2800.50

Unit Quantity Rate Amountin Rs. in Rs.

Hour 3.00 136.00 408.00Hour 6.00 212.60 1275.60Day 1.00 275.00 275.00Day 0.50 310.00 155.00Day 0.50 260.00 130.00Day 6.00 260.00 1560.00Day 3.00 260.00 780.00Day 51.00 215.00 10965.00

Rs: 15548.60155.50

0.14 21.80177.30

Rs: 2766.00Rs: 2800.50Rs: 15548.60

Total Rs: 21115.1014.00% Rs: 2956.11

100.00 cum Rs: 24071.21(A+B+C+D)/100.0 Rs. 240.70

excavated rock neatly in specified dump area or stack yard as directed etc., complete with

UNIT : 100.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 32.00 54 1728.00No. 8.00 6 48.00No. 104.00 11 1144.00Rm 150.00 8 1200.00

Hour 16.00 8.13 130.00

of all toughness by blasting including boulders above 1.2 m dia. for of canal cross drainage and other appurtenant structures and placing the

Page 145: Book 1

Rm 98.30 22.00 2162.6010% 216.26

Rs: 6628.86

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 210.40 1683.20Hour 8.00 696.10 5568.80Hour 16.00 13.50 216.00Hour 16.00 0.00 0.00

Rs: 7468.00

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 136.00 1088.00Hour 16.00 212.60 3401.60Day 1.00 310.00 310.00Day 1.00 260.00 260.00Day 1.00 275.00 275.00Day 6.00 260.00 1560.00Day 6.00 260.00 1560.00Day 51.00 215.00 10965.00

Rs: 19419.60194.20

0.14 27.20221.40

Rs: 6628.86Rs: 7468.00Rs: 19419.60

Total Rs: 33516.4614.00% Rs: 4692.3

100.00 cum Rs: 38208.76(A+B+C+D)/100.0 Rs. 382.10

and other appurtenant structures and placing the excavated rock neatly in

( Data adopted from MORTH)

10.00 cum

for foundations of canal cross drainage

or stack yard as directed etc., complete with specified dump area initial lead upto 50 m and

Page 146: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

day 0.20 275.00 55.00 day 5.00 215.00 1075.00

1130.00

Unit Quantity Rate Amountin Rs. in Rs.

hour 6.00 178.50 1071.00

hour 6.00 556.90 3341.40 hour 6.00 136.00 816.00

5228.40 522.80

0.14 73.20596.00

Rs 1130.00 Rs 5228.40 Rs 0.00 Rs 6358.40

14.00% Rs: 890.1810.00 cum Rs: 7248.58

(A+B+C+D)/10.0 Rs. 724.90

1.25 m length driven into 32 mm dia hole drilled in bed rock and remaining length embedded inconcrete / masonry including cost of all materials, machinery, labour, drilling and cleaning

UNIT : 10.00 Nos.

Unit Quantity Rate Amountin Rs. in Rs.

kg 5.00 5.50 27.50kg 101.00 41.00 4141.00Rm 12.50 22.00 275.0010% 27.50Hour 2.00 8.13 16.25

Rs: 4487.25

25 mm dia 2.50 m long cold twisted deformed steel anchor rods with

hole, driving anchor rod, grouting hole with thick cement slurry etc., complete with initial lead

Page 147: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

Hour 1.00 210.40 210.40Hour 1.00 696.10 696.10Hour 2.00 13.50 27.00Hour 2.00 0.00 0.00

Rs: 933.50

Unit Quantity Rate Amountin Rs. in Rs.

Hour 1.00 136.00 136.00Hour 2.00 212.60 425.20Day 0.50 260.00 130.00Day 0.50 300.00 150.00Day 0.50 275.00 137.50Day 1.00 215.00 215.00

Rs: 1193.70119.40

0.14 16.70136.10

Rs: 4487.25Rs: 933.50Rs: 1193.70

Total Rs: 6614.4514.00% Rs: 926.02

10.00 Nos. Rs: 7540.47(A+B+C+D)/10.0 Rs. 754.00

cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,

UNIT : 1000.00 kg

Unit Quantity Rate Amountin Rs. in Rs.

kg 1050.00 41.00 43050.00kg 8.00 55 440.00LS 3.00 33 99.00

Rs: 43589.00

reinforcement steel bars for RCC works including

Page 148: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 1.00 275.00 275.00Day 6.00 300.00 1800.00Day 11.00 215.00 2365.00

Rs: 4440.004.40

0.14 0.605.00

Rs: 43589.00Rs: 0.00Rs: 4440.00

Total Rs: 48029.0014.00% Rs: 6724.06

1000.00 kg Rs: 54753.06(A+B+C+D)/1000.0 Rs. 54.80

100 x 10 mm angle and 250 x 12 mm plate for sinking for sinking 4.50 m outer diameter foundation wells foundation wells including cost of all materials, machinery, labour, bending, welding, providing anchors etc., complete with initial lead upto 50 m and all lifts.

DETAILS OF FOUNDATION WELL CUTTING EDGE

UNIT : 615.00 kg

Unit Quantity Rate Amountin Rs. in Rs.

kg 216.10 40.00 8644.00kg 342.30 43.00 14718.90kg 56.60 41.00 2320.60

cum 0.50 275 137.50cum 1.50 40 60.00Nos 300.00 9.00 2700.00LS 5.00 33 165.00

structural steel cutting edge consisting of 100 x

Page 149: Book 1

Rs: 28746.00

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 14.50 116.00Hour 8.00 60.40 483.20Hour 30.00 12.90 387.00Hour 30.00 48.30 1449.00LS 10.00 33 330.00

Rs: 2765.20

Unit Quantity Rate Amountin Rs. in Rs.

Day 2.00 310.00 620.00Day 5.00 285.00 1425.00Day 1.00 275.00 275.00Day 5.00 215.00 1075.00

Rs: 3395.005.50

0.14 0.806.30

Rs: 28746.00Rs: 2765.20Rs: 3395.00

Total Rs: 34906.2014.00% Rs: 4886.87

615.00 kg Rs: 39793.07(A+B+C+D)/615.0 Rs. 64.70

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

UNIT : 15.38 cum

Unit Quantity Rate Amountin Rs. in Rs.

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

including cost of all materials, machinery, labour, formwork,

Page 150: Book 1

kg 3998.80 5.50 21993.40kg 46.14 5.50 253.77

cum 6.92 975.00 6747.98cum 4.15 1025.00 4256.42cum 2.77 750.00 2076.30cum 6.15 425 2614.60kg 16.00 54 863.74

sqm 15.38 197.64 3039.7510% 303.97LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 42166.42

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1555.65

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 275.00 275.00Day 1.00 285.00 285.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 15.38 215.00 3306.70Day 1.00 215.00 215.00sqm 15.38 55.65 855.9010% 85.59

Rs: 10984.64714.20

0.14 100.00814.20

Page 151: Book 1

Rs: 42166.42Rs: 1555.65Rs: 10984.64

Total Rs: 54706.7114.00% Rs: 7658.94

15.38 cum Rs: 62365.65(A+B+C+D)/15.38 Rs. 4055.00

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

UNIT : 14.40 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 3600.00 5.50 19800.00kg 43.20 5.50 237.60

cum 4.94 560.00 2765.95cum 4.23 975.00 4127.76cum 2.82 1025.00 2892.96cum 2.12 750.00 1587.60cum 5.04 425 2142.00kg 14.40 54 777.60

sqm 14.40 197.64 2846.0610% 284.61LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 37478.63

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 77.00 616.00Hour 8.00 123.80 990.40Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

including cost of all materials, machinery, labour, formwork,

Page 152: Book 1

Hour 8.00 6.20 49.60Hour 8.00 18.60 148.80

Rs: 2359.65

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 14.40 215.00 3096.00Day 1.00 215.00 215.00sqm 14.40 55.65 801.3610% 80.14

Rs: 10713.95744.00

0.14 104.20848.20

Rs: 37478.63Rs: 2359.65Rs: 10713.95

Total Rs: 50552.2314.00% Rs: 7077.31

14.40 cum Rs: 57629.5406331(A+B+C+D)/14.40 Rs. 4002.10

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

UNIT : 16.36 cum

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

including cost of all materials, machinery, labour, formwork,

Page 153: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

kg 3599.20 5.50 19795.60kg 49.08 5.50 269.94

cum 7.36 975.00 7177.95cum 4.42 1025.00 4527.63cum 2.94 750.00 2208.60cum 6.54 425 2781.20kg 14.40 54 777.43

sqm 16.36 197.64 3233.4410% 323.34LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 41111.63

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1555.65

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 16.36 215.00 3517.40Day 1.00 215.00 215.00sqm 16.36 55.65 910.43

Rs: 11164.28682.40

0.14 95.50

Page 154: Book 1

777.90

Rs: 41111.63Rs: 1555.65Rs: 11164.28

Total Rs: 53831.5614.00% Rs: 7536.42

16.36 cum Rs: 61367.9818026(A+B+C+D)/16.36 Rs. 3751.10

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

UNIT : 14.55 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 3201.00 5.50 17605.50kg 43.65 5.50 240.08

cum 4.99 560.00 2794.76cum 4.28 975.00 4170.76cum 2.85 1025.00 2923.10cum 2.14 750.00 1604.14cum 5.09 425 2164.31kg 12.80 54 691.42

sqm 14.55 197.64 2875.7010% 287.57LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 35373.83

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 77.00 616.00Hour 8.00 123.80 990.40Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

including cost of all materials, machinery, labour, formwork,

Page 155: Book 1

Hour 1.00 233.90 233.90Hour 8.00 6.20 49.60Hour 8.00 18.60 148.80

Rs: 2359.65

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 14.55 215.00 3128.25Day 1.00 215.00 215.00sqm 14.55 55.65 809.7110% 80.97

Rs: 10755.38739.20

0.14 103.50842.70

Rs: 35373.83Rs: 2359.65Rs: 10755.38

Total Rs: 48488.8614.00% Rs: 6788.44

14.55 cum Rs: 55277.2994522(A+B+C+D)/14.55 Rs. 3799.10

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

(Cement content: 310 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

UNIT : 14.19 cum

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

including cost of all materials, machinery, labour, formwork,

( Cement content : 220 kg / cum )

Page 156: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

kg 4398.90 5.50 24193.95kg 42.57 5.50 234.14

cum 6.39 975.00 6225.86cum 3.83 1025.00 3927.08cum 2.55 750.00 1915.65cum 5.68 425 2412.30kg 17.60 54 950.16

sqm 14.19 197.64 2804.5510% 280.46LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 42960.65

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1555.65

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 14.19 215.00 3050.85Day 1.00 215.00 215.00sqm 14.19 55.65 789.6710% 78.97

Rs: 10655.94

Page 157: Book 1

750.900.14 105.10

856.00

Rs: 42960.65Rs: 1555.65Rs: 10655.94

Total Rs: 55172.2414.00% Rs: 7724.11

14.19 cum Rs: 62896.35(A+B+C+D)/14.19 Rs. 4432.40

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

UNIT : 15.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 4800.00 5.50 26400.00kg 75.00 5.50 412.50

cum 6.75 975.00 6581.25cum 4.05 1025.00 4151.25cum 2.70 750.00 2025.00cum 6.00 425 2550.00kg 19.20 54 1036.80

sqm 30.00 197.64 5929.2925% 1482.32LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 50584.91

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

works including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 158: Book 1

Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1555.65

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 4.00 215.00 860.00Day 15.00 215.00 3225.00Day 1.00 215.00 215.00sqm 15.00 55.65 834.7525% 208.69

Rs: 11219.89748.00

0.14 104.70852.70

Rs: 50584.91Rs: 1555.65Rs: 11219.89

Total Rs: 63360.4414.00% Rs: 8870.46

15.00 cum Rs: 72230.90(A+B+C+D)/15.0 Rs. 4815.40

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

works including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 159: Book 1

UNIT : 15.76 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 5200.80 5.50 28604.40kg 78.80 5.50 433.40

cum 8.20 1025.00 8400.08cum 4.41 750.00 3309.60cum 7.09 425 3014.10kg 20.80 54 1123.37

sqm 31.52 197.64 6229.7025% 1557.43LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 52688.58

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1555.65

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 4.00 215.00 860.00Day 15.76 215.00 3388.40Day 1.00 215.00 215.00sqm 31.52 55.65 1754.0925% 438.52

Rs: 12532.46

Page 160: Book 1

795.200.14 111.30

906.50

Rs: 52688.58Rs: 1555.65Rs: 12532.46

Total Rs: 66776.6914.00% Rs: 9348.74

15.76 cum Rs: 76125.4308142(A+B+C+D)/15.76 Rs. 4830.30

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),

UNIT : 15.71 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 4398.80 5.50 24193.40kg 78.55 5.50 432.03

cum 8.17 1025.00 8373.43cum 4.40 750.00 3299.10cum 7.07 425 3004.54kg 17.60 54 950.14

sqm 31.42 197.64 6209.9425% 1552.48LS 0.50 33 16.50

Add seignorage charges on CA @ (included in material rate) Rs: 0.00Add seignorage charges on FA @ (included in material rate) Rs: 0.00

Rs: 48031.56

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

works including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 161: Book 1

Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1555.65

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 4.00 215.00 860.00Day 15.71 215.00 3377.65Day 1.00 215.00 215.00sqm 31.42 55.65 1748.5225% 437.13

Rs: 12514.75796.60

0.14 111.50908.10

Rs: 48031.56Rs: 1555.65Rs: 12514.75

Total Rs: 62101.9614.00% Rs: 8694.27

15.71 cum Rs: 70796.2297088(A+B+C+D)/15.71 Rs. 4506.40

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

works including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 162: Book 1

UNIT : 18.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 3960.00 5.50 21780.00kg 90.00 5.50 495.00

cum 9.36 1025.00 9594.00cum 5.04 750.00 3780.00cum 8.10 425 3442.50kg 15.84 54 855.36

sqm 36.00 197.64 7115.1425% 1778.79LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 48857.29

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1555.65

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 4.00 215.00 860.00Day 18.00 215.00 3870.00Day 1.00 215.00 215.00sqm 36.00 55.65 2003.4025% 500.85

Rs: 13325.70

Page 163: Book 1

740.300.14 103.60

843.90

Rs: 48857.29Rs: 1555.65Rs: 13325.70

Total Rs: 63738.6414.00% Rs: 8923.41

18.00 cum Rs: 72662.047935(A+B+C+D)/18.0 Rs. 4036.80

scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

If water is to be brought from other place add only lead charges @ 500 ltr / cum. 7500(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),

UNIT : 15.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 5250.00 5.50 28875.00cum 7.80 1025.00 7995.00cum 4.20 750.00 3150.00cum 6.75 425 2868.75kg 21.00 54 1134.00

sqm 82.50 217.41 17936.09LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 61975.34

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

including cost of all materials, machinery, labour, formwork,

Page 164: Book 1

Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1035.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 15.00 215.00 3225.00Day 1.00 215.00 215.00sqm 82.50 55.65 4591.13

Rs: 14446.28963.10

0.14 134.801097.90

Rs: 61975.34Rs: 1035.95Rs: 14446.28

Total Rs: 77457.5614.00% Rs: 10844.06

15.00 cum Rs: 88301.6230023(A+B+C+D)/15.0 Rs. 5886.80

scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

UNIT : 15.00 cum

Unit Quantity Rate Amount

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

including cost of all materials, machinery, labour, formwork,

Page 165: Book 1

in Rs. in Rs.kg 4800.00 5.50 26400.00kg 30.00 5.50 165.00

cum 6.75 975.00 6581.25cum 4.05 1025.00 4151.25cum 2.70 750.00 2025.00cum 6.00 425 2550.00kg 19.20 54 1036.80

sqm 60.00 217.41 13044.43LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 55970.23

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1035.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 15.00 215.00 3225.00Day 1.00 215.00 215.00sqm 60.00 55.65 3339.00

Rs: 13194.15879.60

0.14 123.101002.70

Rs: 55970.23Rs: 1035.95

Page 166: Book 1

Rs: 13194.15Total Rs: 70200.33

14.00% Rs: 9828.0515.00 cum Rs: 80028.377638

(A+B+C+D)/15.0 Rs. 5335.20

machinery, labour, batching, mixing, placing in position as per detailed specifications etc.,

(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),

UNIT : 14.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 4900.00 5.50 26950.00cum 7.28 1025.00 7462.00cum 3.92 750.00 2940.00cum 6.30 425 2677.50kg 19.60 54 1058.40

TOTAL Rs: 41087.901% Rs: 410.88

(Included in material ra Rs:(Included in material ra Rs:

Rs: 41498.78

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95LS 5.00 33 165.00

Rs: 1053.75

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Day 1.00 260.00 260.00Day 1.00 275.00 275.00

( 28 days cube compressive strength not less than 15 N / sq down size approved, clean, hard, graded

by tremie or skip box method including cost of all materials,

. ( Cement content : 350 kg / cum )

Page 167: Book 1

Day 4.00 215.00 860.00Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 2.00 215.00 430.00Day 16.00 215.00 3440.00

Rs: 9659.15689.90

0.14 96.60786.50

Rs: 41498.78Rs: 1053.75Rs: 9659.15

Total Rs: 52211.6814.00% Rs: 7309.64

14.00 cum Rs: 59521.319(A+B+C+D)/14.0 Rs. 4251.50

batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with

If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

UNIT : 14.29 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 4001.20 5.50 22006.60cum 6.43 975.00 6269.74cum 3.86 1025.00 3954.76cum 2.57 750.00 1929.15cum 5.72 425 2429.30kg 16.00 54 864.26

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 37453.80

Unit Quantity Rate Amount

( 28 days cube compressive strength not less thandown size approved, clean, hard, graded

including cost of all materials, machinery, labour, cleaning,

Page 168: Book 1

in Rs. in Rs.Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1035.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 14.29 215.00 3072.35Day 1.00 215.00 215.00

Rs: 9702.50679.00

0.14 95.10774.10

Rs: 37453.80Rs: 1035.95Rs: 9702.50

Total Rs: 48192.2514.00% Rs: 6746.92

14.29 cum Rs: 54939.17(A+B+C+D)/14.29 Rs. 3844.60

scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),

28 days cube compressive strength not less than down size approved, clean, hard, graded

including cost of all materials, machinery, labour, formwork,

Page 169: Book 1

UNIT : 15.76 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 5200.80 5.50 28604.40kg 78.80 5.50 433.40

cum 8.20 1025.00 8400.08cum 4.41 750.00 3309.60cum 7.09 425 3014.10kg 20.80 54 1123.37

sqm 15.76 197.64 3114.85LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 48016.30

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1035.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 15.76 215.00 3388.40Day 1.00 215.00 215.00sqm 15.76 55.65 877.04

Rs: 10895.59691.30

0.14 96.80788.10

Page 170: Book 1

Rs: 48016.30Rs: 1035.95Rs: 10895.59

Total Rs: 59947.8514.00% Rs: 8392.7

15.76 cum Rs: 68340.5480057(A+B+C+D)/15.76 Rs. 4336.30

formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

UNIT : 14.40 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 3600.00 5.50 19800.00kg 72.00 5.50 396.00

cum 4.94 560.00 2765.95cum 4.23 975.00 4127.76cum 2.82 1025.00 2892.96cum 2.12 750.00 1587.60cum 5.04 425 2142.00kg 14.40 54 777.60

sqm 39.60 207.52 8217.9930% 2465.40

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 45173.26

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 77.00 616.00Hour 8.00 123.80 990.40Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.20 49.60Hour 8.00 18.60 148.80

Rs: 1839.95

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

including cost of all materials, labour, machinery,

Page 171: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 6.00 215.00 1290.00Day 14.40 215.00 3096.00Day 1.00 215.00 215.00sqm 39.60 55.65 2203.7430% 661.12

Rs: 13236.01919.20

0.14 128.701047.90

Rs: 45173.26Rs: 1839.95Rs: 13236.01

Total Rs: 60249.2214.00% Rs: 8434.89

14.40 cum Rs: 68684.1102355(A+B+C+D)/14.40 Rs. 4769.70

formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

UNIT : 14.55 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 3201.00 5.50 17605.50

( 28 days cube compressive strength not less thandown size approved, clean, hard, graded

including cost of all materials, labour, machinery,

Page 172: Book 1

kg 72.75 5.50 400.13cum 4.99 560.00 2794.76cum 4.28 975.00 4170.76cum 2.85 1025.00 2923.10cum 2.14 750.00 1604.14cum 5.09 425 2164.31kg 12.80 54 691.42

sqm 40.01 207.52 8303.5930% 2491.08

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 43148.78

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 77.00 616.00Hour 8.00 123.80 990.40Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.20 49.60Hour 8.00 18.60 148.80

Rs: 1839.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 6.00 215.00 1290.00Day 14.55 215.00 3128.25Day 1.00 215.00 215.00sqm 40.01 55.65 2226.7030% 668.01

Rs: 13298.10914.00

0.14 128.001042.00

Rs: 43148.78Rs: 1839.95

Page 173: Book 1

Rs: 13298.10Total Rs: 58286.83

14.00% Rs: 8160.1614.55 cum Rs: 66446.9933213

(A+B+C+D)/14.55 Rs. 4566.80

formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

UNIT : 16.36 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 3599.20 5.50 19795.60kg 81.80 5.50 449.90

cum 7.36 975.00 7177.95cum 4.42 1025.00 4527.63cum 2.94 750.00 2208.60cum 6.54 425 2781.20kg 14.40 54 777.43

sqm 44.99 207.52 9336.5530% 2800.96

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 49855.82

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1035.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

including cost of all materials, labour, machinery,

Page 174: Book 1

Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 5.00 215.00 1075.00Day 16.36 215.00 3517.40Day 1.00 215.00 215.00sqm 44.99 55.65 2503.6930% 751.11

Rs: 13832.35845.50

0.14 118.40963.90

Rs: 49855.82Rs: 1035.95Rs: 13832.35

Total Rs: 64724.1214.00% Rs: 9061.38

16.36 cum Rs: 73785.5025565(A+B+C+D)/16.36 Rs. 4510.10

machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,

(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

If water is to be brought from other place add only lead charges @ 500 ltr / cum.

UNIT : 16.25 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 5200.00 5.50 28600.00kg 81.25 5.50 446.88

cum 7.31 975.00 7129.69cum 4.39 1025.00 4497.19cum 2.93 750.00 2193.75

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

aggregates for cantiliver / counterfort retaining walls including cost of all materials,

levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 175: Book 1

cum 6.50 425 2762.50kg 20.80 54 1123.20

sqm 52.81 197.64 10438.0125% 2609.50LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 59817.22

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1035.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 5.00 215.00 1075.00Day 16.25 215.00 3493.75Day 1.00 215.00 215.00sqm 52.81 55.65 2939.0225% 734.75

Rs: 14227.67875.50

0.14 122.60998.10

Rs: 59817.22Rs: 1035.95Rs: 14227.67

Total Rs: 75080.8414.00% Rs: 10511.32

16.25 cum Rs: 85592.1553387

Page 176: Book 1

(A+B+C+D)/16.25 Rs. 5267.20

labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,

If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum,

2.82

UNIT : 18.09 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 4703.40 5.50 25868.70kg 72.36 5.50 397.98

cum 6.92 975.00 6746.44cum 4.15 1025.00 4255.45cum 2.77 750.00 2075.83cum 4.52 310 1401.98cum 6.15 425 2614.01kg 18.81 54 1015.93

sqm 49.75 197.64 9832.2430% 2949.67

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 57158.22

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.20 49.60Hour 8.00 18.60 148.80

Rs: 1087.15

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

placing and sinking plums of size 150 to 80 mm upto 15 percent for gravity etc., including cost of all materials, machinery,

lead upto 50 m and all lifts.

Page 177: Book 1

Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 5.00 215.00 1075.00Day 2.00 215.00 430.00Day 15.38 215.00 3306.70Day 2.00 215.00 430.00Day 1.00 215.00 215.00sqm 49.75 55.65 2768.4530% 830.53

Rs: 14825.83819.60

0.14 114.70934.30

Rs: 57158.22Rs: 1087.15Rs: 14825.83

Total Rs: 73071.2014.00% Rs: 10229.97

18.09 cum Rs: 83301.17(A+B+C+D)/18.09 Rs. 4604.80

batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with

If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

UNIT : 15.38 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 3998.80 5.50 21993.40kg 76.90 5.50 422.95

cum 6.92 975.00 6747.98

( 28 days cube compressive strength not less than down size approved, clean, hard,graded

including cost of all materials, machinery, labour, cleaning,

Page 178: Book 1

cum 4.15 1025.00 4256.42cum 2.77 750.00 2076.30cum 6.15 425 2614.60kg 16.00 54 863.74

sqm 30.76 207.52 6383.4715% 957.52LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 46332.87

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1035.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 15.38 215.00 3306.70Day 1.00 215.00 215.00sqm 30.76 55.65 1711.7915% 256.77

Rs: 11905.41774.10

0.14 108.40882.50

Rs: 46332.87Rs: 1035.95Rs: 11905.41

Total Rs: 59274.23

Page 179: Book 1

14.00% Rs: 8298.3915.38 cum Rs: 67572.6227247

(A+B+C+D)/15.38 Rs. 4393.50

cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

If water is to be brought from other place add only lead charges @ 500 ltr / cum.(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

UNIT : 14.40 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 3600.00 5.50 19800.00kg 72.00 5.50 396.00

cum 4.94 560.00 2765.95cum 4.23 975.00 4127.76cum 2.82 1025.00 2892.96cum 2.12 750.00 1587.60cum 5.04 425 2142.00kg 14.40 54 777.60

sqm 28.80 207.52 5976.7215% 896.51

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 41363.10

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 77.00 616.00Hour 8.00 123.80 990.40Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.20 49.60Hour 8.00 18.60 148.80

Rs: 1839.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

including cost of all materials, labour, machinery, formwork,

Page 180: Book 1

Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 14.40 215.00 3096.00Day 1.00 215.00 215.00sqm 28.80 55.65 1602.7215% 240.41

Rs: 11569.28803.40

0.14 112.50915.90

Rs: 41363.10Rs: 1839.95Rs: 11569.28

Total Rs: 54772.3314.00% Rs: 7668.13

14.40 cum Rs: 62440.46(A+B+C+D)/14.40 Rs. 4336.10

scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing

If water is to be brought from other place add only lead charges @ 500 ltr / cum. (Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),

UNIT : 15.76 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 5200.80 5.50 28604.40kg 78.80 5.50 433.40

cum 8.20 1025.00 8400.08cum 4.41 750.00 3309.60cum 7.09 425 3014.10kg 20.80 54 1123.37

( 28 days cube compressive strength not less than down size approved, clean, hard, graded

including cost of all materials,machinery, labour, formwork,

( Cement content : 300 kg / cum )

Page 181: Book 1

sqm 39.40 242.86 9568.57250% 23921.43

LS 1.00 33 33.00(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 78407.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1035.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 2.00 285.00 570.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 4.00 215.00 860.00Day 15.76 215.00 3388.40Day 1.00 215.00 215.00sqm 39.40 55.65 2192.61

250% 5481.53Rs: 18192.68

1154.400.14 161.60

1316.00

Rs: 78407.95Rs: 1035.95Rs: 18192.68

Total Rs: 97636.5914.00% Rs: 13669.12

15.76 cum Rs: 111305.71(A+B+C+D)/15.76 Rs. 7062.50

Page 182: Book 1

formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,

If water is to be brought from other place add only lead charges @ 500 ltr / cum.(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),

UNIT : 15.76 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 5200.80 5.50 28604.40kg 78.80 5.50 433.40

cum 8.20 1025.00 8400.08cum 4.41 750.00 3309.60cum 7.09 425 3014.10kg 20.80 54 1123.37

sqm 78.80 197.64 15574.2650% 7787.13LS 1.00 33 33.00

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 68279.34

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1035.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

( 28 days cube compressive strength not less thandown size approved, clean, hard, graded

including cost of all materials, labour, machinery,

initial lead upto 50 m and all lifts. ( Cement content : 300

Page 183: Book 1

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 15.76 215.00 3388.40Day 1.00 215.00 215.00sqm 78.80 55.65 4385.2250% 2192.61

Rs: 16596.381053.10

0.14 147.401200.50

Rs: 68279.34Rs: 1035.95Rs: 16596.38

Total Rs: 85911.6714.00% Rs: 12027.63

15.76 cum Rs: 97939.30(A+B+C+D)/15.76 Rs. 6214.40

cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,

If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),

UNIT : 15.76 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 5200.80 5.50 28604.40kg 78.80 5.50 433.40

cum 8.20 1025.00 8400.08cum 4.41 750.00 3309.60cum 7.09 425 3014.10kg 20.80 54 1123.37

sqm 7.88 197.64 1557.43LS 5.00 33 165.00

(Included in material ra Rs: 0.00

( 28 days cube compressive strength not less than 20 N / down size approved, clean, hard, graded

including cost of all materials, machinery, labour, formwork,

finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 m

Page 184: Book 1

(Included in material ra Rs: 0.00Rs: 46607.38

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1035.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 2.00 285.00 570.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 4.00 215.00 860.00Day 15.76 215.00 3388.40Day 2.00 215.00 430.00sqm 7.88 55.65 438.52

Rs: 11172.07708.90

0.14 99.20808.10

Rs: 46607.38Rs: 1035.95Rs: 11172.07

Total Rs: 58815.4014.00% Rs: 8234.16

15.76 cum Rs: 67049.56(A+B+C+D)/15.76 Rs. 4254.40

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than

scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing

down size approved, clean, hard, graded including cost of all materials, machinery, labour, formwork,

Page 185: Book 1

If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),

UNIT : 15.76 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 5200.80 5.50 28604.40kg 78.80 5.50 433.40

cum 8.20 1025.00 8400.08cum 4.41 750.00 3309.60cum 7.09 425 3014.10kg 20.80 54 1123.37

sqm 70.92 197.64 14016.8325% 3504.21LS 0.50 33 16.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 62422.49

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 8.00 6.00 48.00Hour 8.00 12.40 99.20

Rs: 1035.95

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 8.00 102.00 816.00Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 5.00 215.00 1075.00Day 15.76 215.00 3388.40Day 1.00 215.00 215.00

. ( Cement content : 300 kg / cum )

Page 186: Book 1

sqm 70.92 55.65 3946.7025% 986.67

Rs: 15381.92976.00

0.14 136.601112.60

Rs: 62422.49Rs: 1035.95Rs: 15381.92

Total Rs: 78840.3614.00% Rs: 11037.65

15.76 cum Rs: 89878.0133319(A+B+C+D)/15.76 Rs. 5702.90

260.00 day 31.20285.00 day 285.00215.00 day 430.00

746.20

422.30 hour 844.60

233.90 hour 467.80106.30 hour 212.60

Consumables in sinking @ 10% of machinery charges 152.501677.502423.70

14.00% 339.32

2763.02or say ( Rate upto 3.0m for 6.0 m well sinking ) 2763.00

898.7014.00% 125.80

Sinking RCC wells vertically for foundation of piers and abutments in all kinds of soil, sand and soft rock by approved well sinking method including cost of all materials, machinery, labour, kent - ledge arrangements, disposal of excavated material as directed etc., complete with lead upto 50 m for disposal of excavated material.(diameter of well 6.00m)

Page 187: Book 1

labour component/unit qty(including contractor's profit) 1024.50

260.00 day 39.00285.00 day 356.25215.00 day 537.50

932.75

422.30 hour 1266.90

233.90 hour 701.70106.30 hour 318.90

Consumables in sinking @ 10% of machinery charges 228.752516.253449.00

14.00% 482.86

3931.863931.90

1161.500.14 162.60

labour component/unit qty(including contractor's profit) 1324.10

ramming as directed including cost of all materials, machinery, labour etc., complete with

UNIT : 15.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

cum 15.75 325 5118.750.00 0.00

(Included in material ra Rs: 0.00Rs: 5118.75

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

in layers of 25 to 30 cm and compacting by watering,

Page 188: Book 1

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 0.25 275.00 68.75Day 4.00 215.00 860.00

Rs: 928.7561.90

0.14 8.7070.60

Rs: 5118.75Rs: 0.00Rs: 928.75

Total Rs: 6047.5014.00% Rs: 846.65

15.00 cum Rs: 6894.15(A+B+C+D)/15.0 Rs. 459.60

cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging

(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,

UNIT : 10.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 1430.00 5.50 7865.00cum 8.50 265 2252.50cum 1.50 310 465.00cum 4.00 425 1700.00

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 12282.50

Unit Quantity Rate Amountin Rs. in Rs.

Hour 1.00 285.80 285.80

un-coursed rubble stone masonry with approved stones infor sub-structure portions of return walls / abutments etc., including

lead upto 50 m and all lifts.

Page 189: Book 1

Hour 1.00 233.90 233.90Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95

Rs: 554.85

Unit Quantity Rate Amountin Rs. in Rs.

Hour 1.00 106.30 106.30Hour 0.50 71.10 35.55Day 1.00 275.00 275.00Day 1.00 285.00 285.00Day 2.00 260.00 520.00

Day 4.00 215.00 860.00Day 2.00 215.00 430.00Day 1.00 215.00 215.00Day 3.00 215.00 645.00Day 1.00 215.00 215.00Day 4.00 215.00 860.00

Rs: 4446.85444.70

0.14 62.30507.00

Rs: 12282.50Rs: 554.85Rs: 4446.85

Total Rs: 17284.2014.00% Rs: 2419.79

10.00 cum Rs: 19703.99(A+B+C+D)/10.0 Rs. 1970.40

cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging

(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,

UNIT : 10.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

un-coursed rubble stone masonry with approved stones infor super-structure portions of return walls / abutments etc., including

lead upto 50 m and all lifts.

Page 190: Book 1

kg 1430.00 5.50 7865.00cum 8.50 265 2252.50cum 1.50 310 465.00cum 4.00 425 1700.00

TOTAL Rs: 12282.502.5% Rs: 307.06

(Included in material ra Rs:(Included in material ra Rs:

Rs: 12589.56

Unit Quantity Rate Amountin Rs. in Rs.

Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95

Rs: 554.85

Unit Quantity Rate Amountin Rs. in Rs.

Hour 1.00 106.30 106.30Hour 0.50 71.10 35.55Day 1.00 275.00 275.00Day 1.00 285.00 285.00Day 2.00 260.00 520.00

Day 4.00 215.00 860.00Day 2.00 215.00 430.00Day 1.00 215.00 215.00Day 3.00 215.00 645.00Day 1.00 215.00 215.00Day 4.00 215.00 860.00

TOTAL Rs: 4446.852.5% Rs: 111.17

Rs: 4558.02455.80

0.14 63.80519.60

Rs: 12589.56Rs: 554.85Rs: 4558.02

Total Rs: 17702.4314.00% Rs: 2478.34

10.00 cum Rs: 20180.77375

Page 191: Book 1

(A+B+C+D)/10.0 Rs. 2018.10

stones from approved source including cost of all materials, machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with

(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones

UNIT : 10.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 1330.00 5.50 7315.00Nos 60.00 32 1920.00Nos 180.00 12 2160.00cum 4.50 265 1192.50cum 1.50 310 465.00cum 3.50 425 1487.50

TOTAL Rs: 14540.002.5% Rs: 363.50

(Included in material ra Rs:(Included in material ra Rs:

Rs: 14903.50

Unit Quantity Rate Amountin Rs. in Rs.

Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95

Rs: 554.85

Unit Quantity Rate Amountin Rs. in Rs.

Hour 1.00 106.30 106.30Hour 0.50 71.10 35.55Day 1.00 275.00 275.00Day 3.00 260.00 780.00Day 1.00 285.00 285.00Day 2.00 260.00 520.00

Day 4.00 215.00 860.00Day 3.00 215.00 645.00

coursed rubble masonry second sort in CM 1:4 proportion with

Page 192: Book 1

Day 1.00 215.00 215.00Day 3.00 215.00 645.00Day 1.00 215.00 215.00Day 2.00 215.00 430.00

TOTAL Rs: 5011.852.5% Rs: 125.30

Rs: 5137.15513.70

0.14 71.90585.60

Rs: 14903.50Rs: 554.85Rs: 5137.15

Total Rs: 20595.5014.00% Rs: 2883.37

10.00 cum Rs: 23478.86625(A+B+C+D)/10.0 Rs. 2347.90

Providing and constructing coursed rubble masonry first sort in CM 1:4 proportion withstones from approved source including cost of all materials, machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with

(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones

UNIT : 10.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 1330.00 5.50 7315.00Nos 60.00 32 1920.00Nos 180.00 12 2160.00cum 4.50 265 1192.50cum 1.50 310 465.00cum 3.50 425 1487.50

TOTAL Rs: 14540.002.5% Rs: 363.50

(Included in material ra Rs:(Included in material ra Rs:

Rs: 14903.50

Unit Quantity Rate Amount

Page 193: Book 1

in Rs. in Rs.Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95

Rs: 554.85

Unit Quantity Rate Amountin Rs. in Rs.

Hour 1.00 106.30 106.30Hour 0.50 71.10 35.55Day 1.00 275.00 275.00Day 6.00 260.00 1560.00Day 1.00 285.00 285.00Day 2.00 260.00 520.00

Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 1.00 215.00 215.00Day 3.00 215.00 645.00Day 1.00 215.00 215.00Day 2.00 215.00 430.00

TOTAL Rs: 5791.852.5% Rs: 144.80

Rs: 5936.65593.70

0.14 83.10676.80

Rs: 14903.50Rs: 554.85Rs: 5936.65

Total Rs: 21395.0014.00% Rs: 2995.3

10.00 cum Rs: 24390.29625(A+B+C+D)/10.0 Rs. 2439.00

proportion by volume including raking and cleaning joints for 50 mm depth, pressing cementmortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with

UNIT : 100.00 sqm

to coursed rubble face stone masonry in CM 1 : 2

Page 194: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

kg 456.00 5.50 2508.00cum 0.75 425 318.75

TOTAL Rs: 2826.752.5% Rs: 70.67

(Included in material ra Rs:Rs: 2897.42

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 10.00 285.00 2850.00Day 1.00 275.00 275.00Day 10.00 215.00 2150.00

Rs: 5275.0052.80

0.14 7.4060.20

Rs: 2897.42Rs: 0.00Rs: 5275.00

Total Rs: 8172.4214.00% Rs: 1144.14

100.00 sqm Rs: 9316.55875(A+B+C+D)/100.0 Rs. 93.20

proportion by volume including raking and cleaning joints for 50 mm depth, pressing cementmortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with

UNIT : 100.00 sqm

Unit Quantity Rate Amountin Rs. in Rs.

kg 322.00 5.50 1771.00

to coursed rubble face stone masonry in CM 1 : 3

Page 195: Book 1

cum 0.75 425 318.75TOTAL Rs: 2089.75

2.5% Rs: 52.24(Included in material ra Rs:

Rs: 2141.99

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 10.00 285.00 2850.00Day 1.00 275.00 275.00Day 10.00 215.00 2150.00

Rs: 5275.0052.80

0.14 7.4060.20

Rs: 2141.99Rs: 0.00Rs: 5275.00

Total Rs: 7416.9914.00% Rs: 1038.38

100.00 sqm Rs: 8455.37375(A+B+C+D)/100.0 Rs. 84.60

of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,

UNIT : 100.00 sqm

Unit Quantity Rate Amountin Rs. in Rs.

kg 629.00 5.50 3459.50cum 1.32 425 561.00

TOTAL Rs: 4020.502.5% Rs: 100.51

(Included in material ra Rs:

12 mm thick plastering in cement mortar 1:3 proportion by volume including cost

Page 196: Book 1

Rs: 4121.01

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 10.00 285.00 2850.00Day 1.00 275.00 275.00Day 20.00 215.00 4300.00

Rs: 7425.0074.30

0.14 10.4084.70

Rs: 4121.01Rs: 0.00Rs: 7425.00

Total Rs: 11546.0114.00% Rs: 1616.44

100.00 sqm Rs: 13162.4525(A+B+C+D)/100.0 Rs. 131.60

of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,

UNIT : 100.00 sqm

Unit Quantity Rate Amountin Rs. in Rs.

kg 472.00 5.50 2596.00cum 1.32 425 561.00

TOTAL Rs: 3157.002.5% Rs: 78.93

(Included in material ra Rs:Rs: 3235.93

12 mm thick plastering in cement mortar 1:4 proportion by volume including cost

Page 197: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 10.00 285.00 2850.00Day 1.00 275.00 275.00Day 20.00 215.00 4300.00

Rs: 7425.0074.30

0.14 10.4084.70

Rs: 3235.93Rs: 0.00Rs: 7425.00

Total Rs: 10660.9314.00% Rs: 1492.53

100.00 sqm Rs: 12153.455(A+B+C+D)/100.0 Rs. 121.50

of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,

UNIT : 100.00 sqm

Unit Quantity Rate Amountin Rs. in Rs.

kg 1050.00 5.50 5775.00cum 2.20 425 935.00

TOTAL Rs: 6710.002.5% Rs: 167.75

(Included in material ra Rs:Rs: 6877.75

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.00

20 mm thick plastering in cement mortar 1:3 proportion by volume including cost

Page 198: Book 1

0.00 0.00 0.00Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 15.00 285.00 4275.00Day 1.00 275.00 275.00Day 25.00 215.00 5375.00

Rs: 9925.0099.30

0.14 13.90113.20

Rs: 6877.75Rs: 0.00Rs: 9925.00

Total Rs: 16802.7514.00% Rs: 2352.39

100.00 sqm Rs: 19155.14(A+B+C+D)/100.0 Rs. 191.60

of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,

UNIT : 100.00 sqm

Unit Quantity Rate Amountin Rs. in Rs.

kg 788.00 5.50 4334.00cum 2.20 425 935.00

TOTAL Rs: 5269.002.5% Rs: 131.73

(Included in material ra Rs:Rs: 5400.73

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

20 mm thick plastering in cement mortar 1:4 proportion by volume including cost

Page 199: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

Day 15.00 285.00 4275.00Day 1.00 275.00 275.00Day 25.00 215.00 5375.00

Rs: 9925.0099.30

0.14 13.90113.20

Rs: 5400.73Rs: 0.00Rs: 9925.00

Total Rs: 15325.7314.00% Rs: 2145.6

100.00 sqm Rs: 17471.325(A+B+C+D)/100.0 Rs. 174.70

(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)

UNIT : 10.00 sqm

Unit Quantity Rate Amountin Rs. in Rs.

kg 75.00 5.50 412.50cum 0.30 425 127.50sqm 10.50 227 2383.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 2923.50

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

roughly dressed burnt stone slabs for coping set in proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including

cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto

Page 200: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

Day 1.00 260.00 260.00Day 1.00 260.00 260.00Day 0.50 275.00 137.50Day 2.00 215.00 430.00

Rs: 1087.50108.80

0.14 15.20124.00

Rs: 2923.50Rs: 0.00Rs: 1087.50

Total Rs: 4011.0014.00% Rs: 561.54

10.00 sqm Rs: 4572.54(A+B+C+D)/10.0 Rs. 457.30

CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including

(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm

UNIT : 10.00 sqm

Unit Quantity Rate Amountin Rs. in Rs.

kg 75.00 5.50 412.50cum 0.30 425 127.50sqm 10.50 227 2383.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 2923.50

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

one line dressed burnt stone slabs for coping set in

cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto

Page 201: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

Day 1.00 260.00 260.00Day 4.00 285.00 1140.00Day 0.50 275.00 137.50Day 2.00 215.00 430.00

Rs: 1967.50196.80

0.14 27.60224.40

Rs: 2923.50Rs: 0.00Rs: 1967.50

Total Rs: 4891.0014.00% Rs: 684.74

10.00 sqm Rs: 5575.74(A+B+C+D)/10.0 Rs. 557.60

(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm

UNIT : 10.00 sqm

Unit Quantity Rate Amountin Rs. in Rs.

kg 75.00 5.50 412.50cum 0.30 425 127.50sqm 10.50 227 2383.50

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 2923.50

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

two line dressed burnt stone slabs for coping set in proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including

cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto

Page 202: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

Day 1.00 260.00 260.00Day 8.00 285.00 2280.00Day 0.50 275.00 137.50Day 2.00 215.00 430.00

Rs: 3107.50310.80

0.14 43.50354.30

Rs: 2923.50Rs: 0.00Rs: 3107.50

Total Rs: 6031.0014.00% Rs: 844.34

10.00 sqm Rs: 6875.34(A+B+C+D)/10.0 Rs. 687.50

cleaning surface, batching, mixing, placing in position, levelling, compacting, finishing, curing

(Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement),

UNIT : 14.67 cum

Unit Quantity Rate Amountin Rs. in Rs.

kg 4401.00 5.50 24205.50kg 73.35 5.50 403.42

cum 7.63 1025.00 7819.11cum 4.11 750.00 3080.70cum 6.60 425 2805.64kg 17.60 54 950.62

sqm 80.69 197.64 15946.81sqm 1.00 33 33.00

Add seignorage charges on Stone @(Included in material rate) Rs: 0.00Add seignorage charges on Sand @ (Included in material rate) Rs: 0.00

Rs: 55244.80

( 28 days cube compressive strength not less than 15 N / down size approved clean, hard, graded

including cost of all materials, machinery, labour, formwork,

lead upto 50 m and initial lift upto 3 m.

Page 203: Book 1

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 44.80 358.40Hour 8.00 61.90 495.20Hour 0.50 8.40 4.20Hour 0.50 61.90 30.95Hour 1.00 285.80 285.80Hour 1.00 233.90 233.90

Rs: 1408.45

Unit Quantity Rate Amountin Rs. in Rs.

Hour 8.00 141.70 1133.60Hour 0.50 71.10 35.55Hour 1.00 106.30 106.30Day 1.00 285.00 285.00Day 1.00 275.00 275.00

Day 11.00 215.00 2365.00Day 4.00 215.00 860.00Day 3.00 215.00 645.00Day 14.67 215.00 3154.05Day 1.00 215.00 215.00sqm 80.69 55.65 4490.12

Rs: 13564.62924.70

0.14 129.501054.20

Rs: 55244.80Rs: 1408.45Rs: 13564.62

Total Rs: 70217.8714.00% Rs: 9830.5

14.67 cum Rs: 80048.37(A+B+C+D)/14.67 Rs. 5456.60

Providing and constructing protective railing consisting of in-situ railing posts of size 15 x15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre to centre in M-20 gradeconcrete using 20 mm down size graded aggregates and with each post reinforced by 4 Nos.of 8 mm dia main bars embedded in kerb concrete for a depth of 40 cm and 5 Nos. of 6 mmdia. stirrups including fixing 3 rows of 40 mm dia. GI pipes with one coat of red oxide primerand two coats of synthetic enamel paint, cost of all materials, machinery, labour, formwork,

Page 204: Book 1

UNIT : 10.00 Rm

Unit Quantity Rate Amountin Rs. in Rs.

kg 30.00 5.50 165.00cum 0.04 1025.00 41.00cum 0.02 750.00 15.00cum 0.04 425 17.00kg 16.39 41.00 671.99Rm 30.00 189 5670.00sqm 3.00 197.64 592.93LS 4.00 33 132.00

Add seignorage charges on Stone @ (Included in material rate) Rs: 0.00Add seignorage charges on Sand @(Included in material rate) Rs: 0.00

Rs: 7304.92

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 0.50 285.00 142.50Day 0.50 300.00 150.00Day 0.50 275.00 137.50Day 1.50 215.00 322.50Day 0.50 260.00 130.00Day 0.50 260.00 130.00

Rs: 1012.50101.30

0.14 14.20115.50

Rs: 7304.92Rs: 0.00Rs: 1012.50

Total Rs: 8317.4214.00% Rs: 1164.44

10.00 Rm Rs: 9481.858529(A+B+C+D)/10.0 Rs. 948.20

Page 205: Book 1

proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

(Cement content: 9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)

UNIT : 10.00 Joints

Unit Quantity Rate Amountin Rs. in Rs.

kg 99.00 5.50 544.50cum 0.10 425 42.50kg 0.91 60 54.60

(Included in material ra Rs: 0.00Rs: 641.60

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 2.00 260.00 520.00Day 1.00 275.00 275.00Day 3.00 215.00 645.00

Rs: 1440.00144.00

0.14 20.20164.20

Rs: 641.60Rs: 0.00Rs: 1440.00

Total Rs: 2081.6014.00% Rs: 291.42

10.00 Joints Rs: 2373.02(A+B+C+D)/10.0 Rs. 237.30

NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 206: Book 1

proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

(Cement content: 17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)

UNIT : 10.00 Joints

Unit Quantity Rate Amountin Rs. in Rs.

kg 174.00 5.50 957.00cum 0.22 425 93.50kg 1.27 60 76.20

(Included in material ra Rs: 0.00Rs: 1126.70

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 2.00 260.00 520.00Day 1.00 275.00 275.00Day 3.00 215.00 645.00

Rs: 1440.00144.00

0.14 20.20164.20

Rs: 1126.70Rs: 0.00Rs: 1440.00

Total Rs: 2566.7014.00% Rs: 359.34

10.00 Joints Rs: 2926.04(A+B+C+D)/10.0 Rs. 292.60

NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 207: Book 1

proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

(Cement content: 24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)

UNIT : 10.00 Joints

Unit Quantity Rate Amountin Rs. in Rs.

kg 248.00 5.50 1364.00cum 0.25 425 106.25kg 2.20 60 132.00

(Included in material ra Rs: 0.00Rs: 1602.25

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 2.50 260.00 650.00Day 1.00 275.00 275.00Day 4.00 215.00 860.00

Rs: 1785.00178.50

0.14 25.00203.50

Rs: 1602.25Rs: 0.00Rs: 1785.00

Total Rs: 3387.2514.00% Rs: 474.22

10.00 Joints Rs: 3861.47(A+B+C+D)/10.0 Rs. 386.10

NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 208: Book 1

proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

(Cement content: 32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint)

UNIT : 10.00 Joints

Unit Quantity Rate Amountin Rs. in Rs.

kg 321.00 5.50 1765.50cum 0.31 425 131.75kg 2.50 60 150.00

(Included in material ra Rs: 0.00Rs: 2047.25

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 2.50 260.00 650.00Day 1.00 275.00 275.00Day 4.00 215.00 860.00

Rs: 1785.00178.50

0.14 25.00203.50

Rs: 2047.25Rs: 0.00Rs: 1785.00

Total Rs: 3832.2514.00% Rs: 536.52

10.00 Joints Rs: 4368.77(A+B+C+D)/10.0 Rs. 436.90

NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 209: Book 1

proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

(Cement content: 39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)

UNIT : 10.00 Joints

Unit Quantity Rate Amountin Rs. in Rs.

kg 396.00 5.50 2178.00cum 0.39 425 165.75kg 3.10 60 186.00

(Included in material ra Rs: 0.00Rs: 2529.75

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 3.00 260.00 780.00Day 1.00 275.00 275.00Day 5.00 215.00 1075.00

Rs: 2130.00213.00

0.14 29.80242.80

Rs: 2529.75Rs: 0.00Rs: 2130.00

Total Rs: 4659.7514.00% Rs: 652.37

10.00 Joints Rs: 5312.12(A+B+C+D)/10.0 Rs. 531.20

NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 210: Book 1

proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

(Cement content: 44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)

UNIT : 10.00 Joints

Unit Quantity Rate Amountin Rs. in Rs.

kg 446.00 5.50 2453.00cum 0.45 425 191.25kg 3.40 60 204.00

(Included in material ra Rs: 0.00Rs: 2848.25

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 3.00 260.00 780.00Day 1.00 275.00 275.00Day 5.00 215.00 1075.00

Rs: 2130.00213.00

0.14 29.80242.80

Rs: 2848.25Rs: 0.00Rs: 2130.00

Total Rs: 4978.2514.00% Rs: 696.96

10.00 Joints Rs: 5675.21(A+B+C+D)/10.0 Rs. 567.50

NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 211: Book 1

proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

(Cement content: 49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)

UNIT : 10.00 Joints

Unit Quantity Rate Amountin Rs. in Rs.

kg 495.00 5.50 2722.50cum 0.50 425 212.50kg 3.77 60 226.20

(Included in material ra Rs: 0.00Rs: 3161.20

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 3.00 260.00 780.00Day 1.00 275.00 275.00Day 6.00 215.00 1290.00

Rs: 2345.00234.50

0.14 32.80267.30

Rs: 3161.20Rs: 0.00Rs: 2345.00

Total Rs: 5506.2014.00% Rs: 770.87

10.00 Joints Rs: 6277.07(A+B+C+D)/10.0 Rs. 627.70

NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 212: Book 1

proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

(Cement content: 56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)

UNIT : 10.00 Joints

Unit Quantity Rate Amountin Rs. in Rs.

kg 569.00 5.50 3129.50cum 0.58 425 246.50kg 4.15 60 249.00

(Included in material ra Rs: 0.00Rs: 3625.00

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 3.00 260.00 780.00Day 1.00 275.00 275.00Day 6.00 215.00 1290.00

Rs: 2345.00234.50

0.14 32.80267.30

Rs: 3625.00Rs: 0.00Rs: 2345.00

Total Rs: 5970.0014.00% Rs: 835.8

10.00 Joints Rs: 6805.8(A+B+C+D)/10.0 Rs. 680.60

class or IRC standard hume pipes in CM 1 : 2

Page 213: Book 1

proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,

(Cement content: 66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)

UNIT : 10.00 Joints

Unit Quantity Rate Amountin Rs. in Rs.

kg 668.00 5.50 3674.00cum 0.69 425 293.25kg 4.53 60 271.80

(Included in material ra Rs: 0.00Rs: 4239.05

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 4.00 260.00 1040.00Day 1.00 275.00 275.00Day 7.00 215.00 1505.00

Rs: 2820.00282.00

0.14 39.50321.50

Rs: 4239.05Rs: 0.00Rs: 2820.00

Total Rs: 7059.0514.00% Rs: 988.27

10.00 Joints Rs: 8047.32(A+B+C+D)/10.0 Rs. 804.70

NP- 2 class or IRC standard hume pipes in CM 1 : 2

labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto

Page 214: Book 1

including cost of all materials, machinery, labour, watering, ramming etc., complete with initial

UNIT : 10.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

cum 10.00 265 2650.00cum 4.00 325 1300.00

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 3950.00

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 0.50 275.00 137.50Day 1.00 260.00 260.00Day 4.00 215.00 860.00

Rs: 1257.50125.80

0.14 17.60143.40

Rs: 3950.00Rs: 0.00Rs: 1257.50

Total Rs: 5207.5014.00% Rs: 729.05

10.00 cum Rs: 5936.55(A+B+C+D)/10.0 Rs. 593.70

behind abutment and return walls in layers

Page 215: Book 1

including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by earth

UNIT : 10.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

cum 12.00 80 960.000.00 0.00 0.00

(Included in material ra Rs: 0.00Rs: 960.00

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 0.50 305.00 152.50Day 0.50 275.00 137.50Day 6.00 215.00 1290.00

Rs: 1580.00158.00

0.14 22.10180.10

Rs: 960.00Rs: 0.00Rs: 1580.00

Total Rs: 2540.0014.00% Rs: 355.6

10.00 cum Rs: 2895.6(A+B+C+D)/10.0 Rs. 289.60

including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by power

( CNS soil ) for foundation or around pipes

density control of not less than 95 percent etc., complete with lead

( CNS soil ) for foundation or above pipes

density control of not less than 98 percent etc., complete with lead upto

Page 216: Book 1

UNIT : 10.00 cum

Unit Quantity Rate Amountin Rs. in Rs.

cum 12.00 80 960.000.00 0.00 0.00

(Included in material ra Rs: 0.00Rs: 960.00

Unit Quantity Rate Amountin Rs. in Rs.

Hour 0.17 151.50 25.85Hour 0.17 556.90 95.03

Rs: 120.89

Unit Quantity Rate Amountin Rs. in Rs.

Hour 0.17 136.00 23.21Day 0.50 305.00 152.50Day 0.50 275.00 137.50Day 1.50 215.00 322.50

Rs: 635.7163.60

0.14 8.9072.50

Rs: 960.00Rs: 120.89Rs: 635.71

Total Rs: 1716.6014.00% Rs: 240.32

10.00 cum Rs: 1956.91556314(A+B+C+D)/10.0 Rs. 195.70

size 70x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats syntheticenamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost

111x35x25 cm thick IRC standard kilometre stone in down size aggregates including excavating pit of

of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

Page 217: Book 1

UNIT : 4 Nos.

Unit Quantity Rate Amountin Rs. in Rs.

No. 4.00 340 1360.00cum 0.20 975.00 195.00cum 0.15 1025.00 153.75cum 0.10 750.00 75.00cum 0.20 425 85.00kg 100.00 5.50 550.00ltr 1.00 184.00 184.00LS 4.00 33 132.00

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 2734.75

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 1.00 260.00 260.00Day 1.00 275.00 275.00Day 1.00 215.00 215.00Day 1.00 300.00 300.00

Rs: 1050.00262.50

0.14 36.80299.30

Rs: 2734.75Rs: 0.00Rs: 1050.00

Total Rs: 3784.7514.00% Rs: 529.87

4.00 Nos. Rs: 4314.62(A+B+C+D)/4.0 Rs. 1078.70

size 50x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic

65x15x10 cm thick IRC standard hectometre stone in down size aggregates including excavating pit of

Page 218: Book 1

enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost

UNIT : 4 Nos.

Unit Quantity Rate Amountin Rs. in Rs.

No. 4.00 180 720.00cum 0.20 975.00 195.00cum 0.15 1025.00 153.75cum 0.10 750.00 75.00cum 0.20 425 85.00kg 100.00 5.50 550.00ltr 0.40 184.00 73.60LS 1.00 33 33.00

(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00(Included in material ra Rs: 0.00

Rs: 1885.35

Unit Quantity Rate Amountin Rs. in Rs.

0.00 0.00 0.000.00 0.00 0.00

Rs: 0.00

Unit Quantity Rate Amountin Rs. in Rs.

Day 1.00 260.00 260.00Day 1.00 275.00 275.00Day 1.00 215.00 215.00Day 0.50 300.00 150.00

Rs: 900.00225.00

0.14 31.50256.50

Rs: 1885.35Rs: 0.00Rs: 900.00

Total Rs: 2785.3514.00% Rs: 389.95

4.00 Nos. Rs: 3175.3(A+B+C+D)/4.0 Rs. 793.80

of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.