BNSF Railways- Nason Creek LWP Reconnection ProjectPRCC/Tributary Fund– November 10, 2011
Wenatchee, WA
![Page 2: BNSF Railways- Nason Creek LWP Reconnection Project PRCC/Tributary Fund– November 10, 2011 Wenatchee, WA.](https://reader035.fdocuments.us/reader035/viewer/2022080915/56649e265503460f94b168a0/html5/thumbnails/2.jpg)
Nason LWP Project Costs – February 2011 vs. June 2011 Element February 2011 June 2011
Downstream B+ Downstream B+
Bridge Construction (55’ span) includes all contingencies and taxes
$727k $659K $733k $660k
BNSF Flagger/Engineering, Easement
$116k $116k $110k $110k
Earthwork (access and grading)
$542k $274K $542k $272k
Construction Subtotal$1.385 Million $1.049 million $1.385 Million $1.042 Million
Bridge Future Expansion$396k $347K $396k $150k
BNSF Bridge Replacement Fee
$992k $992k $992k $800k
BNSF Bridge Maintenance Fee
$124k $124k $124k $100k
Mitigation Subtotal$1.512 Million $1.463 million $1.512 Million $1.050 Million
CCNRD Admin- - - $70k
Total $2.897 Million $2.512 Million $2.897 Million $2.162 Million
![Page 3: BNSF Railways- Nason Creek LWP Reconnection Project PRCC/Tributary Fund– November 10, 2011 Wenatchee, WA.](https://reader035.fdocuments.us/reader035/viewer/2022080915/56649e265503460f94b168a0/html5/thumbnails/3.jpg)
Nason LWP Project Costs – November 2011 vs. June 2011Element November 2011 June 2011
Downstream B+ Downstream (55’) B+ (55’)
Bridge Construction (89’ span)
$489k $489k $733k $660k
BNSF Flagger/Engineering, Easement
$277k $277k $110k $110k
Earthwork (access and grading)
$348k $172k $542k $272k
Construction Subtotal $1.114 Million $0.938 Million $1.385 Million $1.042 Million
Bridge Future Expansion (BNSF Estimate)
$694k (BNSF 10/31/11) $694k (BNSF 10/31/11)
$396k $150k
BNSF Bridge Replacement Fee
$489k $489k $992k $800k
BNSF Bridge Maintenance Fee
$175k $175k $124k $100k
Mitigation Subtotal $1.358 Million $1.358 Million $1.512 Million $1.050 Million
CCNRD Admin $50k $50k - $70kTotal $2.522 Million $2.346 Million $2.897 Million $2.162 Million
![Page 4: BNSF Railways- Nason Creek LWP Reconnection Project PRCC/Tributary Fund– November 10, 2011 Wenatchee, WA.](https://reader035.fdocuments.us/reader035/viewer/2022080915/56649e265503460f94b168a0/html5/thumbnails/4.jpg)
Primary Difference Between June 2011 and November 2011 Costs
Construction• November bridge construction prices based on BNSF Estimate on
Conceptual Bridge Plans returned 10/31/11• BNSF Survey, Monitoring, and Engineering time added approximately
$180k to October estimate.Mitigation• Cost for future expansion bridge is for entire structure (Nov), not just piles
(June).• BNSF review of our proposed future expansion bridge costs: BNSF retained
original BNSF estimates for track work and bridge spans which resulted in an estimate of $694K; greater than our estimate of $616K but less than their original estimate of $844K.
• Bridge replacement fee reflects BNSF estimate for mainline bridge construction ($489k)
• Maintenance fee ($175k) reflects 75 year time period.
![Page 5: BNSF Railways- Nason Creek LWP Reconnection Project PRCC/Tributary Fund– November 10, 2011 Wenatchee, WA.](https://reader035.fdocuments.us/reader035/viewer/2022080915/56649e265503460f94b168a0/html5/thumbnails/5.jpg)
Timeline
Key Dates For Construction in 2012• March 2012 - CCNRD/BNSF Agreement In Place
– Establishes funding/payment mechanisms– BNSF orders bridge materials
• April – CCNRD opens bids for earthwork contractor and awards permit reciept.
• May 1st – Project permits in hand.• June – CCNRD earthwork contractor builds access. BSNF begins bridge
construction.• August/September – BNSF sets bridge decks. BNSF must be complete
with bridge construction by September 1st in order to be able to complete earthwork by end of in-water work window.
• September/October – CCNRD earthwork contractor constructs channel/bridge openings. In-water work completed by October 15th.
• November 1st – BNSF Peak Season Begins. No On-Track Work Allowed.
![Page 6: BNSF Railways- Nason Creek LWP Reconnection Project PRCC/Tributary Fund– November 10, 2011 Wenatchee, WA.](https://reader035.fdocuments.us/reader035/viewer/2022080915/56649e265503460f94b168a0/html5/thumbnails/6.jpg)
Project Costs and FundingDownstream B+
Cost Ele
ments
Construction Subtotal $1.114 Million $0.938 Million
Mitigation Subtotal $1.358 Million $1.358 Million
CCNRD Admin $50k $50k
Total $2.522 Million $2.346 Million
Funding Co
mmitment
Yakama Nation $2.522 Million
SRFB TBD (easement costs) $162,000
BPA Programmatic $1,500,000HCP Trib Committee- Initial commitment $150,000
PRCC - Initial commitment ($312,000 for In-Channel)* $38,000*
Combined Committees (Oct. 11) $400,000
Total $2.522 Million $2.252 Million
![Page 7: BNSF Railways- Nason Creek LWP Reconnection Project PRCC/Tributary Fund– November 10, 2011 Wenatchee, WA.](https://reader035.fdocuments.us/reader035/viewer/2022080915/56649e265503460f94b168a0/html5/thumbnails/7.jpg)
Current Status
• See Handout
![Page 8: BNSF Railways- Nason Creek LWP Reconnection Project PRCC/Tributary Fund– November 10, 2011 Wenatchee, WA.](https://reader035.fdocuments.us/reader035/viewer/2022080915/56649e265503460f94b168a0/html5/thumbnails/8.jpg)
B+ Culvert Option – Cost Estimate Assumptions
• 12’ Diameter x 75’ round pipe; daylight at toe of rail prism into connector channel.
• Need BNSF variance on freeboard – should be granted.• Culvert limits higher flow volumes – may be an advantage for
limiting flows and velocities along rail prism in connector channel. May be a disadvantage to fish passage.
• Future extension assumes 30’ pipe extension.• Catastrophic failure assumes no reconstruction.
![Page 9: BNSF Railways- Nason Creek LWP Reconnection Project PRCC/Tributary Fund– November 10, 2011 Wenatchee, WA.](https://reader035.fdocuments.us/reader035/viewer/2022080915/56649e265503460f94b168a0/html5/thumbnails/9.jpg)
Nason LWP Project Costs – B+ Bridge vs CulvertElement B+ 89’ Bridge B+ Culvert (12’ Jack)
Construction $489k $784K
BNSF Flagger/Engineering, Easement
$277k $197k
Earthwork (access and grading)
$172k $120k
Construction Subtotal $938K $1.101 Million
Future Expansion$694k $40k
BNSF Replacement Fee $489k $0
BNSF Maintenance Fee$175k $175K
Mitigation Subtotal $1.358 million $215K
CCNRD Admin $50k $50kTotal $2.346 Million $1.366 Million