Bond Projects Update
Madison Elementary SD
Madison Elementary SD
December 2015
![Page 2: Bond Projects Update Madison Elementary SD December 2015.](https://reader035.fdocuments.us/reader035/viewer/2022062804/5697bf9b1a28abf838c92f22/html5/thumbnails/2.jpg)
Tonight's topicsTonight's topics
Simis progress update, move into new building and phase two schedule.
Park café replacement timeline.Meadows two-story replacement
timeline.Other projects scheduled for
winter recess.
![Page 3: Bond Projects Update Madison Elementary SD December 2015.](https://reader035.fdocuments.us/reader035/viewer/2022062804/5697bf9b1a28abf838c92f22/html5/thumbnails/3.jpg)
Simis replacementSimis replacement
![Page 4: Bond Projects Update Madison Elementary SD December 2015.](https://reader035.fdocuments.us/reader035/viewer/2022062804/5697bf9b1a28abf838c92f22/html5/thumbnails/4.jpg)
Simis replacementSimis replacement
![Page 5: Bond Projects Update Madison Elementary SD December 2015.](https://reader035.fdocuments.us/reader035/viewer/2022062804/5697bf9b1a28abf838c92f22/html5/thumbnails/5.jpg)
Simis replacementSimis replacement
![Page 6: Bond Projects Update Madison Elementary SD December 2015.](https://reader035.fdocuments.us/reader035/viewer/2022062804/5697bf9b1a28abf838c92f22/html5/thumbnails/6.jpg)
Simis replacementSimis replacement
![Page 7: Bond Projects Update Madison Elementary SD December 2015.](https://reader035.fdocuments.us/reader035/viewer/2022062804/5697bf9b1a28abf838c92f22/html5/thumbnails/7.jpg)
Simis replacementSimis replacement
![Page 8: Bond Projects Update Madison Elementary SD December 2015.](https://reader035.fdocuments.us/reader035/viewer/2022062804/5697bf9b1a28abf838c92f22/html5/thumbnails/8.jpg)
Simis replacementSimis replacement
![Page 9: Bond Projects Update Madison Elementary SD December 2015.](https://reader035.fdocuments.us/reader035/viewer/2022062804/5697bf9b1a28abf838c92f22/html5/thumbnails/9.jpg)
The moveThe move
Staff have been delivered boxes and instructions (10/15/15)
Completion of packing (12/18/15)
Items moved to new location (12/19-23/15)Staff unpacking and preparing
for students return (12/28-29/15)
![Page 10: Bond Projects Update Madison Elementary SD December 2015.](https://reader035.fdocuments.us/reader035/viewer/2022062804/5697bf9b1a28abf838c92f22/html5/thumbnails/10.jpg)
Out with the old
Out with the old
FurnitureTechnology
![Page 11: Bond Projects Update Madison Elementary SD December 2015.](https://reader035.fdocuments.us/reader035/viewer/2022062804/5697bf9b1a28abf838c92f22/html5/thumbnails/11.jpg)
Simis ReplacementSimis Replacement
![Page 12: Bond Projects Update Madison Elementary SD December 2015.](https://reader035.fdocuments.us/reader035/viewer/2022062804/5697bf9b1a28abf838c92f22/html5/thumbnails/12.jpg)
Timeline for major Bond
ProjectsTimeline for major Bond
Projects
Madison Park Café replacement, Project start (3/15/16) Completion (8/1/16)
Madison Meadows two-story classroom replacement, project start (9/1/16) Completion (7/1/17)
![Page 13: Bond Projects Update Madison Elementary SD December 2015.](https://reader035.fdocuments.us/reader035/viewer/2022062804/5697bf9b1a28abf838c92f22/html5/thumbnails/13.jpg)
Other projects during winter
recessOther projects during winter
recessHVAC replacement, Rose Lane
ElementaryHVAC replacement, Heights
ElementaryConcrete floor re-polish MTAWarranty on wrought iron
fencing, MTA